SlideShare a Scribd company logo
Subrata Das subrata.das@hcst.edu.in
START-UP & COMMISSIO
1,200 MEGAWATT GAS TURBINE POWER PLANT
The power plant is a two-unit 1200 MW steam turbine generator plant with the usual
additional features of:
Water treatment building Warehouse/machine shop
Administration building Guardhouse
Fuel-oil pump house Intake building
At the start of the project, managers prepare a detailed plan and schedule. They review
drawings, specifications and plans. During the critical final phase of commissioning, specialists
in the field conduct performance tests to assure that equipment is functioning as specified and
that the plant systems are ready for operation. They prepare plant documentation and train the
plant operators and maintenance crew. The start-up and commissioning must be detailed and
flexible to cater for all events. The teams must be ready to respond to any surprises but keep
within the planned schedule of time and costs.
Start-up services include preparation of operation and maintenance manuals, system
descriptions and operating instructions, and integrated operating instructions, including
vendor O&M manuals.
The start-up manager must perform the following duties.
• Establishes a contractor release schedule and packages.
• Schedules test witnesses and monitoring
• Sets safety and environmental standards
On-site field engineers conduct:
• Component testing
• Flushing
• Chemical cleaning
• Steam blowing
• Initial equipment operation system facility tests such as performance, emissions,
and noise control.
Key start-up events included:
• Electrical back-feed
• First fire of each combustion turbine generator
• Testing of the steam supply to the steam turbine generators
• Performance testing
When the facility is operational, start-up and commissioning experts train power plant
personnel to operate and maintain the new plant or system. They provide direct instruction
about the balance of plant systems and coordinated vendor training for control systems,
turbine generators, and the water treatment.
1

More Related Content

What's hot

Refinery Overhauling Introduction
Refinery Overhauling IntroductionRefinery Overhauling Introduction
Refinery Overhauling Introduction
Ashar Ahmed
 
Tables Presentation Refinery Overhauling
Tables Presentation Refinery OverhaulingTables Presentation Refinery Overhauling
Tables Presentation Refinery Overhauling
Ashar Ahmed
 
Raghunath Patil
Raghunath Patil Raghunath Patil
Raghunath Patil
Raghunath Patil
 
Operation and maintanance
Operation and maintananceOperation and maintanance
Operation and maintanance
AnasMirza10
 
boiler operator cv
boiler operator cvboiler operator cv
boiler operator cvHamad Talhaa
 
ALBARICK POWER PLANT NEW CV
ALBARICK POWER PLANT NEW CVALBARICK POWER PLANT NEW CV
ALBARICK POWER PLANT NEW CVal barick
 
Pankaj Sharma 2015 Resume
Pankaj Sharma 2015 ResumePankaj Sharma 2015 Resume
Pankaj Sharma 2015 Resumesharmapower
 
Fuel Injection Department Brochure
Fuel Injection Department BrochureFuel Injection Department Brochure
Fuel Injection Department BrochureKIMI SA
 
Arun Goyle resume
Arun Goyle resumeArun Goyle resume
Arun Goyle resumeArun Goyle
 
EF boiler house risk assessment
EF boiler house risk assessmentEF boiler house risk assessment
EF boiler house risk assessment
Leigh Ridlington
 
David DiBiase Resume-2
David DiBiase Resume-2David DiBiase Resume-2
David DiBiase Resume-2David DiBiase
 
David DiBiase Resume-2
David DiBiase Resume-2David DiBiase Resume-2
David DiBiase Resume-2David DiBiase
 

What's hot (20)

chayana
chayanachayana
chayana
 
Refinery Overhauling Introduction
Refinery Overhauling IntroductionRefinery Overhauling Introduction
Refinery Overhauling Introduction
 
Tables Presentation Refinery Overhauling
Tables Presentation Refinery OverhaulingTables Presentation Refinery Overhauling
Tables Presentation Refinery Overhauling
 
Raghunath Patil
Raghunath Patil Raghunath Patil
Raghunath Patil
 
Operation and maintanance
Operation and maintananceOperation and maintanance
Operation and maintanance
 
Saravanan resume
Saravanan resumeSaravanan resume
Saravanan resume
 
boiler operator cv
boiler operator cvboiler operator cv
boiler operator cv
 
ALBARICK POWER PLANT NEW CV
ALBARICK POWER PLANT NEW CVALBARICK POWER PLANT NEW CV
ALBARICK POWER PLANT NEW CV
 
Pankaj Sharma 2015 Resume
Pankaj Sharma 2015 ResumePankaj Sharma 2015 Resume
Pankaj Sharma 2015 Resume
 
Resume
ResumeResume
Resume
 
new resume2016
new resume2016new resume2016
new resume2016
 
Resume R
Resume RResume R
Resume R
 
Fuel Injection Department Brochure
Fuel Injection Department BrochureFuel Injection Department Brochure
Fuel Injection Department Brochure
 
Arun Goyle resume
Arun Goyle resumeArun Goyle resume
Arun Goyle resume
 
Saikaat Saha CV
Saikaat Saha CVSaikaat Saha CV
Saikaat Saha CV
 
CV_Anand
CV_AnandCV_Anand
CV_Anand
 
manju_cv_ updated
manju_cv_ updatedmanju_cv_ updated
manju_cv_ updated
 
EF boiler house risk assessment
EF boiler house risk assessmentEF boiler house risk assessment
EF boiler house risk assessment
 
David DiBiase Resume-2
David DiBiase Resume-2David DiBiase Resume-2
David DiBiase Resume-2
 
David DiBiase Resume-2
David DiBiase Resume-2David DiBiase Resume-2
David DiBiase Resume-2
 

Viewers also liked

An Application of Energy and Exergy Analysis of Transport Sector of India
An Application of Energy and Exergy Analysis of Transport  Sector of IndiaAn Application of Energy and Exergy Analysis of Transport  Sector of India
An Application of Energy and Exergy Analysis of Transport Sector of India
IJMER
 
Ppt for power plant
Ppt for power plantPpt for power plant
Ppt for power plant
ra m
 
Engineering thermodynamics ece
Engineering thermodynamics eceEngineering thermodynamics ece
Engineering thermodynamics ecephysics101
 
Exergy Based Performance Analysis of FGPS (NTPC Faridabad)
Exergy Based Performance Analysis of FGPS (NTPC Faridabad)Exergy Based Performance Analysis of FGPS (NTPC Faridabad)
Exergy Based Performance Analysis of FGPS (NTPC Faridabad)
Santosh Verma
 
CAPE PENINSULA UNIVERSITY OF TECHONOLOGY DEPARTMENT OF MECHENICAL ENGINEERIN...
CAPE PENINSULA UNIVERSITY OF TECHONOLOGY  DEPARTMENT OF MECHENICAL ENGINEERIN...CAPE PENINSULA UNIVERSITY OF TECHONOLOGY  DEPARTMENT OF MECHENICAL ENGINEERIN...
CAPE PENINSULA UNIVERSITY OF TECHONOLOGY DEPARTMENT OF MECHENICAL ENGINEERIN...
lizwi nyandu
 
Gas Turbine Power Generation Plant Engineer Ref 1212 10
Gas Turbine Power Generation Plant Engineer Ref 1212 10Gas Turbine Power Generation Plant Engineer Ref 1212 10
Gas Turbine Power Generation Plant Engineer Ref 1212 10
Sean Durrant
 
Energy and exergy analysis of reverse brayton refrigerator for gas turbine po...
Energy and exergy analysis of reverse brayton refrigerator for gas turbine po...Energy and exergy analysis of reverse brayton refrigerator for gas turbine po...
Energy and exergy analysis of reverse brayton refrigerator for gas turbine po...
fsnexuss
 
Decarbonization CCPP
Decarbonization CCPPDecarbonization CCPP
Decarbonization CCPP
Igor Petrikej
 
Exergy profile for Solar Services
Exergy profile for Solar ServicesExergy profile for Solar Services
Exergy profile for Solar Services
Tarun Rathore
 
Cairo 2nd Petrol Lecture 7
Cairo 2nd Petrol Lecture 7Cairo 2nd Petrol Lecture 7
Cairo 2nd Petrol Lecture 7Esmail Bialy
 
Lab 1 the dryness fraction of the steam(mech)
Lab 1   the dryness fraction of the steam(mech)Lab 1   the dryness fraction of the steam(mech)
Lab 1 the dryness fraction of the steam(mech)
lizwi nyandu
 
Lab 3 boiler efficiency & condensers
Lab 3   boiler efficiency & condensersLab 3   boiler efficiency & condensers
Lab 3 boiler efficiency & condensers
lizwi nyandu
 
Phonicsalphabetsong 090506031454 Phpapp02
Phonicsalphabetsong 090506031454 Phpapp02Phonicsalphabetsong 090506031454 Phpapp02
Phonicsalphabetsong 090506031454 Phpapp02
Nanaisa
 
Clausius - Clapeyron Equation
Clausius - Clapeyron EquationClausius - Clapeyron Equation
Clausius - Clapeyron Equation
Marx Endico
 
Thermodynamics - Experiment 2
Thermodynamics - Experiment 2Thermodynamics - Experiment 2
Thermodynamics - Experiment 2
syar2604
 
Final lab report for thermos 2(mech)
Final lab report for thermos 2(mech)Final lab report for thermos 2(mech)
Final lab report for thermos 2(mech)
lizwi nyandu
 
50 MW solar-thermal-dpr
50 MW solar-thermal-dpr50 MW solar-thermal-dpr
50 MW solar-thermal-dpr
Exergy
 
2 law and exergy change
2 law and exergy change2 law and exergy change
2 law and exergy change
ISEL
 

Viewers also liked (20)

An Application of Energy and Exergy Analysis of Transport Sector of India
An Application of Energy and Exergy Analysis of Transport  Sector of IndiaAn Application of Energy and Exergy Analysis of Transport  Sector of India
An Application of Energy and Exergy Analysis of Transport Sector of India
 
Ppt for power plant
Ppt for power plantPpt for power plant
Ppt for power plant
 
Engineering thermodynamics ece
Engineering thermodynamics eceEngineering thermodynamics ece
Engineering thermodynamics ece
 
Exergy Based Performance Analysis of FGPS (NTPC Faridabad)
Exergy Based Performance Analysis of FGPS (NTPC Faridabad)Exergy Based Performance Analysis of FGPS (NTPC Faridabad)
Exergy Based Performance Analysis of FGPS (NTPC Faridabad)
 
18 quantifiable e xergy
18 quantifiable e xergy18 quantifiable e xergy
18 quantifiable e xergy
 
CAPE PENINSULA UNIVERSITY OF TECHONOLOGY DEPARTMENT OF MECHENICAL ENGINEERIN...
CAPE PENINSULA UNIVERSITY OF TECHONOLOGY  DEPARTMENT OF MECHENICAL ENGINEERIN...CAPE PENINSULA UNIVERSITY OF TECHONOLOGY  DEPARTMENT OF MECHENICAL ENGINEERIN...
CAPE PENINSULA UNIVERSITY OF TECHONOLOGY DEPARTMENT OF MECHENICAL ENGINEERIN...
 
Gas Turbine Power Generation Plant Engineer Ref 1212 10
Gas Turbine Power Generation Plant Engineer Ref 1212 10Gas Turbine Power Generation Plant Engineer Ref 1212 10
Gas Turbine Power Generation Plant Engineer Ref 1212 10
 
Energy and exergy analysis of reverse brayton refrigerator for gas turbine po...
Energy and exergy analysis of reverse brayton refrigerator for gas turbine po...Energy and exergy analysis of reverse brayton refrigerator for gas turbine po...
Energy and exergy analysis of reverse brayton refrigerator for gas turbine po...
 
Decarbonization CCPP
Decarbonization CCPPDecarbonization CCPP
Decarbonization CCPP
 
Exergy profile for Solar Services
Exergy profile for Solar ServicesExergy profile for Solar Services
Exergy profile for Solar Services
 
Cairo 2nd Petrol Lecture 7
Cairo 2nd Petrol Lecture 7Cairo 2nd Petrol Lecture 7
Cairo 2nd Petrol Lecture 7
 
Lab 1 the dryness fraction of the steam(mech)
Lab 1   the dryness fraction of the steam(mech)Lab 1   the dryness fraction of the steam(mech)
Lab 1 the dryness fraction of the steam(mech)
 
Lab 3 boiler efficiency & condensers
Lab 3   boiler efficiency & condensersLab 3   boiler efficiency & condensers
Lab 3 boiler efficiency & condensers
 
Phonicsalphabetsong 090506031454 Phpapp02
Phonicsalphabetsong 090506031454 Phpapp02Phonicsalphabetsong 090506031454 Phpapp02
Phonicsalphabetsong 090506031454 Phpapp02
 
Clausius - Clapeyron Equation
Clausius - Clapeyron EquationClausius - Clapeyron Equation
Clausius - Clapeyron Equation
 
Thermodynamics - Experiment 2
Thermodynamics - Experiment 2Thermodynamics - Experiment 2
Thermodynamics - Experiment 2
 
95396211 heat-transfer-lab-manual
95396211 heat-transfer-lab-manual95396211 heat-transfer-lab-manual
95396211 heat-transfer-lab-manual
 
Final lab report for thermos 2(mech)
Final lab report for thermos 2(mech)Final lab report for thermos 2(mech)
Final lab report for thermos 2(mech)
 
50 MW solar-thermal-dpr
50 MW solar-thermal-dpr50 MW solar-thermal-dpr
50 MW solar-thermal-dpr
 
2 law and exergy change
2 law and exergy change2 law and exergy change
2 law and exergy change
 

Similar to 1,200 megawatt gas turbine

Mohammad Rehan Akbar Khan 2- CV
Mohammad Rehan Akbar Khan 2- CVMohammad Rehan Akbar Khan 2- CV
Mohammad Rehan Akbar Khan 2- CVRehan Khan
 
Mohammad Rehan Akbar Khan .P.M
Mohammad Rehan Akbar Khan .P.MMohammad Rehan Akbar Khan .P.M
Mohammad Rehan Akbar Khan .P.MRehan Khan
 
aqeel shaikh CV IRAQ
aqeel shaikh CV IRAQaqeel shaikh CV IRAQ
aqeel shaikh CV IRAQAqeel Shaikh
 
Mechanical Maintenance Supervisor CV
Mechanical  Maintenance  Supervisor CVMechanical  Maintenance  Supervisor CV
Mechanical Maintenance Supervisor CVvaithiya nathan
 
Curriculum Vitae BDP(rev)
Curriculum Vitae BDP(rev)Curriculum Vitae BDP(rev)
Curriculum Vitae BDP(rev)Budi Prihartono
 
Scott hammond planning scheduling #2
Scott hammond planning scheduling   #2Scott hammond planning scheduling   #2
Scott hammond planning scheduling #2
Scott Hammond
 
Scott Hammond Planning Scheduling - #2
Scott Hammond Planning Scheduling - #2Scott Hammond Planning Scheduling - #2
Scott Hammond Planning Scheduling - #2Scott Hammond
 
Giridhar
GiridharGiridhar
Giridhar
Giridhar C
 
Steve Wonnacott Resume
Steve Wonnacott ResumeSteve Wonnacott Resume
Steve Wonnacott Resume
Steve Wonnacott
 

Similar to 1,200 megawatt gas turbine (20)

Mohammad Rehan Akbar Khan 2- CV
Mohammad Rehan Akbar Khan 2- CVMohammad Rehan Akbar Khan 2- CV
Mohammad Rehan Akbar Khan 2- CV
 
sengu cv
sengu cvsengu cv
sengu cv
 
Zaheer-CV- 2015
Zaheer-CV- 2015Zaheer-CV- 2015
Zaheer-CV- 2015
 
Mohammad Rehan Akbar Khan .P.M
Mohammad Rehan Akbar Khan .P.MMohammad Rehan Akbar Khan .P.M
Mohammad Rehan Akbar Khan .P.M
 
Resume-Ramasamy Ganapathy
Resume-Ramasamy GanapathyResume-Ramasamy Ganapathy
Resume-Ramasamy Ganapathy
 
MOHANNAD CV
MOHANNAD  CVMOHANNAD  CV
MOHANNAD CV
 
aqeel shaikh CV IRAQ
aqeel shaikh CV IRAQaqeel shaikh CV IRAQ
aqeel shaikh CV IRAQ
 
Mechanical Maintenance Supervisor CV
Mechanical  Maintenance  Supervisor CVMechanical  Maintenance  Supervisor CV
Mechanical Maintenance Supervisor CV
 
Sudhanshu Final
Sudhanshu FinalSudhanshu Final
Sudhanshu Final
 
JAI RESUME
JAI RESUMEJAI RESUME
JAI RESUME
 
Sushil podia Ahm
Sushil podia AhmSushil podia Ahm
Sushil podia Ahm
 
Curriculum Vitae BDP(rev)
Curriculum Vitae BDP(rev)Curriculum Vitae BDP(rev)
Curriculum Vitae BDP(rev)
 
CV Nagashiva
CV Nagashiva CV Nagashiva
CV Nagashiva
 
vivek curricullum vitae
vivek curricullum vitaevivek curricullum vitae
vivek curricullum vitae
 
Scott hammond planning scheduling #2
Scott hammond planning scheduling   #2Scott hammond planning scheduling   #2
Scott hammond planning scheduling #2
 
Scott Hammond Planning Scheduling - #2
Scott Hammond Planning Scheduling - #2Scott Hammond Planning Scheduling - #2
Scott Hammond Planning Scheduling - #2
 
Nizami cv
Nizami cvNizami cv
Nizami cv
 
Mahesh_Y_Patil
Mahesh_Y_PatilMahesh_Y_Patil
Mahesh_Y_Patil
 
Giridhar
GiridharGiridhar
Giridhar
 
Steve Wonnacott Resume
Steve Wonnacott ResumeSteve Wonnacott Resume
Steve Wonnacott Resume
 

More from skdass23

Graphics internal chemical
Graphics internal chemicalGraphics internal chemical
Graphics internal chemical
skdass23
 
Com fuel
Com fuelCom fuel
Com fuel
skdass23
 
Cogeneration
CogenerationCogeneration
Cogeneration
skdass23
 
2 gas turbinepp
2 gas turbinepp2 gas turbinepp
2 gas turbinepp
skdass23
 
Msme questionaire
Msme questionaireMsme questionaire
Msme questionaire
skdass23
 
4 model productivity improvement msme
4 model productivity  improvement msme4 model productivity  improvement msme
4 model productivity improvement msme
skdass23
 

More from skdass23 (6)

Graphics internal chemical
Graphics internal chemicalGraphics internal chemical
Graphics internal chemical
 
Com fuel
Com fuelCom fuel
Com fuel
 
Cogeneration
CogenerationCogeneration
Cogeneration
 
2 gas turbinepp
2 gas turbinepp2 gas turbinepp
2 gas turbinepp
 
Msme questionaire
Msme questionaireMsme questionaire
Msme questionaire
 
4 model productivity improvement msme
4 model productivity  improvement msme4 model productivity  improvement msme
4 model productivity improvement msme
 

Recently uploaded

Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
top1002
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
AmarGB2
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 

Recently uploaded (20)

Basic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparelBasic Industrial Engineering terms for apparel
Basic Industrial Engineering terms for apparel
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
Investor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptxInvestor-Presentation-Q1FY2024 investor presentation document.pptx
Investor-Presentation-Q1FY2024 investor presentation document.pptx
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 

1,200 megawatt gas turbine

  • 1. Subrata Das subrata.das@hcst.edu.in START-UP & COMMISSIO 1,200 MEGAWATT GAS TURBINE POWER PLANT The power plant is a two-unit 1200 MW steam turbine generator plant with the usual additional features of: Water treatment building Warehouse/machine shop Administration building Guardhouse Fuel-oil pump house Intake building At the start of the project, managers prepare a detailed plan and schedule. They review drawings, specifications and plans. During the critical final phase of commissioning, specialists in the field conduct performance tests to assure that equipment is functioning as specified and that the plant systems are ready for operation. They prepare plant documentation and train the plant operators and maintenance crew. The start-up and commissioning must be detailed and flexible to cater for all events. The teams must be ready to respond to any surprises but keep within the planned schedule of time and costs. Start-up services include preparation of operation and maintenance manuals, system descriptions and operating instructions, and integrated operating instructions, including vendor O&M manuals. The start-up manager must perform the following duties. • Establishes a contractor release schedule and packages. • Schedules test witnesses and monitoring • Sets safety and environmental standards On-site field engineers conduct: • Component testing • Flushing • Chemical cleaning • Steam blowing • Initial equipment operation system facility tests such as performance, emissions, and noise control. Key start-up events included: • Electrical back-feed • First fire of each combustion turbine generator • Testing of the steam supply to the steam turbine generators • Performance testing When the facility is operational, start-up and commissioning experts train power plant personnel to operate and maintain the new plant or system. They provide direct instruction about the balance of plant systems and coordinated vendor training for control systems, turbine generators, and the water treatment. 1