SlideShare a Scribd company logo
1 of 16
Download to read offline
Centennial
Transportation
Extension of the SR-241 Toll Road

Engineers:
Alireza Behbahani
Megan Hanrahan
Sarah Kevorkian
Kevin Kirk
Chosita Sribhibhadh

0
Executive Summary
The transportation engineers at Centennial Transportation were charged with the task of
designing a two lane highway extension of the toll road SR-241 that would connect it to SR-74,
the Ortega Highway. This extension, approximately 4 miles long, would span along the Cota de
Caza mountainous terrain. In order to devise the desired design that would allow a converging
path joining the 241 and 74 corridors, it was necessary for the specific safety and design
standards of Caltrans and AASHTO to be satisfied while producing the project plan. It was also
important to take into consideration the environmental impacts of this freeway which would span
along untouched nature inhabited by many forms of wildlife. The challenge before us was to
meet standards, please nearby residents, environmentalists, and future travelers of the road all
while keeping construction cost and time at a minimum to increase efficiency. A more detailed
description of the design standards that we went by is given in Chapter One of this report.
The five skilled engineers that worked on this project started off by discussing
environmental concerns. It would have been easiest just to construct the highway along the path
with the most consistent elevation, but we wanted to take into consideration the surroundings of
the highway that residents use every day. Once we factored in the surrounding area of the
highway, we were then able to choose a path connecting the corridors. This straight path was
then connected with horizontal curves. The lengths and radii of these curves was set by safety
standards of the design speed of seventy miles per hour. The highway extension has many
horizontal curves since it goes out of its way to try and not disturb nature and wildlife habitats as
much as possible. Horizontal curves are discussed further in Chapter Two of this report.
The next task at hand for the team was designing vertical curves. Since our highway goes
through mountainous terrain and changes grade and elevation often, it was necessary to make
sure that the ride was as smooth as possible for drivers, as well as safe. In order to ensure this,
fifteen vertical curves were put in place along our highway. In placing these vertical curves, it
was necessary to ensure that they were all contained within horizontal curves for good design
practice and it was necessary to make sure that cut and fill levels of earthwork were relatively
even. More about the vertical curves in the highway extension can be found in Chapter Three of
this report.
Superelevation is an extremely important factor in ensuring the safety of drivers along the
highway. Banked roads help make horizontal curves more safe by reducing sliding friction. This
is especially important since the highway design speed is relatively high. Because of the need for
superelevated roads, much time and care was put into calculating superelevation transition
lengths of the important stations along our curves. The full list of superelevation transition
calculations can be found in Chapter Four of this report.
The last step in the design of our highway was choosing the proper pavement design.
Several different combinations of materials were available for selection, but it was important to
choose the right combination that had the least cost. All thicknesses were calculated from
AASHTO safety standards and all prices were calculated from those given in the project
description. A more detailed description of the pavement design chosen for the freeway
extension is given in Chapter Five of this report.
In the end, through the careful planning of the highway extension, construction time and
cost were minimized, while safety and environmental protection were maximized.

1
Table of Contents

Page number

Chapter1: Overview of Design
Section 1.1: Summary……………………………………………………………. 3
Section 1.2: Alternate Designs…………………………………………………… 4
Section 1.3: Selection of Optimal Design………………………………………... 4
Chapter 2: Horizontal Alignment
Section 2.1: Design Criteria…………………………………………………….... 5
Section 2.2: Design Methodology……………………………………………...… 5
Section 2.3: Summary Table………………………………………………...…… 6
Chapter 3: Vertical Alignment
Section 3.1: Design Criteria………………………………………………………. 7
Section 3.2: Design Methodology……………………………………………........ 8
Section 3.3: Summary Table……………………………………………………… 8
Chapter 4: Superelevation Runoff
Section 4.1: Selection and required lengths…………………………………….…. 9
Section 4.2 Summary Tables………………………………………………….…... 9
Chapter 5: Pavement Design
Section 5.1: Optimal Design…………………………………………………....… 14
Section 5.2: Summary Tables…………………………………………………...... 15
Appendices:
A1: Plan and Profile Views of Horizontal and Vertical Curves………………….. 16
A2: Sample Calculations………………………………………………………….. 46

2
Chapter 1: Overview of Design
Section 1.1 Summary:
In order to produce a proper highway design that would join the CA-241 and SR-74
corridors, many factors were taken into consideration. In order to reach our goal, it was
necessary to follow all Caltrans design standards and the AASHTO pavement design method.
Here we highlight some key points of the project design including components and
characteristics of the project that are vital in many, if not all, areas of the design process. A
simple, yet critical factor was the design speed of 70 miles per hour, which determined many
design features from the early stages of the project. Also, the project’s region, residing in a rural
and mountainous area, constantly changing in elevation, also dictated certain components due to
design standards. Another factor taken into consideration was the fact that the highway only
consists of two lanes, with lane widths of 12 feet and shoulder widths of 8 feet. These basic, yet
crucial, elements of the project gave us the fundamental standard to start with and allowed us to
go forth in producing a proper design.
The production of the horizontal alignment involved the implementation of tangent paths,
with minimum elevation changes using the given topographic map. The starting and ending
points match the latitude, longitude, and elevation given as well. Once completing tangent lines,
circular curves are used to connect the tangents. These circular curves follow the Caltrans
standard radii from its design speed in the Caltrans Design Manual (Table 203).
Following the creation of the horizontal alignment, the vertical alignment was created
following Caltrans design standards, taking into consideration factors such as maximum and
minimum grades for rolling terrain (Table 204.3), the algebraic grade differences (Section
204.4), Sight Distance standards (Table 201.1), and minimum curve lengths (Figure 201.4 and
201.5) depending on tangents created. Also, the design is congruent with the initial and final
grade at the BP and EP specified by the project description while crest curves length exceeding
more than half a mile were avoided. We also made sure to practice good design form by keeping
all vertical curves within horizontal curves.
In designing the superelevation runoff of the highway, we made certain to meet
AASHTO minimum standards, selecting the appropriate superelevation for the horizontal curves
from the Caltrans design manual from Table 202.2. Once the proper superelevation rate was
chosen, the proper crown runoff and superelevation runoff lengths were chosen from Figure
202.5A on superelevation transition.
Finally, considering the pavement design, we chose an optimal design following
AASHTO flexible pavement design methods and AASHTO’s standards for minimum thickness
for each layer of pavement found in the project description. We compared the cost estimate for
each design option to find the minimal pavement cost in order to efficiently execute this project.

3
Section 1.2 Alternate Designs:
While producing this project, two different sets of alignments were constructed with
varying design elements. By comparison, we were able to implement transportation engineering
judgment in order to choose between the more superior of the two possible plans.
The first of the two possible highway design options, Design A, had a total length of
27,262 feet. It contained 22 horizontal curves and 14 vertical curves. This particular design was
comprised mostly of earthwork area which needed to be filled that was much greater than the
amount of cut needed.
In comparison to the first possible design, the second design option, Design B, features a
total design length of 26,883 feet. It consists of 11 horizontal curves and 15 vertical curves. This
design provided more evenly distributed areas of cut and fill, which in nature is more efficient in
overall project production, as it not only is beneficial to the budget, but also time spent in
constructing the highway.
Section 1.3 Selection of Optimal Design:
The optimal design between the two choices, we felt, was Design B. The cost of
construction in Design A would be greater than that of the latter design, due to the fact that its
length is greater than that of Design B. Also, the fact that Design A has many horizontal curves
contributes to why it is not the primary choice in design, as having a minimal amount of curves
provides a more aesthetically pleasing environment for drivers. In addition, the overall grade
change of design A was more than the grade change produced in Design B, which contains
smoother transitions in the elevation change throughout the alignment.
In consideration of the earthwork involved in the project, it costs more to seek out soil
from other locations than to use the cut area of soil from the same project to fill the necessary
space. Design A requires a significant amount of soil to be filled, which exceeds the amount of
area cut out from the design. This would result in more time and money spent displacing soil in
order to achieve adequate results. In comparison, Design B allows for cut soil from this project to
be transported to areas close by needing to be filled, which in nature is more efficient in
earthwork costs and time spent on cut and fill.
The final factor in the decision to choose Design B, was that the initial and final grades
and elevation of Design A did not correspond to that of the project description. In Design A, the
end point elevation is not the specified elevation in the provided project description and the final
grade of +3.0% did not agree as well. Though Design A did not meet the required grades and
elevation, Design B executes these necessary factors in designing the projected highway.

4
Chapter 2: Horizontal Alignment
Section 2.1 Design Criteria:
This section outlines the design standards followed in creating the highway’s horizontal
alignment. The focus of the highway was to keep the road on the same contour line, in order to
keep the elevation difference to an absolute minimum to keep cost low. As a part of our public
outreach, the group decided to avoid building too close to a school, Tesoro High School, located
near our starting point. Due to environmental issues, the design also took into account the
location of the Thomas F. Riley Wilderness Park, located east of the planned highway. The last
restricted area was a power plant near the end point of the highway. All precautions were taken
into account and all sensitive sites will not be disturbed by this freeway design. This project
followed its own design standards, in accordance with the standards provided by AASHTO and
Caltrans. Based off of the geometric design Table 203.2 in the Caltrans Design Manual, with a
highway design speed of 70 miles per hour, the horizontal curve’s minimum radius in the
alignment is equivalent to 2,100 feet in addition to a minimum horizontal curve length of 750
feet. This planned horizontal alignment does not implement any broken back, reverse, or
compound horizontal curves.
Section 2.2 Design Methodology:
Several factors were considered in designing the highway’s horizontal alignment:
Follow the Caltrans design standards:
I.
II.
III.
IV.
V.
VI.

A study of the vertical profile of the land before finalizing the design
Minimizing cost where applicable without losing any safety factors
Avoiding any restricted areas
Following the BP and EP latitude/longitude points given by the project guidelines
Keeping all vertical curves within horizontal curves
Exceeding minimum curve radii

The maximum horizontal curve length of 2,100 feet was not exceeded; therefore the
earthwork’s cost was minimized. In general, horizontal curves with bigger curve lengths incur a
greater cost, compared to shorter horizontal curve lengths. Table 1 represents all the information
of the eleven horizontal curves present in our project. It was crucial that our team avoided steep
drops and great inclines in the route, as this would incur great costs by requiring large amounts
of cut and fill. The highway’s horizontal alignment consisted of curves that followed the design
standards for curve radius and length while providing the highest level of safety for the lowest
projected cost.

5
Section 2.3 Summary Table:
Table 1: Horizontal Alignment Summary

PC [stations]

HC 1
25+84.08

HC 2
30+78.70

HC 3
58+37.36

HC 4
84+31.98

HC 5
108+38.21

HC 6
141+56.95

Elevation-PC [ft]

687.25

680.16

699.26

685.98

671.41

596.02

PT [stations]

27+43.45

40+51.78

63+78.08

98+60.81

112+08.74

155+65.26

Elevation-PT [ft]

683.81

679.83

702.45

675.62

668.87

555.49

Curve Length
[ft]
Radius [ft]
Central Angle
[degrees]
Tangent Length
[ft]
Superelevation
Rate [ft/ft]
Superelevation
Runoff Length
[ft]
Crown Runoff
Length [ft]
Superelevation
Transition
Length [ft]

159.36

973.08

540.71

1428.83

370.53

1408.32

2100
4.348

2100
26.5491

2100
14.7526

2100
38.9837

2100
10.1094

2100
38.4241

79.7195229

495.4341518

271.8591243

743.3128475

185.7465682

731.7926234

0.06

0.06

0.06

0.06

0.06

0.06

150

150

150

150

150

150

50

50

50

50

50

50

200

200

200

200

200

200

PC [stations]
Elevation-PC [ft]
PT [stations]
Elevation-PT [ft]
Curve Length [ft]
Radius [ft]
Central Angle
[degrees]
Tangent Length
[ft]
Superelevation
Rate [ft/ft]
Superelevation
Runoff Length [ft]
Crown Runoff
Length [ft]
Superelevation
Transition Length
[ft]

HC 7
187+83.48
502.12
193+08.37
495.7
524.9
2100
14.3212

HC 8
200+89.38
486.15
203+73.26
481.98
283.89
2100
7.7455

HC 9
223+02.04
441.12
227+97.25
429.11
495.22
2100
13.5114

HC 10
237+94.36
400.8
250+79.05
346.17
1284.68
2100
35.0509

HC 11
250+79.05
346.19
275+05.63
260.32
2426.58
2100
66.2061

263.8246902

142.1602634

248.7632243

663.1531235

1369.132077

0.06

0.06

0.06

0.06

0.06

150

150

150

150

150

50

50

50

50

50

200

200

200

200

200

6
Chapter 3: Vertical Alignment
Section 3.1 Design Criteria:
In this project were able to designate vertical curves which coincide with standards of
both the given project as well as the corresponding rules and regulations specified in the Caltrans
Highway Design Manual. In designing these Vertical curves, grade standards were kept in mind.
Referencing to Table 204.3, which provides the maximum grades for various forms of terrain
and highways, the corresponding grade for rolling terrain is 5%. This was the maximum grade
that was allowable in the project which was not exceeded. Also, the minimum grade of 0.3% was
met, also mentioned in Table 204.3.
An important factor in geometric design standards is sight distance, consisting of both
Stopping Sight Distance and Passing Sight Distance. The Caltrans Highway Design Manual
provides Table 201.1: Sight Distance Standards which gives a list of design speeds and their
corresponding stopping sight distances and passing sight distances in accordance with
AASHTO’s standards. With a design speed of 70 mph, the corresponding stopping sight distance
and passing sight distance are 750 ft and 2,500 ft, respectively. The consideration of the passing
sight distance is particularly important in this two lane design, for section 201.2 highlights that
only in 2-lane roads would there be consideration of a passing sight distance.
Various factors are taken into consideration when designing vertical curves, including
curve length as well as sight distance which may be considered further. In order to consider the
proper curve lengths and stopping sight distance on crest vertical curves, Figure 201.4 was
utilized to take the correct precautions. It provides two equations which factor in sight distance,
curve length, and algebraic grade difference which provides us with proper curve length. Crest
curve lengths exceeding more than half a mile were avoided, following standards. Also, the
Figure 201.5 provides proper stopping sight distance on sag vertical curves and also provides a
reference for proper curve length based on specified design speeds. There are two unique
equations to sag vertical curves relating the curve length, sight distance, and algebraic grade
difference for each curve. Sample calculations for both crest and sag curves are provided;
however, one must also consider the minimum curve lengths specified in the manual.
Due to standards, specified in Section 204.4 of the manual, an algebraic grade difference
between initial and final grades of less than 2% has a corresponding minimum vertical curve
length of 200 feet. Also, in this section is a reference to minimum curve lengths in situations
where the grade difference is greater than 2 percent and with a design speed exceeding 40 miles
per hour, stating that in such situations the minimum length of the vertical curve would be 10
times the velocity. With a design speed of 70 miles per hour, the minimum vertical curve length
is 700 ft, which would override the sample calculations of curve lengths below this number. This
condition was applied to several curves as the grade difference and design speed satisfies the
requirements. Overall, the vertical alignment design was created accurately, following standards,
and agrees with the beginning and end points, as specified in the project description.

7
Section 3.2 Design Methodology:
Using the proper minimum grades and minimum vertical curve lengths, we were able to
produce a design that coincides with the Caltrans safety standards. However, this project enabled
us to practice our personal opinions as transportation engineers on design as well, particularly in
terms of earthwork. As previously mentioned, we chose a design which resulted in more evenly
distributed volume between cut and fill, which would reduce both time and monetary needs to
conclude the project. Though we used more Vertical Curves than initially intended with the
previous design, we were able to reach our goal of a more efficient project result in earthwork.
Also, we hoped to produce a corridor path that would be both aesthetically pleasing and
safe for drivers. The given project, in nature, was a challenge in producing a design in such a
terrain as the Coto de Caza mountainous area, with large elevation differences. However, we
were able to design this project under such conditions while following proper Caltrans standards.
Overall, as section 204.4 in Caltrans manual states, correctly designed vertical curves
should provide safety, comfortable driving, proper drainage, adequate sight distance, and be
aesthetically pleasing. We believe that we have complied with all of the above.
Section 3.3: Summary Table
Table 2: Vertical Alignment Summary

PVC [Stations]
PVT [Stations]
Curve Length
[ft]
Initial Grade
[%]
Final Grade [%]
Grade
Difference
Min. Length of
Curve [ft]

PVC [Stations]
PVT [Stations]
Curve Length [ft]
Initial Grade [%]
Final Grade [%]
Grade Difference
Min. Length of
Curve [ft]

VC 1
VC 2
VC 3
VC 4
VC 5
VC 6
VC 7
VC 8
26+81.74 34+91.00 44+76.55 60+00.00 70+10.75 80+85.46 121+50.00 146+64.20
28+81.74 36+91.00 46+76.55 62+00.00 72+10.75 82+85.46 128+50.00 148+64.20
200
200
200
200
200
200
700
200
-2.5

-0.72

0.73

1.24

0.3

-1.25

-0.69

-3.86

-0.72
1.78

0.73
1.45

1.24
0.51

0.3
0.94

-1.25
1.55

-0.39
0.86

-3.86
3.17

-2.13
1.73

200

200

200

200

200

200

700

200

VC 14
273+56.08
280+56.08
700
-3.12
0.06
3.18
700

VC 15
285+52.07
287+52.07
200
0.06
3
2.94
200

VC 9
170+00.00
172+00.00
200
-2.13
-1.22
0.91
200

VC 10
202+21.65
204+21.65
200
-1.22
-2.13
0.91
200

VC 11
VC 12
224+94.09 238+42.62
226+94.09 245+42.62
200
700
-2.13
-2.84
-2.84
-4.88
0.71
2.04
200
700

VC 13
255+85.69
257+85.69
200
-4.88
-3.12
1.76
200

8
Chapter 4: Superelevation Runoff
Section 4.1 Selection and required lengths:
For this highway design there are 11 horizontal curves, all with equal radii of 2100 feet.
Referencing to the Table 202.2 in the Caltrans Design Manual, for a 2-lane conventional
highway with a curve radii between 1900 and 2199 feet, will have a superelevation of 0.06 feet
per foot when the curve is in full superelevation. Therefore all of the horizontal curves’
superelevation runoff lengths are the same and have a value of 150 feet. The curves also all have
the same crown runoff lengths of 50 feet, as well as a normal crown of 2% and a shoulder cross
slope of 5%. Curves were designed with minimum lengths to ensure that the requirements for
driver safety and comfort are achieved.
Section 4.2 Summary Table
Table 3: Superelevation Transition Summary
Left
Stations

Curve
1
North
End

Shoulder
Elevation

Centerline
Shoulder
Offset

Pavement
Elevation

Elevation

Offset

Shoulder
Elevation

1

23+50.75
24+34.08

691.01

-0.24

691.01

-0.24

691.25

-0.24

691.01

-0.64

690.61

24+84.08

690

0

690

0

690

-0.24

689.76

-0.64

689.36

4

25+34.05

688.99

0.24

688.99

0.24

688.75

-0.24

688.51

-0.64

688.11

PC

25+84.08

687.73

0.48

687.73

0.48

687.25

-0.48

686.77

-0.64

686.61

6

26+34.08

686.97

0.72

686.97

0.72

686.25

-0.72

685.53

-0.72

685.53

6'

26+93.45

685.29

0.72

685.29

0.72

684.57

-0.72

683.85

-0.72

683.85

PT

27+43.45

684.01

0.48

684.01

0.48

683.53

-0.48

683.05

-0.64

682.89

4'

27+93.45

682.78

0.24

682.78

0.24

682.54

-0.24

682.3

-0.64

681.9

3'

28+43.45

682.01

0

682.01

0

682.01

-0.24

681.77

-0.64

681.37

2'

28+93.45

681.21

-0.24

681.21

-0.24

681.45

-0.24

681.21

-0.64

680.81

1'

29+46.78

680.43

-0.64

680.83

-0.24

681.07

-0.24

680.83

-0.64

680.43

1

28+45.37

680.94

-0.64

681.34

-0.24

681.58

-0.24

681.34

-0.64

680.94

2

29+28.70

681

-0.24

681

-0.24

681.24

-0.24

681

-0.64

680.6

3

29+78.70

680.87

0

680.87

0

680.87

-0.24

680.63

-0.64

680.23

4

30+28.70

680.76

0.24

680.76

0.24

680.52

-0.24

680.28

-0.64

679.88

PC
South
End

-0.24

Shoulder
Offset

3

Curve
2
North
End

-0.24

Pavement
Elevation

2

South
End

-0.64

Offset

Right

-0.64

30+78.70

680.64

0.48

680.64

0.48

680.16

-0.48

679.68

-0.64

679.52

6

31+28.7

680.5

0.72

680.5

0.72

679.78

-0.72

679.06

-0.72

679.06

9
6'

679.46

-0.72

678.74

-0.72

678.74

40+51.78

680.31

0.48

680.31

0.48

679.83

-0.48

679.35

-0.64

679.19

41+01.78

680.43

0.24

680.43

0.24

680.19

-0.24

679.95

-0.64

679.55

41+51.78

681.56

0

681.56

0

681.56

-0.24

681.32

-0.64

680.92

42+01.78

680.7

-0.24

680.7

-0.24

680.94

-0.24

680.7

-0.64

680.3

1'

42+85.11

680.88

-0.64

681.28

-0.24

681.52

-0.24

681.28

1

56+04.03

695.71

-0.64

696.11

-0.24

696.35

-0.24

696.11

-0.64

695.71

2

56+87.36

696.77

-0.64

697.17

-0.24

697.41

-0.24

697.17

-0.24

697.17

3

57+37.36

697.4

-0.64

697.8

-0.24

698.04

0

698.04

0

698.04

4

57+87.36

698.04

-0.64

698.44

-0.24

698.68

0.24

698.92

0.24

698.92

PC

58+37.36

698.62

-0.64

698.78

-0.48

699.26

0.48

699.74

0.48

699.74

6

58+87.36

699.17

-0.72

699.17

-0.72

699.89

0.72

700.61

0.72

700.61

6'

63+28.08

-0.72

-0.72

-0.72

-0.72

0.72

0.72

0.72

0.72

PT

63+78.08

701.81

-0.64

701.97

-0.48

702.45

0.48

702.93

0.48

702.93

4'

64+28.08

701.84

-0.64

702.24

-0.24

702.48

0.24

702.72

0.24

702.72

3'

64+78.08

701.86

-0.64

702.26

-0.24

702.5

0

702.5

0

702.5

2'

65+28.08

701.88

-0.64

702.28

-0.24

702.52

-0.24

702.28

-0.24

702.28

1'

66+11.41

701.88

-0.64

702.28

-0.24

702.52

-0.24

702.28

-0.64

701.88

1

81+98.65

688.22

-0.64

688.62

-0.24

688.86

-0.24

688.62

-0.64

688.22

2

82+81.98

687.2

-0.64

687.6

-0.24

687.84

-0.24

687.6

-0.24

687.6

3

83+31.98

686.6

-0.64

687

-0.24

687.24

0

687.24

0

687.24

4

83+81.98

685.33

-0.64

685.73

-0.24

685.97

0.24

686.21

0.24

686.21

PC

84+31.98

685.34

-0.64

685.5

-0.48

685.98

0.48

686.46

0.48

686.46

6

84+81.98

684.62

-0.72

684.62

-0.72

685.34

0.72

686.06

0.72

686.06

6'

98+10.81

685.13

-0.72

685.13

-0.72

685.85

0.72

686.57

0.72

686.57

PT

98+60.81

674.98

-0.64

675.14

-0.48

675.62

0.48

676.1

0.48

676.1

4'

99+10.81

674.8

-0.64

675.2

-0.24

675.44

0.24

675.68

0.24

675.68

3'

99+60.81

674.58

-0.64

674.98

-0.24

675.22

0

675.22

0

675.22

2'

100+10.81

674.36

-0.64

674.76

-0.24

675

-0.24

674.76

-0.24

674.76

1'
Curve
5
North
End

0.72

2'

South
End

680.18

3'

Curve
4
North
End

0.72

4'

South
End

680.18

PT

Curve
3
North
End

40+01.78

100+94.14

674.05

-0.64

674.45

-0.24

674.69

-0.24

674.45

-0.64

674.05

1

106+04.88

672.11

-0.64

672.51

-0.24

672.75

-0.24

672.51

-0.64

672.11

2

106+88.21

671.94

-0.24

671.94

-0.24

672.18

-0.24

671.94

-0.64

671.54

681.52

10
3

671.83

0

671.83

-0.24

671.59

-0.64

671.19

107+88.21

671.73

0.24

671.73

0.24

671.49

-0.24

671.25

-0.64

670.85

108+38.21

671.89

0.48

671.89

0.48

671.41

-0.48

670.93

-0.64

670.77

6

108+88.21

671.72

0.72

671.72

0.72

671

-0.72

670.28

-0.72

670.28

6'

111+58.74

669.94

0.72

669.94

0.72

669.22

-0.72

668.5

-0.72

668.5

PT

112+08.74

669.35

0.48

669.35

0.48

668.87

-0.48

668.39

-0.64

668.23

4'

112+58.74

668.76

0.24

668.76

0.24

668.52

-0.24

668.28

-0.64

667.88

3'

113+08.74

667.98

0

667.98

0

667.98

-0.24

667.74

-0.64

667.34

2'

113+58.74

667.61

-0.24

667.61

-0.24

667.85

-0.24

667.61

-0.64

667.21

1'

114+42.07

666.65

-0.64

667.05

-0.24

667.29

-0.24

667.05

1

139+23.62

604.39

-0.64

604.79

-0.24

605.03

-0.24

604.79

-0.64

604.39

2

140+06.95

601.57

-0.24

601.57

-0.24

601.81

-0.24

601.57

-0.64

601.17

3

140+56.95

599.88

0

599.88

0

599.88

-0.24

599.64

-0.64

599.24

4

141+06.95

598.19

0.24

598.19

0.24

597.95

-0.24

597.71

-0.64

597.31

PC

141+56.95

596.5

0.48

596.5

0.48

596.02

-0.48

595.54

-0.64

595.38

6
South
End

0

PC

Curve
6
North
End

671.83

4

South
End

107+38.21

142+06.95

594.85

0.72

594.85

0.72

594.13

-0.72

593.41

-0.72

593.41

6'

155+15.26

557.29

0.72

557.29

0.72

556.57

-0.72

555.85

-0.72

555.85

PT

155+65.26

555.97

0.48

555.97

0.48

555.49

-0.48

555.01

-0.64

554.85

4'

156+15.26

554.68

0.24

554.68

0.24

554.44

-0.24

554.2

-0.64

553.8

3'

156+65.26

553.38

0

553.38

0

553.38

-0.24

553.14

-0.64

552.74

2'

157+15.26

552.07

-0.24

552.07

-0.24

552.31

-0.24

552.07

-0.64

551.67

1'

157+98.59

551.56

-0.64

551.96

-0.24

552.2

-0.24

551.96

-0.64

551.56

667.29

11
Curve
7
North
End

-0.24

504.97

-0.24

504.73

-0.64

504.33

186+33.48

503.71

-0.24

503.71

-0.24

503.95

-0.24

503.71

-0.64

503.31

186+83.48

503.34

0

503.34

0

503.34

-0.24

503.1

-0.64

502.7

187+33.48

502.97

0.24

502.97

0.24

502.73

-0.24

502.49

-0.64

502.09

187+83.48

502.6

0.48

502.6

0.48

502.12

-0.48

501.64

-0.64

501.48

6

188+33.48

502.22

0.72

502.22

0.72

501.5

-0.72

500.78

-0.72

500.78

6'

192+58.37

497.03

0.72

497.03

0.72

496.31

-0.72

495.59

-0.72

495.59

PT

193+08.37

495.57

0.48

495.57

0.48

495.09

-0.48

494.61

-0.64

494.45

4'

193+58.37

494.72

0.24

494.72

0.24

494.48

-0.24

494.24

-0.64

493.84

3'

194+08.37

493.87

0

493.87

0

493.87

-0.24

493.63

-0.64

493.23

2'

194+58.37

493.02

-0.24

493.02

-0.24

493.26

-0.24

493.02

-0.64

492.62

1'

195+41.67

491.6

-0.64

492

-0.24

492.24

-0.24

492

-0.64

491.6

1

198+56.06

488.36

-0.64

488.76

-0.24

489

-0.24

488.76

-0.64

488.36

2

199+39.38

487.34

-0.64

487.74

-0.24

487.98

-0.24

487.74

-0.24

487.74

3

199+89.38

486.73

-0.64

487.13

-0.24

487.37

0

487.37

0

487.37

4

200+39.38

486.12

-0.64

486.52

-0.24

486.76

0.24

487

0.24

487

PC

200+89.38

485.51

-0.64

485.67

-0.48

486.15

0.48

486.63

0.48

486.63

6

201+39.38

484.82

-0.72

484.82

-0.72

485.54

0.72

486.26

0.72

486.26

6'

203+23.26

452.1

-0.72

452.1

-0.72

452.82

0.72

453.54

0.72

453.54

PT

203+73.26

481.34

-0.64

481.5

-0.48

481.98

0.48

482.46

0.48

482.46

4'

204+23.26

480.5

-0.64

480.9

-0.24

481.14

0.24

481.38

0.24

481.38

3'

204+73.26

479.43

-0.64

479.83

-0.24

480.07

0

480.07

0

480.07

2'

205+23.26

478.37

-0.64

478.77

-0.24

479.01

-0.24

478.77

-0.24

478.77

1'

206+06.59

476.59

-0.64

476.99

-0.24

477.23

-0.24

476.99

-0.64

476.59

1

220+68.71

445.36

-0.64

445.76

-0.24

446

-0.24

445.76

-0.64

445.36

2

221+52.04

443.58

-0.64

443.98

-0.24

444.22

-0.24

443.98

-0.24

443.98

3

222+02.04

442.52

-0.64

442.92

-0.24

443.16

0

443.16

0

443.16

4

222+52.04

441.51

-0.64

441.91

-0.24

442.15

0.24

442.39

0.24

442.39

PC

223+02.04

440.48

-0.64

440.64

-0.48

441.12

0.48

441.6

0.48

441.6

6
South
End

504.73

PC

Curve
9
North
End

-0.64

4

South
End

504.33

3

Curve
8
North
End

185+50.15

2

South
End

1

223+52.04

439.32

-0.72

439.32

-0.72

440.04

0.72

440.76

0.72

440.76

6'

227+47.25

429.81

-0.72

429.81

-0.72

430.53

0.72

431.25

0.72

431.25

PT

227+97.25

428.47

-0.64

428.63

-0.48

429.11

0.48

429.59

0.48

429.59

4'

228+47.25

427.06

-0.64

427.46

-0.24

427.7

0.24

427.94

0.24

427.94

12
3'

-0.24

426.27

0

426.27

0

426.27

229+47.25

424.21

-0.64

424.61

-0.24

424.85

-0.24

424.61

-0.24

424.61

230+30.58

421.84

-0.64

422.24

-0.24

422.48

-0.24

422.24

-0.64

421.84

1

235+61.03

406.74

-0.64

407.14

-0.24

407.38

-0.24

407.14

-0.64

406.74

236+44.36

404.37

-0.64

404.77

-0.24

405.01

-0.24

404.77

-0.24

404.77

3

236+94.36

402.95

-0.64

403.35

-0.24

403.59

0

403.59

0

403.59

4

237+44.36

401.53

-0.64

401.93

-0.24

402.17

0.24

402.41

0.24

402.41

PC

237+94.36

400.16

-0.64

400.32

-0.48

400.8

0.48

401.28

0.48

401.28

6

238+44.36

398.61

-0.72

398.61

-0.72

399.33

0.72

400.05

0.72

400.05

6'

250+29.05

347.9

-0.72

347.9

-0.72

348.62

0.72

349.34

0.72

349.34

PT

250+79.05

345.53

-0.64

345.69

-0.48

346.17

0.48

346.65

0.48

346.65

4'

251+29.05

343.09

-0.64

343.49

-0.24

343.73

0.24

343.97

0.24

343.97

3'

251+79.05

340.65

-0.64

341.05

-0.24

341.29

0

341.29

0

341.29

2'

252+29.05

338.21

-0.64

338.61

-0.24

338.85

-0.24

338.61

-0.24

338.61

1'

253+12.38

334.14

-0.64

334.54

-0.24

334.78

-0.24

334.54

-0.64

334.14

1

248+45.72

356.92

-0.64

357.32

-0.24

357.56

-0.24

357.32

-0.64

356.92

2

249+29.05

353.26

-0.24

353.26

-0.24

353.5

-0.24

353.26

-0.64

352.86

3

249+79.05

351.06

0

351.06

0

351.06

-0.24

350.82

-0.64

350.42

4

250+29.05

348.86

0.24

348.86

0.24

348.62

-0.24

348.38

-0.64

347.98

PC

250+79.05

346.67

0.48

346.67

0.48

346.19

-0.48

345.71

-0.64

345.55

6
South
End

426.03

2

Curve
11
North
End

-0.64

1'

South
End

425.63

2'

Curve
10
North
End

228+97.25

251+29.05

344.45

0.72

344.45

0.72

343.73

-0.72

343.01

-0.72

343.01

6'

274+55.63

262.43

0.72

262.43

0.72

261.71

-0.72

260.99

-0.72

260.99

PT

275+05.63

260.8

0.48

260.8

0.48

260.32

-0.48

259.84

-0.64

259.68

4'

275+55.63

259.42

0.24

259.42

0.24

259.18

-0.24

258.94

-0.64

258.54

3'

276+05.63

258.21

0

258.21

0

258.21

-0.24

257.97

-0.64

257.57

2'

276+55.63

257

-0.24

257

-0.24

257.24

-0.24

257

-0.64

256.6

1'

277+38.96

255.26

-0.64

255.66

-0.24

255.9

-0.24

255.66

-0.64

255.26

13
Chapter 5: Pavement Design
Section 5.1 Optimal Design:
The pavement of the highway extension was designed using the AASHTO Flexible
Pavement Design Method. The cross section of the pavement design chosen, design #2, is shown
in the picture below. The surface course is made up of 5.7 inches of plant mix asphalt, with a 6
inch, cement treated base course and a 6 inch sandy clay subbase course. The objective was to
keep the cost for pavement construction as low as possible. This particular design was chosen as
the optimal design because it meets all the standards for safety and is the most affordable of all
three alternative designs. About 9,000 vehicles utilize the highway each day per lane, but only
about 720 of these vehicles are trucks that cause significant damage to the pavement over time.
The thicknesses of each section of the pavement are based on the daily axle loading of the trucks
assuming that the structural number was 4 and checking this assumption with the AASHTO
Nomograph. Because of the small percentage of trucks on the highway, it was okay to stick with
the minimum allowable thickness for the subbase layer when designing the pavement. The cost
to construct each layer of the pavement was based on the cost per volume of its individual
material. Volumes were computed from the thickness of each layer, the width of the highway
(12.2m), and the length of the entire stretch of highway (8,193.6m).

Figure 1: Cross Section of Optimal Pavement Design

14
Section 5.2 Summary:
Table 4: Pavement Design Summaries
Design #1
Materials
Road Mix
Sandy Gravel
Sandy Clay

Thickness
17”
5.5”
6”

Cost
$6,474,534
$698,234
$837,881

Total Cost: $8,010,649
Design #2
Materials

Thickness

Cost

Plant Mix
Cement treatment
Sandy Clay

5.7”
6”
6”

$2,894,497
$1,371,078
$837,881

Total Cost: $5,103,456
Design #3
Materials
Plant Mix

Thickness
7.4”

Cost
$3,757,768

Crushed stone
Sandy Clay

4.2”
6”

$799,795
$837,881

Total Cost: $5,395,444

15

More Related Content

What's hot

Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution . Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution . gunjatetm
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Malyar Talash
 
Conen 442 module2: Highway Geometric Design
Conen  442 module2: Highway Geometric DesignConen  442 module2: Highway Geometric Design
Conen 442 module2: Highway Geometric DesignWael ElDessouki
 
Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Civil Zone
 
Designing the highway
Designing the highwayDesigning the highway
Designing the highwayRron de Guzman
 
Irs concrete bridge code
Irs concrete bridge codeIrs concrete bridge code
Irs concrete bridge codeAjay Kumar
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometricsKHUSHBU SHAH
 
Chapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaaChapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaaBashaFayissa1
 
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUISubhendu Samui
 
Sight Distance for horizontal curves
Sight Distance for horizontal curvesSight Distance for horizontal curves
Sight Distance for horizontal curvesLatif Hyder Wadho
 
Geometrical design of highways
Geometrical design of highwaysGeometrical design of highways
Geometrical design of highwaysFresher Thinking
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highwayJunaid Jamadar
 
presentation on Proposal for road survey & construction
presentation on Proposal for road survey & constructionpresentation on Proposal for road survey & construction
presentation on Proposal for road survey & constructionDipendra Bhattarai
 
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Nandan Shandilya
 
Design of vertical alignment
Design of vertical alignmentDesign of vertical alignment
Design of vertical alignmentWyman Words
 
Highway geometric design
Highway geometric designHighway geometric design
Highway geometric designkhaledalshami93
 
Geometric Design of highway
Geometric Design of highway Geometric Design of highway
Geometric Design of highway RAMPRASAD KUMAWAT
 
Lec 04 Geometric Design (Transportation Engineering)
Lec 04 Geometric Design (Transportation Engineering) Lec 04 Geometric Design (Transportation Engineering)
Lec 04 Geometric Design (Transportation Engineering) Hossam Shafiq I
 

What's hot (20)

Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution . Highway Design - Techniques for proper Planning and Execution .
Highway Design - Techniques for proper Planning and Execution .
 
Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)Highway design presentation (Malyar Talash)
Highway design presentation (Malyar Talash)
 
Conen 442 module2: Highway Geometric Design
Conen  442 module2: Highway Geometric DesignConen  442 module2: Highway Geometric Design
Conen 442 module2: Highway Geometric Design
 
Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)Capacity & level of service (transportation engineering)
Capacity & level of service (transportation engineering)
 
Irccode
IrccodeIrccode
Irccode
 
Designing the highway
Designing the highwayDesigning the highway
Designing the highway
 
Irs concrete bridge code
Irs concrete bridge codeIrs concrete bridge code
Irs concrete bridge code
 
Chapter 2 Road geometrics
Chapter 2 Road geometricsChapter 2 Road geometrics
Chapter 2 Road geometrics
 
Chapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaaChapter 2 highway route surveys and locationaa
Chapter 2 highway route surveys and locationaa
 
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI[PDF]PROJECT ON HIGHWAY BY SUBHENDU  SAMUI
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
 
Sight Distance for horizontal curves
Sight Distance for horizontal curvesSight Distance for horizontal curves
Sight Distance for horizontal curves
 
Geometrical design of highways
Geometrical design of highwaysGeometrical design of highways
Geometrical design of highways
 
Geometric design of highway
Geometric design of highwayGeometric design of highway
Geometric design of highway
 
presentation on Proposal for road survey & construction
presentation on Proposal for road survey & constructionpresentation on Proposal for road survey & construction
presentation on Proposal for road survey & construction
 
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)
 
01. general design
01. general design01. general design
01. general design
 
Design of vertical alignment
Design of vertical alignmentDesign of vertical alignment
Design of vertical alignment
 
Highway geometric design
Highway geometric designHighway geometric design
Highway geometric design
 
Geometric Design of highway
Geometric Design of highway Geometric Design of highway
Geometric Design of highway
 
Lec 04 Geometric Design (Transportation Engineering)
Lec 04 Geometric Design (Transportation Engineering) Lec 04 Geometric Design (Transportation Engineering)
Lec 04 Geometric Design (Transportation Engineering)
 

Similar to Transportation Systems Design Project

5 oregon hdm 05 urban-rural-freeway
5 oregon hdm 05 urban-rural-freeway5 oregon hdm 05 urban-rural-freeway
5 oregon hdm 05 urban-rural-freewaySierra Francisco Justo
 
Case Study on Geometry of Four Lane Highway
Case Study on Geometry of Four Lane HighwayCase Study on Geometry of Four Lane Highway
Case Study on Geometry of Four Lane HighwayIRJET Journal
 
Value engineering and application
Value engineering and applicationValue engineering and application
Value engineering and applicationSourish ghosh
 
karthik yadav BATCH 3.pptx
karthik yadav BATCH 3.pptxkarthik yadav BATCH 3.pptx
karthik yadav BATCH 3.pptxMRVOLDEMORT1
 
HIGHWAY ENGINEERING 1 (ii).doc
HIGHWAY ENGINEERING 1 (ii).docHIGHWAY ENGINEERING 1 (ii).doc
HIGHWAY ENGINEERING 1 (ii).docsydneyaugust1
 
Vertical Curves_Presentation_NR.pptx
Vertical Curves_Presentation_NR.pptxVertical Curves_Presentation_NR.pptx
Vertical Curves_Presentation_NR.pptxNaniRoy9
 
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdfEr. Bam Bhandari
 
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PROPLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PROIRJET Journal
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge ConstructionSukhdeep Jat
 
ANSYS Fluent Analysis of Drag Force Three Pickup Truck Options
ANSYS Fluent Analysis of Drag Force Three Pickup Truck OptionsANSYS Fluent Analysis of Drag Force Three Pickup Truck Options
ANSYS Fluent Analysis of Drag Force Three Pickup Truck OptionsSteven Cooke
 
Joint Traffic Management Center Parking Structure
Joint Traffic Management Center Parking StructureJoint Traffic Management Center Parking Structure
Joint Traffic Management Center Parking StructurePostTensioningInstitute
 
Minor project ppt1.pdf
Minor project ppt1.pdfMinor project ppt1.pdf
Minor project ppt1.pdfAnshuRaj51911
 
CV_Anil Malagi
CV_Anil MalagiCV_Anil Malagi
CV_Anil MalagiAnil Malagi
 
Accelerated Bridge Construction( ABC)
Accelerated Bridge  Construction( ABC)Accelerated Bridge  Construction( ABC)
Accelerated Bridge Construction( ABC)varun km
 
Foundation Design For the abutment and footing design, soil anal.docx
Foundation Design For the abutment and footing design, soil anal.docxFoundation Design For the abutment and footing design, soil anal.docx
Foundation Design For the abutment and footing design, soil anal.docxbudbarber38650
 

Similar to Transportation Systems Design Project (20)

5 oregon hdm 05 urban-rural-freeway
5 oregon hdm 05 urban-rural-freeway5 oregon hdm 05 urban-rural-freeway
5 oregon hdm 05 urban-rural-freeway
 
Ch 4
Ch 4Ch 4
Ch 4
 
Case Study on Geometry of Four Lane Highway
Case Study on Geometry of Four Lane HighwayCase Study on Geometry of Four Lane Highway
Case Study on Geometry of Four Lane Highway
 
Value engineering and application
Value engineering and applicationValue engineering and application
Value engineering and application
 
karthik yadav BATCH 3.pptx
karthik yadav BATCH 3.pptxkarthik yadav BATCH 3.pptx
karthik yadav BATCH 3.pptx
 
HIGHWAY ENGINEERING 1 (ii).doc
HIGHWAY ENGINEERING 1 (ii).docHIGHWAY ENGINEERING 1 (ii).doc
HIGHWAY ENGINEERING 1 (ii).doc
 
Vertical Curves_Presentation_NR.pptx
Vertical Curves_Presentation_NR.pptxVertical Curves_Presentation_NR.pptx
Vertical Curves_Presentation_NR.pptx
 
cv Updated M.Anwar
cv Updated M.Anwarcv Updated M.Anwar
cv Updated M.Anwar
 
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
1. ii Highway Alignment,, Engineering Survey and feasibility study.pdf
 
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PROPLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
PLANNING DESIGNING AND ANALYSIS OF FLYOVEER BY USING STAAD PRO
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge Construction
 
ANSYS Fluent Analysis of Drag Force Three Pickup Truck Options
ANSYS Fluent Analysis of Drag Force Three Pickup Truck OptionsANSYS Fluent Analysis of Drag Force Three Pickup Truck Options
ANSYS Fluent Analysis of Drag Force Three Pickup Truck Options
 
Joint Traffic Management Center Parking Structure
Joint Traffic Management Center Parking StructureJoint Traffic Management Center Parking Structure
Joint Traffic Management Center Parking Structure
 
Minor project ppt1.pdf
Minor project ppt1.pdfMinor project ppt1.pdf
Minor project ppt1.pdf
 
CV_Anil Malagi
CV_Anil MalagiCV_Anil Malagi
CV_Anil Malagi
 
Mumbai-Nagpur.pdf
Mumbai-Nagpur.pdfMumbai-Nagpur.pdf
Mumbai-Nagpur.pdf
 
Accelerated Bridge Construction( ABC)
Accelerated Bridge  Construction( ABC)Accelerated Bridge  Construction( ABC)
Accelerated Bridge Construction( ABC)
 
Foundation Design For the abutment and footing design, soil anal.docx
Foundation Design For the abutment and footing design, soil anal.docxFoundation Design For the abutment and footing design, soil anal.docx
Foundation Design For the abutment and footing design, soil anal.docx
 
R E T 565construction Technology Infrastructure
R E T 565construction Technology InfrastructureR E T 565construction Technology Infrastructure
R E T 565construction Technology Infrastructure
 
Construction Technology
Construction TechnologyConstruction Technology
Construction Technology
 

More from Megan Hanrahan

CEE171 Final Project
CEE171  Final ProjectCEE171  Final Project
CEE171 Final ProjectMegan Hanrahan
 
CEE81B AutoCAD Practice
CEE81B AutoCAD PracticeCEE81B AutoCAD Practice
CEE81B AutoCAD PracticeMegan Hanrahan
 
CEE81B Introduction to ArcGIS
CEE81B Introduction to ArcGISCEE81B Introduction to ArcGIS
CEE81B Introduction to ArcGISMegan Hanrahan
 
CEE81A Homework 2
CEE81A Homework 2CEE81A Homework 2
CEE81A Homework 2Megan Hanrahan
 
First AutoCAD Project
First AutoCAD ProjectFirst AutoCAD Project
First AutoCAD ProjectMegan Hanrahan
 
Intro to Fluid Mechanics Design Project
Intro to Fluid Mechanics Design ProjectIntro to Fluid Mechanics Design Project
Intro to Fluid Mechanics Design ProjectMegan Hanrahan
 

More from Megan Hanrahan (6)

CEE171 Final Project
CEE171  Final ProjectCEE171  Final Project
CEE171 Final Project
 
CEE81B AutoCAD Practice
CEE81B AutoCAD PracticeCEE81B AutoCAD Practice
CEE81B AutoCAD Practice
 
CEE81B Introduction to ArcGIS
CEE81B Introduction to ArcGISCEE81B Introduction to ArcGIS
CEE81B Introduction to ArcGIS
 
CEE81A Homework 2
CEE81A Homework 2CEE81A Homework 2
CEE81A Homework 2
 
First AutoCAD Project
First AutoCAD ProjectFirst AutoCAD Project
First AutoCAD Project
 
Intro to Fluid Mechanics Design Project
Intro to Fluid Mechanics Design ProjectIntro to Fluid Mechanics Design Project
Intro to Fluid Mechanics Design Project
 

Recently uploaded

Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajanpragatimahajan3
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 đź’ž Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 đź’ž Full Nigh...Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 đź’ž Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 đź’ž Full Nigh...Pooja Nehwal
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeThiyagu K
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxShobhayan Kirtania
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...anjaliyadav012327
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Dr. Mazin Mohamed alkathiri
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 

Recently uploaded (20)

INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
social pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajansocial pharmacy d-pharm 1st year by Pragati K. Mahajan
social pharmacy d-pharm 1st year by Pragati K. Mahajan
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 đź’ž Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 đź’ž Full Nigh...Russian Call Girls in Andheri Airport Mumbai WhatsApp  9167673311 đź’ž Full Nigh...
Russian Call Girls in Andheri Airport Mumbai WhatsApp 9167673311 đź’ž Full Nigh...
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptx
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
 
Advance Mobile Application Development class 07
Advance Mobile Application Development class 07Advance Mobile Application Development class 07
Advance Mobile Application Development class 07
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
CĂłdigo Creativo y Arte de Software | Unidad 1
CĂłdigo Creativo y Arte de Software | Unidad 1CĂłdigo Creativo y Arte de Software | Unidad 1
CĂłdigo Creativo y Arte de Software | Unidad 1
 

Transportation Systems Design Project