Marks: 1
Many people consider project integration management the key
to overall pr= oject success.
Answer:
Question 2
Marks: 1
The ____ section of the project plan should describe the major
project functions and activities and identify those individuals
who are responsible for them.
Choose one answer.
a. organizational charts
b. other organizational or process-related informatio= n
c. project responsibilities
d. management objectives
Question 3
Marks: 1
____ should result in improvements in project performance.
Choose one answer.
a. Corrective actions
b. Corrective reports
c. Preventive actions
d. Proactive methods
Question 4
Marks: 1
The majority of time on a project is usually spent on ____, as is
most of= the project’s budget.
Choose one answer.
a. execution
b. planning
c. closing
d. monitoring and controlling </= label>
Question 5
Marks: 1
A ____ is a document that includes details related to the
identified proj= ect stakeholders.
Choose one answer.
a. stakeholder register
b. stakeholder list
c. stakeholder directory
d. stakeholder contact list
Question 6
Marks: 1
Key outcomes of the executing process group are formal
acceptance of the = work and creation of closing documents.
Answer:
Question 7
Marks: 1
____ provide information on how project execution is going.
Choose one answer.
a. Performance reports
b. Change requests
c. Deliverables
d. Contracts
Question 8
Marks: 1
Decisions and actions taken in one knowledge area at a certain
time rarel= y affect other knowledge areas.
Answer:
Question 9
Marks: 1
____ is a planning process falling under the Project Integration
Manageme= nt knowledge area.
Choose one answer.
a. Schedule development
b. Develop project management plan =
c. Create WBS
d. Quality planning
Question 10
Marks: 1
Project integration management must occur just within the
context of a pa= rticular project.
Answer:
Question 11
Marks: 1
During ____ processes for a new project, the organization
recognizes that a new project exists, and completes a project
charter as part of this recognition.
Choose one answer.
a. initiating
b. planning
c. opening
d. controlling
Question 12
Marks: 1
Author ____, who developed the concept of the strategic value
of competitive advantage, has written several books and articles
on strategic planning and competition.
Choose one answer.
a. James Bacon
b. Michael Porter
c. Robert Cooper
d. Carol Matlack
Question 13
Marks: 1
Opportunities and directives are essentially the same thing.
Answer:
Question 14
Marks: 1
____ tools track the execution of business process flows and
expose how the state of supporting IT systems and resources is
impacting end-to-end business process performance in real time.
Choose one answer.
a. BSM
b. CCB
c. CCA
d. BSC
Question 15
Marks: 1
____ analysis is a method of calculating the expected net
monetary gain or loss from a project by discounting all expected
future cash inflows and outflows to the present point in time.
Choose one answer.
a. Cost of capital
b. Net present value
c. Cash flow
d. Payback
Question 16
Marks: 1
____ the project involves taking the actions necessary to ensure
that act= ivities in the project plan are completed.
Choose one answer.
a. Executing
b. Initiating
c. Starting
d. Coordinating
Question 17
Marks: 1
As projects progress, the organization must reevaluate the need,
funding, and will for each project to determine if the project
should be continued, redefined, or terminated.
Answer:
Question 18
Marks: 1
An organization’s information technology project selection
proces= s should guide the strategic plan.
Answer:
Question 19
Marks: 1
The ____ provides a basis for creating the project schedule and
performing earned value management for measuring and
forecasting project performance.
Choose one answer.
a. WSB
b. project team analysis
c. WBS
d. project tool
Question 20
Marks: 1
A/An ____ is a document that describes the products or services
to be cre= ated by the project team.
Choose one answer.
a. contract
b. statement of work
c. project charter
d. business case
Question 21
Marks: 1
A stakeholder management strategy is an approach to help
increase the sup= port of stakeholders throughout the project.
Answer:
Question 22
Marks: 1
The project procurement management knowledge area maps to
the ____ process group through the activity of administering
procurements.
Choose one answer.
a. initiating
b. planning
c. executing
d. monitoring and controlling </= label>
Question 23
Marks: 1
Which of the following is an important input to the integrated
change con= trol process?
Choose one answer.
a. Deliverables
b. Work performance information =
c. Approved and rejected change requests =
d. Approved and validated defect repair =
Question 24
Marks: 1
All projects can benefit from using some type of project
management information system to coordinate and communicate
project information.
Answer:
Question 25
Marks: 1
Project managers should never be involved in strategic planning
and proje= ct selection.
Answer:
Question 26
Marks: 1
Executing the project includes work required to introduce any
new hardwar= e, software, and procedures into normal
operations.
Answer:
Question 27
Marks: 1
In the ____ stage of selecting information technology projects,
organizat= ions select information technology projects.
Choose one answer.
a. Project Planning
b. Business Area Analysis
c. Resource Allocation
d. Information Technology Strategy Planning =
Question 28
Marks: 1
The project scope management knowledge area maps to the
____ process group through the activities of scope verification
and scope control.
Choose one answer.
a. initiating
b. planning
c. executing
d. monitoring and controlling </= label>
Question 29
Marks: 1
A commonsense approach to improving the coordination
between project plan development and execution is to follow
this simple rule: Those who will do the work should not plan
the work.
Answer:
Question 30
Marks: 1
A/An ____ is a formal group of people responsible for
approving or reject= ing changes to a project.
Choose one answer.
a. CCA
b. CCB
c. CCC
d. CCD
Question 31
Marks: 1
A/An ____ is a formal, documented process that describes when
and how off= icial project documents may be changed.
Choose one answer.
a. integrated change control
b. change request
c. performance report
d. change control system
Question 32
Marks: 1
____ support contributes the most to successful information
technology pr= ojects.
Choose one answer.
a. Stakeholder
b. Team
c. Executive
d. User
Question 33
Marks: 1
The first step in determining the NPV is to ____.
Choose one answer.
a. determine the estimated costs and benefits for the= life of the
project and the products it produces
b. determine the discount rate <= /label>
c. calculate the net present value =
d. determine the cash flow
Question 34
Marks: 1
A milestone list is an output list associated with the Project
Scope Mana= gement knowledge area.
Answer:
Question 35
Marks: 1
Projects that address ____ are much more likely to be
successful because = they will be important to the organization.
Choose one answer.
a. a balanced scorecard
b. a weighted scoring model
c. broad organizational needs </= label>
d. net present value
Question 36
Marks: 1
In the ____ stage, organizations tie information technology
strategy to mission and vision of organization and identify key
business areas.
Choose one answer.
a. Project Planning
b. Business Area Analysis
c. Resource Allocation
d. Information Technology Strategy Planning =
Question 37
Marks: 1
____ are new requirements imposed by management,
government, or some exte= rnal influence.
Choose one answer.
a. Opportunities
b. Commands
c. Problems
d. Directives
Question 38
Marks: 1
Information technology is usually a support function in an
organization.<= /div>
Answer:
Question 39
Marks: 1
The ____ is the minimum acceptable rate of return on an
investment.
Choose one answer.
a. return on investment
b. internal rate of return
c. external rate of return
d. required rate of return
Question 40
Marks: 1
Research shows that ____ is the number one reason cited for
why organizat= ions invest in information technology projects.
Choose one answer.
a. providing financial incentives =
b. supporting implicit business objectives =
c. supporting explicit business objectives =
d. keeping abreast of technological advances =
Question 41
Marks: 1
One method for selecting projects based on ____ is to determine
whether they first meet three important criteria: need, funding,
and will.
Choose one answer.
a. broad organizational needs </= label>
b. using a weighted scoring model =
c. implementing a balanced scorecard =
d. categorizing information technology projects =
Question 42
Marks: 1
Administrative activities are often involved in ____, such as
archiving project files, closing out contracts, documenting
lessons learned, and receiving formal acceptance of the
delivered work as part of the phase or project.
Choose one answer.
a. monitoring and controlling processes =
b. executing processes
c. initiating processes
d. closing processes
Question 43
Marks: 1
Project integration management does not include interface
management.
Answer:
Question 44
Marks: 1
A/An ____ is a document that formally recognizes the existence
of a project and provides direction on the project’s objectives
and management.
Choose one answer.
a. balanced scorecard
b. business case
c. net present value analysis </= label>
d. project charter
Question 45
Marks: 1
A ____ is a meeting held at the beginning of a project so that
stakeholders can meet each other, review the goals of the
project, and discuss future plans.
Choose one answer.
a. kick-off party
b. launch meeting
c. kick-off meeting
d. project launch meeting
Question 46
Marks: 1
The project integration management knowledge area maps to the
____ process group through the activities of developing project
charters.
Choose one answer.
a. initiating
b. planning
c. executing
d. monitoring and controlling </= label>
Question 47
Marks: 1
____ is a monitoring and controlling process.
Choose one answer.
a. Develop project team
b. Request seller responses
c. Risk response planning
d. Integrated change control
Question 48
Marks: 1
The project procurement management knowledge area maps to
the ____ process group through the activities conducting
procurements.
Choose one answer.
a. initiating
b. planning
c. executing
d. monitoring and controlling </= label>
Question 49
Marks: 1
Projects involve ____ project management process groups.
Choose one answer.
a. three
b. five
c. eight
d. ten
Question 50
Marks: 1
The first step in creating a weighted scoring model is to assign
a weight= to each criterion.
Answer:
Question 51
Marks: 1
Some people might use a contract in place of a charter.
Answer:
Question 52
Marks: 1
The ____ step in the planning process is to tie the information
technology strategic plan to the organization’s overall strategic
p= lan.
Choose one answer.
a. first
b. second
c. third
d. fourth
Question 53
Marks: 1
Project management plans document project planning
assumptions and decisi= ons regarding choices.
Answer:
Question 54
Marks: 1
In addition to progress reports, an important tool for monitoring
and controlling a project is using project management software.
Answer:
Question 55
Marks: 1
____ include devising and maintaining a workable scheme to
ensure that th= e project addresses the organization’s needs.
Choose one answer.
a. Initiating processes
b. Planning processes
c. Executing processes
d. Monitoring and controlling processes =
Question 56
Marks: 1
A/An ____ is a document used to coordinate all project planning
documents= and help guide a project’s execution and control.
Choose one answer.
a. project management plan
b. statement of work
c. scope statement
d. contact
Question 57
Marks: 1
In the ____ information technology planning stage, the analysis
outlines business processes that are central to achieving
strategic goals and helps determine which ones could most
benefit from information technology.
Choose one answer.
a. Project Planning
b. Business Area Analysis
c. Resource Allocation
d. Information Technology Strategy Planning =
Question 58
Marks: 1
Initiating processes take place during each phase of a project.
Answer:
Question 59
Marks: 1
Directing and managing project execution involves carrying out
the project management plan by performing the activities
included in it.
Answer:
Question 60
Marks: 1
A ____ is an approach to help increase the support of
stakeholders throug= hout the project.
Choose one answer.
a. stakeholder management plan <= /label>
b. stakeholder strategy
c. stakeholder management strategy =
d. stakeholder management list <= /label>
Question 61
Marks: 1
The ____ process involves gaining stakeholder and customer
acceptance of the final products and services and bringing the
project, or project phase, to an orderly end.
Choose one answer.
a. ending
b. closing
c. developing
d. completing
Question 62
Marks: 1
____ ensures that the descriptions of the project’s products are
= correct and complete.
Choose one answer.
a. CCB
b. Correction management
c. Configuration management
d. Product description management =
Question 63
Marks: 1
In the ____ stage of selecting information technology projects,
organizat= ions define project scope, benefits, and constraints.
Choose one answer.
a. Project Planning
b. Business Area Analysis
c. Resource Allocation
d. Information Technology Strategy Planning =
Question 64
Marks: 1
On large projects, many project managers say that ____ percent
of the job= is communicating and managing changes.
Choose one answer.
a. 50
b. 70
c. 90
d. 100
Question 65
Marks: 1
It is good practice to focus on the ____ of meetings.
Choose one answer.
a. flow
b. planning
c. agenda
d. results
Question 66
Marks: 1
The process of acquiring a project team falls under the Project
Human Res= ource Management knowledge area.
Answer:
Question 67
Marks: 1
____ is an iterative software development process that focuses
on team productivity and delivers software best practices to all
team members.
Choose one answer.
a. RAP
b. RIP
c. RUP
d. ROP
Question 68
Marks: 1
An annual discount factor is a multiplier for each year based on
the disc= ount rate and year.
Answer:
Question 69
Marks: 1
In the long-term view, it is better to have a huge success on an
unimportant project than to have a moderate success on an
important project.
Answer:
Question 70
Marks: 1
____ involves coordinating all planning efforts to create a
consistent, c= oherent document.
Choose one answer.
a. Developing the project charter =
b. Developing the preliminary project scope statement=
c. Developing the project management plan =
d. Directing and managing project execution =
Question 71
Marks: 1
____ should serve as the foundation for deciding which projects
to pursue= .
Choose one answer.
a. Strategic planning
b. Project managers
c. Successful past projects
d. Employee abilities
Question 72
Marks: 1
The level of activity and length of each process group varies for
every p= roject.
Answer:
Question 73
Marks: 1
Examples of ____ include acquiring and developing the project
team, performing quality assurance, distributing information,
managing stakeholder expectations, and conducting
procurements.
Choose one answer.
a. monitoring and controlling processes =
b. executing processes
c. planning processes
d. initiating processes
Question 74
Marks: 1
The project communications management knowledge area maps
to the ____ process group through the activity of information
distribution.
Choose one answer.
a. initiating
b. planning
c. executing
d. monitoring and controlling </= label>
Question 75
Marks: 1
Many people are familiar with SWOT analysis—analyzing
Strengths,= Weaknesses, Opportunities, and Threats—which is
used to aid in ____= .
Choose one answer.
a. project initiation
b. project planning
c. strategic planning
d. strategic initiation
=

More Related Content

Similar to 1Marks 1Many people consider project integratio.docx

Question 11 ptsWhen composing a risk management plan, one of the a.pdf
Question 11 ptsWhen composing a risk management plan, one of the a.pdfQuestion 11 ptsWhen composing a risk management plan, one of the a.pdf
Question 11 ptsWhen composing a risk management plan, one of the a.pdf
Choices3
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
IRESH3
 
Mb0033 mb0049
Mb0033 mb0049Mb0033 mb0049
Mb0033 mb0049amitpr
 
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshareLiberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
Song Love
 
Liberty university busi 313 quiz 2 complete solutions correct answers key
Liberty university busi 313 quiz 2 complete solutions correct answers keyLiberty university busi 313 quiz 2 complete solutions correct answers key
Liberty university busi 313 quiz 2 complete solutions correct answers key
Matt Smith
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
Project Cubicle
 
150 PMP Questions
150 PMP Questions 150 PMP Questions
150 PMP Questions
Amina .M.Gidado
 
Certified Associate in Project Management
Certified Associate in Project ManagementCertified Associate in Project Management
Certified Associate in Project Management
Ellina Beckman
 
pmp 200 q ans_key
pmp 200 q ans_keypmp 200 q ans_key
pmp 200 q ans_key
Qamar S Satti
 
Pmstudy exam 4
Pmstudy exam 4Pmstudy exam 4
Pmstudy exam 4
Mohamed Saeed
 
415 quiz1 answers
415 quiz1 answers415 quiz1 answers
415 quiz1 answers
IIUM
 
Itpm question bank
Itpm   question bankItpm   question bank
Itpm question bank
Hussain111321
 
MGT150. PROJECT MANAGEMENT (MGT150) TAKE ASSESSMENT FINAL EXAM.docx
MGT150. PROJECT MANAGEMENT (MGT150)  TAKE ASSESSMENT FINAL EXAM.docxMGT150. PROJECT MANAGEMENT (MGT150)  TAKE ASSESSMENT FINAL EXAM.docx
MGT150. PROJECT MANAGEMENT (MGT150) TAKE ASSESSMENT FINAL EXAM.docx
annandleola
 
Project Management - Which of the following is not a suggestion for performin...
Project Management - Which of the following is not a suggestion for performin...Project Management - Which of the following is not a suggestion for performin...
Project Management - Which of the following is not a suggestion for performin...
Suma Kamadod
 
Project Management - __________________ is a network diagramming technique ...
Project Management -   __________________ is a network diagramming technique ...Project Management -   __________________ is a network diagramming technique ...
Project Management - __________________ is a network diagramming technique ...
Suma Kamadod
 
Project Management - Project manager is responsible for a) overseeing change ...
Project Management - Project manager is responsible for a) overseeing change ...Project Management - Project manager is responsible for a) overseeing change ...
Project Management - Project manager is responsible for a) overseeing change ...
Suma Kamadod
 
Project Management - _________________ is known for his work on quality con...
Project Management -   _________________ is known for his work on quality con...Project Management -   _________________ is known for his work on quality con...
Project Management - _________________ is known for his work on quality con...
Suma Kamadod
 
Project Management - A ________________ is a document that formally recogni...
Project Management - A   ________________ is a document that formally recogni...Project Management - A   ________________ is a document that formally recogni...
Project Management - A ________________ is a document that formally recogni...
Suma Kamadod
 
Project Management - The theory of constraints (toc) is successfully applied ...
Project Management - The theory of constraints (toc) is successfully applied ...Project Management - The theory of constraints (toc) is successfully applied ...
Project Management - The theory of constraints (toc) is successfully applied ...
Suma Kamadod
 

Similar to 1Marks 1Many people consider project integratio.docx (20)

Question 11 ptsWhen composing a risk management plan, one of the a.pdf
Question 11 ptsWhen composing a risk management plan, one of the a.pdfQuestion 11 ptsWhen composing a risk management plan, one of the a.pdf
Question 11 ptsWhen composing a risk management plan, one of the a.pdf
 
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docxQuestion 1 Artifacts” in the Scrum terminology are the equiva.docx
Question 1 Artifacts” in the Scrum terminology are the equiva.docx
 
Mb0033 mb0049
Mb0033 mb0049Mb0033 mb0049
Mb0033 mb0049
 
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshareLiberty university busi 313 quiz 2 complete solutions correct answers slideshare
Liberty university busi 313 quiz 2 complete solutions correct answers slideshare
 
Liberty university busi 313 quiz 2 complete solutions correct answers key
Liberty university busi 313 quiz 2 complete solutions correct answers keyLiberty university busi 313 quiz 2 complete solutions correct answers key
Liberty university busi 313 quiz 2 complete solutions correct answers key
 
PMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdfPMP-Prep-Exam-Test-200_Questions.pdf
PMP-Prep-Exam-Test-200_Questions.pdf
 
150 PMP Questions
150 PMP Questions 150 PMP Questions
150 PMP Questions
 
Certified Associate in Project Management
Certified Associate in Project ManagementCertified Associate in Project Management
Certified Associate in Project Management
 
pmp 200 q ans_key
pmp 200 q ans_keypmp 200 q ans_key
pmp 200 q ans_key
 
Pmstudy exam 4
Pmstudy exam 4Pmstudy exam 4
Pmstudy exam 4
 
415 quiz1 answers
415 quiz1 answers415 quiz1 answers
415 quiz1 answers
 
Itpm question bank
Itpm   question bankItpm   question bank
Itpm question bank
 
Sad quiz
Sad quizSad quiz
Sad quiz
 
MGT150. PROJECT MANAGEMENT (MGT150) TAKE ASSESSMENT FINAL EXAM.docx
MGT150. PROJECT MANAGEMENT (MGT150)  TAKE ASSESSMENT FINAL EXAM.docxMGT150. PROJECT MANAGEMENT (MGT150)  TAKE ASSESSMENT FINAL EXAM.docx
MGT150. PROJECT MANAGEMENT (MGT150) TAKE ASSESSMENT FINAL EXAM.docx
 
Project Management - Which of the following is not a suggestion for performin...
Project Management - Which of the following is not a suggestion for performin...Project Management - Which of the following is not a suggestion for performin...
Project Management - Which of the following is not a suggestion for performin...
 
Project Management - __________________ is a network diagramming technique ...
Project Management -   __________________ is a network diagramming technique ...Project Management -   __________________ is a network diagramming technique ...
Project Management - __________________ is a network diagramming technique ...
 
Project Management - Project manager is responsible for a) overseeing change ...
Project Management - Project manager is responsible for a) overseeing change ...Project Management - Project manager is responsible for a) overseeing change ...
Project Management - Project manager is responsible for a) overseeing change ...
 
Project Management - _________________ is known for his work on quality con...
Project Management -   _________________ is known for his work on quality con...Project Management -   _________________ is known for his work on quality con...
Project Management - _________________ is known for his work on quality con...
 
Project Management - A ________________ is a document that formally recogni...
Project Management - A   ________________ is a document that formally recogni...Project Management - A   ________________ is a document that formally recogni...
Project Management - A ________________ is a document that formally recogni...
 
Project Management - The theory of constraints (toc) is successfully applied ...
Project Management - The theory of constraints (toc) is successfully applied ...Project Management - The theory of constraints (toc) is successfully applied ...
Project Management - The theory of constraints (toc) is successfully applied ...
 

More from hyacinthshackley2629

Your company nameYour nameInstruction Page1. O.docx
Your company nameYour nameInstruction Page1. O.docxYour company nameYour nameInstruction Page1. O.docx
Your company nameYour nameInstruction Page1. O.docx
hyacinthshackley2629
 
Your Company NameYour Company NameBudget Proposalfor[ent.docx
Your Company NameYour Company NameBudget Proposalfor[ent.docxYour Company NameYour Company NameBudget Proposalfor[ent.docx
Your Company NameYour Company NameBudget Proposalfor[ent.docx
hyacinthshackley2629
 
Your company recently reviewed the results of a penetration test.docx
Your company recently reviewed the results of a penetration test.docxYour company recently reviewed the results of a penetration test.docx
Your company recently reviewed the results of a penetration test.docx
hyacinthshackley2629
 
Your company wants to explore moving much of their data and info.docx
Your company wants to explore moving much of their data and info.docxYour company wants to explore moving much of their data and info.docx
Your company wants to explore moving much of their data and info.docx
hyacinthshackley2629
 
Your company plans to establish MNE manufacturing operations in Sout.docx
Your company plans to establish MNE manufacturing operations in Sout.docxYour company plans to establish MNE manufacturing operations in Sout.docx
Your company plans to establish MNE manufacturing operations in Sout.docx
hyacinthshackley2629
 
Your company just purchased a Dell server MD1420 DAS to use to store.docx
Your company just purchased a Dell server MD1420 DAS to use to store.docxYour company just purchased a Dell server MD1420 DAS to use to store.docx
Your company just purchased a Dell server MD1420 DAS to use to store.docx
hyacinthshackley2629
 
your company is moving to a new HRpayroll system that is sponsored .docx
your company is moving to a new HRpayroll system that is sponsored .docxyour company is moving to a new HRpayroll system that is sponsored .docx
your company is moving to a new HRpayroll system that is sponsored .docx
hyacinthshackley2629
 
Your company is considering the implementation of a technology s.docx
Your company is considering the implementation of a technology s.docxYour company is considering the implementation of a technology s.docx
Your company is considering the implementation of a technology s.docx
hyacinthshackley2629
 
Your company is a security service contractor that consults with bus.docx
Your company is a security service contractor that consults with bus.docxYour company is a security service contractor that consults with bus.docx
Your company is a security service contractor that consults with bus.docx
hyacinthshackley2629
 
Your company has just sent you to a Project Management Conference on.docx
Your company has just sent you to a Project Management Conference on.docxYour company has just sent you to a Project Management Conference on.docx
Your company has just sent you to a Project Management Conference on.docx
hyacinthshackley2629
 
Your company has designed an information system for a library.  The .docx
Your company has designed an information system for a library.  The .docxYour company has designed an information system for a library.  The .docx
Your company has designed an information system for a library.  The .docx
hyacinthshackley2629
 
Your company has had embedded HR generalists in business units for t.docx
Your company has had embedded HR generalists in business units for t.docxYour company has had embedded HR generalists in business units for t.docx
Your company has had embedded HR generalists in business units for t.docx
hyacinthshackley2629
 
Your company You are a new Supply Chain Analyst with the ACME.docx
Your company   You are a new Supply Chain Analyst with the ACME.docxYour company   You are a new Supply Chain Analyst with the ACME.docx
Your company You are a new Supply Chain Analyst with the ACME.docx
hyacinthshackley2629
 
Your company has asked that you create a survey to collect data .docx
Your company has asked that you create a survey to collect data .docxYour company has asked that you create a survey to collect data .docx
Your company has asked that you create a survey to collect data .docx
hyacinthshackley2629
 
Your Communications PlanDescriptionA.What is your .docx
Your Communications PlanDescriptionA.What is your .docxYour Communications PlanDescriptionA.What is your .docx
Your Communications PlanDescriptionA.What is your .docx
hyacinthshackley2629
 
Your community includes people from diverse backgrounds. Answer .docx
Your community includes people from diverse backgrounds. Answer .docxYour community includes people from diverse backgrounds. Answer .docx
Your community includes people from diverse backgrounds. Answer .docx
hyacinthshackley2629
 
Your Communications Plan Please respond to the following.docx
Your Communications Plan Please respond to the following.docxYour Communications Plan Please respond to the following.docx
Your Communications Plan Please respond to the following.docx
hyacinthshackley2629
 
Your Communication InvestigationFor your mission after reading y.docx
Your Communication InvestigationFor your mission after reading y.docxYour Communication InvestigationFor your mission after reading y.docx
Your Communication InvestigationFor your mission after reading y.docx
hyacinthshackley2629
 
Your Communications PlanFirst step Choose a topic. Revi.docx
Your Communications PlanFirst step Choose a topic. Revi.docxYour Communications PlanFirst step Choose a topic. Revi.docx
Your Communications PlanFirst step Choose a topic. Revi.docx
hyacinthshackley2629
 
Your coffee franchise cleared for business in both countries (Mexico.docx
Your coffee franchise cleared for business in both countries (Mexico.docxYour coffee franchise cleared for business in both countries (Mexico.docx
Your coffee franchise cleared for business in both countries (Mexico.docx
hyacinthshackley2629
 

More from hyacinthshackley2629 (20)

Your company nameYour nameInstruction Page1. O.docx
Your company nameYour nameInstruction Page1. O.docxYour company nameYour nameInstruction Page1. O.docx
Your company nameYour nameInstruction Page1. O.docx
 
Your Company NameYour Company NameBudget Proposalfor[ent.docx
Your Company NameYour Company NameBudget Proposalfor[ent.docxYour Company NameYour Company NameBudget Proposalfor[ent.docx
Your Company NameYour Company NameBudget Proposalfor[ent.docx
 
Your company recently reviewed the results of a penetration test.docx
Your company recently reviewed the results of a penetration test.docxYour company recently reviewed the results of a penetration test.docx
Your company recently reviewed the results of a penetration test.docx
 
Your company wants to explore moving much of their data and info.docx
Your company wants to explore moving much of their data and info.docxYour company wants to explore moving much of their data and info.docx
Your company wants to explore moving much of their data and info.docx
 
Your company plans to establish MNE manufacturing operations in Sout.docx
Your company plans to establish MNE manufacturing operations in Sout.docxYour company plans to establish MNE manufacturing operations in Sout.docx
Your company plans to establish MNE manufacturing operations in Sout.docx
 
Your company just purchased a Dell server MD1420 DAS to use to store.docx
Your company just purchased a Dell server MD1420 DAS to use to store.docxYour company just purchased a Dell server MD1420 DAS to use to store.docx
Your company just purchased a Dell server MD1420 DAS to use to store.docx
 
your company is moving to a new HRpayroll system that is sponsored .docx
your company is moving to a new HRpayroll system that is sponsored .docxyour company is moving to a new HRpayroll system that is sponsored .docx
your company is moving to a new HRpayroll system that is sponsored .docx
 
Your company is considering the implementation of a technology s.docx
Your company is considering the implementation of a technology s.docxYour company is considering the implementation of a technology s.docx
Your company is considering the implementation of a technology s.docx
 
Your company is a security service contractor that consults with bus.docx
Your company is a security service contractor that consults with bus.docxYour company is a security service contractor that consults with bus.docx
Your company is a security service contractor that consults with bus.docx
 
Your company has just sent you to a Project Management Conference on.docx
Your company has just sent you to a Project Management Conference on.docxYour company has just sent you to a Project Management Conference on.docx
Your company has just sent you to a Project Management Conference on.docx
 
Your company has designed an information system for a library.  The .docx
Your company has designed an information system for a library.  The .docxYour company has designed an information system for a library.  The .docx
Your company has designed an information system for a library.  The .docx
 
Your company has had embedded HR generalists in business units for t.docx
Your company has had embedded HR generalists in business units for t.docxYour company has had embedded HR generalists in business units for t.docx
Your company has had embedded HR generalists in business units for t.docx
 
Your company You are a new Supply Chain Analyst with the ACME.docx
Your company   You are a new Supply Chain Analyst with the ACME.docxYour company   You are a new Supply Chain Analyst with the ACME.docx
Your company You are a new Supply Chain Analyst with the ACME.docx
 
Your company has asked that you create a survey to collect data .docx
Your company has asked that you create a survey to collect data .docxYour company has asked that you create a survey to collect data .docx
Your company has asked that you create a survey to collect data .docx
 
Your Communications PlanDescriptionA.What is your .docx
Your Communications PlanDescriptionA.What is your .docxYour Communications PlanDescriptionA.What is your .docx
Your Communications PlanDescriptionA.What is your .docx
 
Your community includes people from diverse backgrounds. Answer .docx
Your community includes people from diverse backgrounds. Answer .docxYour community includes people from diverse backgrounds. Answer .docx
Your community includes people from diverse backgrounds. Answer .docx
 
Your Communications Plan Please respond to the following.docx
Your Communications Plan Please respond to the following.docxYour Communications Plan Please respond to the following.docx
Your Communications Plan Please respond to the following.docx
 
Your Communication InvestigationFor your mission after reading y.docx
Your Communication InvestigationFor your mission after reading y.docxYour Communication InvestigationFor your mission after reading y.docx
Your Communication InvestigationFor your mission after reading y.docx
 
Your Communications PlanFirst step Choose a topic. Revi.docx
Your Communications PlanFirst step Choose a topic. Revi.docxYour Communications PlanFirst step Choose a topic. Revi.docx
Your Communications PlanFirst step Choose a topic. Revi.docx
 
Your coffee franchise cleared for business in both countries (Mexico.docx
Your coffee franchise cleared for business in both countries (Mexico.docxYour coffee franchise cleared for business in both countries (Mexico.docx
Your coffee franchise cleared for business in both countries (Mexico.docx
 

Recently uploaded

Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Po-Chuan Chen
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
Vikramjit Singh
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
vaibhavrinwa19
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
TechSoup
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
TechSoup
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
Peter Windle
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
MIRIAMSALINAS13
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
Tamralipta Mahavidyalaya
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
Peter Windle
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
beazzy04
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
Jean Carlos Nunes Paixão
 

Recently uploaded (20)

Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdfAdversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
Adversarial Attention Modeling for Multi-dimensional Emotion Regression.pdf
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Digital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and ResearchDigital Tools and AI for Teaching Learning and Research
Digital Tools and AI for Teaching Learning and Research
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
 
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup   New Member Orientation and Q&A (May 2024).pdfWelcome to TechSoup   New Member Orientation and Q&A (May 2024).pdf
Welcome to TechSoup New Member Orientation and Q&A (May 2024).pdf
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
Introduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp NetworkIntroduction to AI for Nonprofits with Tapp Network
Introduction to AI for Nonprofits with Tapp Network
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
A Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in EducationA Strategic Approach: GenAI in Education
A Strategic Approach: GenAI in Education
 
Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345Sha'Carri Richardson Presentation 202345
Sha'Carri Richardson Presentation 202345
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 
Lapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdfLapbook sobre os Regimes Totalitários.pdf
Lapbook sobre os Regimes Totalitários.pdf
 

1Marks 1Many people consider project integratio.docx

  • 1. 1 Marks: 1 Many people consider project integration management the key to overall pr= oject success. Answer: Question 2 Marks: 1 The ____ section of the project plan should describe the major project functions and activities and identify those individuals who are responsible for them. Choose one answer. a. organizational charts b. other organizational or process-related informatio= n c. project responsibilities d. management objectives Question 3
  • 2. Marks: 1 ____ should result in improvements in project performance. Choose one answer. a. Corrective actions b. Corrective reports c. Preventive actions d. Proactive methods Question 4 Marks: 1 The majority of time on a project is usually spent on ____, as is most of= the project’s budget. Choose one answer. a. execution b. planning c. closing d. monitoring and controlling </= label> Question 5 Marks: 1
  • 3. A ____ is a document that includes details related to the identified proj= ect stakeholders. Choose one answer. a. stakeholder register b. stakeholder list c. stakeholder directory d. stakeholder contact list Question 6 Marks: 1 Key outcomes of the executing process group are formal acceptance of the = work and creation of closing documents. Answer: Question 7 Marks: 1 ____ provide information on how project execution is going. Choose one answer. a. Performance reports b. Change requests c. Deliverables
  • 4. d. Contracts Question 8 Marks: 1 Decisions and actions taken in one knowledge area at a certain time rarel= y affect other knowledge areas. Answer: Question 9 Marks: 1 ____ is a planning process falling under the Project Integration Manageme= nt knowledge area. Choose one answer. a. Schedule development b. Develop project management plan = c. Create WBS d. Quality planning Question 10 Marks: 1 Project integration management must occur just within the context of a pa= rticular project.
  • 5. Answer: Question 11 Marks: 1 During ____ processes for a new project, the organization recognizes that a new project exists, and completes a project charter as part of this recognition. Choose one answer. a. initiating b. planning c. opening d. controlling Question 12 Marks: 1 Author ____, who developed the concept of the strategic value of competitive advantage, has written several books and articles on strategic planning and competition. Choose one answer. a. James Bacon b. Michael Porter
  • 6. c. Robert Cooper d. Carol Matlack Question 13 Marks: 1 Opportunities and directives are essentially the same thing. Answer: Question 14 Marks: 1 ____ tools track the execution of business process flows and expose how the state of supporting IT systems and resources is impacting end-to-end business process performance in real time. Choose one answer. a. BSM b. CCB c. CCA d. BSC Question 15 Marks: 1 ____ analysis is a method of calculating the expected net
  • 7. monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time. Choose one answer. a. Cost of capital b. Net present value c. Cash flow d. Payback Question 16 Marks: 1 ____ the project involves taking the actions necessary to ensure that act= ivities in the project plan are completed. Choose one answer. a. Executing b. Initiating c. Starting d. Coordinating Question 17 Marks: 1 As projects progress, the organization must reevaluate the need, funding, and will for each project to determine if the project
  • 8. should be continued, redefined, or terminated. Answer: Question 18 Marks: 1 An organization’s information technology project selection proces= s should guide the strategic plan. Answer: Question 19 Marks: 1 The ____ provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance. Choose one answer. a. WSB b. project team analysis c. WBS d. project tool Question 20 Marks: 1
  • 9. A/An ____ is a document that describes the products or services to be cre= ated by the project team. Choose one answer. a. contract b. statement of work c. project charter d. business case Question 21 Marks: 1 A stakeholder management strategy is an approach to help increase the sup= port of stakeholders throughout the project. Answer: Question 22 Marks: 1 The project procurement management knowledge area maps to the ____ process group through the activity of administering procurements. Choose one answer. a. initiating
  • 10. b. planning c. executing d. monitoring and controlling </= label> Question 23 Marks: 1 Which of the following is an important input to the integrated change con= trol process? Choose one answer. a. Deliverables b. Work performance information = c. Approved and rejected change requests = d. Approved and validated defect repair = Question 24 Marks: 1 All projects can benefit from using some type of project management information system to coordinate and communicate project information. Answer: Question 25
  • 11. Marks: 1 Project managers should never be involved in strategic planning and proje= ct selection. Answer: Question 26 Marks: 1 Executing the project includes work required to introduce any new hardwar= e, software, and procedures into normal operations. Answer: Question 27 Marks: 1 In the ____ stage of selecting information technology projects, organizat= ions select information technology projects. Choose one answer. a. Project Planning b. Business Area Analysis c. Resource Allocation d. Information Technology Strategy Planning =
  • 12. Question 28 Marks: 1 The project scope management knowledge area maps to the ____ process group through the activities of scope verification and scope control. Choose one answer. a. initiating b. planning c. executing d. monitoring and controlling </= label> Question 29 Marks: 1 A commonsense approach to improving the coordination between project plan development and execution is to follow this simple rule: Those who will do the work should not plan the work. Answer: Question 30 Marks: 1 A/An ____ is a formal group of people responsible for approving or reject= ing changes to a project.
  • 13. Choose one answer. a. CCA b. CCB c. CCC d. CCD Question 31 Marks: 1 A/An ____ is a formal, documented process that describes when and how off= icial project documents may be changed. Choose one answer. a. integrated change control b. change request c. performance report d. change control system Question 32 Marks: 1 ____ support contributes the most to successful information technology pr= ojects. Choose one answer.
  • 14. a. Stakeholder b. Team c. Executive d. User Question 33 Marks: 1 The first step in determining the NPV is to ____. Choose one answer. a. determine the estimated costs and benefits for the= life of the project and the products it produces b. determine the discount rate <= /label> c. calculate the net present value = d. determine the cash flow Question 34 Marks: 1 A milestone list is an output list associated with the Project Scope Mana= gement knowledge area. Answer:
  • 15. Question 35 Marks: 1 Projects that address ____ are much more likely to be successful because = they will be important to the organization. Choose one answer. a. a balanced scorecard b. a weighted scoring model c. broad organizational needs </= label> d. net present value Question 36 Marks: 1 In the ____ stage, organizations tie information technology strategy to mission and vision of organization and identify key business areas. Choose one answer. a. Project Planning b. Business Area Analysis c. Resource Allocation d. Information Technology Strategy Planning = Question 37
  • 16. Marks: 1 ____ are new requirements imposed by management, government, or some exte= rnal influence. Choose one answer. a. Opportunities b. Commands c. Problems d. Directives Question 38 Marks: 1 Information technology is usually a support function in an organization.<= /div> Answer: Question 39 Marks: 1 The ____ is the minimum acceptable rate of return on an investment. Choose one answer. a. return on investment
  • 17. b. internal rate of return c. external rate of return d. required rate of return Question 40 Marks: 1 Research shows that ____ is the number one reason cited for why organizat= ions invest in information technology projects. Choose one answer. a. providing financial incentives = b. supporting implicit business objectives = c. supporting explicit business objectives = d. keeping abreast of technological advances = Question 41 Marks: 1 One method for selecting projects based on ____ is to determine whether they first meet three important criteria: need, funding, and will. Choose one answer. a. broad organizational needs </= label>
  • 18. b. using a weighted scoring model = c. implementing a balanced scorecard = d. categorizing information technology projects = Question 42 Marks: 1 Administrative activities are often involved in ____, such as archiving project files, closing out contracts, documenting lessons learned, and receiving formal acceptance of the delivered work as part of the phase or project. Choose one answer. a. monitoring and controlling processes = b. executing processes c. initiating processes d. closing processes Question 43 Marks: 1 Project integration management does not include interface management. Answer: Question 44
  • 19. Marks: 1 A/An ____ is a document that formally recognizes the existence of a project and provides direction on the project’s objectives and management. Choose one answer. a. balanced scorecard b. business case c. net present value analysis </= label> d. project charter Question 45 Marks: 1 A ____ is a meeting held at the beginning of a project so that stakeholders can meet each other, review the goals of the project, and discuss future plans. Choose one answer. a. kick-off party b. launch meeting c. kick-off meeting d. project launch meeting Question 46
  • 20. Marks: 1 The project integration management knowledge area maps to the ____ process group through the activities of developing project charters. Choose one answer. a. initiating b. planning c. executing d. monitoring and controlling </= label> Question 47 Marks: 1 ____ is a monitoring and controlling process. Choose one answer. a. Develop project team b. Request seller responses c. Risk response planning d. Integrated change control Question 48 Marks: 1
  • 21. The project procurement management knowledge area maps to the ____ process group through the activities conducting procurements. Choose one answer. a. initiating b. planning c. executing d. monitoring and controlling </= label> Question 49 Marks: 1 Projects involve ____ project management process groups. Choose one answer. a. three b. five c. eight d. ten Question 50 Marks: 1 The first step in creating a weighted scoring model is to assign
  • 22. a weight= to each criterion. Answer: Question 51 Marks: 1 Some people might use a contract in place of a charter. Answer: Question 52 Marks: 1 The ____ step in the planning process is to tie the information technology strategic plan to the organization’s overall strategic p= lan. Choose one answer. a. first b. second c. third d. fourth Question 53 Marks: 1
  • 23. Project management plans document project planning assumptions and decisi= ons regarding choices. Answer: Question 54 Marks: 1 In addition to progress reports, an important tool for monitoring and controlling a project is using project management software. Answer: Question 55 Marks: 1 ____ include devising and maintaining a workable scheme to ensure that th= e project addresses the organization’s needs. Choose one answer. a. Initiating processes b. Planning processes c. Executing processes d. Monitoring and controlling processes = Question 56 Marks: 1
  • 24. A/An ____ is a document used to coordinate all project planning documents= and help guide a project’s execution and control. Choose one answer. a. project management plan b. statement of work c. scope statement d. contact Question 57 Marks: 1 In the ____ information technology planning stage, the analysis outlines business processes that are central to achieving strategic goals and helps determine which ones could most benefit from information technology. Choose one answer. a. Project Planning b. Business Area Analysis c. Resource Allocation d. Information Technology Strategy Planning = Question 58 Marks: 1
  • 25. Initiating processes take place during each phase of a project. Answer: Question 59 Marks: 1 Directing and managing project execution involves carrying out the project management plan by performing the activities included in it. Answer: Question 60 Marks: 1 A ____ is an approach to help increase the support of stakeholders throug= hout the project. Choose one answer. a. stakeholder management plan <= /label> b. stakeholder strategy c. stakeholder management strategy = d. stakeholder management list <= /label> Question 61
  • 26. Marks: 1 The ____ process involves gaining stakeholder and customer acceptance of the final products and services and bringing the project, or project phase, to an orderly end. Choose one answer. a. ending b. closing c. developing d. completing Question 62 Marks: 1 ____ ensures that the descriptions of the project’s products are = correct and complete. Choose one answer. a. CCB b. Correction management c. Configuration management d. Product description management = Question 63 Marks: 1
  • 27. In the ____ stage of selecting information technology projects, organizat= ions define project scope, benefits, and constraints. Choose one answer. a. Project Planning b. Business Area Analysis c. Resource Allocation d. Information Technology Strategy Planning = Question 64 Marks: 1 On large projects, many project managers say that ____ percent of the job= is communicating and managing changes. Choose one answer. a. 50 b. 70 c. 90 d. 100 Question 65 Marks: 1 It is good practice to focus on the ____ of meetings.
  • 28. Choose one answer. a. flow b. planning c. agenda d. results Question 66 Marks: 1 The process of acquiring a project team falls under the Project Human Res= ource Management knowledge area. Answer: Question 67 Marks: 1 ____ is an iterative software development process that focuses on team productivity and delivers software best practices to all team members. Choose one answer. a. RAP b. RIP c. RUP
  • 29. d. ROP Question 68 Marks: 1 An annual discount factor is a multiplier for each year based on the disc= ount rate and year. Answer: Question 69 Marks: 1 In the long-term view, it is better to have a huge success on an unimportant project than to have a moderate success on an important project. Answer: Question 70 Marks: 1 ____ involves coordinating all planning efforts to create a consistent, c= oherent document. Choose one answer. a. Developing the project charter = b. Developing the preliminary project scope statement=
  • 30. c. Developing the project management plan = d. Directing and managing project execution = Question 71 Marks: 1 ____ should serve as the foundation for deciding which projects to pursue= . Choose one answer. a. Strategic planning b. Project managers c. Successful past projects d. Employee abilities Question 72 Marks: 1 The level of activity and length of each process group varies for every p= roject. Answer: Question 73 Marks: 1
  • 31. Examples of ____ include acquiring and developing the project team, performing quality assurance, distributing information, managing stakeholder expectations, and conducting procurements. Choose one answer. a. monitoring and controlling processes = b. executing processes c. planning processes d. initiating processes Question 74 Marks: 1 The project communications management knowledge area maps to the ____ process group through the activity of information distribution. Choose one answer. a. initiating b. planning c. executing d. monitoring and controlling </= label> Question 75 Marks: 1
  • 32. Many people are familiar with SWOT analysis—analyzing Strengths,= Weaknesses, Opportunities, and Threats—which is used to aid in ____= . Choose one answer. a. project initiation b. project planning c. strategic planning d. strategic initiation =