1. Work BreakdownStructure Of BuilingWhichare ConstructedinUniversityof Lahore.1
SubmittedBy:ShahzadAli2
SubmittedTo:SirJunaidAhmad3
4
UOL
1 Cnstruction of
Two Storey
Building
1.1 Concrete
Work
1.1.1 Raft
1.1.2 Pouringof
Column
1.1.3 Pour
columns
1.1.4 Pour Beams
Pour of slab
1.2 Electrical
Work
1.2.1 Installation
of pipe
1.2.2 Installation
of Wires
Installation of
button
1.3 Plumbing
Work
1.3.1 Water Pipes
1.3.2 Gas pipes
1.3.3 Severage
1.4 Exterior
1.4.1 Plaster
1.4.2 Weather
Shield
1.5 Interior
Finishes
1.5.1 Plaster
1.5.2 White
cement