This document provides an overview of environmental impact assessments (EIAs) in India. It discusses the EIA procedure, guidelines, and actors involved such as project proponents, environment consultants, and impact assessment agencies. Key points covered include:
- EIAs were made mandatory in India in 1994 to predict and mitigate environmental impacts of projects.
- The process involves screening, scoping, studies of social/health impacts, risk assessments, and public hearings.
- Impact assessment is conducted by three divisions covering different project sectors like industry, mining, and infrastructure.
- Projects requiring EIA clearance are categorized based on their expected impacts. Some projects are exempt from EIAs.
- Several acts
What sustainability means in mining today or what mining means to sustainabil...Mining On Top
The document discusses the role and contributions of mining to sustainability and the global economy. It makes the following key points:
1) Mining contributes around 10% directly and up to 45% indirectly to the global economy through supporting industries and downstream uses of minerals.
2) Mining disturbs less than 1% of the Earth's surface but provides over 45% of global economic activity and is essential for clean water, clean air, and other environmental needs.
3) For mining to be sustainable, it must contribute to human well-being, ecosystem well-being, and economic viability at the local, national and international levels through its operations and post-closure plans.
The document summarizes an environmental impact assessment report for a road improvement project between the border of China and Vietnam. It describes the project location and design alternatives considered. It also summarizes the physical, ecological and human environment along the project corridor. Potential environmental impacts during construction and operation are outlined, including on agricultural land, communities, and traffic. Mitigation measures are proposed to address impacts from land acquisition, noise, dust, erosion and more. Public involvement during the assessment is also summarized.
The Planning Team researched the viability of piezoelectric energy generation for Phase II of the Cornell Tech Campus. Piezoelectric tiles could harvest energy from pedestrian traffic but current technology is still inefficient and costly. While a full piezoelectric system would not pay for itself, small-scale applications like a piezoelectric event stage could showcase the technology and have practical uses with minimal costs. The team recommends revisiting piezoelectric energy as the technology advances further in the future for Phase II.
The document discusses assessing greenhouse gas emissions and climate change impacts as part of an environmental impact assessment for a hypothetical sustainable airport project with a design life from 2025-2050. It identifies key issues to consider for the construction, operational, and airline phases in order to demonstrate a pathway to net zero emissions by 2050. These include emissions from construction materials and transport, surface access and airport infrastructure emissions, and the need for sustainable aviation fuels and new aircraft technologies to significantly reduce airline emissions over the project lifetime.
This document summarizes a project report on the design and implementation of a land-based wind turbine. It examines various design alternatives and performs a cost analysis of the chosen design. The report was submitted by three students to fulfill the requirements for a Bachelor of Science degree. It considers economic, environmental, sustainability, constructability, ethical, health and safety, and social/political constraints as required by ABET for a capstone design experience.
The document summarizes a project called REE4EU that aims to develop a process for extracting rare earth elements from permanent magnets and nickel metal hydride battery waste to strengthen the European rare earth element supply chain. The process involves using high temperature electrolysis and ionic liquid extraction. In the first year of the project, lab-scale integration of these steps was completed and an engineering design for the industrial-scale process was developed. A report on stakeholders in the rare earth element value chain was also produced to help with dissemination efforts.
1. This document summarizes the environmental impact assessment conducted for the Jaipur Metro Rail Project in Jaipur, India.
2. Key aspects of the project include the construction of an underground metro system 12067km in length to help address the inadequate public transportation infrastructure in the growing city of over 3 million people.
3. The EIA process included collecting environmental baseline data, identifying potential impacts such as vibration, noise, waste generation during construction, and developing mitigation measures to minimize impacts and ensure compliance with relevant regulations.
What sustainability means in mining today or what mining means to sustainabil...Mining On Top
The document discusses the role and contributions of mining to sustainability and the global economy. It makes the following key points:
1) Mining contributes around 10% directly and up to 45% indirectly to the global economy through supporting industries and downstream uses of minerals.
2) Mining disturbs less than 1% of the Earth's surface but provides over 45% of global economic activity and is essential for clean water, clean air, and other environmental needs.
3) For mining to be sustainable, it must contribute to human well-being, ecosystem well-being, and economic viability at the local, national and international levels through its operations and post-closure plans.
The document summarizes an environmental impact assessment report for a road improvement project between the border of China and Vietnam. It describes the project location and design alternatives considered. It also summarizes the physical, ecological and human environment along the project corridor. Potential environmental impacts during construction and operation are outlined, including on agricultural land, communities, and traffic. Mitigation measures are proposed to address impacts from land acquisition, noise, dust, erosion and more. Public involvement during the assessment is also summarized.
The Planning Team researched the viability of piezoelectric energy generation for Phase II of the Cornell Tech Campus. Piezoelectric tiles could harvest energy from pedestrian traffic but current technology is still inefficient and costly. While a full piezoelectric system would not pay for itself, small-scale applications like a piezoelectric event stage could showcase the technology and have practical uses with minimal costs. The team recommends revisiting piezoelectric energy as the technology advances further in the future for Phase II.
The document discusses assessing greenhouse gas emissions and climate change impacts as part of an environmental impact assessment for a hypothetical sustainable airport project with a design life from 2025-2050. It identifies key issues to consider for the construction, operational, and airline phases in order to demonstrate a pathway to net zero emissions by 2050. These include emissions from construction materials and transport, surface access and airport infrastructure emissions, and the need for sustainable aviation fuels and new aircraft technologies to significantly reduce airline emissions over the project lifetime.
This document summarizes a project report on the design and implementation of a land-based wind turbine. It examines various design alternatives and performs a cost analysis of the chosen design. The report was submitted by three students to fulfill the requirements for a Bachelor of Science degree. It considers economic, environmental, sustainability, constructability, ethical, health and safety, and social/political constraints as required by ABET for a capstone design experience.
The document summarizes a project called REE4EU that aims to develop a process for extracting rare earth elements from permanent magnets and nickel metal hydride battery waste to strengthen the European rare earth element supply chain. The process involves using high temperature electrolysis and ionic liquid extraction. In the first year of the project, lab-scale integration of these steps was completed and an engineering design for the industrial-scale process was developed. A report on stakeholders in the rare earth element value chain was also produced to help with dissemination efforts.
1. This document summarizes the environmental impact assessment conducted for the Jaipur Metro Rail Project in Jaipur, India.
2. Key aspects of the project include the construction of an underground metro system 12067km in length to help address the inadequate public transportation infrastructure in the growing city of over 3 million people.
3. The EIA process included collecting environmental baseline data, identifying potential impacts such as vibration, noise, waste generation during construction, and developing mitigation measures to minimize impacts and ensure compliance with relevant regulations.
2021 hidalgo et al. - development of an innovative process involving the us...Jokin Hidalgo
Development of an innovative process involving the use of
ionic liquids for the recovery and purification of rare earths
from permanent magnets and NIMH batteries
A cradle to grave comparison of Hybrid Electric Vehicles and their conventional counterparts during their different life cycle stages: Manufacturing, Utilization & Recycling.
Site selection and suitability analysis for aquavoltaic system in TaiwanYa-hsuan Chiu
This document summarizes a presentation on site selection and suitability analysis for aquavoltaic systems in Taiwan. The methodology involved identifying zones for aquavoltaic installations based on environmental and social impact assessments. Data on biodiversity, coastal areas, cultural sites and public facilities was overlaid to map environmentally and socially sensitive areas as no-go or attention zones. Field surveys and stakeholder interviews further informed zone delineation. The results provided guidance on siting, planning and operations to mitigate issues. Future work includes training on the assessment and monitoring long-term impacts.
Quis custodiet ipsos custodes? The EU's energy efficiency policies scrutinise...Leonardo ENERGY
The European Court of Auditors (ECA) promotes accountability and transparency, and acts as the independent guardian of the financial interests of the EU citizens. ECA recently published two reports about EU energy efficiency policies (about appliances and buildings).
This webinar will present ECA’s role in the EU policy process, how it relates to evaluation, and the main conclusions from the two recent reports.
Introducing the Global Observatory on Peer-to-Peer, Community Self-Consumpti...Leonardo ENERGY
Launched in September 2019, the Global Observatory is a three-year collaborative research project led by University College London (UCL) under the User-Centred Energy Systems Technical Collaboration Programme by the International Energy Agency (IEA). It represents a forum for international collaboration to understand the policy, regulatory, social and technological conditions necessary to support the wider deployment of peer-to-peer, community self-consumption and transactive energy models. It includes 130 participants from 10+ countries, representing a range of sectors (academia, industry, non-profits) and currently working on the researching and implementation of these new business models. To learn more, please visit: https://userstcp.org/annex/peer-to-peer-energy-trading/.
Joint Crediting Mechanism or JCM is a new scheme for bilateral carbon trading. This presentation is describing the role of the project participant in JCM.
EIA an introduction - Case study wrt Coastal development & AquacultureKANTHARAJAN GANESAN
This document summarizes an environmental impact assessment for the Mumbai Coastal Road Project. It describes the objectives of the EIA study as establishing the baseline environmental conditions, identifying elements that could be affected, predicting impacts, and developing mitigation measures. The report structure includes chapters on project description, alternatives analysis, environmental description, anticipated impacts and mitigation measures, and an environmental management plan. The coastal road project aims to address traffic issues in the dense city of Mumbai by constructing a 29.2 km road along the western coast, and the EIA aims to assess the project's environmental impacts and ensure sustainable development.
Investigating Business Models for Building Integrated Photovoltaics (BIPV)Leonardo ENERGY
Solar cells (photovoltaics, PV) for electricity generation is forecasted to become one of the main contributors in the future energy system. Better building integration of PV (BIPV) is desired for aesthetical reasons and potentially also for cost savings. As of now, BIPV is generally more expensive than ordinary building applied PV installations (BAPV) or regular building components, which means there is a need to include other values in BIPV business models. This webinar presents the results from an inventory of existing business models and case studies, performed within the work of IEA-PVPS Task 15.
The document provides an overview of environmental impact assessments (EIAs). It defines EIAs as decision-making tools used to predict and compare the environmental effects of proposed projects and activities. The document then outlines the history and evolution of EIAs in India, describes the different types (rapid vs. comprehensive), and explains the key stages of an EIA - from initial screening and scoping to impact analysis, mitigation planning, public hearings, and licensing. The goal of an EIA process is to balance environmental and developmental concerns by identifying impacts and following suitable mitigation measures to ensure sustainable development outcomes.
Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA) is a systematic and integrative process for considering possible impacts prior to a decision being taken on whether or not a proposal should be given approval to proceed. (Wood 2003)
EIA Tool for Evaluating Pre & Post Impacts of Development ProjectsOsada Vishvajith
EIA is a commonly used tool to foresee the development impacts of multi scale projects. Sri Lanka, with a long history of EIA legislation has been used for evaluating number of projects so far.
The failure of addressing the key issues in the EIA process has been resulted disastrous impacts to the economy, society and environment. This presentation evaluates the weaknesses of EIA procedure in evaluating international airport project in Sri Lanka and how it could be improved to avoid future losses.
The document discusses environmental and social issues related to port development projects and public-private partnerships in Indonesia. It reviews the relevant legislation and regulatory framework, including requirements for Environmental Impact Assessments (AMDAL/EIA) and Land Acquisition and Resettlement Plans (LARAP). It also covers potential environmental issues like dredging, waste management, and biodiversity impacts. Social issues discussed include community health, land acquisition, and the different standards of Indonesia's national regulations versus international standards like IFC Performance Standards.
EIA is a process of evaluating the likely environmental impacts of a proposed project or development, taking into account inter-related socio-economic, cultural and human-health impacts, both beneficial and adverse.
EIA 1994 and the further amendments are explained i.e. 2006 and 2020.
It was taken into account before irrevocable development decisions are made. This paper attempts to review the developed framework for use into mining project proponents in the preparation of Environmental Impact Evaluation reports to meet the requirements of the Mines, Minerals Act and other statutory and legislative instruments dealing with the environment. It describe the significance of the environmental impact assessment EIA and its report or guidelines, as well as the procedures in stages on how project proponent interfaces with the federal ministry of environment and other entities in project management. It considers the environmental management plan EMP as compensatory measures for EIA and Mentioned also was the ability to identify key environmental impacts against project cycle for mining. The criteria and categories of mining projects according to environmental impact levels were discussed. Amosu Cyril Olumuyiwa "Environmental Impact Evaluation of Mining" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-5 | Issue-2 , February 2021, URL: https://www.ijtsrd.com/papers/ijtsrd38456.pdf Paper Url: https://www.ijtsrd.com/engineering/petroleum-engineering/38456/environmental-impact-evaluation-of-mining/amosu-cyril-olumuyiwa
The document discusses the importance of conducting comprehensive site investigations and obtaining an accurate report from an EPA-accredited auditor when remediating contaminated land. It outlines a court case where an inaccurate site investigation report led to additional costs and delays for the project. Thorough investigations and reliable reporting are essential to properly assess contamination levels and ensure development projects meet regulatory standards.
A structured process of evaluating likely beneficial and adverse environmental consequences of proposed developmental projects on air, water, soil, human health, society, flora, fauna, economy, and heritage.
This document discusses environmental impact assessments (EIAs). It defines EIAs as evaluations of the effects of major projects on the natural and human environment to assist decision-making. EIAs aim to prevent environmental degradation by providing information on industrial projects' environmental consequences. The document outlines how EIAs identify possible environmental effects, propose mitigation measures, and predict residual impacts. It notes EIAs were made mandatory for new projects in India in 1994 to require environmental clearance.
2021 hidalgo et al. - development of an innovative process involving the us...Jokin Hidalgo
Development of an innovative process involving the use of
ionic liquids for the recovery and purification of rare earths
from permanent magnets and NIMH batteries
A cradle to grave comparison of Hybrid Electric Vehicles and their conventional counterparts during their different life cycle stages: Manufacturing, Utilization & Recycling.
Site selection and suitability analysis for aquavoltaic system in TaiwanYa-hsuan Chiu
This document summarizes a presentation on site selection and suitability analysis for aquavoltaic systems in Taiwan. The methodology involved identifying zones for aquavoltaic installations based on environmental and social impact assessments. Data on biodiversity, coastal areas, cultural sites and public facilities was overlaid to map environmentally and socially sensitive areas as no-go or attention zones. Field surveys and stakeholder interviews further informed zone delineation. The results provided guidance on siting, planning and operations to mitigate issues. Future work includes training on the assessment and monitoring long-term impacts.
Quis custodiet ipsos custodes? The EU's energy efficiency policies scrutinise...Leonardo ENERGY
The European Court of Auditors (ECA) promotes accountability and transparency, and acts as the independent guardian of the financial interests of the EU citizens. ECA recently published two reports about EU energy efficiency policies (about appliances and buildings).
This webinar will present ECA’s role in the EU policy process, how it relates to evaluation, and the main conclusions from the two recent reports.
Introducing the Global Observatory on Peer-to-Peer, Community Self-Consumpti...Leonardo ENERGY
Launched in September 2019, the Global Observatory is a three-year collaborative research project led by University College London (UCL) under the User-Centred Energy Systems Technical Collaboration Programme by the International Energy Agency (IEA). It represents a forum for international collaboration to understand the policy, regulatory, social and technological conditions necessary to support the wider deployment of peer-to-peer, community self-consumption and transactive energy models. It includes 130 participants from 10+ countries, representing a range of sectors (academia, industry, non-profits) and currently working on the researching and implementation of these new business models. To learn more, please visit: https://userstcp.org/annex/peer-to-peer-energy-trading/.
Joint Crediting Mechanism or JCM is a new scheme for bilateral carbon trading. This presentation is describing the role of the project participant in JCM.
EIA an introduction - Case study wrt Coastal development & AquacultureKANTHARAJAN GANESAN
This document summarizes an environmental impact assessment for the Mumbai Coastal Road Project. It describes the objectives of the EIA study as establishing the baseline environmental conditions, identifying elements that could be affected, predicting impacts, and developing mitigation measures. The report structure includes chapters on project description, alternatives analysis, environmental description, anticipated impacts and mitigation measures, and an environmental management plan. The coastal road project aims to address traffic issues in the dense city of Mumbai by constructing a 29.2 km road along the western coast, and the EIA aims to assess the project's environmental impacts and ensure sustainable development.
Investigating Business Models for Building Integrated Photovoltaics (BIPV)Leonardo ENERGY
Solar cells (photovoltaics, PV) for electricity generation is forecasted to become one of the main contributors in the future energy system. Better building integration of PV (BIPV) is desired for aesthetical reasons and potentially also for cost savings. As of now, BIPV is generally more expensive than ordinary building applied PV installations (BAPV) or regular building components, which means there is a need to include other values in BIPV business models. This webinar presents the results from an inventory of existing business models and case studies, performed within the work of IEA-PVPS Task 15.
The document provides an overview of environmental impact assessments (EIAs). It defines EIAs as decision-making tools used to predict and compare the environmental effects of proposed projects and activities. The document then outlines the history and evolution of EIAs in India, describes the different types (rapid vs. comprehensive), and explains the key stages of an EIA - from initial screening and scoping to impact analysis, mitigation planning, public hearings, and licensing. The goal of an EIA process is to balance environmental and developmental concerns by identifying impacts and following suitable mitigation measures to ensure sustainable development outcomes.
Environmental Impact Assessment (EIA)
Environmental Impact Assessment (EIA) is a systematic and integrative process for considering possible impacts prior to a decision being taken on whether or not a proposal should be given approval to proceed. (Wood 2003)
EIA Tool for Evaluating Pre & Post Impacts of Development ProjectsOsada Vishvajith
EIA is a commonly used tool to foresee the development impacts of multi scale projects. Sri Lanka, with a long history of EIA legislation has been used for evaluating number of projects so far.
The failure of addressing the key issues in the EIA process has been resulted disastrous impacts to the economy, society and environment. This presentation evaluates the weaknesses of EIA procedure in evaluating international airport project in Sri Lanka and how it could be improved to avoid future losses.
The document discusses environmental and social issues related to port development projects and public-private partnerships in Indonesia. It reviews the relevant legislation and regulatory framework, including requirements for Environmental Impact Assessments (AMDAL/EIA) and Land Acquisition and Resettlement Plans (LARAP). It also covers potential environmental issues like dredging, waste management, and biodiversity impacts. Social issues discussed include community health, land acquisition, and the different standards of Indonesia's national regulations versus international standards like IFC Performance Standards.
EIA is a process of evaluating the likely environmental impacts of a proposed project or development, taking into account inter-related socio-economic, cultural and human-health impacts, both beneficial and adverse.
EIA 1994 and the further amendments are explained i.e. 2006 and 2020.
It was taken into account before irrevocable development decisions are made. This paper attempts to review the developed framework for use into mining project proponents in the preparation of Environmental Impact Evaluation reports to meet the requirements of the Mines, Minerals Act and other statutory and legislative instruments dealing with the environment. It describe the significance of the environmental impact assessment EIA and its report or guidelines, as well as the procedures in stages on how project proponent interfaces with the federal ministry of environment and other entities in project management. It considers the environmental management plan EMP as compensatory measures for EIA and Mentioned also was the ability to identify key environmental impacts against project cycle for mining. The criteria and categories of mining projects according to environmental impact levels were discussed. Amosu Cyril Olumuyiwa "Environmental Impact Evaluation of Mining" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-5 | Issue-2 , February 2021, URL: https://www.ijtsrd.com/papers/ijtsrd38456.pdf Paper Url: https://www.ijtsrd.com/engineering/petroleum-engineering/38456/environmental-impact-evaluation-of-mining/amosu-cyril-olumuyiwa
The document discusses the importance of conducting comprehensive site investigations and obtaining an accurate report from an EPA-accredited auditor when remediating contaminated land. It outlines a court case where an inaccurate site investigation report led to additional costs and delays for the project. Thorough investigations and reliable reporting are essential to properly assess contamination levels and ensure development projects meet regulatory standards.
A structured process of evaluating likely beneficial and adverse environmental consequences of proposed developmental projects on air, water, soil, human health, society, flora, fauna, economy, and heritage.
This document discusses environmental impact assessments (EIAs). It defines EIAs as evaluations of the effects of major projects on the natural and human environment to assist decision-making. EIAs aim to prevent environmental degradation by providing information on industrial projects' environmental consequences. The document outlines how EIAs identify possible environmental effects, propose mitigation measures, and predict residual impacts. It notes EIAs were made mandatory for new projects in India in 1994 to require environmental clearance.
This document provides a summary of the Environmental Impact Assessment (EIA) report for the proposed Orange Line Metro Train project in Lahore, Pakistan. The summary includes:
- Background on the project and objectives to provide safe, congestion-free public transportation.
- A description of the project scope, including an assessment of physical, biological, and socioeconomic environmental impacts and mitigation measures.
- Key aspects of the project design, including the route, train specifications, power requirements, and facilities.
- An overview of the existing physical, ecological, and socioeconomic environment in the project area that may be affected.
- Potential positive and negative impacts during construction and operation, and mitigation measures to address things like
This document provides a summary of an Environmental Impact Assessment report for the proposed Lahore Eastern Bypass project in Pakistan. The 18.3 km project aims to connect key roads and reduce traffic congestion in Lahore. The EIA study involved assessing baseline environmental conditions, potential impacts of construction and operation, and mitigation measures. Key findings include minor impacts on air quality, noise and vibration during construction which can be mitigated. The report recommends implementing the Environmental Management Plan during construction and operation to minimize impacts and enhance benefits of the project.
The document discusses a project to support green and resilient infrastructure investments in Organized Industrial Zones (OIZs) in Turkey. A World Bank technical analysis found that $1 billion in investment could cut carbon emissions by 1.23 million tons and improve energy, water and waste management efficiency. The project will be implemented by the Ministry of Industry and Technology and OIZs, with World Bank financing and oversight. An Environmental and Social Management Framework was developed to govern the project activities and address environmental, social and capacity issues to ensure compliance with World Bank standards.
This document provides a summary of the environmental impact assessment report for the proposed 50 MW wind power project in Sindh, Pakistan. The project involves constructing 34 wind turbines in two phases, with related infrastructure like access roads and a substation. Key potential impacts identified include disturbance of vegetation and wildlife during construction, air and noise pollution from construction vehicles and equipment, solid waste management, and health and safety risks for workers. Mitigation measures proposed include limiting construction to daylight hours, using dust suppression and maintaining equipment, developing waste management plans, and implementing a health and safety manual. An environmental management plan is included to ensure mitigation measures are followed. Public consultations were also conducted to understand local attitudes toward the project.
The document summarizes the process for obtaining an Environmental Clearance (EC) in India. It outlines that an EC is required for new projects and expansions listed under Categories A and B. Category A projects require clearance from the central government, while Category B only needs clearance from the state-level authority. The process involves 4 stages - screening, scoping, public consultation, and appraisal. Projects are categorized as A or B based on their impacts. The roles of different stakeholders like the project proponent, EIA consultant, and regulatory authorities at each stage are also defined.
Project Control Staff – Make or Buy? by "Mike Laws - Project Controls Manager...Project Controls Expo
The document discusses Mike Laws' presentation on attracting, retaining, and developing skilled project controls professionals. It provides background on Mike Laws and his experience in program management. It also gives overviews of several large infrastructure projects that CH2M has worked on, including Crossrail, High Speed 2, Team2100, Lower Thames Crossing, and the Panama Canal expansion. These case studies highlight CH2M's roles in providing program controls, cost estimation, and risk management services. The final sections discuss a systems model of program communication and the breadth of skills needed in program and project controls roles.
EIA Report Preparation and its Challenges.pptxAmit Chaudhary
The document summarizes the environmental impact assessment (EIA) process in Nepal and identifies challenges. It outlines the key steps in an EIA, which includes scoping, terms of reference, detailed studies, public consultation, and report preparation and approval. Major challenges include perceptions of EIA as just a formality, low-quality reports, lack of alternative analysis, delays in approval, and ineffective implementation of environmental management plans. The conclusions recommend strengthening implementation and following standards to make EIAs more project-specific and effective in mitigating environmental impacts.
Similar to 2008 environmental impact-assessment (20)
Removing Uninteresting Bytes in Software FuzzingAftab Hussain
Imagine a world where software fuzzing, the process of mutating bytes in test seeds to uncover hidden and erroneous program behaviors, becomes faster and more effective. A lot depends on the initial seeds, which can significantly dictate the trajectory of a fuzzing campaign, particularly in terms of how long it takes to uncover interesting behaviour in your code. We introduce DIAR, a technique designed to speedup fuzzing campaigns by pinpointing and eliminating those uninteresting bytes in the seeds. Picture this: instead of wasting valuable resources on meaningless mutations in large, bloated seeds, DIAR removes the unnecessary bytes, streamlining the entire process.
In this work, we equipped AFL, a popular fuzzer, with DIAR and examined two critical Linux libraries -- Libxml's xmllint, a tool for parsing xml documents, and Binutil's readelf, an essential debugging and security analysis command-line tool used to display detailed information about ELF (Executable and Linkable Format). Our preliminary results show that AFL+DIAR does not only discover new paths more quickly but also achieves higher coverage overall. This work thus showcases how starting with lean and optimized seeds can lead to faster, more comprehensive fuzzing campaigns -- and DIAR helps you find such seeds.
- These are slides of the talk given at IEEE International Conference on Software Testing Verification and Validation Workshop, ICSTW 2022.
How to Get CNIC Information System with Paksim Ga.pptxdanishmna97
Pakdata Cf is a groundbreaking system designed to streamline and facilitate access to CNIC information. This innovative platform leverages advanced technology to provide users with efficient and secure access to their CNIC details.
UiPath Test Automation using UiPath Test Suite series, part 6DianaGray10
Welcome to UiPath Test Automation using UiPath Test Suite series part 6. In this session, we will cover Test Automation with generative AI and Open AI.
UiPath Test Automation with generative AI and Open AI webinar offers an in-depth exploration of leveraging cutting-edge technologies for test automation within the UiPath platform. Attendees will delve into the integration of generative AI, a test automation solution, with Open AI advanced natural language processing capabilities.
Throughout the session, participants will discover how this synergy empowers testers to automate repetitive tasks, enhance testing accuracy, and expedite the software testing life cycle. Topics covered include the seamless integration process, practical use cases, and the benefits of harnessing AI-driven automation for UiPath testing initiatives. By attending this webinar, testers, and automation professionals can gain valuable insights into harnessing the power of AI to optimize their test automation workflows within the UiPath ecosystem, ultimately driving efficiency and quality in software development processes.
What will you get from this session?
1. Insights into integrating generative AI.
2. Understanding how this integration enhances test automation within the UiPath platform
3. Practical demonstrations
4. Exploration of real-world use cases illustrating the benefits of AI-driven test automation for UiPath
Topics covered:
What is generative AI
Test Automation with generative AI and Open AI.
UiPath integration with generative AI
Speaker:
Deepak Rai, Automation Practice Lead, Boundaryless Group and UiPath MVP
Dr. Sean Tan, Head of Data Science, Changi Airport Group
Discover how Changi Airport Group (CAG) leverages graph technologies and generative AI to revolutionize their search capabilities. This session delves into the unique search needs of CAG’s diverse passengers and customers, showcasing how graph data structures enhance the accuracy and relevance of AI-generated search results, mitigating the risk of “hallucinations” and improving the overall customer journey.
Let's Integrate MuleSoft RPA, COMPOSER, APM with AWS IDP along with Slackshyamraj55
Discover the seamless integration of RPA (Robotic Process Automation), COMPOSER, and APM with AWS IDP enhanced with Slack notifications. Explore how these technologies converge to streamline workflows, optimize performance, and ensure secure access, all while leveraging the power of AWS IDP and real-time communication via Slack notifications.
UiPath Test Automation using UiPath Test Suite series, part 5DianaGray10
Welcome to UiPath Test Automation using UiPath Test Suite series part 5. In this session, we will cover CI/CD with devops.
Topics covered:
CI/CD with in UiPath
End-to-end overview of CI/CD pipeline with Azure devops
Speaker:
Lyndsey Byblow, Test Suite Sales Engineer @ UiPath, Inc.
“An Outlook of the Ongoing and Future Relationship between Blockchain Technologies and Process-aware Information Systems.” Invited talk at the joint workshop on Blockchain for Information Systems (BC4IS) and Blockchain for Trusted Data Sharing (B4TDS), co-located with with the 36th International Conference on Advanced Information Systems Engineering (CAiSE), 3 June 2024, Limassol, Cyprus.
Communications Mining Series - Zero to Hero - Session 1DianaGray10
This session provides introduction to UiPath Communication Mining, importance and platform overview. You will acquire a good understand of the phases in Communication Mining as we go over the platform with you. Topics covered:
• Communication Mining Overview
• Why is it important?
• How can it help today’s business and the benefits
• Phases in Communication Mining
• Demo on Platform overview
• Q/A
GraphRAG for Life Science to increase LLM accuracyTomaz Bratanic
GraphRAG for life science domain, where you retriever information from biomedical knowledge graphs using LLMs to increase the accuracy and performance of generated answers
Goodbye Windows 11: Make Way for Nitrux Linux 3.5.0!SOFTTECHHUB
As the digital landscape continually evolves, operating systems play a critical role in shaping user experiences and productivity. The launch of Nitrux Linux 3.5.0 marks a significant milestone, offering a robust alternative to traditional systems such as Windows 11. This article delves into the essence of Nitrux Linux 3.5.0, exploring its unique features, advantages, and how it stands as a compelling choice for both casual users and tech enthusiasts.
In the rapidly evolving landscape of technologies, XML continues to play a vital role in structuring, storing, and transporting data across diverse systems. The recent advancements in artificial intelligence (AI) present new methodologies for enhancing XML development workflows, introducing efficiency, automation, and intelligent capabilities. This presentation will outline the scope and perspective of utilizing AI in XML development. The potential benefits and the possible pitfalls will be highlighted, providing a balanced view of the subject.
We will explore the capabilities of AI in understanding XML markup languages and autonomously creating structured XML content. Additionally, we will examine the capacity of AI to enrich plain text with appropriate XML markup. Practical examples and methodological guidelines will be provided to elucidate how AI can be effectively prompted to interpret and generate accurate XML markup.
Further emphasis will be placed on the role of AI in developing XSLT, or schemas such as XSD and Schematron. We will address the techniques and strategies adopted to create prompts for generating code, explaining code, or refactoring the code, and the results achieved.
The discussion will extend to how AI can be used to transform XML content. In particular, the focus will be on the use of AI XPath extension functions in XSLT, Schematron, Schematron Quick Fixes, or for XML content refactoring.
The presentation aims to deliver a comprehensive overview of AI usage in XML development, providing attendees with the necessary knowledge to make informed decisions. Whether you’re at the early stages of adopting AI or considering integrating it in advanced XML development, this presentation will cover all levels of expertise.
By highlighting the potential advantages and challenges of integrating AI with XML development tools and languages, the presentation seeks to inspire thoughtful conversation around the future of XML development. We’ll not only delve into the technical aspects of AI-powered XML development but also discuss practical implications and possible future directions.
Maruthi Prithivirajan, Head of ASEAN & IN Solution Architecture, Neo4j
Get an inside look at the latest Neo4j innovations that enable relationship-driven intelligence at scale. Learn more about the newest cloud integrations and product enhancements that make Neo4j an essential choice for developers building apps with interconnected data and generative AI.
AI 101: An Introduction to the Basics and Impact of Artificial IntelligenceIndexBug
Imagine a world where machines not only perform tasks but also learn, adapt, and make decisions. This is the promise of Artificial Intelligence (AI), a technology that's not just enhancing our lives but revolutionizing entire industries.
Threats to mobile devices are more prevalent and increasing in scope and complexity. Users of mobile devices desire to take full advantage of the features
available on those devices, but many of the features provide convenience and capability but sacrifice security. This best practices guide outlines steps the users can take to better protect personal devices and information.
Sudheer Mechineni, Head of Application Frameworks, Standard Chartered Bank
Discover how Standard Chartered Bank harnessed the power of Neo4j to transform complex data access challenges into a dynamic, scalable graph database solution. This keynote will cover their journey from initial adoption to deploying a fully automated, enterprise-grade causal cluster, highlighting key strategies for modelling organisational changes and ensuring robust disaster recovery. Learn how these innovations have not only enhanced Standard Chartered Bank’s data infrastructure but also positioned them as pioneers in the banking sector’s adoption of graph technology.
GraphSummit Singapore | The Art of the Possible with Graph - Q2 2024Neo4j
Neha Bajwa, Vice President of Product Marketing, Neo4j
Join us as we explore breakthrough innovations enabled by interconnected data and AI. Discover firsthand how organizations use relationships in data to uncover contextual insights and solve our most pressing challenges – from optimizing supply chains, detecting fraud, and improving customer experiences to accelerating drug discoveries.
Unlocking Productivity: Leveraging the Potential of Copilot in Microsoft 365, a presentation by Christoforos Vlachos, Senior Solutions Manager – Modern Workplace, Uni Systems
1. Presentation By
Pravin Kolhe, BE (Civil), MTech
Assistant Executive Engineer
Maharashtra
Engineering Training
Academy, Nashik 19
July 2008
1
2. Introduction
The EIA Procedure
EIA Guidelines
Role of different actors in EIA
Projects subjected to EIA
EIA in India
Conclusion
References
2
PPT Downloaded from http://www.pravinkolhe.com/
3. a tool that seeks to ensure sustainable
development through the evaluation of those
impacts arising from a major activity
(policy, plan, program, or project) that are likely
to have significant environmental effects.
It is anticipatory, participatory, and systematic in
nature and relies on multidisciplinary input
(Glasson et al. 1994).
3
PPT Downloaded from http://www.pravinkolhe.com/
4. EIA was made mandatory in 1994 under the
environmental protection Act of 1986 with the
following four objectives:
Predict environmental impact of projects;
Find ways and means to reduce adverse impacts;
Shape the projects to suit local environment;
Present the predictions and options to the decision-
makers.
4
PPT Downloaded from http://www.pravinkolhe.com/
5. Description of the proposed activities;
Description of the base environmental and climatic
conditions
Analysis of the
land use and land use change,
waste generation
water consumption
power consumption
Along with the
Social and health impacts
5
PPT Downloaded from http://www.pravinkolhe.com/
6. An assessment of air pollution and noise
generation.
A risk assessment report and disaster
management plan to mitigate adverse
environmental impacts of proposed activity;
An indication of the likely area to be affected by
the proposed activity or its alternatives;
A detailed environmental feasibility report of all
the information provided.
6
PPT Downloaded from http://www.pravinkolhe.com/
7. A major amendment to EIA Notification was made
in April 1997 for introduction of Public Hearing
(PH) as a part of assessment procedure for
ensuring participation of local people and
stakeholders in various proposed development
activities.
Recent Amendment in the Public hearing
notifications is that hearings are now mandatory
for all projects to which the EIA notification
applies.
7
PPT Downloaded from http://www.pravinkolhe.com/
8. The Impact Assessment
Agency has the overall
responsibility to
administer, and enforce the
provisions related to EIA.
The IAA would be the
Union Ministry of
Environment and Forests.
To deal with projects of
different sectors, three
impact assessment
divisions were constituted.
8
Impact Assessment Division-III (IA-III)
Impact Assessment Division-II (IA-II)
Impact Assessment Division-I (IA-I)
PPT Downloaded from http://www.pravinkolhe.com/
9. 9
Impact Assessment Division-III (IA-III)
Ports & Harbour Projects Tourism Projects
Human Settlement
Projects
Communication Projects
Impact Assessment Division-II (IA-II)
Industrial Projects Thermal Power Projects Mining Projects
Impact Assessment Division-I (IA-I)
River Valley Projects Major Irrigation Projects Hydel Power Projects
PPT Downloaded from http://www.pravinkolhe.com/
10. 10
• Eco-system Management
• Air/Water Pollution Control
• Water Resources Management
• Flora/Fauna Conservation & Management
• Land Use Planning
• Social Sciences/Rehabilitation
• Project Appraisal
• Ecology
• Environmental Health
• Subject Areas Specialists
• Representatives of NGO
• Persons Concerned with environmental
issues
PPT Downloaded from http://www.pravinkolhe.com/
11. The ministry has also
set up six regional
offices for Post
Project Monitoring of
Environment to
monitor and interact
with authorities of
different regions.
11
PPT Downloaded from http://www.pravinkolhe.com/
16. Project Proponent:
Environment Consultant
State Pollution Control Board/Pollution
Control Committee
Public Law
Impact Assessment Agency
16
PPT Downloaded from http://www.pravinkolhe.com/
17. 17
Project
proponent
IAA Environment
Consultant
Reviewer Public Admi
nistra
tive
Body
Screening Decides the type of
project and also
about requirement
of Environmental
Clearance
Guides the
proponent in
the initial
screening
stage.
Determines if the
initial project
description
submitted is
adequate.
Scoping Provide TOR Guidance is
provided to the
proponent, if
needed
Establish if an
EIA study is
required and if
so, finalize the
scope of the
study.
EIA Report Prepares detailed
project report and
provide information
in logical and
transparent
manner
Examines if
procedures have
been followed as
per MoEF
notifications,
assesses the
report.
Has to go through
the EIA Report
very carefully.
After the
completion of
EIA report, the
law requires that
the public must
be informed and
consulted.PPT Downloaded from http://www.pravinkolhe.com/
18. 18
Baseline
Conditions
/Adhere to the
attributes,
recommended by
the BIS, CPCB, and
MoEF.
Should be conversant
with the existing legal
and procedural
requirements for the
project.
Responsible for assessing the
compatibility of the proposed
development with prescribed
standards.
Public
Hearing
Approach the SPCB
for holding the public
hearing. Obliged to
respond to issues
raised during the
hearing
SPCB forward the
details of Public
hearing to IAA.
SPCB's hold the public
hearing as per the provisions
of EIA Notification and
forward the details to IAA.
Decision
Making
IAA assists
administrative
authority in the
decision making
process
Justify the findings in
the EIA during
meetings with the
expert group.
Makes decision along with IAA
Monitoring
clearance
conditions
Should be done in
the construction and
operation phase.
Plays a role in the
monitoring process
by examining
reports and taking
further action
Should monitor the
implementation of conditions
PPT Downloaded from http://www.pravinkolhe.com/
20. Projects where EIA is mandatory and requires clearance
from Central government.
As of now, EIA clearance is required for 30 categories of
industries from the central government which can be
broadly categorized under sectors of-
20
PPT Downloaded from http://www.pravinkolhe.com/
Industries,
Mining,
Thermal power plants,
River valley, ports, harbors
and airports,
Communication,
Atomic energy,
Transport (rail, road,
highway),
Tourism (including hotels,
beach resorts)
21. Projects where EIA is mandatory and requires clearance
from State Governments.
Projects coming under this category are thermal power
plants namely;
all capacity cogeneration plants,
captive coal and gas/naphtha based power plants up to 250 MW,
coal based power plants up to 250 MW using conventional
technologies,
coal based plants up to 500 MW using fluidized bed technology
gas/naphtha based plants up to 500 MW require environmental
clearance from the state government.
21
PPT Downloaded from http://www.pravinkolhe.com/
22. For these projects EIA is not necessary:
Some of the projects that come under this category include-
defense related road construction projects in border areas,
production of bulk drugs based on genetically engineered organisms
Construction activities related to the projects of Department of Atomic
Energy
laying of pipelines, conveying systems including transmission lines;
Exploration and extraction of oil and natural gas is also permitted between
Low Tide Line (LTL) and High Tide Line (HTL) in areas, which are not
ecologically sensitive,
pipeline projects;
Facilities for receipt and storage of Liquefied Natural Gas (LNG) and
facilities for its re-gasification.
22
PPT Downloaded from http://www.pravinkolhe.com/
23. 23
PPT Downloaded from http://www.pravinkolhe.com/
Religious and historic places
Archaeological monuments/sites
Scenic areas
Hill resorts/mountains/ hills
Beach resorts
Health resorts
Coastal areas rich in corals,
mangroves, breeding grounds of
specific species
Estuaries rich in mangroves, breeding
ground of specific species
Gulf areas
Biosphere reserves
National park and wildlife sanctuaries
Natural lakes, swamps, Seismic zones tribal
Settlements
Areas of scientific and geological interests
Defense installations, specially those of
security importance and sensitive to pollution
Border areas (international)
Airport
Tiger reserves/elephant reserve/turtle nestling
grounds
Habitat for migratory birds
Lakes, reservoirs, dams
Streams/rivers/estuary/seas
Railway lines
Highways
Urban agglomeration
24. Acts Related to Environment in
India-
24
PPT Downloaded from http://www.pravinkolhe.com/
26. In this presentation we
had discussed about-
1. Introduction and matters
covered in EIA
2. Administrative
arrangement and Expert
Committees
3. EIA Procedure
4. Role of different actors in
EIA
5. Projects subjected to EIA
(Category I, II and III)
Some improvement is
needed in this
controversial issue in India
because of little
participatory democracy in
the formulation and
implementation of
environmental legislation.
Another major
improvement required is in
the area of PAP
involvement.
26
PPT Downloaded from http://www.pravinkolhe.com/
27. The literature reveals that the EIA Notification contains
many of the key elements found in most processes
throughout the world including
1. screening,
2. scoping,
3. comprehensive study,
4. progress reports,
5. review,
6. decision and
7. follow-up.
27
PPT Downloaded from http://www.pravinkolhe.com/
28. Banham, W. and D. Brew (1996). "A review of the development of environmental impact Assessment in India."
Project Appraisal 11(3): 195-202.
Canter, L. W. (1996) Environmental Impact Assessment (New York, McGraw-Hill).
Chapin, H. & Deneau, D. (1978) 'Access and the Policy-making Process'; Ottawa, Canadian Council on Social
Development.
Divan, Shyam and Rosencranz, Armin (2001) 'Environmental Law and Policy in India', Oxford University
Press, New Delhi.
Dwivedi, O. P. (1997). India's Environmental Policies, Programmes and Stewardship.New York, St. Martin's
Press
Gelhorn, E. (1971) 'Public participation in administrative proceedings', Yale Law Journal, 81, pp. 359--387.
Gibson, R. (1993). "Environmental assessment design: lessons from the Canadian experience." The
Environmental Professional 15: 12-24.
Glasson, J., Therivel, R. & Chadwick, A. (1994) 'Introduction to Environmental Impact Assessment' (London
UCL Press)
Government of India Ministry of Environment & Forests website: http://www.envfor.nic.in
Grima, A. P. (1985) 'Participatory rites: integrating public involvement in environmental impact assessment', in:
J.B.R. Whitney & V.W. Maclaren (Eds) Environmental Impact Assessment: The Canadian Experience
(Toronto, University of Toronto).
28
PPT Downloaded from http://www.pravinkolhe.com/
29. Kohli, Kanchi and Menon, Manju (2002) 'Environmental Impacts-Biased Assessments', The Survey of the Environment, The
Hindu
Krimsky, S. & Plough, A. (1988) Environmental Hazards: Communicating Risks as a Social Process Dover, MA, Auburn
House
Mazumdar, Madhusree (2000) 'Environmental Impact Assessment in India', Journal of Social and Economic Development,
Vol III, No 1, Jan-June
Olokesusi, Femi (1998) 'Legal and Institutional Framework of Environmental Impact Assessment in Nigeria: An Initial Impact
Assessment', Environmental Impact Assessment Review Vol 18: 159-174.
Palerm, J (1999a) 'Public Participation in EIA in Hungary: An Analysis through three Case Studies', Environmental Impact
Assessment Review Vol. 19: 201-220.
Palerm, J (1999b) 'Public Participation in EIA in Spain: An assessment of the national, the Catalan and the Balearic
Legislation, Impact Assessment and Project Appraisal, 17(4): 259-271.
Palerm, Juan R., (2000) 'An Empirical - Theoretical framework for Public Participation in the Environmental Impact
Assessment', Journal of Environmental Planning and Management. Vol 43, Issue 5.
Pardo, Mercedes (1997) 'Environmental Impact Assessment: Myth or Reality? Lessons from Spain', Environmental Impact
Assessment Review Vol. 17: 123-142.
29
PPT Downloaded from http://www.pravinkolhe.com/
30. Pearce, D. W., Edwards, L. & Beuret, G. (1979) 'Decision-making for Energy Futures: A Case Study of the Windscale Inquiry'
(London, Macmillan, in association with the SSRC).
Portney, K. E. (1991) 'Public environmental policy decision-making: citizen roles, in: R.A. Chechile & S. Carlisle (Eds)
Environmental Decision-making: A Multidisciplinary Perspective' (New York, Van Nostrand Reinhold).
Rajan, S.C (1997) 'Impact Assessments Fundamentally Flawed', The Survey of the Environment 'The Hindu'.
Shepherd, Anne and Bowler, Christi (1997) 'Beyond the Requirements: Improving Public Participation', Journal of Environment
Planning and Management Vol 40(6): 725-739.
Sinclair.J and Diduck.A (1999) 'Public Involvement in Hydro Development in Kullu District, Himachal Pradesh, India' Shastri
Project on Urban Development and Environmental Impacts in a Mountain Context Technical Report No. 13.
Strong, A. L., Mandelker, D. R. & Kelly, E. D. (1996) 'Property rights and Takings', Journal of the American Planning
Association, 62(1): 5-16
Thakur, K. (1997). Environmental Protection Law and Policy in India. New Delhi, Deep and Deep Publications
UNEP (1988) Environment Impact Assessment: Basic Procedures for Developing Countries (Nairobi, UNEP office for Asia and
the Pacific)
Webler, Thomas., Kastenholz, Hans., and Renn, Ortwin (1995) 'Public Participation in Impact Assessment: A Social Learning
Perspective', Environmental Impact Assessment Review Vol 15 pp 443-463.
30
PPT Downloaded from http://www.pravinkolhe.com/
31. http://www-
wds.worldbank.org/servlet/WDS_IBank_Servle
t (for document and reports)
http://www.unep.org/unep/products/eeu/eeupu
b.htm
http://www.europa.eu.int/comm/environment/ei
a/home.htm
http://www.ceaa.gc.ca
http://earth1.epa.gov/Access - An
Environmental Directory
http://www.enrin.gov.au/net/eianet.html
http://iisd1.iisd.ca/
31
http://www-
wds.worldbank.org/servlet/WDS_IBank_Servle
t (for document and reports)
http://www.unep.org/unep/products/eeu/eeupu
b.htm
http://www.europa.eu.int/comm/environment/ei
a/home.htm
http://www.ceaa.gc.ca
http://earth1.epa.gov/Access - An
Environmental Directory
http://www.enrin.gov.au/net/eianet.html
http://iisd1.iisd.ca/
PPT Downloaded from http://www.pravinkolhe.com/