Successfully reported this slideshow.
We use your LinkedIn profile and activity data to personalize ads and to show you more relevant ads. You can change your ad preferences anytime.

Sunset cove restoration project -update

19 views

Published on

update by the Jamaica Bay Ecowatchers on sunset cove restoration project as the project is now completed for the phase 1 construction and plans for the volunteer planting and phase 2 construction

Published in: Environment
  • Be the first to comment

  • Be the first to like this

Sunset cove restoration project -update

  1. 1. Sunset Cove---Update u 12 acre site u Spectacular views of Jamaica Bay and NYC u Located at extreme south end of Broad Channel u NYC Parks land adjacent to NPS wetlands u Wetland cove and upland area u Unique Opportunity to restore Degraded shoreline area u Currently the largest Restoration Project underway in Jamaica Bay
  2. 2. History u Small Marina since the 40’s u Marina greatly expanded thru illegal fill in 1970’s and 80’s. u Court action at both state and Federal level u Resulted in 1998 decision to reduce size u 2008 decision for additional violations led to state acquisition u 2008 Land put under jurisdiction of NYC DCAS
  3. 3. History ´ Broad Channel Civic Association led effort to have area deeded to NYC Parks. ´ Worked thru Councilman Ulrich’s office to have transferred to NYC Parks in 2009 ´ BCCA passed unanimous resolution in February of 2010 endorsing wetlands restoration, upland forest, walking trails, boardwalk plan. ´ BCCA plan submitted to NYC PARKS RFEI— only plan submitted
  4. 4. Features of Project: u • Restoration of approximately 4 acres of low marsh. u • Restoration of approximately 0.5 acres of high marsh. u • Restoration of approximately 4 acres of scrubland. u • Restoration of approximately 3.5 acres of coastal forest. u • Restoration of approximately 1,000 linear feet of upland perimeter. u • Construction of boardwalk, outdoor classroom and perimeter walking trail/Berm and Eco-dock for student use .
  5. 5. Sunset Cove 2006
  6. 6. Sunset Cove 2013
  7. 7. Phase 1 funding u NEWIPCC EPA Grant - $60,000 u State EPF Grant - $50,000 u DOI NFWF Grant - $4,850,000 u DEC Mitigation Payments u Transco Williams - $500,000 u Dept of Sanitation - $750,000 u NYCDOT - $990,000 u DPR - $70,000 (Beach 108 Bulkhead Project) u DEP Design Contribution - $50,000 u Total original Funding expectation- $7,320,000
  8. 8. Partners u NYC Parks u NYC DEP u NYS DEC u National Parks Service u Jamaica Bay Ecowatchers u American Littoral Society
  9. 9. Dept of Interior Grant awarded for 4.8 Million
  10. 10. Funding shortfall u Project out for bid in May 2017 u Minimum bid received 7 million short u Project in Jeopardy and DOI Funding u Ecowatchers and BCCA lobby Mayors office u Elected officials lend full support u October 6th Funding received from Mayors Office
  11. 11. Press Conference- October 6th 2017
  12. 12. Plantings u Over 2000 container plants and trees planted by contractor u 200,000 plugs planted -100,000 of these will be Spartina planted by volunteers supervised by the American Littoral Society Volunteers are needed
  13. 13. Community Planting u 100,000 plugs of Spartina u Managed by the American Littoral Society u Volunteer dates u June 8 and 9 - Small group, test pilot events u June 12, 13, 14 - Corporate, club groups, mid-week u June 15 - Open Public Day - large volunteer effort u June 29 and 30 - Public Volunteer effort continued COME ON OUT AND GET INVOLVED !!
  14. 14. Phase 2 Funding-- } Total final cost estimate $ 1.8 Million } Funding Sources-- ◦ Broad Channel CRZ NY Rising- -----$500,000 ◦ Queens Borough President Melinda Katz--$1,000,000 ◦ Assemblywoman Amato - $125,000 ◦ State Senator Addabbo--$ 175,000 ◦ Broad Channel Civic thru Participatory Budget-$200,00
  15. 15. Boardwalk and Entrance to Park –Phase 2
  16. 16. fun
  17. 17. u
  18. 18. Wetlands Experience
  19. 19. Boardwalk design using restored lumber from Rockaway Boardwalk
  20. 20. Learning/Research-ECO DOCK
  21. 21. Solstice Markers

×