SlideShare a Scribd company logo
1 of 15
Download to read offline
217
217
217
200
200
200
255
255
255
0
0
0
163
163
163
131
132
122
239
65
53
110
135
120
112
92
56
62
102
130
102
56
48
130
120
111
237
237
237
80
119
27
252
174
.59
“The views, opinions and findings contained in this report are
those of the authors(s) and should not be construed as an
official Department of the Army position, policy or decision,
unless so designated by other official documentation.”
HUDSON RARITAN ESTUARY ECOSYSTEM
RESTORATION – JAMAICA BAY UPDATE
JAMAICABAY TASK FORCE MEETING
LISA BARON
PROJECT MANAGER, CIVIL WORKS
NEW YORK DISTRICT
NOVEMBER 30, 2023
1
File Name
File Name
2
Agenda
Spring Creek North
Spring Creek South
HRE- Fresh Creek
HRE- Duck Point
HRE- Stony Creek
3
STONY CREEK MARSH ISLAND
Field Investigations Completed:
• NPS Special Use Permit issued 26 May 2023
• ERDC Hydrodynamic Data Collection
 Instrument Deployment: 27 May - 2 June 2023
 Instrument Service/Interim Data Download: 6-9 November 2023
• Data to be used to validate a system-wide hydrodynamic numeric model developed
to evaluate sediment flux, stabilization techniques and restoration alternatives for the
marsh islands.
Green – Wave/Current Profiler
Blue – Wave Sensors
Magenta – Water Level Loggers
Red Lines – Roving Current Survey
Surficial Sediment Grabs (not shown)
Atmospheric Sensor (not shown)
4
STONY CREEK MARSH ISLAND
Field Investigations Completed:
• Bathymetric Survey: 16 June – 2 July 2023
• Awarded Biological Ecological Cultural Resources Contract
(BECR) Task order: 20 September 2023
• Biological Surveys: 23 October – 3 November 2023
 Wetland Delineation
 Bio-benchmark Surveys
 Vegetative Mapping (for Hummock Relocation)
5
STONY CREEK MARSH ISLAND
Future Field Investigations
Topographic Survey (A) (Pending
SUP for Drone Use- January 2024)
Geophysical Sampling
(Pending SUP - Spring 2024)
Standard Penetration Testing (SPT) and
Dilatometer Testing (DMT)
6
STONY CREEK MARSH ISLAND
30% Draft Design Compared to Feasibility Design
• Based on publicly
available NOAA data,
awaiting higher
resolution topographic
survey
• High resolution
bathymetric data
indicated significantly
greater offshore depths
when compared to FS
study data- yielding
decreased restoration
acreages and increased
sand volume needed
• Preservation of healthy contiguous existing marsh,
assumed to be at or near lower end of design elevations
7
STONY CREEK MARSH ISLAND
Shoreline Stabilization Options
Christmas Tree
Fascines
Terraced Coir
Logs
Quick Reef/
ECOncrete
Decisions on types and placement
will be informed by hydrodynamic
modeling results.
8
STONY CREEK MARSH ISLAND
• Complete 30% Designs
(December)
• Complete Field Sampling:
Topographic Survey (January)
and Geotechnical Sampling
(Spring)
• Complete 60%, 90% and 100%
design progressions
• Execute Project Partnership
Agreement for Construction
• Construction coordinated
with Navigation Project (end
2025)
Next Steps
9
HRE - Fresh Creek Restoration
• Received $500,000 to initiate Engineering and Design in 2023
• Design Agreement under review by NYC Law for approval to execute
• Remaining Funds ($2,750,000) included in the House and Senate
Appropriation Bills
10
HRE – Duck Point Marsh Island Restoration
• All Federal funds ($2,275,000) were included in the 2022 Bipartisan
Infrastructure Law Summer Spend Plan.
• Design Agreement under review by NYC Law for approval to execute
November20, 2023 (high tide)
Spring Creek North Ecosystem Restoration
(Continuing Authorities Program)
• Restoration of 43.2-acres including:
 18.8 acres of wetlands
 24.4 acres of maritime uplands
• Restoration through excavating and
recontouring uplands to intertidal
elevations, removing invasives
species and replanting; as well as
restoring existing degraded wetlands
with Thin Layer Placement techniques
• Regulatory Permit Package submitted
to NYSDEC in May 2023
• 100% DesignsCompleted
November2023
• Designs are under Team Review
with plannedapproval by
Christmas
• Ready to Advertise early 2024 and
ConstructionSummer2024
Spring Creek South (Howard Beach) Multi-purpose
Feasibility Study
Ecosystem Restoration and Coastal Storm Risk Management (CSRM)
• Focus on solutions that avoid contamination
• Focus on CSRM features in Shellbank and Hawtree Basins
• Feasibility Cost Share Agreement under negotiation
Spring CreekSouth
NPS Remediation
13
HRE
Restoration
Sites in
Jamaica Bay
327 acres of habitat
restoration:
- 206 acres of
marsh islands
- 121 acres along
perimeter
155,000 CYD
62 acres
41 acres
80 acres
215,000 CYD
40 acres
285,000 CYD
29 acres
328,000 CYD
24 acres
352,000 CYD
29 acres
10 acres
2024
2023
2022
ADDITIONAL HRE RESTORATION PROJECTS
OUTSIDE OF JAMAICABAY
14
Ongoing Design:
• Flushing Creek (NYCDEP)
• Bronx Zoo & Dam/Stone Mill Dam (NYC Parks)
• Oysters at Naval Weapons Station Earle (NJDEP)
Future Design ($500,000 BIL Summer Spend Plan):
• Garth Woods/Harney Road (WestchesterCounty)
Future Feasibility Study ($500,000 House/Senate Appropriations Bill):
• Harlem River Restoration (NYCDEP)
15
Questions?

More Related Content

Similar to Baron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdf

Introduction to the U.S. Geological Survey and USGS-GCD Cooperative Studies, ...
Introduction to the U.S. Geological Survey and USGS-GCD Cooperative Studies, ...Introduction to the U.S. Geological Survey and USGS-GCD Cooperative Studies, ...
Introduction to the U.S. Geological Survey and USGS-GCD Cooperative Studies, ...
Texas Alliance of Groundwater Districts
 
Capstone presentation final
Capstone presentation finalCapstone presentation final
Capstone presentation final
MattieRourk
 
20131030 baid nssi_briefing
20131030 baid nssi_briefing20131030 baid nssi_briefing
20131030 baid nssi_briefing
Proper Printshop
 
MTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docx
MTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docxMTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docx
MTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docx
gilpinleeanna
 

Similar to Baron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdf (20)

Headings - 2014 issue 1
Headings - 2014 issue 1Headings - 2014 issue 1
Headings - 2014 issue 1
 
Introduction to the U.S. Geological Survey and USGS-GCD Cooperative Studies, ...
Introduction to the U.S. Geological Survey and USGS-GCD Cooperative Studies, ...Introduction to the U.S. Geological Survey and USGS-GCD Cooperative Studies, ...
Introduction to the U.S. Geological Survey and USGS-GCD Cooperative Studies, ...
 
ACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ACOE Coastal Storm Management Alternative for Jamaica Bay CommunitiesACOE Coastal Storm Management Alternative for Jamaica Bay Communities
ACOE Coastal Storm Management Alternative for Jamaica Bay Communities
 
Beach samp stakeholder_tools_071415
Beach samp stakeholder_tools_071415Beach samp stakeholder_tools_071415
Beach samp stakeholder_tools_071415
 
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
 
Lightning Round on Current TWDB Studies
Lightning Round on Current TWDB StudiesLightning Round on Current TWDB Studies
Lightning Round on Current TWDB Studies
 
Capstone Final Powerpoint
Capstone Final PowerpointCapstone Final Powerpoint
Capstone Final Powerpoint
 
Development of a Field-Scale Research Facility to Assess the Effects of Sea L...
Development of a Field-Scale Research Facility to Assess the Effects of Sea L...Development of a Field-Scale Research Facility to Assess the Effects of Sea L...
Development of a Field-Scale Research Facility to Assess the Effects of Sea L...
 
Presentation final
Presentation finalPresentation final
Presentation final
 
Capstone presentation final
Capstone presentation finalCapstone presentation final
Capstone presentation final
 
Policy for Malad and Bear River Drainages
Policy for Malad and Bear River DrainagesPolicy for Malad and Bear River Drainages
Policy for Malad and Bear River Drainages
 
Coastal Landcover Trends & Applications in the NW
Coastal Landcover Trends & Applications in the NWCoastal Landcover Trends & Applications in the NW
Coastal Landcover Trends & Applications in the NW
 
Barnack Drive Outfall Restoration Project Completion
Barnack Drive Outfall Restoration Project CompletionBarnack Drive Outfall Restoration Project Completion
Barnack Drive Outfall Restoration Project Completion
 
20131030 baid nssi_briefing
20131030 baid nssi_briefing20131030 baid nssi_briefing
20131030 baid nssi_briefing
 
May 2022 TWDB Updates - Robert Bradley
May 2022 TWDB Updates - Robert BradleyMay 2022 TWDB Updates - Robert Bradley
May 2022 TWDB Updates - Robert Bradley
 
Hawaii Pacific GIS Conference 2012: Plenary Session Keynote - Positioning the...
Hawaii Pacific GIS Conference 2012: Plenary Session Keynote - Positioning the...Hawaii Pacific GIS Conference 2012: Plenary Session Keynote - Positioning the...
Hawaii Pacific GIS Conference 2012: Plenary Session Keynote - Positioning the...
 
Dredging and Disposal Site Reclamation at John Redmond Reservoir, Kansas
Dredging and Disposal Site Reclamation at John Redmond Reservoir, KansasDredging and Disposal Site Reclamation at John Redmond Reservoir, Kansas
Dredging and Disposal Site Reclamation at John Redmond Reservoir, Kansas
 
GISapplication.ppt
GISapplication.pptGISapplication.ppt
GISapplication.ppt
 
MTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docx
MTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docxMTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docx
MTH 251 Lab 7 FALL 2016NAME 1. Inverse trigonometric .docx
 
Professional Geologist Work Experience
Professional Geologist Work ExperienceProfessional Geologist Work Experience
Professional Geologist Work Experience
 

More from ecowatchers

More from ecowatchers (20)

NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptxNYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
NYCParks_HookCreekSedimentPlacement_20231130_FINAL.pptx
 
Fall 2023 JBTF presentation on Additional HRE project areas. .pptx
Fall 2023 JBTF presentation on Additional HRE project areas. .pptxFall 2023 JBTF presentation on Additional HRE project areas. .pptx
Fall 2023 JBTF presentation on Additional HRE project areas. .pptx
 
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdfNPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
 
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdfNYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
 
November 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdfNovember 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdf
 
Jamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdfJamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdf
 
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
 
Ribbed Mussel Study Status JBTF.pdf
Ribbed Mussel Study Status JBTF.pdfRibbed Mussel Study Status JBTF.pdf
Ribbed Mussel Study Status JBTF.pdf
 
Weppler jam bay task force 3 nov 21
Weppler jam bay task force  3 nov 21Weppler jam bay task force  3 nov 21
Weppler jam bay task force 3 nov 21
 
Jb task force 2021 1103
Jb task force 2021 1103Jb task force 2021 1103
Jb task force 2021 1103
 
201130 west pond reduced
201130 west pond reduced201130 west pond reduced
201130 west pond reduced
 
Jamaica bay ecowatchers task force presentation 12.9.2020
Jamaica bay ecowatchers task force presentation   12.9.2020Jamaica bay ecowatchers task force presentation   12.9.2020
Jamaica bay ecowatchers task force presentation 12.9.2020
 
Nyc parks marine debris removal
Nyc parks marine debris removalNyc parks marine debris removal
Nyc parks marine debris removal
 
Raptor mgmt presentation12 09-2020
Raptor mgmt presentation12 09-2020Raptor mgmt presentation12 09-2020
Raptor mgmt presentation12 09-2020
 
20191113 jbfs presentation final
20191113 jbfs presentation final20191113 jbfs presentation final
20191113 jbfs presentation final
 
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
 
Ribbed Mussel ability to remove Nitrogen from water bodies.
Ribbed Mussel ability to remove Nitrogen from water bodies.Ribbed Mussel ability to remove Nitrogen from water bodies.
Ribbed Mussel ability to remove Nitrogen from water bodies.
 
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodiesNYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
 
Shirley Chisholm State Park-Brooklyn Update on phase two work
Shirley Chisholm State Park-Brooklyn Update on phase two workShirley Chisholm State Park-Brooklyn Update on phase two work
Shirley Chisholm State Park-Brooklyn Update on phase two work
 
Army Corps of Engineers updates on future Jamaica Bay Projects
Army Corps of Engineers updates on future Jamaica Bay ProjectsArmy Corps of Engineers updates on future Jamaica Bay Projects
Army Corps of Engineers updates on future Jamaica Bay Projects
 

Recently uploaded

一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
zubnm
 
Corporate_Science-based_Target_Setting.pptx
Corporate_Science-based_Target_Setting.pptxCorporate_Science-based_Target_Setting.pptx
Corporate_Science-based_Target_Setting.pptx
arnab132
 

Recently uploaded (20)

Palynology: History, branches, basic principles and application, collection o...
Palynology: History, branches, basic principles and application, collection o...Palynology: History, branches, basic principles and application, collection o...
Palynology: History, branches, basic principles and application, collection o...
 
Introduction to heat waves and Heatwaves in Bangladesh.pptx
Introduction to heat waves and Heatwaves in Bangladesh.pptxIntroduction to heat waves and Heatwaves in Bangladesh.pptx
Introduction to heat waves and Heatwaves in Bangladesh.pptx
 
Smart Watering Solutions for Your Garden
Smart Watering Solutions for Your GardenSmart Watering Solutions for Your Garden
Smart Watering Solutions for Your Garden
 
Heavy metals with their causes and effect.ppt
Heavy metals with their causes and effect.pptHeavy metals with their causes and effect.ppt
Heavy metals with their causes and effect.ppt
 
Mastering Sustainable Living: Your Comprehensive Guide to Greener Choices in ...
Mastering Sustainable Living: Your Comprehensive Guide to Greener Choices in ...Mastering Sustainable Living: Your Comprehensive Guide to Greener Choices in ...
Mastering Sustainable Living: Your Comprehensive Guide to Greener Choices in ...
 
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
一比一原版(UMiami毕业证书)迈阿密大学毕业证如何办理
 
2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx
2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx
2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx
 
CAUSES,EFFECTS,CONTROL OF DEFORESTATION.pptx
CAUSES,EFFECTS,CONTROL OF DEFORESTATION.pptxCAUSES,EFFECTS,CONTROL OF DEFORESTATION.pptx
CAUSES,EFFECTS,CONTROL OF DEFORESTATION.pptx
 
Urban Farming: 3 Benefits, Challenges & The Rise of Green Cities | CIO Women ...
Urban Farming: 3 Benefits, Challenges & The Rise of Green Cities | CIO Women ...Urban Farming: 3 Benefits, Challenges & The Rise of Green Cities | CIO Women ...
Urban Farming: 3 Benefits, Challenges & The Rise of Green Cities | CIO Women ...
 
Role of nanotechnology in management of stored grain pests of cereals and pulses
Role of nanotechnology in management of stored grain pests of cereals and pulsesRole of nanotechnology in management of stored grain pests of cereals and pulses
Role of nanotechnology in management of stored grain pests of cereals and pulses
 
Cooperative Mangrove Project: Introduction, Scope, and Perspectives
Cooperative Mangrove Project: Introduction, Scope, and PerspectivesCooperative Mangrove Project: Introduction, Scope, and Perspectives
Cooperative Mangrove Project: Introduction, Scope, and Perspectives
 
Jumping Scales and Producing peripheries.pptx
Jumping Scales and Producing peripheries.pptxJumping Scales and Producing peripheries.pptx
Jumping Scales and Producing peripheries.pptx
 
cg1.docx꧁❤ Gwalior Get the most entertaining, Call,,Girls and Lovely Girl 825...
cg1.docx꧁❤ Gwalior Get the most entertaining, Call,,Girls and Lovely Girl 825...cg1.docx꧁❤ Gwalior Get the most entertaining, Call,,Girls and Lovely Girl 825...
cg1.docx꧁❤ Gwalior Get the most entertaining, Call,,Girls and Lovely Girl 825...
 
NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...
NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...
NO1 Pakistan Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpin...
 
NO1 Pakistan online istikhara for love marriage vashikaran specialist love pr...
NO1 Pakistan online istikhara for love marriage vashikaran specialist love pr...NO1 Pakistan online istikhara for love marriage vashikaran specialist love pr...
NO1 Pakistan online istikhara for love marriage vashikaran specialist love pr...
 
Corporate_Science-based_Target_Setting.pptx
Corporate_Science-based_Target_Setting.pptxCorporate_Science-based_Target_Setting.pptx
Corporate_Science-based_Target_Setting.pptx
 
Yil Me Hu Summer 2023 Edition - Nisqually Salmon Recovery Newsletter
Yil Me Hu Summer 2023 Edition - Nisqually Salmon Recovery NewsletterYil Me Hu Summer 2023 Edition - Nisqually Salmon Recovery Newsletter
Yil Me Hu Summer 2023 Edition - Nisqually Salmon Recovery Newsletter
 
Role of Copper and Zinc Nanoparticles in Plant Disease Management
Role of Copper and Zinc Nanoparticles in Plant Disease ManagementRole of Copper and Zinc Nanoparticles in Plant Disease Management
Role of Copper and Zinc Nanoparticles in Plant Disease Management
 
ADBB 5cladba Precursor JWH018 +85244677121
ADBB 5cladba Precursor JWH018 +85244677121ADBB 5cladba Precursor JWH018 +85244677121
ADBB 5cladba Precursor JWH018 +85244677121
 
A Complete Guide to Understanding Air Quality Monitoring.pptx
A Complete Guide to Understanding Air Quality Monitoring.pptxA Complete Guide to Understanding Air Quality Monitoring.pptx
A Complete Guide to Understanding Air Quality Monitoring.pptx
 

Baron - Jamaica Bay Task Force Meeting 2 - 30Nov23.pdf

  • 1. 217 217 217 200 200 200 255 255 255 0 0 0 163 163 163 131 132 122 239 65 53 110 135 120 112 92 56 62 102 130 102 56 48 130 120 111 237 237 237 80 119 27 252 174 .59 “The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.” HUDSON RARITAN ESTUARY ECOSYSTEM RESTORATION – JAMAICA BAY UPDATE JAMAICABAY TASK FORCE MEETING LISA BARON PROJECT MANAGER, CIVIL WORKS NEW YORK DISTRICT NOVEMBER 30, 2023 1 File Name
  • 2. File Name 2 Agenda Spring Creek North Spring Creek South HRE- Fresh Creek HRE- Duck Point HRE- Stony Creek
  • 3. 3 STONY CREEK MARSH ISLAND Field Investigations Completed: • NPS Special Use Permit issued 26 May 2023 • ERDC Hydrodynamic Data Collection  Instrument Deployment: 27 May - 2 June 2023  Instrument Service/Interim Data Download: 6-9 November 2023 • Data to be used to validate a system-wide hydrodynamic numeric model developed to evaluate sediment flux, stabilization techniques and restoration alternatives for the marsh islands. Green – Wave/Current Profiler Blue – Wave Sensors Magenta – Water Level Loggers Red Lines – Roving Current Survey Surficial Sediment Grabs (not shown) Atmospheric Sensor (not shown)
  • 4. 4 STONY CREEK MARSH ISLAND Field Investigations Completed: • Bathymetric Survey: 16 June – 2 July 2023 • Awarded Biological Ecological Cultural Resources Contract (BECR) Task order: 20 September 2023 • Biological Surveys: 23 October – 3 November 2023  Wetland Delineation  Bio-benchmark Surveys  Vegetative Mapping (for Hummock Relocation)
  • 5. 5 STONY CREEK MARSH ISLAND Future Field Investigations Topographic Survey (A) (Pending SUP for Drone Use- January 2024) Geophysical Sampling (Pending SUP - Spring 2024) Standard Penetration Testing (SPT) and Dilatometer Testing (DMT)
  • 6. 6 STONY CREEK MARSH ISLAND 30% Draft Design Compared to Feasibility Design • Based on publicly available NOAA data, awaiting higher resolution topographic survey • High resolution bathymetric data indicated significantly greater offshore depths when compared to FS study data- yielding decreased restoration acreages and increased sand volume needed • Preservation of healthy contiguous existing marsh, assumed to be at or near lower end of design elevations
  • 7. 7 STONY CREEK MARSH ISLAND Shoreline Stabilization Options Christmas Tree Fascines Terraced Coir Logs Quick Reef/ ECOncrete Decisions on types and placement will be informed by hydrodynamic modeling results.
  • 8. 8 STONY CREEK MARSH ISLAND • Complete 30% Designs (December) • Complete Field Sampling: Topographic Survey (January) and Geotechnical Sampling (Spring) • Complete 60%, 90% and 100% design progressions • Execute Project Partnership Agreement for Construction • Construction coordinated with Navigation Project (end 2025) Next Steps
  • 9. 9 HRE - Fresh Creek Restoration • Received $500,000 to initiate Engineering and Design in 2023 • Design Agreement under review by NYC Law for approval to execute • Remaining Funds ($2,750,000) included in the House and Senate Appropriation Bills
  • 10. 10 HRE – Duck Point Marsh Island Restoration • All Federal funds ($2,275,000) were included in the 2022 Bipartisan Infrastructure Law Summer Spend Plan. • Design Agreement under review by NYC Law for approval to execute November20, 2023 (high tide)
  • 11. Spring Creek North Ecosystem Restoration (Continuing Authorities Program) • Restoration of 43.2-acres including:  18.8 acres of wetlands  24.4 acres of maritime uplands • Restoration through excavating and recontouring uplands to intertidal elevations, removing invasives species and replanting; as well as restoring existing degraded wetlands with Thin Layer Placement techniques • Regulatory Permit Package submitted to NYSDEC in May 2023 • 100% DesignsCompleted November2023 • Designs are under Team Review with plannedapproval by Christmas • Ready to Advertise early 2024 and ConstructionSummer2024
  • 12. Spring Creek South (Howard Beach) Multi-purpose Feasibility Study Ecosystem Restoration and Coastal Storm Risk Management (CSRM) • Focus on solutions that avoid contamination • Focus on CSRM features in Shellbank and Hawtree Basins • Feasibility Cost Share Agreement under negotiation Spring CreekSouth NPS Remediation
  • 13. 13 HRE Restoration Sites in Jamaica Bay 327 acres of habitat restoration: - 206 acres of marsh islands - 121 acres along perimeter 155,000 CYD 62 acres 41 acres 80 acres 215,000 CYD 40 acres 285,000 CYD 29 acres 328,000 CYD 24 acres 352,000 CYD 29 acres 10 acres 2024 2023 2022
  • 14. ADDITIONAL HRE RESTORATION PROJECTS OUTSIDE OF JAMAICABAY 14 Ongoing Design: • Flushing Creek (NYCDEP) • Bronx Zoo & Dam/Stone Mill Dam (NYC Parks) • Oysters at Naval Weapons Station Earle (NJDEP) Future Design ($500,000 BIL Summer Spend Plan): • Garth Woods/Harney Road (WestchesterCounty) Future Feasibility Study ($500,000 House/Senate Appropriations Bill): • Harlem River Restoration (NYCDEP)