SlideShare a Scribd company logo
1 of 20
Download to read offline
Project report for
K.M.D.A. PROJECT, PARK CIRCUS-ROB
FLYOVER
Prepared by RAJDIP DAS
ROLL- 14ID60R04
M.TECH - Summer Internship
R.C.G. SCHOOL OF INFRASTRUCTURE DESIGN AND MANAGEMENT
I.I.T. KHARAGPUR
ACKNOWLEDGMENT
Rajdip Das - Internship Project Report (L&T) 2
Mr. S.Ghosh
Mr. P.Dutta
Mr. R.Rakshit
Mr. H.Bhattacharya
Mr. Shankar Jha
Rajdip Das - Internship Project Report (L&T) 3
CONTENTS
Project brief............................................................................................................... 4
Pile………………………………………………………………………………………………………………………..8
Pier……………………………………………………………………………………………………………………….10
Deck Construction…………………………………………………………………………………………………13
Crash Barrier Construction………………………………………………………………………………......14
Fabrication…………………………………………………………………………………………………………….15
Heavy machineries…………………………………………………………………………………………………16
Safety…………………………………………………………………………………………………………………….17
Social responsibilities - world environment day………………………………………….....19
My internship experience ………………………………………………………………………………20
• Project taken up by KMDA in 2007
• Project started in 2010
• Construction started in 2012
• Projected date of project completion - 2015
• Total Project Cost – 86 crore
• Project location – Park Circus, Kolkata
PROJECT BRIEF
Rajdip Das - Internship Project Report (L&T) 4
Fig 1. Fig 2.
PLAN
ELEVATION
Rajdip Das - Internship Project Report (L&T) 5
Fig 4.
Fig 3.
LENGTH OF THE SPAN BETWEEN PIERS
PP104 TO C3 – 35258mm X 1
C4 TO C2 – 21954mm X 2
C2 TO P18 – 32374mm X 1
P18 TO P9 – 27500mm X 9
P9 TO P8 – 70000mm X 1
P8 TO C1 – 27500mm X 8
C1 X P87 – 30126mm X 1
NUMBER OF PILES
C4 – 8 piles
C3 – 6 piles
C2 – 8 piles
P18, P17, P16 – 8 piles each
P15, P14, P13, P12, P11, P10 – 6 piles each
Rajdip Das - Internship Project Report (L&T) 6
Fig 6.
Fig 5.
PCC SLAB
GIRDER
BEARING PEDESTAL
PIER CAP
PIER
PILE CAP
PILE
SEISMIC ARREST
Rajdip Das - Internship Project Report (L&T) 7
Fig 7.
PILE
PLAN OF THE PILE CAP ‘C4’
Diameter of the piles – 1200mm
Depth of the pile – 41metres
All dimensions are in mm
Rajdip Das - Internship Project Report (L&T) 8
Fig 8.
PHASES OF PILE FOUNDATION
CONSTRUCTION “C4”
1 4
5
3
6
2
1) Casing followed by boring.
2) Mud circulation mixing bentonite to
prevent collapse of the subsiding soil.
3) Cage lowering.
4) Breaking of pile head as it contains lame
concrete.
5) Shoring.
6) Reinforcement process being done for
the pile cap.
Rajdip Das - Internship Project Report (L&T)
9
Fig 10.
Fig 9.
Fig 12.
Fig 13.
Fig 14.
Fig 11.
PIER
1 3
42
1) REINFORCEMENT OF
THE PIER
2) SHUTTERING OF THE
PIER
3) REINFORCEMENT
AND SHUTTERING OF
THE PIER CAP
4) FINISHED PIER
CONCRETE AND PIER
CAP.
Rajdip Das - Internship Project Report (L&T) 10
Fig 15. Fig 16.
Fig 17.
Fig 18.
CONSTRUCTION SEQUENCE SUB-STRUCTURE
• STAGE 1 – In this stage pier is to be casted
• STAGE 2- In this stage pier cap is to be casted by providing temporary support
• STAGE 3- Total number of cables 1, 2, 3, 4, 5, 6, 7, 8.
Cable number 2,4,6 & 8 are stressed to 45MPA (28 days)
• STAGE 4- PSC girders for superstructure on 7 point connector side to be casted
excluding deck slab and crash barrier.
• STAGE 5 – In this stage deck slab for superstructure on 7 point connector side to be
casted.
• STAGE 6 – Cables 1,3,5 & 7 are stressed to 76.5% of UTS
• STAGE 7- In this stage wearing coat and crash barrier for both spans to be casted.
PARAMETERS USED FOR DESIGN
• Coefficient of friction = 0.17/radius
• Anchorage slip = 6mm
• Concrete control Mix having 28days characteristic strength of 45N/sq.mm
• Pre-stressing steel of 15.2mm Diameter
• UTS – 260.7 Kn Yield Strength – 1860 MPA
• Area – 140 Sq M.
Rajdip Das - Internship Project Report (L&T) 11
PIER TYPE
ECCENTRIC PIER – Used where there is space constrain
due to existing condition and built forms.
CONCENTRIC PIER – Used where space is available.
Centre line of the pile cap , pier , pier cap and deck slab
is one single line.
Rajdip Das - Internship Project Report (L&T) 12
Fig 20.
Fig 19.
DECK CONSTRUCTION
Precast concrete girder used
between two adjacent piers.
They are placed on the
pedestal located on top of
the pier cap.
Precast concrete
slabs laid on the
girder
Reinforcement
over the PCC
slab for the
pavement
Expansion joint
Rajdip Das - Internship Project Report (L&T) 13
Fig 22. Fig 24.Fig 23.Fig 21.
PHASE WISE
CONSTRUCTION OF CRASH
BARRIER
1 2
3 4 5
Rajdip Das - Internship Project Report (L&T) 14
Fig 27.
Fig 26.
Fig 28.
Fig 25.
Fig 29.
FABRICATION
70m span
Starting from P8 to P9
Type – Bowstring
Total weight – 354 ton (Approximate)
Parts –
• Bottom chord girder
Bottom cross girder beam
• Hanger
• Bots – 8.8 Grade ( 16 mm to 24 mm diameter)
• Top Arch
• Top chord bracing
• IS2062BO Splice plate
• Bottom chord bracing
Labor type – All skilled labor
Heavy machinery used –
Crane- RT40 crane 40 ton capacity
Hydra 50 ton capacity
Rajdip Das - Internship Project Report (L&T) 15
Fig 31.
Fig 30.
HEAVY MACHINERY USED
EXCAVATOR
RT40 CRANE
used for
fabrication
Hydraulic
rotary drilling
rig
Rajdip Das - Internship Project Report (L&T) 16
Fig 34.
Fig 33.
Fig 32.
Life line
Tag line
LIFE-LINE – In circumstances where a guard-rail cannot be provided at the same time there is
high risk of a “fall” , fall protection lifeline systems are installed as the next line of fall
protection. Lifeline systems can be used to arrest workers in the event of a fall or restrain
workers from reaching a fall hazard.
TAG-LINE – Rope attached to the beam/truss that is being lifted. The rope is used by a worker on
the ground to control the item as it swings up.
Rajdip Das - Internship Project Report (L&T) 17
Fig 35. Fig 36.
SAFETY
SINAGES to make public aware
about safety and changes in the
pedestrian ways due to
construction
Mesh/Net used to prevent the
materials and workers from
having a free fall
Barricades used
assure better
work
environment and
safety
Compulsory rule
for the staffs and
workers to Wear
helmet at the
construction site
to assure safety
Rajdip Das - Internship Project Report (L&T) 18
Fig 37. Fig 38.
Fig 39.
SOCIAL RESPONSIBILITIES - WORLD ENVIRONMENT DAY
L&T group and their employees at site are aware about the environmental degradation that is
happening all around the world. So on the world environment day they undertook a unique
initiative of planting numerous plants across the sites.
It was great initiative, where right from the senior most site engineer to the labors, everyone
took part whole heartedly.
The engineers gave speech to the labors about the environmental awareness and tried to
make them aware about the importance of the environment.
Rajdip Das - Internship Project Report (L&T) 19
Fig 40. Fig 42.Fig 41.
Rajdip Das - Internship Project Report (L&T) 20
I had a lifetime experience during my internship stint of two months at L&T. I was reporting at
the park circus site where a flyover construction is being executed and presently it is at the final
stage of construction and at the verge of completion.
Dedicated employees and strict work ethics are the very first thing that I have observed about L&T
during my internship. Quality and safety are two extremely important criterion for the
organization. Timely completion of work and meeting the project deadlines set by KMDA is another
parameter in which L&T is successful .
When it comes to my personal knowledge gain from the internship, I consider myself extremely
lucky to get such an opportunity to stay at the site. I became aware about the construction
procedures, heavy machineries that are being used, how work is distributed among the
subcontractors, labor policies that are untaken at the site and also the social responsibilities like
plantation of new trees on the world environment day. The precautionary measures and guidelines
of L&T ensuring safety of the workers and the employees at site is something that has amazed me.
I would like to express my gratitude to Mr. P.Dutta Sir and MR. Ghosh Sir for giving me an
opportunity to stay at the site, and last but not the least Mr. R. Rakshit Sir for helping me out at the
site in all possible ways.
RAJDIP DAS
M.TECH, INTERN
IIT KGP
My internship experience

More Related Content

What's hot

Training project report NHAI by Amit Kumar
Training project report NHAI by Amit KumarTraining project report NHAI by Amit Kumar
Training project report NHAI by Amit KumarAmitKumar7069
 
CONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGECONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGEAnkit Gautam
 
Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCCRakshita Raghunath
 
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015Mohd Murtaza
 
widening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage systemwidening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage systemeakram akhtar
 
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...Bharat Badre
 
training report civil engg. 7th sem
training report civil engg. 7th semtraining report civil engg. 7th sem
training report civil engg. 7th semRajat kashv
 
AjayasankarK M _ Engineer
AjayasankarK M _ EngineerAjayasankarK M _ Engineer
AjayasankarK M _ EngineerAjay Sankar
 
Deepak_CV_05-04-16_des
Deepak_CV_05-04-16_desDeepak_CV_05-04-16_des
Deepak_CV_05-04-16_desDeepak Jotawar
 
Rajapeth flyover ROB(by akash Kolamkar) an research report
Rajapeth flyover ROB(by akash Kolamkar)  an research report Rajapeth flyover ROB(by akash Kolamkar)  an research report
Rajapeth flyover ROB(by akash Kolamkar) an research report Bharat Badre
 
TRAINING REPORT A PROJECT ON ROAD WIDENI...
                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...
TRAINING REPORT A PROJECT ON ROAD WIDENI...Pradeep Yadav
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report KRISHNA MURARI
 

What's hot (20)

Training project report NHAI by Amit Kumar
Training project report NHAI by Amit KumarTraining project report NHAI by Amit Kumar
Training project report NHAI by Amit Kumar
 
Kpr resume tunnel engineer
Kpr resume tunnel engineerKpr resume tunnel engineer
Kpr resume tunnel engineer
 
CONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGECONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGE
 
Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCC
 
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
RESUME Senior Geotechnical & Material NATM Tunnel Engineer 21032015
 
widening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage systemwidening of flexible pavement AND construction of drainage system
widening of flexible pavement AND construction of drainage system
 
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...
(by mr.akash kolamkar) Rajapeth amravati rob flyover amravati presentation ps...
 
Shib
ShibShib
Shib
 
Flexible pavement
Flexible pavement  Flexible pavement
Flexible pavement
 
training report civil engg. 7th sem
training report civil engg. 7th semtraining report civil engg. 7th sem
training report civil engg. 7th sem
 
Project report
Project reportProject report
Project report
 
Revised Resume
Revised ResumeRevised Resume
Revised Resume
 
AjayasankarK M _ Engineer
AjayasankarK M _ EngineerAjayasankarK M _ Engineer
AjayasankarK M _ Engineer
 
Deepak_CV_05-04-16_des
Deepak_CV_05-04-16_desDeepak_CV_05-04-16_des
Deepak_CV_05-04-16_des
 
Rajapeth flyover ROB(by akash Kolamkar) an research report
Rajapeth flyover ROB(by akash Kolamkar)  an research report Rajapeth flyover ROB(by akash Kolamkar)  an research report
Rajapeth flyover ROB(by akash Kolamkar) an research report
 
UNDERPASS DESIGN
UNDERPASS DESIGNUNDERPASS DESIGN
UNDERPASS DESIGN
 
TRAINING REPORT A PROJECT ON ROAD WIDENI...
                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...
TRAINING REPORT A PROJECT ON ROAD WIDENI...
 
Training PPT
Training PPTTraining PPT
Training PPT
 
civil enginnering industrial training report
civil enginnering industrial training report civil enginnering industrial training report
civil enginnering industrial training report
 
Flexible pavement
Flexible pavementFlexible pavement
Flexible pavement
 

Viewers also liked

Daytime Impairment due to College Student Technology Use during S(1)
Daytime Impairment due to College Student Technology Use during S(1)Daytime Impairment due to College Student Technology Use during S(1)
Daytime Impairment due to College Student Technology Use during S(1)Rachel Feragne
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION L&W BUILDING SOLUTIONS PVT. LMT.
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTIONAbhishek Singh
 
Summer internship report L&T
Summer internship report L&TSummer internship report L&T
Summer internship report L&TUmed Paliwal
 

Viewers also liked (7)

Daytime Impairment due to College Student Technology Use during S(1)
Daytime Impairment due to College Student Technology Use during S(1)Daytime Impairment due to College Student Technology Use during S(1)
Daytime Impairment due to College Student Technology Use during S(1)
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
 
flyover and bridge problems and its solutions
flyover and bridge problems and its solutionsflyover and bridge problems and its solutions
flyover and bridge problems and its solutions
 
Flyover bridge
Flyover bridgeFlyover bridge
Flyover bridge
 
Metro presentation
Metro presentationMetro presentation
Metro presentation
 
Summer internship report L&T
Summer internship report L&TSummer internship report L&T
Summer internship report L&T
 

Similar to L&t PARKCIRCUS

IRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET Journal
 
Structural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete StructureStructural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete StructureIJERA Editor
 
Internship report 2015 (1)
Internship report 2015 (1)Internship report 2015 (1)
Internship report 2015 (1)Navneet Kumar
 
ANALYSIS AND DESIGN OF BRIDGE FOUNDATION
ANALYSIS AND DESIGN OF BRIDGE FOUNDATIONANALYSIS AND DESIGN OF BRIDGE FOUNDATION
ANALYSIS AND DESIGN OF BRIDGE FOUNDATIONScott Donald
 
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...IRJET Journal
 
Development of Demolished Concrete Mix Using Pre-Coating Technique
Development of Demolished Concrete Mix Using Pre-Coating TechniqueDevelopment of Demolished Concrete Mix Using Pre-Coating Technique
Development of Demolished Concrete Mix Using Pre-Coating TechniqueIRJET Journal
 
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEIRJET Journal
 
IRJET- A Basic Study on Fly Ash Lime Gypsum Composite with Sodium Carbonate a...
IRJET- A Basic Study on Fly Ash Lime Gypsum Composite with Sodium Carbonate a...IRJET- A Basic Study on Fly Ash Lime Gypsum Composite with Sodium Carbonate a...
IRJET- A Basic Study on Fly Ash Lime Gypsum Composite with Sodium Carbonate a...IRJET Journal
 
Review Paper on Implementation Technology to Repair Pothole Using Waste Plastic
Review Paper on Implementation Technology to Repair Pothole Using Waste PlasticReview Paper on Implementation Technology to Repair Pothole Using Waste Plastic
Review Paper on Implementation Technology to Repair Pothole Using Waste PlasticIRJET Journal
 
IRJET-To Study Various Construction Equipment used in Metro Project
IRJET-To Study Various Construction Equipment used in Metro ProjectIRJET-To Study Various Construction Equipment used in Metro Project
IRJET-To Study Various Construction Equipment used in Metro ProjectIRJET Journal
 
Design of RCC Beam By using C Programming
Design of RCC Beam By using C ProgrammingDesign of RCC Beam By using C Programming
Design of RCC Beam By using C ProgrammingIRJET Journal
 
Board and pillar working with lhd and sdl. Mining engineering final year project
Board and pillar working with lhd and sdl. Mining engineering final year projectBoard and pillar working with lhd and sdl. Mining engineering final year project
Board and pillar working with lhd and sdl. Mining engineering final year projectAnuragGupta39373
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technologyAbhishek Paul
 
IRJET- Analysis of Flood Resistant Rehab Shelter
IRJET- Analysis of Flood Resistant Rehab ShelterIRJET- Analysis of Flood Resistant Rehab Shelter
IRJET- Analysis of Flood Resistant Rehab ShelterIRJET Journal
 
IRJET- Design and Analysis of Overhead Water Tank at Phule Nagar, Ambernath
IRJET-  	  Design and Analysis of Overhead Water Tank at Phule Nagar, AmbernathIRJET-  	  Design and Analysis of Overhead Water Tank at Phule Nagar, Ambernath
IRJET- Design and Analysis of Overhead Water Tank at Phule Nagar, AmbernathIRJET Journal
 
IJSRED-V2I2P21
IJSRED-V2I2P21IJSRED-V2I2P21
IJSRED-V2I2P21IJSRED
 
Design of Sugarcane Roots Remover
Design of Sugarcane Roots RemoverDesign of Sugarcane Roots Remover
Design of Sugarcane Roots RemoverIRJET Journal
 
IRJET- Design of Box Culvert using Visual Basic
IRJET- Design of Box Culvert using Visual BasicIRJET- Design of Box Culvert using Visual Basic
IRJET- Design of Box Culvert using Visual BasicIRJET Journal
 

Similar to L&t PARKCIRCUS (20)

IRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing Technique
 
Structural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete StructureStructural Design and Rehabilitation of Reinforced Concrete Structure
Structural Design and Rehabilitation of Reinforced Concrete Structure
 
Internship report 2015 (1)
Internship report 2015 (1)Internship report 2015 (1)
Internship report 2015 (1)
 
ANALYSIS AND DESIGN OF BRIDGE FOUNDATION
ANALYSIS AND DESIGN OF BRIDGE FOUNDATIONANALYSIS AND DESIGN OF BRIDGE FOUNDATION
ANALYSIS AND DESIGN OF BRIDGE FOUNDATION
 
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
RENOVATION OF OLD LIME STONE PORTICO SLAB AT ST THOMAS MOUNT WITH FILLER BLOC...
 
Final report
Final reportFinal report
Final report
 
Development of Demolished Concrete Mix Using Pre-Coating Technique
Development of Demolished Concrete Mix Using Pre-Coating TechniqueDevelopment of Demolished Concrete Mix Using Pre-Coating Technique
Development of Demolished Concrete Mix Using Pre-Coating Technique
 
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPEAN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
AN INVESTIGATION ON SEISMIC STABILITY OF MINE OVERBURDEN DUMP SLOPE
 
IRJET- A Basic Study on Fly Ash Lime Gypsum Composite with Sodium Carbonate a...
IRJET- A Basic Study on Fly Ash Lime Gypsum Composite with Sodium Carbonate a...IRJET- A Basic Study on Fly Ash Lime Gypsum Composite with Sodium Carbonate a...
IRJET- A Basic Study on Fly Ash Lime Gypsum Composite with Sodium Carbonate a...
 
Tanya project report
Tanya project reportTanya project report
Tanya project report
 
Review Paper on Implementation Technology to Repair Pothole Using Waste Plastic
Review Paper on Implementation Technology to Repair Pothole Using Waste PlasticReview Paper on Implementation Technology to Repair Pothole Using Waste Plastic
Review Paper on Implementation Technology to Repair Pothole Using Waste Plastic
 
IRJET-To Study Various Construction Equipment used in Metro Project
IRJET-To Study Various Construction Equipment used in Metro ProjectIRJET-To Study Various Construction Equipment used in Metro Project
IRJET-To Study Various Construction Equipment used in Metro Project
 
Design of RCC Beam By using C Programming
Design of RCC Beam By using C ProgrammingDesign of RCC Beam By using C Programming
Design of RCC Beam By using C Programming
 
Board and pillar working with lhd and sdl. Mining engineering final year project
Board and pillar working with lhd and sdl. Mining engineering final year projectBoard and pillar working with lhd and sdl. Mining engineering final year project
Board and pillar working with lhd and sdl. Mining engineering final year project
 
presentation on shotcrete technology
presentation on shotcrete technologypresentation on shotcrete technology
presentation on shotcrete technology
 
IRJET- Analysis of Flood Resistant Rehab Shelter
IRJET- Analysis of Flood Resistant Rehab ShelterIRJET- Analysis of Flood Resistant Rehab Shelter
IRJET- Analysis of Flood Resistant Rehab Shelter
 
IRJET- Design and Analysis of Overhead Water Tank at Phule Nagar, Ambernath
IRJET-  	  Design and Analysis of Overhead Water Tank at Phule Nagar, AmbernathIRJET-  	  Design and Analysis of Overhead Water Tank at Phule Nagar, Ambernath
IRJET- Design and Analysis of Overhead Water Tank at Phule Nagar, Ambernath
 
IJSRED-V2I2P21
IJSRED-V2I2P21IJSRED-V2I2P21
IJSRED-V2I2P21
 
Design of Sugarcane Roots Remover
Design of Sugarcane Roots RemoverDesign of Sugarcane Roots Remover
Design of Sugarcane Roots Remover
 
IRJET- Design of Box Culvert using Visual Basic
IRJET- Design of Box Culvert using Visual BasicIRJET- Design of Box Culvert using Visual Basic
IRJET- Design of Box Culvert using Visual Basic
 

L&t PARKCIRCUS

  • 1. Project report for K.M.D.A. PROJECT, PARK CIRCUS-ROB FLYOVER Prepared by RAJDIP DAS ROLL- 14ID60R04 M.TECH - Summer Internship R.C.G. SCHOOL OF INFRASTRUCTURE DESIGN AND MANAGEMENT I.I.T. KHARAGPUR
  • 2. ACKNOWLEDGMENT Rajdip Das - Internship Project Report (L&T) 2 Mr. S.Ghosh Mr. P.Dutta Mr. R.Rakshit Mr. H.Bhattacharya Mr. Shankar Jha
  • 3. Rajdip Das - Internship Project Report (L&T) 3 CONTENTS Project brief............................................................................................................... 4 Pile………………………………………………………………………………………………………………………..8 Pier……………………………………………………………………………………………………………………….10 Deck Construction…………………………………………………………………………………………………13 Crash Barrier Construction………………………………………………………………………………......14 Fabrication…………………………………………………………………………………………………………….15 Heavy machineries…………………………………………………………………………………………………16 Safety…………………………………………………………………………………………………………………….17 Social responsibilities - world environment day………………………………………….....19 My internship experience ………………………………………………………………………………20
  • 4. • Project taken up by KMDA in 2007 • Project started in 2010 • Construction started in 2012 • Projected date of project completion - 2015 • Total Project Cost – 86 crore • Project location – Park Circus, Kolkata PROJECT BRIEF Rajdip Das - Internship Project Report (L&T) 4 Fig 1. Fig 2.
  • 5. PLAN ELEVATION Rajdip Das - Internship Project Report (L&T) 5 Fig 4. Fig 3.
  • 6. LENGTH OF THE SPAN BETWEEN PIERS PP104 TO C3 – 35258mm X 1 C4 TO C2 – 21954mm X 2 C2 TO P18 – 32374mm X 1 P18 TO P9 – 27500mm X 9 P9 TO P8 – 70000mm X 1 P8 TO C1 – 27500mm X 8 C1 X P87 – 30126mm X 1 NUMBER OF PILES C4 – 8 piles C3 – 6 piles C2 – 8 piles P18, P17, P16 – 8 piles each P15, P14, P13, P12, P11, P10 – 6 piles each Rajdip Das - Internship Project Report (L&T) 6 Fig 6. Fig 5.
  • 7. PCC SLAB GIRDER BEARING PEDESTAL PIER CAP PIER PILE CAP PILE SEISMIC ARREST Rajdip Das - Internship Project Report (L&T) 7 Fig 7.
  • 8. PILE PLAN OF THE PILE CAP ‘C4’ Diameter of the piles – 1200mm Depth of the pile – 41metres All dimensions are in mm Rajdip Das - Internship Project Report (L&T) 8 Fig 8.
  • 9. PHASES OF PILE FOUNDATION CONSTRUCTION “C4” 1 4 5 3 6 2 1) Casing followed by boring. 2) Mud circulation mixing bentonite to prevent collapse of the subsiding soil. 3) Cage lowering. 4) Breaking of pile head as it contains lame concrete. 5) Shoring. 6) Reinforcement process being done for the pile cap. Rajdip Das - Internship Project Report (L&T) 9 Fig 10. Fig 9. Fig 12. Fig 13. Fig 14. Fig 11.
  • 10. PIER 1 3 42 1) REINFORCEMENT OF THE PIER 2) SHUTTERING OF THE PIER 3) REINFORCEMENT AND SHUTTERING OF THE PIER CAP 4) FINISHED PIER CONCRETE AND PIER CAP. Rajdip Das - Internship Project Report (L&T) 10 Fig 15. Fig 16. Fig 17. Fig 18.
  • 11. CONSTRUCTION SEQUENCE SUB-STRUCTURE • STAGE 1 – In this stage pier is to be casted • STAGE 2- In this stage pier cap is to be casted by providing temporary support • STAGE 3- Total number of cables 1, 2, 3, 4, 5, 6, 7, 8. Cable number 2,4,6 & 8 are stressed to 45MPA (28 days) • STAGE 4- PSC girders for superstructure on 7 point connector side to be casted excluding deck slab and crash barrier. • STAGE 5 – In this stage deck slab for superstructure on 7 point connector side to be casted. • STAGE 6 – Cables 1,3,5 & 7 are stressed to 76.5% of UTS • STAGE 7- In this stage wearing coat and crash barrier for both spans to be casted. PARAMETERS USED FOR DESIGN • Coefficient of friction = 0.17/radius • Anchorage slip = 6mm • Concrete control Mix having 28days characteristic strength of 45N/sq.mm • Pre-stressing steel of 15.2mm Diameter • UTS – 260.7 Kn Yield Strength – 1860 MPA • Area – 140 Sq M. Rajdip Das - Internship Project Report (L&T) 11
  • 12. PIER TYPE ECCENTRIC PIER – Used where there is space constrain due to existing condition and built forms. CONCENTRIC PIER – Used where space is available. Centre line of the pile cap , pier , pier cap and deck slab is one single line. Rajdip Das - Internship Project Report (L&T) 12 Fig 20. Fig 19.
  • 13. DECK CONSTRUCTION Precast concrete girder used between two adjacent piers. They are placed on the pedestal located on top of the pier cap. Precast concrete slabs laid on the girder Reinforcement over the PCC slab for the pavement Expansion joint Rajdip Das - Internship Project Report (L&T) 13 Fig 22. Fig 24.Fig 23.Fig 21.
  • 14. PHASE WISE CONSTRUCTION OF CRASH BARRIER 1 2 3 4 5 Rajdip Das - Internship Project Report (L&T) 14 Fig 27. Fig 26. Fig 28. Fig 25. Fig 29.
  • 15. FABRICATION 70m span Starting from P8 to P9 Type – Bowstring Total weight – 354 ton (Approximate) Parts – • Bottom chord girder Bottom cross girder beam • Hanger • Bots – 8.8 Grade ( 16 mm to 24 mm diameter) • Top Arch • Top chord bracing • IS2062BO Splice plate • Bottom chord bracing Labor type – All skilled labor Heavy machinery used – Crane- RT40 crane 40 ton capacity Hydra 50 ton capacity Rajdip Das - Internship Project Report (L&T) 15 Fig 31. Fig 30.
  • 16. HEAVY MACHINERY USED EXCAVATOR RT40 CRANE used for fabrication Hydraulic rotary drilling rig Rajdip Das - Internship Project Report (L&T) 16 Fig 34. Fig 33. Fig 32.
  • 17. Life line Tag line LIFE-LINE – In circumstances where a guard-rail cannot be provided at the same time there is high risk of a “fall” , fall protection lifeline systems are installed as the next line of fall protection. Lifeline systems can be used to arrest workers in the event of a fall or restrain workers from reaching a fall hazard. TAG-LINE – Rope attached to the beam/truss that is being lifted. The rope is used by a worker on the ground to control the item as it swings up. Rajdip Das - Internship Project Report (L&T) 17 Fig 35. Fig 36. SAFETY
  • 18. SINAGES to make public aware about safety and changes in the pedestrian ways due to construction Mesh/Net used to prevent the materials and workers from having a free fall Barricades used assure better work environment and safety Compulsory rule for the staffs and workers to Wear helmet at the construction site to assure safety Rajdip Das - Internship Project Report (L&T) 18 Fig 37. Fig 38. Fig 39.
  • 19. SOCIAL RESPONSIBILITIES - WORLD ENVIRONMENT DAY L&T group and their employees at site are aware about the environmental degradation that is happening all around the world. So on the world environment day they undertook a unique initiative of planting numerous plants across the sites. It was great initiative, where right from the senior most site engineer to the labors, everyone took part whole heartedly. The engineers gave speech to the labors about the environmental awareness and tried to make them aware about the importance of the environment. Rajdip Das - Internship Project Report (L&T) 19 Fig 40. Fig 42.Fig 41.
  • 20. Rajdip Das - Internship Project Report (L&T) 20 I had a lifetime experience during my internship stint of two months at L&T. I was reporting at the park circus site where a flyover construction is being executed and presently it is at the final stage of construction and at the verge of completion. Dedicated employees and strict work ethics are the very first thing that I have observed about L&T during my internship. Quality and safety are two extremely important criterion for the organization. Timely completion of work and meeting the project deadlines set by KMDA is another parameter in which L&T is successful . When it comes to my personal knowledge gain from the internship, I consider myself extremely lucky to get such an opportunity to stay at the site. I became aware about the construction procedures, heavy machineries that are being used, how work is distributed among the subcontractors, labor policies that are untaken at the site and also the social responsibilities like plantation of new trees on the world environment day. The precautionary measures and guidelines of L&T ensuring safety of the workers and the employees at site is something that has amazed me. I would like to express my gratitude to Mr. P.Dutta Sir and MR. Ghosh Sir for giving me an opportunity to stay at the site, and last but not the least Mr. R. Rakshit Sir for helping me out at the site in all possible ways. RAJDIP DAS M.TECH, INTERN IIT KGP My internship experience