The project provides approximately 3,600 linear feet (LF) of new stormwater conveyance; and 2,000 LF of new sanitary main and service connections for 23 homes; and fully milled and repaved Hayfield Road, Telegraph Road intersection and Bridgewater Court. Presented at a Hayfield Citizens Association Meeting on September 16, 2020.
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Hayfield Road Pipe Conveyance Project Meeting September 16, 2020
1. A Fairfax County, VA, publication
Department of Public Works and Environmental Services
Working for You!
September 16, 2020
Hayfield Road
Pipe
Conveyance
Project
Hayfield Citizens Association Meeting –
September 16, 2020
3. 3
The project provides:
o Approximately 3,600 LF of new stormwater conveyance.
• This design will carry the 100-year storm event.
• Improves/removes the flood risk for at least 45 homes that sit over/near the original 72” pipe. This
includes the homes on the west side of Hayfield Road & the properties adjoining these parcels’ rear
property boundaries.
o Approximately 2,000 LF of new sanitary main & service
later connections for 23 homes.
o Contract allowed 365 days. Project completed
almost 2 months early.
o Fully milled & repaved Hayfield Road, Telegraph Road
intersection, & Bridgewater Court
Correct the outfall condition
o Designed outfall elevation is too low for the surrounding grade & water ponds
• Design revisions will provide excavated/lowered drainage swales around the central tree save area
• A stone sill will be installed to help protect the tree save area from flows & direct stormwater
discharge to the new swales
• Native vegetation plantings will be used to stabilize the swales & help manage flow velocities
• Schedule is to complete this fall
WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
Hayfield Road Pipe Conveyance Project
OVERVIEW
4. Plantings
o Hayfield Road median: Replace trees removed during project with same species with one exception
• These include Red maple (Acer rubrum), American holly (Ilex opaca), and Red bud (Cercis canadensis).
• At the direction of the HCA Board, the Silver maple will be replaced with Red maple.
• At the original median planting, the landscaper installed Silver maples in error.
• Several additional trees will be planted to replace a few in severe decline & to fill an open
area near Telegraph Road.
• Scheduled for the fall 2020 planting window after the outfall regrading is complete.
o Median flowers: To the extent that construction removed/damaged any of the flowers (Ice Follies and King Alfred
daffodils) planted on the ends of medians, these will be replaced. Timing is spring 2021 after blooming.
o Outfall: Remove & replace the plantings installed in the fall 2019
• The landscape subcontractor did not provide only native plantings.
• Contrary to the design requirements, cultivars were installed.
• Cost to be borne by the primary/subcontractor.
• Replacements scheduled to be completed this fall.
4WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
Hayfield Road Pipe Conveyance Project
OVERVIEW
o Following all the heavy construction traffic & deliveries, the Swim Club
driveway & access is replaced/restored.
o Hayfield Park was not used for storage & staging. So, no restoration work
required.
5. 5
Project warranty
o Hardscape & infrastructure (pipe, box culvert, curb & gutter, etc.) carry a 1-year warranty
from the date of Substantial Completion beginning August 21, 2020.
o Plantings carry a 1-year warranty from the date the last plant is installed.
• Woodies & plugs: 1-year from the date the final plant is installed fall 2020.
• Ephemerals/flowers: 1-year from the date the damaged/removed bulbs are planted
spring 2021.
Hayfield Road Pipe Conveyance Project
WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
REMAINING WORK
(Plantings cont’d)
o Additional outfall plantings
• With the outfall regrading complete, the area inside the fish-scale weirs will be planted with native
wetland plugs to stabilize the soil & manage discharge velocities.
• Side slopes of outfall area will also receive additional native trees & shrubs
• Examples: River birch (Betula nigra), Hackberry (Celtis occindetalis), Paw paw (Asimina triloba),
Sweetbay magnolia (Magnolia virginiana), Silky dogwood (Cornus amomum), Soft rush (Juncus
effuses), Wool grass (Scirpus cuperinus)
Unintended benefit is improved water quality discharged into Dogue
Creek/Huntley Meadows Park due to the combination of all plantings in &
around the outfall area & the level spreaders.
6. 6
Outfall level spreaders – pictures & functions
Hayfield Road Pipe Conveyance Project
WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
Coir logs & native shrub plantings
on each side. The coir logs &
shrubs form an impediment to
flow slowing velocity & forcing
flow into shallow sheet flow.
Graded level spreader surrounded by new plantings &
existing forest. Grading provides a low spot for water to
collect, slow, & spread out until it then flows over the
downstream side of the graded area.
Outfall area below plunge pool – fish-scale weirs under construction.
Wood forms will be filled with concrete & native wetland plugs will
be planted inside the curved cells. Discharged water will flow over
the concrete being slowed & spread out.
Level spreaders serve to slow water flow
velocity, force the water to spread out in
shallow sheet flow, & prevent
concentrated flow from forming.
Concentrated flows pose the biggest
erosion risk.
The extensive tree, shrub, & plug plantings
also help slow flow velocity, stabilize the
soil, & uptake & use the water & any
contaminants (think primarily nitrogen &
phosphorus) as growth nutrients. This
plant uptake removes contaminants from
the discharge & thereby polishes &
improves the water quality leaving the new
conveyance system.
7. 7
WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
Other Matters
Hayfield Road Pipe Conveyance Project
Please join us for a ribbon cutting ceremony to recognize
completing the project.
Where: Hayfield Swim Club parking lot
When: Thursday, October 1
Time: 4:45 pm start
Rain date: Thursday, October 8 – other details remain the same
Board Chairman Jeff McKay,
Lee District Supervisor Rodney Lusk, &
County Executive Bryan Hill
are scheduled to join us.
8. Contact Information
During the warranty period, Brendan Schillo & I
remain the project managers
8WATERSHED PROJECTS IMPLEMENTATION BRANCH – SOUTH, STORMWATER PLANNING DIVISION
Dave Anglin, Section Chief
dave.anglin@fairfaxcounty.gov
703-324-5500
www.fairfaxcounty.gov/dpwes
Hayfield Road Pipe Conveyance Project
Brendan Schillo, PE, Project Engineer
703-659-7048
Brendan.schillo@fairfaxcounty.gov