SlideShare a Scribd company logo
AUTHOR:
DATE:
URP M&E 1st Quarterly
Progress Report
Overview
URP M&E Team
6 August 2018
INTRODUCTION
 Background
 Structure of URP
 Purpose of 1st QPR
 Methodology
 Status of KAAs
 Challenges
 Opportunities
 Recommendations
Broader Context
 URP is consistent with Higher Level Objectives
 GoB’s 7th 5-year Plan & NSDS (Nat’l SD Strategy)
 WB’s Country Partnership Framework with GoB
 Objectives (PDO) of URP:
Strengthen GoB’s capacity to respond to emergency
events; and
Reduce vulnerability of future buildings to disasters in
Dhaka and Sylhet.
Structure of URP
 4 Components
 A: Reinforce Country’s EMR Capacity
 B: Vulnerability Ass’t & Risk-based LUC
 C: Improved Construction, Urban Planning and
Dev’t
 D: URP Coordination and M&E
 E: (contingency in case of disaster)
Purpose of 1st QPR
 Provide “feedback” to IAs on Progress in
last quarter (4th Q FY2018)
 Help M&E Team set up monitoring system
for KAAs
 Build communication rapport with IAs
 Identify Challenges & Opportunities
 Make tentative Recommendations
Method of Tracking KAAs
 M&E Team tracked progress made by each
IA on Key Agreed Actions (KAAs)
 Created individual KAA Tracking Forms for
each IA (plus 3 “common” KAAs)
 DDM: 4 KAAs
 DNCC: 22
 RAJUK: 20
 PCMU: 6
 Collected Info from IAs in July
Component A
 A-1: DDM to renovate ERCC & NDMRTI
 A-2: DNCC to renovate City Corp & FSCD
 A-3: DNCC to supply ECT equipment
 A-4: DNCC to supply SAR equipment
 A-5: DDM to provide TED assistance
DDM – A1 & A5
 A1: DDM renovate ERCC & NDMRTI
 Waiting for design approval from MoDMR
 Contract not signed yet
 A5: TED Assistance Program
 Waiting for NOL from WB
 Pending approval from MoDMR
 Verification by M&E Team pending
DNCC- A2, A3 & A4
 A2: Renovate City Corp & FSCD facilities
 Substantial progress made on most KAAs
 Constructed 19/20 warehouses
 A3: Supply ECT equipment
Delivery to FSCD expected by Nov.
 A4: Provide SAR equipment
 Substantial progress procuring equipment
Component B - RAJUK
 B1: Vulnerability Assessment (VA)
 NOL not received yet (S-4)
 Evaluation not done yet for Earthquake &
Seismic equipment (G-9).
 B2: Risk-Sensitive Land use Plan (RSLUP)
 WB decision pending (S-5)
 Re-tendering yet to start for Earthquake &
Seismic equipment for RSLUP (G-10)
Component C - RAJUK
 C1: Establish URU in RAJUK
 Most KAAs provide institutional “infrastructure”
 Mixed progress (only 2/8 KAAs completed)
 C2: e-permitting system for construction
 Contract not signed (S-7); expected by Aug18.
 C3: Professional Accreditation Program
 Re-RPF not done (S-8); expected in Sept18
 C4: Improve Building Code Enforcement
 CCGP approval not received (S-9); in August18
Component D - PCMU
 PCMU/URP
Coordination helpful in establishing
communication with IAs
 Insufficient KAA reporting
 M&E Team
 Shall continue monitoring progress of IAs
 Develop M&E Framework & Report
 Develop PMIS prototype by end of 2018 &
final PMIS & website by 3rd Q FY19
Challenges
 How to achieve greater implementation
efficiency & effectiveness?
 Turning Activities & Outputs into Outcomes
 Ensuring IA’s absorption of TA
 Complex & confusing WB requirements
 Lengthy & time-consuming staffing decisions
 Maintaining M&E’s Independence/Credibility
 Increase flow & ease of Info between IAs
 Reach consensus on URP Scope & Duration
Opportunities
 Greater “harmonization” of reporting forms
 Use “results chains” to links outputs to outcomes
 Improve IA’s Communication & Coordination
 Make better use of information from other DRM
projects like CDMP, BUERP, ECRRP, etc…
 Increase IA “absorptive capacity” (RAJUK)
 Changes to Scope or Duration of URP?
Recommendations
 “Harmonize” reporting formats to ease reporting
burden on IAs – M&E Team can help
 Shift IA focus away from Activities & Outputs to
focus on Outcomes & PDO – results chains
 Increase Capacity-building Assistance
 Increase Communication and Coordination
among URP IAs
Recommendations
continued
 Accelerate Staff Hiring & Approval
decisions –IA involvement in selection
 Make greater use of Info from other recent
DRM projects in Bangladesh
 Address fundamental question of the Best
Path Forward for URP at mid-point

More Related Content

Similar to 1st APR-URP Presentation

2014_ATIP_Final.pdf
2014_ATIP_Final.pdf2014_ATIP_Final.pdf
2014_ATIP_Final.pdf
健 李
 
Visual Guide to UNDP Programming Cycle PC_complete_visual_guide_v3.0.pdf
Visual Guide to UNDP Programming Cycle PC_complete_visual_guide_v3.0.pdfVisual Guide to UNDP Programming Cycle PC_complete_visual_guide_v3.0.pdf
Visual Guide to UNDP Programming Cycle PC_complete_visual_guide_v3.0.pdf
MaggieYan11
 
Performance Measures for Highway Capacity Decision Making
Performance Measures forHighway Capacity Decision MakingPerformance Measures forHighway Capacity Decision Making
Performance Measures for Highway Capacity Decision Making
pyoungkyova
 
PMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/Manaus
Peter Mello
 
Integrating cost and schedule in p6 - Oracle Primavera P6 Collaborate 14
Integrating cost and schedule in p6 - Oracle Primavera P6 Collaborate 14Integrating cost and schedule in p6 - Oracle Primavera P6 Collaborate 14
Integrating cost and schedule in p6 - Oracle Primavera P6 Collaborate 14
p6academy
 
CP5 Enhancements Delivery Plan June 15 UPDATE
CP5 Enhancements Delivery Plan  June 15 UPDATECP5 Enhancements Delivery Plan  June 15 UPDATE
CP5 Enhancements Delivery Plan June 15 UPDATESepehr Aghamehdi
 
kiran Planning sche engineer CV
kiran Planning sche engineer CVkiran Planning sche engineer CV
kiran Planning sche engineer CVkiran kumar Reddy
 
Bangkok M&E[1] Nigel
Bangkok M&E[1] NigelBangkok M&E[1] Nigel
Bangkok M&E[1] Nigelsakphouseth
 
Menarid: Fourth learning workshop
Menarid: Fourth learning workshopMenarid: Fourth learning workshop
Menarid: Fourth learning workshopICARDA
 
Mansour l menarid-presentation-rbm-m&e
Mansour l menarid-presentation-rbm-m&eMansour l menarid-presentation-rbm-m&e
Mansour l menarid-presentation-rbm-m&egroundwatercop
 
CV Shray Jain
CV Shray Jain CV Shray Jain
CV Shray Jain
Shray Jain
 
Eurporean nuclear conference 2016 enkom
Eurporean nuclear conference 2016  enkomEurporean nuclear conference 2016  enkom
Eurporean nuclear conference 2016 enkom
Martyn Jenkins
 
RESUME_difronzo_2016
RESUME_difronzo_2016RESUME_difronzo_2016
RESUME_difronzo_2016john difronzo
 

Similar to 1st APR-URP Presentation (20)

JJC-CV - April-2016
JJC-CV - April-2016JJC-CV - April-2016
JJC-CV - April-2016
 
2014_ATIP_Final.pdf
2014_ATIP_Final.pdf2014_ATIP_Final.pdf
2014_ATIP_Final.pdf
 
Updated CV
Updated CVUpdated CV
Updated CV
 
Visual Guide to UNDP Programming Cycle PC_complete_visual_guide_v3.0.pdf
Visual Guide to UNDP Programming Cycle PC_complete_visual_guide_v3.0.pdfVisual Guide to UNDP Programming Cycle PC_complete_visual_guide_v3.0.pdf
Visual Guide to UNDP Programming Cycle PC_complete_visual_guide_v3.0.pdf
 
William paterson governance in dgh june 14 2011
William paterson governance in dgh june 14 2011William paterson governance in dgh june 14 2011
William paterson governance in dgh june 14 2011
 
Performance Measures for Highway Capacity Decision Making
Performance Measures forHighway Capacity Decision MakingPerformance Measures forHighway Capacity Decision Making
Performance Measures for Highway Capacity Decision Making
 
Ghandi p bill paterson ppt v 3
Ghandi p bill paterson ppt v 3Ghandi p bill paterson ppt v 3
Ghandi p bill paterson ppt v 3
 
Symons
SymonsSymons
Symons
 
PMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/Manaus
 
Integrating cost and schedule in p6 - Oracle Primavera P6 Collaborate 14
Integrating cost and schedule in p6 - Oracle Primavera P6 Collaborate 14Integrating cost and schedule in p6 - Oracle Primavera P6 Collaborate 14
Integrating cost and schedule in p6 - Oracle Primavera P6 Collaborate 14
 
CP5 Enhancements Delivery Plan June 15 UPDATE
CP5 Enhancements Delivery Plan  June 15 UPDATECP5 Enhancements Delivery Plan  June 15 UPDATE
CP5 Enhancements Delivery Plan June 15 UPDATE
 
kiran Planning sche engineer CV
kiran Planning sche engineer CVkiran Planning sche engineer CV
kiran Planning sche engineer CV
 
Geraldine_Goh-CV
Geraldine_Goh-CVGeraldine_Goh-CV
Geraldine_Goh-CV
 
Building country M&E capacity to manage for and report on results - Nigel Brett
Building country M&E capacity to manage for and report on results - Nigel BrettBuilding country M&E capacity to manage for and report on results - Nigel Brett
Building country M&E capacity to manage for and report on results - Nigel Brett
 
Bangkok M&E[1] Nigel
Bangkok M&E[1] NigelBangkok M&E[1] Nigel
Bangkok M&E[1] Nigel
 
Menarid: Fourth learning workshop
Menarid: Fourth learning workshopMenarid: Fourth learning workshop
Menarid: Fourth learning workshop
 
Mansour l menarid-presentation-rbm-m&e
Mansour l menarid-presentation-rbm-m&eMansour l menarid-presentation-rbm-m&e
Mansour l menarid-presentation-rbm-m&e
 
CV Shray Jain
CV Shray Jain CV Shray Jain
CV Shray Jain
 
Eurporean nuclear conference 2016 enkom
Eurporean nuclear conference 2016  enkomEurporean nuclear conference 2016  enkom
Eurporean nuclear conference 2016 enkom
 
RESUME_difronzo_2016
RESUME_difronzo_2016RESUME_difronzo_2016
RESUME_difronzo_2016
 

Recently uploaded

Steel & Timber Design according to British Standard
Steel & Timber Design according to British StandardSteel & Timber Design according to British Standard
Steel & Timber Design according to British Standard
AkolbilaEmmanuel1
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
manasideore6
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
aqil azizi
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
Kamal Acharya
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
manasideore6
 

Recently uploaded (20)

Steel & Timber Design according to British Standard
Steel & Timber Design according to British StandardSteel & Timber Design according to British Standard
Steel & Timber Design according to British Standard
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Fundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptxFundamentals of Electric Drives and its applications.pptx
Fundamentals of Electric Drives and its applications.pptx
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdfTutorial for 16S rRNA Gene Analysis with QIIME2.pdf
Tutorial for 16S rRNA Gene Analysis with QIIME2.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Water billing management system project report.pdf
Water billing management system project report.pdfWater billing management system project report.pdf
Water billing management system project report.pdf
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Fundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptxFundamentals of Induction Motor Drives.pptx
Fundamentals of Induction Motor Drives.pptx
 

1st APR-URP Presentation

  • 1. AUTHOR: DATE: URP M&E 1st Quarterly Progress Report Overview URP M&E Team 6 August 2018
  • 2. INTRODUCTION  Background  Structure of URP  Purpose of 1st QPR  Methodology  Status of KAAs  Challenges  Opportunities  Recommendations
  • 3. Broader Context  URP is consistent with Higher Level Objectives  GoB’s 7th 5-year Plan & NSDS (Nat’l SD Strategy)  WB’s Country Partnership Framework with GoB  Objectives (PDO) of URP: Strengthen GoB’s capacity to respond to emergency events; and Reduce vulnerability of future buildings to disasters in Dhaka and Sylhet.
  • 4. Structure of URP  4 Components  A: Reinforce Country’s EMR Capacity  B: Vulnerability Ass’t & Risk-based LUC  C: Improved Construction, Urban Planning and Dev’t  D: URP Coordination and M&E  E: (contingency in case of disaster)
  • 5. Purpose of 1st QPR  Provide “feedback” to IAs on Progress in last quarter (4th Q FY2018)  Help M&E Team set up monitoring system for KAAs  Build communication rapport with IAs  Identify Challenges & Opportunities  Make tentative Recommendations
  • 6. Method of Tracking KAAs  M&E Team tracked progress made by each IA on Key Agreed Actions (KAAs)  Created individual KAA Tracking Forms for each IA (plus 3 “common” KAAs)  DDM: 4 KAAs  DNCC: 22  RAJUK: 20  PCMU: 6  Collected Info from IAs in July
  • 7. Component A  A-1: DDM to renovate ERCC & NDMRTI  A-2: DNCC to renovate City Corp & FSCD  A-3: DNCC to supply ECT equipment  A-4: DNCC to supply SAR equipment  A-5: DDM to provide TED assistance
  • 8. DDM – A1 & A5  A1: DDM renovate ERCC & NDMRTI  Waiting for design approval from MoDMR  Contract not signed yet  A5: TED Assistance Program  Waiting for NOL from WB  Pending approval from MoDMR  Verification by M&E Team pending
  • 9. DNCC- A2, A3 & A4  A2: Renovate City Corp & FSCD facilities  Substantial progress made on most KAAs  Constructed 19/20 warehouses  A3: Supply ECT equipment Delivery to FSCD expected by Nov.  A4: Provide SAR equipment  Substantial progress procuring equipment
  • 10. Component B - RAJUK  B1: Vulnerability Assessment (VA)  NOL not received yet (S-4)  Evaluation not done yet for Earthquake & Seismic equipment (G-9).  B2: Risk-Sensitive Land use Plan (RSLUP)  WB decision pending (S-5)  Re-tendering yet to start for Earthquake & Seismic equipment for RSLUP (G-10)
  • 11. Component C - RAJUK  C1: Establish URU in RAJUK  Most KAAs provide institutional “infrastructure”  Mixed progress (only 2/8 KAAs completed)  C2: e-permitting system for construction  Contract not signed (S-7); expected by Aug18.  C3: Professional Accreditation Program  Re-RPF not done (S-8); expected in Sept18  C4: Improve Building Code Enforcement  CCGP approval not received (S-9); in August18
  • 12. Component D - PCMU  PCMU/URP Coordination helpful in establishing communication with IAs  Insufficient KAA reporting  M&E Team  Shall continue monitoring progress of IAs  Develop M&E Framework & Report  Develop PMIS prototype by end of 2018 & final PMIS & website by 3rd Q FY19
  • 13. Challenges  How to achieve greater implementation efficiency & effectiveness?  Turning Activities & Outputs into Outcomes  Ensuring IA’s absorption of TA  Complex & confusing WB requirements  Lengthy & time-consuming staffing decisions  Maintaining M&E’s Independence/Credibility  Increase flow & ease of Info between IAs  Reach consensus on URP Scope & Duration
  • 14. Opportunities  Greater “harmonization” of reporting forms  Use “results chains” to links outputs to outcomes  Improve IA’s Communication & Coordination  Make better use of information from other DRM projects like CDMP, BUERP, ECRRP, etc…  Increase IA “absorptive capacity” (RAJUK)  Changes to Scope or Duration of URP?
  • 15. Recommendations  “Harmonize” reporting formats to ease reporting burden on IAs – M&E Team can help  Shift IA focus away from Activities & Outputs to focus on Outcomes & PDO – results chains  Increase Capacity-building Assistance  Increase Communication and Coordination among URP IAs
  • 16. Recommendations continued  Accelerate Staff Hiring & Approval decisions –IA involvement in selection  Make greater use of Info from other recent DRM projects in Bangladesh  Address fundamental question of the Best Path Forward for URP at mid-point