SlideShare a Scribd company logo
1 of 14
EVALUATION OF CONSTRUCTION
PROGRAMME OF WORKS FOR CENTRE OF
EXCELLENCE USING MICROSOFT PROJECT.
BY
KOTOKO, ALI ZANNAH
U11BD1017
SUPERVISOR: DR. DALHAT ABDULSALAM
BACKGROUND TO THE STUDY
1. The construction industry is being transformed to meet the
new demands of the twenty-first century (Levy, 2007).
2. Time is vitally important for all participant in the
construction process.
3. Improper time management, many problems will occur such
as extension of time or time overrun.
4. Time overrun become the most general problem in
construction industry worldwide (Olawale & Sun, 2010)
5. A myriad of details are considered in planning and
developing a realistic schedule, and then in monitoring
the progress of the project.
Aim
To assess the application of MS Project in
construction program of works for Centre of Excellence
with a view of optimizing the progress of building
production process.
Objectives
1. To develop a construction program of works for
Centre of excellence.
2. To compare the construction program of works
developed by this study with that developed by the
contractors.
3. To evaluate the level of implementation and
compliance of the construction program of works.
LITERATURE REVIEW
1. Construction Project Life Cycle
2. Construction Programme For Building Projects
3. CPM and PERT Networks
4. Bar/Gantt Chart
5. Line-of-Balance (LOB)
6. Developing The Construction Programme
RESEARCH METHODOLOGY
Research Design
1. The case study was selected using a checklist of a set of
formulated criteria.
2. The use of checklist to compare the developed and the
actual POW.
3. The use of MS Project software to evaluate the
implementation and measure progress of work; by
identifying:
a. Project Status
b. Late Activities/Task
c. Resource Allocations
Microsoft Project Steps Overview
1. Starting a new plan and
setting its start date
2. Entering the plan’s title
and other properties
3. Enter task names,
durations, and start and
finish values
4. Create summary tasks to
outline a task list.
5. Resource assignment
6. Viewing the project’s
critical path
PRESENTATION, ANALYSIS AND
DISCUSSION OF RESULTS
1. The project:
A five-storey semi-
circular shaped hostel
building with an internal
radius of 24.5m located at
NDA Kaduna.
2. Calculation Sheet:
Quantities are extracted
directly from working
drawings.
CPW on MS Project
1. Red bars: Duration of activities
2. Yellow line: Progress of work recorded.
3. Blue: Summary Task.
Comparison of Programmes of
Works
1. MS Project comparison report.
2. Shows the differences in duration and start day.
3. Difference increasingly negative.
Checklist for Project status
As at July, 2016:
The percentage of duration of
the overall project completed is
calculated to be (124%), having
an overall scheduled duration of
(676days), with over (835days)
being exhausted hence creating
a time overrun of over
(160days).
LATE ACTIVITIES/TASK
Tasks that are late as compared to the status date. A task is
late if its finish date has passed or it is not progressing as
planned.
As at July 2016:
1. (35%) of activities
completed.
2. (65%) of activities
of the overall
project are
automatically late.
Resources Usage Overview
824 hrs
960 hrs 1,012 hrs
120 hrs
1,376 hrs
136 hrs 328 hrs 128 hrs 56 hrs 0 hrs 80 hrs 320 hrs 112 hrs
3,982 hrs
0 hrs472 hrs 200 hrs
1,760 hrs
0 hrs 0 hrs 48 hrs 48 hrs 16 hrs 0 hrs 48 hrs 16 hrs 0 hrs
2,144 hrs
4,578 hrs
4,200 hrs
1,296 hrs
1,160 hrs
2,772 hrs
120 hrs
1,376 hrs
184 hrs 376 hrs 144 hrs 56 hrs 48 hrs 96 hrs 320 hrs
2,256 hrs
8,560 hrs
4,200 hrs
0 hrs
1,000 hrs
2,000 hrs
3,000 hrs
4,000 hrs
5,000 hrs
6,000 hrs
7,000 hrs
8,000 hrs
9,000 hrs
Masons Iron Benders Carpenters Unskilled
Labourers
Excavators Concrete
Pumper
Concrete
Mixers
Small
Concrete
Mixers
Dumper Batching
Plant
Crane Surveyors Other skilled
personnel
Debour
Technicians
German
Technicians
Actual Work Remaining Work Work
RESOURCES
2,744 hrs
2,596 hrs
112 hrs
3,982 hrs
0 hrs 0 hrs 0 hrs0 hrs
1,032 hrs
3,592 hrs
4,578 hrs
4,200 hrs
0 hrs 128 hrs
2,744 hrs
3,628 hrs 3,704 hrs
8,560 hrs
4,200 hrs
0 hrs 128 hrs
0 hrs
1,000 hrs
2,000 hrs
3,000 hrs
4,000 hrs
5,000 hrs
6,000 hrs
7,000 hrs
8,000 hrs
9,000 hrs
SUBSTRUCTURE SUPERSTRUCTURE FINISHINGS
DOCUMENTS
M & E AIR CONDITIONING
AND VENTILATION
LIFT INSTALLATION FINAL WORKS
Actual Work Remaining Work Work
RESOURCES
As at July, 2016:
1. Out of cumulative overall
work of (22,964hrs),
(9,464hrs; 41%) of work
have been completed
leaving (13,500hrs; 59%)
of work remaining.
2. ‘Substructure’ had
consumed (2,744hrs) of
actual work against
(2,744hrs) of scheduled
work, making the activity
(100%) complete, as
‘there is no any work to
SUMMARY OF FINDINGS
1. The MS project software was used in this study to develop a
new construction programme of works with improved
efficiency for CBN Centre of Excellence.
2. The entire project is on time overrun of over 160days.
The study shows that over 41% of the amount of work
has been completed.
3. The Study also shows that on 35% of the entire project is
completed while 65% of the entire project activities are late
tasks.
CONCLUSION AND RECOMMENDATIONS
1. The application of MS Project software in the evaluation of
CPW enhances construction planning process, aids in fast
tracking, easy monitoring and handling of projects by project
managers.
2. Further exploration of MS Projects resource management
tool such as the leveling options, controlling the resource
pool and resource over-allocation.
3. Implementation of MS projects cost management tool to
monitor cost and budget, cash flow and cost overruns of
projects.

More Related Content

What's hot

Ms Project 2007(advanced)
Ms Project 2007(advanced)Ms Project 2007(advanced)
Ms Project 2007(advanced)Dinesh Singh
 
Calendar in Primavera P6 R15.2
Calendar in Primavera P6 R15.2Calendar in Primavera P6 R15.2
Calendar in Primavera P6 R15.2Nikhil Raj
 
Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6 Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6 Nikhil Raj
 
Speed To Market_Office_ROI
Speed To Market_Office_ROISpeed To Market_Office_ROI
Speed To Market_Office_ROIAustin Berke
 
ANAPLAN - 102: Introduction to Model Building
ANAPLAN - 102: Introduction to Model BuildingANAPLAN - 102: Introduction to Model Building
ANAPLAN - 102: Introduction to Model BuildingAlexis Choeung
 
Land Development Update-NAIOP/NVBIA Joint Meeting: Sept. 8, 2016
Land Development Update-NAIOP/NVBIA Joint Meeting: Sept. 8, 2016Land Development Update-NAIOP/NVBIA Joint Meeting: Sept. 8, 2016
Land Development Update-NAIOP/NVBIA Joint Meeting: Sept. 8, 2016Fairfax County
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iitKushal Patel
 
Project status one page
Project status one pageProject status one page
Project status one pageBim Akinfenwa
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training pptglobalp7
 
Rohit Naik updated Resume
Rohit Naik updated ResumeRohit Naik updated Resume
Rohit Naik updated ResumeRohit Naik
 
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraUse of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraAmit Kumar Senapati, PMP®
 

What's hot (15)

Shipments app door Tim Mercken
Shipments app door Tim MerckenShipments app door Tim Mercken
Shipments app door Tim Mercken
 
Ms Project 2007(advanced)
Ms Project 2007(advanced)Ms Project 2007(advanced)
Ms Project 2007(advanced)
 
Calendar in Primavera P6 R15.2
Calendar in Primavera P6 R15.2Calendar in Primavera P6 R15.2
Calendar in Primavera P6 R15.2
 
Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6 Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6
 
Speed To Market_Office_ROI
Speed To Market_Office_ROISpeed To Market_Office_ROI
Speed To Market_Office_ROI
 
ANAPLAN - 102: Introduction to Model Building
ANAPLAN - 102: Introduction to Model BuildingANAPLAN - 102: Introduction to Model Building
ANAPLAN - 102: Introduction to Model Building
 
cv avik
cv avikcv avik
cv avik
 
Land Development Update-NAIOP/NVBIA Joint Meeting: Sept. 8, 2016
Land Development Update-NAIOP/NVBIA Joint Meeting: Sept. 8, 2016Land Development Update-NAIOP/NVBIA Joint Meeting: Sept. 8, 2016
Land Development Update-NAIOP/NVBIA Joint Meeting: Sept. 8, 2016
 
David Choi
David ChoiDavid Choi
David Choi
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
 
Project status one page
Project status one pageProject status one page
Project status one page
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training ppt
 
Rohit Naik updated Resume
Rohit Naik updated ResumeRohit Naik updated Resume
Rohit Naik updated Resume
 
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraUse of forward pass and backward pass in primavera
Use of forward pass and backward pass in primavera
 

Similar to Project Defense

Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUPKeshav Seewraz
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfkripeshdubey1
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&tNishant Pandey
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800PRIYANSHU KUMAR
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPSagar Kaptan
 
Project Management Project 1 Report
Project Management Project 1 Report Project Management Project 1 Report
Project Management Project 1 Report Sharon Yu Jung Lim
 
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...
IRJET- Optimization of Time and Cost of Building Construction using Fast ...IRJET Journal
 
Scheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise BuildingScheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise Buildingiosrjce
 
Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...Emre Dirlik
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Schedulingijtsrd
 
76 s201905
76 s20190576 s201905
76 s201905IJRAT
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...IRJET Journal
 
Work scheduling(2)
Work scheduling(2)Work scheduling(2)
Work scheduling(2)ngiyari
 
Software Project Management: Project Summary
Software Project Management: Project SummarySoftware Project Management: Project Summary
Software Project Management: Project SummaryMinhas Kamal
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-controlJatindra Malik
 

Similar to Project Defense (20)

Project management Report - GROUP
Project management Report - GROUPProject management Report - GROUP
Project management Report - GROUP
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
 
Vocational training report l&t
Vocational training report l&tVocational training report l&t
Vocational training report l&t
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Project Management Project 1 Report
Project Management Project 1 Report Project Management Project 1 Report
Project Management Project 1 Report
 
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
 
A012610106
A012610106A012610106
A012610106
 
Scheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise BuildingScheduling and Financial Analysis of a High Rise Building
Scheduling and Financial Analysis of a High Rise Building
 
Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...Project Management Leadership, And Skills : Planning And Control | Assignment...
Project Management Leadership, And Skills : Planning And Control | Assignment...
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
 
76 s201905
76 s20190576 s201905
76 s201905
 
Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012
 
Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...Research study on Optimization of Cost and Duration with Line of Balance by U...
Research study on Optimization of Cost and Duration with Line of Balance by U...
 
TEAM LEADERSHIP
TEAM LEADERSHIPTEAM LEADERSHIP
TEAM LEADERSHIP
 
Work scheduling(2)
Work scheduling(2)Work scheduling(2)
Work scheduling(2)
 
Software Project Management: Project Summary
Software Project Management: Project SummarySoftware Project Management: Project Summary
Software Project Management: Project Summary
 
Project planning-and-control
Project planning-and-controlProject planning-and-control
Project planning-and-control
 
Primavera trainer
Primavera trainerPrimavera trainer
Primavera trainer
 
DZ04-Program narrative_R1
DZ04-Program narrative_R1DZ04-Program narrative_R1
DZ04-Program narrative_R1
 

Project Defense

  • 1. EVALUATION OF CONSTRUCTION PROGRAMME OF WORKS FOR CENTRE OF EXCELLENCE USING MICROSOFT PROJECT. BY KOTOKO, ALI ZANNAH U11BD1017 SUPERVISOR: DR. DALHAT ABDULSALAM
  • 2. BACKGROUND TO THE STUDY 1. The construction industry is being transformed to meet the new demands of the twenty-first century (Levy, 2007). 2. Time is vitally important for all participant in the construction process. 3. Improper time management, many problems will occur such as extension of time or time overrun. 4. Time overrun become the most general problem in construction industry worldwide (Olawale & Sun, 2010) 5. A myriad of details are considered in planning and developing a realistic schedule, and then in monitoring the progress of the project.
  • 3. Aim To assess the application of MS Project in construction program of works for Centre of Excellence with a view of optimizing the progress of building production process. Objectives 1. To develop a construction program of works for Centre of excellence. 2. To compare the construction program of works developed by this study with that developed by the contractors. 3. To evaluate the level of implementation and compliance of the construction program of works.
  • 4. LITERATURE REVIEW 1. Construction Project Life Cycle 2. Construction Programme For Building Projects 3. CPM and PERT Networks 4. Bar/Gantt Chart 5. Line-of-Balance (LOB) 6. Developing The Construction Programme
  • 5. RESEARCH METHODOLOGY Research Design 1. The case study was selected using a checklist of a set of formulated criteria. 2. The use of checklist to compare the developed and the actual POW. 3. The use of MS Project software to evaluate the implementation and measure progress of work; by identifying: a. Project Status b. Late Activities/Task c. Resource Allocations
  • 6. Microsoft Project Steps Overview 1. Starting a new plan and setting its start date 2. Entering the plan’s title and other properties 3. Enter task names, durations, and start and finish values 4. Create summary tasks to outline a task list. 5. Resource assignment 6. Viewing the project’s critical path
  • 7. PRESENTATION, ANALYSIS AND DISCUSSION OF RESULTS 1. The project: A five-storey semi- circular shaped hostel building with an internal radius of 24.5m located at NDA Kaduna. 2. Calculation Sheet: Quantities are extracted directly from working drawings.
  • 8. CPW on MS Project 1. Red bars: Duration of activities 2. Yellow line: Progress of work recorded. 3. Blue: Summary Task.
  • 9. Comparison of Programmes of Works 1. MS Project comparison report. 2. Shows the differences in duration and start day. 3. Difference increasingly negative.
  • 10. Checklist for Project status As at July, 2016: The percentage of duration of the overall project completed is calculated to be (124%), having an overall scheduled duration of (676days), with over (835days) being exhausted hence creating a time overrun of over (160days).
  • 11. LATE ACTIVITIES/TASK Tasks that are late as compared to the status date. A task is late if its finish date has passed or it is not progressing as planned. As at July 2016: 1. (35%) of activities completed. 2. (65%) of activities of the overall project are automatically late.
  • 12. Resources Usage Overview 824 hrs 960 hrs 1,012 hrs 120 hrs 1,376 hrs 136 hrs 328 hrs 128 hrs 56 hrs 0 hrs 80 hrs 320 hrs 112 hrs 3,982 hrs 0 hrs472 hrs 200 hrs 1,760 hrs 0 hrs 0 hrs 48 hrs 48 hrs 16 hrs 0 hrs 48 hrs 16 hrs 0 hrs 2,144 hrs 4,578 hrs 4,200 hrs 1,296 hrs 1,160 hrs 2,772 hrs 120 hrs 1,376 hrs 184 hrs 376 hrs 144 hrs 56 hrs 48 hrs 96 hrs 320 hrs 2,256 hrs 8,560 hrs 4,200 hrs 0 hrs 1,000 hrs 2,000 hrs 3,000 hrs 4,000 hrs 5,000 hrs 6,000 hrs 7,000 hrs 8,000 hrs 9,000 hrs Masons Iron Benders Carpenters Unskilled Labourers Excavators Concrete Pumper Concrete Mixers Small Concrete Mixers Dumper Batching Plant Crane Surveyors Other skilled personnel Debour Technicians German Technicians Actual Work Remaining Work Work RESOURCES 2,744 hrs 2,596 hrs 112 hrs 3,982 hrs 0 hrs 0 hrs 0 hrs0 hrs 1,032 hrs 3,592 hrs 4,578 hrs 4,200 hrs 0 hrs 128 hrs 2,744 hrs 3,628 hrs 3,704 hrs 8,560 hrs 4,200 hrs 0 hrs 128 hrs 0 hrs 1,000 hrs 2,000 hrs 3,000 hrs 4,000 hrs 5,000 hrs 6,000 hrs 7,000 hrs 8,000 hrs 9,000 hrs SUBSTRUCTURE SUPERSTRUCTURE FINISHINGS DOCUMENTS M & E AIR CONDITIONING AND VENTILATION LIFT INSTALLATION FINAL WORKS Actual Work Remaining Work Work RESOURCES As at July, 2016: 1. Out of cumulative overall work of (22,964hrs), (9,464hrs; 41%) of work have been completed leaving (13,500hrs; 59%) of work remaining. 2. ‘Substructure’ had consumed (2,744hrs) of actual work against (2,744hrs) of scheduled work, making the activity (100%) complete, as ‘there is no any work to
  • 13. SUMMARY OF FINDINGS 1. The MS project software was used in this study to develop a new construction programme of works with improved efficiency for CBN Centre of Excellence. 2. The entire project is on time overrun of over 160days. The study shows that over 41% of the amount of work has been completed. 3. The Study also shows that on 35% of the entire project is completed while 65% of the entire project activities are late tasks.
  • 14. CONCLUSION AND RECOMMENDATIONS 1. The application of MS Project software in the evaluation of CPW enhances construction planning process, aids in fast tracking, easy monitoring and handling of projects by project managers. 2. Further exploration of MS Projects resource management tool such as the leveling options, controlling the resource pool and resource over-allocation. 3. Implementation of MS projects cost management tool to monitor cost and budget, cash flow and cost overruns of projects.