SlideShare a Scribd company logo
1 of 27
Download to read offline
Module : 2
Plant
Design
Rashmi S
Dept of IE&M
JSS Academy of Technical Education,
Bengaluru
Contents
Plant Design:
 Layout procedure
 study of some approaches (Immer, Nadler,
Muther, Apple James and Reed’s approach)
 systematic layout planning
 the activity relationship chart
 Constructing the activity relationship chart
 Activity relationship diagram
October 5, 2020
Rashmi S, Dept. of IEM, JSSATE-B
2
Design Procedure
Typically, design problems do not have well-defined, unique,
optimum solutions. We are interested in obtaining a satisfactory
solution.
General Procedure for Solving Engineering Design Problems
1. Formulate the problem.
2. Analyze the problem.
3. Search for alternative solutions.
4. Evaluate the design alternatives.
5. Select the preferred design.
6. Implement the design.
October 5, 2020
3
Rashmi S, Dept. of IEM, JSSATE-B
Application of the Engineering Design Process to Facility Planning
1. Define (or redefine) the objective of the facility: Specify quantitatively the
products to be produced or service to be provided.
2. Specify the primary and support activities to be performed in accomplishing
the objective: Requirements for primary activities include operations,
equipment, personnel, and material flows.
3. Determine the interrelationships among all activities: Both qualitative and
quantitative relationships should be defined.
4. Determine the space requirements for all activities: These are determined
considering the equipment, materials, and personnel requirements.
5. Generate alternative facility plans: Including alternative facility locations and
alternative designs for the facility.
6. Evaluate alternative facility plans: Determine the important factors
October 5, 2020
4
Rashmi S, Dept. of IEM, JSSATE-B
Contd…
7. Select a facility plan: Cost may not be the only major consideration. Use
the information in step 6 to determine a plan (pairwise comparison is a good
ranking procedure).
8. Implement the facility plan: Considerable amount of planning must
precede the construction of a facility or the layout of an area.
9. Maintain and adapt the facility plan: The facility plan must be modified as
new requirements are placed, e.g., new energy saving measures, changes in
product design may require different flow pattern or handling equipment,
etc.
10. Redefine the objective of the facility: Similar to step 1. Changes in product
design and/or quantities may require changes into the layout plan.
October 5, 2020
5
Rashmi S, Dept. of IEM, JSSATE-B
Facility Layout
A Layout problem may be to
• Determine the location for a new machine
• Develop a new layout for an existing production plant
• Develop a layout for a new production plant
A Layout problem may arises due to changes in the design of a product,
• Addition or deletion of a product
• Change in the demand of a product
• Changes in the design of the process
• Addition or deletion of a process
• Replacement of equipment
October 5, 2020
6
Rashmi S, Dept. of IEM, JSSATE-B
Facility Layout
A Layout problem may be to
 Determine the location for a new machine,
 Develop a new layout for an existing production plant,
 Develop a layout for a new production plant,
A Layout problem may arises due to
 Changes in the design of a product,
 Addition or deletion of a product,
 Change in the demand of a product,
 Changes in the design of the process,
 Addition or deletion of a process,
 Replacement of equipment,
October 5, 2020
7
Rashmi S, Dept. of IEM, JSSATE-B
Objectives of Facility Layout
• Minimize investment in equipment.
• Minimize production time.
• Minimize material handling cost.
• Maximize utilization of space.
• Maintain flexibility of arrangement and operation.
• Provide safety and comfort to employees.
October 5, 2020
8
Rashmi S, Dept. of IEM, JSSATE-B
Product
Design
Production
Planning
Process
Design
Facility
Layout
Material
Handling
System
Design
Sequential Approach vs Integrated Approach
Sequential Approach :
October 5, 2020
9
Rashmi S, Dept. of IEM, JSSATE-B
Sequential Approach vs Integrated Approach
Integrated
Approach :
Impressive results in
cost, quality,
productivity, sales,
customer satisfaction,
delivery time, inventory
levels, space +
handling requirements,
building size, etc.
Product
Design
Process
Design
Schedule
Design
Layout Design
+
Material
Handling System
Design
Concurrent Engineering
Terms of product,
process, scheduling
and facility design
planners work with
marketing, purchasing,
etc. Personnel address
the design process in
an integrated way.
October 5, 2020
10
Rashmi S, Dept. of IEM, JSSATE-B
Traditional Facility Layout Procedures
• Naddler’s Ideal System Approach (1961)
• Immer’s Basic Steps (1950)
• Apple’s Plant Layout Procedure (1977)
• Reed’s Plant Layout Procedure (1961)
• Muther’s Systematic Layout Planning (1961)
October 5, 2020
11
Rashmi S, Dept. of IEM, JSSATE-B
Naddler’s Ideal System Approach
The ideal system approach is based on the
following hierarchical approach toward
design:
1. Aim for the “theoretical ideal
system.”
2. Conceptualize the “ultimate ideal
system.”
3. Design the “technologically
workable ideal system.”
4. Install the “recommended system.”
Theoretical ideal system
Ultimate ideal system
Technologically workable
system
Recommended
system
Present system
October 5, 2020
12
Rashmi S, Dept. of IEM, JSSATE-B
Immer’s Basic Steps
Immer described the analysis of a layout problem to be composed of three
simple steps, which can be applied to any type of layout problem.
The steps are:
1. Put the problem on the paper.
2. Show lines of flow.
3. Convert flow lines to machine lines.
October 5, 2020
13
Rashmi S, Dept. of IEM, JSSATE-B
Apple’s Plant Layout Procedure
Apple recommended that the following detailed sequence of steps be used in
designing a plant layout.
1. Procure the basic data. 11. Determine storage requirements
2. Analyze the basic data. 12. Plan service and auxiliary activities.
3. Design the productive process. 13. Determine space requirements.
4. Plan the material flow pattern. 14. Allocate activities to total space.
5. Consider the general material handling plan. 15. Consider building type
6. Calculate equipment requirements. 16. Consider master layouts.
7. Plan individual work stations. 17. Evaluate, adjust and check the layout.
8. Select specific material handling equipment. 18. Obtain approval.
9. Coordinate groups of related operations. 19. Install the layout.
10. Design activity relationships. 20. Follow up on implementation of layout.
October 5, 2020
14
Rashmi S, Dept. of IEM, JSSATE-B
Reed’s Plant Layout Procedure
In “planning for and preparing the layout,” Reed recommended that the
following steps be taken in his “systematic plan of attach”:
1. Analyze the product to be produced.
2. Determine the process required to manufacture the product.
3. Prepare layout planning charts.
4. Determine work stations.
5. Analyze storage area requirements.
6. Establish minimum aisle widths.
7. Establish office requirements.
8. Consider personnel facilities and services.
9. Survey plant services.
10. Provide for future expansion.
October 5, 2020
15
Rashmi S, Dept. of IEM, JSSATE-B
Systematic Layout Planning Procedure (Muther 1961)
Systematic layout planning is an organized way to conduct layout
planning, it consists of a framework of phases, a pattern of procedures and
a set of conventions for identifying , rating and visualizing the elements
and areas involved in a plan.
SLP is a framework of four planning phases:
•Analysis
•Search
•Evaluation
•Selection
October 5, 2020
16
Rashmi S, Dept. of IEM, JSSATE-B
October 5, 2020
17
Rashmi
S,
Dept.
of
IEM,
JSSATE-B
Each layout rests on three fundamentals
 RELATIONSHIPS –
Degree of closeness desired among things
 SPACE –
The amount, kind, shape of configuration of the things to be
laid out
 ADJUSTMENTS –
Arrangement of things into a realistic best fit
These are the heart of any layout plan regardless of products,
processes or size.
October 5, 2020
18
Rashmi S, Dept. of IEM, JSSATE-B
There are 20 steps in SLP Pattern:
 Procure data
 Analyze data
 Design production process
 Design material flow pattern
 Select/ design material handling plan
 Calculate requirement of equipments
 Plan work areas
 Select material handling equipments
 Plan group of related operations
 Design activity relationship
• Calculate space requirements
• Plan service activities
• Calculate total space requirements
• Allocate activities to space
• Consider building types
• Construct model layout
• Evaluate, adjust, and check layout
• Justify
• Install
• Nurture layout
October 5, 2020
19
Rashmi S, Dept. of IEM, JSSATE-B
The activity relationship diagram also called the Affinity analysis diagram in the facility layout.
“An activity relationship chart (ARC) is a tabular means of displaying the closeness rating among
all activities or departments.
In general, there are 6 closeness rating are used” This rating is named as “A, E, I, O, U, And X”
This rating has a specific meaning attached to it.
Activity Relationship diagram
October 5, 2020
20
Rashmi S, Dept. of IEM, JSSATE-B
Rating symbols
 Following is the rating symbols with the meaning
 A Is Absolutely necessary
 E is especially Important
 I am Important
 O is Ordinary
 U is unimportant
 X should be i
October 5, 2020
21
Rashmi S, Dept. of IEM, JSSATE-B
October 5, 2020
22
Rashmi S, Dept. of IEM, JSSATE-B
October 5, 2020
23
Rashmi S, Dept. of IEM, JSSATE-B
Reasons codes:
Reasons codes are used for finding the volume or importance of a
relationship to the rating symbol. Following are some of the reasons
codes;
 Same table
 Flow of materials
 Service
 Inventory control
 Volume
 Flow of parts
 Cleanliness
 Communications
October 5, 2020
24
Rashmi S, Dept. of IEM, JSSATE-B
Rule of thumb:
 These rules of thumb are used for assigning code to any activity
relationship diagram, you shouldn’t violate these rules otherwise the
facility layout will not be that effective.
 Used few “A” And “X” relationships <5%
 No more than 10% of “E” Relationships in the activity relationship
diagram.
 “I” should be used less than 15%
 No more than 20% should be “O” relationships.
 About 50% of the relationships should be “U”
October 5, 2020
25
Rashmi S, Dept. of IEM, JSSATE-B
Contd…
 The basic purpose of the activity relationship diagram is to ensure that
the facility you are designing has the minimal distance between the
two facilities that are important for each other.
 One activity can’t be performing if the previous activity has not been
done.
 Like, first you do welding then painting, what if you send a piece of
metal to paint first and then to the welding? So, the basic purpose is
to place facilities closer and to reduce cycle time.
October 5, 2020
26
Rashmi S, Dept. of IEM, JSSATE-B
October 5, 2020
Rashmi S, Dept. of IEM, JSSATE-B
27
References
 Facilities Planning, Third Edition By JAMES A. Tompkins
 Plant Layout And Materials Handling By James M. Apple
 Facility Planning & Layout Design by Chandrashekar
Hiregoudar, B Raghavendra Reddy

More Related Content

What's hot

Manufacturing System, Product design & development
Manufacturing System, Product design & developmentManufacturing System, Product design & development
Manufacturing System, Product design & developmentPrashant Ranjan
 
Group technology, Production flow Analysis
Group technology, Production flow AnalysisGroup technology, Production flow Analysis
Group technology, Production flow AnalysisKEERTHIVASAN RAVI
 
Design for Assembly (DFA)
Design for Assembly (DFA)Design for Assembly (DFA)
Design for Assembly (DFA)Richard Farr
 
Production Planning and Control (Operations Management)
Production Planning and Control (Operations Management)Production Planning and Control (Operations Management)
Production Planning and Control (Operations Management)Manu Alias
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & ControlKunalJagtap5
 
Plant Lay out and Material Handeling
Plant Lay out and Material HandelingPlant Lay out and Material Handeling
Plant Lay out and Material HandelingShreyashPatel24
 
Industrial engineering intro
Industrial engineering introIndustrial engineering intro
Industrial engineering introvishnuvardhinikj
 
manufacturing resource planning
manufacturing resource planningmanufacturing resource planning
manufacturing resource planningDinesh Nikam
 
Introduction of Industrial Engineering
Introduction of Industrial EngineeringIntroduction of Industrial Engineering
Introduction of Industrial Engineeringvijay kumar
 
Facility layout ppt
Facility layout pptFacility layout ppt
Facility layout pptAnju Rana
 
Product, process, fixed and group layouts
Product, process, fixed and group layoutsProduct, process, fixed and group layouts
Product, process, fixed and group layoutsAjith Antony
 

What's hot (20)

Manufacturing System, Product design & development
Manufacturing System, Product design & developmentManufacturing System, Product design & development
Manufacturing System, Product design & development
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
Group technology, Production flow Analysis
Group technology, Production flow AnalysisGroup technology, Production flow Analysis
Group technology, Production flow Analysis
 
Plant Layout
Plant LayoutPlant Layout
Plant Layout
 
Plant layout
Plant layoutPlant layout
Plant layout
 
Design for Assembly (DFA)
Design for Assembly (DFA)Design for Assembly (DFA)
Design for Assembly (DFA)
 
Production Planning and Control (Operations Management)
Production Planning and Control (Operations Management)Production Planning and Control (Operations Management)
Production Planning and Control (Operations Management)
 
Aggregate planning
Aggregate planningAggregate planning
Aggregate planning
 
Product Operation Planning & Control
Product Operation Planning & ControlProduct Operation Planning & Control
Product Operation Planning & Control
 
CIM 15ME62 Module-1
CIM 15ME62   Module-1CIM 15ME62   Module-1
CIM 15ME62 Module-1
 
Group Technology
Group TechnologyGroup Technology
Group Technology
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
 
Plant Lay out and Material Handeling
Plant Lay out and Material HandelingPlant Lay out and Material Handeling
Plant Lay out and Material Handeling
 
Industrial engineering intro
Industrial engineering introIndustrial engineering intro
Industrial engineering intro
 
Unit 4 ppc
Unit 4 ppcUnit 4 ppc
Unit 4 ppc
 
manufacturing resource planning
manufacturing resource planningmanufacturing resource planning
manufacturing resource planning
 
Introduction of Industrial Engineering
Introduction of Industrial EngineeringIntroduction of Industrial Engineering
Introduction of Industrial Engineering
 
Facility layout ppt
Facility layout pptFacility layout ppt
Facility layout ppt
 
Product, process, fixed and group layouts
Product, process, fixed and group layoutsProduct, process, fixed and group layouts
Product, process, fixed and group layouts
 
Introduction to manufacturing process
Introduction to manufacturing processIntroduction to manufacturing process
Introduction to manufacturing process
 

Similar to Module 2 plant design

facility layout.ppt
facility layout.pptfacility layout.ppt
facility layout.pptRenu Lamba
 
facility layout.ppt
facility layout.pptfacility layout.ppt
facility layout.pptRenu Lamba
 
Facilities planning - Module 1 Plant Location and Material handling
Facilities planning - Module 1 Plant Location and Material handlingFacilities planning - Module 1 Plant Location and Material handling
Facilities planning - Module 1 Plant Location and Material handlingRashmi Srinivas
 
A Framework to optimize Construction Site Layout Planning
A Framework to optimize Construction Site Layout PlanningA Framework to optimize Construction Site Layout Planning
A Framework to optimize Construction Site Layout PlanningIRJET Journal
 
Designing and Redesigning business process: Plant Location
Designing and Redesigning business process: Plant LocationDesigning and Redesigning business process: Plant Location
Designing and Redesigning business process: Plant LocationMOHD AMAAN HASAN
 
The Strategic Facility Layout Problem in Industry
The Strategic Facility Layout Problem in IndustryThe Strategic Facility Layout Problem in Industry
The Strategic Facility Layout Problem in IndustryProplanner Asia
 
Mba ii pmom_unit-2.3 facility layout a
Mba ii pmom_unit-2.3 facility layout aMba ii pmom_unit-2.3 facility layout a
Mba ii pmom_unit-2.3 facility layout aRai University
 
FP - Spring 2021 - Lecture 1 - Introduction.pdf
FP - Spring 2021 - Lecture 1 - Introduction.pdfFP - Spring 2021 - Lecture 1 - Introduction.pdf
FP - Spring 2021 - Lecture 1 - Introduction.pdfamrahmed683029
 
What i es do iie iab v2
What i es do iie iab v2What i es do iie iab v2
What i es do iie iab v2Jitesh Gaurav
 
Om rak-sbs-2 (1)
Om rak-sbs-2 (1)Om rak-sbs-2 (1)
Om rak-sbs-2 (1)smumbahelp
 
A Review on Design of a Fixture for Rear Cover
A Review on Design of a Fixture for Rear CoverA Review on Design of a Fixture for Rear Cover
A Review on Design of a Fixture for Rear Coverijsrd.com
 
Facility planning
Facility planningFacility planning
Facility planningMANJUNATH N
 
Lecture 1 a_review_design_process
Lecture 1 a_review_design_processLecture 1 a_review_design_process
Lecture 1 a_review_design_processAzua Marian
 
The Pact Processes - Overview
The Pact Processes - OverviewThe Pact Processes - Overview
The Pact Processes - OverviewEPPIC Inc.
 
QFD (Quality Function Deployment)
QFD (Quality Function Deployment)QFD (Quality Function Deployment)
QFD (Quality Function Deployment)Kamal Joshi
 
BA205 -POM_TOPIC 9-PROCESS SELECTION, FACILITIES LAY-OUT AND LOCATION DECISIO...
BA205 -POM_TOPIC 9-PROCESS SELECTION, FACILITIES LAY-OUT AND LOCATION DECISIO...BA205 -POM_TOPIC 9-PROCESS SELECTION, FACILITIES LAY-OUT AND LOCATION DECISIO...
BA205 -POM_TOPIC 9-PROCESS SELECTION, FACILITIES LAY-OUT AND LOCATION DECISIO...CyrilAlbertMercado
 
Manufacturing and Plant Master Planning
Manufacturing and Plant Master PlanningManufacturing and Plant Master Planning
Manufacturing and Plant Master PlanningGary Rushin
 
IRJET- Study and Implementation of ‘5 S’ System in Manufacturing Industry
IRJET-  	  Study and Implementation of ‘5 S’ System in Manufacturing IndustryIRJET-  	  Study and Implementation of ‘5 S’ System in Manufacturing Industry
IRJET- Study and Implementation of ‘5 S’ System in Manufacturing IndustryIRJET Journal
 

Similar to Module 2 plant design (20)

facility layout.ppt
facility layout.pptfacility layout.ppt
facility layout.ppt
 
facility layout.ppt
facility layout.pptfacility layout.ppt
facility layout.ppt
 
Facilities planning - Module 1 Plant Location and Material handling
Facilities planning - Module 1 Plant Location and Material handlingFacilities planning - Module 1 Plant Location and Material handling
Facilities planning - Module 1 Plant Location and Material handling
 
A Framework to optimize Construction Site Layout Planning
A Framework to optimize Construction Site Layout PlanningA Framework to optimize Construction Site Layout Planning
A Framework to optimize Construction Site Layout Planning
 
Designing and Redesigning business process: Plant Location
Designing and Redesigning business process: Plant LocationDesigning and Redesigning business process: Plant Location
Designing and Redesigning business process: Plant Location
 
The Strategic Facility Layout Problem in Industry
The Strategic Facility Layout Problem in IndustryThe Strategic Facility Layout Problem in Industry
The Strategic Facility Layout Problem in Industry
 
FACILITY PLANNING
FACILITY PLANNINGFACILITY PLANNING
FACILITY PLANNING
 
Mba ii pmom_unit-2.3 facility layout a
Mba ii pmom_unit-2.3 facility layout aMba ii pmom_unit-2.3 facility layout a
Mba ii pmom_unit-2.3 facility layout a
 
FP - Spring 2021 - Lecture 1 - Introduction.pdf
FP - Spring 2021 - Lecture 1 - Introduction.pdfFP - Spring 2021 - Lecture 1 - Introduction.pdf
FP - Spring 2021 - Lecture 1 - Introduction.pdf
 
What i es do iie iab v2
What i es do iie iab v2What i es do iie iab v2
What i es do iie iab v2
 
Om rak-sbs-2 (1)
Om rak-sbs-2 (1)Om rak-sbs-2 (1)
Om rak-sbs-2 (1)
 
A Review on Design of a Fixture for Rear Cover
A Review on Design of a Fixture for Rear CoverA Review on Design of a Fixture for Rear Cover
A Review on Design of a Fixture for Rear Cover
 
Facility planning
Facility planningFacility planning
Facility planning
 
Lecture 1 a_review_design_process
Lecture 1 a_review_design_processLecture 1 a_review_design_process
Lecture 1 a_review_design_process
 
Togaf introduction ver1 0
Togaf introduction ver1 0Togaf introduction ver1 0
Togaf introduction ver1 0
 
The Pact Processes - Overview
The Pact Processes - OverviewThe Pact Processes - Overview
The Pact Processes - Overview
 
QFD (Quality Function Deployment)
QFD (Quality Function Deployment)QFD (Quality Function Deployment)
QFD (Quality Function Deployment)
 
BA205 -POM_TOPIC 9-PROCESS SELECTION, FACILITIES LAY-OUT AND LOCATION DECISIO...
BA205 -POM_TOPIC 9-PROCESS SELECTION, FACILITIES LAY-OUT AND LOCATION DECISIO...BA205 -POM_TOPIC 9-PROCESS SELECTION, FACILITIES LAY-OUT AND LOCATION DECISIO...
BA205 -POM_TOPIC 9-PROCESS SELECTION, FACILITIES LAY-OUT AND LOCATION DECISIO...
 
Manufacturing and Plant Master Planning
Manufacturing and Plant Master PlanningManufacturing and Plant Master Planning
Manufacturing and Plant Master Planning
 
IRJET- Study and Implementation of ‘5 S’ System in Manufacturing Industry
IRJET-  	  Study and Implementation of ‘5 S’ System in Manufacturing IndustryIRJET-  	  Study and Implementation of ‘5 S’ System in Manufacturing Industry
IRJET- Study and Implementation of ‘5 S’ System in Manufacturing Industry
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 

Module 2 plant design

  • 1. Module : 2 Plant Design Rashmi S Dept of IE&M JSS Academy of Technical Education, Bengaluru
  • 2. Contents Plant Design:  Layout procedure  study of some approaches (Immer, Nadler, Muther, Apple James and Reed’s approach)  systematic layout planning  the activity relationship chart  Constructing the activity relationship chart  Activity relationship diagram October 5, 2020 Rashmi S, Dept. of IEM, JSSATE-B 2
  • 3. Design Procedure Typically, design problems do not have well-defined, unique, optimum solutions. We are interested in obtaining a satisfactory solution. General Procedure for Solving Engineering Design Problems 1. Formulate the problem. 2. Analyze the problem. 3. Search for alternative solutions. 4. Evaluate the design alternatives. 5. Select the preferred design. 6. Implement the design. October 5, 2020 3 Rashmi S, Dept. of IEM, JSSATE-B
  • 4. Application of the Engineering Design Process to Facility Planning 1. Define (or redefine) the objective of the facility: Specify quantitatively the products to be produced or service to be provided. 2. Specify the primary and support activities to be performed in accomplishing the objective: Requirements for primary activities include operations, equipment, personnel, and material flows. 3. Determine the interrelationships among all activities: Both qualitative and quantitative relationships should be defined. 4. Determine the space requirements for all activities: These are determined considering the equipment, materials, and personnel requirements. 5. Generate alternative facility plans: Including alternative facility locations and alternative designs for the facility. 6. Evaluate alternative facility plans: Determine the important factors October 5, 2020 4 Rashmi S, Dept. of IEM, JSSATE-B
  • 5. Contd… 7. Select a facility plan: Cost may not be the only major consideration. Use the information in step 6 to determine a plan (pairwise comparison is a good ranking procedure). 8. Implement the facility plan: Considerable amount of planning must precede the construction of a facility or the layout of an area. 9. Maintain and adapt the facility plan: The facility plan must be modified as new requirements are placed, e.g., new energy saving measures, changes in product design may require different flow pattern or handling equipment, etc. 10. Redefine the objective of the facility: Similar to step 1. Changes in product design and/or quantities may require changes into the layout plan. October 5, 2020 5 Rashmi S, Dept. of IEM, JSSATE-B
  • 6. Facility Layout A Layout problem may be to • Determine the location for a new machine • Develop a new layout for an existing production plant • Develop a layout for a new production plant A Layout problem may arises due to changes in the design of a product, • Addition or deletion of a product • Change in the demand of a product • Changes in the design of the process • Addition or deletion of a process • Replacement of equipment October 5, 2020 6 Rashmi S, Dept. of IEM, JSSATE-B
  • 7. Facility Layout A Layout problem may be to  Determine the location for a new machine,  Develop a new layout for an existing production plant,  Develop a layout for a new production plant, A Layout problem may arises due to  Changes in the design of a product,  Addition or deletion of a product,  Change in the demand of a product,  Changes in the design of the process,  Addition or deletion of a process,  Replacement of equipment, October 5, 2020 7 Rashmi S, Dept. of IEM, JSSATE-B
  • 8. Objectives of Facility Layout • Minimize investment in equipment. • Minimize production time. • Minimize material handling cost. • Maximize utilization of space. • Maintain flexibility of arrangement and operation. • Provide safety and comfort to employees. October 5, 2020 8 Rashmi S, Dept. of IEM, JSSATE-B
  • 9. Product Design Production Planning Process Design Facility Layout Material Handling System Design Sequential Approach vs Integrated Approach Sequential Approach : October 5, 2020 9 Rashmi S, Dept. of IEM, JSSATE-B
  • 10. Sequential Approach vs Integrated Approach Integrated Approach : Impressive results in cost, quality, productivity, sales, customer satisfaction, delivery time, inventory levels, space + handling requirements, building size, etc. Product Design Process Design Schedule Design Layout Design + Material Handling System Design Concurrent Engineering Terms of product, process, scheduling and facility design planners work with marketing, purchasing, etc. Personnel address the design process in an integrated way. October 5, 2020 10 Rashmi S, Dept. of IEM, JSSATE-B
  • 11. Traditional Facility Layout Procedures • Naddler’s Ideal System Approach (1961) • Immer’s Basic Steps (1950) • Apple’s Plant Layout Procedure (1977) • Reed’s Plant Layout Procedure (1961) • Muther’s Systematic Layout Planning (1961) October 5, 2020 11 Rashmi S, Dept. of IEM, JSSATE-B
  • 12. Naddler’s Ideal System Approach The ideal system approach is based on the following hierarchical approach toward design: 1. Aim for the “theoretical ideal system.” 2. Conceptualize the “ultimate ideal system.” 3. Design the “technologically workable ideal system.” 4. Install the “recommended system.” Theoretical ideal system Ultimate ideal system Technologically workable system Recommended system Present system October 5, 2020 12 Rashmi S, Dept. of IEM, JSSATE-B
  • 13. Immer’s Basic Steps Immer described the analysis of a layout problem to be composed of three simple steps, which can be applied to any type of layout problem. The steps are: 1. Put the problem on the paper. 2. Show lines of flow. 3. Convert flow lines to machine lines. October 5, 2020 13 Rashmi S, Dept. of IEM, JSSATE-B
  • 14. Apple’s Plant Layout Procedure Apple recommended that the following detailed sequence of steps be used in designing a plant layout. 1. Procure the basic data. 11. Determine storage requirements 2. Analyze the basic data. 12. Plan service and auxiliary activities. 3. Design the productive process. 13. Determine space requirements. 4. Plan the material flow pattern. 14. Allocate activities to total space. 5. Consider the general material handling plan. 15. Consider building type 6. Calculate equipment requirements. 16. Consider master layouts. 7. Plan individual work stations. 17. Evaluate, adjust and check the layout. 8. Select specific material handling equipment. 18. Obtain approval. 9. Coordinate groups of related operations. 19. Install the layout. 10. Design activity relationships. 20. Follow up on implementation of layout. October 5, 2020 14 Rashmi S, Dept. of IEM, JSSATE-B
  • 15. Reed’s Plant Layout Procedure In “planning for and preparing the layout,” Reed recommended that the following steps be taken in his “systematic plan of attach”: 1. Analyze the product to be produced. 2. Determine the process required to manufacture the product. 3. Prepare layout planning charts. 4. Determine work stations. 5. Analyze storage area requirements. 6. Establish minimum aisle widths. 7. Establish office requirements. 8. Consider personnel facilities and services. 9. Survey plant services. 10. Provide for future expansion. October 5, 2020 15 Rashmi S, Dept. of IEM, JSSATE-B
  • 16. Systematic Layout Planning Procedure (Muther 1961) Systematic layout planning is an organized way to conduct layout planning, it consists of a framework of phases, a pattern of procedures and a set of conventions for identifying , rating and visualizing the elements and areas involved in a plan. SLP is a framework of four planning phases: •Analysis •Search •Evaluation •Selection October 5, 2020 16 Rashmi S, Dept. of IEM, JSSATE-B
  • 18. Each layout rests on three fundamentals  RELATIONSHIPS – Degree of closeness desired among things  SPACE – The amount, kind, shape of configuration of the things to be laid out  ADJUSTMENTS – Arrangement of things into a realistic best fit These are the heart of any layout plan regardless of products, processes or size. October 5, 2020 18 Rashmi S, Dept. of IEM, JSSATE-B
  • 19. There are 20 steps in SLP Pattern:  Procure data  Analyze data  Design production process  Design material flow pattern  Select/ design material handling plan  Calculate requirement of equipments  Plan work areas  Select material handling equipments  Plan group of related operations  Design activity relationship • Calculate space requirements • Plan service activities • Calculate total space requirements • Allocate activities to space • Consider building types • Construct model layout • Evaluate, adjust, and check layout • Justify • Install • Nurture layout October 5, 2020 19 Rashmi S, Dept. of IEM, JSSATE-B
  • 20. The activity relationship diagram also called the Affinity analysis diagram in the facility layout. “An activity relationship chart (ARC) is a tabular means of displaying the closeness rating among all activities or departments. In general, there are 6 closeness rating are used” This rating is named as “A, E, I, O, U, And X” This rating has a specific meaning attached to it. Activity Relationship diagram October 5, 2020 20 Rashmi S, Dept. of IEM, JSSATE-B
  • 21. Rating symbols  Following is the rating symbols with the meaning  A Is Absolutely necessary  E is especially Important  I am Important  O is Ordinary  U is unimportant  X should be i October 5, 2020 21 Rashmi S, Dept. of IEM, JSSATE-B
  • 22. October 5, 2020 22 Rashmi S, Dept. of IEM, JSSATE-B
  • 23. October 5, 2020 23 Rashmi S, Dept. of IEM, JSSATE-B
  • 24. Reasons codes: Reasons codes are used for finding the volume or importance of a relationship to the rating symbol. Following are some of the reasons codes;  Same table  Flow of materials  Service  Inventory control  Volume  Flow of parts  Cleanliness  Communications October 5, 2020 24 Rashmi S, Dept. of IEM, JSSATE-B
  • 25. Rule of thumb:  These rules of thumb are used for assigning code to any activity relationship diagram, you shouldn’t violate these rules otherwise the facility layout will not be that effective.  Used few “A” And “X” relationships <5%  No more than 10% of “E” Relationships in the activity relationship diagram.  “I” should be used less than 15%  No more than 20% should be “O” relationships.  About 50% of the relationships should be “U” October 5, 2020 25 Rashmi S, Dept. of IEM, JSSATE-B
  • 26. Contd…  The basic purpose of the activity relationship diagram is to ensure that the facility you are designing has the minimal distance between the two facilities that are important for each other.  One activity can’t be performing if the previous activity has not been done.  Like, first you do welding then painting, what if you send a piece of metal to paint first and then to the welding? So, the basic purpose is to place facilities closer and to reduce cycle time. October 5, 2020 26 Rashmi S, Dept. of IEM, JSSATE-B
  • 27. October 5, 2020 Rashmi S, Dept. of IEM, JSSATE-B 27 References  Facilities Planning, Third Edition By JAMES A. Tompkins  Plant Layout And Materials Handling By James M. Apple  Facility Planning & Layout Design by Chandrashekar Hiregoudar, B Raghavendra Reddy