Storage Tank Management
Requirements
Emphasis on Greater Than 10,000-
Gallons
April 7, 2021
David P. Horowitz, PE, CSP
Tighe & Bond
413.572.3211 (office)
413.250.2487 (cell)
@dphorowitz
dphorowitz@tighebond.com
Storage Tank Management
Requirements
Thanks to:
H. Jacob Nunnemacher
Office of the State Fire Marshal
Commonwealth of Massachusetts
Gary M. Roberts, API 653 Inspector
Joseph A. Macknight, STI Inspector
Tighe & Bond
Agenda - Storage Tank Flow Chart
Aboveground
40 CFR 112
(SPCC)
Codes &
Standards
Industry
Standard
Tank Testing
Federal,
State, NFPA,
UL
Applicable Code - NFPA
■ “… reduce the worldwide burden of fire and other
hazards on the quality of life by providing and
advocating consensus codes and standards, research,
training and education”
■ National Fire Protection Association (NFPA)
– NFPA 30: Flammable and Combustible Liquids Code
– NFPA 30A: Motor Fuel Dispensing Facilities and Repair Garages
– NFPA 31: Installation of Oil-Burning Equipment
Applicable Code - UL
■ … an independent, not-for-profit product-safety testing and
certification organization.
■ Underwriters Laboratory Inc. (UL)
– UL 80: Standard for Steel Tanks for Oil-Burner Fuel
– UL 142: Standard for Steel Aboveground Tanks for
Flammable and Combustible Liquids
– UL 2085: Standard for Protected Aboveground Tanks
for Flammable and Combustible Liquids
– UL 1316: Standard for Glass-Fiber-Reinforced Plastic
Underground Storage Tanks for Petroleum Products
SPCC Regulations 101
■ 40 CFR 112 – SPCC
– Federal Regulation
– Oil
– 1,320 gallons
– Aboveground
Integrity Testing – Industry Standards
■ API 653 – Tank Inspection, Repair, Alteration and Reconstruction
■ API 575 – Inspection of Atmospheric and Low-Pressure Tanks
■ API 570 – Piping Inspection Code
■ ASME B31.3 – Process Piping
■ ASME 31.4 – Liquid Transportation Systems for Hydrocarbons,
Liquid Petroleum Gas, Anhydrous Ammonia and Alcohols
■ STI SP001 – Standard for the Inspection of Aboveground Storage
Tanks
■ UL 142 – Steel Aboveground Tanks for Flammable and
Combustible Liquids
Applicable federal, state ……
■ 40 CFR 112 – SPCC
■ 40 CFR 261 – Hazardous Waste
■ 40 CFR 279 – Used Oil
■ 40 CFR 372 - EPCRA
■ NFPA 30/30A – Flammable & Combustible Liquids
■ NFPA 31 – Oil-Burning Equipment
■ UL 80
■ UL 142
■ UL 2085
■ UL 1316 – Tank Construction
■ State – 502 CMR 5.0
■ Local
SP001
ISSUED SEPTEMBER 2011
5th EDITION
502 CMR 5.0
502 CMR 5.0
502 CMR 5.0
https://www.mass.gov/service-details/dfs-licensing
502 CMR 5.0
Tank Owner Tanks Permit Expiration
Alnylam 6 11/18/24
Analog Devices Decommissioned ……
Harvard 1 9/24/24
Kendall Green Energy 3 9/26/21
MIT 3 10/28/25
Novartis 1 6/12/21
502 CMR 5.0 – Important Forms
■ FP-101 Application for Construction and Installation
■ AST Declaration of the Approved Standard
■ AST 101A Approved Standard Declaration Form
■ FP-111 AST Content Descriptions & Categories
■ AST Use Permit Renewal Form
502 CMR 5.0 – What You Need
■ New aboveground storage tank permits
– all new construction
– new installations of ASTs (including relocated tanks and installation of
used tanks).
■ Applications must include:
– Completed application for installation or construction
– Plot plan reviewed by a MA professional engineer
– Foundation plan reviewed by a MA professional engineer
– Dike plan reviewed by a MA professional engineer
– Mechanical tank drawings reviewed by a MA professional engineer
502 CMR 5.0 – What You Need
■ Applications must include:
– Fire safety analysis reviewed by a MA professional engineer. The
analysis is only for flammable gases, or where required by the State
Fire Marshal.
– You need a detailed inspection investigation and suitability assessment
report for used tanks. A professional Massachusetts engineer must
review the report.
– Copy of manufacturer's Data Report for Pressure Vessels (if applicable)
– Copy of the land license (MGL C 148 s.13) if applicable
502 CMR 5.0 – What You Need
■ Applications must include:
– Copy of the current registration for the property (MGL C 148 s.13) if
applicable
– Identification and declaration of approved standard. This is used for the
inspection and maintenance of the tank
– Fee
– Submit three sets of the application and attachments.
502 CMR 5.0 – Important Forms
■ FP-101 Application for Construction and Installation
■ AST Declaration of the Approved Standard
■ AST 101A Approved Standard Declaration Form
■ FP-111 AST Content Descriptions & Categories
■ AST Use Permit Renewal Form
502 CMR 5.0 – Important Forms
■ AST Declaration of the Approved Standard
– Due in August 2019
– Declared an inspection standard
■ AST 101A Approved Standard Declaration Form
■ FP-111 AST Content Descriptions & Categories
– Previously approved descriptions and categories
■ AST Use Permit Renewal Form
– 5 Year renewal cycle (2016 start)
– Approximately 45 days in advance of permit renewal
STI Inspection Results
SP001 – AST Categories
SP001 – Inspection Schedule
ASTs
Normal Venting
Emergency Venting
Spill Containers
Overfill Prevention
Secondary Containment
Compliance Issues
Why
?
Why
?
Ultra-Sonic Thickness Testing
Ideal Installation – Generator Tank
Ideal Installation – Generator Tank
Ideal Installation – Tank Installation
Observation Results
FINDINGS
■ 200+ Tanks observed for tank integrity
■ Two* with >75% wall thickness losses
– Compared to existing standards
■ Most with regulatory, code compliance,
operational issues
– Vent heights & vent configuration/operation
– No overfill protection / Level detection devices
– Not UL 142 standard construction
– No spill prevention devices
– Improper protection from vehicular impact
■ Some with evident corrosion
– Interior of double wall
– External
QUESTIONS?
Aboveground
40 CFR 112
(SPCC)
Codes &
Standards
Industry
Standard
Tank Testing
Federal,
State, NFPA,
UL
Thank You!

More Related Content

Similar to Cambridge Local Emergency Planning Committee Meeting

Gas Technology Institute & ET Environmental - CNG/LPG Garage Maintenance Cons...
Gas Technology Institute & ET Environmental - CNG/LPG Garage Maintenance Cons...Gas Technology Institute & ET Environmental - CNG/LPG Garage Maintenance Cons...
Gas Technology Institute & ET Environmental - CNG/LPG Garage Maintenance Cons...Wisconsin Clean Cities
 
NDDH North Dakota Industrial Stormwater Permit
NDDH North Dakota Industrial Stormwater PermitNDDH North Dakota Industrial Stormwater Permit
NDDH North Dakota Industrial Stormwater PermitLoren Larson, CHMM, CPEA
 
Pakistan ordinance factories (pof)
Pakistan ordinance factories (pof)Pakistan ordinance factories (pof)
Pakistan ordinance factories (pof)Nauman khan
 
Regulatory Briefing | Final Revision To SPCC Rule | Caltha LLP
Regulatory Briefing |  Final Revision To SPCC Rule | Caltha LLPRegulatory Briefing |  Final Revision To SPCC Rule | Caltha LLP
Regulatory Briefing | Final Revision To SPCC Rule | Caltha LLPLoren Larson, CHMM, CSO, CEI
 
1 s2.0-s0360319915300094-main
1 s2.0-s0360319915300094-main1 s2.0-s0360319915300094-main
1 s2.0-s0360319915300094-mainChaitanya Ghodke
 
Non-OEM / PMA Components and DER Repairs: Best Practices
Non-OEM / PMA Components and DER Repairs: Best PracticesNon-OEM / PMA Components and DER Repairs: Best Practices
Non-OEM / PMA Components and DER Repairs: Best PracticesATOEvents
 
steam-turbine-generator-overhaul-and-inspection-epri.pdf
steam-turbine-generator-overhaul-and-inspection-epri.pdfsteam-turbine-generator-overhaul-and-inspection-epri.pdf
steam-turbine-generator-overhaul-and-inspection-epri.pdfchintanraval24
 
2015 Caterpillar EH&S Conference
2015 Caterpillar EH&S Conference2015 Caterpillar EH&S Conference
2015 Caterpillar EH&S ConferenceDavid Horowitz
 
Environmental code of practice for aboveground storage tank containing petrol...
Environmental code of practice for aboveground storage tank containing petrol...Environmental code of practice for aboveground storage tank containing petrol...
Environmental code of practice for aboveground storage tank containing petrol...Jin Chen
 
MARPOL Annex VI Chapter 1-3: “Air Pollution and GHG Emissions from Internati...
MARPOL Annex VI Chapter 1-3: “Air Pollution and GHG Emissions from Internati...MARPOL Annex VI Chapter 1-3: “Air Pollution and GHG Emissions from Internati...
MARPOL Annex VI Chapter 1-3: “Air Pollution and GHG Emissions from Internati...Mohammud Hanif Dewan M.Phil.
 
2016_EHS Seminar_Portsmouth NH slides
2016_EHS Seminar_Portsmouth NH slides2016_EHS Seminar_Portsmouth NH slides
2016_EHS Seminar_Portsmouth NH slidesWayne Bates
 
Developments Under the Clean Air Act Implications and Ramifications
Developments Under the Clean Air Act  Implications and RamificationsDevelopments Under the Clean Air Act  Implications and Ramifications
Developments Under the Clean Air Act Implications and RamificationsQuarles & Brady
 
Development of ASME Codes and Standards
Development of ASME Codes and StandardsDevelopment of ASME Codes and Standards
Development of ASME Codes and StandardsMark Mitchell
 
C.V. Jan30-2017 -
C.V. Jan30-2017 -C.V. Jan30-2017 -
C.V. Jan30-2017 -wickins
 
How to Survive a Ramp Check: Aircraft Operator Maintenance Responsibilities
How to Survive a Ramp Check: Aircraft Operator Maintenance ResponsibilitiesHow to Survive a Ramp Check: Aircraft Operator Maintenance Responsibilities
How to Survive a Ramp Check: Aircraft Operator Maintenance ResponsibilitiesFAA Safety Team Central Florida
 

Similar to Cambridge Local Emergency Planning Committee Meeting (20)

Gas Technology Institute & ET Environmental - CNG/LPG Garage Maintenance Cons...
Gas Technology Institute & ET Environmental - CNG/LPG Garage Maintenance Cons...Gas Technology Institute & ET Environmental - CNG/LPG Garage Maintenance Cons...
Gas Technology Institute & ET Environmental - CNG/LPG Garage Maintenance Cons...
 
2010 4.1
2010 4.12010 4.1
2010 4.1
 
Saes s-060
Saes s-060Saes s-060
Saes s-060
 
NDDH North Dakota Industrial Stormwater Permit
NDDH North Dakota Industrial Stormwater PermitNDDH North Dakota Industrial Stormwater Permit
NDDH North Dakota Industrial Stormwater Permit
 
Inspection of-pressure-vessels
Inspection of-pressure-vesselsInspection of-pressure-vessels
Inspection of-pressure-vessels
 
Pakistan ordinance factories (pof)
Pakistan ordinance factories (pof)Pakistan ordinance factories (pof)
Pakistan ordinance factories (pof)
 
Regulatory Briefing | Final Revision To SPCC Rule | Caltha LLP
Regulatory Briefing |  Final Revision To SPCC Rule | Caltha LLPRegulatory Briefing |  Final Revision To SPCC Rule | Caltha LLP
Regulatory Briefing | Final Revision To SPCC Rule | Caltha LLP
 
1 s2.0-s0360319915300094-main
1 s2.0-s0360319915300094-main1 s2.0-s0360319915300094-main
1 s2.0-s0360319915300094-main
 
Non-OEM / PMA Components and DER Repairs: Best Practices
Non-OEM / PMA Components and DER Repairs: Best PracticesNon-OEM / PMA Components and DER Repairs: Best Practices
Non-OEM / PMA Components and DER Repairs: Best Practices
 
steam-turbine-generator-overhaul-and-inspection-epri.pdf
steam-turbine-generator-overhaul-and-inspection-epri.pdfsteam-turbine-generator-overhaul-and-inspection-epri.pdf
steam-turbine-generator-overhaul-and-inspection-epri.pdf
 
2015 Caterpillar EH&S Conference
2015 Caterpillar EH&S Conference2015 Caterpillar EH&S Conference
2015 Caterpillar EH&S Conference
 
Environmental code of practice for aboveground storage tank containing petrol...
Environmental code of practice for aboveground storage tank containing petrol...Environmental code of practice for aboveground storage tank containing petrol...
Environmental code of practice for aboveground storage tank containing petrol...
 
MARPOL Annex VI Chapter 1-3: “Air Pollution and GHG Emissions from Internati...
MARPOL Annex VI Chapter 1-3: “Air Pollution and GHG Emissions from Internati...MARPOL Annex VI Chapter 1-3: “Air Pollution and GHG Emissions from Internati...
MARPOL Annex VI Chapter 1-3: “Air Pollution and GHG Emissions from Internati...
 
2016_EHS Seminar_Portsmouth NH slides
2016_EHS Seminar_Portsmouth NH slides2016_EHS Seminar_Portsmouth NH slides
2016_EHS Seminar_Portsmouth NH slides
 
Developments Under the Clean Air Act Implications and Ramifications
Developments Under the Clean Air Act  Implications and RamificationsDevelopments Under the Clean Air Act  Implications and Ramifications
Developments Under the Clean Air Act Implications and Ramifications
 
Development of ASME Codes and Standards
Development of ASME Codes and StandardsDevelopment of ASME Codes and Standards
Development of ASME Codes and Standards
 
C.V. Jan30-2017 -
C.V. Jan30-2017 -C.V. Jan30-2017 -
C.V. Jan30-2017 -
 
How to Survive a Ramp Check: Aircraft Operator Maintenance Responsibilities
How to Survive a Ramp Check: Aircraft Operator Maintenance ResponsibilitiesHow to Survive a Ramp Check: Aircraft Operator Maintenance Responsibilities
How to Survive a Ramp Check: Aircraft Operator Maintenance Responsibilities
 
Presentation on SECVIII
Presentation on SECVIIIPresentation on SECVIII
Presentation on SECVIII
 
14 mq11 02-te-0000-ee0012-0
14 mq11 02-te-0000-ee0012-014 mq11 02-te-0000-ee0012-0
14 mq11 02-te-0000-ee0012-0
 

More from David Horowitz

2020 NEWEA Joint Session - Industrial &Safety
2020 NEWEA Joint Session - Industrial &Safety2020 NEWEA Joint Session - Industrial &Safety
2020 NEWEA Joint Session - Industrial &SafetyDavid Horowitz
 
2018 Western Massachusetts Water Works
2018 Western Massachusetts Water Works2018 Western Massachusetts Water Works
2018 Western Massachusetts Water WorksDavid Horowitz
 
Health & Safety Training - Plymouth County Water Works Association
Health & Safety Training - Plymouth County Water Works AssociationHealth & Safety Training - Plymouth County Water Works Association
Health & Safety Training - Plymouth County Water Works AssociationDavid Horowitz
 
NBM 2018 - Spring Technical Session
NBM 2018 - Spring Technical SessionNBM 2018 - Spring Technical Session
NBM 2018 - Spring Technical SessionDavid Horowitz
 
How to Read (and Understand) Safety Data Sheets!
How to Read (and Understand) Safety Data Sheets!How to Read (and Understand) Safety Data Sheets!
How to Read (and Understand) Safety Data Sheets!David Horowitz
 
Chemistry for Water Treatment Plant Operators
Chemistry for Water Treatment Plant OperatorsChemistry for Water Treatment Plant Operators
Chemistry for Water Treatment Plant OperatorsDavid Horowitz
 
Health & Safety At Water Treatment Plants
Health & Safety At Water Treatment PlantsHealth & Safety At Water Treatment Plants
Health & Safety At Water Treatment PlantsDavid Horowitz
 
2017 NEWEA Annual Conference
2017 NEWEA Annual Conference2017 NEWEA Annual Conference
2017 NEWEA Annual ConferenceDavid Horowitz
 
2016 New England APWA - Fall Conference
2016 New England APWA - Fall Conference2016 New England APWA - Fall Conference
2016 New England APWA - Fall ConferenceDavid Horowitz
 
NBM Highway Association 2016 Fall Technical Session
NBM Highway Association 2016 Fall Technical SessionNBM Highway Association 2016 Fall Technical Session
NBM Highway Association 2016 Fall Technical SessionDavid Horowitz
 
Tighe & Bond Breakfast Seminar Series 2016
Tighe & Bond Breakfast Seminar Series 2016Tighe & Bond Breakfast Seminar Series 2016
Tighe & Bond Breakfast Seminar Series 2016David Horowitz
 
International Low Impact Development Conference 2016
International Low Impact Development Conference  2016International Low Impact Development Conference  2016
International Low Impact Development Conference 2016David Horowitz
 
OSHA Top Ten - 2016 NEWEA Annual Conference
OSHA Top Ten -  2016 NEWEA Annual ConferenceOSHA Top Ten -  2016 NEWEA Annual Conference
OSHA Top Ten - 2016 NEWEA Annual ConferenceDavid Horowitz
 
Tighe & Bond Breakfast Seminar Series 2015
Tighe & Bond Breakfast Seminar Series 2015Tighe & Bond Breakfast Seminar Series 2015
Tighe & Bond Breakfast Seminar Series 2015David Horowitz
 
Health & Safety For Water Treatment Plant Operators
Health & Safety For Water Treatment Plant OperatorsHealth & Safety For Water Treatment Plant Operators
Health & Safety For Water Treatment Plant OperatorsDavid Horowitz
 
Tighe & Bond Breakfast Seminar Series 2015
Tighe & Bond Breakfast Seminar Series 2015Tighe & Bond Breakfast Seminar Series 2015
Tighe & Bond Breakfast Seminar Series 2015David Horowitz
 
2015 Multi-Sector General Permit for Stormwater Discharge
2015 Multi-Sector General Permit for Stormwater Discharge2015 Multi-Sector General Permit for Stormwater Discharge
2015 Multi-Sector General Permit for Stormwater DischargeDavid Horowitz
 
Safety for Water Treatment Plant Facilities
Safety for Water Treatment Plant FacilitiesSafety for Water Treatment Plant Facilities
Safety for Water Treatment Plant FacilitiesDavid Horowitz
 
CTAWWA Health & Safety Training
CTAWWA Health & Safety TrainingCTAWWA Health & Safety Training
CTAWWA Health & Safety TrainingDavid Horowitz
 
Environmental, Health & Safety for New Hampshire Water Works Association
Environmental, Health & Safety for New Hampshire Water Works AssociationEnvironmental, Health & Safety for New Hampshire Water Works Association
Environmental, Health & Safety for New Hampshire Water Works AssociationDavid Horowitz
 

More from David Horowitz (20)

2020 NEWEA Joint Session - Industrial &Safety
2020 NEWEA Joint Session - Industrial &Safety2020 NEWEA Joint Session - Industrial &Safety
2020 NEWEA Joint Session - Industrial &Safety
 
2018 Western Massachusetts Water Works
2018 Western Massachusetts Water Works2018 Western Massachusetts Water Works
2018 Western Massachusetts Water Works
 
Health & Safety Training - Plymouth County Water Works Association
Health & Safety Training - Plymouth County Water Works AssociationHealth & Safety Training - Plymouth County Water Works Association
Health & Safety Training - Plymouth County Water Works Association
 
NBM 2018 - Spring Technical Session
NBM 2018 - Spring Technical SessionNBM 2018 - Spring Technical Session
NBM 2018 - Spring Technical Session
 
How to Read (and Understand) Safety Data Sheets!
How to Read (and Understand) Safety Data Sheets!How to Read (and Understand) Safety Data Sheets!
How to Read (and Understand) Safety Data Sheets!
 
Chemistry for Water Treatment Plant Operators
Chemistry for Water Treatment Plant OperatorsChemistry for Water Treatment Plant Operators
Chemistry for Water Treatment Plant Operators
 
Health & Safety At Water Treatment Plants
Health & Safety At Water Treatment PlantsHealth & Safety At Water Treatment Plants
Health & Safety At Water Treatment Plants
 
2017 NEWEA Annual Conference
2017 NEWEA Annual Conference2017 NEWEA Annual Conference
2017 NEWEA Annual Conference
 
2016 New England APWA - Fall Conference
2016 New England APWA - Fall Conference2016 New England APWA - Fall Conference
2016 New England APWA - Fall Conference
 
NBM Highway Association 2016 Fall Technical Session
NBM Highway Association 2016 Fall Technical SessionNBM Highway Association 2016 Fall Technical Session
NBM Highway Association 2016 Fall Technical Session
 
Tighe & Bond Breakfast Seminar Series 2016
Tighe & Bond Breakfast Seminar Series 2016Tighe & Bond Breakfast Seminar Series 2016
Tighe & Bond Breakfast Seminar Series 2016
 
International Low Impact Development Conference 2016
International Low Impact Development Conference  2016International Low Impact Development Conference  2016
International Low Impact Development Conference 2016
 
OSHA Top Ten - 2016 NEWEA Annual Conference
OSHA Top Ten -  2016 NEWEA Annual ConferenceOSHA Top Ten -  2016 NEWEA Annual Conference
OSHA Top Ten - 2016 NEWEA Annual Conference
 
Tighe & Bond Breakfast Seminar Series 2015
Tighe & Bond Breakfast Seminar Series 2015Tighe & Bond Breakfast Seminar Series 2015
Tighe & Bond Breakfast Seminar Series 2015
 
Health & Safety For Water Treatment Plant Operators
Health & Safety For Water Treatment Plant OperatorsHealth & Safety For Water Treatment Plant Operators
Health & Safety For Water Treatment Plant Operators
 
Tighe & Bond Breakfast Seminar Series 2015
Tighe & Bond Breakfast Seminar Series 2015Tighe & Bond Breakfast Seminar Series 2015
Tighe & Bond Breakfast Seminar Series 2015
 
2015 Multi-Sector General Permit for Stormwater Discharge
2015 Multi-Sector General Permit for Stormwater Discharge2015 Multi-Sector General Permit for Stormwater Discharge
2015 Multi-Sector General Permit for Stormwater Discharge
 
Safety for Water Treatment Plant Facilities
Safety for Water Treatment Plant FacilitiesSafety for Water Treatment Plant Facilities
Safety for Water Treatment Plant Facilities
 
CTAWWA Health & Safety Training
CTAWWA Health & Safety TrainingCTAWWA Health & Safety Training
CTAWWA Health & Safety Training
 
Environmental, Health & Safety for New Hampshire Water Works Association
Environmental, Health & Safety for New Hampshire Water Works AssociationEnvironmental, Health & Safety for New Hampshire Water Works Association
Environmental, Health & Safety for New Hampshire Water Works Association
 

Recently uploaded

Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxkalpana413121
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...ronahami
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptAfnanAhmad53
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxNANDHAKUMARA10
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementDr. Deepak Mudgal
 

Recently uploaded (20)

Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 

Cambridge Local Emergency Planning Committee Meeting

  • 1.
  • 2. Storage Tank Management Requirements Emphasis on Greater Than 10,000- Gallons April 7, 2021 David P. Horowitz, PE, CSP Tighe & Bond 413.572.3211 (office) 413.250.2487 (cell) @dphorowitz dphorowitz@tighebond.com
  • 3. Storage Tank Management Requirements Thanks to: H. Jacob Nunnemacher Office of the State Fire Marshal Commonwealth of Massachusetts Gary M. Roberts, API 653 Inspector Joseph A. Macknight, STI Inspector Tighe & Bond
  • 4. Agenda - Storage Tank Flow Chart Aboveground 40 CFR 112 (SPCC) Codes & Standards Industry Standard Tank Testing Federal, State, NFPA, UL
  • 5. Applicable Code - NFPA ■ “… reduce the worldwide burden of fire and other hazards on the quality of life by providing and advocating consensus codes and standards, research, training and education” ■ National Fire Protection Association (NFPA) – NFPA 30: Flammable and Combustible Liquids Code – NFPA 30A: Motor Fuel Dispensing Facilities and Repair Garages – NFPA 31: Installation of Oil-Burning Equipment
  • 6. Applicable Code - UL ■ … an independent, not-for-profit product-safety testing and certification organization. ■ Underwriters Laboratory Inc. (UL) – UL 80: Standard for Steel Tanks for Oil-Burner Fuel – UL 142: Standard for Steel Aboveground Tanks for Flammable and Combustible Liquids – UL 2085: Standard for Protected Aboveground Tanks for Flammable and Combustible Liquids – UL 1316: Standard for Glass-Fiber-Reinforced Plastic Underground Storage Tanks for Petroleum Products
  • 7. SPCC Regulations 101 ■ 40 CFR 112 – SPCC – Federal Regulation – Oil – 1,320 gallons – Aboveground
  • 8. Integrity Testing – Industry Standards ■ API 653 – Tank Inspection, Repair, Alteration and Reconstruction ■ API 575 – Inspection of Atmospheric and Low-Pressure Tanks ■ API 570 – Piping Inspection Code ■ ASME B31.3 – Process Piping ■ ASME 31.4 – Liquid Transportation Systems for Hydrocarbons, Liquid Petroleum Gas, Anhydrous Ammonia and Alcohols ■ STI SP001 – Standard for the Inspection of Aboveground Storage Tanks ■ UL 142 – Steel Aboveground Tanks for Flammable and Combustible Liquids
  • 9. Applicable federal, state …… ■ 40 CFR 112 – SPCC ■ 40 CFR 261 – Hazardous Waste ■ 40 CFR 279 – Used Oil ■ 40 CFR 372 - EPCRA ■ NFPA 30/30A – Flammable & Combustible Liquids ■ NFPA 31 – Oil-Burning Equipment ■ UL 80 ■ UL 142 ■ UL 2085 ■ UL 1316 – Tank Construction ■ State – 502 CMR 5.0 ■ Local SP001 ISSUED SEPTEMBER 2011 5th EDITION
  • 13. 502 CMR 5.0 Tank Owner Tanks Permit Expiration Alnylam 6 11/18/24 Analog Devices Decommissioned …… Harvard 1 9/24/24 Kendall Green Energy 3 9/26/21 MIT 3 10/28/25 Novartis 1 6/12/21
  • 14. 502 CMR 5.0 – Important Forms ■ FP-101 Application for Construction and Installation ■ AST Declaration of the Approved Standard ■ AST 101A Approved Standard Declaration Form ■ FP-111 AST Content Descriptions & Categories ■ AST Use Permit Renewal Form
  • 15. 502 CMR 5.0 – What You Need ■ New aboveground storage tank permits – all new construction – new installations of ASTs (including relocated tanks and installation of used tanks). ■ Applications must include: – Completed application for installation or construction – Plot plan reviewed by a MA professional engineer – Foundation plan reviewed by a MA professional engineer – Dike plan reviewed by a MA professional engineer – Mechanical tank drawings reviewed by a MA professional engineer
  • 16. 502 CMR 5.0 – What You Need ■ Applications must include: – Fire safety analysis reviewed by a MA professional engineer. The analysis is only for flammable gases, or where required by the State Fire Marshal. – You need a detailed inspection investigation and suitability assessment report for used tanks. A professional Massachusetts engineer must review the report. – Copy of manufacturer's Data Report for Pressure Vessels (if applicable) – Copy of the land license (MGL C 148 s.13) if applicable
  • 17. 502 CMR 5.0 – What You Need ■ Applications must include: – Copy of the current registration for the property (MGL C 148 s.13) if applicable – Identification and declaration of approved standard. This is used for the inspection and maintenance of the tank – Fee – Submit three sets of the application and attachments.
  • 18. 502 CMR 5.0 – Important Forms ■ FP-101 Application for Construction and Installation ■ AST Declaration of the Approved Standard ■ AST 101A Approved Standard Declaration Form ■ FP-111 AST Content Descriptions & Categories ■ AST Use Permit Renewal Form
  • 19. 502 CMR 5.0 – Important Forms ■ AST Declaration of the Approved Standard – Due in August 2019 – Declared an inspection standard ■ AST 101A Approved Standard Declaration Form ■ FP-111 AST Content Descriptions & Categories – Previously approved descriptions and categories ■ AST Use Permit Renewal Form – 5 Year renewal cycle (2016 start) – Approximately 45 days in advance of permit renewal
  • 21. SP001 – AST Categories
  • 23. ASTs
  • 28.
  • 32. Ideal Installation – Generator Tank
  • 33. Ideal Installation – Generator Tank
  • 34. Ideal Installation – Tank Installation
  • 35. Observation Results FINDINGS ■ 200+ Tanks observed for tank integrity ■ Two* with >75% wall thickness losses – Compared to existing standards ■ Most with regulatory, code compliance, operational issues – Vent heights & vent configuration/operation – No overfill protection / Level detection devices – Not UL 142 standard construction – No spill prevention devices – Improper protection from vehicular impact ■ Some with evident corrosion – Interior of double wall – External
  • 36. QUESTIONS? Aboveground 40 CFR 112 (SPCC) Codes & Standards Industry Standard Tank Testing Federal, State, NFPA, UL