CALCULATION OF THE CONSTRUCTION TIME- SYSTEMATIC
MANAGEMENT OF PROJECT UNCERTAINTIES IN RUSH PROJECTS
IN MAKKAH
M. M. Mostafa1
, W.W.Al-Buzz2
1
Civil engineering Dept. Taif University, Al-Hawih, P.O.Box 888, Z.C.21974, Taif Saudi Arabia
2
Civil engineering Dept. Taif University, Al-Hawih, P.O.Box 888, Z.C.21974, Taif Saudi Arabia
Abstract
New fast track construction projects worth more than $100 billion are being implemented in Makkah to improve services being
rendered to millions of pilgrims who come for Hajj and Umrah. The new development projects in Makkah, including largest
expansion of the Grand Mosque. The time factor has become increasingly as an outstanding requirement on this construction
projects. In the present work, the question "acceleration of construction projects" is moved in the center. Consequently, innovative
structures, procedures and techniques are required for a time-oriented project management; consistently and purposefully focus
on the reduction of process time and not to shrink back from entirely new, unfamiliar processes. so recommendations for the
efficient management of construction projects always need to be developed taking into account the specific objectives and
framework. This article discusses also the deterministic method, the simplified stochastic method and the application of the
Monte-Carlo simulation as a stochastic method. With increasing of level of detail of the information content of the project and
increases the calculation effort with the result that the range of the construction time decreases, thus the accuracy increases.
Based on this range, finally the construction time of the building as well as the part times for the individual construction phases
are determined.
Keywords – Construction industry, Risk management, Construction Projects, project uncertainties, fast track projects,
construction time, project management
-------------------------------------------------------------------***-------------------------------------------------------------------
1. INTRODUCTION
The construction time is an essential indicator of the project
success, as both the construction cost and quality are
significantly affected by the construction period. The
construction time is usually given from the client. The
construction time should be respected by the contractors or
their subcontractors subsequently. The client has to manage
those conditions as part of his contractual obligations that
ensure the compliance of the construction time. New fast
track construction projects worth more than $100 billion are
being implemented in Mecca to improve services being
rendered to millions of pilgrims who come for Hajj and
Umrah. The new development projects in Mecca, including
largest expansion of the Grand Mosque. An important
requirement for a fast track construction project is the
stability in the project and the project environment. To
calculate the construction time, quantities and performance
rates are required. If the project is being considered as a
whole, for example, the gross volume of the building or
tunnel length in the transport infrastructure is used for the
quantity calculation. The quantities are calculated from the
plans. The precision of the calculation of quantities depends
on the considered phase of the project and the associated
level of detailing. In early project phases, the calculation of
quantities can be specified only in larger ranges. From these
uncertainties and due to the fact that the nature and scope of
activities and the range of the activity performance cannot
be accurately described or identified, it is also possible to
estimate the production factors only within a range. These
uncertainties in earlier stages of the project are higher than
in later ones. Based on the level of information, trying
possible combinations of the production factors will be
developed in order to get approaches for the production
performance. With the production performance, on the one
hand the client can close on the construction time and on the
other hand the bidders or contractors subsequent to the
required use of production factors.
2. AIMS OF THE STUDY
If you can determine the specific project requirements
highly efficient procedures only as a function, so
recommendations for the efficient management of
construction projects always need to be developed taking
into account the specific objectives and framework.
In the present work, the question "acceleration of
construction projects" is moved in the center. This is
because the demand structures and needs in the real estate
market are changing faster and faster. A short planning and
execution time is becoming increasingly clearer to an
outstanding performance feature of construction projects.
Expected and more often in the future a particularly short
duration even become a decisive factor in the choice of the
project team.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 04 Issue: 05 | May-2015, Available @ http://www.ijret.org 395
The acceleration is even from the construction perspective
an interesting challenge, but it is neither an exclusively
technical problem nor a matter of scheduling. The
acceleration of construction processes is primarily an
organizational and "group dynamics" challenge for the
management. It must never be based on the setting, but
everything as before, but a bit faster.
If the short duration of a project is based only on Pressure so
suffers both the psyche of all interested parties and the
quality of the work. Consequently, innovative structures,
procedures and techniques are required for a time-oriented
project management; consistently and purposefully focus on
the reduction of process time and not to shrink back from
entirely new, unfamiliar processes.
3. THE TIME FACTOR AS A CHALLENGE FOR
THE CONSTRUCTION PROJECT
MANAGEMENT
In recent years, the time factor has become increasingly as
an outstanding requirement on a construction project. This is
due to an attitude change towards the real estate and due to a
tougher economic environment. A construction must more
often not only cheap and functional, but also can be offered
to the tenant or buyer as soon as possible. Particularly in the
commercial and industrial sector buildings are also
becoming less as long-term investments and more and more
considered as a commodity. If "time to market" is the
decisive criterion, so long-term construction processes
cannot be accepted. Industrial construction projects often
have a compulsory given time limit - and often to be
available only for a certain period of time.
3.1 Restrictions in the Fast-Track Construction
Process
Although the factor still so clearly moved in the foreground,
but all other relevant objectives of the work must lie within
a common or usual objectives scope. A high speed may not
be acquired through poor quality or unduly high costs. The
investment in a plant or in an investment property is only
useful if the construction costs stay within a reasonable
budget and the functionality is fully guaranteed.
3.2 Acceleration as an Organizational Problem
Suitable tools and the required basic knowledge of the
project management are a prerequisite, they bring alone but
no acceleration of the construction process. Also the
constructional engineering provides today many approaches
for speeding up the construction work, but their
effectiveness begins only at an advanced stage of the long
construction process. If they are also not included in the
early stages of the project in the planning, so they only
develop a minimal effect. In contrast, when considered as
whole project cycle time period from the decision of the
implementation of a building till its commissioning, so
often the early decisions and concepts of the customer, the
authorization phases or the pre-engineering project will be
the more time-consuming sections. With the acceleration of
construction projects is then rather more an organizational
than a technical problem. The determination of the basic
organizational principles take places, together with many
other dominant elements, even in the earliest stages of the
project through the client.
4. PRAGMATIC ACCELERATION AND
TACTICS INNOVATIVE TIME MANAGEMENT
The problem of a very tight schedule is not new for the
construction practices. It is confronted with a demand for a
very fast implementation of projects and usually reacts with
the following tactics.
 "False shortening" of the operation duration
When scheduling of construction projects is not
infrequently assumed from luxuriantly designed
schedules. A first reaction of the urging of the client to
an acceleration is now to reduce the long-term operation
durations. However, it is not a real time reduction, but
only to the reduction of unnecessary time reserves.
 Acceleration through consistent project management
Since in many project planning, not the same attention
comes up to time-related aspects as the cost or the
functionality, a first acceleration can be achieved by the
intensification of scheduling and monitoring. By
increasing use of techniques of scheduling, an
optimization is obtained. However, only negligence can
be prevented and deadlines are met more easily. With
these measures, neither innovative methods nor
organizational changes are involved.
 Project acceleration by streamlining and
concentration
In the context of known project processes, a change can
take place in the priorities of the Costs and the design of
the deadlines. Under our clear prioritization of the period
falls easier on all parties, the streamlining of all activities
and deadline focus formation. Backed by a strong,
competent project management, with emphasis forms the
corresponding priorities in the formulation of guidelines,
priorities set by current decisions and allocation of
resources and (out) and a rigorous, advanced project
controlling operates, a substantial acceleration can be
achieved.
 Minimum project duration by massive use of
resources (crash projects)
Already, the construction industry is in a position under
exceptional conditions to cause massive acceleration.
This is usually done by the extraordinary use of
resources, and by the application of special authority and
an extraordinary motivation impact for all involved.
However, this type of acceleration has its price. Other
activities will be postponed or left undone, and the
project team is under a non constant to be maintained
pressure. This approach should therefore remain an
exception.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 04 Issue: 05 | May-2015, Available @ http://www.ijret.org 396
Acceleration due to
parallelization and
overlap
Duration of the
- Overall process
+
Higher coordination
costs
Acceleration due to
increased use of
resources
Fig.1. Duration of the process as a function of increased
resource utilization and parallelization on the one hand and
increasing coordination effort on the other hand
The parallelization of sub-processes offers as well as the
higher simultaneous use of resources an enormous
acceleration potential. But there is a significantly greater
coordination and communication requirements, which in
turn can cause loss of time.
5. PRINCIPLES FOR THE ACCELERATION OF
CONSTRUCTION PROJECTS
The duration of an overall process is determined by the
processing time, the waiting time between the individual
processing steps and the time sequence of individual sub-
processes. The easiest way is to shorten the processing time.
This can be done through the use of additional resources or
technical tools, but predominantly through the use of know-
how. The waiting times between processing cycles can be
traced back to missing information or to a suboptimal
organizational structure. To their reduction especially the
interactions between the involved subsystems or processes
are optimized. For each information flow and every
interaction takes time and increases the risk of waiting
times. The largest accelerating effect can be achieved by
clever variations in the sequence of the individual sub-
processes of an overall process. Corresponding sequence
patterns can be aimed on the elimination of individual sub-
processes, their overlapping or simultaneous processing, but
also to the "redundant" problematic part machining
processes.
Accelerating action on these three levels (processing time,
reduced wait times or less interactions and variation in the
sequence of sub-processes) are always interrelated
relationships. Therefore, a key objective in the
organizational design must be the reduction of interactions
and dependencies by decomposition. It creates the
prerequisite for rational to edit individual packages can be
formed and can be connected in parallel processes
efficiently.
5.1 Time Effectively Process Elements
The traditional project management focuses on the
optimization of specified sequences by the use of traditional
processing techniques of scheduling. It begins with an
optimal use of resources and the elimination of non-value
added time periods. In an innovative time management,
however, are all basic possibilities of action of interest that
have an influence on the duration of the overall process.
This can be derived from the following schematic
illustration of a sequential workflow in the industry.
In construction projects, exist the same approaches for
acceleration:
 Reduction in the processing time: The processing
time depends on the human, technical and
professional capacity. Management has influence
through the planning and the supply of the
necessary resources and the selection of appropriate
technical tools.
 Reduction of waiting- or lay-time between the
processing steps: between the individual work
steps, it always comes back to lay time. This may
due to lack of capacity (for seamless further
processing) or
 Be caused from the available information. You will
face the classic management especially with
efficient scheduling and resource planning. A
higher-level organizational approach seeks,
however, after the reduction of dependencies or
interactions between individual processing steps.
 The sequence of sub-processes: In a conventional
approach, the individual steps are processed
sequentially. The nested, parallel or early
implementation of processes represents a time-
effective alternative to the sequential processing.
6. DETERMINANTS OF FAST-TRACK
PROJECT
The speed of construction projects is predetermined in the
earliest stages of the project by the customer. He is
responsible for ensuring that the truly dominant performance
determinants are taken into account as early as the project
start. The ability of the co-operation of the overall system.
The rapid construction project is the result of many
individual measures, but finally the performance of an
optimally functioning, highly productive overall system.
The most important approaches:
 The ability of the co-operation of the overall
system: The rapid construction project is the result
of many individual measures, but finally the
performance of an optimally functioning, highly
productive overall system.
 The complexity of the structure: the simpler the
building and the construction process are
structured, the greater the acceleration potential.
 The collaboration between the client and the
contractor: the purposeful work on all parties to a
clearly defined end state toward the faster the
project proceeds. Uncertainties and changes in the
requirements slow down the project by a variety of
information gaps, additional clarifications and
multiple repetition of work already undertaken.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 04 Issue: 05 | May-2015, Available @ http://www.ijret.org 397
7. RELATIONSHIP BETWEEN COMPLEXITY
AND PROJECT DURATION
The more parties involved in a project, the more
complicated the construction tasks to be solved, and the
more objectives or possible developments (high dynamic
range) to be taken into consideration, the more difficult it is
the design of objective-based, efficient and above all fast
project process. There is a direct relationship between the
complexity of a project and its duration. So take for
example, many projects longer than necessary, or get out of
hand,
 By the "construction" of unnecessary dependencies
in the task and the project organization, for
example by emphasizing claims of secondary
importance, unnecessary complexity is established.
 High flexibility and late decisions are sought by
many clients and parties involved in the project
have to work in unsafe or variable objects.
 The project organizations by escalating functional
differentiation and Long information paths are
unnecessarily bloated. Through many dependencies
decisions are delayed and responsibilities “diluted".
8. RECOMMENDATIONS FOR THE
ACCELERATION OF CONSTRUCTION
PROJECTS
The acceleration of construction projects is primarily a
question of the organization. The project management must
always be oriented from the first phases of the project in
hand, through an appropriate design of the project and
project organization to get all activities with a high speed.
Thus, the contribution constructional and technical measures
cannot be negated, These will bring their accelerating effect
but only in the later stages of the project and only if
appropriate conditions have been created previously.
9. BASES FOR THE CALCULATION OF
CONSTRUCTION TIME FOR THE EXECUTION
STAGE
The number of parameters for the calculation of the
construction period depends on the project phase. Some few
values are needed for rough construction period inquiries
more hundred values for the calculations for detailed
considerations are depending on consideration depth
required.
The calculation equations are represented and described for
duration, performance and complete cost value in the
following which are required for a rough calculation in the
phase's building shell. These calculation equations form the
base for all further methods of calculation. As production
quantity cubic meters of reinforced concrete will be used.
The presented calculation methods do not replace detailed
considerations for the calculation of construction time and
construction costs.
10. METHODS
10.1 Deterministic Approach
The length of the construction time has essential influence
on the construction and very well also on the planning
process. At ‚normal„ construction time, where the limits
don't have to be exceeded for economic use of the factors of
production, these factors still can be planned optimally. The
shorter the construction time, the higher also is the demands
to the planning process. By the project management for a
short construction time, it must be considered, for example,
how is the lack, because it is not installable, cranes can be
compensated by other means of transport or other
construction method.
As a rule, too short construction Times are provided for
construction projects with regard to productive use of the
factors of production. However, long lead times contrast for
competitions and the planning with the short construction
times.
10.1.1 Calculation of the duration of the Reinforced
Concrete Works
The duration is calculated in the deterministic approach as a
scalar quantity. For each calculation passage scalar quantity
for each parameter will be used. As input parameters for the
calculation, for example, base values are used. Basing on
these base values in terms of opportunity and risk
assessment, the final values are determined for the
calculation passage.
For Eq. 1 with the average values for the quantity of
concrete BTM [m³] and performance LSTB [m³/d] the duration
DSTB [d] is calculated.
STB
M
STB
L
BT
D 
(1)
To the consideration of disturbances in the calculation, a
buffer PUSTB,Z [%] should be included which leads to the
following equation.









100
1
,
,
ZSTB
STBPUSTB
PU
DD
(2)
The amount of buffer depends on the complexity of the
construction and the number of construction stages in
winter. From our experiences it has shown that the buffer is
between 5 and 15%. In 'normal' construction time the buffer
should be at 5% and at least at 15% for a very short
construction time.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 04 Issue: 05 | May-2015, Available @ http://www.ijret.org 398
The buffer takes into account, for example, additional
performance or project unawareness
10.1.2 Daily Performance of the Reinforced
Concrete Works
The average daily performance for the reinforced concrete
work LSTB [m³/d] is calculated according to to Eq. 3 In the
numerator it result in multiplying the number of workers
AKSTB [Std/h] with the daily working AZSTB [h/d] the daily
labor hours.
The denominator is the total cost value AWSTB [Std/m³] for
the reinforced concrete work.
STB
STBSTB
STB
AW
AZAK
L


(3)
In Figure 1 are shown decisive influences on performance.
This serves as an exemplary presentation of a qualitative
assessment of risks and opportunities portfolio.
The average performance can be calculated for the entire
construction or individual structural components. Depending
on the level of detail of the project and the project stage,
typically rise the accuracy of the input variables and thus the
calculation result.
Fig 1: key influences on performance [Hofstadler]
10.2 Simplified Stochastic Approach
For the simplified stochastic calculation method also
deterministic calculation rules are to develop. However, for
the calculation operation is not one value per parameter
required, but three values. In addition, three values must be
chosen for the probability of occurrence.
10.2.1 Flexible Method
For the respective input values in the calculation equations
respectively three values are used, namely a minimum value,
a most frequent value and a maximum value. These values
are multiplied by the respective, subjectively defined
probability of occurrence. By adding the three products you
get the subjectively most probable value
For the probability of occurrence (PEW,i) applies::
 1,iEWp
(4)
10.2.2 PERT-Method
The PERT method assumes a fixed distribution type, the
BETA-distribution. In the PERT method three input values
to calculate the desired value is required. The counters are
the minimum and maximum value, unweighted and
weighted with 4 common value used. The three values are
added together and the weighted average the weighted mean
average value formed from this.
6
valuecpessimisti1aluefrequent v4valueOptimistic1 
Duration
(5)
In addition to this balanced approach, there are two
asymmetric approaches. Werner argues in his dissertation,
an optimistic and pessimistic calculation equation.
In the optimistic calculation, the weighted value higher than
the optimistic and pessimistic, the calculation is done
according to Eq. 6
6
valuecpessimisti1aluefrequent v3valueOptimistic2 
Duration
(6)
On the other hand, it is by the pessimistic analysis the
pessimistic value is evaluated with a higher value. The
calculation is performed according to Eq. 8
6
valuecpessimisti2aluefrequent v3valueOptimistic1 
Duration
(7)
10.3 Monte-Carlo Simulation
The Monte Carlo method, for example, allows the
calculation of the probability distribution for the
construction time. In an arbitrary number of iterations
generates a software program (in this case @ RISK) for the
input values random values, which are used in each pre-
defined probability density functions, and combines them
for a given calculation rule (the calculation equations of the
deterministic method), the distribution function of the
results.
 The input parameters are:
 fluctuation margin
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 04 Issue: 05 | May-2015, Available @ http://www.ijret.org 399
 The most probable value (if possible according to
the selected distribution function)
 Distribution functions
For the stochastic calculation method, individual selected
parameters are proved with a distribution function (e.g. flow
chart for calculating the construction time shown in Figure
3). The distribution functions are chosen so that they come
closest to reality. Since for the individual parameters still
there are not clear characteristic distribution functions,
asymmetric triangles will be used here. For each parameter
in the flow chart shown values, respectively values are given
for the optimistic and pessimistic value and the most
probable value.
Fig 2: Calculation mode for the Monte-Carlo simulation
[Hofstadler]
The values are determined in consideration of the
construction management and construction-specific
boundary conditions. As a basis for the values, for example,
internal company records or data from the literature (e.g.
working time guidelines for building superstructures) are
used. For example, if the total value of expenditure
considered and asymmetric triangular distributions is used, a
most probable value will be specified by the cost values for
shuttering work, reinforcement and concreting. Based on
these values, the opportunities and risks in the course of a
situation analysis will be evaluated, which means it is used
to determine to what extent these values fall below or could
be exceeded.
By including of considerations of probability in the
calculations, a significant improvement in the decision-
making is possible. Due to the used range and distribution
functions, probability distributions are presented according
to selected number of iterations for the required results. For
the calculation shown in Figure mode is as a result of the
total cost value (AWSTB) the daily performance (LSTB, WS), a
period with no buffer (DSTB, WS) and the duration with buffer
(DSTB, WS, PU ) respectively output a probability distribution.
For the calculation mode shown in Figure 6 is as a result of
the total cost value (AWSTB) ,the daily performance (LSTB,WS),
a duration without buffer (DSTB,WS) and the duration
including buffer (DSTB,WS,PU) each has a probability
distribution output.
11. CONCLUSION& RECOMMENDATIONS
The general recommendation relating to the organization
must be theoretically that all processes in the project must be
organized, that the individual sub-processes should be
executed as quickly as possible, that there will be no lay- or
waiting-times between the individual processing steps, and
that as many sub-processes can be parallel implemented.
However, construction projects are complex systems in
which all works closely interlocked and run in a tight
network of dependencies. From project to project and even
from one project to the next phase, the tasks, work priorities
and relationships in the system will change. The task of the
project management is always defrenciated - and especially
with the demand for acceleration - specifically customized
solutions must be adapted.
To calculate the construction time, production volumes on
the one hand and the production performance on the other
hand are required for rough considerations. If the entire
project is split into sub-systems, the relationships between
the systems (e.g., building shell construction, Construction
development, construction Engineering) should be defined.
In addition to the uncertainties in the calculation of the
partial times for each system now also the uncertainties must
be recorded in the relationships and to be evaluated.
Here for each project, the opportunities and risks need to be
reviewed. As a starting point here are the experiences from
past projects that are only useful if the resulting data can be
transparently analyzed. First base values can be determined,
based on the chances- and risk assessment, optimistic and
pessimistic values are determined.
The preparation of the deterministic calculation rule forms
the basis for the stochastic methods. If the stochastic
calculation methods systematically and dutifully applied,
their results form a good basis for the interpretation of
output and ultimately for decision making.
Further studies for the characteristics of distribution
functions for cost values and construction parameters (such
as formwork ratio, reinforcement ratio) can be performed.
The effects of correlations between the input variables are
also examined for their relevance. The results will to be
published.
ACKNOWLEDGMENTS
First of all I would like to express my great thanks to God
Almighty for helping me to finish this humbly research, and
this is my pleasure to express my special thanks to “Taif
University Administration”, for their full support to the
scientific research in the university, I‟m also grateful to my
family, all engineers and engineering companies who gave
me their hands to help, for granting and supporting me by
the data that I need to complete the research.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 04 Issue: 05 | May-2015, Available @ http://www.ijret.org 400
REFERENCES
[1] Smith, N.J. (2003) Apprisal, Risk and
Uncertainty.Thomas Telford Ltd., London, 13-87.
[2] Brauers, W.K. (1986) Essay Review Article:
Risk,Uncertainty and Risk Analysis. Long Range
Planning,Vol. 19, No. 6, 139-143.
[3] Chapman, C., Ward, S. (2003) Constructively simple
estimating: a project management example, Journal
of the Operational Research Society, Vol. 54, No. 10,
1050-1058.
[4] Snyder, L.V. (2005) Facility location under
uncertainty: A review. In: Lehigh University Dept. of
ISE Technical Report #04T-015 (accepted to publish
in IIE Transactions).
[5] del Cano, A. and Pilar de la Cruz, M. (2002)
Integrated Methodology for Project Risk
Management,Journal of Construction Engineering
and Management, Vol. 128, No. 6, 473-485.
[6] Ustinovicius, L., Popov, V., Migilinskas, D. (2005)
Automated management, modeling and choosing of
economically effective variant in construction,
Transport and Telecommunication (Proceedings of
International Conference "RelStat‟04" – Transport
and Telecommunication Institute, Riga, Latvia), Vol.
6, No. 1, 183-189.
[7] Gabbar, H., A., Aoyama, A., Naka, Y. (2004)
Modelbased computer-aided design environment for
operational design, Computers & Industrial
Engineering,Vol. 46, No. 3, 413-430.
[8] Popovas, V., Ustinovichius, L., Mikalauskas,
S.(2004) Technique for computer aided evaluation of
economic indicators of a construction project,
Selected papers of The 8th International Conference
"Modern building materials, structures and
techniques", Vilnius, Lithuania, May 19-21, 242-248.
[9] Leinonen, J. and Kähkönen, K. (2003) New
construction management practice based on the
virtual reality technology, In: 4D CAD and
Visualization in Construction. Issa, R.R.A., Flood, I.,
O'Brien, W.J. (Eds.), A.A. Balkema Publishers,
Lisse, 75-100.
[10] Xu, J.P., Wang, Sh., Shi., J.M. (2001) Superiority
Index Method for Multiple Attribute Decision-
Making under Uncertainty, In: MADIS Working
Paper MSPS-E-01-14, Tokyo University of Science,
Tokyo.
[11] AACE (2004). Estimating lost labor productivity in
construction claims, AACE International
Recommended Practice No. 25R-03, Morgantown.
[12] Herbsman, Z. and Ellis, R. (1990). “Research of
factors influencing construction productivity.”
Construction Management and Economics, Vol. 8,
No. 1, pp. 49–61. Lee, H. S., Ryu, H. G., Yu, J. H.,
and Kim, J. J. (2005). “Method for calculating
schedule delay considering lost productivity.” Journal
of Construction Engineering and Management,
ASCE, Vol. 131, No. 11, pp. 1147–1154
[13] Proverbs, D. G., Holt, G. D. and Olomolaiye, P. O.
(1998). “Factors impacting construction project
duration: A comparison between France, Germany
and the U.K.” Building and Environment, Vol. 34,
No. 2, pp. 197–204
[14] Hofstadler, Christian (2010). Monte-Carlo
Simulation in der Arbeits-/Projektvorbereitung –
Anwendung bei der Berechnung der Bauzeit. In:
Heck, Detlef/Hofstadler, Christian/Lechner, Hans
(Hrsg.): Arbeitsvorbereitung für Bauprojekte, 8.
Grazer Baubetriebs- und Bauwirtschaftssymposium.
Graz: Verlag der Technischen Universität Graz
[15] Hofstadler, Christian (2010). Application of the
Monte-Carlo method to determine the time required
for construction projects – Influence of ranges and
correlations on probability distribution. In: Faber,
Michael H./Köhler, Jochen/Nishijima, Kazuyoshi:
Applications of Statistics and Probability in Civil
Engineering. Zürich: Eidgenössische Technische
Hochschule Zürich
[16] ECI, TPM European Construction Institute (ECI),
Total Productivity Management volume 1:On-Site
Productivity, European Construction Institute, 1994
[17] Eversheim, Unternehmensorganisation W. Eversheim
(Hrsg.), Prozessorientierte
Unternehmensorganisation, Springer-Verlag, 1996
[18] Hager, Beschleunigungsmassnahmen Bauvorhaben
Dipl.-Ing. Henning Hager, Untersuchung von
Einflussgrössen und Kostenänderungen bei
Beschleunigungsmassnahmen von Bauvorhaben,
VDI Fortschrittsberichte Reihe 4:
Bauingenieurwesen, Nr. 106, VDI-Verlag GmbH,
Düsseldorf, 1991
[19] Rösel, Baumanagement Wofgang Rösel,
Baumanagement: Grundlagen, Technik, Praxis, 2.
überarb. Und erw. Auflage, Springer Verlag, 1992
[20] SBV, Bauwirtschaft in Zahlen Schweizerischer
Baumeisterverband, Schweizerische Bauwirtschaft in
Zahlen, Ausgabe 1997 (Aktualisierung 1998 folgt im
Juni!!)
[21] Schaleher, Projektmanagement Prof. Dr. H.R.
Schalcher, Projektmanagement,
Vorlesungsunterlagen WS 1996/97
[22] Doka:
http://www.doka.com/doka/de_global/planning/schoo
ls/pages/05394/index.php. 17.8.2009, 13:05

More Related Content

What's hot

Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based projecteSAT Journals
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingSHAZEBALIKHAN1
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSIAEME Publication
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...IRJET Journal
 
76 s201905
76 s20190576 s201905
76 s201905IJRAT
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and schedulingAditi Garg
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesMichael Pink
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis IOSR Journals
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1Ahmad Basim Hamza
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...IRJET Journal
 
1 b, evaluation of project
1 b, evaluation of project1 b, evaluation of project
1 b, evaluation of projectDr.R. SELVAM
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsSHAZEBALIKHAN1
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJTapesh Ajmera
 
Project controls
Project controlsProject controls
Project controlsAshok Kumar
 

What's hot (20)

Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Activity schedule and affective control of component based project
Activity schedule and affective control of component based projectActivity schedule and affective control of component based project
Activity schedule and affective control of component based project
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
76 s201905
76 s20190576 s201905
76 s201905
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
09 lecture project scheduling 1
09 lecture project scheduling 109 lecture project scheduling 1
09 lecture project scheduling 1
 
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
Planning, Scheduling, Resource Allocating and Tracking of Residential (G+2) V...
 
1 b, evaluation of project
1 b, evaluation of project1 b, evaluation of project
1 b, evaluation of project
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling Factors
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
 
Project controls
Project controlsProject controls
Project controls
 

Viewers also liked

Design and characterization of various shapes of microcantilever for human im...
Design and characterization of various shapes of microcantilever for human im...Design and characterization of various shapes of microcantilever for human im...
Design and characterization of various shapes of microcantilever for human im...eSAT Journals
 
Product optimization by scheduling formulation & optimal storage strategy...
Product optimization by scheduling formulation & optimal storage strategy...Product optimization by scheduling formulation & optimal storage strategy...
Product optimization by scheduling formulation & optimal storage strategy...eSAT Journals
 
Accelerated seam carving using cuda
Accelerated seam carving using cudaAccelerated seam carving using cuda
Accelerated seam carving using cudaeSAT Journals
 
Real time attendance and estimation of performance using business intelligence
Real time attendance and estimation of performance using business intelligenceReal time attendance and estimation of performance using business intelligence
Real time attendance and estimation of performance using business intelligenceeSAT Journals
 
Automatic transmission gearbox with centrifugal clutches
Automatic transmission gearbox with centrifugal clutchesAutomatic transmission gearbox with centrifugal clutches
Automatic transmission gearbox with centrifugal clutcheseSAT Journals
 
Modeling of size reduction, particle size analysis and flow characterisation ...
Modeling of size reduction, particle size analysis and flow characterisation ...Modeling of size reduction, particle size analysis and flow characterisation ...
Modeling of size reduction, particle size analysis and flow characterisation ...eSAT Journals
 
Prevention against new cell counting attack against tor network
Prevention against new cell counting attack against tor networkPrevention against new cell counting attack against tor network
Prevention against new cell counting attack against tor networkeSAT Journals
 
Wireless sensor network using zigbee
Wireless sensor network using zigbeeWireless sensor network using zigbee
Wireless sensor network using zigbeeeSAT Journals
 
An innovative fea methodology for modeling fasteners
An innovative fea methodology for modeling fastenersAn innovative fea methodology for modeling fasteners
An innovative fea methodology for modeling fastenerseSAT Journals
 
Assessment of groundwater quality for irrigation use
Assessment of groundwater quality for irrigation useAssessment of groundwater quality for irrigation use
Assessment of groundwater quality for irrigation useeSAT Journals
 
Comparitive analysis of doa and beamforming algorithms for smart antenna systems
Comparitive analysis of doa and beamforming algorithms for smart antenna systemsComparitive analysis of doa and beamforming algorithms for smart antenna systems
Comparitive analysis of doa and beamforming algorithms for smart antenna systemseSAT Journals
 
Statistical analysis of green energy power genartion using biogas methanation...
Statistical analysis of green energy power genartion using biogas methanation...Statistical analysis of green energy power genartion using biogas methanation...
Statistical analysis of green energy power genartion using biogas methanation...eSAT Journals
 
Effect of skew angle on static behaviour of reinforced concrete slab bridge d...
Effect of skew angle on static behaviour of reinforced concrete slab bridge d...Effect of skew angle on static behaviour of reinforced concrete slab bridge d...
Effect of skew angle on static behaviour of reinforced concrete slab bridge d...eSAT Journals
 
Phytochemical screening of orange peel and pulp
Phytochemical screening of orange peel and pulpPhytochemical screening of orange peel and pulp
Phytochemical screening of orange peel and pulpeSAT Journals
 
Defense mechanism for ddos attack through machine learning
Defense mechanism for ddos attack through machine learningDefense mechanism for ddos attack through machine learning
Defense mechanism for ddos attack through machine learningeSAT Journals
 
Effects of coconut fibers on the properties of concrete
Effects of coconut fibers on the properties of concreteEffects of coconut fibers on the properties of concrete
Effects of coconut fibers on the properties of concreteeSAT Journals
 
Comparative study of rc framed structures using spectra based pushover analysis
Comparative study of rc framed structures using spectra based pushover analysisComparative study of rc framed structures using spectra based pushover analysis
Comparative study of rc framed structures using spectra based pushover analysiseSAT Journals
 
Review paper on seismic responses of multistored rcc building with mass irreg...
Review paper on seismic responses of multistored rcc building with mass irreg...Review paper on seismic responses of multistored rcc building with mass irreg...
Review paper on seismic responses of multistored rcc building with mass irreg...eSAT Journals
 

Viewers also liked (18)

Design and characterization of various shapes of microcantilever for human im...
Design and characterization of various shapes of microcantilever for human im...Design and characterization of various shapes of microcantilever for human im...
Design and characterization of various shapes of microcantilever for human im...
 
Product optimization by scheduling formulation & optimal storage strategy...
Product optimization by scheduling formulation & optimal storage strategy...Product optimization by scheduling formulation & optimal storage strategy...
Product optimization by scheduling formulation & optimal storage strategy...
 
Accelerated seam carving using cuda
Accelerated seam carving using cudaAccelerated seam carving using cuda
Accelerated seam carving using cuda
 
Real time attendance and estimation of performance using business intelligence
Real time attendance and estimation of performance using business intelligenceReal time attendance and estimation of performance using business intelligence
Real time attendance and estimation of performance using business intelligence
 
Automatic transmission gearbox with centrifugal clutches
Automatic transmission gearbox with centrifugal clutchesAutomatic transmission gearbox with centrifugal clutches
Automatic transmission gearbox with centrifugal clutches
 
Modeling of size reduction, particle size analysis and flow characterisation ...
Modeling of size reduction, particle size analysis and flow characterisation ...Modeling of size reduction, particle size analysis and flow characterisation ...
Modeling of size reduction, particle size analysis and flow characterisation ...
 
Prevention against new cell counting attack against tor network
Prevention against new cell counting attack against tor networkPrevention against new cell counting attack against tor network
Prevention against new cell counting attack against tor network
 
Wireless sensor network using zigbee
Wireless sensor network using zigbeeWireless sensor network using zigbee
Wireless sensor network using zigbee
 
An innovative fea methodology for modeling fasteners
An innovative fea methodology for modeling fastenersAn innovative fea methodology for modeling fasteners
An innovative fea methodology for modeling fasteners
 
Assessment of groundwater quality for irrigation use
Assessment of groundwater quality for irrigation useAssessment of groundwater quality for irrigation use
Assessment of groundwater quality for irrigation use
 
Comparitive analysis of doa and beamforming algorithms for smart antenna systems
Comparitive analysis of doa and beamforming algorithms for smart antenna systemsComparitive analysis of doa and beamforming algorithms for smart antenna systems
Comparitive analysis of doa and beamforming algorithms for smart antenna systems
 
Statistical analysis of green energy power genartion using biogas methanation...
Statistical analysis of green energy power genartion using biogas methanation...Statistical analysis of green energy power genartion using biogas methanation...
Statistical analysis of green energy power genartion using biogas methanation...
 
Effect of skew angle on static behaviour of reinforced concrete slab bridge d...
Effect of skew angle on static behaviour of reinforced concrete slab bridge d...Effect of skew angle on static behaviour of reinforced concrete slab bridge d...
Effect of skew angle on static behaviour of reinforced concrete slab bridge d...
 
Phytochemical screening of orange peel and pulp
Phytochemical screening of orange peel and pulpPhytochemical screening of orange peel and pulp
Phytochemical screening of orange peel and pulp
 
Defense mechanism for ddos attack through machine learning
Defense mechanism for ddos attack through machine learningDefense mechanism for ddos attack through machine learning
Defense mechanism for ddos attack through machine learning
 
Effects of coconut fibers on the properties of concrete
Effects of coconut fibers on the properties of concreteEffects of coconut fibers on the properties of concrete
Effects of coconut fibers on the properties of concrete
 
Comparative study of rc framed structures using spectra based pushover analysis
Comparative study of rc framed structures using spectra based pushover analysisComparative study of rc framed structures using spectra based pushover analysis
Comparative study of rc framed structures using spectra based pushover analysis
 
Review paper on seismic responses of multistored rcc building with mass irreg...
Review paper on seismic responses of multistored rcc building with mass irreg...Review paper on seismic responses of multistored rcc building with mass irreg...
Review paper on seismic responses of multistored rcc building with mass irreg...
 

Similar to Calculation of the construction time systematic management of project uncertainties in rush projects in makkah

IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET Journal
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET Journal
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessIRJET Journal
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project managementIRJET Journal
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...IRJET Journal
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsIRJET Journal
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET Journal
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET Journal
 
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET-  	  Optimized Project Planning and Scheduling of Multistorey BuildingIRJET-  	  Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey BuildingIRJET Journal
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsIRJET Journal
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIRJET Journal
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET Journal
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptpisal3
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptxPranshiGoyal2
 
A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning Olivia Wilson
 
Lec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfLec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfGhulamQadirWaqar1
 

Similar to Calculation of the construction time systematic management of project uncertainties in rush projects in makkah (20)

IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project Success
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
H1303055462
H1303055462H1303055462
H1303055462
 
IRJET- Identification of Constraints and there Impact on Construction Pro...
IRJET-  	  Identification of Constraints and there Impact on Construction Pro...IRJET-  	  Identification of Constraints and there Impact on Construction Pro...
IRJET- Identification of Constraints and there Impact on Construction Pro...
 
Analysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction ProjectsAnalysis of Cost Over Run in Construction Projects
Analysis of Cost Over Run in Construction Projects
 
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
IRJET- Project Management, Planning and its Prospectus in the Context of Proj...
 
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
IRJET- Review Paper on “Budget and Schedule Overrun in the Construction Phase...
 
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET-  	  Optimized Project Planning and Scheduling of Multistorey BuildingIRJET-  	  Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
 
Time, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction ProjectsTime, Cost, and Quality Trade-off Analysis in Construction Projects
Time, Cost, and Quality Trade-off Analysis in Construction Projects
 
PERT
PERTPERT
PERT
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.pptCONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
 
Project Life Cycle final.pptx
Project Life Cycle final.pptxProject Life Cycle final.pptx
Project Life Cycle final.pptx
 
A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning A Project Management-Based Approach to Commissioning
A Project Management-Based Approach to Commissioning
 
Lec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfLec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdf
 
Planning And Managing The Project
Planning And Managing The ProjectPlanning And Managing The Project
Planning And Managing The Project
 

More from eSAT Journals

Mechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementsMechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementseSAT Journals
 
Material management in construction – a case study
Material management in construction – a case studyMaterial management in construction – a case study
Material management in construction – a case studyeSAT Journals
 
Managing drought short term strategies in semi arid regions a case study
Managing drought    short term strategies in semi arid regions  a case studyManaging drought    short term strategies in semi arid regions  a case study
Managing drought short term strategies in semi arid regions a case studyeSAT Journals
 
Life cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreLife cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreeSAT Journals
 
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialsLaboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialseSAT Journals
 
Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...eSAT Journals
 
Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...eSAT Journals
 
Influence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizerInfluence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizereSAT Journals
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementeSAT Journals
 
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...eSAT Journals
 
Factors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteFactors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteeSAT Journals
 
Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...eSAT Journals
 
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...eSAT Journals
 
Evaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabsEvaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabseSAT Journals
 
Evaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaEvaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaeSAT Journals
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...eSAT Journals
 
Estimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodEstimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodeSAT Journals
 
Estimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniquesEstimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniqueseSAT Journals
 
Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...eSAT Journals
 
Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...eSAT Journals
 

More from eSAT Journals (20)

Mechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavementsMechanical properties of hybrid fiber reinforced concrete for pavements
Mechanical properties of hybrid fiber reinforced concrete for pavements
 
Material management in construction – a case study
Material management in construction – a case studyMaterial management in construction – a case study
Material management in construction – a case study
 
Managing drought short term strategies in semi arid regions a case study
Managing drought    short term strategies in semi arid regions  a case studyManaging drought    short term strategies in semi arid regions  a case study
Managing drought short term strategies in semi arid regions a case study
 
Life cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangaloreLife cycle cost analysis of overlay for an urban road in bangalore
Life cycle cost analysis of overlay for an urban road in bangalore
 
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materialsLaboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
 
Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...Laboratory investigation of expansive soil stabilized with natural inorganic ...
Laboratory investigation of expansive soil stabilized with natural inorganic ...
 
Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of reinforcement on the behavior of hollow concrete block masonry p...
 
Influence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizerInfluence of compaction energy on soil stabilized with chemical stabilizer
Influence of compaction energy on soil stabilized with chemical stabilizer
 
Geographical information system (gis) for water resources management
Geographical information system (gis) for water resources managementGeographical information system (gis) for water resources management
Geographical information system (gis) for water resources management
 
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
 
Factors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concreteFactors influencing compressive strength of geopolymer concrete
Factors influencing compressive strength of geopolymer concrete
 
Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...Experimental investigation on circular hollow steel columns in filled with li...
Experimental investigation on circular hollow steel columns in filled with li...
 
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
 
Evaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabsEvaluation of punching shear in flat slabs
Evaluation of punching shear in flat slabs
 
Evaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in indiaEvaluation of performance of intake tower dam for recent earthquake in india
Evaluation of performance of intake tower dam for recent earthquake in india
 
Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...Evaluation of operational efficiency of urban road network using travel time ...
Evaluation of operational efficiency of urban road network using travel time ...
 
Estimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn methodEstimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of surface runoff in nallur amanikere watershed using scs cn method
 
Estimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniquesEstimation of morphometric parameters and runoff using rs & gis techniques
Estimation of morphometric parameters and runoff using rs & gis techniques
 
Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...Effect of variation of plastic hinge length on the results of non linear anal...
Effect of variation of plastic hinge length on the results of non linear anal...
 
Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...Effect of use of recycled materials on indirect tensile strength of asphalt c...
Effect of use of recycled materials on indirect tensile strength of asphalt c...
 

Recently uploaded

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spaintimesproduction05
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLManishPatel169454
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 

Recently uploaded (20)

Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
 
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELLPVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
PVC VS. FIBERGLASS (FRP) GRAVITY SEWER - UNI BELL
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 

Calculation of the construction time systematic management of project uncertainties in rush projects in makkah

  • 1. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 04 Issue: 05 | May-2015, Available @ http://www.ijret.org 394 CALCULATION OF THE CONSTRUCTION TIME- SYSTEMATIC MANAGEMENT OF PROJECT UNCERTAINTIES IN RUSH PROJECTS IN MAKKAH M. M. Mostafa1 , W.W.Al-Buzz2 1 Civil engineering Dept. Taif University, Al-Hawih, P.O.Box 888, Z.C.21974, Taif Saudi Arabia 2 Civil engineering Dept. Taif University, Al-Hawih, P.O.Box 888, Z.C.21974, Taif Saudi Arabia Abstract New fast track construction projects worth more than $100 billion are being implemented in Makkah to improve services being rendered to millions of pilgrims who come for Hajj and Umrah. The new development projects in Makkah, including largest expansion of the Grand Mosque. The time factor has become increasingly as an outstanding requirement on this construction projects. In the present work, the question "acceleration of construction projects" is moved in the center. Consequently, innovative structures, procedures and techniques are required for a time-oriented project management; consistently and purposefully focus on the reduction of process time and not to shrink back from entirely new, unfamiliar processes. so recommendations for the efficient management of construction projects always need to be developed taking into account the specific objectives and framework. This article discusses also the deterministic method, the simplified stochastic method and the application of the Monte-Carlo simulation as a stochastic method. With increasing of level of detail of the information content of the project and increases the calculation effort with the result that the range of the construction time decreases, thus the accuracy increases. Based on this range, finally the construction time of the building as well as the part times for the individual construction phases are determined. Keywords – Construction industry, Risk management, Construction Projects, project uncertainties, fast track projects, construction time, project management -------------------------------------------------------------------***------------------------------------------------------------------- 1. INTRODUCTION The construction time is an essential indicator of the project success, as both the construction cost and quality are significantly affected by the construction period. The construction time is usually given from the client. The construction time should be respected by the contractors or their subcontractors subsequently. The client has to manage those conditions as part of his contractual obligations that ensure the compliance of the construction time. New fast track construction projects worth more than $100 billion are being implemented in Mecca to improve services being rendered to millions of pilgrims who come for Hajj and Umrah. The new development projects in Mecca, including largest expansion of the Grand Mosque. An important requirement for a fast track construction project is the stability in the project and the project environment. To calculate the construction time, quantities and performance rates are required. If the project is being considered as a whole, for example, the gross volume of the building or tunnel length in the transport infrastructure is used for the quantity calculation. The quantities are calculated from the plans. The precision of the calculation of quantities depends on the considered phase of the project and the associated level of detailing. In early project phases, the calculation of quantities can be specified only in larger ranges. From these uncertainties and due to the fact that the nature and scope of activities and the range of the activity performance cannot be accurately described or identified, it is also possible to estimate the production factors only within a range. These uncertainties in earlier stages of the project are higher than in later ones. Based on the level of information, trying possible combinations of the production factors will be developed in order to get approaches for the production performance. With the production performance, on the one hand the client can close on the construction time and on the other hand the bidders or contractors subsequent to the required use of production factors. 2. AIMS OF THE STUDY If you can determine the specific project requirements highly efficient procedures only as a function, so recommendations for the efficient management of construction projects always need to be developed taking into account the specific objectives and framework. In the present work, the question "acceleration of construction projects" is moved in the center. This is because the demand structures and needs in the real estate market are changing faster and faster. A short planning and execution time is becoming increasingly clearer to an outstanding performance feature of construction projects. Expected and more often in the future a particularly short duration even become a decisive factor in the choice of the project team.
  • 2. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 04 Issue: 05 | May-2015, Available @ http://www.ijret.org 395 The acceleration is even from the construction perspective an interesting challenge, but it is neither an exclusively technical problem nor a matter of scheduling. The acceleration of construction processes is primarily an organizational and "group dynamics" challenge for the management. It must never be based on the setting, but everything as before, but a bit faster. If the short duration of a project is based only on Pressure so suffers both the psyche of all interested parties and the quality of the work. Consequently, innovative structures, procedures and techniques are required for a time-oriented project management; consistently and purposefully focus on the reduction of process time and not to shrink back from entirely new, unfamiliar processes. 3. THE TIME FACTOR AS A CHALLENGE FOR THE CONSTRUCTION PROJECT MANAGEMENT In recent years, the time factor has become increasingly as an outstanding requirement on a construction project. This is due to an attitude change towards the real estate and due to a tougher economic environment. A construction must more often not only cheap and functional, but also can be offered to the tenant or buyer as soon as possible. Particularly in the commercial and industrial sector buildings are also becoming less as long-term investments and more and more considered as a commodity. If "time to market" is the decisive criterion, so long-term construction processes cannot be accepted. Industrial construction projects often have a compulsory given time limit - and often to be available only for a certain period of time. 3.1 Restrictions in the Fast-Track Construction Process Although the factor still so clearly moved in the foreground, but all other relevant objectives of the work must lie within a common or usual objectives scope. A high speed may not be acquired through poor quality or unduly high costs. The investment in a plant or in an investment property is only useful if the construction costs stay within a reasonable budget and the functionality is fully guaranteed. 3.2 Acceleration as an Organizational Problem Suitable tools and the required basic knowledge of the project management are a prerequisite, they bring alone but no acceleration of the construction process. Also the constructional engineering provides today many approaches for speeding up the construction work, but their effectiveness begins only at an advanced stage of the long construction process. If they are also not included in the early stages of the project in the planning, so they only develop a minimal effect. In contrast, when considered as whole project cycle time period from the decision of the implementation of a building till its commissioning, so often the early decisions and concepts of the customer, the authorization phases or the pre-engineering project will be the more time-consuming sections. With the acceleration of construction projects is then rather more an organizational than a technical problem. The determination of the basic organizational principles take places, together with many other dominant elements, even in the earliest stages of the project through the client. 4. PRAGMATIC ACCELERATION AND TACTICS INNOVATIVE TIME MANAGEMENT The problem of a very tight schedule is not new for the construction practices. It is confronted with a demand for a very fast implementation of projects and usually reacts with the following tactics.  "False shortening" of the operation duration When scheduling of construction projects is not infrequently assumed from luxuriantly designed schedules. A first reaction of the urging of the client to an acceleration is now to reduce the long-term operation durations. However, it is not a real time reduction, but only to the reduction of unnecessary time reserves.  Acceleration through consistent project management Since in many project planning, not the same attention comes up to time-related aspects as the cost or the functionality, a first acceleration can be achieved by the intensification of scheduling and monitoring. By increasing use of techniques of scheduling, an optimization is obtained. However, only negligence can be prevented and deadlines are met more easily. With these measures, neither innovative methods nor organizational changes are involved.  Project acceleration by streamlining and concentration In the context of known project processes, a change can take place in the priorities of the Costs and the design of the deadlines. Under our clear prioritization of the period falls easier on all parties, the streamlining of all activities and deadline focus formation. Backed by a strong, competent project management, with emphasis forms the corresponding priorities in the formulation of guidelines, priorities set by current decisions and allocation of resources and (out) and a rigorous, advanced project controlling operates, a substantial acceleration can be achieved.  Minimum project duration by massive use of resources (crash projects) Already, the construction industry is in a position under exceptional conditions to cause massive acceleration. This is usually done by the extraordinary use of resources, and by the application of special authority and an extraordinary motivation impact for all involved. However, this type of acceleration has its price. Other activities will be postponed or left undone, and the project team is under a non constant to be maintained pressure. This approach should therefore remain an exception.
  • 3. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 04 Issue: 05 | May-2015, Available @ http://www.ijret.org 396 Acceleration due to parallelization and overlap Duration of the - Overall process + Higher coordination costs Acceleration due to increased use of resources Fig.1. Duration of the process as a function of increased resource utilization and parallelization on the one hand and increasing coordination effort on the other hand The parallelization of sub-processes offers as well as the higher simultaneous use of resources an enormous acceleration potential. But there is a significantly greater coordination and communication requirements, which in turn can cause loss of time. 5. PRINCIPLES FOR THE ACCELERATION OF CONSTRUCTION PROJECTS The duration of an overall process is determined by the processing time, the waiting time between the individual processing steps and the time sequence of individual sub- processes. The easiest way is to shorten the processing time. This can be done through the use of additional resources or technical tools, but predominantly through the use of know- how. The waiting times between processing cycles can be traced back to missing information or to a suboptimal organizational structure. To their reduction especially the interactions between the involved subsystems or processes are optimized. For each information flow and every interaction takes time and increases the risk of waiting times. The largest accelerating effect can be achieved by clever variations in the sequence of the individual sub- processes of an overall process. Corresponding sequence patterns can be aimed on the elimination of individual sub- processes, their overlapping or simultaneous processing, but also to the "redundant" problematic part machining processes. Accelerating action on these three levels (processing time, reduced wait times or less interactions and variation in the sequence of sub-processes) are always interrelated relationships. Therefore, a key objective in the organizational design must be the reduction of interactions and dependencies by decomposition. It creates the prerequisite for rational to edit individual packages can be formed and can be connected in parallel processes efficiently. 5.1 Time Effectively Process Elements The traditional project management focuses on the optimization of specified sequences by the use of traditional processing techniques of scheduling. It begins with an optimal use of resources and the elimination of non-value added time periods. In an innovative time management, however, are all basic possibilities of action of interest that have an influence on the duration of the overall process. This can be derived from the following schematic illustration of a sequential workflow in the industry. In construction projects, exist the same approaches for acceleration:  Reduction in the processing time: The processing time depends on the human, technical and professional capacity. Management has influence through the planning and the supply of the necessary resources and the selection of appropriate technical tools.  Reduction of waiting- or lay-time between the processing steps: between the individual work steps, it always comes back to lay time. This may due to lack of capacity (for seamless further processing) or  Be caused from the available information. You will face the classic management especially with efficient scheduling and resource planning. A higher-level organizational approach seeks, however, after the reduction of dependencies or interactions between individual processing steps.  The sequence of sub-processes: In a conventional approach, the individual steps are processed sequentially. The nested, parallel or early implementation of processes represents a time- effective alternative to the sequential processing. 6. DETERMINANTS OF FAST-TRACK PROJECT The speed of construction projects is predetermined in the earliest stages of the project by the customer. He is responsible for ensuring that the truly dominant performance determinants are taken into account as early as the project start. The ability of the co-operation of the overall system. The rapid construction project is the result of many individual measures, but finally the performance of an optimally functioning, highly productive overall system. The most important approaches:  The ability of the co-operation of the overall system: The rapid construction project is the result of many individual measures, but finally the performance of an optimally functioning, highly productive overall system.  The complexity of the structure: the simpler the building and the construction process are structured, the greater the acceleration potential.  The collaboration between the client and the contractor: the purposeful work on all parties to a clearly defined end state toward the faster the project proceeds. Uncertainties and changes in the requirements slow down the project by a variety of information gaps, additional clarifications and multiple repetition of work already undertaken.
  • 4. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 04 Issue: 05 | May-2015, Available @ http://www.ijret.org 397 7. RELATIONSHIP BETWEEN COMPLEXITY AND PROJECT DURATION The more parties involved in a project, the more complicated the construction tasks to be solved, and the more objectives or possible developments (high dynamic range) to be taken into consideration, the more difficult it is the design of objective-based, efficient and above all fast project process. There is a direct relationship between the complexity of a project and its duration. So take for example, many projects longer than necessary, or get out of hand,  By the "construction" of unnecessary dependencies in the task and the project organization, for example by emphasizing claims of secondary importance, unnecessary complexity is established.  High flexibility and late decisions are sought by many clients and parties involved in the project have to work in unsafe or variable objects.  The project organizations by escalating functional differentiation and Long information paths are unnecessarily bloated. Through many dependencies decisions are delayed and responsibilities “diluted". 8. RECOMMENDATIONS FOR THE ACCELERATION OF CONSTRUCTION PROJECTS The acceleration of construction projects is primarily a question of the organization. The project management must always be oriented from the first phases of the project in hand, through an appropriate design of the project and project organization to get all activities with a high speed. Thus, the contribution constructional and technical measures cannot be negated, These will bring their accelerating effect but only in the later stages of the project and only if appropriate conditions have been created previously. 9. BASES FOR THE CALCULATION OF CONSTRUCTION TIME FOR THE EXECUTION STAGE The number of parameters for the calculation of the construction period depends on the project phase. Some few values are needed for rough construction period inquiries more hundred values for the calculations for detailed considerations are depending on consideration depth required. The calculation equations are represented and described for duration, performance and complete cost value in the following which are required for a rough calculation in the phase's building shell. These calculation equations form the base for all further methods of calculation. As production quantity cubic meters of reinforced concrete will be used. The presented calculation methods do not replace detailed considerations for the calculation of construction time and construction costs. 10. METHODS 10.1 Deterministic Approach The length of the construction time has essential influence on the construction and very well also on the planning process. At ‚normal„ construction time, where the limits don't have to be exceeded for economic use of the factors of production, these factors still can be planned optimally. The shorter the construction time, the higher also is the demands to the planning process. By the project management for a short construction time, it must be considered, for example, how is the lack, because it is not installable, cranes can be compensated by other means of transport or other construction method. As a rule, too short construction Times are provided for construction projects with regard to productive use of the factors of production. However, long lead times contrast for competitions and the planning with the short construction times. 10.1.1 Calculation of the duration of the Reinforced Concrete Works The duration is calculated in the deterministic approach as a scalar quantity. For each calculation passage scalar quantity for each parameter will be used. As input parameters for the calculation, for example, base values are used. Basing on these base values in terms of opportunity and risk assessment, the final values are determined for the calculation passage. For Eq. 1 with the average values for the quantity of concrete BTM [m³] and performance LSTB [m³/d] the duration DSTB [d] is calculated. STB M STB L BT D  (1) To the consideration of disturbances in the calculation, a buffer PUSTB,Z [%] should be included which leads to the following equation.          100 1 , , ZSTB STBPUSTB PU DD (2) The amount of buffer depends on the complexity of the construction and the number of construction stages in winter. From our experiences it has shown that the buffer is between 5 and 15%. In 'normal' construction time the buffer should be at 5% and at least at 15% for a very short construction time.
  • 5. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 04 Issue: 05 | May-2015, Available @ http://www.ijret.org 398 The buffer takes into account, for example, additional performance or project unawareness 10.1.2 Daily Performance of the Reinforced Concrete Works The average daily performance for the reinforced concrete work LSTB [m³/d] is calculated according to to Eq. 3 In the numerator it result in multiplying the number of workers AKSTB [Std/h] with the daily working AZSTB [h/d] the daily labor hours. The denominator is the total cost value AWSTB [Std/m³] for the reinforced concrete work. STB STBSTB STB AW AZAK L   (3) In Figure 1 are shown decisive influences on performance. This serves as an exemplary presentation of a qualitative assessment of risks and opportunities portfolio. The average performance can be calculated for the entire construction or individual structural components. Depending on the level of detail of the project and the project stage, typically rise the accuracy of the input variables and thus the calculation result. Fig 1: key influences on performance [Hofstadler] 10.2 Simplified Stochastic Approach For the simplified stochastic calculation method also deterministic calculation rules are to develop. However, for the calculation operation is not one value per parameter required, but three values. In addition, three values must be chosen for the probability of occurrence. 10.2.1 Flexible Method For the respective input values in the calculation equations respectively three values are used, namely a minimum value, a most frequent value and a maximum value. These values are multiplied by the respective, subjectively defined probability of occurrence. By adding the three products you get the subjectively most probable value For the probability of occurrence (PEW,i) applies::  1,iEWp (4) 10.2.2 PERT-Method The PERT method assumes a fixed distribution type, the BETA-distribution. In the PERT method three input values to calculate the desired value is required. The counters are the minimum and maximum value, unweighted and weighted with 4 common value used. The three values are added together and the weighted average the weighted mean average value formed from this. 6 valuecpessimisti1aluefrequent v4valueOptimistic1  Duration (5) In addition to this balanced approach, there are two asymmetric approaches. Werner argues in his dissertation, an optimistic and pessimistic calculation equation. In the optimistic calculation, the weighted value higher than the optimistic and pessimistic, the calculation is done according to Eq. 6 6 valuecpessimisti1aluefrequent v3valueOptimistic2  Duration (6) On the other hand, it is by the pessimistic analysis the pessimistic value is evaluated with a higher value. The calculation is performed according to Eq. 8 6 valuecpessimisti2aluefrequent v3valueOptimistic1  Duration (7) 10.3 Monte-Carlo Simulation The Monte Carlo method, for example, allows the calculation of the probability distribution for the construction time. In an arbitrary number of iterations generates a software program (in this case @ RISK) for the input values random values, which are used in each pre- defined probability density functions, and combines them for a given calculation rule (the calculation equations of the deterministic method), the distribution function of the results.  The input parameters are:  fluctuation margin
  • 6. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 04 Issue: 05 | May-2015, Available @ http://www.ijret.org 399  The most probable value (if possible according to the selected distribution function)  Distribution functions For the stochastic calculation method, individual selected parameters are proved with a distribution function (e.g. flow chart for calculating the construction time shown in Figure 3). The distribution functions are chosen so that they come closest to reality. Since for the individual parameters still there are not clear characteristic distribution functions, asymmetric triangles will be used here. For each parameter in the flow chart shown values, respectively values are given for the optimistic and pessimistic value and the most probable value. Fig 2: Calculation mode for the Monte-Carlo simulation [Hofstadler] The values are determined in consideration of the construction management and construction-specific boundary conditions. As a basis for the values, for example, internal company records or data from the literature (e.g. working time guidelines for building superstructures) are used. For example, if the total value of expenditure considered and asymmetric triangular distributions is used, a most probable value will be specified by the cost values for shuttering work, reinforcement and concreting. Based on these values, the opportunities and risks in the course of a situation analysis will be evaluated, which means it is used to determine to what extent these values fall below or could be exceeded. By including of considerations of probability in the calculations, a significant improvement in the decision- making is possible. Due to the used range and distribution functions, probability distributions are presented according to selected number of iterations for the required results. For the calculation shown in Figure mode is as a result of the total cost value (AWSTB) the daily performance (LSTB, WS), a period with no buffer (DSTB, WS) and the duration with buffer (DSTB, WS, PU ) respectively output a probability distribution. For the calculation mode shown in Figure 6 is as a result of the total cost value (AWSTB) ,the daily performance (LSTB,WS), a duration without buffer (DSTB,WS) and the duration including buffer (DSTB,WS,PU) each has a probability distribution output. 11. CONCLUSION& RECOMMENDATIONS The general recommendation relating to the organization must be theoretically that all processes in the project must be organized, that the individual sub-processes should be executed as quickly as possible, that there will be no lay- or waiting-times between the individual processing steps, and that as many sub-processes can be parallel implemented. However, construction projects are complex systems in which all works closely interlocked and run in a tight network of dependencies. From project to project and even from one project to the next phase, the tasks, work priorities and relationships in the system will change. The task of the project management is always defrenciated - and especially with the demand for acceleration - specifically customized solutions must be adapted. To calculate the construction time, production volumes on the one hand and the production performance on the other hand are required for rough considerations. If the entire project is split into sub-systems, the relationships between the systems (e.g., building shell construction, Construction development, construction Engineering) should be defined. In addition to the uncertainties in the calculation of the partial times for each system now also the uncertainties must be recorded in the relationships and to be evaluated. Here for each project, the opportunities and risks need to be reviewed. As a starting point here are the experiences from past projects that are only useful if the resulting data can be transparently analyzed. First base values can be determined, based on the chances- and risk assessment, optimistic and pessimistic values are determined. The preparation of the deterministic calculation rule forms the basis for the stochastic methods. If the stochastic calculation methods systematically and dutifully applied, their results form a good basis for the interpretation of output and ultimately for decision making. Further studies for the characteristics of distribution functions for cost values and construction parameters (such as formwork ratio, reinforcement ratio) can be performed. The effects of correlations between the input variables are also examined for their relevance. The results will to be published. ACKNOWLEDGMENTS First of all I would like to express my great thanks to God Almighty for helping me to finish this humbly research, and this is my pleasure to express my special thanks to “Taif University Administration”, for their full support to the scientific research in the university, I‟m also grateful to my family, all engineers and engineering companies who gave me their hands to help, for granting and supporting me by the data that I need to complete the research.
  • 7. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 04 Issue: 05 | May-2015, Available @ http://www.ijret.org 400 REFERENCES [1] Smith, N.J. (2003) Apprisal, Risk and Uncertainty.Thomas Telford Ltd., London, 13-87. [2] Brauers, W.K. (1986) Essay Review Article: Risk,Uncertainty and Risk Analysis. Long Range Planning,Vol. 19, No. 6, 139-143. [3] Chapman, C., Ward, S. (2003) Constructively simple estimating: a project management example, Journal of the Operational Research Society, Vol. 54, No. 10, 1050-1058. [4] Snyder, L.V. (2005) Facility location under uncertainty: A review. In: Lehigh University Dept. of ISE Technical Report #04T-015 (accepted to publish in IIE Transactions). [5] del Cano, A. and Pilar de la Cruz, M. (2002) Integrated Methodology for Project Risk Management,Journal of Construction Engineering and Management, Vol. 128, No. 6, 473-485. [6] Ustinovicius, L., Popov, V., Migilinskas, D. (2005) Automated management, modeling and choosing of economically effective variant in construction, Transport and Telecommunication (Proceedings of International Conference "RelStat‟04" – Transport and Telecommunication Institute, Riga, Latvia), Vol. 6, No. 1, 183-189. [7] Gabbar, H., A., Aoyama, A., Naka, Y. (2004) Modelbased computer-aided design environment for operational design, Computers & Industrial Engineering,Vol. 46, No. 3, 413-430. [8] Popovas, V., Ustinovichius, L., Mikalauskas, S.(2004) Technique for computer aided evaluation of economic indicators of a construction project, Selected papers of The 8th International Conference "Modern building materials, structures and techniques", Vilnius, Lithuania, May 19-21, 242-248. [9] Leinonen, J. and Kähkönen, K. (2003) New construction management practice based on the virtual reality technology, In: 4D CAD and Visualization in Construction. Issa, R.R.A., Flood, I., O'Brien, W.J. (Eds.), A.A. Balkema Publishers, Lisse, 75-100. [10] Xu, J.P., Wang, Sh., Shi., J.M. (2001) Superiority Index Method for Multiple Attribute Decision- Making under Uncertainty, In: MADIS Working Paper MSPS-E-01-14, Tokyo University of Science, Tokyo. [11] AACE (2004). Estimating lost labor productivity in construction claims, AACE International Recommended Practice No. 25R-03, Morgantown. [12] Herbsman, Z. and Ellis, R. (1990). “Research of factors influencing construction productivity.” Construction Management and Economics, Vol. 8, No. 1, pp. 49–61. Lee, H. S., Ryu, H. G., Yu, J. H., and Kim, J. J. (2005). “Method for calculating schedule delay considering lost productivity.” Journal of Construction Engineering and Management, ASCE, Vol. 131, No. 11, pp. 1147–1154 [13] Proverbs, D. G., Holt, G. D. and Olomolaiye, P. O. (1998). “Factors impacting construction project duration: A comparison between France, Germany and the U.K.” Building and Environment, Vol. 34, No. 2, pp. 197–204 [14] Hofstadler, Christian (2010). Monte-Carlo Simulation in der Arbeits-/Projektvorbereitung – Anwendung bei der Berechnung der Bauzeit. In: Heck, Detlef/Hofstadler, Christian/Lechner, Hans (Hrsg.): Arbeitsvorbereitung für Bauprojekte, 8. Grazer Baubetriebs- und Bauwirtschaftssymposium. Graz: Verlag der Technischen Universität Graz [15] Hofstadler, Christian (2010). Application of the Monte-Carlo method to determine the time required for construction projects – Influence of ranges and correlations on probability distribution. In: Faber, Michael H./Köhler, Jochen/Nishijima, Kazuyoshi: Applications of Statistics and Probability in Civil Engineering. Zürich: Eidgenössische Technische Hochschule Zürich [16] ECI, TPM European Construction Institute (ECI), Total Productivity Management volume 1:On-Site Productivity, European Construction Institute, 1994 [17] Eversheim, Unternehmensorganisation W. Eversheim (Hrsg.), Prozessorientierte Unternehmensorganisation, Springer-Verlag, 1996 [18] Hager, Beschleunigungsmassnahmen Bauvorhaben Dipl.-Ing. Henning Hager, Untersuchung von Einflussgrössen und Kostenänderungen bei Beschleunigungsmassnahmen von Bauvorhaben, VDI Fortschrittsberichte Reihe 4: Bauingenieurwesen, Nr. 106, VDI-Verlag GmbH, Düsseldorf, 1991 [19] Rösel, Baumanagement Wofgang Rösel, Baumanagement: Grundlagen, Technik, Praxis, 2. überarb. Und erw. Auflage, Springer Verlag, 1992 [20] SBV, Bauwirtschaft in Zahlen Schweizerischer Baumeisterverband, Schweizerische Bauwirtschaft in Zahlen, Ausgabe 1997 (Aktualisierung 1998 folgt im Juni!!) [21] Schaleher, Projektmanagement Prof. Dr. H.R. Schalcher, Projektmanagement, Vorlesungsunterlagen WS 1996/97 [22] Doka: http://www.doka.com/doka/de_global/planning/schoo ls/pages/05394/index.php. 17.8.2009, 13:05