SlideShare a Scribd company logo
1 of 20
Presented ByPresented By
PraveenPraveen
INTRODUCTION:
POWER REQUIREMENT IS INCREASING DAY BY DAY DUE
TO THE MAXIMUM POWER UTILIZATION. IN ORDER TO MEET
THIS DEMAND A LARGE POWER HAS TO BE GENERATED IN AN
EFFICIENT WAY. A NEW MACHINE NAMELY “POWERFORMER”
CAN DO THIS. THE CONVENTIONAL PLANT GENERATED
VOLTAGE IS LIMITED TO 30KV. THIS VOLTAGE IS STEPPED UP
TO A HIGH VOLTAGE LEVEL IN THE ORDER OF 800KV WITH THE
HELP OF POWER STEP-UP TRANSFORMERS. THE STEP-UP
TRANSFORMER IMPOSES GREAT DRAWBACKS ON THE
POWER PLANT, STARTING FROM REDUCTION IN EFFICIENCY,
HIGH MAINTENANCE COSTS, AND MORE SPACE LESS
AVAILABILITY.
• DURING THE LAST CENTURY, A NUMBER OF ATTEMPTS
WERE MADE AT DEVELOPING A HIGH-VOLTAGE GENERATOR
THAT COULD BE CONNECTED DIRECTLY TO THE POWER
GRID, I.E. WITHOUT GOING ANY STEP-UP TRANSFORMER.
THE POWERFORMER HAS OPENED A NEW CHAPTER IN THE
GENERATION AND TRANSMISSION OF ELECTRICAL ENERGY.
OBJECTIVES:
• POWERFORMER CONCEPT
• INNOVATIVE DESIGN
• THE FIRST POWERFORMER
INSTALLATION
• ADVANTAGES OF POWERFORMER
POWERFORMER CONCEPT:
•POWERFORMER IS A NEW MACHINE, IT IS A 3-PHASE AC GENERATOR
WITH A ROTOR OF CONVENTIONAL DESIGN.
•THE DIFFERENCE COMPARED WITH CONVENTIONAL GENERATOR LIES IN
THE STATOR WINDINGS.
•IN POWERFORMER STATOR WINDING CONSISTS OF HIGH-VOLTAGE
CABLES INSTEAD OF TODAY’S WINDINGS WITH A SQUARE CROSS-
SECTION.
•BY USING HIGH-VOLTAGE CABLES AS GENERATOR STATOR WINDING, IT
IS POSSIBLE TO HIGHLY INCREASE THE GENERATED VOLTAGE.
•THE DECISIVE DIFFERENCE BETWEEN THIS DESIGN AND PRESENT-DAY
TECHNOLOGY IS THAT POWERFORMER ALLOWS DIRECT CONNECTION
TO THE HIGH-VOLTAGE GRID.
SCHEMATIC DIAGRAM OF A CONVENTIONAL PLANT WITH STEP-UP
TRANSFORMER (A), AND THE SAME PLANT WHEN THE NEW
TECHNOLOGY IS USED (B).
1. GENERATOR
2. GENERATOR CIRCUIT BREAKER
3. SURGE ARRESTER
4. STEP-UP TRANSFORMER
5. LINE CIRCUIT BREAKER
•THIS DESIGN IMPLIES THE OMISSION OF THE GENERATOR
CIRCUIT BREAKER, THE HIGH CURRENT BUS BAR AND THE
STEP-UP POWER TRANSFORMER FROM THE POWER PLANT,
BECAUSE POWERFORMER COMPRISES THE FUNCTIONS OF
BOTH GENERATOR AND STEP-UP TRANSFORMER AS
REALIZED FROM ABOVE FIGURE
•AS A CONSEQUENCE THERE IS AN INCREASE UP TO 1.5% IN
TOTAL ELECTRIC POWER EFFICIENCY COMPARED WITH
TODAY’S BEST DESIGNS, WITHOUT USING
SUPERCONDUCTIVE MATERIALS.
INNOVATIVE DESIGN:
•POWERFORMER HAS BEEN DESIGNED WITH SEVERAL
UNIQUE FEATURES THAT ALLOW IT TO EXCEED THE 30KV
LIMIT, INCLUDING A WINDING CONSISTING OF POWER
CABLES AND AN INNOVATIVE STATOR DESIGN.
POWERFORMER WINDINGS:
• THE WINDING CONSISTS OF A POWER CABLE WITH SOLID
INSULATION AND TWO SEMICONDUCTING LAYERS, ONE
SURROUNDS THE CONDUCTOR AND THE OTHER OUTSIDE
THE INSULATION.
•THE INSULATION MATERIAL IS CROSS-LINKED
POLYETHYLENE
• HIGH-VOLTAGE POWER CABLES ARE USED IN WINDING.
•THESE CABLES USED TO MANY ADVANTAGES OVER
CONVENTIONAL DESIGNS
A CROSS SECTION OF THE POWER CABLE USED IN THE
STATOR WINDING OF POWERFORMER:
POWERFORMER CABLE VERSUS CONVENTIONAL
RECTANGULAR CONDUCTORS:
NON CONVENTIONAL STATOR DESIGN:
THE STATOR OF POWERFORMER CONSISTS OF A LAMINATED
CORE.
THESE LAMINATED CORE ARE BUILT UP FROM ELECTRICAL
SHEET.
THE WINDING IS LOCATED IN THE SLOTS FORMED BY THE
TEETH, THE CROSS SECTION OF THE SLOTS DECREASES . THE
WINDING TURN REQUIRES LESS CABLE INSULATION THE
CLOSER IT IS TO THE ROTOR.
EACH SLOT HAS CIRCULAR BORES AT INTERVALS, FORMING
NARROW WAISTS BETWEEN THE WINDING LAYERS, AS
SHOWN IN FIGURE BELOW.
SECTION OF THE STATOR IN POWERFORMER:
THE FIRST POWERFORMER INSTALLATION:
•THE WORLD’S FIRST HIGH-VOLTAGE GENERATOR BASED ON
THE NEW TECHNOLOGY; A HYDROPOWER MACHINE IS
RATED AT 11 MVA, 45 KV, AND 600 RPM. THE MACHINE HAS
ALREADY BEEN TESTED IN THE FACTORY AND INSTALLED AT
THE PORJUS HYDROPOWER CENTER ON THE LULE RIVER IN
NORTHERN SWEDEN. THE MACHINE IS DIRECTLY
CONNECTED TO THE 45 KV TRANSMISSION POWER GRIDS;
ITS STATOR IS SHOWN IN BELOW FIGURE
STATOR VIEW OF THE FIRST POWERFORMER:STATOR VIEW OF THE FIRST POWERFORMER:
1.It generates Low voltage
(<30kv)
1.It generates High voltage
(>>30kV)
2. High current 2. Low current
3. Stator has Short teeth 3. Stator Long teeth
4. High weight 4. Less weight
5. Mount winding is used 5. Thread cable is used
6. Impregnating windings 6. Extrusion type winding is used
7. High temperature 7. Low temperature
COMPARISON OF CONVENTIONAL GENERATOR AND
POWERFORMER:
•HIGHER EFFICIENCY
•LOW MAINTENANCE COSTS
• POWER TRANSFER FORM GENERATOR TO POWER
GRID WITHOUT GOING VIA THE STEP-UP
TRANSFORMER
•BETTER AVAILABILITY
ADVANTAGES OF POWERFORMER:
CONCLUSION:
ABB’S NEW HIGH-VOLTAGE GENERATOR (POWERFORMER) HAS BEEN
STUDIED THE NEW CONCEPT PROVIDES THE POSSIBILITY TO DIRECTLY
CONNECT A ROTATING MACHINE TO THE HIGH-VOLTAGE POWER GRID
WITHOUT GOING ANY STEP-UP TRANSFORMER. POWERFORMER IS A
HIGH-VOLTAGE GENERATOR; THE LIMITATION IN ITS RATED VOLTAGE
IS SET SOLELY BY THE AC
• POWER CABLE AND THE CABLE ACCESSORIES (TERMINATIONS AND
JOINTS) USED IN ITS STATOR WINDING. THIS MEANS THAT
POWERFORMER OF VOLTAGE RATINGS UP TO 400 KV CAN BE REALIZED,
ALTHOUGH HAS NOT BEEN PROVED YET.
Power former
Power former

More Related Content

What's hot

Electrical Machines - II
Electrical Machines - IIElectrical Machines - II
Electrical Machines - IIkarthi1017
 
INTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERINTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERNitish NIT
 
Report On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationReport On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationEkram Bin Mamun
 
Chapter 3 Generation of high voltages and current
Chapter 3 Generation of high voltages and currentChapter 3 Generation of high voltages and current
Chapter 3 Generation of high voltages and currentmukund mukund.m
 
Measurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionMeasurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionAman Ansari
 
Lecture 9c - Wave Trap.pptx
Lecture 9c - Wave Trap.pptxLecture 9c - Wave Trap.pptx
Lecture 9c - Wave Trap.pptxAniruddhaRay11
 
Static excitation-system
Static excitation-systemStatic excitation-system
Static excitation-systemDeepak Jha
 
Protection of three phase synchronous generator
Protection of three phase synchronous generatorProtection of three phase synchronous generator
Protection of three phase synchronous generatorMohammad Abdullah
 
132 kv substation
132 kv substation132 kv substation
132 kv substationWipro
 
Transmission line insulators
Transmission line insulatorsTransmission line insulators
Transmission line insulatorsPrashant Sharma
 
Voltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTSVoltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTSKarthik Bharadwaj
 
Grid synchronisation
Grid synchronisationGrid synchronisation
Grid synchronisationmanogna gwen
 
An introduction to FACTS
An introduction to FACTSAn introduction to FACTS
An introduction to FACTSAyyarao T S L V
 
A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationSubhrajit Ghosh
 
Power Line Carrier Communication
Power Line Carrier CommunicationPower Line Carrier Communication
Power Line Carrier CommunicationNeha Gethe
 
Ee 791 drives lab maual
Ee 791 drives lab maualEe 791 drives lab maual
Ee 791 drives lab maualDivya15121983
 

What's hot (20)

upfc
upfcupfc
upfc
 
Electrical Machines - II
Electrical Machines - IIElectrical Machines - II
Electrical Machines - II
 
INTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERINTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLER
 
Report On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-StationReport On Industrial Tour At Khulshi Grid Sub-Station
Report On Industrial Tour At Khulshi Grid Sub-Station
 
Fc tcr.newpptx
Fc tcr.newpptxFc tcr.newpptx
Fc tcr.newpptx
 
Chapter 3 Generation of high voltages and current
Chapter 3 Generation of high voltages and currentChapter 3 Generation of high voltages and current
Chapter 3 Generation of high voltages and current
 
Measurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionMeasurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_version
 
Lecture 9c - Wave Trap.pptx
Lecture 9c - Wave Trap.pptxLecture 9c - Wave Trap.pptx
Lecture 9c - Wave Trap.pptx
 
220 kv G.S.S (report)
220 kv G.S.S (report)220 kv G.S.S (report)
220 kv G.S.S (report)
 
Static excitation-system
Static excitation-systemStatic excitation-system
Static excitation-system
 
Protection of three phase synchronous generator
Protection of three phase synchronous generatorProtection of three phase synchronous generator
Protection of three phase synchronous generator
 
132 kv substation
132 kv substation132 kv substation
132 kv substation
 
Transmission line insulators
Transmission line insulatorsTransmission line insulators
Transmission line insulators
 
Voltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTSVoltage source Converters as a building block of HVDC and FACTS
Voltage source Converters as a building block of HVDC and FACTS
 
Grid synchronisation
Grid synchronisationGrid synchronisation
Grid synchronisation
 
An introduction to FACTS
An introduction to FACTSAn introduction to FACTS
An introduction to FACTS
 
A Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv SubstationA Training Report Of Saltlake 132/33kv Substation
A Training Report Of Saltlake 132/33kv Substation
 
Power Line Carrier Communication
Power Line Carrier CommunicationPower Line Carrier Communication
Power Line Carrier Communication
 
Ee 791 drives lab maual
Ee 791 drives lab maualEe 791 drives lab maual
Ee 791 drives lab maual
 
UPFC
UPFCUPFC
UPFC
 

Viewers also liked

Viewers also liked (20)

Modern Trends in Engineering, Science and Technology
Modern Trends in Engineering, Science and TechnologyModern Trends in Engineering, Science and Technology
Modern Trends in Engineering, Science and Technology
 
Lunar solar power system
Lunar solar power systemLunar solar power system
Lunar solar power system
 
Recent Trends In Power Generation
Recent Trends In Power GenerationRecent Trends In Power Generation
Recent Trends In Power Generation
 
Building Vibrant Communities
Building Vibrant CommunitiesBuilding Vibrant Communities
Building Vibrant Communities
 
Dc machines 2
Dc machines 2Dc machines 2
Dc machines 2
 
Dc 2
Dc 2Dc 2
Dc 2
 
Legge 10/91
Legge 10/91Legge 10/91
Legge 10/91
 
Studytransformers
StudytransformersStudytransformers
Studytransformers
 
Ozone depletion
Ozone depletionOzone depletion
Ozone depletion
 
MICROCONTROLLER BASED SOLAR POWER INVERTER
MICROCONTROLLER BASED SOLAR POWER INVERTERMICROCONTROLLER BASED SOLAR POWER INVERTER
MICROCONTROLLER BASED SOLAR POWER INVERTER
 
Nuclear Power Plant
Nuclear Power PlantNuclear Power Plant
Nuclear Power Plant
 
PPT_Major@2015
PPT_Major@2015PPT_Major@2015
PPT_Major@2015
 
International Space Station
International Space Station International Space Station
International Space Station
 
Gas insulated transmission line
Gas insulated transmission lineGas insulated transmission line
Gas insulated transmission line
 
Gas insulated transmission line
Gas insulated transmission lineGas insulated transmission line
Gas insulated transmission line
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
 
Final presentation on antimatter
Final presentation on antimatterFinal presentation on antimatter
Final presentation on antimatter
 
Lunar solar power system
Lunar solar power systemLunar solar power system
Lunar solar power system
 
Augustus - Rise To Power
Augustus - Rise To PowerAugustus - Rise To Power
Augustus - Rise To Power
 
electricity generation from speed breaker
electricity generation from speed breakerelectricity generation from speed breaker
electricity generation from speed breaker
 

Similar to Power former

Wind power generation presentation by vikas gupta
Wind power generation presentation by vikas guptaWind power generation presentation by vikas gupta
Wind power generation presentation by vikas guptaVikas Gupta
 
Micro Hydrro electricc projects
Micro Hydrro electricc projectsMicro Hydrro electricc projects
Micro Hydrro electricc projectsAbhishek Raj
 
Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Avirup Ghosh
 
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING Om Prakash
 
Hydro Electric project
Hydro Electric projectHydro Electric project
Hydro Electric projectRanjeet Verma
 
Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Pratik Diyora
 
foor step power generation ppt
foor step power generation pptfoor step power generation ppt
foor step power generation pptRajendra Prasad
 
UGVCL DHRUMIL 2003.pptx hhkhftyhjnkkkkookn
UGVCL DHRUMIL 2003.pptx hhkhftyhjnkkkkooknUGVCL DHRUMIL 2003.pptx hhkhftyhjnkkkkookn
UGVCL DHRUMIL 2003.pptx hhkhftyhjnkkkkooknHKChanel
 
Hydro Energy Technology
Hydro Energy TechnologyHydro Energy Technology
Hydro Energy TechnologyAjay Bhatnagar
 
Design and development of pico micro hydro system by using house hold water s...
Design and development of pico micro hydro system by using house hold water s...Design and development of pico micro hydro system by using house hold water s...
Design and development of pico micro hydro system by using house hold water s...eSAT Publishing House
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxAkshaiSai2
 
Powerstar Brochure
Powerstar BrochurePowerstar Brochure
Powerstar BrochureTracy Eaton
 

Similar to Power former (20)

Wind power generation presentation by vikas gupta
Wind power generation presentation by vikas guptaWind power generation presentation by vikas gupta
Wind power generation presentation by vikas gupta
 
Paper presentation1
Paper presentation1Paper presentation1
Paper presentation1
 
Micro Hydrro electricc projects
Micro Hydrro electricc projectsMicro Hydrro electricc projects
Micro Hydrro electricc projects
 
Power factor improvement
Power factor improvementPower factor improvement
Power factor improvement
 
Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.Industrial Training at Howrah 220 kV Substation.
Industrial Training at Howrah 220 kV Substation.
 
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
FEROZE GANDHI UNCHAHAR THERMAL POWER PLANT(NTPC UNCHAHAR) SUMMER TRAINING
 
Hydro Electric project
Hydro Electric projectHydro Electric project
Hydro Electric project
 
Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008
 
A Project Report
A Project ReportA Project Report
A Project Report
 
foor step power generation ppt
foor step power generation pptfoor step power generation ppt
foor step power generation ppt
 
Ashwani
AshwaniAshwani
Ashwani
 
UGVCL DHRUMIL 2003.pptx hhkhftyhjnkkkkookn
UGVCL DHRUMIL 2003.pptx hhkhftyhjnkkkkooknUGVCL DHRUMIL 2003.pptx hhkhftyhjnkkkkookn
UGVCL DHRUMIL 2003.pptx hhkhftyhjnkkkkookn
 
Hydro Energy Technology
Hydro Energy TechnologyHydro Energy Technology
Hydro Energy Technology
 
Basics of hvdc
Basics of hvdc Basics of hvdc
Basics of hvdc
 
Design and development of pico micro hydro system by using house hold water s...
Design and development of pico micro hydro system by using house hold water s...Design and development of pico micro hydro system by using house hold water s...
Design and development of pico micro hydro system by using house hold water s...
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
 
Amit ekka1.pptx
Amit ekka1.pptxAmit ekka1.pptx
Amit ekka1.pptx
 
kamal project ppt
kamal project pptkamal project ppt
kamal project ppt
 
Construction of PCC Parapet
Construction of PCC Parapet Construction of PCC Parapet
Construction of PCC Parapet
 
Powerstar Brochure
Powerstar BrochurePowerstar Brochure
Powerstar Brochure
 

Recently uploaded

KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 

Recently uploaded (20)

KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 

Power former

  • 2. INTRODUCTION: POWER REQUIREMENT IS INCREASING DAY BY DAY DUE TO THE MAXIMUM POWER UTILIZATION. IN ORDER TO MEET THIS DEMAND A LARGE POWER HAS TO BE GENERATED IN AN EFFICIENT WAY. A NEW MACHINE NAMELY “POWERFORMER” CAN DO THIS. THE CONVENTIONAL PLANT GENERATED VOLTAGE IS LIMITED TO 30KV. THIS VOLTAGE IS STEPPED UP TO A HIGH VOLTAGE LEVEL IN THE ORDER OF 800KV WITH THE HELP OF POWER STEP-UP TRANSFORMERS. THE STEP-UP TRANSFORMER IMPOSES GREAT DRAWBACKS ON THE POWER PLANT, STARTING FROM REDUCTION IN EFFICIENCY, HIGH MAINTENANCE COSTS, AND MORE SPACE LESS AVAILABILITY.
  • 3. • DURING THE LAST CENTURY, A NUMBER OF ATTEMPTS WERE MADE AT DEVELOPING A HIGH-VOLTAGE GENERATOR THAT COULD BE CONNECTED DIRECTLY TO THE POWER GRID, I.E. WITHOUT GOING ANY STEP-UP TRANSFORMER. THE POWERFORMER HAS OPENED A NEW CHAPTER IN THE GENERATION AND TRANSMISSION OF ELECTRICAL ENERGY.
  • 4. OBJECTIVES: • POWERFORMER CONCEPT • INNOVATIVE DESIGN • THE FIRST POWERFORMER INSTALLATION • ADVANTAGES OF POWERFORMER
  • 5. POWERFORMER CONCEPT: •POWERFORMER IS A NEW MACHINE, IT IS A 3-PHASE AC GENERATOR WITH A ROTOR OF CONVENTIONAL DESIGN. •THE DIFFERENCE COMPARED WITH CONVENTIONAL GENERATOR LIES IN THE STATOR WINDINGS. •IN POWERFORMER STATOR WINDING CONSISTS OF HIGH-VOLTAGE CABLES INSTEAD OF TODAY’S WINDINGS WITH A SQUARE CROSS- SECTION. •BY USING HIGH-VOLTAGE CABLES AS GENERATOR STATOR WINDING, IT IS POSSIBLE TO HIGHLY INCREASE THE GENERATED VOLTAGE. •THE DECISIVE DIFFERENCE BETWEEN THIS DESIGN AND PRESENT-DAY TECHNOLOGY IS THAT POWERFORMER ALLOWS DIRECT CONNECTION TO THE HIGH-VOLTAGE GRID.
  • 6. SCHEMATIC DIAGRAM OF A CONVENTIONAL PLANT WITH STEP-UP TRANSFORMER (A), AND THE SAME PLANT WHEN THE NEW TECHNOLOGY IS USED (B). 1. GENERATOR 2. GENERATOR CIRCUIT BREAKER 3. SURGE ARRESTER 4. STEP-UP TRANSFORMER 5. LINE CIRCUIT BREAKER
  • 7. •THIS DESIGN IMPLIES THE OMISSION OF THE GENERATOR CIRCUIT BREAKER, THE HIGH CURRENT BUS BAR AND THE STEP-UP POWER TRANSFORMER FROM THE POWER PLANT, BECAUSE POWERFORMER COMPRISES THE FUNCTIONS OF BOTH GENERATOR AND STEP-UP TRANSFORMER AS REALIZED FROM ABOVE FIGURE •AS A CONSEQUENCE THERE IS AN INCREASE UP TO 1.5% IN TOTAL ELECTRIC POWER EFFICIENCY COMPARED WITH TODAY’S BEST DESIGNS, WITHOUT USING SUPERCONDUCTIVE MATERIALS.
  • 8. INNOVATIVE DESIGN: •POWERFORMER HAS BEEN DESIGNED WITH SEVERAL UNIQUE FEATURES THAT ALLOW IT TO EXCEED THE 30KV LIMIT, INCLUDING A WINDING CONSISTING OF POWER CABLES AND AN INNOVATIVE STATOR DESIGN.
  • 9. POWERFORMER WINDINGS: • THE WINDING CONSISTS OF A POWER CABLE WITH SOLID INSULATION AND TWO SEMICONDUCTING LAYERS, ONE SURROUNDS THE CONDUCTOR AND THE OTHER OUTSIDE THE INSULATION. •THE INSULATION MATERIAL IS CROSS-LINKED POLYETHYLENE • HIGH-VOLTAGE POWER CABLES ARE USED IN WINDING. •THESE CABLES USED TO MANY ADVANTAGES OVER CONVENTIONAL DESIGNS
  • 10. A CROSS SECTION OF THE POWER CABLE USED IN THE STATOR WINDING OF POWERFORMER:
  • 11. POWERFORMER CABLE VERSUS CONVENTIONAL RECTANGULAR CONDUCTORS:
  • 12. NON CONVENTIONAL STATOR DESIGN: THE STATOR OF POWERFORMER CONSISTS OF A LAMINATED CORE. THESE LAMINATED CORE ARE BUILT UP FROM ELECTRICAL SHEET. THE WINDING IS LOCATED IN THE SLOTS FORMED BY THE TEETH, THE CROSS SECTION OF THE SLOTS DECREASES . THE WINDING TURN REQUIRES LESS CABLE INSULATION THE CLOSER IT IS TO THE ROTOR. EACH SLOT HAS CIRCULAR BORES AT INTERVALS, FORMING NARROW WAISTS BETWEEN THE WINDING LAYERS, AS SHOWN IN FIGURE BELOW.
  • 13. SECTION OF THE STATOR IN POWERFORMER:
  • 14. THE FIRST POWERFORMER INSTALLATION: •THE WORLD’S FIRST HIGH-VOLTAGE GENERATOR BASED ON THE NEW TECHNOLOGY; A HYDROPOWER MACHINE IS RATED AT 11 MVA, 45 KV, AND 600 RPM. THE MACHINE HAS ALREADY BEEN TESTED IN THE FACTORY AND INSTALLED AT THE PORJUS HYDROPOWER CENTER ON THE LULE RIVER IN NORTHERN SWEDEN. THE MACHINE IS DIRECTLY CONNECTED TO THE 45 KV TRANSMISSION POWER GRIDS; ITS STATOR IS SHOWN IN BELOW FIGURE
  • 15. STATOR VIEW OF THE FIRST POWERFORMER:STATOR VIEW OF THE FIRST POWERFORMER:
  • 16. 1.It generates Low voltage (<30kv) 1.It generates High voltage (>>30kV) 2. High current 2. Low current 3. Stator has Short teeth 3. Stator Long teeth 4. High weight 4. Less weight 5. Mount winding is used 5. Thread cable is used 6. Impregnating windings 6. Extrusion type winding is used 7. High temperature 7. Low temperature COMPARISON OF CONVENTIONAL GENERATOR AND POWERFORMER:
  • 17. •HIGHER EFFICIENCY •LOW MAINTENANCE COSTS • POWER TRANSFER FORM GENERATOR TO POWER GRID WITHOUT GOING VIA THE STEP-UP TRANSFORMER •BETTER AVAILABILITY ADVANTAGES OF POWERFORMER:
  • 18. CONCLUSION: ABB’S NEW HIGH-VOLTAGE GENERATOR (POWERFORMER) HAS BEEN STUDIED THE NEW CONCEPT PROVIDES THE POSSIBILITY TO DIRECTLY CONNECT A ROTATING MACHINE TO THE HIGH-VOLTAGE POWER GRID WITHOUT GOING ANY STEP-UP TRANSFORMER. POWERFORMER IS A HIGH-VOLTAGE GENERATOR; THE LIMITATION IN ITS RATED VOLTAGE IS SET SOLELY BY THE AC • POWER CABLE AND THE CABLE ACCESSORIES (TERMINATIONS AND JOINTS) USED IN ITS STATOR WINDING. THIS MEANS THAT POWERFORMER OF VOLTAGE RATINGS UP TO 400 KV CAN BE REALIZED, ALTHOUGH HAS NOT BEEN PROVED YET.