SlideShare a Scribd company logo
1 of 10
Rank Positional weight
(RPW) for assembly line
balancing
HEURISTIC METHOD
Rank positional weight
 It is a heuristic algorithm used to solve the assembly line balancing
problem. This methods depends on the processing times for all tasks and
their followers.
RPW Example
 The below figure shows the tasks, times and precedence relation for each
element used in cashew machine assembly.
Tas Time
(min)
Description Predecessor
1 20 Frame assembly -
2 20 Cutter assembly 1
3 45 Motor assembly 2
4 10 Crank assembly 3
5 7 Pickup assembly 2
6 5 Belt cover assembly 5
7 8 Cup assembly 5
8 20 Bucket and disk assembly with
shaft
5
9 15 Feed motor and belt assembly 5
10 5 Circuit assembly 5
11 4 Hopper assembly 6,7,8,9,10
12 45 Connect wires 11,4
13 6 Outer cover assembly 12
Precedence diagram
RPW solution method
 1-draw precedence diagram.
 2- for each task find the transitive followers (followers of followers till you
reach the end of the graph).
 3- calculate the RPW for each task (i). (RPW(i)= time of the task (i)+
summation of times of tasks in the transitive followers (i)
 4-re-arrange tasks according to their RPW in descending order
 5-open a work station and assign the feasible tasks till the cycle time is
reached or no more assignable tasks in the station.
 6- Repeat step 5 till all tasksare added to work stations.
RPW
Task RPW
1 210
2 190
3 106
4 61
5 115
6 60
7 63
8 75
9 70
10 60
11 55
12 51
13 6
RPW in descending order
Task RPW
1 210
2 190
5 106
3 61
8 115
9 60
7 63
4 75
6 70
10 60
11 55
12 51
13 6
Assign to work stations
Station task time Sum of station time
1
1 20 20
2 20 40
5 7 47
7 8 55
2
3 45 45
4 10 55
3
8 20 20
9 15 35
6 5 40
10 5 45
11 4 49
4
12 45 45
13 6 51
RPW software
 The RPW software available can be purchased by 10$ only
 Contact me for more information
 Shadymagdy@windowslive.com
Thank You!
SOMEONE@EXAMPLE.COM

More Related Content

What's hot

Assembly Line Balancing | Case Study
Assembly Line Balancing | Case StudyAssembly Line Balancing | Case Study
Assembly Line Balancing | Case StudyMd Abu Bakar Siddique
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line BalancingAlan Wei Teck
 
Line balancing ppt By Wakil Kumar
Line balancing ppt By Wakil KumarLine balancing ppt By Wakil Kumar
Line balancing ppt By Wakil KumarWakil Kumar
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancingRohit Goutam
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulationavijit biswas
 
07 Line Balancing
07 Line Balancing07 Line Balancing
07 Line BalancingArif Rahman
 
Lead time takt time cycle time and throughput
Lead time takt time cycle time and throughputLead time takt time cycle time and throughput
Lead time takt time cycle time and throughputHpm India
 
Introduction to time study
Introduction to time studyIntroduction to time study
Introduction to time studymechanical2015
 
What is cycle time in the manufacturing process
What is cycle time in the manufacturing processWhat is cycle time in the manufacturing process
What is cycle time in the manufacturing processMRPeasy
 
Assembly systems & line balance
Assembly systems & line balanceAssembly systems & line balance
Assembly systems & line balanceSudhir Reddy
 
Principles of Motion Economy
Principles of Motion EconomyPrinciples of Motion Economy
Principles of Motion EconomyJoseph Konnully
 

What's hot (20)

Assembly Line Balancing | Case Study
Assembly Line Balancing | Case StudyAssembly Line Balancing | Case Study
Assembly Line Balancing | Case Study
 
Line balancing
Line balancingLine balancing
Line balancing
 
Line balancing & EOQ
Line balancing & EOQLine balancing & EOQ
Line balancing & EOQ
 
Line balancing
Line balancingLine balancing
Line balancing
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line Balancing
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line Balancing
 
Line balancing ppt By Wakil Kumar
Line balancing ppt By Wakil KumarLine balancing ppt By Wakil Kumar
Line balancing ppt By Wakil Kumar
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancing
 
World class manufacturing
World class manufacturingWorld class manufacturing
World class manufacturing
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulation
 
Time study
Time studyTime study
Time study
 
07 Line Balancing
07 Line Balancing07 Line Balancing
07 Line Balancing
 
Lead time takt time cycle time and throughput
Lead time takt time cycle time and throughputLead time takt time cycle time and throughput
Lead time takt time cycle time and throughput
 
Introduction to time study
Introduction to time studyIntroduction to time study
Introduction to time study
 
What is cycle time in the manufacturing process
What is cycle time in the manufacturing processWhat is cycle time in the manufacturing process
What is cycle time in the manufacturing process
 
Shop Floor Planning & Control
Shop Floor Planning & ControlShop Floor Planning & Control
Shop Floor Planning & Control
 
Line balancing and heuristics
Line balancing and heuristicsLine balancing and heuristics
Line balancing and heuristics
 
Assembly systems & line balance
Assembly systems & line balanceAssembly systems & line balance
Assembly systems & line balance
 
CIM 15ME62 Module-3
CIM 15ME62  Module-3CIM 15ME62  Module-3
CIM 15ME62 Module-3
 
Principles of Motion Economy
Principles of Motion EconomyPrinciples of Motion Economy
Principles of Motion Economy
 

Similar to Assembly line balancing using Rank positional weight (RPW)

final Line balancing slide12.ppt
final Line balancing slide12.pptfinal Line balancing slide12.ppt
final Line balancing slide12.pptxicohos114
 
Scheduling ppt @ doms
Scheduling ppt @ doms Scheduling ppt @ doms
Scheduling ppt @ doms Babasab Patil
 
Scheduling ppt @ DOMS
Scheduling ppt @ DOMSScheduling ppt @ DOMS
Scheduling ppt @ DOMSBabasab Patil
 
79971255-assembly-line-balancing-130223195412-phpapp02.pdf
79971255-assembly-line-balancing-130223195412-phpapp02.pdf79971255-assembly-line-balancing-130223195412-phpapp02.pdf
79971255-assembly-line-balancing-130223195412-phpapp02.pdfRobin8015873726
 
Aminullah Assagaf_P14-Ch.17_Scheduling-32.pptx
Aminullah Assagaf_P14-Ch.17_Scheduling-32.pptxAminullah Assagaf_P14-Ch.17_Scheduling-32.pptx
Aminullah Assagaf_P14-Ch.17_Scheduling-32.pptxAminullah Assagaf
 
[CCC'21] Evaluation of Work Stealing Algorithms
[CCC'21] Evaluation of Work Stealing Algorithms[CCC'21] Evaluation of Work Stealing Algorithms
[CCC'21] Evaluation of Work Stealing AlgorithmsUniversidad de los Andes
 
XPDDS18: Real Time in XEN on ARM - Andrii Anisov, EPAM Systems Inc.
XPDDS18: Real Time in XEN on ARM - Andrii Anisov, EPAM Systems Inc.XPDDS18: Real Time in XEN on ARM - Andrii Anisov, EPAM Systems Inc.
XPDDS18: Real Time in XEN on ARM - Andrii Anisov, EPAM Systems Inc.The Linux Foundation
 
Computer_Architecture_3rd_Edition_by_Moris_Mano_Ch_09.ppt
Computer_Architecture_3rd_Edition_by_Moris_Mano_Ch_09.pptComputer_Architecture_3rd_Edition_by_Moris_Mano_Ch_09.ppt
Computer_Architecture_3rd_Edition_by_Moris_Mano_Ch_09.pptHermellaGashaw
 
Unit 3-pipelining & vector processing
Unit 3-pipelining & vector processingUnit 3-pipelining & vector processing
Unit 3-pipelining & vector processingvishal choudhary
 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingLean6Sigma4all
 
Vsm and wip with arena simulation
Vsm and wip with  arena simulationVsm and wip with  arena simulation
Vsm and wip with arena simulationuniceder1111
 

Similar to Assembly line balancing using Rank positional weight (RPW) (20)

final Line balancing slide12.ppt
final Line balancing slide12.pptfinal Line balancing slide12.ppt
final Line balancing slide12.ppt
 
chapter 17.pdf
chapter 17.pdfchapter 17.pdf
chapter 17.pdf
 
Scheduling ppt @ doms
Scheduling ppt @ doms Scheduling ppt @ doms
Scheduling ppt @ doms
 
Scheduling ppt @ DOMS
Scheduling ppt @ DOMSScheduling ppt @ DOMS
Scheduling ppt @ DOMS
 
scheduling_1.ppt
scheduling_1.pptscheduling_1.ppt
scheduling_1.ppt
 
C17
C17C17
C17
 
79971255-assembly-line-balancing-130223195412-phpapp02.pdf
79971255-assembly-line-balancing-130223195412-phpapp02.pdf79971255-assembly-line-balancing-130223195412-phpapp02.pdf
79971255-assembly-line-balancing-130223195412-phpapp02.pdf
 
Aminullah Assagaf_P14-Ch.17_Scheduling-32.pptx
Aminullah Assagaf_P14-Ch.17_Scheduling-32.pptxAminullah Assagaf_P14-Ch.17_Scheduling-32.pptx
Aminullah Assagaf_P14-Ch.17_Scheduling-32.pptx
 
[CCC'21] Evaluation of Work Stealing Algorithms
[CCC'21] Evaluation of Work Stealing Algorithms[CCC'21] Evaluation of Work Stealing Algorithms
[CCC'21] Evaluation of Work Stealing Algorithms
 
XPDDS18: Real Time in XEN on ARM - Andrii Anisov, EPAM Systems Inc.
XPDDS18: Real Time in XEN on ARM - Andrii Anisov, EPAM Systems Inc.XPDDS18: Real Time in XEN on ARM - Andrii Anisov, EPAM Systems Inc.
XPDDS18: Real Time in XEN on ARM - Andrii Anisov, EPAM Systems Inc.
 
Scheduling
SchedulingScheduling
Scheduling
 
Scheduling
SchedulingScheduling
Scheduling
 
Scheduling
SchedulingScheduling
Scheduling
 
Computer_Architecture_3rd_Edition_by_Moris_Mano_Ch_09.ppt
Computer_Architecture_3rd_Edition_by_Moris_Mano_Ch_09.pptComputer_Architecture_3rd_Edition_by_Moris_Mano_Ch_09.ppt
Computer_Architecture_3rd_Edition_by_Moris_Mano_Ch_09.ppt
 
Unit 3-pipelining & vector processing
Unit 3-pipelining & vector processingUnit 3-pipelining & vector processing
Unit 3-pipelining & vector processing
 
5.CPU Scheduling
5.CPU Scheduling5.CPU Scheduling
5.CPU Scheduling
 
Online Architecture Assignment Help
Online Architecture Assignment HelpOnline Architecture Assignment Help
Online Architecture Assignment Help
 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream Mapping
 
ch6.ppt
ch6.pptch6.ppt
ch6.ppt
 
Vsm and wip with arena simulation
Vsm and wip with  arena simulationVsm and wip with  arena simulation
Vsm and wip with arena simulation
 

Recently uploaded

High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 

Recently uploaded (20)

High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 

Assembly line balancing using Rank positional weight (RPW)

  • 1. Rank Positional weight (RPW) for assembly line balancing HEURISTIC METHOD
  • 2. Rank positional weight  It is a heuristic algorithm used to solve the assembly line balancing problem. This methods depends on the processing times for all tasks and their followers.
  • 3. RPW Example  The below figure shows the tasks, times and precedence relation for each element used in cashew machine assembly. Tas Time (min) Description Predecessor 1 20 Frame assembly - 2 20 Cutter assembly 1 3 45 Motor assembly 2 4 10 Crank assembly 3 5 7 Pickup assembly 2 6 5 Belt cover assembly 5 7 8 Cup assembly 5 8 20 Bucket and disk assembly with shaft 5 9 15 Feed motor and belt assembly 5 10 5 Circuit assembly 5 11 4 Hopper assembly 6,7,8,9,10 12 45 Connect wires 11,4 13 6 Outer cover assembly 12
  • 5. RPW solution method  1-draw precedence diagram.  2- for each task find the transitive followers (followers of followers till you reach the end of the graph).  3- calculate the RPW for each task (i). (RPW(i)= time of the task (i)+ summation of times of tasks in the transitive followers (i)  4-re-arrange tasks according to their RPW in descending order  5-open a work station and assign the feasible tasks till the cycle time is reached or no more assignable tasks in the station.  6- Repeat step 5 till all tasksare added to work stations.
  • 6. RPW Task RPW 1 210 2 190 3 106 4 61 5 115 6 60 7 63 8 75 9 70 10 60 11 55 12 51 13 6
  • 7. RPW in descending order Task RPW 1 210 2 190 5 106 3 61 8 115 9 60 7 63 4 75 6 70 10 60 11 55 12 51 13 6
  • 8. Assign to work stations Station task time Sum of station time 1 1 20 20 2 20 40 5 7 47 7 8 55 2 3 45 45 4 10 55 3 8 20 20 9 15 35 6 5 40 10 5 45 11 4 49 4 12 45 45 13 6 51
  • 9. RPW software  The RPW software available can be purchased by 10$ only  Contact me for more information  Shadymagdy@windowslive.com