SlideShare a Scribd company logo
1 of 20
Construction Contract Relationships
Group Members:
Hasan Alhashhoush
Ismail Fakhro
Mohamad Gheath Kreaker
Naska Abbassi
Laur Vatsfeld
Public
Procurement Award Criteria
Procurement Routes
Factors Affecting Selection of Procurement Route
Procurement Phases and Procedure
Awarding Criteria Selection
Interviews
Conclusion
Content
 What is Public procurement ?
 The acquisition, whether under formal contract or not, of
works, purchases and services by public organizations.
 Ranges from the buying of goods or services to formal
tendering and placing contracts for large infrastructural projects
Public procurement is concerned with how public-sector
organizations spend taxpayers money on goods and services.
Introduction
Procurement Routes
There are three different
methods of procurement
routes
The type of procurement
route is selected by
public client
Selection of procurement
route is based on many
variables
Procurement Routes: Traditional Method
 Widely used for public procurement and can be described as step-by-step approach.
 This method is relatively secure, especially when
it comes to value for money.
 On the other hand it can take relatively long time to accomplish the desired outcome. For
instance, fixing any kind of flawed aspect of the project takes a lot of time, because usually there
are different contractors for different parts of the developed project.
Procurement Routes: Design and Build (DB)
Can be single stage or two-stage.
Relative speed and cost certainty.
 less time consuming.
 the contracting authority loses some degree of control over the design process as the design will
be the responsibility of a contractor (design and build ).
Procurement Routes: Managing Contracts
 Relatively fast compared to the other two methods.
 There is a lot of uncertainty for the client until the completion of the project.
 Design developed by an architect employed by the client.
Factors Affecting Selection of Procurement Route
• Client resources: client’s knowledge and experience.
• Project characteristics: size, complexity and location of the project.
• Ability to make changes at various stages.
• Risk management.
• Cost issues
• Timing
Procurement Phases
The procurement process has two main phases that are dependent on the procurement route:
1- The supplier selection (the choice of adequate suppliers).
2-The supplier evaluation (assessment of performance).
Allowable Procedure for Public Procurement
 Open procedures : all interested parties can participate in the tendering process.
 Restricted procedures : only selected contractors may submit tenders.
 Negotiated procedures : clients consult with the contractors before making the decision which
one to select.
 Competitive dialogue : more complicated procedure used when contracting authorities find
that it is not possible to achieve the desired goals with one of the
aforementioned procedures.
Awarding Criteria Selection
 Historically the performance assessment of construction contractors has based on the lowest price
criteria, as it is an objective and transparent approach.
 Researches have shown that there can be many hidden risks behind the so called ‘cheapest tender’:
1. Does not ensure lowest overall project cost (cost overruns).
2. Can result in high costs during the building life cycle.
3. Lowest price may not provide quality or satisfaction among clients.
Awarding Criteria Selection
 More complex award systems with different non-
price criteria also known as scoring-based
competitive tendering have been developed .
 Research results in Sweden show that local
authorities prefer price or easily measured non-price
criteria.
 The same research states that project-specific
selection criteria include (listed from more to less
popular) :
Tender price
Individual experience
of key project
personnel
Personality related
criteria of key project
personnel
Technical aspects of design
Innovative/creative solutions
Project execution/action plan
Aesthetic aspects of design and life-cycle costs
Less Popular
Awarding Criteria Selection
 This list confirms that even though there are quality requirements in supplier selection, in most
cases public clients want to reassure that those requirements are met.
 Another important aspect that needs to be kept in mind when using scoring-based tendering:
“If multiple criteria are to be used, there are rules to safeguard that they are applied
transparently”.
Research in Sweden shows that For public projects :
Tender price: up to 70% weight
Project organization: as quality criterion between 10% and 15% weight
Interview #1: ChristerFröberg,KjellgrenKaminskyArchitectureAB
 Office manager and business developer at Kjellgren Kaminsky Architecture AB. Fröberg is
currently working with public procurement projects for Gothenburg´s municipality.
Projects they are involved in are mainly 600 housing units and planning.
Criteria such as sustainability, durability and quality give additional points. However, the price
owns the highest points ratio.
Interview #1: ChristerFröberg,KjellgrenKaminskyArchitectureAB
 Most common procurement route is the traditional method.
Architects must put a value of their creation, the creative process into "working hours“ for the
price criteria.
Usually the contracts by Gothenburg’s municipality are open, where they announce the
project and the companies apply for it, while they have a list of ranked companies, and they
choose according to the most economically feasible.
They also use lump sump contracts and guaranteed maximum price contracts.
Interview #2: JessicaDosenius,Trafikverket
Public procurement officer from Trafikverket. Dosenius is currently working with an IT system
procurement with a budgeted cost of 400 MSEK.
Trafikverket have different selection strategies for projects from different infrastructure
sectors. They use a prequalification system, TransQ.
The award criteria for Trafikverket’s projects is based on a category strategy. Price is only award
criteria for a standard performance contract.
Interview #2: JessicaDosenius,Trafikverket
Additional award criteria is applied in complex projects.
1. Collaboration
2. Risk
3. Environment
Additional criteria is usually regarding quality and environmental management (e.g. ISO 9001).
The use of traditional or design and build method depends on the project typology.
Usually the contracts are open, unless there should are specific requirements.
Conclusion
 Construction management is a procurement route in which the works are constructed by a
number of different trade contractors.
Governments and firms spend large amount of money on procurement. The traditional
approach specifies every dimension, and gives opportunity to choose the lowest price
contractor.
There is a high focus on price or more easily measured non-price criteria in municipal tender
evaluations. This, in turn, suggests a limited ability of municipal officials to evaluate consultant
competence, especially aspects related to design and execution of projects.
Moreover, a majority of the respondents reported that they use ‘personal’ information and
prequalification sources as basis for their procurement decisions.
References
1. Araújo, M. C. B., Alencar, L. H. & Miranda Mota, C. M., 2017. Project procurement management: A structured literature review. International Journal of Project
Management, Volume 35, pp. 353-377.
2. Lambropoulos, S., 2013. Objective Construction Contract Award using Cost, Time and Durability Utility. Procedia - Social and Behavioral Sciences, Volume 74, pp.
123-133.
3. Lundberg, S., Marklund, P.-O. & Strömbäck, E., 2016. Is Environmental Policy by Public Procurement Effective?. Public Finance Review, 44(4), pp. 478-499.
4. Morledge, R. & Smith, A., 2013. Building Procurement. 2 ed. Hoboken: John Wiley & Sons.
5. PETERSEN, D. Public procurement. TEK 140 construction contract releationships , 22nd November 2017 Chalmers University of Technology, Gothenburg.
6. POTTS, K. F., ANKRAH, N. & DAWSONERA 2013. Construction cost management: learning from case studies, Milton Park, Abingdon, Oxon, Routledge.
7. Sporrong, J., 2011. Criteria in consultant selection: public procurement of architectural and engineering services. Australasian Journal of Construction Economics
and Building, 11(4), pp. 59-76.
8. Sporrong, J. & Bröchner, J., 2009. Public Procurement Incentives for Sustainable Design Services: Swedish Experiences. Architectural Engineering and Design
Management, 5(1-2), pp. 24-35.
9. Varnäs, A., Balfors, B. & Faith-Ell, C., 2009. Environmental consideration in procurement of construction contracts: current practice, problems and opportunities in
green procurement in the Swedish construction industry. Journal of Cleaner Production, Volume 17, p. 1214–1222.
10. Waara, F., 2008. Mitigating contractual hazards in public procurement: a study of Swedish local authorities. Construction Management and Economics, 26(2), pp.
137-145.
11. WALKER, H. & BRAMMER, S. 2009. Sustainable procurement in the United Kingdom public sector. Supply Chain Management: An International Journal, 14, 128-
137.
Thank You !

More Related Content

Similar to Construction Contract Relationships Presentation.pptx

Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...
Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...
Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...ssusered96e2
 
Best value contracting
Best value contractingBest value contracting
Best value contractingahmed saeed
 
Project Procurement - Principles and Case Study
Project Procurement - Principles and Case StudyProject Procurement - Principles and Case Study
Project Procurement - Principles and Case StudyKiran Radhakrishnan
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 
Pp1 report
Pp1 reportPp1 report
Pp1 reportahmong4
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)OECD Governance
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Michael Audu
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
Ashworth 5e chapter 1 web ready
Ashworth 5e   chapter 1 web readyAshworth 5e   chapter 1 web ready
Ashworth 5e chapter 1 web readySumit Gupta
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentHaziq1511
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)tfkc1212
 
IRJET- Decision Making in Construction Management using AHP and Expert Ch...
IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...
IRJET- Decision Making in Construction Management using AHP and Expert Ch...IRJET Journal
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projectsijtsrd
 
IRJET- Android Application for Service by using Bidding and Ratings in nearby...
IRJET- Android Application for Service by using Bidding and Ratings in nearby...IRJET- Android Application for Service by using Bidding and Ratings in nearby...
IRJET- Android Application for Service by using Bidding and Ratings in nearby...IRJET Journal
 
Analysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
Analysis of Optimum Bid and Contractor’s Effort in Obtaining ProfitAnalysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
Analysis of Optimum Bid and Contractor’s Effort in Obtaining ProfitAI Publications
 

Similar to Construction Contract Relationships Presentation.pptx (20)

Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...
Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...
Cost Based Consultant Evaluation and Selection under FIDIC QCBS 1st Edt - Wit...
 
Best value contracting
Best value contractingBest value contracting
Best value contracting
 
Project Procurement - Principles and Case Study
Project Procurement - Principles and Case StudyProject Procurement - Principles and Case Study
Project Procurement - Principles and Case Study
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Pp report
Pp reportPp report
Pp report
 
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE) ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
ECI in Sweden - A. Kadefors, KTH Royal Institute of Technology, Stockholm (SE)
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Strategies in building procurement (summarized)
Strategies in building procurement (summarized)Strategies in building procurement (summarized)
Strategies in building procurement (summarized)
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Ashworth 5e chapter 1 web ready
Ashworth 5e   chapter 1 web readyAshworth 5e   chapter 1 web ready
Ashworth 5e chapter 1 web ready
 
Professional Practice 1 Group Assignment
Professional Practice 1 Group AssignmentProfessional Practice 1 Group Assignment
Professional Practice 1 Group Assignment
 
Procurement system
Procurement systemProcurement system
Procurement system
 
Pp1 final
Pp1 finalPp1 final
Pp1 final
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
 
IRJET- Decision Making in Construction Management using AHP and Expert Ch...
IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...IRJET-  	  Decision Making in Construction Management using AHP and Expert Ch...
IRJET- Decision Making in Construction Management using AHP and Expert Ch...
 
Factors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction ProjectsFactors Influencing Contractors Selection in Construction Projects
Factors Influencing Contractors Selection in Construction Projects
 
IRJET- Android Application for Service by using Bidding and Ratings in nearby...
IRJET- Android Application for Service by using Bidding and Ratings in nearby...IRJET- Android Application for Service by using Bidding and Ratings in nearby...
IRJET- Android Application for Service by using Bidding and Ratings in nearby...
 
Analysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
Analysis of Optimum Bid and Contractor’s Effort in Obtaining ProfitAnalysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
Analysis of Optimum Bid and Contractor’s Effort in Obtaining Profit
 

Recently uploaded

Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 

Recently uploaded (20)

Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 

Construction Contract Relationships Presentation.pptx

  • 1. Construction Contract Relationships Group Members: Hasan Alhashhoush Ismail Fakhro Mohamad Gheath Kreaker Naska Abbassi Laur Vatsfeld Public Procurement Award Criteria
  • 2. Procurement Routes Factors Affecting Selection of Procurement Route Procurement Phases and Procedure Awarding Criteria Selection Interviews Conclusion Content
  • 3.  What is Public procurement ?  The acquisition, whether under formal contract or not, of works, purchases and services by public organizations.  Ranges from the buying of goods or services to formal tendering and placing contracts for large infrastructural projects Public procurement is concerned with how public-sector organizations spend taxpayers money on goods and services. Introduction
  • 4. Procurement Routes There are three different methods of procurement routes The type of procurement route is selected by public client Selection of procurement route is based on many variables
  • 5. Procurement Routes: Traditional Method  Widely used for public procurement and can be described as step-by-step approach.  This method is relatively secure, especially when it comes to value for money.  On the other hand it can take relatively long time to accomplish the desired outcome. For instance, fixing any kind of flawed aspect of the project takes a lot of time, because usually there are different contractors for different parts of the developed project.
  • 6. Procurement Routes: Design and Build (DB) Can be single stage or two-stage. Relative speed and cost certainty.  less time consuming.  the contracting authority loses some degree of control over the design process as the design will be the responsibility of a contractor (design and build ).
  • 7. Procurement Routes: Managing Contracts  Relatively fast compared to the other two methods.  There is a lot of uncertainty for the client until the completion of the project.  Design developed by an architect employed by the client.
  • 8. Factors Affecting Selection of Procurement Route • Client resources: client’s knowledge and experience. • Project characteristics: size, complexity and location of the project. • Ability to make changes at various stages. • Risk management. • Cost issues • Timing
  • 9. Procurement Phases The procurement process has two main phases that are dependent on the procurement route: 1- The supplier selection (the choice of adequate suppliers). 2-The supplier evaluation (assessment of performance).
  • 10. Allowable Procedure for Public Procurement  Open procedures : all interested parties can participate in the tendering process.  Restricted procedures : only selected contractors may submit tenders.  Negotiated procedures : clients consult with the contractors before making the decision which one to select.  Competitive dialogue : more complicated procedure used when contracting authorities find that it is not possible to achieve the desired goals with one of the aforementioned procedures.
  • 11. Awarding Criteria Selection  Historically the performance assessment of construction contractors has based on the lowest price criteria, as it is an objective and transparent approach.  Researches have shown that there can be many hidden risks behind the so called ‘cheapest tender’: 1. Does not ensure lowest overall project cost (cost overruns). 2. Can result in high costs during the building life cycle. 3. Lowest price may not provide quality or satisfaction among clients.
  • 12. Awarding Criteria Selection  More complex award systems with different non- price criteria also known as scoring-based competitive tendering have been developed .  Research results in Sweden show that local authorities prefer price or easily measured non-price criteria.  The same research states that project-specific selection criteria include (listed from more to less popular) : Tender price Individual experience of key project personnel Personality related criteria of key project personnel Technical aspects of design Innovative/creative solutions Project execution/action plan Aesthetic aspects of design and life-cycle costs Less Popular
  • 13. Awarding Criteria Selection  This list confirms that even though there are quality requirements in supplier selection, in most cases public clients want to reassure that those requirements are met.  Another important aspect that needs to be kept in mind when using scoring-based tendering: “If multiple criteria are to be used, there are rules to safeguard that they are applied transparently”. Research in Sweden shows that For public projects : Tender price: up to 70% weight Project organization: as quality criterion between 10% and 15% weight
  • 14. Interview #1: ChristerFröberg,KjellgrenKaminskyArchitectureAB  Office manager and business developer at Kjellgren Kaminsky Architecture AB. Fröberg is currently working with public procurement projects for Gothenburg´s municipality. Projects they are involved in are mainly 600 housing units and planning. Criteria such as sustainability, durability and quality give additional points. However, the price owns the highest points ratio.
  • 15. Interview #1: ChristerFröberg,KjellgrenKaminskyArchitectureAB  Most common procurement route is the traditional method. Architects must put a value of their creation, the creative process into "working hours“ for the price criteria. Usually the contracts by Gothenburg’s municipality are open, where they announce the project and the companies apply for it, while they have a list of ranked companies, and they choose according to the most economically feasible. They also use lump sump contracts and guaranteed maximum price contracts.
  • 16. Interview #2: JessicaDosenius,Trafikverket Public procurement officer from Trafikverket. Dosenius is currently working with an IT system procurement with a budgeted cost of 400 MSEK. Trafikverket have different selection strategies for projects from different infrastructure sectors. They use a prequalification system, TransQ. The award criteria for Trafikverket’s projects is based on a category strategy. Price is only award criteria for a standard performance contract.
  • 17. Interview #2: JessicaDosenius,Trafikverket Additional award criteria is applied in complex projects. 1. Collaboration 2. Risk 3. Environment Additional criteria is usually regarding quality and environmental management (e.g. ISO 9001). The use of traditional or design and build method depends on the project typology. Usually the contracts are open, unless there should are specific requirements.
  • 18. Conclusion  Construction management is a procurement route in which the works are constructed by a number of different trade contractors. Governments and firms spend large amount of money on procurement. The traditional approach specifies every dimension, and gives opportunity to choose the lowest price contractor. There is a high focus on price or more easily measured non-price criteria in municipal tender evaluations. This, in turn, suggests a limited ability of municipal officials to evaluate consultant competence, especially aspects related to design and execution of projects. Moreover, a majority of the respondents reported that they use ‘personal’ information and prequalification sources as basis for their procurement decisions.
  • 19. References 1. Araújo, M. C. B., Alencar, L. H. & Miranda Mota, C. M., 2017. Project procurement management: A structured literature review. International Journal of Project Management, Volume 35, pp. 353-377. 2. Lambropoulos, S., 2013. Objective Construction Contract Award using Cost, Time and Durability Utility. Procedia - Social and Behavioral Sciences, Volume 74, pp. 123-133. 3. Lundberg, S., Marklund, P.-O. & Strömbäck, E., 2016. Is Environmental Policy by Public Procurement Effective?. Public Finance Review, 44(4), pp. 478-499. 4. Morledge, R. & Smith, A., 2013. Building Procurement. 2 ed. Hoboken: John Wiley & Sons. 5. PETERSEN, D. Public procurement. TEK 140 construction contract releationships , 22nd November 2017 Chalmers University of Technology, Gothenburg. 6. POTTS, K. F., ANKRAH, N. & DAWSONERA 2013. Construction cost management: learning from case studies, Milton Park, Abingdon, Oxon, Routledge. 7. Sporrong, J., 2011. Criteria in consultant selection: public procurement of architectural and engineering services. Australasian Journal of Construction Economics and Building, 11(4), pp. 59-76. 8. Sporrong, J. & Bröchner, J., 2009. Public Procurement Incentives for Sustainable Design Services: Swedish Experiences. Architectural Engineering and Design Management, 5(1-2), pp. 24-35. 9. Varnäs, A., Balfors, B. & Faith-Ell, C., 2009. Environmental consideration in procurement of construction contracts: current practice, problems and opportunities in green procurement in the Swedish construction industry. Journal of Cleaner Production, Volume 17, p. 1214–1222. 10. Waara, F., 2008. Mitigating contractual hazards in public procurement: a study of Swedish local authorities. Construction Management and Economics, 26(2), pp. 137-145. 11. WALKER, H. & BRAMMER, S. 2009. Sustainable procurement in the United Kingdom public sector. Supply Chain Management: An International Journal, 14, 128- 137.