SlideShare a Scribd company logo
1 of 15
Execution of a
Pump Installation
in an Industry
Execution, Commissioning
& Testing of Installation
Team 7
Sec A & B
Aishwarya Kohad
21020741083
Harender Singh
21020741099 Upendranath Reddy
21020741127
Shankruth Verma
21020741133
Abhishek Kumar
21020741082
Keyur Tandel
21020741032 Pavan Kumar Kandi
21020741031
Prince Kumar Singh
21020741051
Shubham Mitra
21020741065
Sunil Menaria
21020741070
2
Project Charter
Location: Plant Methodology:
Team Leader: Facilitator: Dr. Sandeep Sharda
Project Title: Installation of a motor for a pump in an Industry
Execution, Commissioning & Testing of a Pump Installation in an Industry
Business Case Opportunity Statement
Incorrect wiring, the pump is not properly
grounded, Low Power, Improperly installed
check valve, Pump not primed, Improper pump
and motor alignment, Not enough room for the
float switch
Successfully install centrifugal pump with all
the necessary equipment such as, an electric
motor, piping layout, mechanical seals etc.
Goal Statement Objective & Business impact
 Pump installation will boost the productivity
of the setup.
 The downtime for the process will drastically
reduce.
 With a newer setup lesser maintenance will
be required.
 Higher efficiency of work posts the pump
installation in industry.
Assumptions - Motor and Pump already
purchased and readily available
Execution of plans - In MSP not only time but
resources and task prerequisites are also
mentioned to ensure a smoother flow of
activities.
MSP Project Timeline - Dividing the full
project till level 3-Activity-based and ensuring
proper timings for project completion
Team Members Project Timeline
Mentor – Dr. Sandeep
Sharda
Members – Prince,
Shankruth, Sunil, Pavan,
Shubham, Upendra,
Harendra, Aishwarya,
Keyur, Abhishek
Start – 14.12.2022
End – 06.01.2023
Benefits to External
Customer
Training Request
 Increased Productivity
 Reduced Downtime
 Less Maintenance
 High Efficiency of Work
Guidance and
training to be
given to operator.
Approval
Project Sponsor:
________________
Date:
________________
Prince
3
Objectives of Project
Execution, Commissioning & Testing of a Pump Installation in an Industry
01
Assumptions
1. Project Start date: 29th
November 2022
2. Motor and Pump already
purchased and readily
available
03
Execution of plans
In MSP not only time but
resources and task
prerequisites are also
mentioned to ensure a
smoother flow of activities.
02
MSP Project
Timeline
Dividing the full project till
level 3- Activity-based and
ensuring proper timings for
project completion
Pump Installation
Pavan
4
Scope of Work
 Testing and commissioning of
the pump & motor
 Documentation of all the testing
result
 Handing over the project to
client
Commissioning
 Understanding of the Project
 Requirement Gathering
 Checking the feasibility of the
project
 Design of Pump Installation
Layout
 Development as per the design
Engineering
 Land Clearance Document
 Manpower Legal Compliance
 Eligibility of the sub-contractor
 Pump design clearance as per
the government norms
Legal
 Issue of proper PPE kit
 Proper care of health and
safety of worker
 Maintenance of tools, machine
and equipment
 Schedule maintenance of
electrical equipment
Safety
 Financial Compliance. Checking
the financial capability of the
supplier, subcontractor
Finances
 Installation of instrument
 Cabling & power supply to
motor
Electrical
 Erection of Pump as per design
 Installation of pump
 Civil Design as per the land
layout
 Construction as per design
Mechanical & Civil
Working agreement for Execution, Commissioning & Testing of a Pump Installation
Upen
5
Organisational Structure
General
Manager
Sales &
Business
Development
Director
Supply Chain
Manager
Manufacturing
Manager
Engineering
Manager
IT Department
Quality
Manager
HR & Financial
Manager
Maintenance
Manager
Sales
Department
Supply chain
Department
Manufacturing
Department
Engineering
Department
Mechanical
Engineering
Civil
Department
Electrical
Department
Quality
Control
Technician
Site
Supervisor
Helper Mason
Aishwarya
6
Responsibility Matrix
RACI Matrix Activities
Plant
Head
Project
Manager
Maintenance
Manager
Electrical
Engineer
Civil
Engineer
Safety
Officer
Regulatory
Officer
Procurement
Manager
Finance
Head
Understanding of the Project A R C C C I C C C
Requirement Gathering I R A C C I I I I
Checking the feasibility of the project I R A R R C I I I
Design of Pump Installation Layout I A R C C C C C I
Development as per the design I A R C C I I I I
Erection of Pump as per design I A R C R C I I I
Installation of pump I A R R C I I I I
Civil Design as per the land layout I A C C R C C I I
Construction as per design I A C I R C C I C
Installation of instrument I A R R C C I I I
Cabling & power supply to motor I A C R I C I I I
Testing and commissioning of the pump & motor I A R R R C I I I
Documentation of all the testing result I R A C I I I I I
Handing over the project to client I R A C I I I I I
Land Clearance Document I A I I C I R I I
Manpower Legal Compliance C A I I I I R I I
Eligibility of the sub-contractor C A I I I I R I I
Pump design clearance as per the government norms I A C C I I R I I
Purchasing of pump I A C C I I I R I
Procurement of the Civil, mechanical & electrical material I A C C C I I R C
Procurement/Rent of tools, machine & Safety wear I A C C C C I R C
Financial Compliance I A I I I I C I R
Checking the financial capability of the supplier, subcontractor I A I I I I I C R
Issue of proper PPE kit I A C C C R I C I
Proper care of health and safety of worker C A I I I R I I I
Maintenance of tools, machine and equipment I A C C I R I I I
Schedule maintenance of electrical equipment I A C C I R I I I
Execution, Commissioning & Testing of a
Pump Installation
Responsible
Accountable
Consult
Inform
Stakeholders Involved
 Plant Head
 Project Manager
 Maintenance Manager
 Electrical Engineer
 Civil Engineer
 Safety Officer
 Regulatory Officer
 Procurement Manager
 Finance Head
Shankruth
7
Pump Installation
Civil
Site grading &
marking, Excavation
of Foundation,
Dewatering, RCC,
Curing and Material
removal
Instrumentation
Seal box installation,
instrument testing and
handing over to
process
Mechanical
Pump shifting and
positioning, pump
leveling, alignment
and Pump Coupling
Electrical
Motor Shifting and
positioning, motor
alignment, site
connection, coupling
connection and load
test
Commission &
Handover
Full load testing,
punch point, cleaning,
boxing and Handover
Level 1
Level 2
Level 3
Work Breakdown Structure
Activity Level
Shubham
8
Timeline of Project
The project work started on 29th November 2022
Site grading &
marking,
Excavation of
Foundation,
Dewatering, RCC,
Curing and
Material removal
Civil Work
14th
Dec’22
Pump shifting and
positioning, pump
levelling, alignment
and Pump
Coupling
Mechanical
Work
23rd
Dec’22
Motor Shifting and
positioning, motor
alignment, site
connection,
coupling
connection and
load test
Electrical Work
27th
Dec’22
Seal box
installation,
instrument testing
and handing over
to process
Instrumental
Work
30th
Dec’22
Full load testing,
punch point,
cleaning, boxing
and Handover
Commissioning,
Testing, and
Handover Work
06th
Jan’22
18th
Dec’22
27rd
Dec’22
1st
Jan’22
7th
Jan’22
13th
Jan’22
Haren
9
Resource Cost Overview
Resource Name Type
Material
Label
Std. Rate Ovt. Rate
Motor Material Unit
Pump Material Unit
Cement Material Bags ₹ 500.00
Saria 12MM Material Kg ₹ 102.00
Saria 8MM Material Kg ₹ 96.00
Coarse Aggregator Material kg ₹ 40.00
Mechanical Engineer Work ₹ 2,000.00/day ₹ 200.00/hr
Civil Engineer Work ₹ 2,000.00/day ₹ 200.00/hr
Mason (Class-A) Work ₹ 700.00/day ₹ 100.00/hr
Mason (Class-B) Work ₹ 400.00/day ₹ 50.00/hr
Helper Work ₹ 300.00/day ₹ 50.00/hr
Site Supervisor Work ₹ 2,300.00/day ₹ 300.00/hr
Water Tanker Material Unit ₹ 600.00
Concrete Mixer Work ₹ 5,000.00/day ₹ 0.00/hr
Forklift Work ₹ 2,500.00/day ₹ 0.00/hr
JCB Work ₹ 5,000.00/day ₹ 0.00/hr
Electrical Engineer Work ₹ 2,200.00/day ₹ 0.00/hr
Technician Work ₹ 1,100.00/day ₹ 0.00/hr
Cable 2.5MM Material Meter
Seal box Material Unit
MCB Material Unit
Insulators Material Unit
₹ 0.00
₹ 5,000.00
₹ 10,000.00
₹ 15,000.00
₹ 20,000.00
₹ 25,000.00
Actual Cost Remaining Cost Baseline Cost
Cost Status
Cost
Distribution
Type Total
Work 90050
Material 233620
Grand Total 323670
Haren
10
Cash Flows
Actual Cost
₹ 3,23,670.00
Cost Variance
₹ 22,010.00
Baseline Cost
₹ 3,01,660.00
₹ 0.00
₹ 50,000.00
₹ 100,000.00
₹ 150,000.00
₹ 200,000.00
₹ 250,000.00
₹ 300,000.00
₹ 350,000.00
4 1
Cost Cumulative Cost
The chart shows the project's
cumulative cost and the cost
per quarter.
₹ 2,90,520.00
Actual cost of work performed
ACWP
₹ 2,71,010.00
Budgeted cost of work performed
BCWP
₹ 2,71,010.00
Budgeted cost of work scheduled
BCWS
0
50000
100000
150000
200000
250000
Work Material
Execute commissioning and testing of a
pump installation in an industry
Pump Installation
Cost
Baseline Cost Report
Baseline Cost Cost Actual Cost
Haren
11
Earned Value
EAC
₹ 3,23,376.65
BCWP
₹ 2,71,010.00
ACWP
₹ 2,90,520.00
₹ 0.00
₹ 50,000.00
₹ 100,000.00
₹ 150,000.00
₹ 200,000.00
₹ 250,000.00
₹ 300,000.00
₹ 350,000.00
'22 '22 '22 '22 '22 '23
ACWP BCWP BCWS
The project is over budgeted, and the project is behind schedule.
-₹ 40,000.00
-₹ 20,000.00
₹ 0.00
₹ 20,000.00
₹ 40,000.00
₹ 60,000.00
₹ 80,000.00
₹ 100,000.00
'22 '22 '22 '22 '22 '23
CV SV
VARIANCE OVER TIME
Cost Variance is negative, project is over budget.
Schedule Variance is positive, project is behind schedule.
Keyur
12
Appraisals of Project
Committing to Pump Lifecycle Enhancement can Save Money and Drive Performance
4/5
Increased
Productivity
Pump installation will
boost the
productivity of the
setup.
3/5
Reduced
Downtime
The downtime for the
process will
drastically reduce.
4/5
Less
Maintenace
With a newer setup
lesser maintenance
will be required.
5/5
High Efficiency
of Work
Higher efficiency of
work post the pump
installation in
industry
Abhishek
13
Risks of Project
Work at very high velocity and pressure
01
Pump should be securely anchored and should
have plenty of clearance
02
Internal parts need to be maintained
04
Check for Air Leaks, Suction Line Blockage
05
Check for and Replace Worn-out Components
and worn suction line fittings and pipe plugs
03
Inspecting pump components before and after
installation
06
Check Discharge Lines for the installation
purposes
07
Make the Pump Accessible (size, fitment and
other related risks)
08
If the pump is located underground, follow
confined space entry procedures.
10
Use the Pump for Its Designated Use for the
installation front
09
Sunil
14
Constraints of Project
01
Electrical
Issues
Incorrect wiring,
The pump is not
properly
grounded, Low
Power
02
Plumbing
Problems
Improperly
installed check
valve, Pump not
primed
03
General
Problems
Improper pump
and motor
alignment, Not
enough room for
the float switch
Major Issues
Sunil
15
Do you have any questions?
Thanks
harender.singh@siom.in
+91 9812969049
Connect with us:
Team 7
Sec A & B
Aishwarya Kohad
21020741083
Harender Singh
21020741099 Upendranath Reddy
21020741127
Shankruth Verma
21020741133
Abhishek Kumar
21020741082
Keyur Tandel
21020741032 Pavan Kumar Kandi
21020741031
Prince Kumar Singh
21020741051
Shubham Mitra
21020741065
Sunil Menaria
21020741070

More Related Content

What's hot

Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updatedPersonal Secret
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil worksMuhammad Shahid
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoignitetribes
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installationslaithu2908
 
Contractor's _obligation.ppt
Contractor's _obligation.pptContractor's _obligation.ppt
Contractor's _obligation.pptBimal Chandra Das
 
Health/Safety and facilities for contractor personnel under FIDIC
Health/Safety and facilities for contractor personnel under FIDICHealth/Safety and facilities for contractor personnel under FIDIC
Health/Safety and facilities for contractor personnel under FIDICnaeem khan
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...John Buchovecky
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5Moustafa Ismail Abu Dief
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
Prequalification document(1)
Prequalification document(1)Prequalification document(1)
Prequalification document(1)Muhammad Akram
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan David H Moloney
 
Ss 06 training fidic moustafa ismail 2018 _ lec 6
Ss 06 training fidic moustafa ismail  2018 _ lec 6Ss 06 training fidic moustafa ismail  2018 _ lec 6
Ss 06 training fidic moustafa ismail 2018 _ lec 6Moustafa Ismail Abu Dief
 

What's hot (20)

Why EPC
Why EPCWhy EPC
Why EPC
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil works
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
110921 commissioning of offshore installations
110921 commissioning of offshore installations110921 commissioning of offshore installations
110921 commissioning of offshore installations
 
Siyabonga Dywili Detailed CV
Siyabonga Dywili Detailed CVSiyabonga Dywili Detailed CV
Siyabonga Dywili Detailed CV
 
Contractor's _obligation.ppt
Contractor's _obligation.pptContractor's _obligation.ppt
Contractor's _obligation.ppt
 
Chiller ppt
Chiller pptChiller ppt
Chiller ppt
 
Health/Safety and facilities for contractor personnel under FIDIC
Health/Safety and facilities for contractor personnel under FIDICHealth/Safety and facilities for contractor personnel under FIDIC
Health/Safety and facilities for contractor personnel under FIDIC
 
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...Engineering, Procurement and Construction Contracts for Infrastructure Projec...
Engineering, Procurement and Construction Contracts for Infrastructure Projec...
 
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5Ss 5 training fidic Dr. Moustafa Ismail  2017 _ lec 5
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
Prequalification document(1)
Prequalification document(1)Prequalification document(1)
Prequalification document(1)
 
Epc contractor
Epc contractorEpc contractor
Epc contractor
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
 
Compressor ppt
Compressor pptCompressor ppt
Compressor ppt
 
Ppt on fidic claims
Ppt on fidic claimsPpt on fidic claims
Ppt on fidic claims
 
Ss 06 training fidic moustafa ismail 2018 _ lec 6
Ss 06 training fidic moustafa ismail  2018 _ lec 6Ss 06 training fidic moustafa ismail  2018 _ lec 6
Ss 06 training fidic moustafa ismail 2018 _ lec 6
 
Hvac
HvacHvac
Hvac
 

Similar to Project Management: Execution of a Pump Installation in an Industry - Execution, Commissioning & Testing of Installation

QA/QC INSPECTION ENGINEER
QA/QC INSPECTION ENGINEERQA/QC INSPECTION ENGINEER
QA/QC INSPECTION ENGINEERMOHAMMED ZUBAIR
 
Electrical & Instrument Engineer
Electrical & Instrument EngineerElectrical & Instrument Engineer
Electrical & Instrument EngineerMukhtar Ahmad
 
NEW UPDATE CV QC ROTATING & STATIC
NEW UPDATE CV QC ROTATING & STATICNEW UPDATE CV QC ROTATING & STATIC
NEW UPDATE CV QC ROTATING & STATICRoy Encallado
 
NEW UPDATE CV QC ROTATING & STATIC
NEW UPDATE CV QC ROTATING & STATICNEW UPDATE CV QC ROTATING & STATIC
NEW UPDATE CV QC ROTATING & STATICRoy Encallado
 
Profile Details (CV)
Profile Details (CV)Profile Details (CV)
Profile Details (CV)Kunal Saha
 
Huzoor-_feb_20091 CV (2)
Huzoor-_feb_20091 CV (2)Huzoor-_feb_20091 CV (2)
Huzoor-_feb_20091 CV (2)Huzoor Ahmed
 
Huzoor-_feb_20091 CV (2)
Huzoor-_feb_20091 CV (2)Huzoor-_feb_20091 CV (2)
Huzoor-_feb_20091 CV (2)Huzoor Ahmed
 
Leo Doc (CV)A(Mechanical Supervisor)
Leo Doc (CV)A(Mechanical Supervisor)Leo Doc (CV)A(Mechanical Supervisor)
Leo Doc (CV)A(Mechanical Supervisor)Leonardo David
 
CV _Shaju Palissery Bhaskaran.DOC
CV _Shaju Palissery Bhaskaran.DOCCV _Shaju Palissery Bhaskaran.DOC
CV _Shaju Palissery Bhaskaran.DOCshaju palissery
 
CV of Mohammad Mujeebuddin - PMO QA Manager
CV of Mohammad Mujeebuddin - PMO QA ManagerCV of Mohammad Mujeebuddin - PMO QA Manager
CV of Mohammad Mujeebuddin - PMO QA ManagerMujeebuddin Mohammad
 
cv_piping engineer updated
cv_piping engineer updatedcv_piping engineer updated
cv_piping engineer updatedAnwar Alam
 

Similar to Project Management: Execution of a Pump Installation in an Industry - Execution, Commissioning & Testing of Installation (20)

QA/QC INSPECTION ENGINEER
QA/QC INSPECTION ENGINEERQA/QC INSPECTION ENGINEER
QA/QC INSPECTION ENGINEER
 
Electrical & Instrument Engineer
Electrical & Instrument EngineerElectrical & Instrument Engineer
Electrical & Instrument Engineer
 
NEW UPDATE CV QC ROTATING & STATIC
NEW UPDATE CV QC ROTATING & STATICNEW UPDATE CV QC ROTATING & STATIC
NEW UPDATE CV QC ROTATING & STATIC
 
NEW UPDATE CV QC ROTATING & STATIC
NEW UPDATE CV QC ROTATING & STATICNEW UPDATE CV QC ROTATING & STATIC
NEW UPDATE CV QC ROTATING & STATIC
 
Profile Details (CV)
Profile Details (CV)Profile Details (CV)
Profile Details (CV)
 
A.H.K.C.V.NEW (2)
A.H.K.C.V.NEW (2)A.H.K.C.V.NEW (2)
A.H.K.C.V.NEW (2)
 
Huzoor-_feb_20091 CV (2)
Huzoor-_feb_20091 CV (2)Huzoor-_feb_20091 CV (2)
Huzoor-_feb_20091 CV (2)
 
Huzoor-_feb_20091 CV (2)
Huzoor-_feb_20091 CV (2)Huzoor-_feb_20091 CV (2)
Huzoor-_feb_20091 CV (2)
 
QA.QC E&I feb
QA.QC E&I febQA.QC E&I feb
QA.QC E&I feb
 
M Imran
M ImranM Imran
M Imran
 
Leo Doc (CV)A(Mechanical Supervisor)
Leo Doc (CV)A(Mechanical Supervisor)Leo Doc (CV)A(Mechanical Supervisor)
Leo Doc (CV)A(Mechanical Supervisor)
 
Siddharth_resume_Engg.
Siddharth_resume_Engg.Siddharth_resume_Engg.
Siddharth_resume_Engg.
 
Rajesh CV -
Rajesh CV - Rajesh CV -
Rajesh CV -
 
CV _Shaju Palissery Bhaskaran.DOC
CV _Shaju Palissery Bhaskaran.DOCCV _Shaju Palissery Bhaskaran.DOC
CV _Shaju Palissery Bhaskaran.DOC
 
Instrumentation Inspector
Instrumentation InspectorInstrumentation Inspector
Instrumentation Inspector
 
CV Chenna
CV ChennaCV Chenna
CV Chenna
 
CV of Mohammad Mujeebuddin - PMO QA Manager
CV of Mohammad Mujeebuddin - PMO QA ManagerCV of Mohammad Mujeebuddin - PMO QA Manager
CV of Mohammad Mujeebuddin - PMO QA Manager
 
Piping Welding Engineer
Piping Welding EngineerPiping Welding Engineer
Piping Welding Engineer
 
Aftab CV.
Aftab CV.Aftab CV.
Aftab CV.
 
cv_piping engineer updated
cv_piping engineer updatedcv_piping engineer updated
cv_piping engineer updated
 

More from Harender Singh

Alpha : Challenges in consulting industry
Alpha : Challenges in consulting industryAlpha : Challenges in consulting industry
Alpha : Challenges in consulting industryHarender Singh
 
Amazon case study: Amazon prime air - A delivery by aerial drone project
Amazon case study: Amazon prime air - A delivery by aerial drone projectAmazon case study: Amazon prime air - A delivery by aerial drone project
Amazon case study: Amazon prime air - A delivery by aerial drone projectHarender Singh
 
E-Business Operations: A case study on infoedge-naukri.com
E-Business Operations: A case study on infoedge-naukri.comE-Business Operations: A case study on infoedge-naukri.com
E-Business Operations: A case study on infoedge-naukri.comHarender Singh
 
Creativity and Design Thinking Project
Creativity and Design Thinking ProjectCreativity and Design Thinking Project
Creativity and Design Thinking ProjectHarender Singh
 
Creativity and Design Thinking Project
Creativity and Design Thinking ProjectCreativity and Design Thinking Project
Creativity and Design Thinking ProjectHarender Singh
 
Digital Transformation: A case study on tata steel
Digital Transformation: A case study on tata steelDigital Transformation: A case study on tata steel
Digital Transformation: A case study on tata steelHarender Singh
 
Circular Design Strategies: A case of mahindra to make it circular
Circular Design Strategies: A case of mahindra to make it circularCircular Design Strategies: A case of mahindra to make it circular
Circular Design Strategies: A case of mahindra to make it circularHarender Singh
 
Blockchain project: e-voting system based upon blockchain technology
Blockchain project: e-voting system based upon blockchain technologyBlockchain project: e-voting system based upon blockchain technology
Blockchain project: e-voting system based upon blockchain technologyHarender Singh
 
Payment for exports and export promotion scheme
Payment for exports and export promotion schemePayment for exports and export promotion scheme
Payment for exports and export promotion schemeHarender Singh
 
A bibliometric analysis on cost and risk estimation in DevOps project menthod...
A bibliometric analysis on cost and risk estimation in DevOps project menthod...A bibliometric analysis on cost and risk estimation in DevOps project menthod...
A bibliometric analysis on cost and risk estimation in DevOps project menthod...Harender Singh
 
Mock Investor Summit - 2022
Mock Investor Summit - 2022Mock Investor Summit - 2022
Mock Investor Summit - 2022Harender Singh
 
Hypothesis Testing - Continuous Normal Data (Y) and Variance tests with exam...
Hypothesis Testing - Continuous Normal Data (Y) and  Variance tests with exam...Hypothesis Testing - Continuous Normal Data (Y) and  Variance tests with exam...
Hypothesis Testing - Continuous Normal Data (Y) and Variance tests with exam...Harender Singh
 
Responsive supply chain: sensitive to customer requirements
Responsive supply chain: sensitive to customer requirementsResponsive supply chain: sensitive to customer requirements
Responsive supply chain: sensitive to customer requirementsHarender Singh
 
Essential of Marketing Management: StartUp Idea
Essential of Marketing Management: StartUp IdeaEssential of Marketing Management: StartUp Idea
Essential of Marketing Management: StartUp IdeaHarender Singh
 
Inventory Control Techniques
Inventory Control TechniquesInventory Control Techniques
Inventory Control TechniquesHarender Singh
 
Supply chain management case study :Toyota and its component Suppliers
Supply chain management case study :Toyota and its component SuppliersSupply chain management case study :Toyota and its component Suppliers
Supply chain management case study :Toyota and its component SuppliersHarender Singh
 
Operations research within UK healthcare: A review
Operations research within UK healthcare: A reviewOperations research within UK healthcare: A review
Operations research within UK healthcare: A reviewHarender Singh
 
Business Statistics | Understanding business for Alliance data
Business Statistics | Understanding business for Alliance dataBusiness Statistics | Understanding business for Alliance data
Business Statistics | Understanding business for Alliance dataHarender Singh
 
Ice House Toys case study
Ice House Toys case studyIce House Toys case study
Ice House Toys case studyHarender Singh
 

More from Harender Singh (20)

Alpha : Challenges in consulting industry
Alpha : Challenges in consulting industryAlpha : Challenges in consulting industry
Alpha : Challenges in consulting industry
 
Amazon case study: Amazon prime air - A delivery by aerial drone project
Amazon case study: Amazon prime air - A delivery by aerial drone projectAmazon case study: Amazon prime air - A delivery by aerial drone project
Amazon case study: Amazon prime air - A delivery by aerial drone project
 
E-Business Operations: A case study on infoedge-naukri.com
E-Business Operations: A case study on infoedge-naukri.comE-Business Operations: A case study on infoedge-naukri.com
E-Business Operations: A case study on infoedge-naukri.com
 
Creativity and Design Thinking Project
Creativity and Design Thinking ProjectCreativity and Design Thinking Project
Creativity and Design Thinking Project
 
Creativity and Design Thinking Project
Creativity and Design Thinking ProjectCreativity and Design Thinking Project
Creativity and Design Thinking Project
 
Digital Transformation: A case study on tata steel
Digital Transformation: A case study on tata steelDigital Transformation: A case study on tata steel
Digital Transformation: A case study on tata steel
 
Circular Design Strategies: A case of mahindra to make it circular
Circular Design Strategies: A case of mahindra to make it circularCircular Design Strategies: A case of mahindra to make it circular
Circular Design Strategies: A case of mahindra to make it circular
 
Blockchain project: e-voting system based upon blockchain technology
Blockchain project: e-voting system based upon blockchain technologyBlockchain project: e-voting system based upon blockchain technology
Blockchain project: e-voting system based upon blockchain technology
 
Business Analytics
Business AnalyticsBusiness Analytics
Business Analytics
 
Payment for exports and export promotion scheme
Payment for exports and export promotion schemePayment for exports and export promotion scheme
Payment for exports and export promotion scheme
 
A bibliometric analysis on cost and risk estimation in DevOps project menthod...
A bibliometric analysis on cost and risk estimation in DevOps project menthod...A bibliometric analysis on cost and risk estimation in DevOps project menthod...
A bibliometric analysis on cost and risk estimation in DevOps project menthod...
 
Mock Investor Summit - 2022
Mock Investor Summit - 2022Mock Investor Summit - 2022
Mock Investor Summit - 2022
 
Hypothesis Testing - Continuous Normal Data (Y) and Variance tests with exam...
Hypothesis Testing - Continuous Normal Data (Y) and  Variance tests with exam...Hypothesis Testing - Continuous Normal Data (Y) and  Variance tests with exam...
Hypothesis Testing - Continuous Normal Data (Y) and Variance tests with exam...
 
Responsive supply chain: sensitive to customer requirements
Responsive supply chain: sensitive to customer requirementsResponsive supply chain: sensitive to customer requirements
Responsive supply chain: sensitive to customer requirements
 
Essential of Marketing Management: StartUp Idea
Essential of Marketing Management: StartUp IdeaEssential of Marketing Management: StartUp Idea
Essential of Marketing Management: StartUp Idea
 
Inventory Control Techniques
Inventory Control TechniquesInventory Control Techniques
Inventory Control Techniques
 
Supply chain management case study :Toyota and its component Suppliers
Supply chain management case study :Toyota and its component SuppliersSupply chain management case study :Toyota and its component Suppliers
Supply chain management case study :Toyota and its component Suppliers
 
Operations research within UK healthcare: A review
Operations research within UK healthcare: A reviewOperations research within UK healthcare: A review
Operations research within UK healthcare: A review
 
Business Statistics | Understanding business for Alliance data
Business Statistics | Understanding business for Alliance dataBusiness Statistics | Understanding business for Alliance data
Business Statistics | Understanding business for Alliance data
 
Ice House Toys case study
Ice House Toys case studyIce House Toys case study
Ice House Toys case study
 

Recently uploaded

Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceDamini Dixit
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwaitdaisycvs
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLJAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Sheetaleventcompany
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...allensay1
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noidadlhescort
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPanhandleOilandGas
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 MonthsIndeedSEO
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 

Recently uploaded (20)

Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort ServiceMalegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
Malegaon Call Girls Service ☎ ️82500–77686 ☎️ Enjoy 24/7 Escort Service
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLJAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
JAYNAGAR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 MonthsSEO Case Study: How I Increased SEO Traffic & Ranking by 50-60%  in 6 Months
SEO Case Study: How I Increased SEO Traffic & Ranking by 50-60% in 6 Months
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 

Project Management: Execution of a Pump Installation in an Industry - Execution, Commissioning & Testing of Installation

  • 1. Execution of a Pump Installation in an Industry Execution, Commissioning & Testing of Installation Team 7 Sec A & B Aishwarya Kohad 21020741083 Harender Singh 21020741099 Upendranath Reddy 21020741127 Shankruth Verma 21020741133 Abhishek Kumar 21020741082 Keyur Tandel 21020741032 Pavan Kumar Kandi 21020741031 Prince Kumar Singh 21020741051 Shubham Mitra 21020741065 Sunil Menaria 21020741070
  • 2. 2 Project Charter Location: Plant Methodology: Team Leader: Facilitator: Dr. Sandeep Sharda Project Title: Installation of a motor for a pump in an Industry Execution, Commissioning & Testing of a Pump Installation in an Industry Business Case Opportunity Statement Incorrect wiring, the pump is not properly grounded, Low Power, Improperly installed check valve, Pump not primed, Improper pump and motor alignment, Not enough room for the float switch Successfully install centrifugal pump with all the necessary equipment such as, an electric motor, piping layout, mechanical seals etc. Goal Statement Objective & Business impact  Pump installation will boost the productivity of the setup.  The downtime for the process will drastically reduce.  With a newer setup lesser maintenance will be required.  Higher efficiency of work posts the pump installation in industry. Assumptions - Motor and Pump already purchased and readily available Execution of plans - In MSP not only time but resources and task prerequisites are also mentioned to ensure a smoother flow of activities. MSP Project Timeline - Dividing the full project till level 3-Activity-based and ensuring proper timings for project completion Team Members Project Timeline Mentor – Dr. Sandeep Sharda Members – Prince, Shankruth, Sunil, Pavan, Shubham, Upendra, Harendra, Aishwarya, Keyur, Abhishek Start – 14.12.2022 End – 06.01.2023 Benefits to External Customer Training Request  Increased Productivity  Reduced Downtime  Less Maintenance  High Efficiency of Work Guidance and training to be given to operator. Approval Project Sponsor: ________________ Date: ________________ Prince
  • 3. 3 Objectives of Project Execution, Commissioning & Testing of a Pump Installation in an Industry 01 Assumptions 1. Project Start date: 29th November 2022 2. Motor and Pump already purchased and readily available 03 Execution of plans In MSP not only time but resources and task prerequisites are also mentioned to ensure a smoother flow of activities. 02 MSP Project Timeline Dividing the full project till level 3- Activity-based and ensuring proper timings for project completion Pump Installation Pavan
  • 4. 4 Scope of Work  Testing and commissioning of the pump & motor  Documentation of all the testing result  Handing over the project to client Commissioning  Understanding of the Project  Requirement Gathering  Checking the feasibility of the project  Design of Pump Installation Layout  Development as per the design Engineering  Land Clearance Document  Manpower Legal Compliance  Eligibility of the sub-contractor  Pump design clearance as per the government norms Legal  Issue of proper PPE kit  Proper care of health and safety of worker  Maintenance of tools, machine and equipment  Schedule maintenance of electrical equipment Safety  Financial Compliance. Checking the financial capability of the supplier, subcontractor Finances  Installation of instrument  Cabling & power supply to motor Electrical  Erection of Pump as per design  Installation of pump  Civil Design as per the land layout  Construction as per design Mechanical & Civil Working agreement for Execution, Commissioning & Testing of a Pump Installation Upen
  • 5. 5 Organisational Structure General Manager Sales & Business Development Director Supply Chain Manager Manufacturing Manager Engineering Manager IT Department Quality Manager HR & Financial Manager Maintenance Manager Sales Department Supply chain Department Manufacturing Department Engineering Department Mechanical Engineering Civil Department Electrical Department Quality Control Technician Site Supervisor Helper Mason Aishwarya
  • 6. 6 Responsibility Matrix RACI Matrix Activities Plant Head Project Manager Maintenance Manager Electrical Engineer Civil Engineer Safety Officer Regulatory Officer Procurement Manager Finance Head Understanding of the Project A R C C C I C C C Requirement Gathering I R A C C I I I I Checking the feasibility of the project I R A R R C I I I Design of Pump Installation Layout I A R C C C C C I Development as per the design I A R C C I I I I Erection of Pump as per design I A R C R C I I I Installation of pump I A R R C I I I I Civil Design as per the land layout I A C C R C C I I Construction as per design I A C I R C C I C Installation of instrument I A R R C C I I I Cabling & power supply to motor I A C R I C I I I Testing and commissioning of the pump & motor I A R R R C I I I Documentation of all the testing result I R A C I I I I I Handing over the project to client I R A C I I I I I Land Clearance Document I A I I C I R I I Manpower Legal Compliance C A I I I I R I I Eligibility of the sub-contractor C A I I I I R I I Pump design clearance as per the government norms I A C C I I R I I Purchasing of pump I A C C I I I R I Procurement of the Civil, mechanical & electrical material I A C C C I I R C Procurement/Rent of tools, machine & Safety wear I A C C C C I R C Financial Compliance I A I I I I C I R Checking the financial capability of the supplier, subcontractor I A I I I I I C R Issue of proper PPE kit I A C C C R I C I Proper care of health and safety of worker C A I I I R I I I Maintenance of tools, machine and equipment I A C C I R I I I Schedule maintenance of electrical equipment I A C C I R I I I Execution, Commissioning & Testing of a Pump Installation Responsible Accountable Consult Inform Stakeholders Involved  Plant Head  Project Manager  Maintenance Manager  Electrical Engineer  Civil Engineer  Safety Officer  Regulatory Officer  Procurement Manager  Finance Head Shankruth
  • 7. 7 Pump Installation Civil Site grading & marking, Excavation of Foundation, Dewatering, RCC, Curing and Material removal Instrumentation Seal box installation, instrument testing and handing over to process Mechanical Pump shifting and positioning, pump leveling, alignment and Pump Coupling Electrical Motor Shifting and positioning, motor alignment, site connection, coupling connection and load test Commission & Handover Full load testing, punch point, cleaning, boxing and Handover Level 1 Level 2 Level 3 Work Breakdown Structure Activity Level Shubham
  • 8. 8 Timeline of Project The project work started on 29th November 2022 Site grading & marking, Excavation of Foundation, Dewatering, RCC, Curing and Material removal Civil Work 14th Dec’22 Pump shifting and positioning, pump levelling, alignment and Pump Coupling Mechanical Work 23rd Dec’22 Motor Shifting and positioning, motor alignment, site connection, coupling connection and load test Electrical Work 27th Dec’22 Seal box installation, instrument testing and handing over to process Instrumental Work 30th Dec’22 Full load testing, punch point, cleaning, boxing and Handover Commissioning, Testing, and Handover Work 06th Jan’22 18th Dec’22 27rd Dec’22 1st Jan’22 7th Jan’22 13th Jan’22 Haren
  • 9. 9 Resource Cost Overview Resource Name Type Material Label Std. Rate Ovt. Rate Motor Material Unit Pump Material Unit Cement Material Bags ₹ 500.00 Saria 12MM Material Kg ₹ 102.00 Saria 8MM Material Kg ₹ 96.00 Coarse Aggregator Material kg ₹ 40.00 Mechanical Engineer Work ₹ 2,000.00/day ₹ 200.00/hr Civil Engineer Work ₹ 2,000.00/day ₹ 200.00/hr Mason (Class-A) Work ₹ 700.00/day ₹ 100.00/hr Mason (Class-B) Work ₹ 400.00/day ₹ 50.00/hr Helper Work ₹ 300.00/day ₹ 50.00/hr Site Supervisor Work ₹ 2,300.00/day ₹ 300.00/hr Water Tanker Material Unit ₹ 600.00 Concrete Mixer Work ₹ 5,000.00/day ₹ 0.00/hr Forklift Work ₹ 2,500.00/day ₹ 0.00/hr JCB Work ₹ 5,000.00/day ₹ 0.00/hr Electrical Engineer Work ₹ 2,200.00/day ₹ 0.00/hr Technician Work ₹ 1,100.00/day ₹ 0.00/hr Cable 2.5MM Material Meter Seal box Material Unit MCB Material Unit Insulators Material Unit ₹ 0.00 ₹ 5,000.00 ₹ 10,000.00 ₹ 15,000.00 ₹ 20,000.00 ₹ 25,000.00 Actual Cost Remaining Cost Baseline Cost Cost Status Cost Distribution Type Total Work 90050 Material 233620 Grand Total 323670 Haren
  • 10. 10 Cash Flows Actual Cost ₹ 3,23,670.00 Cost Variance ₹ 22,010.00 Baseline Cost ₹ 3,01,660.00 ₹ 0.00 ₹ 50,000.00 ₹ 100,000.00 ₹ 150,000.00 ₹ 200,000.00 ₹ 250,000.00 ₹ 300,000.00 ₹ 350,000.00 4 1 Cost Cumulative Cost The chart shows the project's cumulative cost and the cost per quarter. ₹ 2,90,520.00 Actual cost of work performed ACWP ₹ 2,71,010.00 Budgeted cost of work performed BCWP ₹ 2,71,010.00 Budgeted cost of work scheduled BCWS 0 50000 100000 150000 200000 250000 Work Material Execute commissioning and testing of a pump installation in an industry Pump Installation Cost Baseline Cost Report Baseline Cost Cost Actual Cost Haren
  • 11. 11 Earned Value EAC ₹ 3,23,376.65 BCWP ₹ 2,71,010.00 ACWP ₹ 2,90,520.00 ₹ 0.00 ₹ 50,000.00 ₹ 100,000.00 ₹ 150,000.00 ₹ 200,000.00 ₹ 250,000.00 ₹ 300,000.00 ₹ 350,000.00 '22 '22 '22 '22 '22 '23 ACWP BCWP BCWS The project is over budgeted, and the project is behind schedule. -₹ 40,000.00 -₹ 20,000.00 ₹ 0.00 ₹ 20,000.00 ₹ 40,000.00 ₹ 60,000.00 ₹ 80,000.00 ₹ 100,000.00 '22 '22 '22 '22 '22 '23 CV SV VARIANCE OVER TIME Cost Variance is negative, project is over budget. Schedule Variance is positive, project is behind schedule. Keyur
  • 12. 12 Appraisals of Project Committing to Pump Lifecycle Enhancement can Save Money and Drive Performance 4/5 Increased Productivity Pump installation will boost the productivity of the setup. 3/5 Reduced Downtime The downtime for the process will drastically reduce. 4/5 Less Maintenace With a newer setup lesser maintenance will be required. 5/5 High Efficiency of Work Higher efficiency of work post the pump installation in industry Abhishek
  • 13. 13 Risks of Project Work at very high velocity and pressure 01 Pump should be securely anchored and should have plenty of clearance 02 Internal parts need to be maintained 04 Check for Air Leaks, Suction Line Blockage 05 Check for and Replace Worn-out Components and worn suction line fittings and pipe plugs 03 Inspecting pump components before and after installation 06 Check Discharge Lines for the installation purposes 07 Make the Pump Accessible (size, fitment and other related risks) 08 If the pump is located underground, follow confined space entry procedures. 10 Use the Pump for Its Designated Use for the installation front 09 Sunil
  • 14. 14 Constraints of Project 01 Electrical Issues Incorrect wiring, The pump is not properly grounded, Low Power 02 Plumbing Problems Improperly installed check valve, Pump not primed 03 General Problems Improper pump and motor alignment, Not enough room for the float switch Major Issues Sunil
  • 15. 15 Do you have any questions? Thanks harender.singh@siom.in +91 9812969049 Connect with us: Team 7 Sec A & B Aishwarya Kohad 21020741083 Harender Singh 21020741099 Upendranath Reddy 21020741127 Shankruth Verma 21020741133 Abhishek Kumar 21020741082 Keyur Tandel 21020741032 Pavan Kumar Kandi 21020741031 Prince Kumar Singh 21020741051 Shubham Mitra 21020741065 Sunil Menaria 21020741070