Establishing University’s
High Performance Computing (HPC) facility.
Student: Sharyu Mahale
2	
Table of Content
1. Letter of Transmittal 3
2. Project Objectives and Goals 4
3. Strategic Plan 5
4. Organization Structure 6
5. Choosing The Right Vendor 7
6. Project Design 8
7. Critical Success Factors 9
8. Implementation Plan 10
8.1 IDEF0 11
8.2 WBS 12
8.3 RACI 13
8.4 Gantt Chart 14
8.5 CPM 16
9 Project Execution Plan 17
10 Project Maintenance Plan 18
11 Budgeting and Financial Analysis 19
12 Tasks and Responsibilities 23
13 Roles and Responsibilities 24
14 Risk Assessment 26
											14.1 RISK Matrix
15 SWOT Analysis 27
16 Future Scope 28
17 References 29
3	
1. LETTER OF TRANSMITTAL
Professor Klosterman
Subject: Proposal for setting up a High Performance Computing (HPC)
facility for the University.
The objective of the project is to provide state-of-the-art computing infrastructure,
resources and high quality services to the various researchers across different
departments in the university by setting up a centralized High Performance
computing (HPC) facility. This investment will be required to stay internationally
competitive.
High Performance Computing is taking very rapid strides and making a telling
impact in every conceivable field of science and technology. The very popular
Moore’s law states that the number of transistors doubles every two years and
hence the computing power doubles every 18-24 months. This law has been
holding steady for the last 4 decades resulting in faster and faster computers that
increasingly reduce the time to resolve grand challenge problems. The
breakthroughs in semiconductor manufacturing and innovative computer
architectures using commodity parts, make High Performance Computing very
affordable and manageable today.
The estimated initial budget for the HPC facility is US$ 2 Million. Periodic
upgrade to the Computer System will be required roughly every 3 years to take
advantage of the new technologies.
Sincerely,	
Sharyu	Mahale
4	
2. PROJECT OBJECTIVES AND GOALS
Ø The main objective of this project is to set up a centralized HPC facility in
the university to cater the computing needs of students and researchers
Ø To evaluate, procure and install the HPC system within 2-3 months within
the allocated budget of US$ 2M
Ø To choose the HPC system that provides seamless scalability for at least 5
years, resulting in investment protection and smooth enhancement of
computing capabilities to keep in step with technology advancements
Ø To ensure that the computing resources are always made available to the
researchers with minimal or no downtime
Ø To set up a team of specialists who can monitor the usage of the facility
constantly
Ø To encourage industry collaboration in areas of national interest and get
additional funding by way of project grants
Ø Creating a Prestigious Reference site “A case study” for business promotion
and brand building to be recognized as a leading ‘HPC’ solution provider
Ø Strengthen relationships with various OEMs involved in the project for
future support
Ø Attracting OEMs who are left out of the current project for future upcoming
requirements
5	
3. STRATEGIC PLAN
Ø Routine communications between the stakeholders and the project manager
Ø Adopting collaborative customer centric approach to gain confidence
Ø Motivating the team
Ø Organize online Webinars on various subjects of new technology and ROAD
map sharing
Ø Conduct training programs to facilitate customer participation
Ø The training and certification for various software tools, compilers, CUDA
programming will attract customers
6	
4. ORGANIZATION STRUCTURE
Ø Projectized Organization structure is used as every employee is assigned a
specific task during the entire course of project
Ø Project manager is consulted and is accountable for every task
Ø PM will communicate with the clients and resolve any grievances
Figure 1: Organizational Structure
Purchasing	
Department		
Project	Manager		
External	
Consultant	
Engineering	
Department		
Purchase	
Manager		
Systems	
Administrator		
Domain	
Specialist		
Electrical	
Department		
Computer	
Science	Engineer		
Site	Preparation	
Specialist	
	
	S	
Power	and	
Cooling	
Specialist	
Finance	
Manager		
Sales	
Representative
7	
5. CHOOSING THE RIGHT VENDOR
Ø After matching the needs of the University, appropriate vendors(OEMs)
providing different solutions are chosen.
Following is the vendor list:
1. Fujitsu which includes (This constitutes the biggest component of the overall
solution)
2. Fujitsu PRIMERGY Servers
3. Fujitsu ETERNUS Storage
4. Fujitsu HCS Cluster Manager
5. Mellanox Infniband Switches as Primary Interconnect
6. D-Link/Digisol Network Switches as Secondary Interconnect
7. Intel Parallel Studio XE 2015
Ø The design is a fully balanced HPC service that maintains synergy between the
fundamental factors affecting the efficiency of a HPC system, namely: compute
power, memory throughput and storage I/O subsystem capabilities
Ø To meet the requirements, careful architecture is chosen. The latest
technological products will ensure processing performance delivery even under
very demanding or diverse environments
8	
6. PROJECT DESIGN
Ø After understanding the requirements of HPC, the following design is proposed
Ø The proposed logical diagram recommends a solution that best meets the
requirements
Figure 2: Logical diagram for 224 nodes cluster
9	
7. CRITICAL SUCCESS FACTORS
The successful setting up of an operational HPC Facility depends on the following
factors:
Ø Forming a core group of experts with specialization in the field of computer
architecture, software, domain specialists. An external consultant is also
preferred to be part of this team
Ø Prepare a comprehensive document that clearly spells out the architecture and
performance requirements of the proposed HPC system. This requires a great
deal of interaction with the key user community and their specific computing
needs
Ø Shortlist and invite globally reputed computer vendors with proven capabilities
for a technical presentation to the University’s core committee members
Ø Critical evaluation of bids from selected vendors and choosing a vendor among
the technically qualified ones with the best price/performance
Ø Ensuring successful implementation of the selected HPC system and running
comprehensive tests on the system to ensure that it meets the performance
parameters set forward in the RFP
Ø Providing the computing resources to various users based on established criteria
and ensuring maximum uptime of the system. This has to be achieved by a team
of engineers from the supplier providing 24x7 onsite technical support
10	
8. IMPLEMENTATION PLAN
Ø Once all the HPC required documents are gathered project moves on to its
implementation phase
Ø Tools like IDEF0, WBS, RACI, Gantt Chart, CPM helps the project to be on
time and on budget
11	
IDEF0
Ø IDEF0 model is is a function modeling methodology for describing
manufacturing functions, which offers a functional modeling language for the
analysis, development, reengineering, and integration of information systems;
business processes; or software engineering analysis[I]
Figure 3: IDEF0 Diagram
12	
WBS
Ø This tool breaks down the work into subtask which helps in easy monitoring of
various tasks
Ø A work breakdown structure (WBS), in project management and systems
engineering, is a deliverable-oriented decomposition of a project into smaller
components[II]
Figure 4: Work breakdown structure (WBS) Diagram
13	
RACI
Ø This tool helps the project manager to keep a track on the authority on the
project and helps him to monitor the work
Ø Uncertainty in the authority can be avoided by allotting responsibilities to
various team members
Figure 5: RACI Diagram
RACI represents: R –Responsibility, A-Accountable, C-Consulted, I-Informed
• Responsibility = person or role responsible for ensuring that the item is
completed
• Accountable = person or role responsible for actually doing or completing
the item
• Consulted = person or role whose subject matter expertise is required in
order to complete the item
• Informed = person or role that needs to be kept informed of the status of
item completion
14	
Gantt chart
Ø Gantt chart illustrates the start and end date of every task in a project
Ø Interdependencies associated with the tasks are taken into consideration
Ø Tasks which are independent are done simultaneously to reduce the number of
days
15	
Figure 6: Gantt chart
16	
CPM (Critical Path Method)
Ø The project can be completed in 66 days
Ø The critical path for the project is START-2-5-7-8-9-13-15-17-18-20-END
Ø All the activities in the critical path can not be delayed and they need to done on
time to avoid any delay in time frame
Ø Activities 3, 4, 11, 14, 12 can be sufficiently delayed as they are not part of the
critical path
Figure 7: Critical Path Diagram
17	
9. PROJECT EXECUTION PLAN
Content Description Time Remark
Open hardware
and check BOM
Open hard ware boxes, check and
verify BOM with customer
1st
day
Rack Stacking Mount hardware on rack and network
cabling
2nd
day
Update Firmware Update hardware firmware 3rd
day If
Required
Installation Installation Rocks cluster manager and
CentOS in master node and compute
nodes
Installation Torque resource manager
Installation of InfiniBand driver and
IB aware MPI
Installation of open source Compiler
3rd
day
Application
Installation
Installation of user application, run
and test sample program
4th
Day
Benchmarking
submission
Benchmark running and submission
after customer satisfaction
5th
Day
Documentation Prepare and submit documentation One week
time after
installation
Training As Required in the RFP
18	
10. PROJECT MAINTENANCE PLAN
In addition to cutting-edge products and solutions, in Association with Fujitsu and
other OEM, Fujitsu and Micropoint Computers Private Limited company delivers
world-class Maintenance and Support Services: From integrating new technologies
into IT infrastructures to providing fast and uncomplicated maintenance & support
services pro-actively and reactively according to defined SLAs.
Complex HPC solutions often result in multivendor environments which have to be
managed effectively regarding maintenance services. Coordinating between several
hardware and software service providers, is necessary to ensure the smooth running
of a HPC environment.
Some of the key features of Managed Maintenance services are as follows:
Ø Establish clearly defined service responsibilities
Ø Provide a central contact person for maintenance and support
Ø Provide real-time information about service levels and the quality of the service
delivery
Ø Guarantee the availability of the multivendor environment according to the
defined SLA
Ø Enable flexible modification of services to meet changing requirements
Ø Reduce costs and ensures greater economic viability for maintenance work in
multivendor environments
Ø Improve the satisfaction of internal and external customers
Ø Availability of spares specific to installation and locations across the country
Ø Fixing any technical glitches on time to avoid shutdowns
19	
11. BUDGETING AND FINANCIAL ANALYSIS
Ø Product wise cost for every specifications is given below. Bottom-up budget
analysis is done for this project
Ø The initial investment for this project is obtained from company’s funds
Ø The total cost for the project is US$ 1,844,341.8 (without taking into
consideration the optional items)
Ø The major chunk of the project cost is associated with direct cost
Terms of Payment
Ø 50 percent advance before project execution
Ø Balance 40 percent after the delivery of all equipment
Ø 10 percent after satisfactory installation and commissioning
Finances for the project
Ø Micropoint Computers Private Limited company is an established HPC
solution provider, having reputation and experience for last 15 to 20 Years
Ø ‘Micropoint’ has excellent relation and open credit facility from OEM / their
distributors (Original Equipment Manufacturers like DELL, Fujitsu, Mellanox,
Intel, NVIDIA, Ingram, and Avnet)
Ø They have a credit facility for Limited number of period i.e. 45 days to 90
days
Ø The delay in the deliveries or customer payments can allow the credit time to
increase
Ø Only in the extreme cases bank funds and short term finance is required, this
will account for half a million dollars for a period of 3 to 6 months
20	
Product wise Cost:
Sr.
No
Name and Specification of the Item Qty
Unit Price Total Price
1 Master Nodes
1.1 Master Node (in HA Mode) 2
US$
7,612.00
US$
15,224.00
1.2 Login/Compilation nodes
1.2.1 CPU Only 2
US$
7,612.00
US$
15,224.00
1.2.2 GPU Enabled Two Nodes in One Chassis 1
US$
14,258.00
US$
14,258.00
1.2.3
Intel Xeon Phi Enabled - Two Nodes in One
Chassis
1
US$
14,258.00
US$
14,258.00
2 Compute Nodes
2.1 Only CPU(64GB RAM) 126
US$
5,609.00
US$
706,734.32
2.2 With 512GB RAM 4
US$
10,542.00
US$
42,168.00
3
GPU Enabled Compute Nodes - Two Nodes in
One Chassis
8
US$
26,530.00
US$
212,239.96
4
Intel Xeon Phi Enabled Compute Nodes Two
Nodes in One Chassis
8
US$
27,259.00
US$
218,072.00
5 Management node 1
US$
5,810.00
US$ 5,810.00
6 Storage : 1SET 1
US$
221,351.00
US$
221,351.00
21	
7 Software
7.1
Cluster management tool 1SET
Unit Price per node of tool must be quoted to
take in to account any changes in the quantity of
compute nodes.
1
US$
29,500.00
US$
29,500.00
7.2
Intel Parallel Studio XE 2015 cluster edition
with 10 user floating licenses 1SET
1
US$
28,067.75
US$
28,067.75
7.3
Operating System - CENT-OS Open source
Unit Price per node of OS must be quoted to
take in to account any changes in the quantity of
compute nodes.
1 US$ 0.00 US$ 0.00
8 Primary Communication Network
8.1
Single Chassis switch scalable up to 300 ports
with with backplane configured for 100% non-
blocking for all ports without leafs As Per BOM
1
US$
97,076.00
US$
97,076.00
8.2
leaf blade with optical cables, quantity same as
number of ports per leaf blade of appropriate
lengths. As Per BOM
12
US$
13,095.00
US$
157,139.96
9
Secondary Communication Network - As Per
BOM
1
US$
22,607.00
US$
22,607.00
GRAND TOTAL
One million seven hundred ninety-nine thousand seven
hundred thirty
US$
1,799,730.00
10 Installation and commissioning charges LS
Free Of
Cost Free Of Cost
22	
11
Any additional Items required to complete the
solution (provide detailed itemized list) On-Site
Spares as per Requirement
1 Free Of
Cost Free Of Cost
12
Manpower on site for system administration (for
1st year)
2
US$
7435.30 US$ 14870.60
13
Manpower on site for system administration (for
2nd year)
2
US$
7435.30 US$ 14870.60
14
Manpower on site for system administration (for
3rd year)
2
US$
7435.30 US$ 14870.60
Optional Items:
1 AMC for all above mandatory items for 4th year LS
US$
266526.21
US$
266526.21
2 AMC for all above mandatory items for 5th year LS
US$
3165226.21
US$
3165226.21
3
Manpower on site for system administration(for
4th year)
2
US$
7435.30 US$ 14870.60
4
Manpower on site for system administration(for
5th year
2
US$
8950.45
US$
17900.90
23	
12. TASKS AND RESPONSIBILTIES
The project consists of the following three key phases for successful
implementation
1. Project proposal and approval
Ø This is a very critical first phase of the project. It includes preparation of a
detailed requirement document that clearly outlines the need for the HPC
system, the ROI analysis, proposed configuration and approximate budget for
procurement, implementation, training and successful deployment of the HPC
system
Ø This document should clearly specify other costs such as real estate, electric
supply, UPS with backup generators, computer site preparation, manpower
requirements for HPC operations
Ø The proposal has to be sent to the funding agency after the document is
approved by the core committee of the University and the Director. Once the
project funding is approved, the other phases will follow
2. Vendor selection and HPC system installation
Ø This phase consists of sending Request for Proposals to the HPC vendors,
selection of the HPC vendor after a detailed and comprehensive evaluation
process, awarding the contract and supply and installation of the HPC system
and acceptance of the same after running the stipulated tests
3. HPC system deployment
Ø The final phase consists of releasing the HPC resources to the users, monitoring
the usage and maintaining uptime of the system
24	
13. Roles & Responsibilities
Each department and its personnel have a specific role to play which leads to the
successful implementation of the HPC project.
Administration and Finance Department
Ø The administration & finance department is responsible for the commercial and
financial aspects of the project
Ø Its job is to release the final RFP to the vendors, validate the commercial
aspects of the proposal and ensure that this is in line with the Terms and
conditions of the RFP in all respects, coordinate with the technical evaluation
committee to shortlist the qualified vendors, enter in to contract negotiations
and issue the Purchase Contract to the selected vendor
Ø This department is also responsible for releasing payment to the vendor after
they have fulfilled their obligations as per the RFP stipulations
Ø The engineering department is in-charge of setting up and running the plant.
The engineering department handles all technical aspects of the plant
Ø The engineers make sure the plant is set up and runs smoothly and they also
trouble shoot any occasional problems that may arise
Computer Science Department and Computer Centre
Ø They form a part of the technical evaluation committee and play a major role in
forming the technical specifications of the project. They are also responsible for
evaluation and validation of the technical aspects of the bids received from
various vendors
25	
Ø Once the HPC system is delivered and installed, this department will oversee
the various tests performed on the HPC system as per the RFP norms and sign
off the acceptance test report
Domain specialists
Ø The domain specialists come from various user departments and are experts in
various disciplines – Physical sciences, Life Sciences, engineering and others,
who actually make sure that the HPC system configuration is optimized for the
various applications
Ø This group is responsible for defining the performance criteria of the HPC
system and provide benchmark programs to be tested on the system
External Consultant
Ø The external consultant is from a well reputed outside organization which has
already procured and deployed similar HPC system
Ø The consultant provides technical inputs to the University people from the
beginning leading to RFP, selection of vendor leading to the acceptance of the
HPC system
Ø The consultant can only make recommendations to the university but cannot
make the final decision
Electrical engineer and site preparation specialist
Ø These experts are responsible for the power and cooling aspects as well as
defining the space requirements and data center preparation
26	
14. RISK ASSESSMENT
RISK MATRIX
Ø Different risks associated with the project are shown below along with their
likelihood and severity
Ø Critical Risks should be given high priority over other as they can have adverse
effects on the project
Risk NO Risk Associated Likelihood Severity
1 Technical Glitches 5 4
2 Delay in time frame 3 4
3 Scope Creep 2 4
4 Over Budget 2 3
5
Low team
motivation 2 4
6
Conflicts of
opinions 2 2
High 1
Probability Medium 2
Low 6 4 3,5
Low Medium High
Severity
Here:
Ignore the threats Monitor the threats Critical threats
27	
15. SWOT ANALYSIS
STRENGTHS WEAKNESSES OPPORTUNITIES THREATS
Sufficient
capital
available
Exchange of
currency rates
Niche target market Time
constraints
Experience in
the field for 25
years
Time frames,
deadlines and
pressures
New technologies Scope creep
Availability of
excellent
vendors
Expansion of
customer base
Constant
improvement
in technical
support
Strong
technical
support
28	
16. FUTURE SCOPE
Once the installation for the HPC is complete, any modification can be done
effectively.
Ø Material addition can be done with additional cost as per line items price
breakup offered
Ø As per the Demand the processing power can be increased by adding the
compute nodes, increasing memory of existing system for better performance
Ø Similar storage system can be upgraded for additional capacity seamlessly. The
design is scalable for any further expansion in near future of 18 months
(generally after 12 to 18 months the technology changes and the hardware
becomes irrelevant for high performance

More Related Content

What's hot

Project management assignment 1
Project management assignment 1 Project management assignment 1
Project management assignment 1 Weng Chuan
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...IRJET Journal
 
Senior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik AsanSenior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik AsanMohideen Sheik Asan
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryPMI Chennai Chapter
 
Michael E Soukup Resume 6-25-15
Michael E  Soukup Resume 6-25-15Michael E  Soukup Resume 6-25-15
Michael E Soukup Resume 6-25-15Mike E Soukup
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slidesDoreen Yeo
 
Project integration management quiz
Project integration management quizProject integration management quiz
Project integration management quize2e4
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
 
المحاضرة الرابعة والخامسة
المحاضرة الرابعة والخامسةالمحاضرة الرابعة والخامسة
المحاضرة الرابعة والخامسةAhmed Alageed
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET Journal
 
Resume - Premal J Vashi
Resume - Premal J VashiResume - Premal J Vashi
Resume - Premal J VashiPremal vashi
 
A model based method for the design of services in collaborative business env...
A model based method for the design of services in collaborative business env...A model based method for the design of services in collaborative business env...
A model based method for the design of services in collaborative business env...IESS
 

What's hot (20)

Project management assignment 1
Project management assignment 1 Project management assignment 1
Project management assignment 1
 
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
Cost Analysis of Road Construction Project by Earned Value Analysis using Pri...
 
Senior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik AsanSenior Planning Engineer -Mohidee Sheik Asan
Senior Planning Engineer -Mohidee Sheik Asan
 
Pugazhenthi Mathuramuthu CV
Pugazhenthi Mathuramuthu CVPugazhenthi Mathuramuthu CV
Pugazhenthi Mathuramuthu CV
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
113 2 pdri
113 2 pdri113 2 pdri
113 2 pdri
 
Michael E Soukup Resume 6-25-15
Michael E  Soukup Resume 6-25-15Michael E  Soukup Resume 6-25-15
Michael E Soukup Resume 6-25-15
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slides
 
Project integration management quiz
Project integration management quizProject integration management quiz
Project integration management quiz
 
LI, GUANGYA
LI,  GUANGYALI,  GUANGYA
LI, GUANGYA
 
Ch5
Ch5Ch5
Ch5
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
PREMENDRA CV Apr 6
PREMENDRA CV Apr 6PREMENDRA CV Apr 6
PREMENDRA CV Apr 6
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
المحاضرة الرابعة والخامسة
المحاضرة الرابعة والخامسةالمحاضرة الرابعة والخامسة
المحاضرة الرابعة والخامسة
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
Project Management (Soft)
Project Management (Soft)Project Management (Soft)
Project Management (Soft)
 
Resume - Premal J Vashi
Resume - Premal J VashiResume - Premal J Vashi
Resume - Premal J Vashi
 
A model based method for the design of services in collaborative business env...
A model based method for the design of services in collaborative business env...A model based method for the design of services in collaborative business env...
A model based method for the design of services in collaborative business env...
 

Similar to Implementation of a high performace clusther for a university

MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...Aravind NC
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...IRJET Journal
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2Narayan Mane
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&tNishant Pandey
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1ghulam MUSTAFA
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
Team 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxTeam 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxmattinsonjanel
 
Resource planning for QC labs, R&D, RA, or multi- project environments
Resource planning for QC labs, R&D, RA, or multi- project environmentsResource planning for QC labs, R&D, RA, or multi- project environments
Resource planning for QC labs, R&D, RA, or multi- project environmentsGeert Vanhove
 
Assignment 1 ITECH 2250 IT Project Management Techniques.docx
Assignment 1 ITECH 2250 IT Project Management Techniques.docxAssignment 1 ITECH 2250 IT Project Management Techniques.docx
Assignment 1 ITECH 2250 IT Project Management Techniques.docxsherni1
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using PertVishnu RC Vijayan
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptpisal3
 

Similar to Implementation of a high performace clusther for a university (20)

MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...MC0084 – Software Project Management & Quality Assurance - Master of Computer...
MC0084 – Software Project Management & Quality Assurance - Master of Computer...
 
TC-CV-2015
TC-CV-2015TC-CV-2015
TC-CV-2015
 
Krishnan Ramu PM
Krishnan Ramu PM Krishnan Ramu PM
Krishnan Ramu PM
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
 
1.2 project management by bee 2
1.2 project management by bee 21.2 project management by bee 2
1.2 project management by bee 2
 
mg7.pptx
mg7.pptxmg7.pptx
mg7.pptx
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
Project mangement part 1
Project mangement part 1Project mangement part 1
Project mangement part 1
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
Team 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docxTeam 4, Team PMP”IT Installation of the Adelphi V.docx
Team 4, Team PMP”IT Installation of the Adelphi V.docx
 
Resource planning for QC labs, R&D, RA, or multi- project environments
Resource planning for QC labs, R&D, RA, or multi- project environmentsResource planning for QC labs, R&D, RA, or multi- project environments
Resource planning for QC labs, R&D, RA, or multi- project environments
 
MGT-Ch07.ppt
MGT-Ch07.pptMGT-Ch07.ppt
MGT-Ch07.ppt
 
PAC Fast Track Implementation Program
PAC Fast Track Implementation ProgramPAC Fast Track Implementation Program
PAC Fast Track Implementation Program
 
Assignment 1 ITECH 2250 IT Project Management Techniques.docx
Assignment 1 ITECH 2250 IT Project Management Techniques.docxAssignment 1 ITECH 2250 IT Project Management Techniques.docx
Assignment 1 ITECH 2250 IT Project Management Techniques.docx
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using Pert
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
01.SELLAM PANNEERSELVAM
01.SELLAM PANNEERSELVAM01.SELLAM PANNEERSELVAM
01.SELLAM PANNEERSELVAM
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 

Recently uploaded

Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxSaqib Mansoor Ahmed
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girladitipandeya
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 

Recently uploaded (20)

Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptx
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 

Implementation of a high performace clusther for a university

  • 1. 1 Establishing University’s High Performance Computing (HPC) facility. Student: Sharyu Mahale
  • 2. 2 Table of Content 1. Letter of Transmittal 3 2. Project Objectives and Goals 4 3. Strategic Plan 5 4. Organization Structure 6 5. Choosing The Right Vendor 7 6. Project Design 8 7. Critical Success Factors 9 8. Implementation Plan 10 8.1 IDEF0 11 8.2 WBS 12 8.3 RACI 13 8.4 Gantt Chart 14 8.5 CPM 16 9 Project Execution Plan 17 10 Project Maintenance Plan 18 11 Budgeting and Financial Analysis 19 12 Tasks and Responsibilities 23 13 Roles and Responsibilities 24 14 Risk Assessment 26 14.1 RISK Matrix 15 SWOT Analysis 27 16 Future Scope 28 17 References 29
  • 3. 3 1. LETTER OF TRANSMITTAL Professor Klosterman Subject: Proposal for setting up a High Performance Computing (HPC) facility for the University. The objective of the project is to provide state-of-the-art computing infrastructure, resources and high quality services to the various researchers across different departments in the university by setting up a centralized High Performance computing (HPC) facility. This investment will be required to stay internationally competitive. High Performance Computing is taking very rapid strides and making a telling impact in every conceivable field of science and technology. The very popular Moore’s law states that the number of transistors doubles every two years and hence the computing power doubles every 18-24 months. This law has been holding steady for the last 4 decades resulting in faster and faster computers that increasingly reduce the time to resolve grand challenge problems. The breakthroughs in semiconductor manufacturing and innovative computer architectures using commodity parts, make High Performance Computing very affordable and manageable today. The estimated initial budget for the HPC facility is US$ 2 Million. Periodic upgrade to the Computer System will be required roughly every 3 years to take advantage of the new technologies. Sincerely, Sharyu Mahale
  • 4. 4 2. PROJECT OBJECTIVES AND GOALS Ø The main objective of this project is to set up a centralized HPC facility in the university to cater the computing needs of students and researchers Ø To evaluate, procure and install the HPC system within 2-3 months within the allocated budget of US$ 2M Ø To choose the HPC system that provides seamless scalability for at least 5 years, resulting in investment protection and smooth enhancement of computing capabilities to keep in step with technology advancements Ø To ensure that the computing resources are always made available to the researchers with minimal or no downtime Ø To set up a team of specialists who can monitor the usage of the facility constantly Ø To encourage industry collaboration in areas of national interest and get additional funding by way of project grants Ø Creating a Prestigious Reference site “A case study” for business promotion and brand building to be recognized as a leading ‘HPC’ solution provider Ø Strengthen relationships with various OEMs involved in the project for future support Ø Attracting OEMs who are left out of the current project for future upcoming requirements
  • 5. 5 3. STRATEGIC PLAN Ø Routine communications between the stakeholders and the project manager Ø Adopting collaborative customer centric approach to gain confidence Ø Motivating the team Ø Organize online Webinars on various subjects of new technology and ROAD map sharing Ø Conduct training programs to facilitate customer participation Ø The training and certification for various software tools, compilers, CUDA programming will attract customers
  • 6. 6 4. ORGANIZATION STRUCTURE Ø Projectized Organization structure is used as every employee is assigned a specific task during the entire course of project Ø Project manager is consulted and is accountable for every task Ø PM will communicate with the clients and resolve any grievances Figure 1: Organizational Structure Purchasing Department Project Manager External Consultant Engineering Department Purchase Manager Systems Administrator Domain Specialist Electrical Department Computer Science Engineer Site Preparation Specialist S Power and Cooling Specialist Finance Manager Sales Representative
  • 7. 7 5. CHOOSING THE RIGHT VENDOR Ø After matching the needs of the University, appropriate vendors(OEMs) providing different solutions are chosen. Following is the vendor list: 1. Fujitsu which includes (This constitutes the biggest component of the overall solution) 2. Fujitsu PRIMERGY Servers 3. Fujitsu ETERNUS Storage 4. Fujitsu HCS Cluster Manager 5. Mellanox Infniband Switches as Primary Interconnect 6. D-Link/Digisol Network Switches as Secondary Interconnect 7. Intel Parallel Studio XE 2015 Ø The design is a fully balanced HPC service that maintains synergy between the fundamental factors affecting the efficiency of a HPC system, namely: compute power, memory throughput and storage I/O subsystem capabilities Ø To meet the requirements, careful architecture is chosen. The latest technological products will ensure processing performance delivery even under very demanding or diverse environments
  • 8. 8 6. PROJECT DESIGN Ø After understanding the requirements of HPC, the following design is proposed Ø The proposed logical diagram recommends a solution that best meets the requirements Figure 2: Logical diagram for 224 nodes cluster
  • 9. 9 7. CRITICAL SUCCESS FACTORS The successful setting up of an operational HPC Facility depends on the following factors: Ø Forming a core group of experts with specialization in the field of computer architecture, software, domain specialists. An external consultant is also preferred to be part of this team Ø Prepare a comprehensive document that clearly spells out the architecture and performance requirements of the proposed HPC system. This requires a great deal of interaction with the key user community and their specific computing needs Ø Shortlist and invite globally reputed computer vendors with proven capabilities for a technical presentation to the University’s core committee members Ø Critical evaluation of bids from selected vendors and choosing a vendor among the technically qualified ones with the best price/performance Ø Ensuring successful implementation of the selected HPC system and running comprehensive tests on the system to ensure that it meets the performance parameters set forward in the RFP Ø Providing the computing resources to various users based on established criteria and ensuring maximum uptime of the system. This has to be achieved by a team of engineers from the supplier providing 24x7 onsite technical support
  • 10. 10 8. IMPLEMENTATION PLAN Ø Once all the HPC required documents are gathered project moves on to its implementation phase Ø Tools like IDEF0, WBS, RACI, Gantt Chart, CPM helps the project to be on time and on budget
  • 11. 11 IDEF0 Ø IDEF0 model is is a function modeling methodology for describing manufacturing functions, which offers a functional modeling language for the analysis, development, reengineering, and integration of information systems; business processes; or software engineering analysis[I] Figure 3: IDEF0 Diagram
  • 12. 12 WBS Ø This tool breaks down the work into subtask which helps in easy monitoring of various tasks Ø A work breakdown structure (WBS), in project management and systems engineering, is a deliverable-oriented decomposition of a project into smaller components[II] Figure 4: Work breakdown structure (WBS) Diagram
  • 13. 13 RACI Ø This tool helps the project manager to keep a track on the authority on the project and helps him to monitor the work Ø Uncertainty in the authority can be avoided by allotting responsibilities to various team members Figure 5: RACI Diagram RACI represents: R –Responsibility, A-Accountable, C-Consulted, I-Informed • Responsibility = person or role responsible for ensuring that the item is completed • Accountable = person or role responsible for actually doing or completing the item • Consulted = person or role whose subject matter expertise is required in order to complete the item • Informed = person or role that needs to be kept informed of the status of item completion
  • 14. 14 Gantt chart Ø Gantt chart illustrates the start and end date of every task in a project Ø Interdependencies associated with the tasks are taken into consideration Ø Tasks which are independent are done simultaneously to reduce the number of days
  • 16. 16 CPM (Critical Path Method) Ø The project can be completed in 66 days Ø The critical path for the project is START-2-5-7-8-9-13-15-17-18-20-END Ø All the activities in the critical path can not be delayed and they need to done on time to avoid any delay in time frame Ø Activities 3, 4, 11, 14, 12 can be sufficiently delayed as they are not part of the critical path Figure 7: Critical Path Diagram
  • 17. 17 9. PROJECT EXECUTION PLAN Content Description Time Remark Open hardware and check BOM Open hard ware boxes, check and verify BOM with customer 1st day Rack Stacking Mount hardware on rack and network cabling 2nd day Update Firmware Update hardware firmware 3rd day If Required Installation Installation Rocks cluster manager and CentOS in master node and compute nodes Installation Torque resource manager Installation of InfiniBand driver and IB aware MPI Installation of open source Compiler 3rd day Application Installation Installation of user application, run and test sample program 4th Day Benchmarking submission Benchmark running and submission after customer satisfaction 5th Day Documentation Prepare and submit documentation One week time after installation Training As Required in the RFP
  • 18. 18 10. PROJECT MAINTENANCE PLAN In addition to cutting-edge products and solutions, in Association with Fujitsu and other OEM, Fujitsu and Micropoint Computers Private Limited company delivers world-class Maintenance and Support Services: From integrating new technologies into IT infrastructures to providing fast and uncomplicated maintenance & support services pro-actively and reactively according to defined SLAs. Complex HPC solutions often result in multivendor environments which have to be managed effectively regarding maintenance services. Coordinating between several hardware and software service providers, is necessary to ensure the smooth running of a HPC environment. Some of the key features of Managed Maintenance services are as follows: Ø Establish clearly defined service responsibilities Ø Provide a central contact person for maintenance and support Ø Provide real-time information about service levels and the quality of the service delivery Ø Guarantee the availability of the multivendor environment according to the defined SLA Ø Enable flexible modification of services to meet changing requirements Ø Reduce costs and ensures greater economic viability for maintenance work in multivendor environments Ø Improve the satisfaction of internal and external customers Ø Availability of spares specific to installation and locations across the country Ø Fixing any technical glitches on time to avoid shutdowns
  • 19. 19 11. BUDGETING AND FINANCIAL ANALYSIS Ø Product wise cost for every specifications is given below. Bottom-up budget analysis is done for this project Ø The initial investment for this project is obtained from company’s funds Ø The total cost for the project is US$ 1,844,341.8 (without taking into consideration the optional items) Ø The major chunk of the project cost is associated with direct cost Terms of Payment Ø 50 percent advance before project execution Ø Balance 40 percent after the delivery of all equipment Ø 10 percent after satisfactory installation and commissioning Finances for the project Ø Micropoint Computers Private Limited company is an established HPC solution provider, having reputation and experience for last 15 to 20 Years Ø ‘Micropoint’ has excellent relation and open credit facility from OEM / their distributors (Original Equipment Manufacturers like DELL, Fujitsu, Mellanox, Intel, NVIDIA, Ingram, and Avnet) Ø They have a credit facility for Limited number of period i.e. 45 days to 90 days Ø The delay in the deliveries or customer payments can allow the credit time to increase Ø Only in the extreme cases bank funds and short term finance is required, this will account for half a million dollars for a period of 3 to 6 months
  • 20. 20 Product wise Cost: Sr. No Name and Specification of the Item Qty Unit Price Total Price 1 Master Nodes 1.1 Master Node (in HA Mode) 2 US$ 7,612.00 US$ 15,224.00 1.2 Login/Compilation nodes 1.2.1 CPU Only 2 US$ 7,612.00 US$ 15,224.00 1.2.2 GPU Enabled Two Nodes in One Chassis 1 US$ 14,258.00 US$ 14,258.00 1.2.3 Intel Xeon Phi Enabled - Two Nodes in One Chassis 1 US$ 14,258.00 US$ 14,258.00 2 Compute Nodes 2.1 Only CPU(64GB RAM) 126 US$ 5,609.00 US$ 706,734.32 2.2 With 512GB RAM 4 US$ 10,542.00 US$ 42,168.00 3 GPU Enabled Compute Nodes - Two Nodes in One Chassis 8 US$ 26,530.00 US$ 212,239.96 4 Intel Xeon Phi Enabled Compute Nodes Two Nodes in One Chassis 8 US$ 27,259.00 US$ 218,072.00 5 Management node 1 US$ 5,810.00 US$ 5,810.00 6 Storage : 1SET 1 US$ 221,351.00 US$ 221,351.00
  • 21. 21 7 Software 7.1 Cluster management tool 1SET Unit Price per node of tool must be quoted to take in to account any changes in the quantity of compute nodes. 1 US$ 29,500.00 US$ 29,500.00 7.2 Intel Parallel Studio XE 2015 cluster edition with 10 user floating licenses 1SET 1 US$ 28,067.75 US$ 28,067.75 7.3 Operating System - CENT-OS Open source Unit Price per node of OS must be quoted to take in to account any changes in the quantity of compute nodes. 1 US$ 0.00 US$ 0.00 8 Primary Communication Network 8.1 Single Chassis switch scalable up to 300 ports with with backplane configured for 100% non- blocking for all ports without leafs As Per BOM 1 US$ 97,076.00 US$ 97,076.00 8.2 leaf blade with optical cables, quantity same as number of ports per leaf blade of appropriate lengths. As Per BOM 12 US$ 13,095.00 US$ 157,139.96 9 Secondary Communication Network - As Per BOM 1 US$ 22,607.00 US$ 22,607.00 GRAND TOTAL One million seven hundred ninety-nine thousand seven hundred thirty US$ 1,799,730.00 10 Installation and commissioning charges LS Free Of Cost Free Of Cost
  • 22. 22 11 Any additional Items required to complete the solution (provide detailed itemized list) On-Site Spares as per Requirement 1 Free Of Cost Free Of Cost 12 Manpower on site for system administration (for 1st year) 2 US$ 7435.30 US$ 14870.60 13 Manpower on site for system administration (for 2nd year) 2 US$ 7435.30 US$ 14870.60 14 Manpower on site for system administration (for 3rd year) 2 US$ 7435.30 US$ 14870.60 Optional Items: 1 AMC for all above mandatory items for 4th year LS US$ 266526.21 US$ 266526.21 2 AMC for all above mandatory items for 5th year LS US$ 3165226.21 US$ 3165226.21 3 Manpower on site for system administration(for 4th year) 2 US$ 7435.30 US$ 14870.60 4 Manpower on site for system administration(for 5th year 2 US$ 8950.45 US$ 17900.90
  • 23. 23 12. TASKS AND RESPONSIBILTIES The project consists of the following three key phases for successful implementation 1. Project proposal and approval Ø This is a very critical first phase of the project. It includes preparation of a detailed requirement document that clearly outlines the need for the HPC system, the ROI analysis, proposed configuration and approximate budget for procurement, implementation, training and successful deployment of the HPC system Ø This document should clearly specify other costs such as real estate, electric supply, UPS with backup generators, computer site preparation, manpower requirements for HPC operations Ø The proposal has to be sent to the funding agency after the document is approved by the core committee of the University and the Director. Once the project funding is approved, the other phases will follow 2. Vendor selection and HPC system installation Ø This phase consists of sending Request for Proposals to the HPC vendors, selection of the HPC vendor after a detailed and comprehensive evaluation process, awarding the contract and supply and installation of the HPC system and acceptance of the same after running the stipulated tests 3. HPC system deployment Ø The final phase consists of releasing the HPC resources to the users, monitoring the usage and maintaining uptime of the system
  • 24. 24 13. Roles & Responsibilities Each department and its personnel have a specific role to play which leads to the successful implementation of the HPC project. Administration and Finance Department Ø The administration & finance department is responsible for the commercial and financial aspects of the project Ø Its job is to release the final RFP to the vendors, validate the commercial aspects of the proposal and ensure that this is in line with the Terms and conditions of the RFP in all respects, coordinate with the technical evaluation committee to shortlist the qualified vendors, enter in to contract negotiations and issue the Purchase Contract to the selected vendor Ø This department is also responsible for releasing payment to the vendor after they have fulfilled their obligations as per the RFP stipulations Ø The engineering department is in-charge of setting up and running the plant. The engineering department handles all technical aspects of the plant Ø The engineers make sure the plant is set up and runs smoothly and they also trouble shoot any occasional problems that may arise Computer Science Department and Computer Centre Ø They form a part of the technical evaluation committee and play a major role in forming the technical specifications of the project. They are also responsible for evaluation and validation of the technical aspects of the bids received from various vendors
  • 25. 25 Ø Once the HPC system is delivered and installed, this department will oversee the various tests performed on the HPC system as per the RFP norms and sign off the acceptance test report Domain specialists Ø The domain specialists come from various user departments and are experts in various disciplines – Physical sciences, Life Sciences, engineering and others, who actually make sure that the HPC system configuration is optimized for the various applications Ø This group is responsible for defining the performance criteria of the HPC system and provide benchmark programs to be tested on the system External Consultant Ø The external consultant is from a well reputed outside organization which has already procured and deployed similar HPC system Ø The consultant provides technical inputs to the University people from the beginning leading to RFP, selection of vendor leading to the acceptance of the HPC system Ø The consultant can only make recommendations to the university but cannot make the final decision Electrical engineer and site preparation specialist Ø These experts are responsible for the power and cooling aspects as well as defining the space requirements and data center preparation
  • 26. 26 14. RISK ASSESSMENT RISK MATRIX Ø Different risks associated with the project are shown below along with their likelihood and severity Ø Critical Risks should be given high priority over other as they can have adverse effects on the project Risk NO Risk Associated Likelihood Severity 1 Technical Glitches 5 4 2 Delay in time frame 3 4 3 Scope Creep 2 4 4 Over Budget 2 3 5 Low team motivation 2 4 6 Conflicts of opinions 2 2 High 1 Probability Medium 2 Low 6 4 3,5 Low Medium High Severity Here: Ignore the threats Monitor the threats Critical threats
  • 27. 27 15. SWOT ANALYSIS STRENGTHS WEAKNESSES OPPORTUNITIES THREATS Sufficient capital available Exchange of currency rates Niche target market Time constraints Experience in the field for 25 years Time frames, deadlines and pressures New technologies Scope creep Availability of excellent vendors Expansion of customer base Constant improvement in technical support Strong technical support
  • 28. 28 16. FUTURE SCOPE Once the installation for the HPC is complete, any modification can be done effectively. Ø Material addition can be done with additional cost as per line items price breakup offered Ø As per the Demand the processing power can be increased by adding the compute nodes, increasing memory of existing system for better performance Ø Similar storage system can be upgraded for additional capacity seamlessly. The design is scalable for any further expansion in near future of 18 months (generally after 12 to 18 months the technology changes and the hardware becomes irrelevant for high performance