API 5L STANDARD (2007) PRACTICE QUESTIONS
Name : Date of
Examination :
Please answer all the questions as below.
1. What edition ISO standards are added to API 5L?
ISO 3183 -1/2/3(1996)
2. How many specification levels in API 5L and what are they?
Two (PS1 & PS2)
3. What is the PSL stand for?
Product Specification Level
4. Which is more stringent PSL 1 or PSL 2?
PSL2
5. What additional mandatory requirements for PSL 2?
Chemical composition, notch toughness and strength properties and
additional NDE
6. What kind of welding process is EW? Electric Welding
7. What is the formula for carbon equivalent for PSL 2 pipe with a product
analysis carbon mass fraction equal to or less than 0.12% ?
CE =C+Si/30+Mn/20+ Cu/20 +Ni/60+Cr/20+Mo/15+V/10+5B
8. What is the formula for carbon equivalent for PSL 2 pipe with a product
analysis carbon mass fraction greater than 0.12% ?
CW = C + Mn/6 + (Cr+ Mo +V) / 5 + (Ni + Cu)/15
9. The seams of double-seam pipe shall be approximately 180º?
(True/False) True
10. Internal metal separation that creates layers, generally parallel to the
pipe surface is called lamination? (True/False) True
11. What kind of general information to be supplied by the purchaser to the
manufacturer which shall be included in the purchase order when
ordering pipes?
Quantity, PSL level, type of pipe, reference to ISO 3183, steel grade,
outside diameter and wall thickness, Length and type of length,
comfirmation of applicability of individual annexes.
12. The yield strength of API pipe grade B (seamless) is 35 500psi?
(True/False) True
13. The tensile strength of API pipe grade L485 or X 70 is 82 700psi?
(True/False) True
14. What is the minimum average (of a set of three test pieces) absorbed
energy for each pipe weld and HAZ test, based upon full size test pieces
and a test temperature of 0º C for diameter less than 56.000 in. in
grades ≤ L555 or X80 ? 27J
15. For Drop-Weight Tear (DWT) for PSL 2 welded pipe, what is the average
shear fracture for each test based upon a test temperature of 0º C if
thickness is less than 25.4mm? ≥ 85%
16. All pipes shall be free from defects in the finished condition? (True/False)
True
17. All pipes shall be free from cracks, sweats and leaks? (True/False) True
18. The acceptance criteria for imperfections found by non-destructive
inspection shall be in accordance with Annex?
E
19. Undercuts -≤0.4mm depth and regardless in SAW and COW pipes found
by visual inspection is acceptable? acceptable
20. Is arc burns classified as defects? True or False. True
21. Laminations or inclusions extending into the face or bevel of the pipe and
having a visually determined length in the circumferential direction>
6.4mm shall be classified as defects? True or False. True
22. For other than dents, geometric deviations from the normal cylindrical
contour of the pipe(flat spots and peaks) that occur as a result of the pipe
forming process or manufacturing operations and that exceeds 3.2mm in
depth, measured as the gap between the extreme point of the deviation
and the prolongation of the normal contour of the pipe, shall be
considered defects? True or False. True
22. What is the maximum depth for sharp bottom gouges dent if the length of
the dent is equal or less than 0.5D? 3.2mm
23. What is the maximum depth for other dents if the length of
the dent is equal or less than 0.5D? 6.4mm
24. Any hard spot larger than 50mm in any direction shall be classified as a
defect if its hardness exceeds 35HRC,345HV10 or 327HBW, based upon
individual indentations. True or False. True
26. Based on the defects, is it true that, the sections of the pipe containing the
surface defects shall be cut off, within the limits on length? True or False.
True
27. What is the diameter tolerance on end pipe for pipe diameter greater than
168.3mm.? +/- 0.005D but maximum of =/- 1.6mm
28. What is the out-of-roundness tolerances for pipe end for pipe diameter
greater than 168.3mm ? 0.015D
29. What is the tolerance for wall thickness for 8mm seamless pipe (SMLS)?
+0.150t/-0.125t.
30. The total deviation from a straight line (straightness), over the entire pipe
length, shall be ≤ 0.2% of the pipe length? True or False. True
31. The local deviation from a straight line (straightness) in the 1000mm
portion at each pipe end shall be ≤ 4.0mm ? True or False. True
32. PSL pipe shall be furnished with plain ends? True or False. True
33. The out of squareness, measured for finish of plain ends shall be
≤ 1.6mm? True or False. True
34. Unless otherwise agreed, the end faces of plain-end pipe with t> 3.2mm
shall be beveled for welding (bevel angle 30º +5º / -º and width of the root
face of the bevel shall be 1.6mm with a tolerance of +/- 0.8mm)? True or
False. True
35. The outside flash shall be trimmed to an essentially flush condition for EW
& LW pipes. True or False. True
36. The inside flash shall not extend above the contour of the pipe by more
than 1.5mm EW & LW pipes. True or False. True
37. What is the tolerances for mass for pipe grade L175,L175P,A25 and A25P
? +10% -5.0%
38. What is the holding time for hydrostatic test for welded pipe D> 457mm?
not less than 10sec.
39. The hydrostatic test pressure for plain –end pipe shall using what equation
formula with results rounded to the nearest 10psi?
P =2St/D
40. Name the requirements of pipe markings found on completed pipe.
a) Name or mark of manufacturer of the pipe.
b) Specified outside diameter.
c) Number designation of ISO 3183 plus, or alternatively, an identical
national adoption of ISO if agreed.
d) Specified wall thickness.
e) Pipe steel grade
f) Product specification level designation
g) Type of pipe
h) Mark of the customer’s inspection representative
i) An identification number which permits the correlation of the product or
delivery unit with the related inspection document, if applicable.

More Related Content

What's hot

Wis5 stress and distortion 15
Wis5 stress and distortion 15Wis5 stress and distortion 15
Wis5 stress and distortion 15Thang Do Minh
 
Procedure qualification
Procedure qualificationProcedure qualification
Procedure qualificationvaasuBandaru
 
Selection of filler wire
Selection of filler wireSelection of filler wire
Selection of filler wireImran Jamil
 
Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questionsKarthik Banari
 
radiographic-interpretation.pdf
radiographic-interpretation.pdfradiographic-interpretation.pdf
radiographic-interpretation.pdfVENKATESAN S
 
Pqr asme ix completed
Pqr asme ix  completed Pqr asme ix  completed
Pqr asme ix completed CEDEYN
 
Post-Weld-Heat-Treatment-ppt.ppt
Post-Weld-Heat-Treatment-ppt.pptPost-Weld-Heat-Treatment-ppt.ppt
Post-Weld-Heat-Treatment-ppt.pptvipinverma125286
 
Piping sample report
Piping sample reportPiping sample report
Piping sample reportram111eg
 
Welding process
Welding processWelding process
Welding processArunMK17
 
Presentation joining processes
Presentation joining processesPresentation joining processes
Presentation joining processesR G Sanjay Prakash
 
Corrosion under insulation
Corrosion under insulationCorrosion under insulation
Corrosion under insulationpatiphon
 

What's hot (20)

Wis5 stress and distortion 15
Wis5 stress and distortion 15Wis5 stress and distortion 15
Wis5 stress and distortion 15
 
How to produce PQR
How to produce PQRHow to produce PQR
How to produce PQR
 
Procedure qualification
Procedure qualificationProcedure qualification
Procedure qualification
 
Selection of filler wire
Selection of filler wireSelection of filler wire
Selection of filler wire
 
Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questions
 
Tig welding
Tig weldingTig welding
Tig welding
 
cswip-3-1-new-book
 cswip-3-1-new-book cswip-3-1-new-book
cswip-3-1-new-book
 
Welding Defects
Welding DefectsWelding Defects
Welding Defects
 
radiographic-interpretation.pdf
radiographic-interpretation.pdfradiographic-interpretation.pdf
radiographic-interpretation.pdf
 
Pqr asme ix completed
Pqr asme ix  completed Pqr asme ix  completed
Pqr asme ix completed
 
Post-Weld-Heat-Treatment-ppt.ppt
Post-Weld-Heat-Treatment-ppt.pptPost-Weld-Heat-Treatment-ppt.ppt
Post-Weld-Heat-Treatment-ppt.ppt
 
How to Qualify a Welding Procedure
How to Qualify a Welding ProcedureHow to Qualify a Welding Procedure
How to Qualify a Welding Procedure
 
Piping sample report
Piping sample reportPiping sample report
Piping sample report
 
Welding process
Welding processWelding process
Welding process
 
Asme wps-demo
Asme wps-demoAsme wps-demo
Asme wps-demo
 
Presentation joining processes
Presentation joining processesPresentation joining processes
Presentation joining processes
 
Corrosion under insulation
Corrosion under insulationCorrosion under insulation
Corrosion under insulation
 
Radiographic interpretation
Radiographic interpretation Radiographic interpretation
Radiographic interpretation
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 
Welding defects
Welding defectsWelding defects
Welding defects
 

Similar to Api 5l-practice-questions and answers

Itt grinnell products standard and line pipe catalog 2008
Itt grinnell products standard and line pipe catalog 2008Itt grinnell products standard and line pipe catalog 2008
Itt grinnell products standard and line pipe catalog 2008ITTGRINNELL
 
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...Rishabh Sirvaiya
 
Pipelines welding handbook_welding_techn
Pipelines welding handbook_welding_technPipelines welding handbook_welding_techn
Pipelines welding handbook_welding_technAshraf Shaikh
 
Steam Reforming - Tube Design
Steam Reforming - Tube DesignSteam Reforming - Tube Design
Steam Reforming - Tube DesignGerard B. Hawkins
 
406808075-Piping-questonary.pdf
406808075-Piping-questonary.pdf406808075-Piping-questonary.pdf
406808075-Piping-questonary.pdfmoumo1
 
Customer webinar 5
Customer webinar 5Customer webinar 5
Customer webinar 5gbsdirect
 
ASME Section VIII Div 1. design training
ASME Section VIII Div 1.  design trainingASME Section VIII Div 1.  design training
ASME Section VIII Div 1. design trainingSam Jose
 
Sampleq practice-exam-d11-2002 (1)
Sampleq practice-exam-d11-2002 (1)Sampleq practice-exam-d11-2002 (1)
Sampleq practice-exam-d11-2002 (1)Lennard Charles
 
L&T Valves - Effects of Stem and Stuffing Box Roughness on Valve Fugitive Emi...
L&T Valves - Effects of Stem and Stuffing Box Roughness on Valve Fugitive Emi...L&T Valves - Effects of Stem and Stuffing Box Roughness on Valve Fugitive Emi...
L&T Valves - Effects of Stem and Stuffing Box Roughness on Valve Fugitive Emi...Babu Kuriakose
 

Similar to Api 5l-practice-questions and answers (20)

Itt grinnell products standard and line pipe catalog 2008
Itt grinnell products standard and line pipe catalog 2008Itt grinnell products standard and line pipe catalog 2008
Itt grinnell products standard and line pipe catalog 2008
 
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
Production of MDPE gas Pipe as per IS 14885 in Industries with Pictorial Repr...
 
Pipelines Welding Handbook ESAB.pdf
Pipelines Welding Handbook ESAB.pdfPipelines Welding Handbook ESAB.pdf
Pipelines Welding Handbook ESAB.pdf
 
ADITYA IS-4984.pptx
ADITYA IS-4984.pptxADITYA IS-4984.pptx
ADITYA IS-4984.pptx
 
Pipelines welding handbook_welding_techn
Pipelines welding handbook_welding_technPipelines welding handbook_welding_techn
Pipelines welding handbook_welding_techn
 
API_510_for_Exam.pdf
API_510_for_Exam.pdfAPI_510_for_Exam.pdf
API_510_for_Exam.pdf
 
API 570 open book.pdf
API 570 open book.pdfAPI 570 open book.pdf
API 570 open book.pdf
 
Ptc magmeter manual
Ptc magmeter manualPtc magmeter manual
Ptc magmeter manual
 
Steam Reforming - Tube Design
Steam Reforming - Tube DesignSteam Reforming - Tube Design
Steam Reforming - Tube Design
 
406808075-Piping-questonary.pdf
406808075-Piping-questonary.pdf406808075-Piping-questonary.pdf
406808075-Piping-questonary.pdf
 
Customer webinar 5
Customer webinar 5Customer webinar 5
Customer webinar 5
 
Asme sec viii div 1 icb
Asme sec viii div 1 icbAsme sec viii div 1 icb
Asme sec viii div 1 icb
 
ASME Section VIII Div 1. design training
ASME Section VIII Div 1.  design trainingASME Section VIII Div 1.  design training
ASME Section VIII Div 1. design training
 
ATS-Catalogue-Latest
ATS-Catalogue-LatestATS-Catalogue-Latest
ATS-Catalogue-Latest
 
Catalogue-Oil Cooled-Resin Cast CTs-PTs-ATS
Catalogue-Oil Cooled-Resin Cast CTs-PTs-ATSCatalogue-Oil Cooled-Resin Cast CTs-PTs-ATS
Catalogue-Oil Cooled-Resin Cast CTs-PTs-ATS
 
TRANSISTORES
TRANSISTORESTRANSISTORES
TRANSISTORES
 
AMAN PPT 4985 Assignment-1.pptx
AMAN PPT 4985 Assignment-1.pptxAMAN PPT 4985 Assignment-1.pptx
AMAN PPT 4985 Assignment-1.pptx
 
Sampleq practice-exam-d11-2002 (1)
Sampleq practice-exam-d11-2002 (1)Sampleq practice-exam-d11-2002 (1)
Sampleq practice-exam-d11-2002 (1)
 
aurum-alloys
aurum-alloys aurum-alloys
aurum-alloys
 
L&T Valves - Effects of Stem and Stuffing Box Roughness on Valve Fugitive Emi...
L&T Valves - Effects of Stem and Stuffing Box Roughness on Valve Fugitive Emi...L&T Valves - Effects of Stem and Stuffing Box Roughness on Valve Fugitive Emi...
L&T Valves - Effects of Stem and Stuffing Box Roughness on Valve Fugitive Emi...
 

Recently uploaded

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 

Recently uploaded (20)

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 

Api 5l-practice-questions and answers

  • 1. OPEN BOOK EXAMINATION API 5L STANDARD (2007) PRACTICE QUESTIONS Name : Date of Examination : Please answer all the questions as below. 1. What edition ISO standards are added to API 5L? ISO 3183 -1/2/3(1996) 2. How many specification levels in API 5L and what are they? Two (PS1 & PS2) 3. What is the PSL stand for? Product Specification Level 4. Which is more stringent PSL 1 or PSL 2? PSL2 5. What additional mandatory requirements for PSL 2? Chemical composition, notch toughness and strength properties and additional NDE 6. What kind of welding process is EW? Electric Welding 7. What is the formula for carbon equivalent for PSL 2 pipe with a product analysis carbon mass fraction equal to or less than 0.12% ? CE =C+Si/30+Mn/20+ Cu/20 +Ni/60+Cr/20+Mo/15+V/10+5B 8. What is the formula for carbon equivalent for PSL 2 pipe with a product analysis carbon mass fraction greater than 0.12% ? CW = C + Mn/6 + (Cr+ Mo +V) / 5 + (Ni + Cu)/15 9. The seams of double-seam pipe shall be approximately 180º? (True/False) True 10. Internal metal separation that creates layers, generally parallel to the pipe surface is called lamination? (True/False) True 11. What kind of general information to be supplied by the purchaser to the manufacturer which shall be included in the purchase order when ordering pipes? Quantity, PSL level, type of pipe, reference to ISO 3183, steel grade, outside diameter and wall thickness, Length and type of length, comfirmation of applicability of individual annexes. 12. The yield strength of API pipe grade B (seamless) is 35 500psi? (True/False) True 13. The tensile strength of API pipe grade L485 or X 70 is 82 700psi? (True/False) True
  • 2. 14. What is the minimum average (of a set of three test pieces) absorbed energy for each pipe weld and HAZ test, based upon full size test pieces and a test temperature of 0º C for diameter less than 56.000 in. in grades ≤ L555 or X80 ? 27J 15. For Drop-Weight Tear (DWT) for PSL 2 welded pipe, what is the average shear fracture for each test based upon a test temperature of 0º C if thickness is less than 25.4mm? ≥ 85% 16. All pipes shall be free from defects in the finished condition? (True/False) True 17. All pipes shall be free from cracks, sweats and leaks? (True/False) True 18. The acceptance criteria for imperfections found by non-destructive inspection shall be in accordance with Annex? E 19. Undercuts -≤0.4mm depth and regardless in SAW and COW pipes found by visual inspection is acceptable? acceptable 20. Is arc burns classified as defects? True or False. True 21. Laminations or inclusions extending into the face or bevel of the pipe and having a visually determined length in the circumferential direction> 6.4mm shall be classified as defects? True or False. True 22. For other than dents, geometric deviations from the normal cylindrical contour of the pipe(flat spots and peaks) that occur as a result of the pipe forming process or manufacturing operations and that exceeds 3.2mm in depth, measured as the gap between the extreme point of the deviation and the prolongation of the normal contour of the pipe, shall be considered defects? True or False. True 22. What is the maximum depth for sharp bottom gouges dent if the length of the dent is equal or less than 0.5D? 3.2mm 23. What is the maximum depth for other dents if the length of the dent is equal or less than 0.5D? 6.4mm 24. Any hard spot larger than 50mm in any direction shall be classified as a defect if its hardness exceeds 35HRC,345HV10 or 327HBW, based upon individual indentations. True or False. True 26. Based on the defects, is it true that, the sections of the pipe containing the surface defects shall be cut off, within the limits on length? True or False. True
  • 3. 27. What is the diameter tolerance on end pipe for pipe diameter greater than 168.3mm.? +/- 0.005D but maximum of =/- 1.6mm 28. What is the out-of-roundness tolerances for pipe end for pipe diameter greater than 168.3mm ? 0.015D 29. What is the tolerance for wall thickness for 8mm seamless pipe (SMLS)? +0.150t/-0.125t. 30. The total deviation from a straight line (straightness), over the entire pipe length, shall be ≤ 0.2% of the pipe length? True or False. True 31. The local deviation from a straight line (straightness) in the 1000mm portion at each pipe end shall be ≤ 4.0mm ? True or False. True 32. PSL pipe shall be furnished with plain ends? True or False. True 33. The out of squareness, measured for finish of plain ends shall be ≤ 1.6mm? True or False. True 34. Unless otherwise agreed, the end faces of plain-end pipe with t> 3.2mm shall be beveled for welding (bevel angle 30º +5º / -º and width of the root face of the bevel shall be 1.6mm with a tolerance of +/- 0.8mm)? True or False. True 35. The outside flash shall be trimmed to an essentially flush condition for EW & LW pipes. True or False. True 36. The inside flash shall not extend above the contour of the pipe by more than 1.5mm EW & LW pipes. True or False. True 37. What is the tolerances for mass for pipe grade L175,L175P,A25 and A25P ? +10% -5.0% 38. What is the holding time for hydrostatic test for welded pipe D> 457mm? not less than 10sec. 39. The hydrostatic test pressure for plain –end pipe shall using what equation formula with results rounded to the nearest 10psi? P =2St/D 40. Name the requirements of pipe markings found on completed pipe. a) Name or mark of manufacturer of the pipe. b) Specified outside diameter. c) Number designation of ISO 3183 plus, or alternatively, an identical national adoption of ISO if agreed. d) Specified wall thickness. e) Pipe steel grade f) Product specification level designation g) Type of pipe h) Mark of the customer’s inspection representative i) An identification number which permits the correlation of the product or
  • 4. delivery unit with the related inspection document, if applicable.