SlideShare a Scribd company logo
1 of 37
Download to read offline
1
NEMA Junction Box Sizing,NEMA Junction Box Sizing,
Conductor Bending Radii & FiberConductor Bending Radii & Fiber
Optic CableOptic Cable
from: NEC 2002 - Article 314.28, Article 314.54 & Article 770
WSDOT
Fall / Winter 2004
Presented by: Terry Thayer
2
The clear catinkus for Junction Box Sizing and DepthThe clear catinkus for Junction Box Sizing and Depth
u The definition of length
and width
W
L1
L1
L2
Junction box
Junction box
GRS conduit grounded end bushing size table
Size diameter inches
Inches External
add this number
for end bushing
size - then
round up to
nearest quarter
end
bushing
outside
diameter
1/2 0.840 0.75 1 1/2
3/4 1.050 0.75 1 3/4
1 1.315 0.75 2
1 1/4 1.660 0.75 2 1/2
1 1/2 1.900 0.75 2 3/4
2 2.375 0.75 3 1/4
2 1/2 2.875 1.00 4
3 3.500 1.25 4 3/4
3 1/2 4.000 1.25 5 1/4
4 4.500 1.75 6 1/4
5 5.563 2.00 7 1/2
6 6.625 2.00 8 3/4
Example: A 1 1/4" GRS conduit is 1.660" + 0.75" =
2.410". Round 2.410" up to 2.5" or 2 1/2 inches.
L(1) or L(2) = (8) largest conduit in row plus the sum of all
other conduits in row. Calculate for all rows and use sum
of largest row.
W=(6) largest conduit in row plus the sum of all other
conduits in row. Calculate for all rows and use sum of
largest row. NOTE: If no conduit enters the adjacent
sides of the box the dimension is width.
adjacent side
3
Junction Box LengthJunction Box Length -- straight pullstraight pull
β€’ If one or more of the conductors is a # 4 or larger,
β€’ Then the length is not less than 8x the diameter of
the largest conduit if a through pull, regardless of
the number of conduits or conductors. We use this
multiplier: (8x the largest conduit plus the sum of
all the other conduit diameters in the same row) for
all wire sizes to avoid future undersized junction
box problems.
β€’ This assumes no bending and minimal wire storage.
β€’ (NEC 2002 - Article 314.28 for sizing of junction boxes, Article 314.54 directs us to use
methods in Article 314.28.)
44
55
66
7
Junction Box LengthsJunction Box Lengths -- Angle or U PullAngle or U Pull
or with splicesor with splices
β€’ The distance is 6x the diameter of the largest conduit
in the row plus the sum of all the other conduit
diameters in the same row. (There are exceptions to
this in the NEC which we are not likely to encounter.)
β€’ Each row is calculated separately and the single row
that provides the maximum distance shall be used.
β€’ We seldom have more than 3 conduits in a side. This
minimizes conductor bending problems.
8
Exhibit 314.10
An example
showing
calculations
required by
314.28(A)(2)
for splices,
angle pulls or
U pulls.
From 2002 NEC
Handbook, page 313.
99
Water tight conduit
fitting (Meyers Hub)
10
1111
12
Junction Box DepthJunction Box Depth
β€’ The box needs only to be as deep as is needed to install the
conduits and their fittings.
β€’ Consider grounded end bushing size (diameter) in
relationship to the conduit.
β€’ Always round up to the nearest even dimension. Unless
space is restricted, round up to the next (second) even
dimension. (for a 1ΒΌ inch conduit with a 2ΒΌ inches O.D.
grounded end bushing round up to 4 inches as a minimum
but in most cases round up again and call out 6” as the
depth)
β€’ Junction boxes should be positioned to allow all conduits to
enter from the ends.
β€’ This reduces the effort required by the contractor during
construction, allows for easier conductor installation and
allows us to use smaller boxes.
13
Radius of Conduit Bends - NEC 344.24 and 352.24
Conduit
Size
Conduit
Size
One shot
& full shoe
bender
One shot
& full shoe
bender
Other
Bends
Other
Bends
Metric
Designator
Trade
Size mm inch mm inch
16 1/2 101.6 4 101.6 4
21 3/4 114.3 4 1/2 127 5
27 1 146.05 5 3/4 152.4 6
35 1 1/4 184.15 7 1/4 203.2 8
41 1 1/2 209.55 8 1/4 254 10
51 2 241.3 9 1/2 304.8 12
63 2 1/2 266.7 10 1/2 381 15
78 3 330.2 13 457.2 18
91 3 1/2 381 15 533.4 21
103 4 406.4 16 609.6 24
129 5 609.6 24 762 30
155 6 762 30 914.4 36
1) Use entire
chart for GRS
conduit. (NEC
344.24)
2) For field
bending of PVC,
use the β€œother
bends” columns
only. (NEC
352.24)
14
Radius of Conduit Bends - NEC 353.24 (2005)
Conduit
Size
Conduit
Size
Minimum
Bending
Radius
Minimum
Bending
Radius
Metric
Designator
Trade
Size mm inch
16 1/2 250 10
21 3/4 300 12
27 1 350 14
35 1 1/4 450 18
41 1 1/2 500 20
53 2 650 26
63 2 1/2 900 36
78 3 1200 48
103 4 1500 60
1) Use this chart
for HDPE conduit
only.
15
Conductor Bending RadiiConductor Bending Radii
β€’ There should be consideration given to the minimum
bending radii of the conductors.
β€’ When the junction box is sized properly this will not
usually be a problem.
β€’ This must still be checked to insure there is proper
space for conductor bend Radii.
16
Conductor Bending RadiiConductor Bending Radii
A =(6 x 4 In.) + 2 in.+2 In. +28 In. minimum
B =(6 x 4 In.) + 2 In. +2in.+ 28 In. minimum
C = 6 x 2 In. = 12 In. minimum required
between raceways enclosing the same
conductor
D = 6 x 2 In. = 12 In. minimum required
between raceways enclosing the same
conductor
E = 6 x 4 In. = 24 In. minimum required
between raceways
enclosing the same conductor
Exhibit 314.11 Raceway entries enclosing
the same conductors are required to have
a minimum separation between them. The
intent is to provide adequate space for the
conductor to make the bend.
1717
1818
1919
20
ConductorsConductors
2002 NEC 300.34 Conductor Bending Radius.
The conductor shall not be bent to a radius less than
8 times the overall diameter for nonshielded
conductors or 12 times the diameter for shielded or
lead covered conductors during or after installation.
For multicolor or multiplexed single conductor
cables having individually shielded conductors, the
minimum bending radius is 12 times the diameter of
the individually shielded or 7 times the overall
diameter, whichever is greater.
21
Conductors & CableConductors & Cable
CONDUCTORCONDUCTOR OUTSIDE DIAOUTSIDE DIA MULTIPLIERMULTIPLIER BENDING RADIUSBENDING RADIUS
# 8# 8 0.2660.266 88 2.128’’2.128’’
# 6# 6 0.3040.304 88 2.432’’2.432’’
# 4# 4 0.3520.352 88 2.816’’2.816’’
# 2# 2 0.4120.412 88 3.296”3.296”
(ind.cond.) (ind.conductor)(ind.cond.) (ind.conductor)
#2c(#14)#2c(#14) 0.326 ( 0.14)0.326 ( 0.14) 7(12)7(12) 2.282’’2.282’’
#3c(#20)#3c(#20) 0.35 ( 0.07)0.35 ( 0.07) 7(12)7(12) 2.45’’2.45’’
#4c(#18)#4c(#18) 0.41 ( 0.09)0.41 ( 0.09) 7(12)7(12) 2.87’’2.87’’
#5c(#14)#5c(#14) 0.51 ( 0.14)0.51 ( 0.14) 7(12)7(12) 3.57’’3.57’’
#7c(#14)#7c(#14) 0.55 ( 0.14)0.55 ( 0.14) 7(12)7(12) 3.85’’3.85’’
6pr(#19)6pr(#19) 0.56 ( 0.08)0.56 ( 0.08) 7(12)7(12) 3.92’’3.92’’
24 (SM) fiber24 (SM) fiber 0.470.47 2020 9.40”9.40”
48 (SM) fiber48 (SM) fiber 0.470.47 2020 9.40”9.40”
72 (SM) fiber72 (SM) fiber 0.470.47 2020 9.40”9.40”
96 (SM) fiber96 (SM) fiber 0.780.78 2020 15.60”15.60”
144 (SM) fiber144 (SM) fiber 0.780.78 2020 15.60”15.60”
22
ConductorsConductors
β€’ There should be consideration given for the slack
required in the conductors.
β€’ Standard specification 8-20.3(8) requires sufficient
slack wire be installed to allow any conductor to be
raised 18’’ outside of the junction box.
β€’ Discuss this with the electrical inspectors if you
have many circuits in one junction box / conduit
run.
β€’ If you had a through pull and 4 circuits, which does
happen, you would need space for 24’ of slack.
23
ConductorsConductors -- continuedcontinued
β€’ There was a case with 2 conduits passing through
one junction box carrying 11 conductors; that’s
33’ of slack in an 8’’x 8’’ x 18’’ JB.
β€’ The electrical inspectors will usually hold the
contractor to the slack called for in a standard
structure mounted (traffic barrier) junction box
(8’’x 8’’ x 18’’) because there are usually not
many conductors in the run.
β€’ Standard concrete junction boxes have the same
slack requirements as surface mounted boxes.
24
Fiber Optic CableFiber Optic Cable
β€’ The greater the radius of the conduit, the easier the pull.
β€’ Use cable vaults and pull boxes wherever possible – the
conduit then enters from the side of the box and eliminates
180 degrees of sweep at each box.
β€’ Use 36” radius conduit sweeps wherever possible. This is
the WSDOT standard for all jobs.
β€’ When unable to use 36” radius sweep, use a minimum of 20
times the outside diameter of the cable to calculate the
smallest radius that WSDOT will allow to be used. Note:
This usually only applies inside a building or cabinet.
25
Any questions?Any questions?
26
QUIZ #1 QUESTIONSQUIZ #1 QUESTIONS
u 1) Given: one 400watt HPS luminaire @ 480VAC w/50’
pole and 16’ mast arm, #6 copper conductor, 500’ run of wire
to base of luminaire pole. (all service cabinet terminations,
junction boxes & splice distances included in these lengths)
u Find: what is the voltage drop in this circuit?
u 2) Given: ITS service cabinet @120VAC - 1750 watt load.
u Find: size branch breaker
u 3) Given: 10 Kva transformer @ 240VAC - 8500 watt ITS
service cabinet.
u Find: size transformer branch breaker in service cabinet.
u 4) Given: 1 each 2 inch dia, 1 each 1 1/2inch, 1 each 1 inch
conduit - straight pull with splices.
u Find: size junction box.
27
Quiz #2 QuestionsQuiz #2 Questions
u 1) Given: one 400watt HPS luminaire @ 240VAC w/40’
pole and 16’ mast arm, #6 copper conductor, 350’ run of wire
to base of luminaire pole. (all service cabinet terminations,
junction boxes & splice distances included in these lengths)
u Find: what is the voltage drop in this circuit?
u 2) Given: ITS service cabinet @120VAC - 1750 watt load.
u Find: size branch breaker
u 3) Given: 15 Kva transformer @ 480VAC - 10748 watt load
for 5 ITS service cabinets. (1 ramp meter, 1 Camera
Cabinet, 2 Data Stations & 1 HAR Station)
u Find: size transformer branch breaker in service cabinet.
u 4) Given: 1 each 2 1/2 inch dia, 2 each 2 inch, 1 each 1 1/2
inch conduit - straight pull with splices.
u Find: size junction box.
28
QUIZ #1QUIZ #1 QUESTION ANSWERSQUESTION ANSWERS
u 1) Given: one 400watt HPS luminaire @ 480VAC w/50’
pole and 16’ mast arm, #6 AWG copper conductor, 500’ run
of wire to base of luminaire pole. (all service cabinet
terminations, junction boxes & splice distances included in
these lengths)
u Find: what is the voltage drop in this circuit?
u Within LINE LOSS section, see illumination load chart,
slide 20, for luminaire load (amperage).
u Answer: 400watt luminaire @ 480 volts = 1.1 amp
u Vd #6 AWG =2ALR Vd= 2 x 1.1 x 500 x 0.000510
u Vd #10 AWG =2ALR Vd= 2 x 1.1 x 62 x 0.001290
u Vd #6 AWG=0.561000 volts.Vd #10 AWG=0.175956 volts
u Vd total = 0.74 volts
29
QUIZ #1QUIZ #1 QUESTION ANSWERSQUESTION ANSWERS
u2) Given: ITS service cabinet @120 VAC - 1750
watt load.
uFind: size branch breaker
uAnswer:
uUnit load=1750watts/120volts=14.58amps.
uITS breaker= 14.58 amps continuous load x 125%
factor = 18.2amps.
uBranch breaker = 20 amps
30
QUIZ #1QUIZ #1 QUESTION ANSWERSQUESTION ANSWERS
u3) Given: 10 Kva transformer @ 240 VAC - 8500
watt ITS service cabinet.
uFind: size transformer branch breaker in service
cabinet.
uAnswer:
uUnit load = 10000watts/240volts = 41.66amps.
uITS breaker = 41.66 amps load x 125% factor =
52.08 amps.
uBranch breaker = 60 amps
31
QUIZ #1QUIZ #1 QUESTION ANSWERSQUESTION ANSWERS
u 4) Given: one each 2 inch dia, one each 1 1/2inch, one each
1 inch conduit - straight pull with splices.
u Find: size junction box.
u Answer: Length = 2” x 8 + 1 1/2” + 1”
u Length = 16” + 1 1/2” + 1”. Length = 18 1/2”
u Width=2” x 6 + 1 1/2” + 1”. Width=12” +1 1/2” +1”
u Width=14 1/2”
u Depth = largest conduit is 2” in dia. Outside dia. of 2”
conduit is 2.375” or 2 3/8”. A 2” Grounded end bushing is
+ or - 3 1/4” dia.
u Box size = 18 1/2L x 14 1/2W x 4”D (use 6” for depth to
allow clearance for ground lug on j-box)
32
QUIZ #2QUIZ #2 QUESTION ANSWERSQUESTION ANSWERS
u 1) Given: one 400watt HPS luminaire @ 240VAC w/40’
pole and 16’ mast arm, #6 AWG copper conductor, 350’ run
of wire to base of luminaire pole. (all service cabinet
terminations, junction boxes & splice distances included in
these lengths)
u Find: what is the voltage drop in this circuit?
u Within LINE LOSS section, see illumination load chart,
slide 20, for luminaire load (amperage).
u Answer: 400watt luminaire @ 240 volts = 2.1 amp
u Vd #6 AWG =2ALR Vd= 2 x 2.1 x 350 x 0.000510
u Vd #10 AWG =2ALR Vd= 2 x 2.1 x 52 x 0.001290
u Vd #6 AWG=0.749700 volts.Vd #10 AWG=0.281736 volts
u Vd total = 1.03 volts
33
QUIZ #2QUIZ #2 QUESTION ANSWERSQUESTION ANSWERS
u2) Given: ITS service cabinet @120 VAC - 1750
watt load.
uFind: size branch breaker
uAnswer:
uUnit load=1750watts/120volts=14.58amps.
uITS breaker= 14.58 amps continuous load x 125%
factor = 18.2amps.
uBranch breaker = 20 amps
34
QUIZ #2QUIZ #2 QUESTION ANSWERSQUESTION ANSWERS
u3) Given: 15 Kva transformer @ 480VAC - 10748
watt load for 5 ITS service cabinets. (1 ramp meter,
1 Camera Cabinet, 2 Data Stations & 1 HAR
Station)
uFind: size transformer branch breaker in service
cabinet.
uAnswer:
uUnit load = 15000watts/480volts = 31.25amps.
uITS breaker = 31.25 amps load x 125% factor =
39.06 amps.
uBranch breaker = 40 amps
35
QUIZ #2QUIZ #2 QUESTION ANSWERSQUESTION ANSWERS
u 4) 4) Given: 1 each 2 1/2 inch dia, 2 each 2 inch, 1 each 1
1/2 inch conduit - straight pull with splices. Find: size
junction box.
u Answer: Length = 2 1/2” x 8 + (2) 2” + 1 1/2”
u Length = 20” + 4” + 1 1/2”. Length = 25 1/2”
u Width=2 1/2” x 6 +(2) 2” + 1 1/2”. Width=15” +4” +1 1/2”
u Width=20 1/2”
u Depth = largest conduit is 2 1/2” in dia. Outside dia. of
u 2 1/2” conduit is 2.875” or 2 7/8”. A 2 1/2” Grounded end
bushing is + or - 4” dia.
u Box size = 25 1/2L x 20 1/2W x 6”D (use 6” for depth to
allow clearance for ground lug on j-box)
36
Any questions?Any questions?
3710
C
D
E
3
10
C
D
E
3
Circuit A
Circuit B
Circuit D
Circuit E
Circuit C

More Related Content

What's hot

Ppt on rs logix 5000
Ppt on rs logix 5000Ppt on rs logix 5000
Ppt on rs logix 5000Anil Maurya
Β 
API 653 - Material preparado.ppt
API 653 - Material preparado.pptAPI 653 - Material preparado.ppt
API 653 - Material preparado.pptClaudiaPatriciaMagaa1
Β 
Piping training-course
Piping training-coursePiping training-course
Piping training-coursepdmsguy
Β 
Introduction to Industrial Instrumentation
Introduction to Industrial InstrumentationIntroduction to Industrial Instrumentation
Introduction to Industrial InstrumentationMaria Romina Angustia
Β 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineeringMobinVarghese8
Β 
Commissioning of Electrical Equipment or systems.ppt
Commissioning of Electrical Equipment or systems.pptCommissioning of Electrical Equipment or systems.ppt
Commissioning of Electrical Equipment or systems.pptAlemayehuAsmare
Β 
BMS COMMISSIONING CODE C_CIBSE
BMS COMMISSIONING CODE C_CIBSEBMS COMMISSIONING CODE C_CIBSE
BMS COMMISSIONING CODE C_CIBSENicholas Chazapis
Β 
Electrical Drawings and Schematics
Electrical Drawings and SchematicsElectrical Drawings and Schematics
Electrical Drawings and SchematicsLiving Online
Β 
Cable Sizing Calculations
Cable Sizing CalculationsCable Sizing Calculations
Cable Sizing CalculationsSiddhartha mudgal
Β 
Cable entry seals for cabinets and enclosures
Cable entry seals for cabinets and enclosuresCable entry seals for cabinets and enclosures
Cable entry seals for cabinets and enclosuresRoxtec UK & Ireland
Β 
Troubleshooting Electrical Faults
Troubleshooting Electrical FaultsTroubleshooting Electrical Faults
Troubleshooting Electrical FaultsSimutech Multimedia
Β 
Electrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansElectrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansLiving Online
Β 
cable sizing.ppt
cable sizing.pptcable sizing.ppt
cable sizing.pptChadWood16
Β 
Piping handbook
Piping handbookPiping handbook
Piping handbookpdmsguy
Β 

What's hot (20)

Ppt on rs logix 5000
Ppt on rs logix 5000Ppt on rs logix 5000
Ppt on rs logix 5000
Β 
Electrical Wiring Practices and Diagrams
Electrical Wiring Practices and DiagramsElectrical Wiring Practices and Diagrams
Electrical Wiring Practices and Diagrams
Β 
API 653 - Material preparado.ppt
API 653 - Material preparado.pptAPI 653 - Material preparado.ppt
API 653 - Material preparado.ppt
Β 
Piping training-course
Piping training-coursePiping training-course
Piping training-course
Β 
Introduction to Industrial Instrumentation
Introduction to Industrial InstrumentationIntroduction to Industrial Instrumentation
Introduction to Industrial Instrumentation
Β 
Read and Understand The Electrical Diagram
Read and Understand The Electrical DiagramRead and Understand The Electrical Diagram
Read and Understand The Electrical Diagram
Β 
Derrick manual
Derrick manualDerrick manual
Derrick manual
Β 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineering
Β 
Commissioning of Electrical Equipment or systems.ppt
Commissioning of Electrical Equipment or systems.pptCommissioning of Electrical Equipment or systems.ppt
Commissioning of Electrical Equipment or systems.ppt
Β 
BMS COMMISSIONING CODE C_CIBSE
BMS COMMISSIONING CODE C_CIBSEBMS COMMISSIONING CODE C_CIBSE
BMS COMMISSIONING CODE C_CIBSE
Β 
Electrical Drawings and Schematics
Electrical Drawings and SchematicsElectrical Drawings and Schematics
Electrical Drawings and Schematics
Β 
Cable Sizing Calculations
Cable Sizing CalculationsCable Sizing Calculations
Cable Sizing Calculations
Β 
plc-basics.pptx
plc-basics.pptxplc-basics.pptx
plc-basics.pptx
Β 
Cable entry seals for cabinets and enclosures
Cable entry seals for cabinets and enclosuresCable entry seals for cabinets and enclosures
Cable entry seals for cabinets and enclosures
Β 
Allen bradley
Allen bradleyAllen bradley
Allen bradley
Β 
Troubleshooting Electrical Faults
Troubleshooting Electrical FaultsTroubleshooting Electrical Faults
Troubleshooting Electrical Faults
Β 
Electrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and TechniciansElectrical Maintenance for Engineers and Technicians
Electrical Maintenance for Engineers and Technicians
Β 
switchboards
switchboardsswitchboards
switchboards
Β 
cable sizing.ppt
cable sizing.pptcable sizing.ppt
cable sizing.ppt
Β 
Piping handbook
Piping handbookPiping handbook
Piping handbook
Β 

Viewers also liked

Substation design guideliness
Substation design guidelinessSubstation design guideliness
Substation design guidelinessmichaeljmack
Β 
2015 x472 class 07 - system selection ii - pre-class
2015 x472 class 07 - system selection ii - pre-class2015 x472 class 07 - system selection ii - pre-class
2015 x472 class 07 - system selection ii - pre-classmichaeljmack
Β 
X472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leedX472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leedmichaeljmack
Β 
Electrical Lessons learned
Electrical Lessons learnedElectrical Lessons learned
Electrical Lessons learnedmichaeljmack
Β 
Ge generator and ups problems
Ge generator and ups problemsGe generator and ups problems
Ge generator and ups problemsmichaeljmack
Β 
Code questions
Code questionsCode questions
Code questionsmichaeljmack
Β 
Introduction to hvac systems
Introduction to hvac systemsIntroduction to hvac systems
Introduction to hvac systemsmichaeljmack
Β 
Power system slide notes
Power system slide notesPower system slide notes
Power system slide notesmichaeljmack
Β 
2015 x472 class 03 - distribution systems
2015 x472 class 03 - distribution systems2015 x472 class 03 - distribution systems
2015 x472 class 03 - distribution systemsmichaeljmack
Β 
Nec emergency requirements
Nec emergency requirementsNec emergency requirements
Nec emergency requirementsmichaeljmack
Β 
2015 x472 class 06- special building types
2015 x472 class 06- special building types2015 x472 class 06- special building types
2015 x472 class 06- special building typesmichaeljmack
Β 
2015 x472 class 01 - intro and system overview
2015 x472 class 01 - intro and system overview2015 x472 class 01 - intro and system overview
2015 x472 class 01 - intro and system overviewmichaeljmack
Β 
2015 x472 class 05 - system selection
2015 x472 class 05 - system selection2015 x472 class 05 - system selection
2015 x472 class 05 - system selectionmichaeljmack
Β 
2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordinationmichaeljmack
Β 
2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systemsmichaeljmack
Β 
Grounding and bonding testing
Grounding and bonding testingGrounding and bonding testing
Grounding and bonding testingmichaeljmack
Β 
2006 01-16 evap techniques r seidl
2006 01-16 evap techniques r seidl2006 01-16 evap techniques r seidl
2006 01-16 evap techniques r seidlmichaeljmack
Β 
Nfpa 110 review
Nfpa 110 reviewNfpa 110 review
Nfpa 110 reviewmichaeljmack
Β 
Understanding overcurrent protection
Understanding overcurrent protectionUnderstanding overcurrent protection
Understanding overcurrent protectionmichaeljmack
Β 
X472 class 09 1 of 2 title 24 and leed
X472 class 09 1 of 2 title 24 and leedX472 class 09 1 of 2 title 24 and leed
X472 class 09 1 of 2 title 24 and leedmichaeljmack
Β 

Viewers also liked (20)

Substation design guideliness
Substation design guidelinessSubstation design guideliness
Substation design guideliness
Β 
2015 x472 class 07 - system selection ii - pre-class
2015 x472 class 07 - system selection ii - pre-class2015 x472 class 07 - system selection ii - pre-class
2015 x472 class 07 - system selection ii - pre-class
Β 
X472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leedX472 class 09 2 of 2 title 24 and leed
X472 class 09 2 of 2 title 24 and leed
Β 
Electrical Lessons learned
Electrical Lessons learnedElectrical Lessons learned
Electrical Lessons learned
Β 
Ge generator and ups problems
Ge generator and ups problemsGe generator and ups problems
Ge generator and ups problems
Β 
Code questions
Code questionsCode questions
Code questions
Β 
Introduction to hvac systems
Introduction to hvac systemsIntroduction to hvac systems
Introduction to hvac systems
Β 
Power system slide notes
Power system slide notesPower system slide notes
Power system slide notes
Β 
2015 x472 class 03 - distribution systems
2015 x472 class 03 - distribution systems2015 x472 class 03 - distribution systems
2015 x472 class 03 - distribution systems
Β 
Nec emergency requirements
Nec emergency requirementsNec emergency requirements
Nec emergency requirements
Β 
2015 x472 class 06- special building types
2015 x472 class 06- special building types2015 x472 class 06- special building types
2015 x472 class 06- special building types
Β 
2015 x472 class 01 - intro and system overview
2015 x472 class 01 - intro and system overview2015 x472 class 01 - intro and system overview
2015 x472 class 01 - intro and system overview
Β 
2015 x472 class 05 - system selection
2015 x472 class 05 - system selection2015 x472 class 05 - system selection
2015 x472 class 05 - system selection
Β 
2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination
Β 
2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems
Β 
Grounding and bonding testing
Grounding and bonding testingGrounding and bonding testing
Grounding and bonding testing
Β 
2006 01-16 evap techniques r seidl
2006 01-16 evap techniques r seidl2006 01-16 evap techniques r seidl
2006 01-16 evap techniques r seidl
Β 
Nfpa 110 review
Nfpa 110 reviewNfpa 110 review
Nfpa 110 review
Β 
Understanding overcurrent protection
Understanding overcurrent protectionUnderstanding overcurrent protection
Understanding overcurrent protection
Β 
X472 class 09 1 of 2 title 24 and leed
X472 class 09 1 of 2 title 24 and leedX472 class 09 1 of 2 title 24 and leed
X472 class 09 1 of 2 title 24 and leed
Β 

Similar to Pullbox sizing

Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvAlexander Decker
Β 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976Southern Railway
Β 
2 meter vertical dipole array
2 meter vertical dipole array2 meter vertical dipole array
2 meter vertical dipole arrayvilla1451
Β 
Nexans Euromold MV Separable Connectors & Bushings - Interface E
Nexans Euromold MV Separable Connectors & Bushings - Interface ENexans Euromold MV Separable Connectors & Bushings - Interface E
Nexans Euromold MV Separable Connectors & Bushings - Interface EThorne & Derrick International
Β 
Nexans Euromold Interface E 5/8" 700 Series Cable Connectors
Nexans Euromold Interface E 5/8" 700 Series Cable Connectors Nexans Euromold Interface E 5/8" 700 Series Cable Connectors
Nexans Euromold Interface E 5/8" 700 Series Cable Connectors Thorne & Derrick International
Β 
Abb Combiflex Lugs 1.5, Abb Combiflex Lugs 2.5 | AKBAR TRADING EST. JUBAIL
Abb Combiflex Lugs 1.5, Abb Combiflex Lugs 2.5 | AKBAR TRADING EST. JUBAILAbb Combiflex Lugs 1.5, Abb Combiflex Lugs 2.5 | AKBAR TRADING EST. JUBAIL
Abb Combiflex Lugs 1.5, Abb Combiflex Lugs 2.5 | AKBAR TRADING EST. JUBAILAKBAR TRADING
Β 
HA no. 2 EE182LDaet_Valdez
HA no. 2 EE182LDaet_ValdezHA no. 2 EE182LDaet_Valdez
HA no. 2 EE182LDaet_ValdezPrudenceDaet
Β 
Traction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptTraction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptAshish585772
Β 
UNIT - 04 POWER INSTALLATIONS
UNIT - 04 POWER INSTALLATIONSUNIT - 04 POWER INSTALLATIONS
UNIT - 04 POWER INSTALLATIONSPremanandDesai
Β 
Alternator / Synchronous Generator
Alternator / Synchronous GeneratorAlternator / Synchronous Generator
Alternator / Synchronous GeneratorRidwanul Hoque
Β 
Pipelines welding handbook_welding_techn
Pipelines welding handbook_welding_technPipelines welding handbook_welding_techn
Pipelines welding handbook_welding_technAshraf Shaikh
Β 
Rural electrification
Rural electrificationRural electrification
Rural electrificationSamundra Gurung
Β 
Scojet Catalog 2013
Scojet Catalog 2013Scojet Catalog 2013
Scojet Catalog 2013scojetinc
Β 
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) Raychem terminations for polymer...
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) Raychem terminations for polymer...RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) Raychem terminations for polymer...
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) Raychem terminations for polymer...AKBAR TRADING
Β 
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...AKBAR TRADING
Β 
2 Basic Principal Of Utp Installation
2 Basic Principal Of Utp Installation2 Basic Principal Of Utp Installation
2 Basic Principal Of Utp InstallationMrirfan
Β 
Ins00007pdf
Ins00007pdfIns00007pdf
Ins00007pdfrohkj
Β 
Euro-Tech Sales 2016 Catalogue
Euro-Tech Sales 2016 CatalogueEuro-Tech Sales 2016 Catalogue
Euro-Tech Sales 2016 CatalogueShayne Davies
Β 

Similar to Pullbox sizing (20)

Installation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kvInstallation, testing and jointing of lt and ht power cables up to 33 kv
Installation, testing and jointing of lt and ht power cables up to 33 kv
Β 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
Β 
Distribution system 2
Distribution system  2Distribution system  2
Distribution system 2
Β 
2 meter vertical dipole array
2 meter vertical dipole array2 meter vertical dipole array
2 meter vertical dipole array
Β 
Nexans Euromold MV Separable Connectors & Bushings - Interface E
Nexans Euromold MV Separable Connectors & Bushings - Interface ENexans Euromold MV Separable Connectors & Bushings - Interface E
Nexans Euromold MV Separable Connectors & Bushings - Interface E
Β 
Nexans Euromold Interface E 5/8" 700 Series Cable Connectors
Nexans Euromold Interface E 5/8" 700 Series Cable Connectors Nexans Euromold Interface E 5/8" 700 Series Cable Connectors
Nexans Euromold Interface E 5/8" 700 Series Cable Connectors
Β 
Abb Combiflex Lugs 1.5, Abb Combiflex Lugs 2.5 | AKBAR TRADING EST. JUBAIL
Abb Combiflex Lugs 1.5, Abb Combiflex Lugs 2.5 | AKBAR TRADING EST. JUBAILAbb Combiflex Lugs 1.5, Abb Combiflex Lugs 2.5 | AKBAR TRADING EST. JUBAIL
Abb Combiflex Lugs 1.5, Abb Combiflex Lugs 2.5 | AKBAR TRADING EST. JUBAIL
Β 
HA no. 2 EE182LDaet_Valdez
HA no. 2 EE182LDaet_ValdezHA no. 2 EE182LDaet_Valdez
HA no. 2 EE182LDaet_Valdez
Β 
Traction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.pptTraction OHE 30.07.2019.ppt
Traction OHE 30.07.2019.ppt
Β 
UNIT - 04 POWER INSTALLATIONS
UNIT - 04 POWER INSTALLATIONSUNIT - 04 POWER INSTALLATIONS
UNIT - 04 POWER INSTALLATIONS
Β 
Alternator / Synchronous Generator
Alternator / Synchronous GeneratorAlternator / Synchronous Generator
Alternator / Synchronous Generator
Β 
Pipelines welding handbook_welding_techn
Pipelines welding handbook_welding_technPipelines welding handbook_welding_techn
Pipelines welding handbook_welding_techn
Β 
Rural electrification
Rural electrificationRural electrification
Rural electrification
Β 
Scojet Catalog 2013
Scojet Catalog 2013Scojet Catalog 2013
Scojet Catalog 2013
Β 
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) Raychem terminations for polymer...
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) Raychem terminations for polymer...RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) Raychem terminations for polymer...
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) Raychem terminations for polymer...
Β 
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...
RAYCHEM SAUDI ARABIA LTD. (TYCO ELECTRONICS) |AKBAR TRADING EST. SAUDI ARABIA...
Β 
Space closure
Space closure Space closure
Space closure
Β 
2 Basic Principal Of Utp Installation
2 Basic Principal Of Utp Installation2 Basic Principal Of Utp Installation
2 Basic Principal Of Utp Installation
Β 
Ins00007pdf
Ins00007pdfIns00007pdf
Ins00007pdf
Β 
Euro-Tech Sales 2016 Catalogue
Euro-Tech Sales 2016 CatalogueEuro-Tech Sales 2016 Catalogue
Euro-Tech Sales 2016 Catalogue
Β 

More from michaeljmack

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993michaeljmack
Β 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbookmichaeljmack
Β 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbookmichaeljmack
Β 
Surge Protection
Surge ProtectionSurge Protection
Surge Protectionmichaeljmack
Β 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systemsmichaeljmack
Β 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flashmichaeljmack
Β 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgearmichaeljmack
Β 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrushmichaeljmack
Β 
Building information modeling
Building information modelingBuilding information modeling
Building information modelingmichaeljmack
Β 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protectionmichaeljmack
Β 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systemsmichaeljmack
Β 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spacesmichaeljmack
Β 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708michaeljmack
Β 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distributionmichaeljmack
Β 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performancemichaeljmack
Β 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulatormichaeljmack
Β 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plantsmichaeljmack
Β 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Storiesmichaeljmack
Β 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Sheddingmichaeljmack
Β 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentalsmichaeljmack
Β 

More from michaeljmack (20)

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993
Β 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbook
Β 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
Β 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
Β 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
Β 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
Β 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
Β 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
Β 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
Β 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
Β 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
Β 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
Β 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
Β 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
Β 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
Β 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
Β 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plants
Β 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Stories
Β 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
Β 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
Β 

Recently uploaded

How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
Β 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
Β 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)Dr. Mazin Mohamed alkathiri
Β 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
Β 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
Β 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
Β 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
Β 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxabhijeetpadhi001
Β 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
Β 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
Β 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
Β 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
Β 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
Β 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
Β 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
Β 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
Β 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
Β 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
Β 

Recently uploaded (20)

How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
Β 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
Β 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
Β 
Model Call Girl in Tilak Nagar Delhi reach out to us at πŸ”9953056974πŸ”
Model Call Girl in Tilak Nagar Delhi reach out to us at πŸ”9953056974πŸ”Model Call Girl in Tilak Nagar Delhi reach out to us at πŸ”9953056974πŸ”
Model Call Girl in Tilak Nagar Delhi reach out to us at πŸ”9953056974πŸ”
Β 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
Β 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
Β 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
Β 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
Β 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptx
Β 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
Β 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
Β 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
Β 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
Β 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Β 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
Β 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
Β 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Β 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
Β 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
Β 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
Β 

Pullbox sizing

  • 1. 1 NEMA Junction Box Sizing,NEMA Junction Box Sizing, Conductor Bending Radii & FiberConductor Bending Radii & Fiber Optic CableOptic Cable from: NEC 2002 - Article 314.28, Article 314.54 & Article 770 WSDOT Fall / Winter 2004 Presented by: Terry Thayer
  • 2. 2 The clear catinkus for Junction Box Sizing and DepthThe clear catinkus for Junction Box Sizing and Depth u The definition of length and width W L1 L1 L2 Junction box Junction box GRS conduit grounded end bushing size table Size diameter inches Inches External add this number for end bushing size - then round up to nearest quarter end bushing outside diameter 1/2 0.840 0.75 1 1/2 3/4 1.050 0.75 1 3/4 1 1.315 0.75 2 1 1/4 1.660 0.75 2 1/2 1 1/2 1.900 0.75 2 3/4 2 2.375 0.75 3 1/4 2 1/2 2.875 1.00 4 3 3.500 1.25 4 3/4 3 1/2 4.000 1.25 5 1/4 4 4.500 1.75 6 1/4 5 5.563 2.00 7 1/2 6 6.625 2.00 8 3/4 Example: A 1 1/4" GRS conduit is 1.660" + 0.75" = 2.410". Round 2.410" up to 2.5" or 2 1/2 inches. L(1) or L(2) = (8) largest conduit in row plus the sum of all other conduits in row. Calculate for all rows and use sum of largest row. W=(6) largest conduit in row plus the sum of all other conduits in row. Calculate for all rows and use sum of largest row. NOTE: If no conduit enters the adjacent sides of the box the dimension is width. adjacent side
  • 3. 3 Junction Box LengthJunction Box Length -- straight pullstraight pull β€’ If one or more of the conductors is a # 4 or larger, β€’ Then the length is not less than 8x the diameter of the largest conduit if a through pull, regardless of the number of conduits or conductors. We use this multiplier: (8x the largest conduit plus the sum of all the other conduit diameters in the same row) for all wire sizes to avoid future undersized junction box problems. β€’ This assumes no bending and minimal wire storage. β€’ (NEC 2002 - Article 314.28 for sizing of junction boxes, Article 314.54 directs us to use methods in Article 314.28.)
  • 4. 44
  • 5. 55
  • 6. 66
  • 7. 7 Junction Box LengthsJunction Box Lengths -- Angle or U PullAngle or U Pull or with splicesor with splices β€’ The distance is 6x the diameter of the largest conduit in the row plus the sum of all the other conduit diameters in the same row. (There are exceptions to this in the NEC which we are not likely to encounter.) β€’ Each row is calculated separately and the single row that provides the maximum distance shall be used. β€’ We seldom have more than 3 conduits in a side. This minimizes conductor bending problems.
  • 8. 8 Exhibit 314.10 An example showing calculations required by 314.28(A)(2) for splices, angle pulls or U pulls. From 2002 NEC Handbook, page 313.
  • 10. 10
  • 11. 1111
  • 12. 12 Junction Box DepthJunction Box Depth β€’ The box needs only to be as deep as is needed to install the conduits and their fittings. β€’ Consider grounded end bushing size (diameter) in relationship to the conduit. β€’ Always round up to the nearest even dimension. Unless space is restricted, round up to the next (second) even dimension. (for a 1ΒΌ inch conduit with a 2ΒΌ inches O.D. grounded end bushing round up to 4 inches as a minimum but in most cases round up again and call out 6” as the depth) β€’ Junction boxes should be positioned to allow all conduits to enter from the ends. β€’ This reduces the effort required by the contractor during construction, allows for easier conductor installation and allows us to use smaller boxes.
  • 13. 13 Radius of Conduit Bends - NEC 344.24 and 352.24 Conduit Size Conduit Size One shot & full shoe bender One shot & full shoe bender Other Bends Other Bends Metric Designator Trade Size mm inch mm inch 16 1/2 101.6 4 101.6 4 21 3/4 114.3 4 1/2 127 5 27 1 146.05 5 3/4 152.4 6 35 1 1/4 184.15 7 1/4 203.2 8 41 1 1/2 209.55 8 1/4 254 10 51 2 241.3 9 1/2 304.8 12 63 2 1/2 266.7 10 1/2 381 15 78 3 330.2 13 457.2 18 91 3 1/2 381 15 533.4 21 103 4 406.4 16 609.6 24 129 5 609.6 24 762 30 155 6 762 30 914.4 36 1) Use entire chart for GRS conduit. (NEC 344.24) 2) For field bending of PVC, use the β€œother bends” columns only. (NEC 352.24)
  • 14. 14 Radius of Conduit Bends - NEC 353.24 (2005) Conduit Size Conduit Size Minimum Bending Radius Minimum Bending Radius Metric Designator Trade Size mm inch 16 1/2 250 10 21 3/4 300 12 27 1 350 14 35 1 1/4 450 18 41 1 1/2 500 20 53 2 650 26 63 2 1/2 900 36 78 3 1200 48 103 4 1500 60 1) Use this chart for HDPE conduit only.
  • 15. 15 Conductor Bending RadiiConductor Bending Radii β€’ There should be consideration given to the minimum bending radii of the conductors. β€’ When the junction box is sized properly this will not usually be a problem. β€’ This must still be checked to insure there is proper space for conductor bend Radii.
  • 16. 16 Conductor Bending RadiiConductor Bending Radii A =(6 x 4 In.) + 2 in.+2 In. +28 In. minimum B =(6 x 4 In.) + 2 In. +2in.+ 28 In. minimum C = 6 x 2 In. = 12 In. minimum required between raceways enclosing the same conductor D = 6 x 2 In. = 12 In. minimum required between raceways enclosing the same conductor E = 6 x 4 In. = 24 In. minimum required between raceways enclosing the same conductor Exhibit 314.11 Raceway entries enclosing the same conductors are required to have a minimum separation between them. The intent is to provide adequate space for the conductor to make the bend.
  • 17. 1717
  • 18. 1818
  • 19. 1919
  • 20. 20 ConductorsConductors 2002 NEC 300.34 Conductor Bending Radius. The conductor shall not be bent to a radius less than 8 times the overall diameter for nonshielded conductors or 12 times the diameter for shielded or lead covered conductors during or after installation. For multicolor or multiplexed single conductor cables having individually shielded conductors, the minimum bending radius is 12 times the diameter of the individually shielded or 7 times the overall diameter, whichever is greater.
  • 21. 21 Conductors & CableConductors & Cable CONDUCTORCONDUCTOR OUTSIDE DIAOUTSIDE DIA MULTIPLIERMULTIPLIER BENDING RADIUSBENDING RADIUS # 8# 8 0.2660.266 88 2.128’’2.128’’ # 6# 6 0.3040.304 88 2.432’’2.432’’ # 4# 4 0.3520.352 88 2.816’’2.816’’ # 2# 2 0.4120.412 88 3.296”3.296” (ind.cond.) (ind.conductor)(ind.cond.) (ind.conductor) #2c(#14)#2c(#14) 0.326 ( 0.14)0.326 ( 0.14) 7(12)7(12) 2.282’’2.282’’ #3c(#20)#3c(#20) 0.35 ( 0.07)0.35 ( 0.07) 7(12)7(12) 2.45’’2.45’’ #4c(#18)#4c(#18) 0.41 ( 0.09)0.41 ( 0.09) 7(12)7(12) 2.87’’2.87’’ #5c(#14)#5c(#14) 0.51 ( 0.14)0.51 ( 0.14) 7(12)7(12) 3.57’’3.57’’ #7c(#14)#7c(#14) 0.55 ( 0.14)0.55 ( 0.14) 7(12)7(12) 3.85’’3.85’’ 6pr(#19)6pr(#19) 0.56 ( 0.08)0.56 ( 0.08) 7(12)7(12) 3.92’’3.92’’ 24 (SM) fiber24 (SM) fiber 0.470.47 2020 9.40”9.40” 48 (SM) fiber48 (SM) fiber 0.470.47 2020 9.40”9.40” 72 (SM) fiber72 (SM) fiber 0.470.47 2020 9.40”9.40” 96 (SM) fiber96 (SM) fiber 0.780.78 2020 15.60”15.60” 144 (SM) fiber144 (SM) fiber 0.780.78 2020 15.60”15.60”
  • 22. 22 ConductorsConductors β€’ There should be consideration given for the slack required in the conductors. β€’ Standard specification 8-20.3(8) requires sufficient slack wire be installed to allow any conductor to be raised 18’’ outside of the junction box. β€’ Discuss this with the electrical inspectors if you have many circuits in one junction box / conduit run. β€’ If you had a through pull and 4 circuits, which does happen, you would need space for 24’ of slack.
  • 23. 23 ConductorsConductors -- continuedcontinued β€’ There was a case with 2 conduits passing through one junction box carrying 11 conductors; that’s 33’ of slack in an 8’’x 8’’ x 18’’ JB. β€’ The electrical inspectors will usually hold the contractor to the slack called for in a standard structure mounted (traffic barrier) junction box (8’’x 8’’ x 18’’) because there are usually not many conductors in the run. β€’ Standard concrete junction boxes have the same slack requirements as surface mounted boxes.
  • 24. 24 Fiber Optic CableFiber Optic Cable β€’ The greater the radius of the conduit, the easier the pull. β€’ Use cable vaults and pull boxes wherever possible – the conduit then enters from the side of the box and eliminates 180 degrees of sweep at each box. β€’ Use 36” radius conduit sweeps wherever possible. This is the WSDOT standard for all jobs. β€’ When unable to use 36” radius sweep, use a minimum of 20 times the outside diameter of the cable to calculate the smallest radius that WSDOT will allow to be used. Note: This usually only applies inside a building or cabinet.
  • 26. 26 QUIZ #1 QUESTIONSQUIZ #1 QUESTIONS u 1) Given: one 400watt HPS luminaire @ 480VAC w/50’ pole and 16’ mast arm, #6 copper conductor, 500’ run of wire to base of luminaire pole. (all service cabinet terminations, junction boxes & splice distances included in these lengths) u Find: what is the voltage drop in this circuit? u 2) Given: ITS service cabinet @120VAC - 1750 watt load. u Find: size branch breaker u 3) Given: 10 Kva transformer @ 240VAC - 8500 watt ITS service cabinet. u Find: size transformer branch breaker in service cabinet. u 4) Given: 1 each 2 inch dia, 1 each 1 1/2inch, 1 each 1 inch conduit - straight pull with splices. u Find: size junction box.
  • 27. 27 Quiz #2 QuestionsQuiz #2 Questions u 1) Given: one 400watt HPS luminaire @ 240VAC w/40’ pole and 16’ mast arm, #6 copper conductor, 350’ run of wire to base of luminaire pole. (all service cabinet terminations, junction boxes & splice distances included in these lengths) u Find: what is the voltage drop in this circuit? u 2) Given: ITS service cabinet @120VAC - 1750 watt load. u Find: size branch breaker u 3) Given: 15 Kva transformer @ 480VAC - 10748 watt load for 5 ITS service cabinets. (1 ramp meter, 1 Camera Cabinet, 2 Data Stations & 1 HAR Station) u Find: size transformer branch breaker in service cabinet. u 4) Given: 1 each 2 1/2 inch dia, 2 each 2 inch, 1 each 1 1/2 inch conduit - straight pull with splices. u Find: size junction box.
  • 28. 28 QUIZ #1QUIZ #1 QUESTION ANSWERSQUESTION ANSWERS u 1) Given: one 400watt HPS luminaire @ 480VAC w/50’ pole and 16’ mast arm, #6 AWG copper conductor, 500’ run of wire to base of luminaire pole. (all service cabinet terminations, junction boxes & splice distances included in these lengths) u Find: what is the voltage drop in this circuit? u Within LINE LOSS section, see illumination load chart, slide 20, for luminaire load (amperage). u Answer: 400watt luminaire @ 480 volts = 1.1 amp u Vd #6 AWG =2ALR Vd= 2 x 1.1 x 500 x 0.000510 u Vd #10 AWG =2ALR Vd= 2 x 1.1 x 62 x 0.001290 u Vd #6 AWG=0.561000 volts.Vd #10 AWG=0.175956 volts u Vd total = 0.74 volts
  • 29. 29 QUIZ #1QUIZ #1 QUESTION ANSWERSQUESTION ANSWERS u2) Given: ITS service cabinet @120 VAC - 1750 watt load. uFind: size branch breaker uAnswer: uUnit load=1750watts/120volts=14.58amps. uITS breaker= 14.58 amps continuous load x 125% factor = 18.2amps. uBranch breaker = 20 amps
  • 30. 30 QUIZ #1QUIZ #1 QUESTION ANSWERSQUESTION ANSWERS u3) Given: 10 Kva transformer @ 240 VAC - 8500 watt ITS service cabinet. uFind: size transformer branch breaker in service cabinet. uAnswer: uUnit load = 10000watts/240volts = 41.66amps. uITS breaker = 41.66 amps load x 125% factor = 52.08 amps. uBranch breaker = 60 amps
  • 31. 31 QUIZ #1QUIZ #1 QUESTION ANSWERSQUESTION ANSWERS u 4) Given: one each 2 inch dia, one each 1 1/2inch, one each 1 inch conduit - straight pull with splices. u Find: size junction box. u Answer: Length = 2” x 8 + 1 1/2” + 1” u Length = 16” + 1 1/2” + 1”. Length = 18 1/2” u Width=2” x 6 + 1 1/2” + 1”. Width=12” +1 1/2” +1” u Width=14 1/2” u Depth = largest conduit is 2” in dia. Outside dia. of 2” conduit is 2.375” or 2 3/8”. A 2” Grounded end bushing is + or - 3 1/4” dia. u Box size = 18 1/2L x 14 1/2W x 4”D (use 6” for depth to allow clearance for ground lug on j-box)
  • 32. 32 QUIZ #2QUIZ #2 QUESTION ANSWERSQUESTION ANSWERS u 1) Given: one 400watt HPS luminaire @ 240VAC w/40’ pole and 16’ mast arm, #6 AWG copper conductor, 350’ run of wire to base of luminaire pole. (all service cabinet terminations, junction boxes & splice distances included in these lengths) u Find: what is the voltage drop in this circuit? u Within LINE LOSS section, see illumination load chart, slide 20, for luminaire load (amperage). u Answer: 400watt luminaire @ 240 volts = 2.1 amp u Vd #6 AWG =2ALR Vd= 2 x 2.1 x 350 x 0.000510 u Vd #10 AWG =2ALR Vd= 2 x 2.1 x 52 x 0.001290 u Vd #6 AWG=0.749700 volts.Vd #10 AWG=0.281736 volts u Vd total = 1.03 volts
  • 33. 33 QUIZ #2QUIZ #2 QUESTION ANSWERSQUESTION ANSWERS u2) Given: ITS service cabinet @120 VAC - 1750 watt load. uFind: size branch breaker uAnswer: uUnit load=1750watts/120volts=14.58amps. uITS breaker= 14.58 amps continuous load x 125% factor = 18.2amps. uBranch breaker = 20 amps
  • 34. 34 QUIZ #2QUIZ #2 QUESTION ANSWERSQUESTION ANSWERS u3) Given: 15 Kva transformer @ 480VAC - 10748 watt load for 5 ITS service cabinets. (1 ramp meter, 1 Camera Cabinet, 2 Data Stations & 1 HAR Station) uFind: size transformer branch breaker in service cabinet. uAnswer: uUnit load = 15000watts/480volts = 31.25amps. uITS breaker = 31.25 amps load x 125% factor = 39.06 amps. uBranch breaker = 40 amps
  • 35. 35 QUIZ #2QUIZ #2 QUESTION ANSWERSQUESTION ANSWERS u 4) 4) Given: 1 each 2 1/2 inch dia, 2 each 2 inch, 1 each 1 1/2 inch conduit - straight pull with splices. Find: size junction box. u Answer: Length = 2 1/2” x 8 + (2) 2” + 1 1/2” u Length = 20” + 4” + 1 1/2”. Length = 25 1/2” u Width=2 1/2” x 6 +(2) 2” + 1 1/2”. Width=15” +4” +1 1/2” u Width=20 1/2” u Depth = largest conduit is 2 1/2” in dia. Outside dia. of u 2 1/2” conduit is 2.875” or 2 7/8”. A 2 1/2” Grounded end bushing is + or - 4” dia. u Box size = 25 1/2L x 20 1/2W x 6”D (use 6” for depth to allow clearance for ground lug on j-box)