SlideShare a Scribd company logo
Industrial Engineering Letters                                                                  www.iiste.org
ISSN 2224-6096 (Print) ISSN 2225-0581(Online)
Vol 1, No.4, 2011


              Optimization by Heuristic procedure of Scheduling
                        Constraints in Manufacturing System

                           Bharat Chede1*, Dr C.K.Jain2, Dr S.K.Jain3, Aparna Chede4

1.     Reader, Department of Mechanical Engineering, Mahakal Institute of Technology and Management,

     Ujjain

2.     Ex Principal, Ujjain Engineering College, Ujjain

3.     Principal, Ujjain Engineering College, Ujjain

4.     Lecturer, Department of Mechanical Engineering, Mahakal Institute of Technology, Ujjain

*      Email of the corresponding author       : bharat_chede@rediffmail.com Phone 91-9827587234



Abstract
This article provides an insight for optimization the output considering combinations of scheduling
constraints by using simple heuristic for multi-product inventory system. Method so proposed is easy to
implement in real manufacturing situation by using heuristic procedure machines are arranged in optimal
sequence for multiple product to manufacture. This reduces manufacturing lead-time thus enhance profit.


Keywords: Optimization, Scheduling, Heuristic, Inventory, Layouts


1.    Introduction


      Constraints in industry lead to reduction of profit to industry especially some constraints like budgetary
and space when imposed on system. These constraints has impact on cost incurred in that product basically
considering the scheduling as constraints specially in case when we have to adopt in change in product mix,
demand and design.


2.    Traditional approach


      There are many relations for EOQ


                          Q =     √ 2 Ci .Yi       i = 1,2,3 _ _ _n -----------------   (i)
                         Bi
                     For ith product Ci = order cost per unit
              Yi = demand per unit


                                                         11
Industrial Engineering Letters                                                                                 www.iiste.org
ISSN 2224-6096 (Print) ISSN 2225-0581(Online)
Vol 1, No.4, 2011

          Bi = the stock holding cost per unit per unit time
     There are chances when all n products have to be replenished at same time. If restriction of maximum
capital investment (W) at any time in inventory is active, then (A) is valid if Q (i= 1.2. - - - n) satisfy the
constraints
               n
                           ∑ Vi. Qi      ≤     W            ------------------------------                     (ii)
               i =1


Where V is the value of unit of product            i otherwise Q ( i = 1,2, ---- n)


To satisfy (ii) Lagrange multiplier technique is used to obtain modified Q


                       Q    =     √ 2 Ci .Yi                  i = 1,2,3 _ _ _n     -----------------   (iii)
                   Bi + 2µVi


µ - Lagrange multiplier associated with capital investment constraints




But by these also we may not necessarily get optimality.


The proposed simple heuristic rule for staggering of the replenishments of product under equal order
interval method and provide a simple formula for obtaining the upper limit of maximum investment in
inventory we assume that each product is replenished at equal time interval during common order interval T,
i.e. for n product we order at a time interval of T/n and upper limit of maximum investment in inventory
can be obtained by making following arrangement.
     Arranging the item in descending order of demand of each item                    and its unit value (i.e. max [Vi,Yi] is
for i=I) If INV denote the capital investment required at time (j - 1) T/n j = 1,2, --- n then INVj can be
expressed as


                   n
         INVj          =    T/n ∑        rjk. V k . Y k                           j = 1,2----n
                             k=1
                       rjk = n+k-j        if k ≤ j
                       =    k-j          if k ≥ j


         MLUL = max (INVj) gives upper limit of maximum investment in cycle duration j.


To have exact utilization of invested budget the estimated value of T should be obtained from W = MLUL
Comparison of optimal result by both methods. It is clear that heuristic rule provide better cost performance

                                                               12
Industrial Engineering Letters                                                                 www.iiste.org
ISSN 2224-6096 (Print) ISSN 2225-0581(Online)
Vol 1, No.4, 2011

than Lagrange multiplier method.(Table1)


3.    Numerical example


      Considered the company nearby Indore (India) (Table2) for the Demand rate, order cost, stock holding
cost, Value and EOQ.
Maximum allowable investment W = Rs 15000/- If EOQ used ignoring budgetary constraint, the maximum
investment in inventory would be 17,120/- which is greater than W. To find optimal solution by Lagrange
multiplier technique which when applied gives(Table 3)
Q L1 =      88,   Q L2 =    139,   Q L3 =   98      Total cost =   Rs 3541   when   µ = 0.03
From the result it ensures that heuristic rule performs well. Also the proposed rule in easy to implement in
practice.


3.1    In case of Scheduling as constraints we can classify the Layout as


      •     Liner (single and double row machine layout) (Figure 1)
      •     Loop Layout (Figure 2)
      •     Ladder layout (reduces travel distance)(Figure 3)
      •     The Carousel Layout (Part flow in one direction around loop The Load and unload stations are
            placed at one end of loop)(Figure 4)
      •     The Open Field Layout (Consist of Ladder and Loop)(Figure 5)


Scheduling is considered as Static Scheduling where a fixed set of orders are to be scheduled either using
optimization or priority heuristics also as dynamic scheduling problem where orders arrives periodically.


 Process of Solution for problem
Pi be a partial schedule containing i schedule operations.
Si The set of Schedulable operation at stage i corresponding to given Pi
Pj    The earliest time at which operation j and s could be started.
Q     Earliest time at which operation J, sj could be completed.




4.        Priority Rule Used


      •     SPT (Select operation with minimum processing time)
      •     MWKR (Most work remaining)

                                                       13
Industrial Engineering Letters                                                                       www.iiste.org
ISSN 2224-6096 (Print) ISSN 2225-0581(Online)
Vol 1, No.4, 2011

     •     Random (Select operation at random)


4.1 Algorithm


Step 1 :          Let t=0 assume Pt = {Ǿ}
Step 2 :          Determine q* = min {q}and corresponding machine m* on which q* could be             realized.
Step 3 :       For operation which belongs to S that requires machine m* and satisfy the condition p < q*
               identify an operation according to specified priority add this operation to pi for next stage.
Step 4 :          For each new partial schedule    p t+1 created in step 3 update the data set as follows
                  i)       Remove operation j from Si.
                  ii)      From St+1 by adding the direct successor of operation j from si.
                  iii)     Increment by 1
Step 5     :     Repeat step 2 to step 4 for each      p t+1 created in steps and continue in this manner until all
               active schedules       are generated.
Step 6 :       From To chart is developed from routing data the chart indicated number of parts moves between
               the machines.
Step 7 :        Adjust flow matrix is calculated from frequency matrix, distance matrix and cost matrix.
Step 8 :          From to Sums are determined from the adjusted flow matrix.
Step 9     :     Assign the a machine to it on minimum from sums. The machine having the smallest sum is
               selected. If the minimum value is to sum, then the machine placed at the beginning of sequence.
               If the minimum value is from sum, then machine placed at end of sequence.


5.       Example


           Arrangements of machine are considered for Liner layout, loop layout and ladder layout. The input
data required in inter slot distance load unload distances and unit transportation cost, processing times for
different jobs, processing sequence of jobs on different machines.(Table 4)(Table 5)


     •     Inters lot distance and load, unload matrices for Liner layout (Table 6,7)
     •     Inter slot distance and load, unload matrix for Loop Layout(Table 8,9)
     •     Inter slot Distance and Load, Unload Matrices for Ladder Layout (Table 10,11)


6.   Results
     •     Waiting time of machine (Table 12)
     •     Waiting time for Job (Table 13) Production time for a batch of component = 2600 hrs
     •     Sequence of job manufactured on different machine for minimum production time.(table 14)
     •     Machine order and total cost for different types of layouts (Table 15)


7.   Conclusion



                                                           14
Industrial Engineering Letters                                                                 www.iiste.org
ISSN 2224-6096 (Print) ISSN 2225-0581(Online)
Vol 1, No.4, 2011

    The traditional method for determining optimal order quantities and the optimal reorder points in
multi-product inventory system with constraints are not easy to implement in reality but heuristic rule is not
only easy to implement but also give better result than traditional method. By using heuristic procedure
with scheduling as constraint layout is optimized. The other parameters such as flow time, job sequence to
manufactured, Machine sequence, total transportation cost, Machine and job waiting time are determined.




References


         Brown G.G, Dell R.F, Davis R.L and Dutt R.H (2002) “Optimizing plant line schedules and an
         application at Hidden valley Manufacturing Company”, INTERFACES INFORMS Volume 32
         No.-3,   pp 1-14.


         Oke S.A.,Charles E. and Owaba O.E.(2007) “A fuzzy linguistic approach of preventive
         maintenance scheduling cost optimization”, Kathmandu University Journal of science and
         Engineering and Technology Volume 1 No.3 January pp 1-13


         Osman K, Nagi R. Christopher R.M. (2001 “New Lot sizing formulation for less nervous
         production schedules”, Computers and Operation Research 27, pp 1325-1345.


         Pegels C.C and Watrous C. (2005) “Application of theory of constraints to bottleneck operation in
         manufacturing plant”, Journal of Manufacturing Technology Management. Vol 16 No-03, pp
         302-311.


         Solimanpar.M,Vrat .P and Shankar R,(2004) “ A heuristic          to minimize     make span of cell
         scheduling problem”,    International journal of Production Economics 88,pp 231-241.




First Author. Bharat Chede has received Bachelor’s degree from Amravati University, India and Masters
Degree in Mechanical Engineering (Production Engineering) from Shivaji University, India, He is currently
pursuing PhD from Rajiv Gandhi Proudyogiki Vishwavidyalaya Bhopal, India. He is working as Head of
Department (Mechanical Engineering) at Mahakal Institute of Technology and Management Ujjain India.
His Current area of research is Optimization in manufacturing techniques using fuzzy logics.

                                                     15
Industrial Engineering Letters                                                                 www.iiste.org
ISSN 2224-6096 (Print) ISSN 2225-0581(Online)
Vol 1, No.4, 2011


Second Author. Dr C.K.Jain            Phd in Production Engineering from IIT Rourkee. A renowned
academician, was responsible for making trendsetting transformations during his last stint as Principal,
UEC. Having received a Gold Medal in M.Tech and an award winning research scholar during his PhD. His
Current area of research is Casting methods optimization.


Third Author. Dr S.K.Jain. Phd from APS university Rewa India. He is principal Ujjain Engineering
College Ujjain, India . His current areas of research are Fuzzy logic Technique in Engineering


Fourth Author. Aparna Chede has received Bachelors and Masters Degree in Mechanical Engineering
from Rajiv Gandhi Proudyogiki Vishwavidyalaya Bhopal, India. She is currently working as Lecturer in
Mechanical Engineering at      Mahakal Institute of Technology and Science Ujjain India. Her current areas
of research are Industrial Engineering techniques.



    Method           of         T              Q1                 Q2            Q3            Total Cost
    solution
    Langrange                   ---            145                44           114            Rs 4063
    Multiplier
    Heuristic                 0.108            216                54           108            Rs 3919


                          Table No 1: (Comparison of optimal result by both methods)


         Product(i)                                         1             2              3
         Demand rate (units per year) Y                    2000         1000           1000
         Order cost C (Rs per unit per year)                50            50             50
         Stock holding cost B (Rs Per unit per              16            10             4
         year)
         Value V (Rs per unit)                              80           150             20
         EOQ                                                112          100           158


          Table 2:    (Demand rate, order cost, stock holding cost, value and EOQ.)



            Method of solution           T       Q1          Q2         Q3     Total Cost
            Langrange Multiplier        ---      98          88        139     Rs 3541
            Heuristic                  0.079    158          79         79     Rs 3716




                                                      16
Industrial Engineering Letters                                                                                       www.iiste.org
ISSN 2224-6096 (Print) ISSN 2225-0581(Online)
Vol 1, No.4, 2011

                      Table 3: (Optimal solution by Lagrange multiplier technique)




        Job number        J1            J2              J3            J4                      J5                J6
        Batch size        50            40              60            30                      30                70


                                             Table 4: (Job and Batch Size)


Job   First               Second               Third              Fourth                       Fifth                 Sixth
      Operation           Operation            Operation          Operation                    Operation             Operation
      M/C      Time       M/C       Time       M/C     Time       M/C              Time        M/C     Time          M/C     Time
A     M1       8          M2        7          M3      14         M4               9           M4      3             M4      4
B     M2       10         M3        17         M3      6          M5               13          M4      4             M1      3
C     M4       18         M3        16         M4      11         M1               12          M5      3             M2      2
D     M4       16         M1        7          M2      11         M3               4           M5      4             M4      13
E     M2       12         M2        15         M4      9          M1               11          M4      3             M1      4
F     M4       8          M5        7          M4      9          M1               6           M2      11            M2      12


                            Table 5: (Machines with Operation time)


                           Slots        S1      S2      S3        S4           S5         S6
                           S1           0       4       6         8            10         12
                           S2           4       0       4         6            8          10
                           S3           6       4       0         4            6          8
                           S4           8       6       4         0            4          6
                           S5           10      8       6         4            0          4
                           S6           12      10      8         6            4          0


                                   Table 6: (Inter slot distance for Liner Layout)

           Slots                        S1     S2            S3            S4                 S5            S6
           Load Station                 3      5             7             9                  11            13

           Unload Station               13     11            9             7                  5             3




                                                            17
Industrial Engineering Letters                                                                         www.iiste.org
ISSN 2224-6096 (Print) ISSN 2225-0581(Online)
Vol 1, No.4, 2011


                                  Table 7: (Load Unload Matrices for Liner layout)


                        Slots      S1       S2       S3       S4           S5            S6
                        S1         0        4        6        8            10            12
                        S2         4        0        4        6            8             10
                        S3         6        4        0        4            6             8
                        S4         8        6        4        0            4             6
                        S5         10       8        6        4            0             4
                        S6         12       10       8        6            4             0


                                Table 8: (Inter slot distance for Loop Layout)




                Slots               S1      S2           S3           S4            S5            S6
                Load Station        4       6            8            10            12            14
                Unload              14      12           10           8             6             4
                Station


                             Table 9: (Load Unload Matrices for Loop layout)



                          Slots        S1       S2       S3       S4           S5            S6
                          S1           0        6        8        10           12            14
                          S2           6        0        6        8            10            12
                          S3           8        6        0        6            8             10
                          S4           10       8        6        0            6             8
                          S5           12       10       8        6            0             6
                          S6           14       12       10       8            6             0




                                                         18
Industrial Engineering Letters                                                                                   www.iiste.org
ISSN 2224-6096 (Print) ISSN 2225-0581(Online)
Vol 1, No.4, 2011

                                Table 10: (Inter Slot distance for Ladder Layout)
             Slots                   S1          S2             S3              S4                S5             S6
             Load Station            1           5              7               9                 11             13
             Unload Station          13          11             9               7                 5              1



                               Table 11: (Load unload Matrices for Ladder Layout)



             Machine                        M1             M2          M3                M4            M5            M6
             No                             4              6           6                 8             8             6
             Waiting time in minutes        6              8           6                 8             6             4


                                          Table 12: (Waiting Time of machine)



             Job No                  J1          J2             J3                  J4            J5        J6
             Waiting    time    in   3210        3340           1740                3810          3840      1750
             minutes


                            Table 13: (Waiting time for job)


        M/C No                                             Job Sequence
        M1             J1            J6               J4             J3                      J5             J2
        M2             J2            J1               J4             J5                      J1             J3
        M3             J3            J2               J5             J1                      J4             J4
        M4             J3            J6               J4             J5                      J1             J2
        M5             J6            J2               J4             J1                      J3             J5
        M6             J6            J1               J2             J1                      J5             J1


                            Table 14: (Job Sequence for minimum production time)


Type of Layout         Machine arrangement Sequence                                          Total
                                                                                             Transportation
                                                                                             Cost
Liner                 M4       M6        M1      M5        M2              M1                3370
Loop                  M4       M6        M1      M5        M2              M1                3382
Ladder                M4       M1        M5      M6        M2              M1                6324
Open Field            M4       M1        M5      M6        M1              M1                4212


                                                           19
Industrial Engineering Letters                                                                     www.iiste.org
ISSN 2224-6096 (Print) ISSN 2225-0581(Online)
Vol 1, No.4, 2011


                           Table 15: (Machine order and cost for different layout)



Load           2                       2                            2                    2             Unload 2
2
l                                               1                               1                             1
1                  1 S1               S21           S3         S4         S5                 S6




                           Figure 1 Liner (single and double row machine layout)




                               S1                             S2


               1                 1                        2                 1


Load       1                                                                                  S3
2    1

Load                                                                                          S4
                       2
                   1                                                                 1


                               S6                                   S5




                                                     20
International Journals Call for Paper
The IISTE, a U.S. publisher, is currently hosting the academic journals listed below. The peer review process of the following journals
usually takes LESS THAN 14 business days and IISTE usually publishes a qualified article within 30 days. Authors should
send their full paper to the following email address. More information can be found in the IISTE website : www.iiste.org

Business, Economics, Finance and Management               PAPER SUBMISSION EMAIL
European Journal of Business and Management               EJBM@iiste.org
Research Journal of Finance and Accounting                RJFA@iiste.org
Journal of Economics and Sustainable Development          JESD@iiste.org
Information and Knowledge Management                      IKM@iiste.org
Developing Country Studies                                DCS@iiste.org
Industrial Engineering Letters                            IEL@iiste.org


Physical Sciences, Mathematics and Chemistry              PAPER SUBMISSION EMAIL
Journal of Natural Sciences Research                      JNSR@iiste.org
Chemistry and Materials Research                          CMR@iiste.org
Mathematical Theory and Modeling                          MTM@iiste.org
Advances in Physics Theories and Applications             APTA@iiste.org
Chemical and Process Engineering Research                 CPER@iiste.org


Engineering, Technology and Systems                       PAPER SUBMISSION EMAIL
Computer Engineering and Intelligent Systems              CEIS@iiste.org
Innovative Systems Design and Engineering                 ISDE@iiste.org
Journal of Energy Technologies and Policy                 JETP@iiste.org
Information and Knowledge Management                      IKM@iiste.org
Control Theory and Informatics                            CTI@iiste.org
Journal of Information Engineering and Applications       JIEA@iiste.org
Industrial Engineering Letters                            IEL@iiste.org
Network and Complex Systems                               NCS@iiste.org


Environment, Civil, Materials Sciences                    PAPER SUBMISSION EMAIL
Journal of Environment and Earth Science                  JEES@iiste.org
Civil and Environmental Research                          CER@iiste.org
Journal of Natural Sciences Research                      JNSR@iiste.org
Civil and Environmental Research                          CER@iiste.org


Life Science, Food and Medical Sciences                   PAPER SUBMISSION EMAIL
Journal of Natural Sciences Research                      JNSR@iiste.org
Journal of Biology, Agriculture and Healthcare            JBAH@iiste.org
Food Science and Quality Management                       FSQM@iiste.org
Chemistry and Materials Research                          CMR@iiste.org


Education, and other Social Sciences                      PAPER SUBMISSION EMAIL
Journal of Education and Practice                         JEP@iiste.org
Journal of Law, Policy and Globalization                  JLPG@iiste.org                       Global knowledge sharing:
New Media and Mass Communication                          NMMC@iiste.org                       EBSCO, Index Copernicus, Ulrich's
Journal of Energy Technologies and Policy                 JETP@iiste.org                       Periodicals Directory, JournalTOCS, PKP
Historical Research Letter                                HRL@iiste.org                        Open Archives Harvester, Bielefeld
                                                                                               Academic Search Engine, Elektronische
Public Policy and Administration Research                 PPAR@iiste.org                       Zeitschriftenbibliothek EZB, Open J-Gate,
International Affairs and Global Strategy                 IAGS@iiste.org                       OCLC WorldCat, Universe Digtial Library ,
Research on Humanities and Social Sciences                RHSS@iiste.org                       NewJour, Google Scholar.

Developing Country Studies                                DCS@iiste.org                        IISTE is member of CrossRef. All journals
Arts and Design Studies                                   ADS@iiste.org                        have high IC Impact Factor Values (ICV).

More Related Content

What's hot

Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...Alexander Decker
 
Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Alexander Decker
 
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi MachineOptimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
IJAPEJOURNAL
 
Unit 3
Unit 3Unit 3
11.bicriteria in constrained n x 0003www.iiste.org call for paper flow shop t...
11.bicriteria in constrained n x 0003www.iiste.org call for paper flow shop t...11.bicriteria in constrained n x 0003www.iiste.org call for paper flow shop t...
11.bicriteria in constrained n x 0003www.iiste.org call for paper flow shop t...
Alexander Decker
 
Bicriteria in constrained n x 3 flow shop to minimize the rental cost, setup ...
Bicriteria in constrained n x 3 flow shop to minimize the rental cost, setup ...Bicriteria in constrained n x 3 flow shop to minimize the rental cost, setup ...
Bicriteria in constrained n x 3 flow shop to minimize the rental cost, setup ...Alexander Decker
 
Branch and bound technique for three stage flow shop scheduling problem inclu...
Branch and bound technique for three stage flow shop scheduling problem inclu...Branch and bound technique for three stage flow shop scheduling problem inclu...
Branch and bound technique for three stage flow shop scheduling problem inclu...Alexander Decker
 
11.branch and bound technique for three stage flow shop scheduling problem in...
11.branch and bound technique for three stage flow shop scheduling problem in...11.branch and bound technique for three stage flow shop scheduling problem in...
11.branch and bound technique for three stage flow shop scheduling problem in...
Alexander Decker
 
Jonson"s Rule Production scheduling
 Jonson"s Rule Production scheduling Jonson"s Rule Production scheduling
Jonson"s Rule Production scheduling
mrinalmanik64
 
Flow shop scheduling problem, processing time associated with probabilities i...
Flow shop scheduling problem, processing time associated with probabilities i...Flow shop scheduling problem, processing time associated with probabilities i...
Flow shop scheduling problem, processing time associated with probabilities i...
Alexander Decker
 
Bicriteria in n x 2 flow shop scheduling problem under specified rental polic...
Bicriteria in n x 2 flow shop scheduling problem under specified rental polic...Bicriteria in n x 2 flow shop scheduling problem under specified rental polic...
Bicriteria in n x 2 flow shop scheduling problem under specified rental polic...Alexander Decker
 
11.bicriteria in n x 0002www.iiste.org call for paper flow shop scheduling pr...
11.bicriteria in n x 0002www.iiste.org call for paper flow shop scheduling pr...11.bicriteria in n x 0002www.iiste.org call for paper flow shop scheduling pr...
11.bicriteria in n x 0002www.iiste.org call for paper flow shop scheduling pr...
Alexander Decker
 
Modified sub-gradient based combined objective technique and evolutionary pro...
Modified sub-gradient based combined objective technique and evolutionary pro...Modified sub-gradient based combined objective technique and evolutionary pro...
Modified sub-gradient based combined objective technique and evolutionary pro...
IJECEIAES
 
Co36544546
Co36544546Co36544546
Co36544546
IJERA Editor
 
Novel Heuristics for no-Wait Two Stage Multiprocessor Flow Shop with Probable...
Novel Heuristics for no-Wait Two Stage Multiprocessor Flow Shop with Probable...Novel Heuristics for no-Wait Two Stage Multiprocessor Flow Shop with Probable...
Novel Heuristics for no-Wait Two Stage Multiprocessor Flow Shop with Probable...
IRJET Journal
 
Dynamic Economic Dispatch Assessment Using Particle Swarm Optimization Technique
Dynamic Economic Dispatch Assessment Using Particle Swarm Optimization TechniqueDynamic Economic Dispatch Assessment Using Particle Swarm Optimization Technique
Dynamic Economic Dispatch Assessment Using Particle Swarm Optimization Technique
journalBEEI
 
11.minimizing rental cost under specified rental policy in two stage flowshop...
11.minimizing rental cost under specified rental policy in two stage flowshop...11.minimizing rental cost under specified rental policy in two stage flowshop...
11.minimizing rental cost under specified rental policy in two stage flowshop...Alexander Decker
 
Minimizing rental cost under specified rental policy in two stage flowshop se...
Minimizing rental cost under specified rental policy in two stage flowshop se...Minimizing rental cost under specified rental policy in two stage flowshop se...
Minimizing rental cost under specified rental policy in two stage flowshop se...Alexander Decker
 
Layout Case Study
Layout Case StudyLayout Case Study
Layout Case StudyNilam Kabra
 
Minimizing rental cost for n jobs, 2-machines flow shop scheduling, processin...
Minimizing rental cost for n jobs, 2-machines flow shop scheduling, processin...Minimizing rental cost for n jobs, 2-machines flow shop scheduling, processin...
Minimizing rental cost for n jobs, 2-machines flow shop scheduling, processin...Alexander Decker
 

What's hot (20)

Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...
 
Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...Heuristic approach for bicriteria in constrained three stage flow shop schedu...
Heuristic approach for bicriteria in constrained three stage flow shop schedu...
 
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi MachineOptimization of Economic Load Dispatch with Unit Commitment on Multi Machine
Optimization of Economic Load Dispatch with Unit Commitment on Multi Machine
 
Unit 3
Unit 3Unit 3
Unit 3
 
11.bicriteria in constrained n x 0003www.iiste.org call for paper flow shop t...
11.bicriteria in constrained n x 0003www.iiste.org call for paper flow shop t...11.bicriteria in constrained n x 0003www.iiste.org call for paper flow shop t...
11.bicriteria in constrained n x 0003www.iiste.org call for paper flow shop t...
 
Bicriteria in constrained n x 3 flow shop to minimize the rental cost, setup ...
Bicriteria in constrained n x 3 flow shop to minimize the rental cost, setup ...Bicriteria in constrained n x 3 flow shop to minimize the rental cost, setup ...
Bicriteria in constrained n x 3 flow shop to minimize the rental cost, setup ...
 
Branch and bound technique for three stage flow shop scheduling problem inclu...
Branch and bound technique for three stage flow shop scheduling problem inclu...Branch and bound technique for three stage flow shop scheduling problem inclu...
Branch and bound technique for three stage flow shop scheduling problem inclu...
 
11.branch and bound technique for three stage flow shop scheduling problem in...
11.branch and bound technique for three stage flow shop scheduling problem in...11.branch and bound technique for three stage flow shop scheduling problem in...
11.branch and bound technique for three stage flow shop scheduling problem in...
 
Jonson"s Rule Production scheduling
 Jonson"s Rule Production scheduling Jonson"s Rule Production scheduling
Jonson"s Rule Production scheduling
 
Flow shop scheduling problem, processing time associated with probabilities i...
Flow shop scheduling problem, processing time associated with probabilities i...Flow shop scheduling problem, processing time associated with probabilities i...
Flow shop scheduling problem, processing time associated with probabilities i...
 
Bicriteria in n x 2 flow shop scheduling problem under specified rental polic...
Bicriteria in n x 2 flow shop scheduling problem under specified rental polic...Bicriteria in n x 2 flow shop scheduling problem under specified rental polic...
Bicriteria in n x 2 flow shop scheduling problem under specified rental polic...
 
11.bicriteria in n x 0002www.iiste.org call for paper flow shop scheduling pr...
11.bicriteria in n x 0002www.iiste.org call for paper flow shop scheduling pr...11.bicriteria in n x 0002www.iiste.org call for paper flow shop scheduling pr...
11.bicriteria in n x 0002www.iiste.org call for paper flow shop scheduling pr...
 
Modified sub-gradient based combined objective technique and evolutionary pro...
Modified sub-gradient based combined objective technique and evolutionary pro...Modified sub-gradient based combined objective technique and evolutionary pro...
Modified sub-gradient based combined objective technique and evolutionary pro...
 
Co36544546
Co36544546Co36544546
Co36544546
 
Novel Heuristics for no-Wait Two Stage Multiprocessor Flow Shop with Probable...
Novel Heuristics for no-Wait Two Stage Multiprocessor Flow Shop with Probable...Novel Heuristics for no-Wait Two Stage Multiprocessor Flow Shop with Probable...
Novel Heuristics for no-Wait Two Stage Multiprocessor Flow Shop with Probable...
 
Dynamic Economic Dispatch Assessment Using Particle Swarm Optimization Technique
Dynamic Economic Dispatch Assessment Using Particle Swarm Optimization TechniqueDynamic Economic Dispatch Assessment Using Particle Swarm Optimization Technique
Dynamic Economic Dispatch Assessment Using Particle Swarm Optimization Technique
 
11.minimizing rental cost under specified rental policy in two stage flowshop...
11.minimizing rental cost under specified rental policy in two stage flowshop...11.minimizing rental cost under specified rental policy in two stage flowshop...
11.minimizing rental cost under specified rental policy in two stage flowshop...
 
Minimizing rental cost under specified rental policy in two stage flowshop se...
Minimizing rental cost under specified rental policy in two stage flowshop se...Minimizing rental cost under specified rental policy in two stage flowshop se...
Minimizing rental cost under specified rental policy in two stage flowshop se...
 
Layout Case Study
Layout Case StudyLayout Case Study
Layout Case Study
 
Minimizing rental cost for n jobs, 2-machines flow shop scheduling, processin...
Minimizing rental cost for n jobs, 2-machines flow shop scheduling, processin...Minimizing rental cost for n jobs, 2-machines flow shop scheduling, processin...
Minimizing rental cost for n jobs, 2-machines flow shop scheduling, processin...
 

Similar to 11.optimization by heuristic procedure of scheduling constraints in manufacturing system

Procurement Strategy for Manufacturing and JIT
Procurement Strategy for Manufacturing and JITProcurement Strategy for Manufacturing and JIT
Procurement Strategy for Manufacturing and JIT
IJERD Editor
 
Balancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case studyBalancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case study
eSAT Journals
 
Planning of Supply when lead time uncertain: trade-off between holding cost a...
Planning of Supply when lead time uncertain: trade-off between holding cost a...Planning of Supply when lead time uncertain: trade-off between holding cost a...
Planning of Supply when lead time uncertain: trade-off between holding cost a...
ijsrd.com
 
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENTTIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
IRJET Journal
 
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET Journal
 
Sensitivity Analysis of Bread Production at Anifowose Bakery Industry, Offa, ...
Sensitivity Analysis of Bread Production at Anifowose Bakery Industry, Offa, ...Sensitivity Analysis of Bread Production at Anifowose Bakery Industry, Offa, ...
Sensitivity Analysis of Bread Production at Anifowose Bakery Industry, Offa, ...
IRJET Journal
 
Job Shop Layout Design Using Group Technology
Job Shop Layout Design Using Group TechnologyJob Shop Layout Design Using Group Technology
Job Shop Layout Design Using Group Technology
IJMER
 
Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...
IJERA Editor
 
The optimal solution for unit commitment problem using binary hybrid grey wol...
The optimal solution for unit commitment problem using binary hybrid grey wol...The optimal solution for unit commitment problem using binary hybrid grey wol...
The optimal solution for unit commitment problem using binary hybrid grey wol...
IJECEIAES
 
30420140503003
3042014050300330420140503003
30420140503003
IAEME Publication
 
IRJET-Comparative Analysis of Unit Commitment Problem of Electric Power Syste...
IRJET-Comparative Analysis of Unit Commitment Problem of Electric Power Syste...IRJET-Comparative Analysis of Unit Commitment Problem of Electric Power Syste...
IRJET-Comparative Analysis of Unit Commitment Problem of Electric Power Syste...
IRJET Journal
 
Application of dynamic programming model to production planning, in an animal...
Application of dynamic programming model to production planning, in an animal...Application of dynamic programming model to production planning, in an animal...
Application of dynamic programming model to production planning, in an animal...
Alexander Decker
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
pikuoec
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
pikuoec
 
[231005] - 02. Basic EOQ & EPQ.docx
[231005] - 02. Basic EOQ & EPQ.docx[231005] - 02. Basic EOQ & EPQ.docx
[231005] - 02. Basic EOQ & EPQ.docx
Yunitasari619729
 
Design of PID Controller with Inadequate Determination Dependent on Different...
Design of PID Controller with Inadequate Determination Dependent on Different...Design of PID Controller with Inadequate Determination Dependent on Different...
Design of PID Controller with Inadequate Determination Dependent on Different...
ijtsrd
 
30420140503003
3042014050300330420140503003
30420140503003
IAEME Publication
 
Economic dipatch
Economic dipatch Economic dipatch
Economic dipatch
Doni Wahyudi
 

Similar to 11.optimization by heuristic procedure of scheduling constraints in manufacturing system (20)

Procurement Strategy for Manufacturing and JIT
Procurement Strategy for Manufacturing and JITProcurement Strategy for Manufacturing and JIT
Procurement Strategy for Manufacturing and JIT
 
Balancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case studyBalancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case study
 
Planning of Supply when lead time uncertain: trade-off between holding cost a...
Planning of Supply when lead time uncertain: trade-off between holding cost a...Planning of Supply when lead time uncertain: trade-off between holding cost a...
Planning of Supply when lead time uncertain: trade-off between holding cost a...
 
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENTTIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
TIME STUDY – A KEY TECHNIQUE FOR PRODUCTIVITY IMPROVEMENT
 
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
 
Sensitivity Analysis of Bread Production at Anifowose Bakery Industry, Offa, ...
Sensitivity Analysis of Bread Production at Anifowose Bakery Industry, Offa, ...Sensitivity Analysis of Bread Production at Anifowose Bakery Industry, Offa, ...
Sensitivity Analysis of Bread Production at Anifowose Bakery Industry, Offa, ...
 
Job Shop Layout Design Using Group Technology
Job Shop Layout Design Using Group TechnologyJob Shop Layout Design Using Group Technology
Job Shop Layout Design Using Group Technology
 
vignesh conference
vignesh conferencevignesh conference
vignesh conference
 
Job shop
Job shopJob shop
Job shop
 
Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...
 
The optimal solution for unit commitment problem using binary hybrid grey wol...
The optimal solution for unit commitment problem using binary hybrid grey wol...The optimal solution for unit commitment problem using binary hybrid grey wol...
The optimal solution for unit commitment problem using binary hybrid grey wol...
 
30420140503003
3042014050300330420140503003
30420140503003
 
IRJET-Comparative Analysis of Unit Commitment Problem of Electric Power Syste...
IRJET-Comparative Analysis of Unit Commitment Problem of Electric Power Syste...IRJET-Comparative Analysis of Unit Commitment Problem of Electric Power Syste...
IRJET-Comparative Analysis of Unit Commitment Problem of Electric Power Syste...
 
Application of dynamic programming model to production planning, in an animal...
Application of dynamic programming model to production planning, in an animal...Application of dynamic programming model to production planning, in an animal...
Application of dynamic programming model to production planning, in an animal...
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
 
[231005] - 02. Basic EOQ & EPQ.docx
[231005] - 02. Basic EOQ & EPQ.docx[231005] - 02. Basic EOQ & EPQ.docx
[231005] - 02. Basic EOQ & EPQ.docx
 
Design of PID Controller with Inadequate Determination Dependent on Different...
Design of PID Controller with Inadequate Determination Dependent on Different...Design of PID Controller with Inadequate Determination Dependent on Different...
Design of PID Controller with Inadequate Determination Dependent on Different...
 
30420140503003
3042014050300330420140503003
30420140503003
 
Economic dipatch
Economic dipatch Economic dipatch
Economic dipatch
 

More from Alexander Decker

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Alexander Decker
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale in
Alexander Decker
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesAlexander Decker
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksAlexander Decker
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dAlexander Decker
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceAlexander Decker
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifhamAlexander Decker
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaAlexander Decker
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenAlexander Decker
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksAlexander Decker
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget forAlexander Decker
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabAlexander Decker
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...Alexander Decker
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalAlexander Decker
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesAlexander Decker
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbAlexander Decker
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloudAlexander Decker
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveragedAlexander Decker
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenyaAlexander Decker
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health ofAlexander Decker
 

More from Alexander Decker (20)

Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...Abnormalities of hormones and inflammatory cytokines in women affected with p...
Abnormalities of hormones and inflammatory cytokines in women affected with p...
 
A validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale inA validation of the adverse childhood experiences scale in
A validation of the adverse childhood experiences scale in
 
A usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websitesA usability evaluation framework for b2 c e commerce websites
A usability evaluation framework for b2 c e commerce websites
 
A universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banksA universal model for managing the marketing executives in nigerian banks
A universal model for managing the marketing executives in nigerian banks
 
A unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized dA unique common fixed point theorems in generalized d
A unique common fixed point theorems in generalized d
 
A trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistanceA trends of salmonella and antibiotic resistance
A trends of salmonella and antibiotic resistance
 
A transformational generative approach towards understanding al-istifham
A transformational  generative approach towards understanding al-istifhamA transformational  generative approach towards understanding al-istifham
A transformational generative approach towards understanding al-istifham
 
A time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibiaA time series analysis of the determinants of savings in namibia
A time series analysis of the determinants of savings in namibia
 
A therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school childrenA therapy for physical and mental fitness of school children
A therapy for physical and mental fitness of school children
 
A theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banksA theory of efficiency for managing the marketing executives in nigerian banks
A theory of efficiency for managing the marketing executives in nigerian banks
 
A systematic evaluation of link budget for
A systematic evaluation of link budget forA systematic evaluation of link budget for
A systematic evaluation of link budget for
 
A synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjabA synthetic review of contraceptive supplies in punjab
A synthetic review of contraceptive supplies in punjab
 
A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...A synthesis of taylor’s and fayol’s management approaches for managing market...
A synthesis of taylor’s and fayol’s management approaches for managing market...
 
A survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incrementalA survey paper on sequence pattern mining with incremental
A survey paper on sequence pattern mining with incremental
 
A survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniquesA survey on live virtual machine migrations and its techniques
A survey on live virtual machine migrations and its techniques
 
A survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo dbA survey on data mining and analysis in hadoop and mongo db
A survey on data mining and analysis in hadoop and mongo db
 
A survey on challenges to the media cloud
A survey on challenges to the media cloudA survey on challenges to the media cloud
A survey on challenges to the media cloud
 
A survey of provenance leveraged
A survey of provenance leveragedA survey of provenance leveraged
A survey of provenance leveraged
 
A survey of private equity investments in kenya
A survey of private equity investments in kenyaA survey of private equity investments in kenya
A survey of private equity investments in kenya
 
A study to measures the financial health of
A study to measures the financial health ofA study to measures the financial health of
A study to measures the financial health of
 

Recently uploaded

DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
Paul Groth
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
Elena Simperl
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
Product School
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
Guy Korland
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
DianaGray10
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
James Anderson
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
Product School
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
Product School
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
Frank van Harmelen
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Inflectra
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
Alan Dix
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
Elena Simperl
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Jeffrey Haguewood
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 

Recently uploaded (20)

DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 
Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*Neuro-symbolic is not enough, we need neuro-*semantic*
Neuro-symbolic is not enough, we need neuro-*semantic*
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 

11.optimization by heuristic procedure of scheduling constraints in manufacturing system

  • 1. Industrial Engineering Letters www.iiste.org ISSN 2224-6096 (Print) ISSN 2225-0581(Online) Vol 1, No.4, 2011 Optimization by Heuristic procedure of Scheduling Constraints in Manufacturing System Bharat Chede1*, Dr C.K.Jain2, Dr S.K.Jain3, Aparna Chede4 1. Reader, Department of Mechanical Engineering, Mahakal Institute of Technology and Management, Ujjain 2. Ex Principal, Ujjain Engineering College, Ujjain 3. Principal, Ujjain Engineering College, Ujjain 4. Lecturer, Department of Mechanical Engineering, Mahakal Institute of Technology, Ujjain * Email of the corresponding author : bharat_chede@rediffmail.com Phone 91-9827587234 Abstract This article provides an insight for optimization the output considering combinations of scheduling constraints by using simple heuristic for multi-product inventory system. Method so proposed is easy to implement in real manufacturing situation by using heuristic procedure machines are arranged in optimal sequence for multiple product to manufacture. This reduces manufacturing lead-time thus enhance profit. Keywords: Optimization, Scheduling, Heuristic, Inventory, Layouts 1. Introduction Constraints in industry lead to reduction of profit to industry especially some constraints like budgetary and space when imposed on system. These constraints has impact on cost incurred in that product basically considering the scheduling as constraints specially in case when we have to adopt in change in product mix, demand and design. 2. Traditional approach There are many relations for EOQ Q = √ 2 Ci .Yi i = 1,2,3 _ _ _n ----------------- (i) Bi For ith product Ci = order cost per unit Yi = demand per unit 11
  • 2. Industrial Engineering Letters www.iiste.org ISSN 2224-6096 (Print) ISSN 2225-0581(Online) Vol 1, No.4, 2011 Bi = the stock holding cost per unit per unit time There are chances when all n products have to be replenished at same time. If restriction of maximum capital investment (W) at any time in inventory is active, then (A) is valid if Q (i= 1.2. - - - n) satisfy the constraints n ∑ Vi. Qi ≤ W ------------------------------ (ii) i =1 Where V is the value of unit of product i otherwise Q ( i = 1,2, ---- n) To satisfy (ii) Lagrange multiplier technique is used to obtain modified Q Q = √ 2 Ci .Yi i = 1,2,3 _ _ _n ----------------- (iii) Bi + 2µVi µ - Lagrange multiplier associated with capital investment constraints But by these also we may not necessarily get optimality. The proposed simple heuristic rule for staggering of the replenishments of product under equal order interval method and provide a simple formula for obtaining the upper limit of maximum investment in inventory we assume that each product is replenished at equal time interval during common order interval T, i.e. for n product we order at a time interval of T/n and upper limit of maximum investment in inventory can be obtained by making following arrangement. Arranging the item in descending order of demand of each item and its unit value (i.e. max [Vi,Yi] is for i=I) If INV denote the capital investment required at time (j - 1) T/n j = 1,2, --- n then INVj can be expressed as n INVj = T/n ∑ rjk. V k . Y k j = 1,2----n k=1 rjk = n+k-j if k ≤ j = k-j if k ≥ j MLUL = max (INVj) gives upper limit of maximum investment in cycle duration j. To have exact utilization of invested budget the estimated value of T should be obtained from W = MLUL Comparison of optimal result by both methods. It is clear that heuristic rule provide better cost performance 12
  • 3. Industrial Engineering Letters www.iiste.org ISSN 2224-6096 (Print) ISSN 2225-0581(Online) Vol 1, No.4, 2011 than Lagrange multiplier method.(Table1) 3. Numerical example Considered the company nearby Indore (India) (Table2) for the Demand rate, order cost, stock holding cost, Value and EOQ. Maximum allowable investment W = Rs 15000/- If EOQ used ignoring budgetary constraint, the maximum investment in inventory would be 17,120/- which is greater than W. To find optimal solution by Lagrange multiplier technique which when applied gives(Table 3) Q L1 = 88, Q L2 = 139, Q L3 = 98 Total cost = Rs 3541 when µ = 0.03 From the result it ensures that heuristic rule performs well. Also the proposed rule in easy to implement in practice. 3.1 In case of Scheduling as constraints we can classify the Layout as • Liner (single and double row machine layout) (Figure 1) • Loop Layout (Figure 2) • Ladder layout (reduces travel distance)(Figure 3) • The Carousel Layout (Part flow in one direction around loop The Load and unload stations are placed at one end of loop)(Figure 4) • The Open Field Layout (Consist of Ladder and Loop)(Figure 5) Scheduling is considered as Static Scheduling where a fixed set of orders are to be scheduled either using optimization or priority heuristics also as dynamic scheduling problem where orders arrives periodically. Process of Solution for problem Pi be a partial schedule containing i schedule operations. Si The set of Schedulable operation at stage i corresponding to given Pi Pj The earliest time at which operation j and s could be started. Q Earliest time at which operation J, sj could be completed. 4. Priority Rule Used • SPT (Select operation with minimum processing time) • MWKR (Most work remaining) 13
  • 4. Industrial Engineering Letters www.iiste.org ISSN 2224-6096 (Print) ISSN 2225-0581(Online) Vol 1, No.4, 2011 • Random (Select operation at random) 4.1 Algorithm Step 1 : Let t=0 assume Pt = {Ǿ} Step 2 : Determine q* = min {q}and corresponding machine m* on which q* could be realized. Step 3 : For operation which belongs to S that requires machine m* and satisfy the condition p < q* identify an operation according to specified priority add this operation to pi for next stage. Step 4 : For each new partial schedule p t+1 created in step 3 update the data set as follows i) Remove operation j from Si. ii) From St+1 by adding the direct successor of operation j from si. iii) Increment by 1 Step 5 : Repeat step 2 to step 4 for each p t+1 created in steps and continue in this manner until all active schedules are generated. Step 6 : From To chart is developed from routing data the chart indicated number of parts moves between the machines. Step 7 : Adjust flow matrix is calculated from frequency matrix, distance matrix and cost matrix. Step 8 : From to Sums are determined from the adjusted flow matrix. Step 9 : Assign the a machine to it on minimum from sums. The machine having the smallest sum is selected. If the minimum value is to sum, then the machine placed at the beginning of sequence. If the minimum value is from sum, then machine placed at end of sequence. 5. Example Arrangements of machine are considered for Liner layout, loop layout and ladder layout. The input data required in inter slot distance load unload distances and unit transportation cost, processing times for different jobs, processing sequence of jobs on different machines.(Table 4)(Table 5) • Inters lot distance and load, unload matrices for Liner layout (Table 6,7) • Inter slot distance and load, unload matrix for Loop Layout(Table 8,9) • Inter slot Distance and Load, Unload Matrices for Ladder Layout (Table 10,11) 6. Results • Waiting time of machine (Table 12) • Waiting time for Job (Table 13) Production time for a batch of component = 2600 hrs • Sequence of job manufactured on different machine for minimum production time.(table 14) • Machine order and total cost for different types of layouts (Table 15) 7. Conclusion 14
  • 5. Industrial Engineering Letters www.iiste.org ISSN 2224-6096 (Print) ISSN 2225-0581(Online) Vol 1, No.4, 2011 The traditional method for determining optimal order quantities and the optimal reorder points in multi-product inventory system with constraints are not easy to implement in reality but heuristic rule is not only easy to implement but also give better result than traditional method. By using heuristic procedure with scheduling as constraint layout is optimized. The other parameters such as flow time, job sequence to manufactured, Machine sequence, total transportation cost, Machine and job waiting time are determined. References Brown G.G, Dell R.F, Davis R.L and Dutt R.H (2002) “Optimizing plant line schedules and an application at Hidden valley Manufacturing Company”, INTERFACES INFORMS Volume 32 No.-3, pp 1-14. Oke S.A.,Charles E. and Owaba O.E.(2007) “A fuzzy linguistic approach of preventive maintenance scheduling cost optimization”, Kathmandu University Journal of science and Engineering and Technology Volume 1 No.3 January pp 1-13 Osman K, Nagi R. Christopher R.M. (2001 “New Lot sizing formulation for less nervous production schedules”, Computers and Operation Research 27, pp 1325-1345. Pegels C.C and Watrous C. (2005) “Application of theory of constraints to bottleneck operation in manufacturing plant”, Journal of Manufacturing Technology Management. Vol 16 No-03, pp 302-311. Solimanpar.M,Vrat .P and Shankar R,(2004) “ A heuristic to minimize make span of cell scheduling problem”, International journal of Production Economics 88,pp 231-241. First Author. Bharat Chede has received Bachelor’s degree from Amravati University, India and Masters Degree in Mechanical Engineering (Production Engineering) from Shivaji University, India, He is currently pursuing PhD from Rajiv Gandhi Proudyogiki Vishwavidyalaya Bhopal, India. He is working as Head of Department (Mechanical Engineering) at Mahakal Institute of Technology and Management Ujjain India. His Current area of research is Optimization in manufacturing techniques using fuzzy logics. 15
  • 6. Industrial Engineering Letters www.iiste.org ISSN 2224-6096 (Print) ISSN 2225-0581(Online) Vol 1, No.4, 2011 Second Author. Dr C.K.Jain Phd in Production Engineering from IIT Rourkee. A renowned academician, was responsible for making trendsetting transformations during his last stint as Principal, UEC. Having received a Gold Medal in M.Tech and an award winning research scholar during his PhD. His Current area of research is Casting methods optimization. Third Author. Dr S.K.Jain. Phd from APS university Rewa India. He is principal Ujjain Engineering College Ujjain, India . His current areas of research are Fuzzy logic Technique in Engineering Fourth Author. Aparna Chede has received Bachelors and Masters Degree in Mechanical Engineering from Rajiv Gandhi Proudyogiki Vishwavidyalaya Bhopal, India. She is currently working as Lecturer in Mechanical Engineering at Mahakal Institute of Technology and Science Ujjain India. Her current areas of research are Industrial Engineering techniques. Method of T Q1 Q2 Q3 Total Cost solution Langrange --- 145 44 114 Rs 4063 Multiplier Heuristic 0.108 216 54 108 Rs 3919 Table No 1: (Comparison of optimal result by both methods) Product(i) 1 2 3 Demand rate (units per year) Y 2000 1000 1000 Order cost C (Rs per unit per year) 50 50 50 Stock holding cost B (Rs Per unit per 16 10 4 year) Value V (Rs per unit) 80 150 20 EOQ 112 100 158 Table 2: (Demand rate, order cost, stock holding cost, value and EOQ.) Method of solution T Q1 Q2 Q3 Total Cost Langrange Multiplier --- 98 88 139 Rs 3541 Heuristic 0.079 158 79 79 Rs 3716 16
  • 7. Industrial Engineering Letters www.iiste.org ISSN 2224-6096 (Print) ISSN 2225-0581(Online) Vol 1, No.4, 2011 Table 3: (Optimal solution by Lagrange multiplier technique) Job number J1 J2 J3 J4 J5 J6 Batch size 50 40 60 30 30 70 Table 4: (Job and Batch Size) Job First Second Third Fourth Fifth Sixth Operation Operation Operation Operation Operation Operation M/C Time M/C Time M/C Time M/C Time M/C Time M/C Time A M1 8 M2 7 M3 14 M4 9 M4 3 M4 4 B M2 10 M3 17 M3 6 M5 13 M4 4 M1 3 C M4 18 M3 16 M4 11 M1 12 M5 3 M2 2 D M4 16 M1 7 M2 11 M3 4 M5 4 M4 13 E M2 12 M2 15 M4 9 M1 11 M4 3 M1 4 F M4 8 M5 7 M4 9 M1 6 M2 11 M2 12 Table 5: (Machines with Operation time) Slots S1 S2 S3 S4 S5 S6 S1 0 4 6 8 10 12 S2 4 0 4 6 8 10 S3 6 4 0 4 6 8 S4 8 6 4 0 4 6 S5 10 8 6 4 0 4 S6 12 10 8 6 4 0 Table 6: (Inter slot distance for Liner Layout) Slots S1 S2 S3 S4 S5 S6 Load Station 3 5 7 9 11 13 Unload Station 13 11 9 7 5 3 17
  • 8. Industrial Engineering Letters www.iiste.org ISSN 2224-6096 (Print) ISSN 2225-0581(Online) Vol 1, No.4, 2011 Table 7: (Load Unload Matrices for Liner layout) Slots S1 S2 S3 S4 S5 S6 S1 0 4 6 8 10 12 S2 4 0 4 6 8 10 S3 6 4 0 4 6 8 S4 8 6 4 0 4 6 S5 10 8 6 4 0 4 S6 12 10 8 6 4 0 Table 8: (Inter slot distance for Loop Layout) Slots S1 S2 S3 S4 S5 S6 Load Station 4 6 8 10 12 14 Unload 14 12 10 8 6 4 Station Table 9: (Load Unload Matrices for Loop layout) Slots S1 S2 S3 S4 S5 S6 S1 0 6 8 10 12 14 S2 6 0 6 8 10 12 S3 8 6 0 6 8 10 S4 10 8 6 0 6 8 S5 12 10 8 6 0 6 S6 14 12 10 8 6 0 18
  • 9. Industrial Engineering Letters www.iiste.org ISSN 2224-6096 (Print) ISSN 2225-0581(Online) Vol 1, No.4, 2011 Table 10: (Inter Slot distance for Ladder Layout) Slots S1 S2 S3 S4 S5 S6 Load Station 1 5 7 9 11 13 Unload Station 13 11 9 7 5 1 Table 11: (Load unload Matrices for Ladder Layout) Machine M1 M2 M3 M4 M5 M6 No 4 6 6 8 8 6 Waiting time in minutes 6 8 6 8 6 4 Table 12: (Waiting Time of machine) Job No J1 J2 J3 J4 J5 J6 Waiting time in 3210 3340 1740 3810 3840 1750 minutes Table 13: (Waiting time for job) M/C No Job Sequence M1 J1 J6 J4 J3 J5 J2 M2 J2 J1 J4 J5 J1 J3 M3 J3 J2 J5 J1 J4 J4 M4 J3 J6 J4 J5 J1 J2 M5 J6 J2 J4 J1 J3 J5 M6 J6 J1 J2 J1 J5 J1 Table 14: (Job Sequence for minimum production time) Type of Layout Machine arrangement Sequence Total Transportation Cost Liner M4 M6 M1 M5 M2 M1 3370 Loop M4 M6 M1 M5 M2 M1 3382 Ladder M4 M1 M5 M6 M2 M1 6324 Open Field M4 M1 M5 M6 M1 M1 4212 19
  • 10. Industrial Engineering Letters www.iiste.org ISSN 2224-6096 (Print) ISSN 2225-0581(Online) Vol 1, No.4, 2011 Table 15: (Machine order and cost for different layout) Load 2 2 2 2 Unload 2 2 l 1 1 1 1 1 S1 S21 S3 S4 S5 S6 Figure 1 Liner (single and double row machine layout) S1 S2 1 1 2 1 Load 1 S3 2 1 Load S4 2 1 1 S6 S5 20
  • 11. International Journals Call for Paper The IISTE, a U.S. publisher, is currently hosting the academic journals listed below. The peer review process of the following journals usually takes LESS THAN 14 business days and IISTE usually publishes a qualified article within 30 days. Authors should send their full paper to the following email address. More information can be found in the IISTE website : www.iiste.org Business, Economics, Finance and Management PAPER SUBMISSION EMAIL European Journal of Business and Management EJBM@iiste.org Research Journal of Finance and Accounting RJFA@iiste.org Journal of Economics and Sustainable Development JESD@iiste.org Information and Knowledge Management IKM@iiste.org Developing Country Studies DCS@iiste.org Industrial Engineering Letters IEL@iiste.org Physical Sciences, Mathematics and Chemistry PAPER SUBMISSION EMAIL Journal of Natural Sciences Research JNSR@iiste.org Chemistry and Materials Research CMR@iiste.org Mathematical Theory and Modeling MTM@iiste.org Advances in Physics Theories and Applications APTA@iiste.org Chemical and Process Engineering Research CPER@iiste.org Engineering, Technology and Systems PAPER SUBMISSION EMAIL Computer Engineering and Intelligent Systems CEIS@iiste.org Innovative Systems Design and Engineering ISDE@iiste.org Journal of Energy Technologies and Policy JETP@iiste.org Information and Knowledge Management IKM@iiste.org Control Theory and Informatics CTI@iiste.org Journal of Information Engineering and Applications JIEA@iiste.org Industrial Engineering Letters IEL@iiste.org Network and Complex Systems NCS@iiste.org Environment, Civil, Materials Sciences PAPER SUBMISSION EMAIL Journal of Environment and Earth Science JEES@iiste.org Civil and Environmental Research CER@iiste.org Journal of Natural Sciences Research JNSR@iiste.org Civil and Environmental Research CER@iiste.org Life Science, Food and Medical Sciences PAPER SUBMISSION EMAIL Journal of Natural Sciences Research JNSR@iiste.org Journal of Biology, Agriculture and Healthcare JBAH@iiste.org Food Science and Quality Management FSQM@iiste.org Chemistry and Materials Research CMR@iiste.org Education, and other Social Sciences PAPER SUBMISSION EMAIL Journal of Education and Practice JEP@iiste.org Journal of Law, Policy and Globalization JLPG@iiste.org Global knowledge sharing: New Media and Mass Communication NMMC@iiste.org EBSCO, Index Copernicus, Ulrich's Journal of Energy Technologies and Policy JETP@iiste.org Periodicals Directory, JournalTOCS, PKP Historical Research Letter HRL@iiste.org Open Archives Harvester, Bielefeld Academic Search Engine, Elektronische Public Policy and Administration Research PPAR@iiste.org Zeitschriftenbibliothek EZB, Open J-Gate, International Affairs and Global Strategy IAGS@iiste.org OCLC WorldCat, Universe Digtial Library , Research on Humanities and Social Sciences RHSS@iiste.org NewJour, Google Scholar. Developing Country Studies DCS@iiste.org IISTE is member of CrossRef. All journals Arts and Design Studies ADS@iiste.org have high IC Impact Factor Values (ICV).