SlideShare a Scribd company logo
1 of 33
Liberty University BUSI 313 quiz 4 complete solutions correct answers slideshare
Six different versions
https://www.coursemerit.com/solution-details/20165/ Liberty-University-BUSI-313-quiz-4-complete-solutions-correct-answers-A-work
Question 1 Disadvantages of outsourcing project work may likely include all of the following
EXCEPT
Question 2 Experience indicates that colocation of project teams is not worth the extra costs.
Question 3 When using the partnering approach to manage contracted relationships, each party's
goals and objectives are similar but geared to what is best for them.
Question 4 Which of the following is true in regard to negotiation when managing projects?
Question 5 Principled negotiation emphasizes developing win/win solutions while protecting
yourself against those who would take advantage of your forthrightness. Which of the following is
NOT one of the key points of principled negotiation?
Question 6 A partnering charter states the common goals for the project as well as the
procedures that will be used to achieve these goals.
Question 7 What does the acronym BATNA stand for?
Question 8 When considering principled negotiation, both buyers and sellers relying on the blue
book to establish price parameters of a used car would be an example of
Question 9 Jessica just received the following information on her project: PV = 200, EV = 3 00, AC
= 250, BAC = 1500, EAC = 1208. In terms of cost at completion.
Question 10 Which of the following is NOT true regarding scope creep?
Question 11 Because of their easytounderstand visual format, tracking Gantt charts are the most
favored, used, and understandable option for reporting project status.
Question 12 The cost variance for a project is calculated by
Question 13 A ___________ Gantt chart is a simple and effective way to depict progress on a project.
Question 14 A project control system allows for comparing actual performance against plan to
identify deviations; however, the system doesn't impact the quality of communication between
stakeholders.
Question 15 Which of the following are required to assess the current status of a project us ing
the earnedvalue cost/schedule system?
Question 16 A CPI or SPI value less than one indicates that the project is
Question 17 Project closures can fall into all of the following categories EXCEPT
Question 18 Assessing what fundamental organizational culture properties affect project successes
and failures, or become a hindrance to project teams, is a part of the retrospectives methodology.
Question 19 In organizations where projects are managed within a ____________, the team
member's area manager, not the project manager, is responsible for assessing performance.
Question 20 Which part of the final report is designed to be the most useful on future projects?
Question 21 During the closing phase, the project manager's challenge is to keep the project
team focused on the remaining project activities and delivery to the customer until the project is
complete.
Question 22 Which of the following would NOT be appropriate to assess when evaluating team
performance?
Question 23 The final report typically includes profit made on the project.
Question 24 A 360degree performance evaluation includes feedback from peers, project managers,
subordinates, and even customers.
Question 25 Performance appraisals generally fulfill two functions. The first is to identify individual
strengths and weaknesses and to develop action plans for improving performance. The second
involves salary or merit adjustments. Why should these two functions be addressed at different
times?
1. Contracting project work has long been the norm in the _______ industry.
A. Telecommunications
B. Financial
C. Insurance
D. Construction
E. Retail
2. The process for the transferring of business functions or processes to other, often foreign,
companies has traditionally been known as:
A. Subcontracting
B. Downsizing
C. Partnering
D. Joint venture
E. Outsourcing
3. When you call your Internet provider to solve a technical problem and you end up talking to a
technician in India or Romania, you have just experienced:
A. Telecommunications
B. Partnering
C. Outsourcing
D. Service shift
E. Bilingual customer service
4. Which of the following is not a potential part of the outsourcing concept?
A. Computers
B. Faxes
C. Computer-aided design systems
D. Video teleconferencing
E. All the above are correct
5. Advantages of outsourcing project work may likely include all of the following except
A. Shortened project completion
B. Reduced costs
C. Higher level of expertise
D. Reduced conflict
E. Increased flexibility
6. Disadvantages of outsourcing project work may likely include all of the following except
A. Increased conflict
B. Coordination breakdowns
C. Increased costs
D. Loss of control
E. More internal morale issues
7. The driving motive for increasing the use of outsourcing on projects was:
A. Reducing the trade deficit
B. Reducing costs
C. Improving international sales
D. Making products more international in design
E. Securing technology that was not available domestically
8. Recent outsourcing trends have shown an increasing emphasis on the suppliers for all of the
following except:
A. Further cost reductions
B. Increased quality of work performed
C. Increased ability to collaborate
D. Increased ability to work together
E. All of these are recent trends
9. Key practices in partnering relationships include:
A. Single project contracting
B. Goals and objectives are similar
C. Access to each other's organizational resources
D. Both B and C are correct
E. A, B, and C are all correct
10. In the "Competing against the Giants" Snapshot from Practice, SATT Control uses which of the
following to successfully compete against much larger competitors?
A. Excellent project management
B. Acts as a system integrator
C. Using the same subsystem vendors again and again
D. Both A and B are correct
E. A, B, and C are all correct
11. hich of the following is not a key to successful partnering relationships?
A. Mutual trust
B. Jointly shared risk
C. Total company involvement
D. Independent project teams
E. Long-term commitment
12. Which of the following is part of the traditional project process?
A. Structured communications
B. Long-term commitment
C. Total company involvement
D. Both A and B are correct
E. A, B, and C are all correct
13. The traditional project process includes all of the following except:
A. Independent project teams
B. Shared goals and objectives
C. Single project teams
D. Risk is transferred to the other party
E. Limited objectivity
14. Which of the following did the state of Ohio do before starting a bond-financed school
construction project?
A. Create a specific RFP (request for proposal)
B. Have a dress rehearsal
C. Reviews the performance of contractors on past projects
D. Both A and C are correct
E. A, B, and C are all correct
15. Best practices in outsourcing project work include all the following except:
A. Well defined requirements and procedures
B. Training and teambuilding activities
C. Well established conflict management processes
D. Frequent reviews and status updates
E. All of these are best practices
16. In the Snapshot from Practice "Strategies for Communicating with Outsourcers," which of the
following was not one of the suggested strategies?
A. Recognize cultural differences
B. Use a translator to make sure everyone understands
C. Choose the right words
D. Confirm your requirements
E. Set deadlines
17. To make sure that an outsourcer thoroughly understands your requirements you should:
A. Document your conversations in writing
B. Insist that the outsourcer write the requirements in their own words
C. Request they build a prototype
D. Both A and C are correct
E. A, B, and C are all correct
18. The result of teambuilding among the project's participants is a:
A. Signed contract
B. Legal partnership agreement
C. Project plan
D. Partnering charter
E. Responsibility matrix
19. To avoid problems with schedules and deadlines you should:
A. Develop detailed schedules
B. Hold frequent status reviews
C. Add a penalty clause to the contract
D. Hold frequent conversations with the outsourcer
E. Build extra time into the schedules that the outsourcer is not aware of
20. Among the many advantages for establishing long-term partnerships are:
A. Reduced administrative costs
B. Improved performance
C. Improved communication
D. B and C are both correct
E. A, B, and C are all correct
21. Long-term partnerships will provide all the following except:
A. Improved communication
B. More efficient utilization of resources
C. Reduced need for total number of partnerships
D. Lower administrative costs
E. Improved innovation
22. Teambuilding between partners should:
A. Include engineers, architects, lawyers, specialists and other staff
B. Be facilitated by an outside consultant
C. Not take more than one day
D. A and B are both correct
E. A, B, and C are all correct
23. Which of the following would be included in best practices in outsourcing project work?
A. Establishing long-term relationships
B. Include financial incentives
C. Reduce costs by using tried and true methods
D. A and B are both correct
E. A, B, and C are all correct
24. In the Snapshot from Practice dealing with the Value Engineering Awards program, which
branch of the U.S. government was involved?
A. Department of Defense
B. Department of Commerce
C. Department of Transportation
D. N.A.S.A
E. Department of Education
25. Which of the following is not one of the key points of principled negotiation?
A. Use objective criteria when possible
B. Be honest and forthright
C. Focus on interests, not positions
D. Separate the people from the problem
E. Invent options for mutual gain
26. Customer satisfaction can be quantitified by:
A. Perceived performance divided by actual performance
B. Actual performance divided by expected performance
C. Perceived performance divided by expected performance
D. Actual performance divided by perceived performance
E. Expected performance divided by actual performance
27. Which of the following is a part of the noncompetitive view of negotiation?
A. Reaching an agreement
B. Implementation phase
C. Review of the completed project
D. Both A and B are correct
E. A, B, and C are all correct
28. Which of the following is suggested as the best target for a customer satisfaction ratio?
A. 1.00
B. 1.05
C. 1.10
D. 1.20
E. 1.50
29. In the research highlight on IT project managers, which of the following was not one of the
roles taken by project managers?
A. Entrepreneur
B. Politician
C. Friend
D. Marketer
E. Auditor
30. Regarding customer relations, advice passed on by veteran project managers includes:
A. Speak with one voice
B. Speak in precise terms
C. Speak the language of the customer
D. Both A and B are correct
E. Both A and C are correct
31. Which of the following is not one of the elements of good negotiation?
A. Be hard on the problem, soft on the people
B. Conflict on a project can be good
C. Negotiation is not a contest
D. Seek first to understand, then to be understood
E. All of these are elements of good negotiation
32. Which of the following is reflected in the saying "Let anger fly out the window"?
A. Separate people from the problem
B. Be honest
C. Focus on interests, not positions
D. Invent options for mutual gain
E. When possible, use objective criteria
33. Which of the following is reflected in the saying "Seek first to understand, then to be
understood"?
A. Separate people from the problem
B. Be honest
C. Focus on interests, not positions
D. Invent options for mutual gain
E. When possible, use objective criteria
34. The dovetailing technique is used in which of the following keys to good negotiation?
A. Separate people from the problem
B. Be honest
C. Focus on interests, not positions
D. Invent options for mutual gain
E. When possible, use objective criteria
35. Contracting project work has long been the norm in the __________ industry.
36. The __________ project, which created a transportation tunnel between France and England,
involved more than 250 organizations.
37. In a partnering relationship, ________ is shared jointly among the partners, which encourages
innovation and continuous improvement.
38. In a partnering relationship, ________ forms the basis for strong working relationships.
39. In traditional project relationships, ________ is limited due to fear of reprisal and lack of
continuous improvement opportunity.
40. In traditional project relationships, ________ are structured and guarded.
41. In Ohio before starting a bond-financed ____________, projects management consultants and
the related parties get together to figure out how to talk to each others and how to handle
problems.
42. The term __________ has traditionally been applied to the transferring of business functions or
processes to other, often foreign, companies.
43. Many outsourced projects operate in a _________ environment in which people are linked by
computers, faxes, computer-aided design systems, and video teleconferencing.
44. __________ is a major advantage of outsourcing project work because companies can secure
competitive prices for contracted services, especially if the work can be outsourced offshore.
45. Not only can contracted project work be cheaper, it can also be done __________.
46. High levels of __________ and technology can be brought to bear on a project by using
contracted services.
47. Contracting project services can increase a firm's _________ by no longer being constrained by
their own resources.
48. Breakdowns in __________ of professionals from different organizations can occur if the project
work requires close collaboration and mutual adjustment.
49. In the Snapshot from Practice involving SATT Control, a Swedish electronics firm, the company
referred to one of its competencies as being a ________ who subcontracts the subsystems to other
firms.
50. There is a potential loss of __________ over a project when the core team depends on other
organizations that they do not have direct authority over.
51. Projects are more prone to interpersonal _________ because the different participants do not
share the same values, priorities, and culture.
52. There is little disagreement that __________ was the primary motive behind outsourcing project
work.
53. Fisher and Ury champion the ________ approach to negotiation because it emphasizes win/win
solutions while protecting yourself against those who would take advantage of your
forthrightness.
54. ________ satisfaction is measured by the ratio of perceived performance to expected
performance.
55. The best defense against unreasonable, win/lose negotiators is having what Fisher and Ury call
a strong __________.
56. As part of an effort to cut costs the United States Department of Defense issues annual
__________.
57. "Let anger fly out of the window" is an example of the ___________ key point of negotiation.
58. Explaining why a critical task must be done by a specific time is an example of the ___________
key point of negotiation.
59. Dividing perceived performance by expected performance will calculate __________.
60. Toyota and Daimen-Chrysler collaborating with suppliers to develop new automobile platforms
is an example of outsourcing.
61. Participants from different organizations working close together at the construction site or in
shared office space is an example of a virtual team.
62. Working in outsourcing teams, projects can be completed faster and more cheaply.
63. Increased conflict and loss of coordination are typical disadvantages of outsourcing project
work.
64. Trust can be difficult to forge when interactions are limited and people come from different
organizations.
65. In partnering, access to each other's organization resources is available.
66. In the traditional method of managing projects, total company involvement requires
commitment from CEO to team members.
67. In partnering, each party's goals and objectives are similar but geared to what is best for them.
68. As part of an effort to cut costs, the United States Department of Defense issues annual Value
Engineering Awards.
69. In some countries, laws are considered to be guidelines that are not necessarily followed.
70. For people in some countries, a written, signed contract is merely a suggestion.
71. Because English is the language of business, it is not necessary to speak in a direct manner
using short sentences made of basic, simple words as this may taken as an insult.
72. All conversations with outsourcers should be followed up with commitments documented in
writing since they are likely to understand written English better than spoken English.
73. Experience indicates that co-location of project teams is not worth the extra costs.
74. A partnering charter states the common goals for the project as well as the procedures that
will be used to achieve these goals.
75. It is a good idea to add a penalty clause to an outsourcing agreement because deadlines are
often taken as a suggestion rather than a commitment.
76. A prime consideration in choosing outsourcing vendors is to assess the fit with their project
management system.
77. Team-building workshops with outsourcing vendors is usually led by an outside consultant
who is an expert in designing and facilitating such workshops.
78. In project negotiation each negotiator is out to win as much as he or she can for their side.
79. Principled Negotiation emphasizes developing win/win solutions while protecting yourself
against those who would take advantage of your forthrightness.
80. By keeping the focus on the issues and not the personalities, negotiators are better able to let
the other person blow off steam.
81. The best defense against unreasonable, win/lose negotiators is having what Fisher and Ury call
a strong BATNA.
82. A value of 1.5 is the accepted target for the Met-Expectations model of customer satisfaction.
1. A project monitoring system involves all of the following EXCEPT
A. Determining what data to collect
B. Determining how, when, and who will collect the data
C. Adjusting the data
D. Analysis of the data
E. Reporting current progress
2. Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for
each $1 worth of scheduled work. Nancy got this information from viewing the
A. SV
B. TCPI
C. CPI
D. SPI
E. PCIB
3. Jessica just received the following information on her project: PV = 200, EV = 300, AC = 250,
BAC = 1500, EAC = 1208. In terms of cost at completion
A. The project will currently finish under budget
B. The project will currently finish over budget
C. The project will currently finish on budget
D. The project will currently finish behind schedule
E. There is insufficient information to draw conclusions
4. The first step in the project control process for measuring and evaluating project performance
is to
A. Set a baseline plan
B. Determine the project objectives
C. Determine the project deliverables
D. Analyze the project budget
E. Review the project priority matrix
5. The second step in the project control process for measuring and evaluating project
performance is to
A. Review the baseline plan with top management
B. Analyze inputs to control system
C. Compare plan against actual
D. Measure progress and performance
E. Review spending with team members
6. The third step in the project control process for measuring and evaluating project performance
is to
A. Review the baseline plan with top management
B. Analyze inputs to the control system
C. Compare the plan against actual performance
D. Measure both progress and performance
E. Review spending with team members
7. The final step in the project control process for measuring and evaluating project performance
is to
A. Take appropriate action
B. Prepare a report to top management
C. Follow up on corrective action
D. Measure progress and performance
E. Review spending with team members
8. In monitoring project time (schedule) performance, actual performance should be compared to
A. Budgets for the current year
B. Top management's targets
C. Project network schedule derived from the WBS/OBS
D. Progress on similar past projects
E. Previous status reports
9. A ___________ Gantt chart is a simple and effective way to depict progress on a project.
A. Baseline
B. Control
C. Variance
D. Tracking
E. Simple
10. A tool used to monitor past project schedule performance and current performance, and to
estimate future schedule trends is a simple line chart known as a
A. Project schedule control chart
B. Gantt chart
C. PERT chart
D. Network diagram
E. Milestone chart
11. The earned value system starts with the time-phased costs that provide the project baseline,
which is called the
A. Planned budgeted value of work scheduled
B. Planned budgeted value of work completed
C. Earned value of work scheduled
D. Scheduled value of work scheduled
E. Scheduled value of work completed
12. The earned value of a project is the
A. Project cost to date adjusted for project scope changes
B. Total project cost to date
C. Cost incurred minus the planned cost
D. Percent of the original budget that has been earned by actual work
E. The planned time-phased baseline of the value of work scheduled
13. The cost variance for a project is calculated by
A. EV - AC
B. AC - SV
C. PV - EV
D. CU - EV
E. EU - PV
14. The schedule variance for a project is calculated by:
A. EV - AC
B. AC - SV
C. PV - EV
D. CU - EV
E. EV - PV
15. Baseline project budgets are derived from
A. The organization's overall budget
B. Time-phasing the work packages
C. Top management directions
D. The total direct, direct project overhead and G&A overhead costs
E. The earned value system
16. Of the following costs, which are NOT included in baseline?
A. Suppliers
B. Equipment
C. Labor
D. Budget reserves
E. Contractors
17. When someone familiar with each task estimates what percent of the task has been
completed or how much of the task remains, they are creating a method for assigning costs to
the baseline called the
A. 0/100 percent rule
B. Task complete rule
C. Degree complete rule
D. Work complete rule
E. Percent complete rule
18. Which performance index is the most potentially misleading?
A. CPI
B. EV
C. CV
D. SV
E. EAC
19. Which of the following are required to assess the current status of a project using the earned-
value cost/schedule system?
A. BAC, EAC, and ETC
B. VAC, EAC, and BAC
C. CV, SU, and BAC
D. PV, EV, and AC
E. TCPI, EV, and PV
20. Which of the following methods of variance analysis is the best indicator of how far off the
budget a project will be at completion?
A. BAC
B. EAC
C. ETC
D. VAC
E. TCPI
21. Which of the following methods will measure the cost efficiency of the work accomplished to
date?
A. SV/CV
B. EV/PV
C. EV/AC
D. AC/SV
E. AC/CV
22. Which of the following methods will measure the scheduling efficiency of the work
accomplished to date?
A. SV/CV
B. EV/PV
C. EV/AC
D. AC/SV
E. AC/CV
23. A CPI or SPI value less than one indicates that the project is
A. Under cost or behind schedule
B. Over cost or ahead of schedule
C. Under cost or ahead of schedule
D. Over cost or behind schedule
E. On cost or on schedule
24. The value that tells you the planned value of work that has actually been completed is the
A. SV
B. PV
C. EV
D. AC
E. CV
25. The indicator that tells you the amount each remaining dollar must earn in order for the
project to stay within budget is the
A. PCIC
B. VAC
C. CPI
D. SPI
E. TCPI
26. A project manager learns that the project is only earning $.90 of planned work for each dollar
spent by looking at the
A. EV
B. BAC
C. SV
D. SPI
E. CPI
27. A project manager notices that $1,000 worth of work that was scheduled to be completed at
this time has not been accomplished. They know this by looking at the
A. EV
B. TCPI
C. SV
D. PCIB
E. EAC
28. Sally receives the following information on her project: PV = 100, AC = 75, EV = 100. How
well is the project doing in terms of budget?
A. Right on budget
B. 25 under budget
C. 25 over budget
D. 50 under budget
E. 50 over budget
29. Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC =
2000, EAC = 1333. How is the project doing in terms of schedule?
A. More work has been done than planned
B. Less work has been done than planned
C. The same amount of work has been done than planned
D. The project has cost less than planned
E. There is not enough information to draw a conclusion
30. Which of the following is NOT true regarding scope creep?
A. It commonly occurs late in projects
B. It is frequently unnoticed until time delays or cost overruns are observed
C. It wears down team motivation and cohesiveness
D. Project suppliers resent frequent changes
E. Scope changes can represent significant opportunity
31. ________ holds people accountable, prevents small problems from mushrooming into large
problems, and keeps focus.
32. The first step in creating a project control system for measuring and evaluating project
performance is to set a ________.
33. The value that tells you the planned value of the actual work completed is ___________.
34. When someone familiar with each task estimates what percent of the task has been
completed or how much of the task remains, they are creating a method for assigning costs to
the baseline called the ____________ rule.
35. Because of their easy-to-understand visual format, ________ charts are the most favored, used,
and understandable tool used to report project schedule status.
36. The indicator that tells you the planned time-phased value of the work that is scheduled is the
_______________.
37. Baseline project budgets are derived from time-phasing the work ________.
38. The ________ variance is the difference between the earned value and the actual costs for the
work completed to date.
39. The ________ variance is the difference between the earned value to date and the baseline
schedule.
40. ________ is simply the percent complete times the original budget.
41. Conditions or scope can change, which, in turn, will require a change to the __________ plan to
recognize the new information.
42. The project network schedule is derived from the _______ and it serves as the baseline to
compare against actual performance.
43. A negative CV indicates the project is ________ budget.
44. The ________ rule assumes credit is earned for having performed the work once it is completed.
This rule is usually used for work packages having very short durations.
45. The ratio that measures the amount of value each remaining dollar in the budget must earn
to stay within the budget is the _________.
46. The _________ index measures the project percent complete in relation to the resources that
were budgeted.
47. Given that the AC = 300, PV = 400 and EV = 500, this project is _________ budget.
48. Given a BAC of 5,500 and an EAC of 6,000, the project is expected to be completed _________
budget.
49. An SPI index of 1.22 indicates that the project is ________ schedule.
50. Although it is very difficult to measure, measuring ________ performance is as important as
measuring schedule and cost performance.
51. The final step in the project control process for measuring and evaluating project performance
is to take appropriate ________.
52. In some cases, conditions or scope can change, which, in turn, will require a change in the
baseline plan to recognize new information.
53. The PCIC index measures the project percent complete in relation to the resources that have
actually been used so far on the project.
54. The only accurate method for determining the true time progress of the project is to compare
the project network schedule against the actual network schedule to measure if the project is on
time.
55. Schedule variance measures progress in time units.
56. Earned value is defined as the budgeted cost of the actual work performed.
57. The baseline is derived from merging information from the work packages with the project
network.
58. Because of their easy-to-understand visual format, tracking Gantt charts are the most favored,
used, and understandable option for reporting project status.
59. The PV, AC and CV are all required to assess the current status of the project.
60. When revising the estimated cost at completion, there are two approaches. The EACre is
determined by experts in the field and the EACf is a mathematical approach which assumes the
CPI as the basis for forecasting cost at completion.
61. The best method for assigning costs to the baseline under the 50/50 rule is to establish
frequent checkpoints over the duration of the work package and assign completion percentages
in dollar terms.
62. Most changes will not result in serious scope changes and should be absorbed as positive or
negative variances.
63. A “rubber baseline” occurs when, in an effort to disguise poor performance, the baseline
changes to constantly match results.
64. Baseline costs typically include labor, equipment, materials and direct overhead cost.
65. A project control system allows for comparing actual performance against plan to identify
deviations; however, the system doesn’t impact the quality of communication between
stakeholders.
66. Two major reasons for creating a baseline are to monitor and report progress and to estimate
cash flow.
67. In calculating schedule variance and cost variance, a negative variance indicates a desirable
condition, and a positive variance suggests problems.
68. An undesirable schedule variance always indicates that the project is running behind
schedule.
69. Progress and performance can be measured quantitatively as well as qualitatively.
70. A CPI index of 0.97 indicates that the project has spent less money than budgeted.
71. Rachel notices that the current EV for her project is higher than both the PV and the AC.
Rachel has reason to be concerned.
72. All scope changes that result in increased costs should be avoided.
73. Although it is very difficult to measure, measuring technical performance is as important as
measuring schedule and cost performance.
74. Deciding what data to collect, actually collecting the data and analyzing it, and reporting this
data are all parts of structuring a project monitoring information system.
75. A project manager would be glad to see a TCPI of 1.07.
76. A negative VAC indicates that the project will be completed over budget.
1. The most common circumstance for project closure is simply a ________ project.
A. Completed
B. Overdue
C. Over-budget
D. Underachieving
E. Successful
2. Which of the following is NOT a wrap-up closure activity that might be found on a checklist?
A. Getting delivery acceptance from the customer
B. Reassigning project team members
C. Closing accounts and seeing all bills are paid
D. Evaluation of team performance
E. Creating a final report
3. __________ of lessons learned are designed to improve performance on current and future
projects.
A. Retrospectives
B. Corrective action plans
C. Introspectives
D. Culminations
E. Evolutions
4. The content of the final report typically includes the following topics EXCEPT
A. Lessons learned
B. Review and analysis
C. Recommendations
D. Executive summary
E. Team reviews
5. When the project may be completed early with some parts of the project eliminated this is
considered to be ___________ closure.
A. Normal
B. Premature
C. Perpetual
D. Changed Priority
E. Failed Project
6. This type of closure occurs when the project may never seem to end. At some point the review
group should recommend methods for bringing final closure to this type of project. This is
considered to be ___________ closure.
A. Normal
B. Premature
C. Perpetual
D. Changed Priority
E. Failed Project
7. Because of circumstances beyond the control of the project team, many projects are easy for a
review group to close down. This type of project closure is called
A. Normal
B. Premature
C. Perpetual
D. Failed Project
E. Changed Priority
8. When a project starts with a high priority but it is cancelled because its rank erodes or crashes
during its project life cycle, this is an example of what type of project closure?
A. Normal
B. Premature
C. Perpetual
D. Failed Project
E. Changed Priority
9. Which of the following summarizes project performance and provides useful information for
continuous improvement?
A. Customer acceptance
B. The final report
C. Team evaluation
D. 360-degree feedback
E. Project summary
10. Which part of the final report highlights the key findings and facts relating to the project
implementation?
A. Executive summary
B. Review and analysis
C. Recommendations
D. Lessons learned
E. Appendix
11. Which part of the final report examines in detail the underlying causes of problems, issues,
and successes relative to the project and includes concise, factual review statements of the project?
A. Executive summary
B. Review and analysis
C. Recommendations
D. Lessons learned
E. Appendix
12. Which part of the final report presents major improvement actions that should be made?
A. Executive summary
B. Review and analysis
C. Recommendations
D. Lessons learned
E. Appendix
13. Which part of the final report is designed to be the most useful on future projects?
A. Executive summary
B. Review and analysis
C. Recommendations
D. Lessons learned
E. Appendix
14. Which part of the final report includes backup data or details of analysis that would allow
others to follow up if they wished?
A. Executive summary
B. Review and analysis
C. Recommendations
D. Lessons learned
E. Appendix
15. The purpose of project evaluation is to assess how well
A. The project team performed
B. The team members performed
C. The project manager performed
D. The project team and team members performed
E. The project team, team members and the project manager performed
16. Which of the following would NOT be appropriate to assess when evaluating team
performance?
A. How well the team performed in terms of time, cost, and specifications
B. Effectiveness of group decisions
C. Individual strengths and weaknesses
D. Customer satisfaction with project deliverables
E. Trust among group members
17. Before an evaluation of the project team can be effective and useful, a minimum core of
conditions needs to be in place before the project begins. Which of the following would NOT be
one of those conditions?
A. Individuals have the skillset necessar y to successfully complete the project
B. Evaluation criteria beyond time, cost and specifications has been established
C. Rewards are adequate
D. Individual and team responsibilities and performance standards are known by all team
members
E. Standards for measuring performance exist
18. Performance appraisals generally fulfill two functions. The first is to identify individual
strengths and weaknesses and to develop action plans for improving performance. The second
involves salary or merit adjustments. Why should these two functions be addressed at different
times?
A. It is too much information to discuss at once
B. Employees are so eager to learn about a potential raise that they tend to tune out constructive
feedback
C. Managers tend to spend too much time talking about how the employee can improve his or
her performance and not on justifying the salary adjustment
D. If employees are upset over a salary adjustment, they will not be open to listening to ways they
can improve.
E. If the manager is giving employees bad news regarding their salary adjustment, they will not be
honest about the employees’ weaknesses and will tend to focus on their strengths.
19. The following are general tips for conducting performance reviews EXCEPT
A. Begin the process by asking the individual to evaluate his or her own contributions to the
project
B. Use other team members’ performance as a method to compare and evaluate
C. When you have to be critical, focus the criticism on specific examples of behavior and not on
the individual personally
D. Be fair and consistent in your treatment of all team members
E. Treat the review as only one point in an ongoing process
20. An analysis carried out during and shortly after the project life cycle that attempts to capture
positive and negative learning is represented in which of the following?
A. Scenario analysis
B. Variance analyses
C. Lessons learned
D. Performance evaluation
E. Strategic objectives
21. The process for capturing lessons learned continues to evolve, but there are still many barriers
to effectively capitalizing on lessons learned that have been identified. The following are
examples of these barriers EXCEPT
A. Lack of time
B. Teams get little direction or support after lessons are reported
C. Lessons learned often degenerate into blame sessions
D. Lessons learned are being used across different locations
E. The organizational culture doesn’t support the effort that it takes to capitalize on lessons
learned
22. The following are distinguishing characteristics of retrospectives methodology EXCEPT
A. Uses an independent facilitator
B. Establishes in-process learning gates during the project life cycle
C. An owner, typically a team member, is assigned
D. Reviews cannot be linked to percent complete
E. A repository is developed that is easy to use
23. Project closures can fall into all of the following categories EXCEPT
A. Premature
B. Perpetual
C. Failed
D. Changed priority
E. Successful
24. A guide who leads the project team through an analysis of project activities that went well
and of what needs improvement and development of a follow-up action plan with goals and
accountability is a(n)
A. Owner
B. Project sponsor
C. Project manager
D. Facilitator
E. Mediator
25. It is imperative that the closure facilitator possess the following characteristics EXCEPT
A. Has direct involvement or direct interest in the project
B. Is perceived as impartial and fair
C. Has respect for senior management and other project stakeholders
D. Willing to listen
E. Is perceived as having the best interests of the organization in making decisions
26. The typical mechanism for the evaluation of teams is normally
A. A survey completed by the team members
B. A personal interview of each team member
C. An analysis by an outside consultant
D. A survey completed by members of top management
E. A survey completed by the internal or external customers
27. More and more companies are discarding the traditional superior-subordinate performance
feedback process and replacing it with a multi-rater appraisal called
A. Critical incidences review
B. Management by objectives
C. The 360-degree feedback
D. Team evaluation survey
E. Retrospectives
28. Which of the following is NOT a role of the closure facilitator?
A. Create an environment in which stakeholders feel safe to provide input
B. Lead the team in exploring new ways for solving problems
C. Use several questionnaires as a starting point to conduct the post-project retrospective
D. Get delivery acceptance from the customer
E. Elicit a 360-degree view and input from all stakeholders to create a more complete picture of
project issues
29. In organizations where projects are managed within a ____________, the team member's area
manager, not the project manager, is responsible for assessing performance.
A. Functional organization
B. Matrix organization
C. Flat organization
D. Project organization
E. Strong organization
30. Each retrospective is assigned a(n) _________, typically a team member who is very interested in
and familiar with the retrospective. This individual will serve as the contact point for anyone
needing information relating to the retrospective.
A. Owner
B. Project sponsor
C. Project manager
D. Facilitator
E. Mediator
31. ________ project closure is the most common circumstance for project closure and is simply a
completed project.
32. When a project is completed early with some parts of the project eliminated this is known as
_________ project closure.
33. A ____________ project closure is usually easy to identify and easy for a review group to close
down.
34. Projects in process may need to be altered or canceled. Thus, a project may start with a high
priority but see its rank erode or crash during its project life cycle as conditions change. This is
called __________project closure.
35. When the review group recommends methods for bringing final closure to a project that
never seems it will end, this is an example of a ________ project closure.
36. Within the final report, a summary that simply highlights the key findings and facts relating to
project implementation is called the ___________ summary.
37. Implementing the closure process includes several _______ activities, including getting delivery
acceptance from the customer.
38. The ________ section of the final project report includes concise, factual review statements of
the project, such as project mission and objectives, procedures and systems used, and
organizational resources used.
39. Perhaps the_________ section of the final report is the most valuable contribution of the closure
process.
40. The ________ section of the final project report is often technical in nature and focuses on
solutions to problems that surfaced.
41. Within the final report, the ___________ may include backup data or details of analysis that
would allow others to follow up if they wish.
42. The purpose of project __________ is to assess how well the project team, team members, and
project manager performed.
43. ____________ of performance is essential to encourage changes in behavior and to support
individual career development and continuous improvement through organizational learning.
44. The ________ feedback approach gathers anonymous feedback solicited from others that is
compared with the individual's self-evaluations.
45. The typical mechanism for evaluation of teams is a ________ administered by a consultant.
46. The retrospective approach stresses gathering _____________ during project execution and using
them to change remaining work.
47. In organizations where projects are managed within a functional organization, the team
member’s __________ manager is responsible for assessing performance.
48. The most common reason given for not creating lessons learned is the lack of _________.
49. A ________ is a methodology that analyzes a past project event to determine what worked and
what didn't, develop lessons learned, and create an action plan that ensures lessons learned are
used to improve management of future projects.
50. Retrospective reviews should be set up in the project ___________ stage.
51. The ____________ report summarizes project performance and provides useful information for
continuous improvement.
52. A guide who leads the project team through an analysis of project activities that went well
and of what needs improvement and development of a follow-up action plan with goals and
accountability is known as a project ____________.
53. __________ represent an analysis carried out during and shortly after the project life cycle; they
attempt to capture positive and negative project learning.
54. Each retrospective is assigned a(n) __________, typically a team member who is very interested
in and familiar with the retrospective.
55. Motivation can be the chief challenge when wrapping up closure activities. 56. In premature
project closure, the project may be completed early with some parts of the project eliminated.
57. Retrospectives of lessons learned are designed to improve performance on current and future
projects.
58. When a project starts as a high priority but its rank erodes or crashes during its project life
cycle resulting in closure of the project, this is an example of changed priority project closure.
59. The final report typically includes profit made on the project.
60. The project manager's challenge is to keep the project team focused on the remaining project
activities and delivery to the customer until the project is complete.
61. Implementing project closure includes getting delivery acceptance from the customer.
62. Within the final report, the project summary is the summary that simply highlights the key
findings and facts relating to the project implementation.
63. Expectations, standards, supportive organizational culture, and constraints must be in place
before project implementation; if not, the effectiveness of the evaluation process will suffer.
64. Evaluation of performance is essential to encourage changes in behavior and to support
individual career development and continuous improvement through organizational learning.
65. The processes for capturing lessons learned continue to evolve, but there are still barriers to
effectively mining lessons learned.
66. Project managers should wait to give feedback to the project team and team members until
the project has been completed. Giving feedback throughout the project can distract project
teams.
67. Assessing what fundamental organizational culture properties affect project successes and
failures, or become a hindrance to project teams, is a part of the retrospectives methodology.
68. In organizations where projects are managed within a functional organization, the team
member’s area manager, not the project manager, is responsible for assessing performance.
69. The most common circumstance for project closure is simply a completed project such as
building a new facility or creating a customized information system.
70. A project closure where the project is completed early with some parts of the project
eliminated would be classified as a failed project.
71. The key requirement in selection of the facilitator is one who is the end-user.
72. The retrospective facilitator should be able to deliver bad news to the project sponsor or
senior management without recriminations.
73. Retrospective methodology is one positive step toward ensuring lessons learned are
developed and implemented.
74. A 360-degree performance evaluation includes feedback from peers, project managers,
subordinates, and even customers.
75. Project managers should, when possible, draw comparisons to other team members when
conducting individual team member reviews.
76. The retrospective methodology is more inclusive and disciplined than past lessons learned
approaches.

More Related Content

What's hot (18)

Pmp Questions and Answers series #1
Pmp Questions and Answers series #1Pmp Questions and Answers series #1
Pmp Questions and Answers series #1
 
PMI-RMP Handbook
PMI-RMP HandbookPMI-RMP Handbook
PMI-RMP Handbook
 
Pmstudy exam_1
Pmstudy exam_1Pmstudy exam_1
Pmstudy exam_1
 
Free PMP® Exam Sample Question
Free PMP® Exam Sample QuestionFree PMP® Exam Sample Question
Free PMP® Exam Sample Question
 
Pmp questions and answers series #2
Pmp questions and answers series #2Pmp questions and answers series #2
Pmp questions and answers series #2
 
PgMP
PgMP PgMP
PgMP
 
PMP assessment exam 1.1
PMP assessment exam 1.1PMP assessment exam 1.1
PMP assessment exam 1.1
 
Pmp test 02
Pmp test 02Pmp test 02
Pmp test 02
 
Pmp full mock test – 200 questions
Pmp full mock test – 200 questionsPmp full mock test – 200 questions
Pmp full mock test – 200 questions
 
Pmp test 03
Pmp test 03Pmp test 03
Pmp test 03
 
10 pmp communication management exam
10 pmp communication  management exam10 pmp communication  management exam
10 pmp communication management exam
 
Pmi rmp
Pmi rmpPmi rmp
Pmi rmp
 
08 pmp quality management exam
08 pmp quality management exam08 pmp quality management exam
08 pmp quality management exam
 
PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360PMP 1600 Questions by TechFAQ360
PMP 1600 Questions by TechFAQ360
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
PMP Exam Sample Questions Set 4
PMP Exam Sample Questions Set 4PMP Exam Sample Questions Set 4
PMP Exam Sample Questions Set 4
 
PMP Sample Questions Set 3
PMP Sample Questions Set 3PMP Sample Questions Set 3
PMP Sample Questions Set 3
 
Project management
Project managementProject management
Project management
 

Similar to Liberty university busi 313 quiz 4 complete solutions correct answers slideshare

PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfMoncefMakni1
 
ipma-level-d-mcq-sample-paper.pdf
ipma-level-d-mcq-sample-paper.pdfipma-level-d-mcq-sample-paper.pdf
ipma-level-d-mcq-sample-paper.pdfClaudiaFernndez62
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxIRESH3
 
Question 1  Doing procurement functions electronically is termed.docx
Question 1  Doing procurement functions electronically is termed.docxQuestion 1  Doing procurement functions electronically is termed.docx
Question 1  Doing procurement functions electronically is termed.docxIRESH3
 
APMP More MC Questions
APMP More MC QuestionsAPMP More MC Questions
APMP More MC QuestionsMonica Waters
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfProject Cubicle
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions CompleteKareemBullard1
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docxjackiewalcutt
 
1) The term environment” includes all of the following exceptA) a.docx
1) The term environment” includes all of the following exceptA) a.docx1) The term environment” includes all of the following exceptA) a.docx
1) The term environment” includes all of the following exceptA) a.docxhirstcruz
 
Project ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docxProject ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docxwkyra78
 
Mgt 521 final exams
Mgt 521 final examsMgt 521 final exams
Mgt 521 final examsexamzking
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxalfred4lewis58146
 
LONG QUIZ. Operations management.pptx
LONG QUIZ. Operations management.pptxLONG QUIZ. Operations management.pptx
LONG QUIZ. Operations management.pptxJordan Cabaguing
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxIRESH3
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bankBaskar El
 

Similar to Liberty university busi 313 quiz 4 complete solutions correct answers slideshare (20)

PMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdfPMP Lite Mock Exam2.pdf
PMP Lite Mock Exam2.pdf
 
ipma-level-d-mcq-sample-paper.pdf
ipma-level-d-mcq-sample-paper.pdfipma-level-d-mcq-sample-paper.pdf
ipma-level-d-mcq-sample-paper.pdf
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
 
Question 1  Doing procurement functions electronically is termed.docx
Question 1  Doing procurement functions electronically is termed.docxQuestion 1  Doing procurement functions electronically is termed.docx
Question 1  Doing procurement functions electronically is termed.docx
 
Itpm question bank
Itpm   question bankItpm   question bank
Itpm question bank
 
APMP More MC Questions
APMP More MC QuestionsAPMP More MC Questions
APMP More MC Questions
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
 
Pmp Questions Complete
Pmp Questions CompletePmp Questions Complete
Pmp Questions Complete
 
1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx1.A cumulative effort curve for a project generally has an S-shap.docx
1.A cumulative effort curve for a project generally has an S-shap.docx
 
Pmp sample qa3
Pmp sample qa3Pmp sample qa3
Pmp sample qa3
 
150 PMP Questions
150 PMP Questions 150 PMP Questions
150 PMP Questions
 
1) The term environment” includes all of the following exceptA) a.docx
1) The term environment” includes all of the following exceptA) a.docx1) The term environment” includes all of the following exceptA) a.docx
1) The term environment” includes all of the following exceptA) a.docx
 
Free CAPM Exam Sample Q & A
Free CAPM Exam Sample Q & AFree CAPM Exam Sample Q & A
Free CAPM Exam Sample Q & A
 
Project ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docxProject ManagementECE 326 Exam 2Description Exam 2 question.docx
Project ManagementECE 326 Exam 2Description Exam 2 question.docx
 
Mgt 521 final exams
Mgt 521 final examsMgt 521 final exams
Mgt 521 final exams
 
Page 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docxPage 9Introduction to Project Management Principles and Practices.docx
Page 9Introduction to Project Management Principles and Practices.docx
 
LONG QUIZ. Operations management.pptx
LONG QUIZ. Operations management.pptxLONG QUIZ. Operations management.pptx
LONG QUIZ. Operations management.pptx
 
Question 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docxQuestion 1 A project manager has received the following probab.docx
Question 1 A project manager has received the following probab.docx
 
1440 pmp exam question bank
1440 pmp exam question bank1440 pmp exam question bank
1440 pmp exam question bank
 
Pmp test 05
Pmp test 05Pmp test 05
Pmp test 05
 

More from Song Love

Psyc 355 lab project overview and instructions complete solutions correct ans...
Psyc 355 lab project overview and instructions complete solutions correct ans...Psyc 355 lab project overview and instructions complete solutions correct ans...
Psyc 355 lab project overview and instructions complete solutions correct ans...Song Love
 
Economics 248 assignment 2 (version a) complete solutions correct answers key
Economics 248 assignment 2 (version a) complete solutions correct answers keyEconomics 248 assignment 2 (version a) complete solutions correct answers key
Economics 248 assignment 2 (version a) complete solutions correct answers keySong Love
 
Acc330 cumulative project complete solutions correct answers key
Acc330 cumulative project complete solutions correct answers keyAcc330 cumulative project complete solutions correct answers key
Acc330 cumulative project complete solutions correct answers keySong Love
 
Itm310 problem solving #7 complete solutions correct answers key
Itm310 problem solving #7 complete solutions correct answers keyItm310 problem solving #7 complete solutions correct answers key
Itm310 problem solving #7 complete solutions correct answers keySong Love
 
Case study instructions director’s request for p cs complete solutions correc...
Case study instructions director’s request for p cs complete solutions correc...Case study instructions director’s request for p cs complete solutions correc...
Case study instructions director’s request for p cs complete solutions correc...Song Love
 
Tutorial 8 based on lectures 22 24 (tg) complete solutions correct answers key
Tutorial 8 based on lectures 22 24 (tg) complete solutions correct answers keyTutorial 8 based on lectures 22 24 (tg) complete solutions correct answers key
Tutorial 8 based on lectures 22 24 (tg) complete solutions correct answers keySong Love
 
Statistics 141 homework 6 complete solutions correct answers key
Statistics 141 homework 6 complete solutions correct answers keyStatistics 141 homework 6 complete solutions correct answers key
Statistics 141 homework 6 complete solutions correct answers keySong Love
 
Ece175 computer programming for engineering applications homework assignment ...
Ece175 computer programming for engineering applications homework assignment ...Ece175 computer programming for engineering applications homework assignment ...
Ece175 computer programming for engineering applications homework assignment ...Song Love
 
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshareLiberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshareSong Love
 
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshareLiberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshareSong Love
 
Liberty university busi 311 quiz 8 complete solutions correct answers slideshare
Liberty university busi 311 quiz 8 complete solutions correct answers slideshareLiberty university busi 311 quiz 8 complete solutions correct answers slideshare
Liberty university busi 311 quiz 8 complete solutions correct answers slideshareSong Love
 
Liberty university busi 311 quiz 7 complete solutions correct answers slideshare
Liberty university busi 311 quiz 7 complete solutions correct answers slideshareLiberty university busi 311 quiz 7 complete solutions correct answers slideshare
Liberty university busi 311 quiz 7 complete solutions correct answers slideshareSong Love
 
Liberty university busi 311 quiz 5 complete solutions correct answers slideshare
Liberty university busi 311 quiz 5 complete solutions correct answers slideshareLiberty university busi 311 quiz 5 complete solutions correct answers slideshare
Liberty university busi 311 quiz 5 complete solutions correct answers slideshareSong Love
 
Liberty university busi 311 quiz 4 complete solutions correct answers slideshare
Liberty university busi 311 quiz 4 complete solutions correct answers slideshareLiberty university busi 311 quiz 4 complete solutions correct answers slideshare
Liberty university busi 311 quiz 4 complete solutions correct answers slideshareSong Love
 
Liberty university busi 311 quiz 3 complete solutions correct answers slideshare
Liberty university busi 311 quiz 3 complete solutions correct answers slideshareLiberty university busi 311 quiz 3 complete solutions correct answers slideshare
Liberty university busi 311 quiz 3 complete solutions correct answers slideshareSong Love
 
Psyc 355 spss homework 2 complete solutions correct answers key
Psyc 355 spss homework 2 complete solutions correct answers keyPsyc 355 spss homework 2 complete solutions correct answers key
Psyc 355 spss homework 2 complete solutions correct answers keySong Love
 
1 3 my statlab module one problem set complete solutions correct answers key
1 3 my statlab module one problem set complete solutions correct answers key1 3 my statlab module one problem set complete solutions correct answers key
1 3 my statlab module one problem set complete solutions correct answers keySong Love
 
Liberty university psyc 101 quiz 14 solutions answers slideshare
Liberty university psyc 101 quiz 14 solutions answers slideshareLiberty university psyc 101 quiz 14 solutions answers slideshare
Liberty university psyc 101 quiz 14 solutions answers slideshareSong Love
 
Liberty university psyc 101 quiz 13 solutions answers slideshare
Liberty university psyc 101 quiz 13 solutions answers slideshareLiberty university psyc 101 quiz 13 solutions answers slideshare
Liberty university psyc 101 quiz 13 solutions answers slideshareSong Love
 
Liberty university psyc 101 quiz 12 solutions answers slideshare
Liberty university psyc 101 quiz 12 solutions answers slideshareLiberty university psyc 101 quiz 12 solutions answers slideshare
Liberty university psyc 101 quiz 12 solutions answers slideshareSong Love
 

More from Song Love (20)

Psyc 355 lab project overview and instructions complete solutions correct ans...
Psyc 355 lab project overview and instructions complete solutions correct ans...Psyc 355 lab project overview and instructions complete solutions correct ans...
Psyc 355 lab project overview and instructions complete solutions correct ans...
 
Economics 248 assignment 2 (version a) complete solutions correct answers key
Economics 248 assignment 2 (version a) complete solutions correct answers keyEconomics 248 assignment 2 (version a) complete solutions correct answers key
Economics 248 assignment 2 (version a) complete solutions correct answers key
 
Acc330 cumulative project complete solutions correct answers key
Acc330 cumulative project complete solutions correct answers keyAcc330 cumulative project complete solutions correct answers key
Acc330 cumulative project complete solutions correct answers key
 
Itm310 problem solving #7 complete solutions correct answers key
Itm310 problem solving #7 complete solutions correct answers keyItm310 problem solving #7 complete solutions correct answers key
Itm310 problem solving #7 complete solutions correct answers key
 
Case study instructions director’s request for p cs complete solutions correc...
Case study instructions director’s request for p cs complete solutions correc...Case study instructions director’s request for p cs complete solutions correc...
Case study instructions director’s request for p cs complete solutions correc...
 
Tutorial 8 based on lectures 22 24 (tg) complete solutions correct answers key
Tutorial 8 based on lectures 22 24 (tg) complete solutions correct answers keyTutorial 8 based on lectures 22 24 (tg) complete solutions correct answers key
Tutorial 8 based on lectures 22 24 (tg) complete solutions correct answers key
 
Statistics 141 homework 6 complete solutions correct answers key
Statistics 141 homework 6 complete solutions correct answers keyStatistics 141 homework 6 complete solutions correct answers key
Statistics 141 homework 6 complete solutions correct answers key
 
Ece175 computer programming for engineering applications homework assignment ...
Ece175 computer programming for engineering applications homework assignment ...Ece175 computer programming for engineering applications homework assignment ...
Ece175 computer programming for engineering applications homework assignment ...
 
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshareLiberty university busi 313 quiz 3 complete solutions correct answers slideshare
Liberty university busi 313 quiz 3 complete solutions correct answers slideshare
 
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshareLiberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
 
Liberty university busi 311 quiz 8 complete solutions correct answers slideshare
Liberty university busi 311 quiz 8 complete solutions correct answers slideshareLiberty university busi 311 quiz 8 complete solutions correct answers slideshare
Liberty university busi 311 quiz 8 complete solutions correct answers slideshare
 
Liberty university busi 311 quiz 7 complete solutions correct answers slideshare
Liberty university busi 311 quiz 7 complete solutions correct answers slideshareLiberty university busi 311 quiz 7 complete solutions correct answers slideshare
Liberty university busi 311 quiz 7 complete solutions correct answers slideshare
 
Liberty university busi 311 quiz 5 complete solutions correct answers slideshare
Liberty university busi 311 quiz 5 complete solutions correct answers slideshareLiberty university busi 311 quiz 5 complete solutions correct answers slideshare
Liberty university busi 311 quiz 5 complete solutions correct answers slideshare
 
Liberty university busi 311 quiz 4 complete solutions correct answers slideshare
Liberty university busi 311 quiz 4 complete solutions correct answers slideshareLiberty university busi 311 quiz 4 complete solutions correct answers slideshare
Liberty university busi 311 quiz 4 complete solutions correct answers slideshare
 
Liberty university busi 311 quiz 3 complete solutions correct answers slideshare
Liberty university busi 311 quiz 3 complete solutions correct answers slideshareLiberty university busi 311 quiz 3 complete solutions correct answers slideshare
Liberty university busi 311 quiz 3 complete solutions correct answers slideshare
 
Psyc 355 spss homework 2 complete solutions correct answers key
Psyc 355 spss homework 2 complete solutions correct answers keyPsyc 355 spss homework 2 complete solutions correct answers key
Psyc 355 spss homework 2 complete solutions correct answers key
 
1 3 my statlab module one problem set complete solutions correct answers key
1 3 my statlab module one problem set complete solutions correct answers key1 3 my statlab module one problem set complete solutions correct answers key
1 3 my statlab module one problem set complete solutions correct answers key
 
Liberty university psyc 101 quiz 14 solutions answers slideshare
Liberty university psyc 101 quiz 14 solutions answers slideshareLiberty university psyc 101 quiz 14 solutions answers slideshare
Liberty university psyc 101 quiz 14 solutions answers slideshare
 
Liberty university psyc 101 quiz 13 solutions answers slideshare
Liberty university psyc 101 quiz 13 solutions answers slideshareLiberty university psyc 101 quiz 13 solutions answers slideshare
Liberty university psyc 101 quiz 13 solutions answers slideshare
 
Liberty university psyc 101 quiz 12 solutions answers slideshare
Liberty university psyc 101 quiz 12 solutions answers slideshareLiberty university psyc 101 quiz 12 solutions answers slideshare
Liberty university psyc 101 quiz 12 solutions answers slideshare
 

Recently uploaded

Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCRsoniya singh
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...lizamodels9
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCRsoniya singh
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...lizamodels9
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 

Recently uploaded (20)

Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Keshav Puram 🔝 Delhi NCR
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Mehrauli Delhi 💯Call Us 🔝8264348440🔝
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
Lowrate Call Girls In Laxmi Nagar Delhi ❤️8860477959 Escorts 100% Genuine Ser...
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
(8264348440) 🔝 Call Girls In Mahipalpur 🔝 Delhi NCR
 
KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
Lowrate Call Girls In Sector 18 Noida ❤️8860477959 Escorts 100% Genuine Servi...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 

Liberty university busi 313 quiz 4 complete solutions correct answers slideshare

  • 1. Liberty University BUSI 313 quiz 4 complete solutions correct answers slideshare Six different versions https://www.coursemerit.com/solution-details/20165/ Liberty-University-BUSI-313-quiz-4-complete-solutions-correct-answers-A-work Question 1 Disadvantages of outsourcing project work may likely include all of the following EXCEPT Question 2 Experience indicates that colocation of project teams is not worth the extra costs. Question 3 When using the partnering approach to manage contracted relationships, each party's goals and objectives are similar but geared to what is best for them. Question 4 Which of the following is true in regard to negotiation when managing projects? Question 5 Principled negotiation emphasizes developing win/win solutions while protecting yourself against those who would take advantage of your forthrightness. Which of the following is NOT one of the key points of principled negotiation? Question 6 A partnering charter states the common goals for the project as well as the procedures that will be used to achieve these goals. Question 7 What does the acronym BATNA stand for? Question 8 When considering principled negotiation, both buyers and sellers relying on the blue book to establish price parameters of a used car would be an example of Question 9 Jessica just received the following information on her project: PV = 200, EV = 3 00, AC = 250, BAC = 1500, EAC = 1208. In terms of cost at completion. Question 10 Which of the following is NOT true regarding scope creep? Question 11 Because of their easytounderstand visual format, tracking Gantt charts are the most favored, used, and understandable option for reporting project status. Question 12 The cost variance for a project is calculated by Question 13 A ___________ Gantt chart is a simple and effective way to depict progress on a project. Question 14 A project control system allows for comparing actual performance against plan to
  • 2. identify deviations; however, the system doesn't impact the quality of communication between stakeholders. Question 15 Which of the following are required to assess the current status of a project us ing the earnedvalue cost/schedule system? Question 16 A CPI or SPI value less than one indicates that the project is Question 17 Project closures can fall into all of the following categories EXCEPT Question 18 Assessing what fundamental organizational culture properties affect project successes and failures, or become a hindrance to project teams, is a part of the retrospectives methodology. Question 19 In organizations where projects are managed within a ____________, the team member's area manager, not the project manager, is responsible for assessing performance. Question 20 Which part of the final report is designed to be the most useful on future projects? Question 21 During the closing phase, the project manager's challenge is to keep the project team focused on the remaining project activities and delivery to the customer until the project is complete. Question 22 Which of the following would NOT be appropriate to assess when evaluating team performance? Question 23 The final report typically includes profit made on the project. Question 24 A 360degree performance evaluation includes feedback from peers, project managers, subordinates, and even customers. Question 25 Performance appraisals generally fulfill two functions. The first is to identify individual strengths and weaknesses and to develop action plans for improving performance. The second involves salary or merit adjustments. Why should these two functions be addressed at different times?
  • 3. 1. Contracting project work has long been the norm in the _______ industry. A. Telecommunications B. Financial C. Insurance D. Construction E. Retail 2. The process for the transferring of business functions or processes to other, often foreign, companies has traditionally been known as: A. Subcontracting B. Downsizing C. Partnering D. Joint venture E. Outsourcing 3. When you call your Internet provider to solve a technical problem and you end up talking to a technician in India or Romania, you have just experienced: A. Telecommunications B. Partnering C. Outsourcing D. Service shift E. Bilingual customer service 4. Which of the following is not a potential part of the outsourcing concept? A. Computers B. Faxes C. Computer-aided design systems D. Video teleconferencing E. All the above are correct
  • 4. 5. Advantages of outsourcing project work may likely include all of the following except A. Shortened project completion B. Reduced costs C. Higher level of expertise D. Reduced conflict E. Increased flexibility 6. Disadvantages of outsourcing project work may likely include all of the following except A. Increased conflict B. Coordination breakdowns C. Increased costs D. Loss of control E. More internal morale issues 7. The driving motive for increasing the use of outsourcing on projects was: A. Reducing the trade deficit B. Reducing costs C. Improving international sales D. Making products more international in design E. Securing technology that was not available domestically 8. Recent outsourcing trends have shown an increasing emphasis on the suppliers for all of the following except: A. Further cost reductions B. Increased quality of work performed C. Increased ability to collaborate D. Increased ability to work together E. All of these are recent trends 9. Key practices in partnering relationships include: A. Single project contracting B. Goals and objectives are similar C. Access to each other's organizational resources D. Both B and C are correct E. A, B, and C are all correct
  • 5. 10. In the "Competing against the Giants" Snapshot from Practice, SATT Control uses which of the following to successfully compete against much larger competitors? A. Excellent project management B. Acts as a system integrator C. Using the same subsystem vendors again and again D. Both A and B are correct E. A, B, and C are all correct 11. hich of the following is not a key to successful partnering relationships? A. Mutual trust B. Jointly shared risk C. Total company involvement D. Independent project teams E. Long-term commitment 12. Which of the following is part of the traditional project process? A. Structured communications B. Long-term commitment C. Total company involvement D. Both A and B are correct E. A, B, and C are all correct 13. The traditional project process includes all of the following except: A. Independent project teams B. Shared goals and objectives C. Single project teams D. Risk is transferred to the other party E. Limited objectivity 14. Which of the following did the state of Ohio do before starting a bond-financed school construction project? A. Create a specific RFP (request for proposal) B. Have a dress rehearsal C. Reviews the performance of contractors on past projects D. Both A and C are correct E. A, B, and C are all correct
  • 6. 15. Best practices in outsourcing project work include all the following except: A. Well defined requirements and procedures B. Training and teambuilding activities C. Well established conflict management processes D. Frequent reviews and status updates E. All of these are best practices 16. In the Snapshot from Practice "Strategies for Communicating with Outsourcers," which of the following was not one of the suggested strategies? A. Recognize cultural differences B. Use a translator to make sure everyone understands C. Choose the right words D. Confirm your requirements E. Set deadlines 17. To make sure that an outsourcer thoroughly understands your requirements you should: A. Document your conversations in writing B. Insist that the outsourcer write the requirements in their own words C. Request they build a prototype D. Both A and C are correct E. A, B, and C are all correct 18. The result of teambuilding among the project's participants is a: A. Signed contract B. Legal partnership agreement C. Project plan D. Partnering charter E. Responsibility matrix 19. To avoid problems with schedules and deadlines you should: A. Develop detailed schedules B. Hold frequent status reviews C. Add a penalty clause to the contract D. Hold frequent conversations with the outsourcer E. Build extra time into the schedules that the outsourcer is not aware of
  • 7. 20. Among the many advantages for establishing long-term partnerships are: A. Reduced administrative costs B. Improved performance C. Improved communication D. B and C are both correct E. A, B, and C are all correct 21. Long-term partnerships will provide all the following except: A. Improved communication B. More efficient utilization of resources C. Reduced need for total number of partnerships D. Lower administrative costs E. Improved innovation 22. Teambuilding between partners should: A. Include engineers, architects, lawyers, specialists and other staff B. Be facilitated by an outside consultant C. Not take more than one day D. A and B are both correct E. A, B, and C are all correct 23. Which of the following would be included in best practices in outsourcing project work? A. Establishing long-term relationships B. Include financial incentives C. Reduce costs by using tried and true methods D. A and B are both correct E. A, B, and C are all correct 24. In the Snapshot from Practice dealing with the Value Engineering Awards program, which branch of the U.S. government was involved? A. Department of Defense B. Department of Commerce C. Department of Transportation D. N.A.S.A E. Department of Education
  • 8. 25. Which of the following is not one of the key points of principled negotiation? A. Use objective criteria when possible B. Be honest and forthright C. Focus on interests, not positions D. Separate the people from the problem E. Invent options for mutual gain 26. Customer satisfaction can be quantitified by: A. Perceived performance divided by actual performance B. Actual performance divided by expected performance C. Perceived performance divided by expected performance D. Actual performance divided by perceived performance E. Expected performance divided by actual performance 27. Which of the following is a part of the noncompetitive view of negotiation? A. Reaching an agreement B. Implementation phase C. Review of the completed project D. Both A and B are correct E. A, B, and C are all correct 28. Which of the following is suggested as the best target for a customer satisfaction ratio? A. 1.00 B. 1.05 C. 1.10 D. 1.20 E. 1.50 29. In the research highlight on IT project managers, which of the following was not one of the roles taken by project managers? A. Entrepreneur B. Politician C. Friend D. Marketer E. Auditor
  • 9. 30. Regarding customer relations, advice passed on by veteran project managers includes: A. Speak with one voice B. Speak in precise terms C. Speak the language of the customer D. Both A and B are correct E. Both A and C are correct 31. Which of the following is not one of the elements of good negotiation? A. Be hard on the problem, soft on the people B. Conflict on a project can be good C. Negotiation is not a contest D. Seek first to understand, then to be understood E. All of these are elements of good negotiation 32. Which of the following is reflected in the saying "Let anger fly out the window"? A. Separate people from the problem B. Be honest C. Focus on interests, not positions D. Invent options for mutual gain E. When possible, use objective criteria 33. Which of the following is reflected in the saying "Seek first to understand, then to be understood"? A. Separate people from the problem B. Be honest C. Focus on interests, not positions D. Invent options for mutual gain E. When possible, use objective criteria 34. The dovetailing technique is used in which of the following keys to good negotiation? A. Separate people from the problem B. Be honest C. Focus on interests, not positions D. Invent options for mutual gain E. When possible, use objective criteria
  • 10. 35. Contracting project work has long been the norm in the __________ industry. 36. The __________ project, which created a transportation tunnel between France and England, involved more than 250 organizations. 37. In a partnering relationship, ________ is shared jointly among the partners, which encourages innovation and continuous improvement. 38. In a partnering relationship, ________ forms the basis for strong working relationships. 39. In traditional project relationships, ________ is limited due to fear of reprisal and lack of continuous improvement opportunity. 40. In traditional project relationships, ________ are structured and guarded. 41. In Ohio before starting a bond-financed ____________, projects management consultants and the related parties get together to figure out how to talk to each others and how to handle problems. 42. The term __________ has traditionally been applied to the transferring of business functions or processes to other, often foreign, companies. 43. Many outsourced projects operate in a _________ environment in which people are linked by computers, faxes, computer-aided design systems, and video teleconferencing. 44. __________ is a major advantage of outsourcing project work because companies can secure competitive prices for contracted services, especially if the work can be outsourced offshore. 45. Not only can contracted project work be cheaper, it can also be done __________. 46. High levels of __________ and technology can be brought to bear on a project by using contracted services. 47. Contracting project services can increase a firm's _________ by no longer being constrained by their own resources. 48. Breakdowns in __________ of professionals from different organizations can occur if the project work requires close collaboration and mutual adjustment. 49. In the Snapshot from Practice involving SATT Control, a Swedish electronics firm, the company referred to one of its competencies as being a ________ who subcontracts the subsystems to other firms. 50. There is a potential loss of __________ over a project when the core team depends on other organizations that they do not have direct authority over. 51. Projects are more prone to interpersonal _________ because the different participants do not share the same values, priorities, and culture. 52. There is little disagreement that __________ was the primary motive behind outsourcing project work.
  • 11. 53. Fisher and Ury champion the ________ approach to negotiation because it emphasizes win/win solutions while protecting yourself against those who would take advantage of your forthrightness. 54. ________ satisfaction is measured by the ratio of perceived performance to expected performance. 55. The best defense against unreasonable, win/lose negotiators is having what Fisher and Ury call a strong __________. 56. As part of an effort to cut costs the United States Department of Defense issues annual __________. 57. "Let anger fly out of the window" is an example of the ___________ key point of negotiation. 58. Explaining why a critical task must be done by a specific time is an example of the ___________ key point of negotiation. 59. Dividing perceived performance by expected performance will calculate __________. 60. Toyota and Daimen-Chrysler collaborating with suppliers to develop new automobile platforms is an example of outsourcing. 61. Participants from different organizations working close together at the construction site or in shared office space is an example of a virtual team. 62. Working in outsourcing teams, projects can be completed faster and more cheaply. 63. Increased conflict and loss of coordination are typical disadvantages of outsourcing project work. 64. Trust can be difficult to forge when interactions are limited and people come from different organizations. 65. In partnering, access to each other's organization resources is available. 66. In the traditional method of managing projects, total company involvement requires commitment from CEO to team members. 67. In partnering, each party's goals and objectives are similar but geared to what is best for them. 68. As part of an effort to cut costs, the United States Department of Defense issues annual Value Engineering Awards. 69. In some countries, laws are considered to be guidelines that are not necessarily followed. 70. For people in some countries, a written, signed contract is merely a suggestion. 71. Because English is the language of business, it is not necessary to speak in a direct manner using short sentences made of basic, simple words as this may taken as an insult. 72. All conversations with outsourcers should be followed up with commitments documented in writing since they are likely to understand written English better than spoken English.
  • 12. 73. Experience indicates that co-location of project teams is not worth the extra costs. 74. A partnering charter states the common goals for the project as well as the procedures that will be used to achieve these goals. 75. It is a good idea to add a penalty clause to an outsourcing agreement because deadlines are often taken as a suggestion rather than a commitment. 76. A prime consideration in choosing outsourcing vendors is to assess the fit with their project management system. 77. Team-building workshops with outsourcing vendors is usually led by an outside consultant who is an expert in designing and facilitating such workshops. 78. In project negotiation each negotiator is out to win as much as he or she can for their side. 79. Principled Negotiation emphasizes developing win/win solutions while protecting yourself against those who would take advantage of your forthrightness. 80. By keeping the focus on the issues and not the personalities, negotiators are better able to let the other person blow off steam. 81. The best defense against unreasonable, win/lose negotiators is having what Fisher and Ury call a strong BATNA. 82. A value of 1.5 is the accepted target for the Met-Expectations model of customer satisfaction. 1. A project monitoring system involves all of the following EXCEPT A. Determining what data to collect B. Determining how, when, and who will collect the data C. Adjusting the data D. Analysis of the data E. Reporting current progress
  • 13. 2. Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work. Nancy got this information from viewing the A. SV B. TCPI C. CPI D. SPI E. PCIB 3. Jessica just received the following information on her project: PV = 200, EV = 300, AC = 250, BAC = 1500, EAC = 1208. In terms of cost at completion A. The project will currently finish under budget B. The project will currently finish over budget C. The project will currently finish on budget D. The project will currently finish behind schedule E. There is insufficient information to draw conclusions 4. The first step in the project control process for measuring and evaluating project performance is to A. Set a baseline plan B. Determine the project objectives C. Determine the project deliverables D. Analyze the project budget E. Review the project priority matrix 5. The second step in the project control process for measuring and evaluating project performance is to A. Review the baseline plan with top management B. Analyze inputs to control system C. Compare plan against actual D. Measure progress and performance E. Review spending with team members
  • 14. 6. The third step in the project control process for measuring and evaluating project performance is to A. Review the baseline plan with top management B. Analyze inputs to the control system C. Compare the plan against actual performance D. Measure both progress and performance E. Review spending with team members 7. The final step in the project control process for measuring and evaluating project performance is to A. Take appropriate action B. Prepare a report to top management C. Follow up on corrective action D. Measure progress and performance E. Review spending with team members 8. In monitoring project time (schedule) performance, actual performance should be compared to A. Budgets for the current year B. Top management's targets C. Project network schedule derived from the WBS/OBS D. Progress on similar past projects E. Previous status reports 9. A ___________ Gantt chart is a simple and effective way to depict progress on a project. A. Baseline B. Control C. Variance D. Tracking E. Simple
  • 15. 10. A tool used to monitor past project schedule performance and current performance, and to estimate future schedule trends is a simple line chart known as a A. Project schedule control chart B. Gantt chart C. PERT chart D. Network diagram E. Milestone chart 11. The earned value system starts with the time-phased costs that provide the project baseline, which is called the A. Planned budgeted value of work scheduled B. Planned budgeted value of work completed C. Earned value of work scheduled D. Scheduled value of work scheduled E. Scheduled value of work completed 12. The earned value of a project is the A. Project cost to date adjusted for project scope changes B. Total project cost to date C. Cost incurred minus the planned cost D. Percent of the original budget that has been earned by actual work E. The planned time-phased baseline of the value of work scheduled 13. The cost variance for a project is calculated by A. EV - AC B. AC - SV C. PV - EV D. CU - EV E. EU - PV
  • 16. 14. The schedule variance for a project is calculated by: A. EV - AC B. AC - SV C. PV - EV D. CU - EV E. EV - PV 15. Baseline project budgets are derived from A. The organization's overall budget B. Time-phasing the work packages C. Top management directions D. The total direct, direct project overhead and G&A overhead costs E. The earned value system 16. Of the following costs, which are NOT included in baseline? A. Suppliers B. Equipment C. Labor D. Budget reserves E. Contractors 17. When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the A. 0/100 percent rule B. Task complete rule C. Degree complete rule D. Work complete rule E. Percent complete rule 18. Which performance index is the most potentially misleading? A. CPI
  • 17. B. EV C. CV D. SV E. EAC 19. Which of the following are required to assess the current status of a project using the earned- value cost/schedule system? A. BAC, EAC, and ETC B. VAC, EAC, and BAC C. CV, SU, and BAC D. PV, EV, and AC E. TCPI, EV, and PV 20. Which of the following methods of variance analysis is the best indicator of how far off the budget a project will be at completion? A. BAC B. EAC C. ETC D. VAC E. TCPI 21. Which of the following methods will measure the cost efficiency of the work accomplished to date? A. SV/CV B. EV/PV C. EV/AC D. AC/SV E. AC/CV
  • 18. 22. Which of the following methods will measure the scheduling efficiency of the work accomplished to date? A. SV/CV B. EV/PV C. EV/AC D. AC/SV E. AC/CV 23. A CPI or SPI value less than one indicates that the project is A. Under cost or behind schedule B. Over cost or ahead of schedule C. Under cost or ahead of schedule D. Over cost or behind schedule E. On cost or on schedule 24. The value that tells you the planned value of work that has actually been completed is the A. SV B. PV C. EV D. AC E. CV 25. The indicator that tells you the amount each remaining dollar must earn in order for the project to stay within budget is the A. PCIC B. VAC C. CPI D. SPI E. TCPI 26. A project manager learns that the project is only earning $.90 of planned work for each dollar spent by looking at the
  • 19. A. EV B. BAC C. SV D. SPI E. CPI 27. A project manager notices that $1,000 worth of work that was scheduled to be completed at this time has not been accomplished. They know this by looking at the A. EV B. TCPI C. SV D. PCIB E. EAC 28. Sally receives the following information on her project: PV = 100, AC = 75, EV = 100. How well is the project doing in terms of budget? A. Right on budget B. 25 under budget C. 25 over budget D. 50 under budget E. 50 over budget 29. Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000, EAC = 1333. How is the project doing in terms of schedule? A. More work has been done than planned B. Less work has been done than planned C. The same amount of work has been done than planned D. The project has cost less than planned E. There is not enough information to draw a conclusion
  • 20. 30. Which of the following is NOT true regarding scope creep? A. It commonly occurs late in projects B. It is frequently unnoticed until time delays or cost overruns are observed C. It wears down team motivation and cohesiveness D. Project suppliers resent frequent changes E. Scope changes can represent significant opportunity 31. ________ holds people accountable, prevents small problems from mushrooming into large problems, and keeps focus. 32. The first step in creating a project control system for measuring and evaluating project performance is to set a ________. 33. The value that tells you the planned value of the actual work completed is ___________. 34. When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the ____________ rule. 35. Because of their easy-to-understand visual format, ________ charts are the most favored, used, and understandable tool used to report project schedule status. 36. The indicator that tells you the planned time-phased value of the work that is scheduled is the _______________. 37. Baseline project budgets are derived from time-phasing the work ________. 38. The ________ variance is the difference between the earned value and the actual costs for the work completed to date. 39. The ________ variance is the difference between the earned value to date and the baseline schedule. 40. ________ is simply the percent complete times the original budget. 41. Conditions or scope can change, which, in turn, will require a change to the __________ plan to recognize the new information. 42. The project network schedule is derived from the _______ and it serves as the baseline to compare against actual performance.
  • 21. 43. A negative CV indicates the project is ________ budget. 44. The ________ rule assumes credit is earned for having performed the work once it is completed. This rule is usually used for work packages having very short durations. 45. The ratio that measures the amount of value each remaining dollar in the budget must earn to stay within the budget is the _________. 46. The _________ index measures the project percent complete in relation to the resources that were budgeted. 47. Given that the AC = 300, PV = 400 and EV = 500, this project is _________ budget. 48. Given a BAC of 5,500 and an EAC of 6,000, the project is expected to be completed _________ budget. 49. An SPI index of 1.22 indicates that the project is ________ schedule. 50. Although it is very difficult to measure, measuring ________ performance is as important as measuring schedule and cost performance. 51. The final step in the project control process for measuring and evaluating project performance is to take appropriate ________. 52. In some cases, conditions or scope can change, which, in turn, will require a change in the baseline plan to recognize new information. 53. The PCIC index measures the project percent complete in relation to the resources that have actually been used so far on the project. 54. The only accurate method for determining the true time progress of the project is to compare the project network schedule against the actual network schedule to measure if the project is on time. 55. Schedule variance measures progress in time units. 56. Earned value is defined as the budgeted cost of the actual work performed. 57. The baseline is derived from merging information from the work packages with the project network. 58. Because of their easy-to-understand visual format, tracking Gantt charts are the most favored, used, and understandable option for reporting project status. 59. The PV, AC and CV are all required to assess the current status of the project.
  • 22. 60. When revising the estimated cost at completion, there are two approaches. The EACre is determined by experts in the field and the EACf is a mathematical approach which assumes the CPI as the basis for forecasting cost at completion. 61. The best method for assigning costs to the baseline under the 50/50 rule is to establish frequent checkpoints over the duration of the work package and assign completion percentages in dollar terms. 62. Most changes will not result in serious scope changes and should be absorbed as positive or negative variances. 63. A “rubber baseline” occurs when, in an effort to disguise poor performance, the baseline changes to constantly match results. 64. Baseline costs typically include labor, equipment, materials and direct overhead cost. 65. A project control system allows for comparing actual performance against plan to identify deviations; however, the system doesn’t impact the quality of communication between stakeholders. 66. Two major reasons for creating a baseline are to monitor and report progress and to estimate cash flow. 67. In calculating schedule variance and cost variance, a negative variance indicates a desirable condition, and a positive variance suggests problems. 68. An undesirable schedule variance always indicates that the project is running behind schedule. 69. Progress and performance can be measured quantitatively as well as qualitatively. 70. A CPI index of 0.97 indicates that the project has spent less money than budgeted. 71. Rachel notices that the current EV for her project is higher than both the PV and the AC. Rachel has reason to be concerned.
  • 23. 72. All scope changes that result in increased costs should be avoided. 73. Although it is very difficult to measure, measuring technical performance is as important as measuring schedule and cost performance. 74. Deciding what data to collect, actually collecting the data and analyzing it, and reporting this data are all parts of structuring a project monitoring information system. 75. A project manager would be glad to see a TCPI of 1.07. 76. A negative VAC indicates that the project will be completed over budget. 1. The most common circumstance for project closure is simply a ________ project. A. Completed B. Overdue C. Over-budget D. Underachieving E. Successful 2. Which of the following is NOT a wrap-up closure activity that might be found on a checklist? A. Getting delivery acceptance from the customer B. Reassigning project team members C. Closing accounts and seeing all bills are paid D. Evaluation of team performance E. Creating a final report 3. __________ of lessons learned are designed to improve performance on current and future projects. A. Retrospectives B. Corrective action plans C. Introspectives D. Culminations E. Evolutions
  • 24. 4. The content of the final report typically includes the following topics EXCEPT A. Lessons learned B. Review and analysis C. Recommendations D. Executive summary E. Team reviews 5. When the project may be completed early with some parts of the project eliminated this is considered to be ___________ closure. A. Normal B. Premature C. Perpetual D. Changed Priority E. Failed Project 6. This type of closure occurs when the project may never seem to end. At some point the review group should recommend methods for bringing final closure to this type of project. This is considered to be ___________ closure. A. Normal B. Premature C. Perpetual D. Changed Priority E. Failed Project 7. Because of circumstances beyond the control of the project team, many projects are easy for a review group to close down. This type of project closure is called A. Normal B. Premature C. Perpetual D. Failed Project E. Changed Priority
  • 25. 8. When a project starts with a high priority but it is cancelled because its rank erodes or crashes during its project life cycle, this is an example of what type of project closure? A. Normal B. Premature C. Perpetual D. Failed Project E. Changed Priority 9. Which of the following summarizes project performance and provides useful information for continuous improvement? A. Customer acceptance B. The final report C. Team evaluation D. 360-degree feedback E. Project summary 10. Which part of the final report highlights the key findings and facts relating to the project implementation? A. Executive summary B. Review and analysis C. Recommendations D. Lessons learned E. Appendix 11. Which part of the final report examines in detail the underlying causes of problems, issues, and successes relative to the project and includes concise, factual review statements of the project? A. Executive summary B. Review and analysis C. Recommendations D. Lessons learned E. Appendix 12. Which part of the final report presents major improvement actions that should be made?
  • 26. A. Executive summary B. Review and analysis C. Recommendations D. Lessons learned E. Appendix 13. Which part of the final report is designed to be the most useful on future projects? A. Executive summary B. Review and analysis C. Recommendations D. Lessons learned E. Appendix 14. Which part of the final report includes backup data or details of analysis that would allow others to follow up if they wished? A. Executive summary B. Review and analysis C. Recommendations D. Lessons learned E. Appendix 15. The purpose of project evaluation is to assess how well A. The project team performed B. The team members performed C. The project manager performed D. The project team and team members performed E. The project team, team members and the project manager performed 16. Which of the following would NOT be appropriate to assess when evaluating team performance? A. How well the team performed in terms of time, cost, and specifications
  • 27. B. Effectiveness of group decisions C. Individual strengths and weaknesses D. Customer satisfaction with project deliverables E. Trust among group members 17. Before an evaluation of the project team can be effective and useful, a minimum core of conditions needs to be in place before the project begins. Which of the following would NOT be one of those conditions? A. Individuals have the skillset necessar y to successfully complete the project B. Evaluation criteria beyond time, cost and specifications has been established C. Rewards are adequate D. Individual and team responsibilities and performance standards are known by all team members E. Standards for measuring performance exist 18. Performance appraisals generally fulfill two functions. The first is to identify individual strengths and weaknesses and to develop action plans for improving performance. The second involves salary or merit adjustments. Why should these two functions be addressed at different times? A. It is too much information to discuss at once B. Employees are so eager to learn about a potential raise that they tend to tune out constructive feedback C. Managers tend to spend too much time talking about how the employee can improve his or her performance and not on justifying the salary adjustment D. If employees are upset over a salary adjustment, they will not be open to listening to ways they can improve. E. If the manager is giving employees bad news regarding their salary adjustment, they will not be honest about the employees’ weaknesses and will tend to focus on their strengths. 19. The following are general tips for conducting performance reviews EXCEPT
  • 28. A. Begin the process by asking the individual to evaluate his or her own contributions to the project B. Use other team members’ performance as a method to compare and evaluate C. When you have to be critical, focus the criticism on specific examples of behavior and not on the individual personally D. Be fair and consistent in your treatment of all team members E. Treat the review as only one point in an ongoing process 20. An analysis carried out during and shortly after the project life cycle that attempts to capture positive and negative learning is represented in which of the following? A. Scenario analysis B. Variance analyses C. Lessons learned D. Performance evaluation E. Strategic objectives 21. The process for capturing lessons learned continues to evolve, but there are still many barriers to effectively capitalizing on lessons learned that have been identified. The following are examples of these barriers EXCEPT A. Lack of time B. Teams get little direction or support after lessons are reported C. Lessons learned often degenerate into blame sessions D. Lessons learned are being used across different locations E. The organizational culture doesn’t support the effort that it takes to capitalize on lessons learned 22. The following are distinguishing characteristics of retrospectives methodology EXCEPT A. Uses an independent facilitator B. Establishes in-process learning gates during the project life cycle C. An owner, typically a team member, is assigned D. Reviews cannot be linked to percent complete E. A repository is developed that is easy to use
  • 29. 23. Project closures can fall into all of the following categories EXCEPT A. Premature B. Perpetual C. Failed D. Changed priority E. Successful 24. A guide who leads the project team through an analysis of project activities that went well and of what needs improvement and development of a follow-up action plan with goals and accountability is a(n) A. Owner B. Project sponsor C. Project manager D. Facilitator E. Mediator 25. It is imperative that the closure facilitator possess the following characteristics EXCEPT A. Has direct involvement or direct interest in the project B. Is perceived as impartial and fair C. Has respect for senior management and other project stakeholders D. Willing to listen E. Is perceived as having the best interests of the organization in making decisions 26. The typical mechanism for the evaluation of teams is normally A. A survey completed by the team members B. A personal interview of each team member C. An analysis by an outside consultant D. A survey completed by members of top management E. A survey completed by the internal or external customers
  • 30. 27. More and more companies are discarding the traditional superior-subordinate performance feedback process and replacing it with a multi-rater appraisal called A. Critical incidences review B. Management by objectives C. The 360-degree feedback D. Team evaluation survey E. Retrospectives 28. Which of the following is NOT a role of the closure facilitator? A. Create an environment in which stakeholders feel safe to provide input B. Lead the team in exploring new ways for solving problems C. Use several questionnaires as a starting point to conduct the post-project retrospective D. Get delivery acceptance from the customer E. Elicit a 360-degree view and input from all stakeholders to create a more complete picture of project issues 29. In organizations where projects are managed within a ____________, the team member's area manager, not the project manager, is responsible for assessing performance. A. Functional organization B. Matrix organization C. Flat organization D. Project organization E. Strong organization 30. Each retrospective is assigned a(n) _________, typically a team member who is very interested in and familiar with the retrospective. This individual will serve as the contact point for anyone needing information relating to the retrospective. A. Owner B. Project sponsor C. Project manager D. Facilitator E. Mediator
  • 31. 31. ________ project closure is the most common circumstance for project closure and is simply a completed project. 32. When a project is completed early with some parts of the project eliminated this is known as _________ project closure. 33. A ____________ project closure is usually easy to identify and easy for a review group to close down. 34. Projects in process may need to be altered or canceled. Thus, a project may start with a high priority but see its rank erode or crash during its project life cycle as conditions change. This is called __________project closure. 35. When the review group recommends methods for bringing final closure to a project that never seems it will end, this is an example of a ________ project closure. 36. Within the final report, a summary that simply highlights the key findings and facts relating to project implementation is called the ___________ summary. 37. Implementing the closure process includes several _______ activities, including getting delivery acceptance from the customer. 38. The ________ section of the final project report includes concise, factual review statements of the project, such as project mission and objectives, procedures and systems used, and organizational resources used. 39. Perhaps the_________ section of the final report is the most valuable contribution of the closure process. 40. The ________ section of the final project report is often technical in nature and focuses on solutions to problems that surfaced. 41. Within the final report, the ___________ may include backup data or details of analysis that would allow others to follow up if they wish. 42. The purpose of project __________ is to assess how well the project team, team members, and project manager performed. 43. ____________ of performance is essential to encourage changes in behavior and to support individual career development and continuous improvement through organizational learning. 44. The ________ feedback approach gathers anonymous feedback solicited from others that is compared with the individual's self-evaluations. 45. The typical mechanism for evaluation of teams is a ________ administered by a consultant.
  • 32. 46. The retrospective approach stresses gathering _____________ during project execution and using them to change remaining work. 47. In organizations where projects are managed within a functional organization, the team member’s __________ manager is responsible for assessing performance. 48. The most common reason given for not creating lessons learned is the lack of _________. 49. A ________ is a methodology that analyzes a past project event to determine what worked and what didn't, develop lessons learned, and create an action plan that ensures lessons learned are used to improve management of future projects. 50. Retrospective reviews should be set up in the project ___________ stage. 51. The ____________ report summarizes project performance and provides useful information for continuous improvement. 52. A guide who leads the project team through an analysis of project activities that went well and of what needs improvement and development of a follow-up action plan with goals and accountability is known as a project ____________. 53. __________ represent an analysis carried out during and shortly after the project life cycle; they attempt to capture positive and negative project learning. 54. Each retrospective is assigned a(n) __________, typically a team member who is very interested in and familiar with the retrospective. 55. Motivation can be the chief challenge when wrapping up closure activities. 56. In premature project closure, the project may be completed early with some parts of the project eliminated. 57. Retrospectives of lessons learned are designed to improve performance on current and future projects. 58. When a project starts as a high priority but its rank erodes or crashes during its project life cycle resulting in closure of the project, this is an example of changed priority project closure. 59. The final report typically includes profit made on the project. 60. The project manager's challenge is to keep the project team focused on the remaining project activities and delivery to the customer until the project is complete. 61. Implementing project closure includes getting delivery acceptance from the customer. 62. Within the final report, the project summary is the summary that simply highlights the key findings and facts relating to the project implementation. 63. Expectations, standards, supportive organizational culture, and constraints must be in place before project implementation; if not, the effectiveness of the evaluation process will suffer.
  • 33. 64. Evaluation of performance is essential to encourage changes in behavior and to support individual career development and continuous improvement through organizational learning. 65. The processes for capturing lessons learned continue to evolve, but there are still barriers to effectively mining lessons learned. 66. Project managers should wait to give feedback to the project team and team members until the project has been completed. Giving feedback throughout the project can distract project teams. 67. Assessing what fundamental organizational culture properties affect project successes and failures, or become a hindrance to project teams, is a part of the retrospectives methodology. 68. In organizations where projects are managed within a functional organization, the team member’s area manager, not the project manager, is responsible for assessing performance. 69. The most common circumstance for project closure is simply a completed project such as building a new facility or creating a customized information system. 70. A project closure where the project is completed early with some parts of the project eliminated would be classified as a failed project. 71. The key requirement in selection of the facilitator is one who is the end-user. 72. The retrospective facilitator should be able to deliver bad news to the project sponsor or senior management without recriminations. 73. Retrospective methodology is one positive step toward ensuring lessons learned are developed and implemented. 74. A 360-degree performance evaluation includes feedback from peers, project managers, subordinates, and even customers. 75. Project managers should, when possible, draw comparisons to other team members when conducting individual team member reviews. 76. The retrospective methodology is more inclusive and disciplined than past lessons learned approaches.