Procurement Strategy for Manufacturing and JIT
D. K. Singh1
and Dr. Satyendra Singh2
1
Associate Professor, 2
Associate Professor
1
Division of MPA Engineering, Netaji Subhas Institute of Technology, New Delhi – 110078.
2
Deptt. of Mechanical Engg, B. T. Kumaon Institute of Technology, Dwarahat-263653 (Almora).
Abstract: - Procurement involves the purchase of goods and services from the suppliers for the manufacturing
units. Procuring the items in the most optimized way is very much desired to implement JIT effectively.
Manufacturer-supplier relationship is very crucial for effective procurement policy. The present paper deals with
various procurement strategies of manufacturing that include the optimization of manufacturing quantity along
with the procurement of multiple input items. The procurement cycles for input items are considered in small lot
sizes, which are essential for the effective implementation of JIT. The method of integer programming has been
used to find the optimum integer values of number of orders for procuring the input items, which is usually
found to be in fraction for a real manufacturing environment.
Keywords: - JIT, Lot size, Procurement, Supply chain management.
Notations used
Ai = Fixed ordering cost for input item i
C = Fixed set-up cost for end item
di = Replenishment rate of input item i, units/period
E = Total relevant cost considering end product and input item together
F = Annual holding cost fraction
Gi = Unit purchase cost for input item i
ki = No. of orders for procurement of input item i in a production cycle
m = No. of input items required
ni = Units of input item i required for unit end item
p = Production rate (including defective units), units/period
P = Unit production cost (including value addition)
Q = Production lot size (including defective items)
r = Demand rate for end item, units/period
R = Annual demand for end item
V = Maximum inventory level (excluding defective end items)
y = Proportion of non-defective end items in a lot
I. INTRODUCTION
Inventory management is a key management issue for the plants. It is of strategic importance rather
than a mere buying function performed at lower levels of the organization, as has been the case in the past. Just
in time (JIT) has been used as one of the most effective methods to control the level of inventory in the recent
past, and is used even today most competitively and aggressively. It smoothens the flow of materials to arrive
just at the time of their requirements. Deliveries are made directly to the factory floor, thus eliminating the scope
of storage, inspection and transportation. JIT is dependent upon both the excellence of the internal
manufacturing capabilities, and the development and management of strategic relationships with suppliers. The
success of JIT is attributed to the close manufacturer-supplier relationship as a part of procurement strategy [1].
The strong manufacturer-supplier relationship makes a production system more dependable and eliminates any
uncertainty regarding manufacturing schedule [2], and hence makes procurement easy for JIT to work more
effectively. In case of late deliveries from the supplier, a company will be forced to keep large, costly
inventories to keep their own products from being late to their customers [3]. Easy procurement and smooth
flow of materials is directly linked to effective supply chain management. Whom to buy materials from, how to
transport goods and services, and how to distribute them in the cost-effective, timely manner contributes to
much of an organization’s strategic planning. Choosing a wrong supplier and a trust deficit in the supplier-
manufacturer relationship can result in poor quality and late deliveries, which are detrimental in the interest of
an organization. To make an efficient supply chain network, members of the supply chain are required to
collaborate and work together, that is, a synergy is required between them, which in turn, greatly depends on the
Procurement Strategy for Manufacturing and JIT
11
integration of the components of the information system [4]. A supply chain network can fail in the absence of
effective information system.
The complete elimination of inventories is very appealing, but it is not always feasible due to economic
considerations. It is shown, although in case of complex assemblies, that lot-for-lot production in small batches
may not be the best JIT strategy [5]. Significance of lot sizing will always be there whether JIT or traditional
approach is applied for managing production-inventory system. Small lot sizes are useful in the implementation
of JIT, as they tend to fulfill quick customer requirements. Easy and fast consumption of items in small lot size
accelerate the pace of JIT and further procurement becomes more frequent.
The basic EOQ model is a mathematical formulation to find the optimal order size that minimizes the
sum of carrying costs and ordering costs. It is modified by incorporating different complexities [6]. A lot size
model is developed for procurement of any input item in one or more lots during the production cycle [7]. But
replenishment rate of the input item is considered to be infinite. The model is extended in the present paper to
incorporate finite replenishment rate for input items and quality defects in a production system. Further a
methodology is proposed in order to overcome computational difficulties for evaluation of procurement cycles.
II. MODEL FORMULATION
The model formulation for the procurement policy is based on the following assumptions:
 During the production of a batch of end item, 100% inspection is carried out and rejected items are not
added to end item inventory.
 Smaller lot sizes of input items are replenished at the finite rate.
 No price discount is considered on procured input items.
 Replenishment rates of input items are greater than the rate of consumption of these items.
Consider Fig.1, which shows the production-inventory cycles for end items and input items shown together.
Annual inventory holding cost for end items = (V/2) PF
= (yp-r) PFQ/2p [Since, V= (yp-r) Q/p] (1)
The total annual cost for end product consists of set-up cost and holding cost, that is,
(TC)e = RC / yQ + (yp-r) PFQ/2p (2)
If Q is the production lot size, niQ/ki is the procurement lot size for input item i. Since input items inventory
exists for a fraction of cycle time, which is (Q/p) / (yQ/r), that is, r/yp.
Annual inventory carrying costs for input items
m
=  (di –pni) ni r Gi F Q / (2ki di y p) (3)
i=1
The total annual cost for all the input items comprising of costs of carrying and ordering is expressed as
m m
(TC)i =  (R ki / y Q) Ai +  [(di-pni) ni r Gi FQ / (2ki di y p)] (4)
i=1 i=1
Procurement Strategy for Manufacturing and JIT
12
Equating partial derivative of equation (7) with respect to each ki to zero gives
Procurement Strategy for Manufacturing and JIT
13
Equation (8) can be used to find the optimal solutions of ki, where i =1, 2, 3… m, as number of equations are
equal to number of variables. But due to structure of equations, computational difficulties arise, which further
increase as more number of input materials/components is used in real environment. Following methodology is
proposed to overcome the problem. Let
and
From equation (10), values of k1, k2… km can be found in terms of X. Solving these equations, we can obtain k2,
k3, … km in terms of k1, and from equation (9), X is evaluated in terms of k1 only. Value of X, thus, obtained is
substituted in equation (10) in order to get a simple quadratic equation in terms of k1. Optimal value of k1 is
computed, and eventually optimal values of ki for i = 1, 2, 3… m can be obtained easily. However, these values
of ki are most probably in the decimal form. To find out the integer optimum values of ki, method of integer
programming may be adopted.
Analytical Data
We consider the values of various parameters, which are near to practical values. Taking
R = 1200, y = 0.9, C = Rs. 200, F = 0.3, p =120, r =105, P = Rs. 300, and m = 4, the values of Ai, di, Gi and ni
are obtained, and are given in Table 1.
Table 1: Data for input items
Now from equation (10), we have
Substituting values of parameters from Table 1, we get
k1 = 0.3873 X (11)
Similarly,
k2 = 0.3464 X (12)
k3 = 0.3162 X (13)
Procurement Strategy for Manufacturing and JIT
14
and k4 = 0.5345 X (14)
Dividing equations (12), (13) and (14) each by equation (11), we get
k2 = 0.8944 k1 (15)
k3 = 0.8164 k1 (16)
and k4 = 1.38 k1 (17)
Using equation (9), we have
Substituting the values of k2, k3 and k4 from equations (15), (16) and (17), we get
Using equation (11), we have
Or 900 k1
2
+ 1.3478 k1 - 3499.2301 = 0
Which gives k1 = 1.971
From equations (15), (16) and (17), we have
k2 = 1.763
k3 = 1.609
and k4 = 2.72
Using equation (7), we get E = Rs. 3190.78.
To find out the optimum integer number of orders for procurement of input items, proposed heuristic algorithm
[7], which is stated to be more efficient than branch and bound method, is used.
Fig. 2 represents the procedure starting from node I, which is the non-integer solution obtained before.
Since, the value of k1 is 1.971, nearest integers surrounding it are 1 and 2. Node II and Node III represent the
solutions corresponding to k1=2 and 1, respectively. As the value of E with Node II is lesser in comparison to
Node III, Node II is considered for further branching with surrounding integer values of k2. Nodes IV and VII
are chosen in a similar way for emanating the branches. Node VIII represents the integer optimum with cost, E =
Rs. 3198.70. Optimum production lot size, Q can also be obtained using equation (6) by putting values of ki, and
it is found to be 525.21.
Procurement Strategy for Manufacturing and JIT
15
III. DISCUSSION OF RESULTS
(a) Effect of decrease in ordering cost on total annual cost
Fig. 3 shows the effect of decrease in ordering cost for input items on total annual cost. For the data
taken, average ordering cost is decreased by a certain percentage uniformly for each input item, that is, for i = 1
to 4. We find that with up to 30% decrease in average ordering cost, the percentage decrease in total annual cost
is of the order of 11%. In the uncertain economic environment, cost of capital and thus the inventory carrying
cost fraction F varies. The computation is made for various values of F, that is, 0.2, 0.25 and 0.35. Fig. 3 is the
representative of these calculations because the relative decrease in E is similar. This is also evident from
equation (7) as the absolute values of E only differ and percentage decrease in E at various values of F due to
similar percentage decrease in ordering cost may be similar. Values of ki are independent of F and these are
found to be increasing with decreasing Ai, which is obvious.
Procurement Strategy for Manufacturing and JIT
16
(b) Effect of decrease in set-up cost on total annual cost
Fig. 4 shows the effect of decrease in set-up cost for end item on total annual cost. For the data taken,
fixed set-up cost (C) for end item is decreased. We find about 6% decrease in total annual cost for 30% decrease
in set-up cost.
(c) Effect of decrease in non-defective end item on total annual cost
Fig. 5 shows the effect of decrease in proportion of non-defective end items (y) in a lot on total annual
cost. For the data taken, the total annual cost increases with decrease in y. We find the increase of about 5% and
11% in total annual cost corresponding to a respective decrease of about 5% and 10% in the value of y. The
theoretical value of y should be 1. But in many real manufacturing environments, it is not feasible. The
development of a new product is a challenging task as far as its quality control is concerned. It contains many
untried elements that cause unexpected problems [8].
Procurement Strategy for Manufacturing and JIT
17
Failure cost increases with the development of product. However, as long as the increase in sales
revenue exceeds the increase in cost, it is allowed from managerial, profit-oriented point of view. In yet another
case, a company may decide to use an old facility also to take benefit of increase in demand. In spite of old
facility generating more number of defective items, profits may be earned. It is of interest to determine ordering
policy with respect to quality defects. To conduct the sensitivity analysis with respect to quality level,
production cost as well as purchase cost of input items should also be included, since they increase with the
increase in quality defects. Since P is unit production cost including value addition, [(R/y)P] represents annual
production and purchase cost and it is added in corresponding total cost E obtained earlier from equation (7).
The sensitivity analysis is useful in deciding whether to allow more proportion of quality defects in specific
situations.
IV. CONCLUSIONS
The procurement model manifests the procurement policy of lot sizing, and includes some realistic
manufacturing conditions like finite replenishment rate of input items and quality defects in a production
system. Quality and JIT has to work together for better procurement policy, which drastically cuts the level of
work-in-process inventory. The TQM is an integral feature for JIT to be successful in manufacturing plants.
Simultaneously, optimum number of cycles for the procurement of input items has been derived to obtain the
initial solution, and its integer optimum values have also been obtained using method of integer programming.
REFERENCES
[1]. Brown, Steve; Manufacturing the Future, Pearson Education, London, 2000.
[2]. Singh, D.K. and Singh Satyendra; “JIT: Various Aspects of its Implementation”, International Journal
of Modern Engineering Research, Vol.3, Issue 3, May-June 2013, pp. 1582-1586.
[3]. Russell, Roberta S and Taylor III Bernard W; Operations Management, Wiley India (P) Ltd; New
Delhi, 2007.
[4]. Singh, D.K; “JIT Implementation in Strategic Business Environment through Information
Technology”, Industrial Engineering Journal, Vol.36, No.07, July 2007, pp.17-20.
[5]. Anwar, M.F. and Negi, R; “Integrated Lot-sizing and Scheduling for Just-in-Time Production of
Complex Assemblies with Finite Set-ups”, International Journal of Production Research, Vol.35 No.5,
1997, pp. 1447-1470.
[6]. Tersine, R.J. et al; “A composite EOQ Model for Situational Decomposition”, Computers and
Industrial Engineering, Vol. 22 No.3, 1992, pp.283-295.
[7]. Banerjee, A. et al; “Input/output Lot Sizing in Single Stage Batch Production Systems under
Constant Demand”, Computers and Industrial Engineering, Vol.19, No. 1- 4, 1990, pp.37-41.
[8]. Kume, H; “Business Management and Quality Cost: The Japanese View”, Quality Progress, May 1985,
pp.13-18.

More Related Content

What's hot

An Inventory Model with Variable Demand Rate for Deteriorating Items under Pe...
An Inventory Model with Variable Demand Rate for Deteriorating Items under Pe...An Inventory Model with Variable Demand Rate for Deteriorating Items under Pe...
An Inventory Model with Variable Demand Rate for Deteriorating Items under Pe...Editor IJCATR
 
Production analysis me
Production analysis  meProduction analysis  me
Production analysis mepushpa latha
 
| Managerial Accounting | Chapter 1 | An Overview to Managerial Accounting | ...
| Managerial Accounting | Chapter 1 | An Overview to Managerial Accounting | ...| Managerial Accounting | Chapter 1 | An Overview to Managerial Accounting | ...
| Managerial Accounting | Chapter 1 | An Overview to Managerial Accounting | ...Ahmad Hassan
 
Production and cost (economics presentation)
Production and cost (economics presentation)Production and cost (economics presentation)
Production and cost (economics presentation)AliAkberMehedi
 
Theory of production by Raj Naik
Theory of production by Raj NaikTheory of production by Raj Naik
Theory of production by Raj NaikRaj Naik
 
A production - Inventory model with JIT setup cost incorporating inflation an...
A production - Inventory model with JIT setup cost incorporating inflation an...A production - Inventory model with JIT setup cost incorporating inflation an...
A production - Inventory model with JIT setup cost incorporating inflation an...IJMER
 
The (R, Q) Control of A Mixture Inventory Model with Backorders and Lost Sale...
The (R, Q) Control of A Mixture Inventory Model with Backorders and Lost Sale...The (R, Q) Control of A Mixture Inventory Model with Backorders and Lost Sale...
The (R, Q) Control of A Mixture Inventory Model with Backorders and Lost Sale...irjes
 
Product costing system
Product costing systemProduct costing system
Product costing systemMah Noor
 
Process cost systems
Process cost systemsProcess cost systems
Process cost systemsKhalid Aziz
 

What's hot (17)

Multi item inventory model include lead time with demand dependent productio...
 Multi item inventory model include lead time with demand dependent productio... Multi item inventory model include lead time with demand dependent productio...
Multi item inventory model include lead time with demand dependent productio...
 
Production and cost
Production and costProduction and cost
Production and cost
 
Process costing
Process costingProcess costing
Process costing
 
An Inventory Model with Variable Demand Rate for Deteriorating Items under Pe...
An Inventory Model with Variable Demand Rate for Deteriorating Items under Pe...An Inventory Model with Variable Demand Rate for Deteriorating Items under Pe...
An Inventory Model with Variable Demand Rate for Deteriorating Items under Pe...
 
Production analysis me
Production analysis  meProduction analysis  me
Production analysis me
 
| Managerial Accounting | Chapter 1 | An Overview to Managerial Accounting | ...
| Managerial Accounting | Chapter 1 | An Overview to Managerial Accounting | ...| Managerial Accounting | Chapter 1 | An Overview to Managerial Accounting | ...
| Managerial Accounting | Chapter 1 | An Overview to Managerial Accounting | ...
 
Production and cost (economics presentation)
Production and cost (economics presentation)Production and cost (economics presentation)
Production and cost (economics presentation)
 
Production and Cost
Production and CostProduction and Cost
Production and Cost
 
Theory of production by Raj Naik
Theory of production by Raj NaikTheory of production by Raj Naik
Theory of production by Raj Naik
 
Product costing
Product costingProduct costing
Product costing
 
Methods of costing
Methods of costingMethods of costing
Methods of costing
 
A production - Inventory model with JIT setup cost incorporating inflation an...
A production - Inventory model with JIT setup cost incorporating inflation an...A production - Inventory model with JIT setup cost incorporating inflation an...
A production - Inventory model with JIT setup cost incorporating inflation an...
 
The (R, Q) Control of A Mixture Inventory Model with Backorders and Lost Sale...
The (R, Q) Control of A Mixture Inventory Model with Backorders and Lost Sale...The (R, Q) Control of A Mixture Inventory Model with Backorders and Lost Sale...
The (R, Q) Control of A Mixture Inventory Model with Backorders and Lost Sale...
 
Product costing system
Product costing systemProduct costing system
Product costing system
 
Theoryofproduction
TheoryofproductionTheoryofproduction
Theoryofproduction
 
Process cost systems
Process cost systemsProcess cost systems
Process cost systems
 
Production
ProductionProduction
Production
 

Viewers also liked

The Benefits of an Active Procurement Strategy
The Benefits of an Active Procurement StrategyThe Benefits of an Active Procurement Strategy
The Benefits of an Active Procurement StrategyVendorMS
 
Impact of JIT Inventory on procurement function in Perspective of Toyota Moto...
Impact of JIT Inventory on procurement function in Perspective of Toyota Moto...Impact of JIT Inventory on procurement function in Perspective of Toyota Moto...
Impact of JIT Inventory on procurement function in Perspective of Toyota Moto...Enamul Khan
 
Procurement Strategy by Derek Hendrikz
Procurement Strategy by Derek HendrikzProcurement Strategy by Derek Hendrikz
Procurement Strategy by Derek HendrikzDerek Hendrikz
 
Procurement Processes in Automotive Manufacturing
Procurement Processes in Automotive ManufacturingProcurement Processes in Automotive Manufacturing
Procurement Processes in Automotive ManufacturingKevin Harmon-Smith
 
Production Management
Production ManagementProduction Management
Production ManagementUmar Khan
 
JIT, Kanban, Kaizen, Muda in TPS (Toyota Production System)
JIT, Kanban, Kaizen, Muda in TPS (Toyota Production System)JIT, Kanban, Kaizen, Muda in TPS (Toyota Production System)
JIT, Kanban, Kaizen, Muda in TPS (Toyota Production System)Abdul Qadir Master
 
Procurement management - Supply chain training
Procurement management - Supply chain trainingProcurement management - Supply chain training
Procurement management - Supply chain trainingUmar Khan
 
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...Optimus BT
 
Basics Of Procurement Process
Basics Of Procurement ProcessBasics Of Procurement Process
Basics Of Procurement ProcessRameswara Vedula
 
10 Ways To Improve Your Purchasing Department
10 Ways To Improve Your Purchasing Department10 Ways To Improve Your Purchasing Department
10 Ways To Improve Your Purchasing DepartmentKeith Taylor
 
Buyer supplier relationship
Buyer supplier relationshipBuyer supplier relationship
Buyer supplier relationshipAnkit
 

Viewers also liked (14)

The Benefits of an Active Procurement Strategy
The Benefits of an Active Procurement StrategyThe Benefits of an Active Procurement Strategy
The Benefits of an Active Procurement Strategy
 
Impact of JIT Inventory on procurement function in Perspective of Toyota Moto...
Impact of JIT Inventory on procurement function in Perspective of Toyota Moto...Impact of JIT Inventory on procurement function in Perspective of Toyota Moto...
Impact of JIT Inventory on procurement function in Perspective of Toyota Moto...
 
Procurement Strategy by Derek Hendrikz
Procurement Strategy by Derek HendrikzProcurement Strategy by Derek Hendrikz
Procurement Strategy by Derek Hendrikz
 
Procurement Processes in Automotive Manufacturing
Procurement Processes in Automotive ManufacturingProcurement Processes in Automotive Manufacturing
Procurement Processes in Automotive Manufacturing
 
Production Management
Production ManagementProduction Management
Production Management
 
JIT, Kanban, Kaizen, Muda in TPS (Toyota Production System)
JIT, Kanban, Kaizen, Muda in TPS (Toyota Production System)JIT, Kanban, Kaizen, Muda in TPS (Toyota Production System)
JIT, Kanban, Kaizen, Muda in TPS (Toyota Production System)
 
Procurement management - Supply chain training
Procurement management - Supply chain trainingProcurement management - Supply chain training
Procurement management - Supply chain training
 
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
Purchasing, Procurement, Vendor, Contract and RFP Process Management with Sha...
 
Basics Of Procurement Process
Basics Of Procurement ProcessBasics Of Procurement Process
Basics Of Procurement Process
 
Just In Time (JIT) Systems
Just In Time (JIT) SystemsJust In Time (JIT) Systems
Just In Time (JIT) Systems
 
10 Ways To Improve Your Purchasing Department
10 Ways To Improve Your Purchasing Department10 Ways To Improve Your Purchasing Department
10 Ways To Improve Your Purchasing Department
 
Procurement Plan
Procurement PlanProcurement Plan
Procurement Plan
 
Buyer supplier relationship
Buyer supplier relationshipBuyer supplier relationship
Buyer supplier relationship
 
Procurement: Strategies | Best Practices
Procurement: Strategies | Best PracticesProcurement: Strategies | Best Practices
Procurement: Strategies | Best Practices
 

Similar to Procurement Strategy for Manufacturing and JIT

Optimization by heuristic procedure of scheduling constraints in manufacturin...
Optimization by heuristic procedure of scheduling constraints in manufacturin...Optimization by heuristic procedure of scheduling constraints in manufacturin...
Optimization by heuristic procedure of scheduling constraints in manufacturin...Alexander Decker
 
11.optimization by heuristic procedure of scheduling constraints in manufactu...
11.optimization by heuristic procedure of scheduling constraints in manufactu...11.optimization by heuristic procedure of scheduling constraints in manufactu...
11.optimization by heuristic procedure of scheduling constraints in manufactu...Alexander Decker
 
DECISIONS IN A SUPPLY CHAIN MODELING FOR COMPARATIVE EVALUATION STRATEGIES IN...
DECISIONS IN A SUPPLY CHAIN MODELING FOR COMPARATIVE EVALUATION STRATEGIES IN...DECISIONS IN A SUPPLY CHAIN MODELING FOR COMPARATIVE EVALUATION STRATEGIES IN...
DECISIONS IN A SUPPLY CHAIN MODELING FOR COMPARATIVE EVALUATION STRATEGIES IN...IAEME Publication
 
Decisions in a supply chain modeling for comparative evaluation strategies in...
Decisions in a supply chain modeling for comparative evaluation strategies in...Decisions in a supply chain modeling for comparative evaluation strategies in...
Decisions in a supply chain modeling for comparative evaluation strategies in...IAEME Publication
 
STRATEGIES OF DELAY DELIVERY AND CONTROLLABLE LEAD TIME IN SUPPLY CHAIN CONSI...
STRATEGIES OF DELAY DELIVERY AND CONTROLLABLE LEAD TIME IN SUPPLY CHAIN CONSI...STRATEGIES OF DELAY DELIVERY AND CONTROLLABLE LEAD TIME IN SUPPLY CHAIN CONSI...
STRATEGIES OF DELAY DELIVERY AND CONTROLLABLE LEAD TIME IN SUPPLY CHAIN CONSI...IAEME Publication
 
Which of the following basic types of production layout
Which of the following basic types of production layoutWhich of the following basic types of production layout
Which of the following basic types of production layoutjohann11372
 
Which of the following approaches to service design
Which of the following approaches to service designWhich of the following approaches to service design
Which of the following approaches to service designjohann11372
 
Which of the following is a focusing step
Which of the following is a focusing stepWhich of the following is a focusing step
Which of the following is a focusing stepjohann11373
 
1. Which of the following is INCORRECT regarding the process capab.docx
1. Which of the following is INCORRECT regarding the process capab.docx1. Which of the following is INCORRECT regarding the process capab.docx
1. Which of the following is INCORRECT regarding the process capab.docxjackiewalcutt
 
Getting an autograph from a famous person might involve standing in which typ...
Getting an autograph from a famous person might involve standing in which typ...Getting an autograph from a famous person might involve standing in which typ...
Getting an autograph from a famous person might involve standing in which typ...johann11371
 
inventory-management
inventory-managementinventory-management
inventory-managementrajesh.pal45
 
Which of the following is a measure of operations and supply management effic...
Which of the following is a measure of operations and supply management effic...Which of the following is a measure of operations and supply management effic...
Which of the following is a measure of operations and supply management effic...johann11379
 
Chapter10-Inventorymanagement.ppt
Chapter10-Inventorymanagement.pptChapter10-Inventorymanagement.ppt
Chapter10-Inventorymanagement.pptMichael Celis
 
Which of the following is not a problem definition tool
Which of the following is not a problem definition toolWhich of the following is not a problem definition tool
Which of the following is not a problem definition tooljohann11374
 
Application of dynamic programming model to production planning, in an animal...
Application of dynamic programming model to production planning, in an animal...Application of dynamic programming model to production planning, in an animal...
Application of dynamic programming model to production planning, in an animal...Alexander Decker
 
In hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chainsIn hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chainsjohann11371
 
In designing a lean production facility layout
In designing a lean production facility layoutIn designing a lean production facility layout
In designing a lean production facility layoutjohann11371
 
Economic justification of npd project and financial tools
Economic justification of npd project and financial toolsEconomic justification of npd project and financial tools
Economic justification of npd project and financial toolsOmid Aminzadeh Gohari
 

Similar to Procurement Strategy for Manufacturing and JIT (20)

Optimization by heuristic procedure of scheduling constraints in manufacturin...
Optimization by heuristic procedure of scheduling constraints in manufacturin...Optimization by heuristic procedure of scheduling constraints in manufacturin...
Optimization by heuristic procedure of scheduling constraints in manufacturin...
 
11.optimization by heuristic procedure of scheduling constraints in manufactu...
11.optimization by heuristic procedure of scheduling constraints in manufactu...11.optimization by heuristic procedure of scheduling constraints in manufactu...
11.optimization by heuristic procedure of scheduling constraints in manufactu...
 
DECISIONS IN A SUPPLY CHAIN MODELING FOR COMPARATIVE EVALUATION STRATEGIES IN...
DECISIONS IN A SUPPLY CHAIN MODELING FOR COMPARATIVE EVALUATION STRATEGIES IN...DECISIONS IN A SUPPLY CHAIN MODELING FOR COMPARATIVE EVALUATION STRATEGIES IN...
DECISIONS IN A SUPPLY CHAIN MODELING FOR COMPARATIVE EVALUATION STRATEGIES IN...
 
Decisions in a supply chain modeling for comparative evaluation strategies in...
Decisions in a supply chain modeling for comparative evaluation strategies in...Decisions in a supply chain modeling for comparative evaluation strategies in...
Decisions in a supply chain modeling for comparative evaluation strategies in...
 
Inventory 1.1
Inventory 1.1Inventory 1.1
Inventory 1.1
 
Ch14. inventory management
Ch14. inventory managementCh14. inventory management
Ch14. inventory management
 
STRATEGIES OF DELAY DELIVERY AND CONTROLLABLE LEAD TIME IN SUPPLY CHAIN CONSI...
STRATEGIES OF DELAY DELIVERY AND CONTROLLABLE LEAD TIME IN SUPPLY CHAIN CONSI...STRATEGIES OF DELAY DELIVERY AND CONTROLLABLE LEAD TIME IN SUPPLY CHAIN CONSI...
STRATEGIES OF DELAY DELIVERY AND CONTROLLABLE LEAD TIME IN SUPPLY CHAIN CONSI...
 
Which of the following basic types of production layout
Which of the following basic types of production layoutWhich of the following basic types of production layout
Which of the following basic types of production layout
 
Which of the following approaches to service design
Which of the following approaches to service designWhich of the following approaches to service design
Which of the following approaches to service design
 
Which of the following is a focusing step
Which of the following is a focusing stepWhich of the following is a focusing step
Which of the following is a focusing step
 
1. Which of the following is INCORRECT regarding the process capab.docx
1. Which of the following is INCORRECT regarding the process capab.docx1. Which of the following is INCORRECT regarding the process capab.docx
1. Which of the following is INCORRECT regarding the process capab.docx
 
Getting an autograph from a famous person might involve standing in which typ...
Getting an autograph from a famous person might involve standing in which typ...Getting an autograph from a famous person might involve standing in which typ...
Getting an autograph from a famous person might involve standing in which typ...
 
inventory-management
inventory-managementinventory-management
inventory-management
 
Which of the following is a measure of operations and supply management effic...
Which of the following is a measure of operations and supply management effic...Which of the following is a measure of operations and supply management effic...
Which of the following is a measure of operations and supply management effic...
 
Chapter10-Inventorymanagement.ppt
Chapter10-Inventorymanagement.pptChapter10-Inventorymanagement.ppt
Chapter10-Inventorymanagement.ppt
 
Which of the following is not a problem definition tool
Which of the following is not a problem definition toolWhich of the following is not a problem definition tool
Which of the following is not a problem definition tool
 
Application of dynamic programming model to production planning, in an animal...
Application of dynamic programming model to production planning, in an animal...Application of dynamic programming model to production planning, in an animal...
Application of dynamic programming model to production planning, in an animal...
 
In hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chainsIn hau lee's uncertainty framework to classify supply chains
In hau lee's uncertainty framework to classify supply chains
 
In designing a lean production facility layout
In designing a lean production facility layoutIn designing a lean production facility layout
In designing a lean production facility layout
 
Economic justification of npd project and financial tools
Economic justification of npd project and financial toolsEconomic justification of npd project and financial tools
Economic justification of npd project and financial tools
 

More from IJERD Editor

A Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
A Novel Method for Prevention of Bandwidth Distributed Denial of Service AttacksA Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
A Novel Method for Prevention of Bandwidth Distributed Denial of Service AttacksIJERD Editor
 
MEMS MICROPHONE INTERFACE
MEMS MICROPHONE INTERFACEMEMS MICROPHONE INTERFACE
MEMS MICROPHONE INTERFACEIJERD Editor
 
Influence of tensile behaviour of slab on the structural Behaviour of shear c...
Influence of tensile behaviour of slab on the structural Behaviour of shear c...Influence of tensile behaviour of slab on the structural Behaviour of shear c...
Influence of tensile behaviour of slab on the structural Behaviour of shear c...IJERD Editor
 
Gold prospecting using Remote Sensing ‘A case study of Sudan’
Gold prospecting using Remote Sensing ‘A case study of Sudan’Gold prospecting using Remote Sensing ‘A case study of Sudan’
Gold prospecting using Remote Sensing ‘A case study of Sudan’IJERD Editor
 
Reducing Corrosion Rate by Welding Design
Reducing Corrosion Rate by Welding DesignReducing Corrosion Rate by Welding Design
Reducing Corrosion Rate by Welding DesignIJERD Editor
 
Router 1X3 – RTL Design and Verification
Router 1X3 – RTL Design and VerificationRouter 1X3 – RTL Design and Verification
Router 1X3 – RTL Design and VerificationIJERD Editor
 
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...IJERD Editor
 
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVR
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVRMitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVR
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVRIJERD Editor
 
Study on the Fused Deposition Modelling In Additive Manufacturing
Study on the Fused Deposition Modelling In Additive ManufacturingStudy on the Fused Deposition Modelling In Additive Manufacturing
Study on the Fused Deposition Modelling In Additive ManufacturingIJERD Editor
 
Spyware triggering system by particular string value
Spyware triggering system by particular string valueSpyware triggering system by particular string value
Spyware triggering system by particular string valueIJERD Editor
 
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...IJERD Editor
 
Secure Image Transmission for Cloud Storage System Using Hybrid Scheme
Secure Image Transmission for Cloud Storage System Using Hybrid SchemeSecure Image Transmission for Cloud Storage System Using Hybrid Scheme
Secure Image Transmission for Cloud Storage System Using Hybrid SchemeIJERD Editor
 
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...IJERD Editor
 
Gesture Gaming on the World Wide Web Using an Ordinary Web Camera
Gesture Gaming on the World Wide Web Using an Ordinary Web CameraGesture Gaming on the World Wide Web Using an Ordinary Web Camera
Gesture Gaming on the World Wide Web Using an Ordinary Web CameraIJERD Editor
 
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...IJERD Editor
 
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...IJERD Editor
 
Moon-bounce: A Boon for VHF Dxing
Moon-bounce: A Boon for VHF DxingMoon-bounce: A Boon for VHF Dxing
Moon-bounce: A Boon for VHF DxingIJERD Editor
 
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...IJERD Editor
 
Importance of Measurements in Smart Grid
Importance of Measurements in Smart GridImportance of Measurements in Smart Grid
Importance of Measurements in Smart GridIJERD Editor
 
Study of Macro level Properties of SCC using GGBS and Lime stone powder
Study of Macro level Properties of SCC using GGBS and Lime stone powderStudy of Macro level Properties of SCC using GGBS and Lime stone powder
Study of Macro level Properties of SCC using GGBS and Lime stone powderIJERD Editor
 

More from IJERD Editor (20)

A Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
A Novel Method for Prevention of Bandwidth Distributed Denial of Service AttacksA Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
A Novel Method for Prevention of Bandwidth Distributed Denial of Service Attacks
 
MEMS MICROPHONE INTERFACE
MEMS MICROPHONE INTERFACEMEMS MICROPHONE INTERFACE
MEMS MICROPHONE INTERFACE
 
Influence of tensile behaviour of slab on the structural Behaviour of shear c...
Influence of tensile behaviour of slab on the structural Behaviour of shear c...Influence of tensile behaviour of slab on the structural Behaviour of shear c...
Influence of tensile behaviour of slab on the structural Behaviour of shear c...
 
Gold prospecting using Remote Sensing ‘A case study of Sudan’
Gold prospecting using Remote Sensing ‘A case study of Sudan’Gold prospecting using Remote Sensing ‘A case study of Sudan’
Gold prospecting using Remote Sensing ‘A case study of Sudan’
 
Reducing Corrosion Rate by Welding Design
Reducing Corrosion Rate by Welding DesignReducing Corrosion Rate by Welding Design
Reducing Corrosion Rate by Welding Design
 
Router 1X3 – RTL Design and Verification
Router 1X3 – RTL Design and VerificationRouter 1X3 – RTL Design and Verification
Router 1X3 – RTL Design and Verification
 
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...
Active Power Exchange in Distributed Power-Flow Controller (DPFC) At Third Ha...
 
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVR
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVRMitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVR
Mitigation of Voltage Sag/Swell with Fuzzy Control Reduced Rating DVR
 
Study on the Fused Deposition Modelling In Additive Manufacturing
Study on the Fused Deposition Modelling In Additive ManufacturingStudy on the Fused Deposition Modelling In Additive Manufacturing
Study on the Fused Deposition Modelling In Additive Manufacturing
 
Spyware triggering system by particular string value
Spyware triggering system by particular string valueSpyware triggering system by particular string value
Spyware triggering system by particular string value
 
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...
A Blind Steganalysis on JPEG Gray Level Image Based on Statistical Features a...
 
Secure Image Transmission for Cloud Storage System Using Hybrid Scheme
Secure Image Transmission for Cloud Storage System Using Hybrid SchemeSecure Image Transmission for Cloud Storage System Using Hybrid Scheme
Secure Image Transmission for Cloud Storage System Using Hybrid Scheme
 
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...
Application of Buckley-Leverett Equation in Modeling the Radius of Invasion i...
 
Gesture Gaming on the World Wide Web Using an Ordinary Web Camera
Gesture Gaming on the World Wide Web Using an Ordinary Web CameraGesture Gaming on the World Wide Web Using an Ordinary Web Camera
Gesture Gaming on the World Wide Web Using an Ordinary Web Camera
 
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
Hardware Analysis of Resonant Frequency Converter Using Isolated Circuits And...
 
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
Simulated Analysis of Resonant Frequency Converter Using Different Tank Circu...
 
Moon-bounce: A Boon for VHF Dxing
Moon-bounce: A Boon for VHF DxingMoon-bounce: A Boon for VHF Dxing
Moon-bounce: A Boon for VHF Dxing
 
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...
“MS-Extractor: An Innovative Approach to Extract Microsatellites on „Y‟ Chrom...
 
Importance of Measurements in Smart Grid
Importance of Measurements in Smart GridImportance of Measurements in Smart Grid
Importance of Measurements in Smart Grid
 
Study of Macro level Properties of SCC using GGBS and Lime stone powder
Study of Macro level Properties of SCC using GGBS and Lime stone powderStudy of Macro level Properties of SCC using GGBS and Lime stone powder
Study of Macro level Properties of SCC using GGBS and Lime stone powder
 

Recently uploaded

Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxnull - The Open Security Community
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking MenDelhi Call girls
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Mattias Andersson
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
APIForce Zurich 5 April Automation LPDG
APIForce Zurich 5 April  Automation LPDGAPIForce Zurich 5 April  Automation LPDG
APIForce Zurich 5 April Automation LPDGMarianaLemus7
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking MenDelhi Call girls
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...Fwdays
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Scott Keck-Warren
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 

Recently uploaded (20)

Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptxMaking_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
Making_way_through_DLL_hollowing_inspite_of_CFG_by_Debjeet Banerjee.pptx
 
08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men08448380779 Call Girls In Friends Colony Women Seeking Men
08448380779 Call Girls In Friends Colony Women Seeking Men
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?Are Multi-Cloud and Serverless Good or Bad?
Are Multi-Cloud and Serverless Good or Bad?
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
APIForce Zurich 5 April Automation LPDG
APIForce Zurich 5 April  Automation LPDGAPIForce Zurich 5 April  Automation LPDG
APIForce Zurich 5 April Automation LPDG
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
08448380779 Call Girls In Diplomatic Enclave Women Seeking Men
 
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks..."LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
"LLMs for Python Engineers: Advanced Data Analysis and Semantic Kernel",Oleks...
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024Advanced Test Driven-Development @ php[tek] 2024
Advanced Test Driven-Development @ php[tek] 2024
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 

Procurement Strategy for Manufacturing and JIT

  • 1. International Journal of Engineering Research and Development e-ISSN: 2278-067X, p-ISSN: 2278-800X, www.ijerd.com Volume 11, Issue 02 (February 2015), PP.10-17 10 Procurement Strategy for Manufacturing and JIT D. K. Singh1 and Dr. Satyendra Singh2 1 Associate Professor, 2 Associate Professor 1 Division of MPA Engineering, Netaji Subhas Institute of Technology, New Delhi – 110078. 2 Deptt. of Mechanical Engg, B. T. Kumaon Institute of Technology, Dwarahat-263653 (Almora). Abstract: - Procurement involves the purchase of goods and services from the suppliers for the manufacturing units. Procuring the items in the most optimized way is very much desired to implement JIT effectively. Manufacturer-supplier relationship is very crucial for effective procurement policy. The present paper deals with various procurement strategies of manufacturing that include the optimization of manufacturing quantity along with the procurement of multiple input items. The procurement cycles for input items are considered in small lot sizes, which are essential for the effective implementation of JIT. The method of integer programming has been used to find the optimum integer values of number of orders for procuring the input items, which is usually found to be in fraction for a real manufacturing environment. Keywords: - JIT, Lot size, Procurement, Supply chain management. Notations used Ai = Fixed ordering cost for input item i C = Fixed set-up cost for end item di = Replenishment rate of input item i, units/period E = Total relevant cost considering end product and input item together F = Annual holding cost fraction Gi = Unit purchase cost for input item i ki = No. of orders for procurement of input item i in a production cycle m = No. of input items required ni = Units of input item i required for unit end item p = Production rate (including defective units), units/period P = Unit production cost (including value addition) Q = Production lot size (including defective items) r = Demand rate for end item, units/period R = Annual demand for end item V = Maximum inventory level (excluding defective end items) y = Proportion of non-defective end items in a lot I. INTRODUCTION Inventory management is a key management issue for the plants. It is of strategic importance rather than a mere buying function performed at lower levels of the organization, as has been the case in the past. Just in time (JIT) has been used as one of the most effective methods to control the level of inventory in the recent past, and is used even today most competitively and aggressively. It smoothens the flow of materials to arrive just at the time of their requirements. Deliveries are made directly to the factory floor, thus eliminating the scope of storage, inspection and transportation. JIT is dependent upon both the excellence of the internal manufacturing capabilities, and the development and management of strategic relationships with suppliers. The success of JIT is attributed to the close manufacturer-supplier relationship as a part of procurement strategy [1]. The strong manufacturer-supplier relationship makes a production system more dependable and eliminates any uncertainty regarding manufacturing schedule [2], and hence makes procurement easy for JIT to work more effectively. In case of late deliveries from the supplier, a company will be forced to keep large, costly inventories to keep their own products from being late to their customers [3]. Easy procurement and smooth flow of materials is directly linked to effective supply chain management. Whom to buy materials from, how to transport goods and services, and how to distribute them in the cost-effective, timely manner contributes to much of an organization’s strategic planning. Choosing a wrong supplier and a trust deficit in the supplier- manufacturer relationship can result in poor quality and late deliveries, which are detrimental in the interest of an organization. To make an efficient supply chain network, members of the supply chain are required to collaborate and work together, that is, a synergy is required between them, which in turn, greatly depends on the
  • 2. Procurement Strategy for Manufacturing and JIT 11 integration of the components of the information system [4]. A supply chain network can fail in the absence of effective information system. The complete elimination of inventories is very appealing, but it is not always feasible due to economic considerations. It is shown, although in case of complex assemblies, that lot-for-lot production in small batches may not be the best JIT strategy [5]. Significance of lot sizing will always be there whether JIT or traditional approach is applied for managing production-inventory system. Small lot sizes are useful in the implementation of JIT, as they tend to fulfill quick customer requirements. Easy and fast consumption of items in small lot size accelerate the pace of JIT and further procurement becomes more frequent. The basic EOQ model is a mathematical formulation to find the optimal order size that minimizes the sum of carrying costs and ordering costs. It is modified by incorporating different complexities [6]. A lot size model is developed for procurement of any input item in one or more lots during the production cycle [7]. But replenishment rate of the input item is considered to be infinite. The model is extended in the present paper to incorporate finite replenishment rate for input items and quality defects in a production system. Further a methodology is proposed in order to overcome computational difficulties for evaluation of procurement cycles. II. MODEL FORMULATION The model formulation for the procurement policy is based on the following assumptions:  During the production of a batch of end item, 100% inspection is carried out and rejected items are not added to end item inventory.  Smaller lot sizes of input items are replenished at the finite rate.  No price discount is considered on procured input items.  Replenishment rates of input items are greater than the rate of consumption of these items. Consider Fig.1, which shows the production-inventory cycles for end items and input items shown together. Annual inventory holding cost for end items = (V/2) PF = (yp-r) PFQ/2p [Since, V= (yp-r) Q/p] (1) The total annual cost for end product consists of set-up cost and holding cost, that is, (TC)e = RC / yQ + (yp-r) PFQ/2p (2) If Q is the production lot size, niQ/ki is the procurement lot size for input item i. Since input items inventory exists for a fraction of cycle time, which is (Q/p) / (yQ/r), that is, r/yp. Annual inventory carrying costs for input items m =  (di –pni) ni r Gi F Q / (2ki di y p) (3) i=1 The total annual cost for all the input items comprising of costs of carrying and ordering is expressed as m m (TC)i =  (R ki / y Q) Ai +  [(di-pni) ni r Gi FQ / (2ki di y p)] (4) i=1 i=1
  • 3. Procurement Strategy for Manufacturing and JIT 12 Equating partial derivative of equation (7) with respect to each ki to zero gives
  • 4. Procurement Strategy for Manufacturing and JIT 13 Equation (8) can be used to find the optimal solutions of ki, where i =1, 2, 3… m, as number of equations are equal to number of variables. But due to structure of equations, computational difficulties arise, which further increase as more number of input materials/components is used in real environment. Following methodology is proposed to overcome the problem. Let and From equation (10), values of k1, k2… km can be found in terms of X. Solving these equations, we can obtain k2, k3, … km in terms of k1, and from equation (9), X is evaluated in terms of k1 only. Value of X, thus, obtained is substituted in equation (10) in order to get a simple quadratic equation in terms of k1. Optimal value of k1 is computed, and eventually optimal values of ki for i = 1, 2, 3… m can be obtained easily. However, these values of ki are most probably in the decimal form. To find out the integer optimum values of ki, method of integer programming may be adopted. Analytical Data We consider the values of various parameters, which are near to practical values. Taking R = 1200, y = 0.9, C = Rs. 200, F = 0.3, p =120, r =105, P = Rs. 300, and m = 4, the values of Ai, di, Gi and ni are obtained, and are given in Table 1. Table 1: Data for input items Now from equation (10), we have Substituting values of parameters from Table 1, we get k1 = 0.3873 X (11) Similarly, k2 = 0.3464 X (12) k3 = 0.3162 X (13)
  • 5. Procurement Strategy for Manufacturing and JIT 14 and k4 = 0.5345 X (14) Dividing equations (12), (13) and (14) each by equation (11), we get k2 = 0.8944 k1 (15) k3 = 0.8164 k1 (16) and k4 = 1.38 k1 (17) Using equation (9), we have Substituting the values of k2, k3 and k4 from equations (15), (16) and (17), we get Using equation (11), we have Or 900 k1 2 + 1.3478 k1 - 3499.2301 = 0 Which gives k1 = 1.971 From equations (15), (16) and (17), we have k2 = 1.763 k3 = 1.609 and k4 = 2.72 Using equation (7), we get E = Rs. 3190.78. To find out the optimum integer number of orders for procurement of input items, proposed heuristic algorithm [7], which is stated to be more efficient than branch and bound method, is used. Fig. 2 represents the procedure starting from node I, which is the non-integer solution obtained before. Since, the value of k1 is 1.971, nearest integers surrounding it are 1 and 2. Node II and Node III represent the solutions corresponding to k1=2 and 1, respectively. As the value of E with Node II is lesser in comparison to Node III, Node II is considered for further branching with surrounding integer values of k2. Nodes IV and VII are chosen in a similar way for emanating the branches. Node VIII represents the integer optimum with cost, E = Rs. 3198.70. Optimum production lot size, Q can also be obtained using equation (6) by putting values of ki, and it is found to be 525.21.
  • 6. Procurement Strategy for Manufacturing and JIT 15 III. DISCUSSION OF RESULTS (a) Effect of decrease in ordering cost on total annual cost Fig. 3 shows the effect of decrease in ordering cost for input items on total annual cost. For the data taken, average ordering cost is decreased by a certain percentage uniformly for each input item, that is, for i = 1 to 4. We find that with up to 30% decrease in average ordering cost, the percentage decrease in total annual cost is of the order of 11%. In the uncertain economic environment, cost of capital and thus the inventory carrying cost fraction F varies. The computation is made for various values of F, that is, 0.2, 0.25 and 0.35. Fig. 3 is the representative of these calculations because the relative decrease in E is similar. This is also evident from equation (7) as the absolute values of E only differ and percentage decrease in E at various values of F due to similar percentage decrease in ordering cost may be similar. Values of ki are independent of F and these are found to be increasing with decreasing Ai, which is obvious.
  • 7. Procurement Strategy for Manufacturing and JIT 16 (b) Effect of decrease in set-up cost on total annual cost Fig. 4 shows the effect of decrease in set-up cost for end item on total annual cost. For the data taken, fixed set-up cost (C) for end item is decreased. We find about 6% decrease in total annual cost for 30% decrease in set-up cost. (c) Effect of decrease in non-defective end item on total annual cost Fig. 5 shows the effect of decrease in proportion of non-defective end items (y) in a lot on total annual cost. For the data taken, the total annual cost increases with decrease in y. We find the increase of about 5% and 11% in total annual cost corresponding to a respective decrease of about 5% and 10% in the value of y. The theoretical value of y should be 1. But in many real manufacturing environments, it is not feasible. The development of a new product is a challenging task as far as its quality control is concerned. It contains many untried elements that cause unexpected problems [8].
  • 8. Procurement Strategy for Manufacturing and JIT 17 Failure cost increases with the development of product. However, as long as the increase in sales revenue exceeds the increase in cost, it is allowed from managerial, profit-oriented point of view. In yet another case, a company may decide to use an old facility also to take benefit of increase in demand. In spite of old facility generating more number of defective items, profits may be earned. It is of interest to determine ordering policy with respect to quality defects. To conduct the sensitivity analysis with respect to quality level, production cost as well as purchase cost of input items should also be included, since they increase with the increase in quality defects. Since P is unit production cost including value addition, [(R/y)P] represents annual production and purchase cost and it is added in corresponding total cost E obtained earlier from equation (7). The sensitivity analysis is useful in deciding whether to allow more proportion of quality defects in specific situations. IV. CONCLUSIONS The procurement model manifests the procurement policy of lot sizing, and includes some realistic manufacturing conditions like finite replenishment rate of input items and quality defects in a production system. Quality and JIT has to work together for better procurement policy, which drastically cuts the level of work-in-process inventory. The TQM is an integral feature for JIT to be successful in manufacturing plants. Simultaneously, optimum number of cycles for the procurement of input items has been derived to obtain the initial solution, and its integer optimum values have also been obtained using method of integer programming. REFERENCES [1]. Brown, Steve; Manufacturing the Future, Pearson Education, London, 2000. [2]. Singh, D.K. and Singh Satyendra; “JIT: Various Aspects of its Implementation”, International Journal of Modern Engineering Research, Vol.3, Issue 3, May-June 2013, pp. 1582-1586. [3]. Russell, Roberta S and Taylor III Bernard W; Operations Management, Wiley India (P) Ltd; New Delhi, 2007. [4]. Singh, D.K; “JIT Implementation in Strategic Business Environment through Information Technology”, Industrial Engineering Journal, Vol.36, No.07, July 2007, pp.17-20. [5]. Anwar, M.F. and Negi, R; “Integrated Lot-sizing and Scheduling for Just-in-Time Production of Complex Assemblies with Finite Set-ups”, International Journal of Production Research, Vol.35 No.5, 1997, pp. 1447-1470. [6]. Tersine, R.J. et al; “A composite EOQ Model for Situational Decomposition”, Computers and Industrial Engineering, Vol. 22 No.3, 1992, pp.283-295. [7]. Banerjee, A. et al; “Input/output Lot Sizing in Single Stage Batch Production Systems under Constant Demand”, Computers and Industrial Engineering, Vol.19, No. 1- 4, 1990, pp.37-41. [8]. Kume, H; “Business Management and Quality Cost: The Japanese View”, Quality Progress, May 1985, pp.13-18.