SlideShare a Scribd company logo
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 CASTING OF CONCRETE SLABS
Issued: Rev. Date:
Revision: 0
Page 1 of 3 HSEQ -Rev-01(Jan-2023)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
L C RR
1
Concrete Pump
checks on arrival to
site
PRIOR TO SITE
ACCESS
 Use of mobile
concrete pump
 Unauthorized operation of the mobile
pump resulting in incident;
 Failure due to use of un-certificated
pump;
3 4
12
HIGH
i. All mobile concrete pumps to be Third Party Certificated by a DM
approved inspector, documentation available on arrival to site;
ii. Operators to have in-date Third Party certificate by approved body,
available for review on arrival to site;
iii. Visual inspection of pump undertaken by competent person;
Documentation
unavailable for
review
Pump quarantined until
evidence provided
Low
2. Formwork for slab for
temporary support
 Erection of
formwork;
 Works at Height;
 Injury from Fall from Heights;
 Injury from falling objects;
 Manual Handling injuries;
 Incorrect Design and Erection of
formwork resulting in collapse;
 Use of unsupervised or untrained
personnel to erect formwork;
 Erection of Formwork;
4 4
16
HIGH
i. If required for lifting formwork into position, use of mobile crane as per
RA012 – Mobile crane, or RA013 – Tower Crane as applicable;
ii. Safety harness and lanyard are to be used and hooked off to a secure
anchor point when working around exposed edges; No shock lanyard to
be used below 6m in height;
iii. All hand tools to be tied off when working at height over workers below;
iv. Correct manual lifting techniques of formwork communicated to workers;
v. The erection of temporary structures shall be undertaken under
supervision of a competent person under control of the designated
Temporary Works Supervisor in accordance with the TW designer’s
requirements;
vi. All formwork tie rods to be same design/make of wing nuts and not allow
slippage under load, double nut in areas where a risk of collapse onto
workers under load is possible;
vii. Formwork to be supported following a suitable proprietary bracing
system as per design, inadequate or unsuitable fixings shall not be used;
viii. Permit to load to be completed by TWC before loading of formwork;
ix. Temporary Works register to be completed by designated person and
available for review;
x. All workers to be briefed by supervision daily before shift commences;
xi. Area below clear of workers during erection, barriers and signage to be
implemented;
xii. Formwork to be inspected daily before work by designated Temporary
Works Co-ordinator;
xiii. Formwork inspected after damage or incident likely to affect structural
stability such as high winds, heavy rain or electrical storm;
Project Name: xxx
RA Ref No.: xxx
Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Concrete slabs using formwork and falsework
Relevant Applicable MAS:
 01412 – Lifting operations cranes;
Additional Training required:
Temporary Works Coordinator nominated
NOC’s Required for task:
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be?
What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen
frequently
Often (4)
6 to 12 times a year
Likely (3)
1 to 5 times a year
Possible (2)
Once every 5 years
Rarely (1)
Less than once every 5
years
Can the hazard be Eliminated or removed
from the work place?
Catastrophic (5)
Multiple Fatalities
High 25 High 20 High 15 Medium 10 Medium 5
Can the product or process be substituted for
a less hazardous alternative?
Serious (4)
Class 1 single fatality
High 20 High 16 High 12 Medium 8 Low 4
Can the hazard be engineered away with
guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1
Permanently disabling effects
High 15 High 12 Medium 9 Medium 6 Low 3
Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work
restrictions. MTI
Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment &
Clothing be worn to safe guard against
hazards?
Insignificant (1)
FAI
Medium10 Medium 4 Low 3 Low 2 Low 1
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 CASTING OF CONCRETE SLABS
Issued: Rev. Date:
Revision: 0
Page 2 of 3 HSEQ -Rev-01(Jan-2023)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
L C RR
xiv. No overloading of formwork, TWC shall follow design SWL when
distributing materials;
3
Falsework to provide
temporary support to
formwork
 Works at Height;
 Manual Handling;
 Injury from Fall from Heights;
 Injury from falling objects;
 Manual Handling injuries;
 Incorrect Design and Erection of
falsework resulting in collapse;
 Use of unsupervised or untrained
personnel to erect falsework;
 Erection of Falsework;
4 4
16
HIGH
i. Safety harness and lanyard are to be used and hooked off to a secure
anchor point;
ii. No shock lanyard to be used below 6m in height;
iii. All hand tools to be tied off when working at height;
iv. Falsework to be protected when adjacent to traffic routes with suitable
barriers, and indicated by signage;
v. Correct manual lifting techniques of falsework communicated to workers;
vi. The erection of temporary structures shall be undertaken by a competent
persons under control of the designated Temporary Works Supervisor in
accordance with the TW designer’s requirements;
vii. All workers to be briefed and TBT by supervision daily before shift
commences;
viii. Falsework shall be sited on graded, compacted, level ground erected to
standards, with consideration given to soil erosion from heavy rain etc.;
ix. Area below to be clear of workers during erection, barriers and signage to
be implemented;
x. Falsework to be inspected daily before work by designated Temporary
Works Co-ordinator;
xi. Written report weekly on falsework by Engineers, document filed;
xii. Falsework inspected after damage or incident likely to affect structural
stability such as high winds, heavy rain or electrical storm;
xiii. No alterations to falsework by untrained persons;
xiv. No overloading of falsework, TWC shall follow design SWL when
distributing materials;
xv. Ensure good standard of lighting, at night, for the work area.
Extreme weather
conditions
(E.g.: Heavy wind,
Sand storm etc.)
Regular TBT’s & Trainings to
be given on working at heights.
Low
4 Rebar to slabs
 Use of crane;
 Lifting operations;
 Persons underneath load struck by
falling materials;
 Rebar bundles swinging / spinning
uncontrolled;
 Damage to slings from sharp edges;
 Over-sailing of material over
workers;
 Burns/cuts from grinding equipment;
 Injury from slips/trips on rebar;
3 3
9
MED
i. Risk Assessment 12 – mobile Crane to be adhered to regarding lifting of
rebar bundles;
ii. Workers to wear gloves when tying rebar;
iii. Rebar to be stored correctly on deck to ensure safe access and high
level of housekeeping maintained;
iv. All electrical cutting equipment to be tested and safe to use. Operators
shall wear safety glasses;
v. Hot work permit required when cutting rebar at height;
vi. Access planks to be laid on rebar to provide safe walking access to
workers, to be maintained as task progresses;
vii. Daily clean-up of waste material to a designated area or skip below;
Safe access to be provided, such as scaffold stairs, to work area;
5
Access of mobile pump
and delivery trucks to
work areas
 Plant and workers in
same working area;
 Collision with plant or vehicles and
live traffic;
 Workers struck by plant, very high
risk of fatality;
 Uncontrolled pump and truck
reversing;
3 4
12
HIGH
i. Worker pedestrian routes to be designed and implemented with clear
signage to provide segregation;
ii. Instruction to workers at induction on use of access routes around the
project;
iii. Flagmen to be used to control Pump and delivery truck movements;
iv. The Logistics plan shall clearly illustrate pump access and egress points;
Workers not
complying with
flagmen
Regular topic in TBT’s Low
6 Siting and setting up of
concrete pump
 Working in proximity
to existing structures
and services;
 Overturning due to incorrect siting or
incorrect pump outrigger extension;
 Collision of jib with overhead
services;
 Blocking access routes with pump;
3 4
12
High
i. If required for concrete pump as per RA014 – Use of Concrete Pump;
ii. Ensure pump is set up/rigged out correctly, is on firm level ground as per
siting plan with outriggers fully extended;
iii.Solid barriers should be situated, where practicable, to protect pump from
traffic routes around working radius of cab;
Unable to fully
extend outriggers
due to restrictions
in area
Operation revised, pump
moved to new area;
Pump never used without full
outrigger extension
Low
HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 CASTING OF CONCRETE SLABS
Issued: Rev. Date:
Revision: 0
Page 3 of 3 HSEQ -Rev-01(Jan-2023)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
L C RR
 Jib striking stationary structures; iv.Consideration given to overhead services and existing structures when
siting pump;
7
Pumping concrete
(Pump Operator)
 Operator competency;
 Pump planning;
 High pressures;
 Incident due to use of defective
hoses / equipment;
 Concrete spillage;
4 5
20
HIGH
i. Pumping Plan to be completed prior to any pour taking place by
Temporary Works Coordinator;
ii. Method statements and risk assessments to be submitted and adhered to;
iii. Pump load indicator to be functioning correctly, and not to be overridden
under any circumstances;
iv. Operator to adhere to safe working load limits;
v. Daily inspections of hoses, pipes, connections etc. prior to use. Damaged
equipment immediately removed from service;
vi. Pump hopper guards to be in place at all times;
vii. Plastic sheeting placed under hopper to contain spills;
Machine
breakdown
Hydraulic fluid spill
Machine isolated and
quarantined until repaired.
Spoil removed and treated as
hazardous waste
Low
8
Pumping operation
supervision
 Pumping operations
around workers;
 Workers in pump
operating radius;
 Reversing concrete
delivery vehicles;
 Worker struck by delivery vehicle;
 Hose swinging / spinning
uncontrolled;
 Pump operator unable to see task –
high level pumping;
 Over-sailing of material over live
traffic routes;
 Use of concrete – protective gear;
 Working on rebar – risk of injury;
3 5
15
High
viii. No over-sailing of hose over live traffic routes without road closure;
ix. Supervision to undertake visual inspection of all pumping gear and
equipment daily;
x. Workers to wear correct PPE at all times, nitrile gloves, wellingtons,
glasses;
xi. Flagmen controlling delivery truck movements;
xii. Spotters to direct pump operators at high level in clear view at all times;
xiii. All concrete soaked workwear to be removed immediately;
xiv. Planks placed on rebar for worker access, clear access maintained;
Incident – large
concrete spill
Work stopped, area cleared
and full investigation
undertaken
Low
9
Dismantling of form-
work
 Works at Height;
 Manual Handling;
 Worker competency;
 Injury from Fall from Heights;
 Injury from falling objects;
 Manual Handling injuries;
 Use of unsupervised or untrained
personnel to dismantle formwork;
4 4
16
HIGH
i. A dismantling Method Statement shall be produced and approved before
dismantling is undertaken, to ensure safe removal;
ii. The formwork shall be systematically removed as per approved Method
Statement and undertaken by competent persons.
No deviation from the Method Statement will be undertaken without
prior Temporary Works Coordinator approval;
Workers not
adhering to
procedure;
Supervision to constantly
monitor workers; Low
10 Striking of false-work
 Works at Height;
 Manual Handling;
 Injury from Fall from Heights;
 Injury from falling objects;
 Manual Handling injuries;
 Use of unsupervised or untrained
personnel to strike formwork;
4 4
16
HIGH
i. A dismantling Method Statement shall be produced and approved before
dismantling is undertaken, to ensure safe removal;
ii. The falsework shall be systematically removed as per approved Method
Statement and undertaken by competent persons.
iii. No deviation from the Method Statement will be undertaken without prior
Temporary Works Coordinator approval;
Workers not
adhering to
procedure;
Supervision to constantly
monitor workers; Low

More Related Content

Similar to 23 Casting of concrete slabs Risk Assessment Templates.docx

7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates
Dwarika Bhushan Sharma
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
Dwarika Bhushan Sharma
 
18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates
Dwarika Bhushan Sharma
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates
Dwarika Bhushan Sharma
 
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
Dwarika Bhushan Sharma
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
Dwarika Bhushan Sharma
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates
Dwarika Bhushan Sharma
 
6 Excavations (Temporary Works) Risk Assessment Templates.docx
6 Excavations (Temporary Works) Risk Assessment Templates.docx6 Excavations (Temporary Works) Risk Assessment Templates.docx
6 Excavations (Temporary Works) Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
Dwarika Bhushan Sharma
 
6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates
Dwarika Bhushan Sharma
 
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
Dwarika Bhushan Sharma
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
Dwarika Bhushan Sharma
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
Dwarika Bhushan Sharma
 

Similar to 23 Casting of concrete slabs Risk Assessment Templates.docx (20)

7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates7 falsework (temporary works) risk assessment templates
7 falsework (temporary works) risk assessment templates
 
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
11 Piling Operations with Rebar Cage installation Risk Assessment Templates.docx
 
11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates11 piling operations with rebar cage installation risk assessment templates
11 piling operations with rebar cage installation risk assessment templates
 
18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates18 laying blockwork with access scaffolding risk assessment templates
18 laying blockwork with access scaffolding risk assessment templates
 
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx9 Lifting Operations with Tower crane Risk Assessment Templates.docx
9 Lifting Operations with Tower crane Risk Assessment Templates.docx
 
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
16 Scaffolding (Temporary Works) Risk Assessment Templates.docx
 
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
12 Sheet Piling Operations (Temporary Works) Risk Assessment Templates.docx
 
9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates9 lifting operations with tower crane risk assessment templates
9 lifting operations with tower crane risk assessment templates
 
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
18 Laying blockwork with access scaffolding Risk Assessment Templates.docx
 
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx13 Initial Project Site Office Set-up Risk Assessment Templates.docx
13 Initial Project Site Office Set-up Risk Assessment Templates.docx
 
16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates16 scaffolding (temporary works) risk assessment templates
16 scaffolding (temporary works) risk assessment templates
 
12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates12 sheet piling operations (temporary works) risk assessment templates
12 sheet piling operations (temporary works) risk assessment templates
 
25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx25 Demolition of existing concrete structures Risk Assessment Templates.docx
25 Demolition of existing concrete structures Risk Assessment Templates.docx
 
13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates13 initial project site office set up risk assessment templates
13 initial project site office set up risk assessment templates
 
6 Excavations (Temporary Works) Risk Assessment Templates.docx
6 Excavations (Temporary Works) Risk Assessment Templates.docx6 Excavations (Temporary Works) Risk Assessment Templates.docx
6 Excavations (Temporary Works) Risk Assessment Templates.docx
 
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx8 Lifting Operations with mobile crane Risk Assessment Templates.docx
8 Lifting Operations with mobile crane Risk Assessment Templates.docx
 
6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates6 excavations (temporary works) risk assessment templates
6 excavations (temporary works) risk assessment templates
 
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templ...
 
8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates8 lifting operations with mobile crane risk assessment templates
8 lifting operations with mobile crane risk assessment templates
 
10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates10 use of mobile concrete pump risk assessment templates
10 use of mobile concrete pump risk assessment templates
 

More from Dwarika Bhushan Sharma

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
Dwarika Bhushan Sharma
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
Dwarika Bhushan Sharma
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
Dwarika Bhushan Sharma
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
Dwarika Bhushan Sharma
 
1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf
Dwarika Bhushan Sharma
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
Dwarika Bhushan Sharma
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
Dwarika Bhushan Sharma
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
Dwarika Bhushan Sharma
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
Dwarika Bhushan Sharma
 
WITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docxWITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docx
Dwarika Bhushan Sharma
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
Dwarika Bhushan Sharma
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
Dwarika Bhushan Sharma
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
Dwarika Bhushan Sharma
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
Dwarika Bhushan Sharma
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
Dwarika Bhushan Sharma
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
Dwarika Bhushan Sharma
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
Dwarika Bhushan Sharma
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
Dwarika Bhushan Sharma
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
Dwarika Bhushan Sharma
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
Dwarika Bhushan Sharma
 

More from Dwarika Bhushan Sharma (20)

4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
4 - SAFETY IS THE LIFELINE OF YOUR BUSINESS.pdf
 
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
5 - CLOWNS BELONG IN THE CIRCUS & NOT ON THE JOB.pdf
 
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
3-STOP FALLS, CLEAN UP, PICK UP, WIPE UP.pdf
 
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
2-THERE'S A SAFE WAY TO DO EVERY JOB, OF YOU DON'T KNOW ASK.pdf
 
1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf1-HAZARDOUS CHEMICALS.pdf
1-HAZARDOUS CHEMICALS.pdf
 
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docxPRE-START BRIEFING Form # HSEQ - PSB  Rev 2 -.docx
PRE-START BRIEFING Form # HSEQ - PSB Rev 2 -.docx
 
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docxFIRE PREVENTION REQUIREMENTS Form # HSEQ -  Rev 2.docx
FIRE PREVENTION REQUIREMENTS Form # HSEQ - Rev 2.docx
 
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docxSUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
SUB CONTRACTORS HSE CHECKLIST Form # HSEQ - SPSC Rev 2 -.docx
 
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docxSTORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
STORE INSPECTION Form # HSEQ - Form 2 Rev 2.docx
 
WITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docxWITNESS STATEMENT FORM.docx
WITNESS STATEMENT FORM.docx
 
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docxPROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
PROJECT LEADER INCIDENT BRIEFING Form # HSEQ - PLIB Rev 2 -.docx
 
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docxHSE FORMS (COVER PAGE)2 Form # HSEQ -  Rev 2.docx
HSE FORMS (COVER PAGE)2 Form # HSEQ - Rev 2.docx
 
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docxLIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
LIFT SHAFT ENTRY PERMIT Form # HSEQ - LSEP Rev 2 -.docx
 
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docxLIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
LIVE ELECTRICAL WORK PERMIT Form # HSEQ - LEP Rev 2.docx
 
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docxMOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
MOBILE PLANT REGISTER Form # HSEQ - MPR Rev 3.docx
 
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docxLABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
LABOR ACCOMMODATION CHECKLIST Form # HSEQ - LAC Rev 2.docx
 
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docxINCIDENT INVESTIGATION REPORT  Form # HSEQ - IIR Rev 9 -.docx
INCIDENT INVESTIGATION REPORT Form # HSEQ - IIR Rev 9 -.docx
 
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.docHSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
HSE INDUCTION Form # HSEQ - HSEI Rev 2 -.doc
 
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.docHSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
HSE WARNING LETTER-DISCIPLINARY NOTICE Form # HSEQ - HSEWL Rev 6.doc
 
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docxOFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
OFFICE PORTA CABIN INSPECTION Form # HSEQ - OPC Rev 2.docx
 

Recently uploaded

官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
ramrag33
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
riddhimaagrawal986
 
An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...
IJECEIAES
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
GauravCar
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
Gino153088
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
architagupta876
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
TaghreedAltamimi
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
gowrishankartb2005
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
LAXMAREDDY22
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
Seminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptxSeminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptx
Madan Karki
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
Mahmoud Morsy
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 

Recently uploaded (20)

官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
Data Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptxData Control Language.pptx Data Control Language.pptx
Data Control Language.pptx Data Control Language.pptx
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
People as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimalaPeople as resource Grade IX.pdf minimala
People as resource Grade IX.pdf minimala
 
An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...An improved modulation technique suitable for a three level flying capacitor ...
An improved modulation technique suitable for a three level flying capacitor ...
 
artificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptxartificial intelligence and data science contents.pptx
artificial intelligence and data science contents.pptx
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
4. Mosca vol I -Fisica-Tipler-5ta-Edicion-Vol-1.pdf
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
 
Material for memory and display system h
Material for memory and display system hMaterial for memory and display system h
Material for memory and display system h
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
Seminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptxSeminar on Distillation study-mafia.pptx
Seminar on Distillation study-mafia.pptx
 
Certificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi AhmedCertificates - Mahmoud Mohamed Moursi Ahmed
Certificates - Mahmoud Mohamed Moursi Ahmed
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 

23 Casting of concrete slabs Risk Assessment Templates.docx

  • 1. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 CASTING OF CONCRETE SLABS Issued: Rev. Date: Revision: 0 Page 1 of 3 HSEQ -Rev-01(Jan-2023) No Specific Task Step (In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR L C RR 1 Concrete Pump checks on arrival to site PRIOR TO SITE ACCESS  Use of mobile concrete pump  Unauthorized operation of the mobile pump resulting in incident;  Failure due to use of un-certificated pump; 3 4 12 HIGH i. All mobile concrete pumps to be Third Party Certificated by a DM approved inspector, documentation available on arrival to site; ii. Operators to have in-date Third Party certificate by approved body, available for review on arrival to site; iii. Visual inspection of pump undertaken by competent person; Documentation unavailable for review Pump quarantined until evidence provided Low 2. Formwork for slab for temporary support  Erection of formwork;  Works at Height;  Injury from Fall from Heights;  Injury from falling objects;  Manual Handling injuries;  Incorrect Design and Erection of formwork resulting in collapse;  Use of unsupervised or untrained personnel to erect formwork;  Erection of Formwork; 4 4 16 HIGH i. If required for lifting formwork into position, use of mobile crane as per RA012 – Mobile crane, or RA013 – Tower Crane as applicable; ii. Safety harness and lanyard are to be used and hooked off to a secure anchor point when working around exposed edges; No shock lanyard to be used below 6m in height; iii. All hand tools to be tied off when working at height over workers below; iv. Correct manual lifting techniques of formwork communicated to workers; v. The erection of temporary structures shall be undertaken under supervision of a competent person under control of the designated Temporary Works Supervisor in accordance with the TW designer’s requirements; vi. All formwork tie rods to be same design/make of wing nuts and not allow slippage under load, double nut in areas where a risk of collapse onto workers under load is possible; vii. Formwork to be supported following a suitable proprietary bracing system as per design, inadequate or unsuitable fixings shall not be used; viii. Permit to load to be completed by TWC before loading of formwork; ix. Temporary Works register to be completed by designated person and available for review; x. All workers to be briefed by supervision daily before shift commences; xi. Area below clear of workers during erection, barriers and signage to be implemented; xii. Formwork to be inspected daily before work by designated Temporary Works Co-ordinator; xiii. Formwork inspected after damage or incident likely to affect structural stability such as high winds, heavy rain or electrical storm; Project Name: xxx RA Ref No.: xxx Review date: Date: Compiled by: Reviewed by: Approved by: Overall Task Details Concrete slabs using formwork and falsework Relevant Applicable MAS:  01412 – Lifting operations cranes; Additional Training required: Temporary Works Coordinator nominated NOC’s Required for task: RISK SCORE CALCULATOR Use the Risk Score Calculator to Determine the Level of Risk of each Hazard What would be the CONSEQUENCE of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls Frequent/Almost certain (5) Continuous or will happen frequently Often (4) 6 to 12 times a year Likely (3) 1 to 5 times a year Possible (2) Once every 5 years Rarely (1) Less than once every 5 years Can the hazard be Eliminated or removed from the work place? Catastrophic (5) Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative? Serious (4) Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers? Moderate (3) Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted I.e. procedures, job rotation etc. Minor (2) Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards? Insignificant (1) FAI Medium10 Medium 4 Low 3 Low 2 Low 1
  • 2. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 CASTING OF CONCRETE SLABS Issued: Rev. Date: Revision: 0 Page 2 of 3 HSEQ -Rev-01(Jan-2023) No Specific Task Step (In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR L C RR xiv. No overloading of formwork, TWC shall follow design SWL when distributing materials; 3 Falsework to provide temporary support to formwork  Works at Height;  Manual Handling;  Injury from Fall from Heights;  Injury from falling objects;  Manual Handling injuries;  Incorrect Design and Erection of falsework resulting in collapse;  Use of unsupervised or untrained personnel to erect falsework;  Erection of Falsework; 4 4 16 HIGH i. Safety harness and lanyard are to be used and hooked off to a secure anchor point; ii. No shock lanyard to be used below 6m in height; iii. All hand tools to be tied off when working at height; iv. Falsework to be protected when adjacent to traffic routes with suitable barriers, and indicated by signage; v. Correct manual lifting techniques of falsework communicated to workers; vi. The erection of temporary structures shall be undertaken by a competent persons under control of the designated Temporary Works Supervisor in accordance with the TW designer’s requirements; vii. All workers to be briefed and TBT by supervision daily before shift commences; viii. Falsework shall be sited on graded, compacted, level ground erected to standards, with consideration given to soil erosion from heavy rain etc.; ix. Area below to be clear of workers during erection, barriers and signage to be implemented; x. Falsework to be inspected daily before work by designated Temporary Works Co-ordinator; xi. Written report weekly on falsework by Engineers, document filed; xii. Falsework inspected after damage or incident likely to affect structural stability such as high winds, heavy rain or electrical storm; xiii. No alterations to falsework by untrained persons; xiv. No overloading of falsework, TWC shall follow design SWL when distributing materials; xv. Ensure good standard of lighting, at night, for the work area. Extreme weather conditions (E.g.: Heavy wind, Sand storm etc.) Regular TBT’s & Trainings to be given on working at heights. Low 4 Rebar to slabs  Use of crane;  Lifting operations;  Persons underneath load struck by falling materials;  Rebar bundles swinging / spinning uncontrolled;  Damage to slings from sharp edges;  Over-sailing of material over workers;  Burns/cuts from grinding equipment;  Injury from slips/trips on rebar; 3 3 9 MED i. Risk Assessment 12 – mobile Crane to be adhered to regarding lifting of rebar bundles; ii. Workers to wear gloves when tying rebar; iii. Rebar to be stored correctly on deck to ensure safe access and high level of housekeeping maintained; iv. All electrical cutting equipment to be tested and safe to use. Operators shall wear safety glasses; v. Hot work permit required when cutting rebar at height; vi. Access planks to be laid on rebar to provide safe walking access to workers, to be maintained as task progresses; vii. Daily clean-up of waste material to a designated area or skip below; Safe access to be provided, such as scaffold stairs, to work area; 5 Access of mobile pump and delivery trucks to work areas  Plant and workers in same working area;  Collision with plant or vehicles and live traffic;  Workers struck by plant, very high risk of fatality;  Uncontrolled pump and truck reversing; 3 4 12 HIGH i. Worker pedestrian routes to be designed and implemented with clear signage to provide segregation; ii. Instruction to workers at induction on use of access routes around the project; iii. Flagmen to be used to control Pump and delivery truck movements; iv. The Logistics plan shall clearly illustrate pump access and egress points; Workers not complying with flagmen Regular topic in TBT’s Low 6 Siting and setting up of concrete pump  Working in proximity to existing structures and services;  Overturning due to incorrect siting or incorrect pump outrigger extension;  Collision of jib with overhead services;  Blocking access routes with pump; 3 4 12 High i. If required for concrete pump as per RA014 – Use of Concrete Pump; ii. Ensure pump is set up/rigged out correctly, is on firm level ground as per siting plan with outriggers fully extended; iii.Solid barriers should be situated, where practicable, to protect pump from traffic routes around working radius of cab; Unable to fully extend outriggers due to restrictions in area Operation revised, pump moved to new area; Pump never used without full outrigger extension Low
  • 3. HEALTH SAFETY AND ENVIRONMENT Author: Approved: RISK ASSESSMENT: ACT/HSE/RA 001 CASTING OF CONCRETE SLABS Issued: Rev. Date: Revision: 0 Page 3 of 3 HSEQ -Rev-01(Jan-2023) No Specific Task Step (In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR L C RR  Jib striking stationary structures; iv.Consideration given to overhead services and existing structures when siting pump; 7 Pumping concrete (Pump Operator)  Operator competency;  Pump planning;  High pressures;  Incident due to use of defective hoses / equipment;  Concrete spillage; 4 5 20 HIGH i. Pumping Plan to be completed prior to any pour taking place by Temporary Works Coordinator; ii. Method statements and risk assessments to be submitted and adhered to; iii. Pump load indicator to be functioning correctly, and not to be overridden under any circumstances; iv. Operator to adhere to safe working load limits; v. Daily inspections of hoses, pipes, connections etc. prior to use. Damaged equipment immediately removed from service; vi. Pump hopper guards to be in place at all times; vii. Plastic sheeting placed under hopper to contain spills; Machine breakdown Hydraulic fluid spill Machine isolated and quarantined until repaired. Spoil removed and treated as hazardous waste Low 8 Pumping operation supervision  Pumping operations around workers;  Workers in pump operating radius;  Reversing concrete delivery vehicles;  Worker struck by delivery vehicle;  Hose swinging / spinning uncontrolled;  Pump operator unable to see task – high level pumping;  Over-sailing of material over live traffic routes;  Use of concrete – protective gear;  Working on rebar – risk of injury; 3 5 15 High viii. No over-sailing of hose over live traffic routes without road closure; ix. Supervision to undertake visual inspection of all pumping gear and equipment daily; x. Workers to wear correct PPE at all times, nitrile gloves, wellingtons, glasses; xi. Flagmen controlling delivery truck movements; xii. Spotters to direct pump operators at high level in clear view at all times; xiii. All concrete soaked workwear to be removed immediately; xiv. Planks placed on rebar for worker access, clear access maintained; Incident – large concrete spill Work stopped, area cleared and full investigation undertaken Low 9 Dismantling of form- work  Works at Height;  Manual Handling;  Worker competency;  Injury from Fall from Heights;  Injury from falling objects;  Manual Handling injuries;  Use of unsupervised or untrained personnel to dismantle formwork; 4 4 16 HIGH i. A dismantling Method Statement shall be produced and approved before dismantling is undertaken, to ensure safe removal; ii. The formwork shall be systematically removed as per approved Method Statement and undertaken by competent persons. No deviation from the Method Statement will be undertaken without prior Temporary Works Coordinator approval; Workers not adhering to procedure; Supervision to constantly monitor workers; Low 10 Striking of false-work  Works at Height;  Manual Handling;  Injury from Fall from Heights;  Injury from falling objects;  Manual Handling injuries;  Use of unsupervised or untrained personnel to strike formwork; 4 4 16 HIGH i. A dismantling Method Statement shall be produced and approved before dismantling is undertaken, to ensure safe removal; ii. The falsework shall be systematically removed as per approved Method Statement and undertaken by competent persons. iii. No deviation from the Method Statement will be undertaken without prior Temporary Works Coordinator approval; Workers not adhering to procedure; Supervision to constantly monitor workers; Low