3. 3
STONY CREEK MARSH ISLAND
Field Investigations Completed:
• NPS Special Use Permit issued 26 May 2023
• ERDC Hydrodynamic Data Collection
Instrument Deployment: 27 May - 2 June 2023
Instrument Service/Interim Data Download: 6-9 November 2023
• Data to be used to validate a system-wide hydrodynamic numeric model developed
to evaluate sediment flux, stabilization techniques and restoration alternatives for the
marsh islands.
Green – Wave/Current Profiler
Blue – Wave Sensors
Magenta – Water Level Loggers
Red Lines – Roving Current Survey
Surficial Sediment Grabs (not shown)
Atmospheric Sensor (not shown)
4. 4
STONY CREEK MARSH ISLAND
Field Investigations Completed:
• Bathymetric Survey: 16 June – 2 July 2023
• Awarded Biological Ecological Cultural Resources Contract
(BECR) Task order: 20 September 2023
• Biological Surveys: 23 October – 3 November 2023
Wetland Delineation
Bio-benchmark Surveys
Vegetative Mapping (for Hummock Relocation)
5. 5
STONY CREEK MARSH ISLAND
Future Field Investigations
Topographic Survey (A) (Pending
SUP for Drone Use- January 2024)
Geophysical Sampling
(Pending SUP - Spring 2024)
Standard Penetration Testing (SPT) and
Dilatometer Testing (DMT)
6. 6
STONY CREEK MARSH ISLAND
30% Draft Design Compared to Feasibility Design
• Based on publicly
available NOAA data,
awaiting higher
resolution topographic
survey
• High resolution
bathymetric data
indicated significantly
greater offshore depths
when compared to FS
study data- yielding
decreased restoration
acreages and increased
sand volume needed
• Preservation of healthy contiguous existing marsh,
assumed to be at or near lower end of design elevations
7. 7
STONY CREEK MARSH ISLAND
Shoreline Stabilization Options
Christmas Tree
Fascines
Terraced Coir
Logs
Quick Reef/
ECOncrete
Decisions on types and placement
will be informed by hydrodynamic
modeling results.
8. 8
STONY CREEK MARSH ISLAND
• Complete 30% Designs
(December)
• Complete Field Sampling:
Topographic Survey (January)
and Geotechnical Sampling
(Spring)
• Complete 60%, 90% and 100%
design progressions
• Execute Project Partnership
Agreement for Construction
• Construction coordinated
with Navigation Project (end
2025)
Next Steps
9. 9
HRE - Fresh Creek Restoration
• Received $500,000 to initiate Engineering and Design in 2023
• Design Agreement under review by NYC Law for approval to execute
• Remaining Funds ($2,750,000) included in the House and Senate
Appropriation Bills
10. 10
HRE – Duck Point Marsh Island Restoration
• All Federal funds ($2,275,000) were included in the 2022 Bipartisan
Infrastructure Law Summer Spend Plan.
• Design Agreement under review by NYC Law for approval to execute
November20, 2023 (high tide)
11. Spring Creek North Ecosystem Restoration
(Continuing Authorities Program)
• Restoration of 43.2-acres including:
18.8 acres of wetlands
24.4 acres of maritime uplands
• Restoration through excavating and
recontouring uplands to intertidal
elevations, removing invasives
species and replanting; as well as
restoring existing degraded wetlands
with Thin Layer Placement techniques
• Regulatory Permit Package submitted
to NYSDEC in May 2023
• 100% DesignsCompleted
November2023
• Designs are under Team Review
with plannedapproval by
Christmas
• Ready to Advertise early 2024 and
ConstructionSummer2024
12. Spring Creek South (Howard Beach) Multi-purpose
Feasibility Study
Ecosystem Restoration and Coastal Storm Risk Management (CSRM)
• Focus on solutions that avoid contamination
• Focus on CSRM features in Shellbank and Hawtree Basins
• Feasibility Cost Share Agreement under negotiation
Spring CreekSouth
NPS Remediation
13. 13
HRE
Restoration
Sites in
Jamaica Bay
327 acres of habitat
restoration:
- 206 acres of
marsh islands
- 121 acres along
perimeter
155,000 CYD
62 acres
41 acres
80 acres
215,000 CYD
40 acres
285,000 CYD
29 acres
328,000 CYD
24 acres
352,000 CYD
29 acres
10 acres
2024
2023
2022
14. ADDITIONAL HRE RESTORATION PROJECTS
OUTSIDE OF JAMAICABAY
14
Ongoing Design:
• Flushing Creek (NYCDEP)
• Bronx Zoo & Dam/Stone Mill Dam (NYC Parks)
• Oysters at Naval Weapons Station Earle (NJDEP)
Future Design ($500,000 BIL Summer Spend Plan):
• Garth Woods/Harney Road (WestchesterCounty)
Future Feasibility Study ($500,000 House/Senate Appropriations Bill):
• Harlem River Restoration (NYCDEP)