2. The project manager wants to determine the information needs of the project
stakeholders. Which of the following is not a valid source for this activity?
A. Project organization responsibility
B. Stakeholder register
C. Stakeholder's personal social media pages
D. Organizational charts
HINT: Which of the items is not related to the communication requirements analysis tool
and technique?
QUESTION:
3. The correct answer is C.
The project manager wants to determine the information needs of the project
stakeholders. To achieve this goal, the project manager needs to use the communication
requirement analysis tool and technique within the Plan Communications Management
process.
ANSWER:
4. The sources of information typically used to identify and define project communication
requirements include, but are not limited to: organizational charts; project organization
and stakeholder responsibility relationships; disciplines, departments, and specialties
involved in the project; logistics of how many persons will be involved with the project and
at which locations; Internal information needs (e.g., when communicating within
organizations); external information needs (e.g., when communicating with the media,
public, or contractors); and stakeholder information and communication requirements
from within the stakeholder register.
ANSWER:
5. All our questions are updated to the latest A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.