SlideShare a Scribd company logo
1 of 12
Download to read offline
ALIGNMENT DOWELS/BUSHINGS
2
SPIROL’s roll formed hardened Bushings are designed to meet
one or more of the following objectives:
¥ 	Align mating components,
¥ 	Eliminate drilling of a separate bolt hole,
¥ 	Protect bolts from shear loading, and/or
¥	 Maintain joint integrity
Although these hollow, lightweight Bushings are not precision ground
and do not require precision holes, thus saving in component and hole
preparation costs, they are capable of precision alignment if the design
guidelines are followed. Further savings can be achieved by using the
inside of the Dowel Bushing for the bolt and thus eliminating the cost of
a separate bolt hole. This design concept also protects the bolt from
shear loads perpendicular to the bolt and isolates the forces on the
bolt to tension loading. Shear forces acting on a bolted joint cause the
joint members to slip back and forth, which causes the bolts and nuts
to rotate, reducing the pre-load tension. This is particularly the case
with short bolts with a reduced clamping distance.
Spring Alignment
Dowels/Bushings
1
SPRING ACTION
The diameter of the Bushing is slightly
largerthanthehole. Thespringactionof
the Bushing allows it to be installed into
a drilled or cored hole and assume the
diameter of the hole. It is self-retained
once installed.
Product Features
and Benefits
CONTROLLED INSIDE
DIAMETER
The inside diameter of the Dowel
Bushings is designed to provide
clearanceforaboltthroughtheBushing
for the purpose of fastening the aligned
components together. This isolates
the bolt from the shear loading and
increases the joint integrity. It also
eliminates the cost of a separate hole.
STAGGERED SEAM
The staggered seam prevents
interlocking, making these Bushings
suitable for automatic feeding and
eliminating the need to separate them
during manual assembly.
LEAD-IN CHAMFERS
The beveled chamfer around the entire
periphery of the Bushing is designed
to facilitate ease of insertion and to
avoid skiving of the Bushing during
installation.
1
2
Dowel Bushings
Dowel Bushings are used to locate components in conjunction with bolts which pass
through the inside of the Dowel after it has been installed. Separate holes for locating
pins are eliminated. The hardened Dowels also absorb shear loads, isolating the bolts
from these forces.
Series DB100
Inch
Nominal
Bolt
Diameter
Min. ØID
Installed1
ØOD Wall Thickness
T
Chamfer Recommended Ø Hole Size Min. Single
Shear (lbs.)2
Min. Max. C Length ØB Max. Min. Max.
.250 1/4 .256 .325 .335 .028 .050 .308 .315 .320 2,500
.312 5/16 .318 .401 .411 .035 .050 .381 .391 .396 4,000
.375 3/8 .381 .479 .489 .042 .050 .457 .469 .474 5,750
.500 1/2 .510 .640 .650 .057 .060 .615 .630 .635 10,500
Inch
Nominal Bolt
Diameter
Length
.500 .750 1.000 1.250
1/2 3/4 1 1-1/4
.250 1/4
.312 5/16
.375 3/8
.500 1/2
LENGTH TOLERANCE
+.000” -.030”
Metric
Nominal
Bolt
Diameter
Length
12 15 20 25 30 35
6
8
10
12
16
LENGTH TOLERANCE
+ 0.0mm - 1.0mm
MATERIAL	 FINISH
B	 High Carbon Steel	 K Plain, Oiled
Metric
Nominal
Bolt
Diameter
Min. ØID
Installed1
ØOD Wall Thickness
T
Chamfer Recommended Ø Hole Size Min. Single
Shear (kN)2
Min. Max. C Length ØB Max. Min. Max.
6 6.20 7.92 8.18 0.70 1.40 7.50 7.67 7.80 10.9
8 8.20 10.35 10.61 0.90 1.40 9.85 10.10 10.23 18.7
10 10.20 12.75 13.01 1.10 1.40 12.20 12.50 12.63 28.4
12 12.25 15.50 15.76 1.45 1.80 14.85 15.25 15.38 45.4
16 16.25 20.25 20.51 1.80 1.80 19.50 20.00 20.13 74.6
DIMENSIONAL DATA
1
	When installed in recommended hole.
2
	 Single shear minimum, tested in accordance with ISO 8749 and ASME B18.8.2 Appendix B.
Testing can only be performed on Dowels greater than two diameters in length.
•	 On special order plated parts, all dimensions apply prior to plating.
•	 Special lengths and sizes available upon request.
T Ref.
C Ref.
ØODØB
L+0
-LTol
To Order:	 BUSH, Nominal Dowel Size x Length, Material, Finish, Series
Example:	 BUSH 10 x 25 BK DB100
3
Spring Dowels
Spring Dowels are used to accurately locate components with respect to each other.
They are formed around arbors to assure roundness. It is recommended that one half
the hole tolerance be used for the fixed location of the Dowel and one half for the hole
in the mating part.
Series SD200
Metric
Nominal
Dowel
Diameter
Length
12 15 20 25 30
6
8
10
12
MATERIAL	 FINISH
B	 High Carbon Steel	 K Plain, Oiled
Metric
Nominal
Dowel
Diameter
ØOD Wall Thickness
T
Chamfer Recommended Ø Hole Size Min. Single
Shear (kN)1
Min. Max. C Length ØB Max. Min. Max.
6 6.25 6.50 0.55 1.00 5.85 6.00 6.13 6.6
8 8.25 8.50 0.70 1.40 7.80 8.00 8.13 11.5
10 10.25 10.50 0.90 1.40 9.75 10.00 10.13 18.5
12 12.25 12.50 1.10 1.40 11.70 12.00 12.13 27.1
DIMENSIONAL DATA
1
	 Single shear minimum, tested in accordance with ISO 8749. Testing can only be
performed on Dowels greater than two diameters in length.
•	 On special order plated parts, all dimensions apply prior to plating.
•	 Special lengths and sizes available upon request.
•	 Inch sizes available upon request.
T Ref.
C Ref.
ØODØB
L+0
-1.0
To Order:	 BUSH, Nominal Dowel Size x Length, Material, Finish, Series
Example:	 BUSH 8 x 20 BK SD200
4
Design Guidelines
Doweling to Fix Relative Location Of Components
The more common application is to use the Dowels to fix the relative location of two or more components. In this situation,
the Dowels are partially installed in one component, the initial installation, and then holes in the mating component are
pushed over the exposed end of the partially installed Dowel. The following factors need to be considered for precision
location:
¥ Hole dimension tolerance
¥ Relative depth of initial installation
¥ Total length of the Dowel
¥ True position of hole centerlines
These factors are interrelated and need to be considered together. The following general guidelines are helpful in
determining the best design in a specific situation.
¥	Precise holes with reduced hole tolerances increase the cost but also increase
location accuracy and simplify the design considerations.
¥	 Wider hole tolerances require longer Dowels to assure a tight, non-clearance fit in
both components.
¥	 Hole tolerance should be minus in the initial installation hole and plus in the mating
component hole.
¥	 The maximum hole tolerance should not exceed one half (1/2) of the recommended
tolerance range to allow for hole tolerancing of both holes within the tolerance range.
¥	 Fixing the Dowel location in a through hole can be achieved through length of
engagement and hole tolerancing, or both. Generally, an engagement of 60% of
the total length in the smaller hole is recommended for the fixed location.
¥	 If more than one Dowel is used, holes in the upper recommended tolerance range
allow for a wider tolerance in centerline location.
Doweling for Permanent Positioning
If components are located or positioned by methods
other than the Doweling itself, and the issue is to allow for
disassembly and then re-assembly with the components in
exactly the same location – then it is recommended that the
components be drilled together and the Dowel installed in
the assembled condition. During disassembly, the Dowel
may be removed and reinstalled during re-assembly.
This method eliminates the need for hole tolerancing and
hole centerline concerns. It provides for very accurate
permanent locating.
5
Design Guidelines
Precise Holes
If the holes are precise and the same in both
components, such as honed or reamed holes with a
tolerance of .0008” or 0.002mm, then the length of
the Bushing need only receive minor consideration for
purposes of precise relative location. We recommend
using the minimum specified hole in these situations.
The Bushing will assume the diameter of the initial
installation hole and the unsized diameter of the
normally exposed end would compensate for the
tolerance difference between the holes if any. If no
interferencewhatsoeverisacceptablewhenassembling
the mating component over the exposed Bushing, then
it is recommended to keep the exposed Dowel length
to a minimum, or if practical, to push the Dowel through
the initial component to size the exposed end. In any
event it is recommended to install at least two thirds
of the total Dowel length into the initial hole so as to
permanently fix the Dowel position.
Maximum Tolerance Holes
The maximum allowable tolerance is one-half the total
recommended tolerance. This is still within the normal
productionholetolerancefordrilledorcoredholes. The
smaller hole, that is the hole with the minus tolerance,
should be the hole into which the Dowel is initially
installed. The larger hole, that is the hole in the mating
component, should have a plus tolerance. To illustrate:
The total recommended hole tolerance for an ø8mm
Dowel is ø8.00 to ø8.13mm. Take the approximate
midpointandsplitthetolerance. Thesmallerholewould
beø8.00toø8.06mm,thelargerø8.06toø8.13mm. The
smaller hole used for the initial installation will size the
Dowel but the protruding unsized length of the Dowel
remains larger, with the diameter increasing as the
distance from the hole increases. It normally requires
a protruding length equal to 1-1/2 times the Dowel
diameterforaDowelinstalledinaminimumholetohave
a protruding diameter greater than the maximum hole.
Foranø8mmDowelinaø8mmhole,thatwouldrequire
a protrusion of 12mm to have a Dowel diameter at the
protruding end greater than ø8.13mm. The smaller
hole in the initial installation helps in fixing the location
of the Dowel but it is still recommended that the greater
length of engagement be in the smaller initial hole.
Therefore, in the example used here to illustrate the
maximum hole tolerance situation, the Dowel would be
BUSH 8 x 30 BK SD 200.
Total hole tolerance = ø8.00 to ø8.13mm
Hole for fixed Dowel location = ø8.00 to ø8.06mm
Mating component hole = ø8.06 to ø8.13mm
ø8.13mm (Maximum hole
diameter of mating component)
ø8.00mm
(Smallest diameter with tolerance)
12mm
18mm
Equal to hole diameter
≤1 outside diameter
≥60% of
Dowel length
6
Centerline Tolerancing
If more than one Dowel is used, centerline tolerancing
for hole positioning becomes an issue. In situations with
precision holes requiring precision locating, the centerline
tolerancing needs to be accurate and similar to
tolerancing used for solid Dowels. A tolerance
of .0006” or 0.0015mm is recommended. When
a Dowel is installed in a minimum hole, which is
recommended in these cases, the Dowel gap is
butted and further spring action is very limited, if any.
Hole tolerance can be increased to provide for relaxed
positioning tolerances with some sacrifice of rigidity. The
centerline tolerance can be increased to the tolerance of
the holes, or the smallest tolerance if the tolerances of
the holes are different. In the ø8mm Dowel example
used, the centerline tolerance can be 0.06mm. The
net hole at maximum misalignment cannot be less
than the smallest recommended hole; in the example,
ø8mm. The misalignment will normally distribute itself
between the Dowels.
If it is a Dowel Bushing application with a bolt passing
through the Dowel into a threaded component, the
clearance between the minimum inside diameter of the
Dowel Bushing and maximum bolt diameter needs to
be enough to compensate for misalignment. If these
guidelines are used, the standard clearance will always
be adequate at maximum misalignment.
SPIROL APPLICATION SPECIALISTS ARE AVAILABLE TO MAKE RECOMMENDATIONS
BASED ON YOUR REQUIREMENT OR TO REVIEW YOUR APPLICATION.
Blind Holes and Stepped Holes
Blind and stepped holes can be used for Dowel location and stepped holes are generally used for Dowel Bushings used in
conjunction with bolts. Since blind and stepped holes only fix the Dowel location in one direction, it is still recommended
that the Dowel be fixed into location by using the smaller hole and greater length of engagement.
Joint Integrity
Loss of joint integrity due to rotational loosening is triggered by vibration. Loads perpendicular to the axis of the bolt,
particularly cyclic loading cause slip at the bolt head or the nut which translates into rotational loosening. Dowels,
particularly Dowel Bushings, reduce or even eliminate rotational loosening. In this instance, the use of the smallest
hole possible within the tolerance range is recommended to reduce Dowel flexibility after insertion. The shear strength
also needs review. In static loading or a long cycle time between loads, maximum load should not exceed of 75% of the
minimum shear strength. When the loads are in the form of severe vibration, 50% is recommended.
7
Applications
ENGINE HOUSING
ENGINE CAM SHAFT CAPS
SWITCH HOUSING ASSEMBLY
8
INTAKE MANIFOLD HOUSING
OIL PUMP ASSEMBLY
VALVE
9
OIL PUMP HOUSING
TRANSMISSION SOLENOID HOUSING
SPIROL Application Engineers will review your application needs and work
with you to recommend the optimum solution. One way to start the process
is to visit our Optimal Application Engineering portal at SPIROL.com.
© 2018 SPIROL International Corporation 02/18
SPIROL International Corporation
30 Rock Avenue
Danielson, Connecticut 06239 U.S.A.
Tel. +1 860 774 8571
Fax. +1 860 774 2048
SPIROL Shim Division
321 Remington Road
Stow, Ohio 44224 U.S.A.
Tel. +1 330 920 3655
Fax. +1 330 920 3659
SPIROL Canada
3103 St. Etienne Boulevard
Windsor, Ontario N8W 5B1 Canada
Tel. +1 519 974 3334
Fax. +1 519 974 6550
SPIROL Mexico
Avenida Avante #250
Parque Industrial Avante Apodaca
Apodaca, N.L. 66607 Mexico
Tel. +52 81 8385 4390
Fax. +52 81 8385 4391
SPIROL Brazil
Rua Mafalda Barnabé Soliane, 134
Comercial Vitória Martini, Distrito Industrial
CEP 13347-610, Indaiatuba, SP, Brazil
Tel. +55 19 3936 2701
Fax. +55 19 3936 7121
SPIROL France
Cité de l’Automobile ZAC Croix Blandin
18 Rue Léna Bernstein
51100 Reims, France
Tel. +33 3 26 36 31 42
Fax. +33 3 26 09 19 76
SPIROL United Kingdom
17 Princewood Road
Corby, Northants
NN17 4ET United Kingdom
Tel. +44 1536 444800
Fax. +44 1536 203415
SPIROL Germany
Ottostr. 4
80333 Munich, Germany
Tel. +49 89 4 111 905 71
Fax. +49 89 4 111 905 72
SPIROL Spain
08940 Cornellà de Llobregat
Barcelona, Spain
Tel. +34 93 193 05 32
Fax. +34 93 193 25 43
SPIROL Czech Republic	
Sokola Tůmy 743/16
Ostrava-Mariánské Hory 70900
Czech Republic
Tel/Fax. +420 417 537 979
SPIROL Poland
ul. Solec 38 lok. 10
00-394, Warszawa, Poland
Tel. +48 71 399 44 55
SPIROL Asia Headquarters
1st Floor, Building 22, Plot D9, District D
No. 122 HeDan Road
Wai Gao Qiao Free Trade Zone
Shanghai, China 200131
Tel. +86 21 5046 1451
Fax. +86 21 5046 1540
SPIROL Korea
160-5 Seokchon-Dong
Songpa-gu, Seoul, 138-844, Korea
Tel. +86 (0) 21 5046-1451
Fax. +86 (0) 21 5046-1540
Europe
Americas
Asia
Pacific
Technical Centers
info@spirol.com
Please refer to www.SPIROL.com for current specifications and standard product offerings.
e-mail:
SPIROL.com
Installation Technology
Coiled Spring Pins
Rolled Tubular
Components
Spacers
Parts Feeding
Technology
Dowel Bushings /
Spring Dowels
Inserts for Plastics
Precision Shims &
Thin Metal Stampings
Disc Springs
Solid Pins
Ground Hollow
Dowels
Slotted Spring Pins
Precision Washers
Compression
Limiters
Innovative fastening solutions.
Lower assembly costs.

More Related Content

What's hot (13)

Terminologia Cardiotocografía
Terminologia CardiotocografíaTerminologia Cardiotocografía
Terminologia Cardiotocografía
 
Distocia de hombros
Distocia de hombrosDistocia de hombros
Distocia de hombros
 
Monitoreo intraparto 2014
Monitoreo intraparto 2014Monitoreo intraparto 2014
Monitoreo intraparto 2014
 
Eclampsia
EclampsiaEclampsia
Eclampsia
 
Megger 3 factor de potencia pruebas para transformadores
Megger 3  factor de potencia pruebas para transformadoresMegger 3  factor de potencia pruebas para transformadores
Megger 3 factor de potencia pruebas para transformadores
 
Parto anormal
Parto anormalParto anormal
Parto anormal
 
Distocias (Ginecologia)
Distocias (Ginecologia)Distocias (Ginecologia)
Distocias (Ginecologia)
 
Abdomen agudo en el embarazo
Abdomen agudo en el embarazoAbdomen agudo en el embarazo
Abdomen agudo en el embarazo
 
Asma y embarazo 2015
Asma y embarazo 2015Asma y embarazo 2015
Asma y embarazo 2015
 
Transtornos Circulatorios del embarazo
Transtornos Circulatorios del embarazoTranstornos Circulatorios del embarazo
Transtornos Circulatorios del embarazo
 
Cromatografía de Gases
Cromatografía de GasesCromatografía de Gases
Cromatografía de Gases
 
Perfil Biofísico Fetal
Perfil Biofísico FetalPerfil Biofísico Fetal
Perfil Biofísico Fetal
 
Soporte vital pediatrico
Soporte vital pediatricoSoporte vital pediatrico
Soporte vital pediatrico
 

Similar to SPIROL Spring Alignment Dowels and Bushings Catalog

INSERTS FOR PLASTICSF Lτ = F x LInserts.docx
INSERTS FOR PLASTICSF                    Lτ = F x LInserts.docxINSERTS FOR PLASTICSF                    Lτ = F x LInserts.docx
INSERTS FOR PLASTICSF Lτ = F x LInserts.docxdirkrplav
 
Tolerance and Fits
Tolerance and FitsTolerance and Fits
Tolerance and Fitsnmahi96
 
Fitting(metrology)
Fitting(metrology)Fitting(metrology)
Fitting(metrology)Manoj Kumar
 
limit fit tolerance-SPU.pptx
limit fit tolerance-SPU.pptxlimit fit tolerance-SPU.pptx
limit fit tolerance-SPU.pptxSheetalUdgave1
 
Practical production uses_of_smt_adhesives
Practical production uses_of_smt_adhesivesPractical production uses_of_smt_adhesives
Practical production uses_of_smt_adhesivesPSKing1
 
Limit , Fits and Tolerance
Limit , Fits and ToleranceLimit , Fits and Tolerance
Limit , Fits and ToleranceJaspreet Singh
 
manufacturingmajorppt-160513160334.pdf
manufacturingmajorppt-160513160334.pdfmanufacturingmajorppt-160513160334.pdf
manufacturingmajorppt-160513160334.pdfSalimSaleh9
 
3. post retained crown-midterm3
3. post retained crown-midterm33. post retained crown-midterm3
3. post retained crown-midterm3Emjei Mendoza
 
Ipec limits fits
Ipec limits fitsIpec limits fits
Ipec limits fitsManoj Yadav
 
Basic principles of_ tube_expanding
Basic principles of_ tube_expandingBasic principles of_ tube_expanding
Basic principles of_ tube_expandingUjwal Joshi
 
Limits Fits and Tolerances ppt.pdf .
Limits Fits and Tolerances ppt.pdf     .Limits Fits and Tolerances ppt.pdf     .
Limits Fits and Tolerances ppt.pdf .happycocoman
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)ahsanrabbani
 

Similar to SPIROL Spring Alignment Dowels and Bushings Catalog (20)

Tolerance
ToleranceTolerance
Tolerance
 
INSERTS FOR PLASTICSF Lτ = F x LInserts.docx
INSERTS FOR PLASTICSF                    Lτ = F x LInserts.docxINSERTS FOR PLASTICSF                    Lτ = F x LInserts.docx
INSERTS FOR PLASTICSF Lτ = F x LInserts.docx
 
Dowels
DowelsDowels
Dowels
 
Tolerance and Fits
Tolerance and FitsTolerance and Fits
Tolerance and Fits
 
Fitting(metrology)
Fitting(metrology)Fitting(metrology)
Fitting(metrology)
 
limit fit tolerance-SPU.pptx
limit fit tolerance-SPU.pptxlimit fit tolerance-SPU.pptx
limit fit tolerance-SPU.pptx
 
Practical production uses_of_smt_adhesives
Practical production uses_of_smt_adhesivesPractical production uses_of_smt_adhesives
Practical production uses_of_smt_adhesives
 
Limit , Fits and Tolerance
Limit , Fits and ToleranceLimit , Fits and Tolerance
Limit , Fits and Tolerance
 
manufacturingmajorppt-160513160334.pdf
manufacturingmajorppt-160513160334.pdfmanufacturingmajorppt-160513160334.pdf
manufacturingmajorppt-160513160334.pdf
 
Limits, fits and tolerances
Limits, fits and tolerancesLimits, fits and tolerances
Limits, fits and tolerances
 
3. post retained crown-midterm3
3. post retained crown-midterm33. post retained crown-midterm3
3. post retained crown-midterm3
 
Ipec limits fits
Ipec limits fitsIpec limits fits
Ipec limits fits
 
Basic principles of_ tube_expanding
Basic principles of_ tube_expandingBasic principles of_ tube_expanding
Basic principles of_ tube_expanding
 
Axial Insertion machine tooling design for PCB assembly
Axial Insertion machine tooling design for PCB assemblyAxial Insertion machine tooling design for PCB assembly
Axial Insertion machine tooling design for PCB assembly
 
Limits Fits and Tolerances ppt.pdf .
Limits Fits and Tolerances ppt.pdf     .Limits Fits and Tolerances ppt.pdf     .
Limits Fits and Tolerances ppt.pdf .
 
Limits fits
Limits fitsLimits fits
Limits fits
 
Limits Gauges
Limits GaugesLimits Gauges
Limits Gauges
 
Ppt Fits Tolerances[1]
Ppt  Fits   Tolerances[1]Ppt  Fits   Tolerances[1]
Ppt Fits Tolerances[1]
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
 
Mechanical assembly
Mechanical assembly Mechanical assembly
Mechanical assembly
 

More from SPIROL

SPIROL Corporate Brochure
SPIROL Corporate BrochureSPIROL Corporate Brochure
SPIROL Corporate BrochureSPIROL
 
SPIROL Compression Limiters Design Guide
SPIROL Compression Limiters Design GuideSPIROL Compression Limiters Design Guide
SPIROL Compression Limiters Design GuideSPIROL
 
SPIROL Coiled Spring Pins Design Guide
SPIROL Coiled Spring Pins Design GuideSPIROL Coiled Spring Pins Design Guide
SPIROL Coiled Spring Pins Design GuideSPIROL
 
SPIROL Slotted Spring Pin Design Guide
SPIROL Slotted Spring Pin Design GuideSPIROL Slotted Spring Pin Design Guide
SPIROL Slotted Spring Pin Design GuideSPIROL
 
SPIROL Disc Springs Design Guide
SPIROL Disc Springs Design GuideSPIROL Disc Springs Design Guide
SPIROL Disc Springs Design GuideSPIROL
 
SPIROL Precision Ground Hollow Dowels
SPIROL Precision Ground Hollow Dowels SPIROL Precision Ground Hollow Dowels
SPIROL Precision Ground Hollow Dowels SPIROL
 
SPIROL Spacers and Tubular Products Catalog
SPIROL Spacers and Tubular Products CatalogSPIROL Spacers and Tubular Products Catalog
SPIROL Spacers and Tubular Products CatalogSPIROL
 
SPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid Pins
SPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid PinsSPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid Pins
SPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid PinsSPIROL
 

More from SPIROL (8)

SPIROL Corporate Brochure
SPIROL Corporate BrochureSPIROL Corporate Brochure
SPIROL Corporate Brochure
 
SPIROL Compression Limiters Design Guide
SPIROL Compression Limiters Design GuideSPIROL Compression Limiters Design Guide
SPIROL Compression Limiters Design Guide
 
SPIROL Coiled Spring Pins Design Guide
SPIROL Coiled Spring Pins Design GuideSPIROL Coiled Spring Pins Design Guide
SPIROL Coiled Spring Pins Design Guide
 
SPIROL Slotted Spring Pin Design Guide
SPIROL Slotted Spring Pin Design GuideSPIROL Slotted Spring Pin Design Guide
SPIROL Slotted Spring Pin Design Guide
 
SPIROL Disc Springs Design Guide
SPIROL Disc Springs Design GuideSPIROL Disc Springs Design Guide
SPIROL Disc Springs Design Guide
 
SPIROL Precision Ground Hollow Dowels
SPIROL Precision Ground Hollow Dowels SPIROL Precision Ground Hollow Dowels
SPIROL Precision Ground Hollow Dowels
 
SPIROL Spacers and Tubular Products Catalog
SPIROL Spacers and Tubular Products CatalogSPIROL Spacers and Tubular Products Catalog
SPIROL Spacers and Tubular Products Catalog
 
SPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid Pins
SPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid PinsSPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid Pins
SPIROL Straight Solid Pins, Knurled Solid Pins, and Headed Solid Pins
 

Recently uploaded

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 

SPIROL Spring Alignment Dowels and Bushings Catalog

  • 2. 2 SPIROL’s roll formed hardened Bushings are designed to meet one or more of the following objectives: ¥ Align mating components, ¥ Eliminate drilling of a separate bolt hole, ¥ Protect bolts from shear loading, and/or ¥ Maintain joint integrity Although these hollow, lightweight Bushings are not precision ground and do not require precision holes, thus saving in component and hole preparation costs, they are capable of precision alignment if the design guidelines are followed. Further savings can be achieved by using the inside of the Dowel Bushing for the bolt and thus eliminating the cost of a separate bolt hole. This design concept also protects the bolt from shear loads perpendicular to the bolt and isolates the forces on the bolt to tension loading. Shear forces acting on a bolted joint cause the joint members to slip back and forth, which causes the bolts and nuts to rotate, reducing the pre-load tension. This is particularly the case with short bolts with a reduced clamping distance. Spring Alignment Dowels/Bushings
  • 3. 1 SPRING ACTION The diameter of the Bushing is slightly largerthanthehole. Thespringactionof the Bushing allows it to be installed into a drilled or cored hole and assume the diameter of the hole. It is self-retained once installed. Product Features and Benefits CONTROLLED INSIDE DIAMETER The inside diameter of the Dowel Bushings is designed to provide clearanceforaboltthroughtheBushing for the purpose of fastening the aligned components together. This isolates the bolt from the shear loading and increases the joint integrity. It also eliminates the cost of a separate hole. STAGGERED SEAM The staggered seam prevents interlocking, making these Bushings suitable for automatic feeding and eliminating the need to separate them during manual assembly. LEAD-IN CHAMFERS The beveled chamfer around the entire periphery of the Bushing is designed to facilitate ease of insertion and to avoid skiving of the Bushing during installation. 1
  • 4. 2 Dowel Bushings Dowel Bushings are used to locate components in conjunction with bolts which pass through the inside of the Dowel after it has been installed. Separate holes for locating pins are eliminated. The hardened Dowels also absorb shear loads, isolating the bolts from these forces. Series DB100 Inch Nominal Bolt Diameter Min. ØID Installed1 ØOD Wall Thickness T Chamfer Recommended Ø Hole Size Min. Single Shear (lbs.)2 Min. Max. C Length ØB Max. Min. Max. .250 1/4 .256 .325 .335 .028 .050 .308 .315 .320 2,500 .312 5/16 .318 .401 .411 .035 .050 .381 .391 .396 4,000 .375 3/8 .381 .479 .489 .042 .050 .457 .469 .474 5,750 .500 1/2 .510 .640 .650 .057 .060 .615 .630 .635 10,500 Inch Nominal Bolt Diameter Length .500 .750 1.000 1.250 1/2 3/4 1 1-1/4 .250 1/4 .312 5/16 .375 3/8 .500 1/2 LENGTH TOLERANCE +.000” -.030” Metric Nominal Bolt Diameter Length 12 15 20 25 30 35 6 8 10 12 16 LENGTH TOLERANCE + 0.0mm - 1.0mm MATERIAL FINISH B High Carbon Steel K Plain, Oiled Metric Nominal Bolt Diameter Min. ØID Installed1 ØOD Wall Thickness T Chamfer Recommended Ø Hole Size Min. Single Shear (kN)2 Min. Max. C Length ØB Max. Min. Max. 6 6.20 7.92 8.18 0.70 1.40 7.50 7.67 7.80 10.9 8 8.20 10.35 10.61 0.90 1.40 9.85 10.10 10.23 18.7 10 10.20 12.75 13.01 1.10 1.40 12.20 12.50 12.63 28.4 12 12.25 15.50 15.76 1.45 1.80 14.85 15.25 15.38 45.4 16 16.25 20.25 20.51 1.80 1.80 19.50 20.00 20.13 74.6 DIMENSIONAL DATA 1 When installed in recommended hole. 2 Single shear minimum, tested in accordance with ISO 8749 and ASME B18.8.2 Appendix B. Testing can only be performed on Dowels greater than two diameters in length. • On special order plated parts, all dimensions apply prior to plating. • Special lengths and sizes available upon request. T Ref. C Ref. ØODØB L+0 -LTol To Order: BUSH, Nominal Dowel Size x Length, Material, Finish, Series Example: BUSH 10 x 25 BK DB100
  • 5. 3 Spring Dowels Spring Dowels are used to accurately locate components with respect to each other. They are formed around arbors to assure roundness. It is recommended that one half the hole tolerance be used for the fixed location of the Dowel and one half for the hole in the mating part. Series SD200 Metric Nominal Dowel Diameter Length 12 15 20 25 30 6 8 10 12 MATERIAL FINISH B High Carbon Steel K Plain, Oiled Metric Nominal Dowel Diameter ØOD Wall Thickness T Chamfer Recommended Ø Hole Size Min. Single Shear (kN)1 Min. Max. C Length ØB Max. Min. Max. 6 6.25 6.50 0.55 1.00 5.85 6.00 6.13 6.6 8 8.25 8.50 0.70 1.40 7.80 8.00 8.13 11.5 10 10.25 10.50 0.90 1.40 9.75 10.00 10.13 18.5 12 12.25 12.50 1.10 1.40 11.70 12.00 12.13 27.1 DIMENSIONAL DATA 1 Single shear minimum, tested in accordance with ISO 8749. Testing can only be performed on Dowels greater than two diameters in length. • On special order plated parts, all dimensions apply prior to plating. • Special lengths and sizes available upon request. • Inch sizes available upon request. T Ref. C Ref. ØODØB L+0 -1.0 To Order: BUSH, Nominal Dowel Size x Length, Material, Finish, Series Example: BUSH 8 x 20 BK SD200
  • 6. 4 Design Guidelines Doweling to Fix Relative Location Of Components The more common application is to use the Dowels to fix the relative location of two or more components. In this situation, the Dowels are partially installed in one component, the initial installation, and then holes in the mating component are pushed over the exposed end of the partially installed Dowel. The following factors need to be considered for precision location: ¥ Hole dimension tolerance ¥ Relative depth of initial installation ¥ Total length of the Dowel ¥ True position of hole centerlines These factors are interrelated and need to be considered together. The following general guidelines are helpful in determining the best design in a specific situation. ¥ Precise holes with reduced hole tolerances increase the cost but also increase location accuracy and simplify the design considerations. ¥ Wider hole tolerances require longer Dowels to assure a tight, non-clearance fit in both components. ¥ Hole tolerance should be minus in the initial installation hole and plus in the mating component hole. ¥ The maximum hole tolerance should not exceed one half (1/2) of the recommended tolerance range to allow for hole tolerancing of both holes within the tolerance range. ¥ Fixing the Dowel location in a through hole can be achieved through length of engagement and hole tolerancing, or both. Generally, an engagement of 60% of the total length in the smaller hole is recommended for the fixed location. ¥ If more than one Dowel is used, holes in the upper recommended tolerance range allow for a wider tolerance in centerline location. Doweling for Permanent Positioning If components are located or positioned by methods other than the Doweling itself, and the issue is to allow for disassembly and then re-assembly with the components in exactly the same location – then it is recommended that the components be drilled together and the Dowel installed in the assembled condition. During disassembly, the Dowel may be removed and reinstalled during re-assembly. This method eliminates the need for hole tolerancing and hole centerline concerns. It provides for very accurate permanent locating.
  • 7. 5 Design Guidelines Precise Holes If the holes are precise and the same in both components, such as honed or reamed holes with a tolerance of .0008” or 0.002mm, then the length of the Bushing need only receive minor consideration for purposes of precise relative location. We recommend using the minimum specified hole in these situations. The Bushing will assume the diameter of the initial installation hole and the unsized diameter of the normally exposed end would compensate for the tolerance difference between the holes if any. If no interferencewhatsoeverisacceptablewhenassembling the mating component over the exposed Bushing, then it is recommended to keep the exposed Dowel length to a minimum, or if practical, to push the Dowel through the initial component to size the exposed end. In any event it is recommended to install at least two thirds of the total Dowel length into the initial hole so as to permanently fix the Dowel position. Maximum Tolerance Holes The maximum allowable tolerance is one-half the total recommended tolerance. This is still within the normal productionholetolerancefordrilledorcoredholes. The smaller hole, that is the hole with the minus tolerance, should be the hole into which the Dowel is initially installed. The larger hole, that is the hole in the mating component, should have a plus tolerance. To illustrate: The total recommended hole tolerance for an ø8mm Dowel is ø8.00 to ø8.13mm. Take the approximate midpointandsplitthetolerance. Thesmallerholewould beø8.00toø8.06mm,thelargerø8.06toø8.13mm. The smaller hole used for the initial installation will size the Dowel but the protruding unsized length of the Dowel remains larger, with the diameter increasing as the distance from the hole increases. It normally requires a protruding length equal to 1-1/2 times the Dowel diameterforaDowelinstalledinaminimumholetohave a protruding diameter greater than the maximum hole. Foranø8mmDowelinaø8mmhole,thatwouldrequire a protrusion of 12mm to have a Dowel diameter at the protruding end greater than ø8.13mm. The smaller hole in the initial installation helps in fixing the location of the Dowel but it is still recommended that the greater length of engagement be in the smaller initial hole. Therefore, in the example used here to illustrate the maximum hole tolerance situation, the Dowel would be BUSH 8 x 30 BK SD 200. Total hole tolerance = ø8.00 to ø8.13mm Hole for fixed Dowel location = ø8.00 to ø8.06mm Mating component hole = ø8.06 to ø8.13mm ø8.13mm (Maximum hole diameter of mating component) ø8.00mm (Smallest diameter with tolerance) 12mm 18mm Equal to hole diameter ≤1 outside diameter ≥60% of Dowel length
  • 8. 6 Centerline Tolerancing If more than one Dowel is used, centerline tolerancing for hole positioning becomes an issue. In situations with precision holes requiring precision locating, the centerline tolerancing needs to be accurate and similar to tolerancing used for solid Dowels. A tolerance of .0006” or 0.0015mm is recommended. When a Dowel is installed in a minimum hole, which is recommended in these cases, the Dowel gap is butted and further spring action is very limited, if any. Hole tolerance can be increased to provide for relaxed positioning tolerances with some sacrifice of rigidity. The centerline tolerance can be increased to the tolerance of the holes, or the smallest tolerance if the tolerances of the holes are different. In the ø8mm Dowel example used, the centerline tolerance can be 0.06mm. The net hole at maximum misalignment cannot be less than the smallest recommended hole; in the example, ø8mm. The misalignment will normally distribute itself between the Dowels. If it is a Dowel Bushing application with a bolt passing through the Dowel into a threaded component, the clearance between the minimum inside diameter of the Dowel Bushing and maximum bolt diameter needs to be enough to compensate for misalignment. If these guidelines are used, the standard clearance will always be adequate at maximum misalignment. SPIROL APPLICATION SPECIALISTS ARE AVAILABLE TO MAKE RECOMMENDATIONS BASED ON YOUR REQUIREMENT OR TO REVIEW YOUR APPLICATION. Blind Holes and Stepped Holes Blind and stepped holes can be used for Dowel location and stepped holes are generally used for Dowel Bushings used in conjunction with bolts. Since blind and stepped holes only fix the Dowel location in one direction, it is still recommended that the Dowel be fixed into location by using the smaller hole and greater length of engagement. Joint Integrity Loss of joint integrity due to rotational loosening is triggered by vibration. Loads perpendicular to the axis of the bolt, particularly cyclic loading cause slip at the bolt head or the nut which translates into rotational loosening. Dowels, particularly Dowel Bushings, reduce or even eliminate rotational loosening. In this instance, the use of the smallest hole possible within the tolerance range is recommended to reduce Dowel flexibility after insertion. The shear strength also needs review. In static loading or a long cycle time between loads, maximum load should not exceed of 75% of the minimum shear strength. When the loads are in the form of severe vibration, 50% is recommended.
  • 9. 7 Applications ENGINE HOUSING ENGINE CAM SHAFT CAPS SWITCH HOUSING ASSEMBLY
  • 10. 8 INTAKE MANIFOLD HOUSING OIL PUMP ASSEMBLY VALVE
  • 12. SPIROL Application Engineers will review your application needs and work with you to recommend the optimum solution. One way to start the process is to visit our Optimal Application Engineering portal at SPIROL.com. © 2018 SPIROL International Corporation 02/18 SPIROL International Corporation 30 Rock Avenue Danielson, Connecticut 06239 U.S.A. Tel. +1 860 774 8571 Fax. +1 860 774 2048 SPIROL Shim Division 321 Remington Road Stow, Ohio 44224 U.S.A. Tel. +1 330 920 3655 Fax. +1 330 920 3659 SPIROL Canada 3103 St. Etienne Boulevard Windsor, Ontario N8W 5B1 Canada Tel. +1 519 974 3334 Fax. +1 519 974 6550 SPIROL Mexico Avenida Avante #250 Parque Industrial Avante Apodaca Apodaca, N.L. 66607 Mexico Tel. +52 81 8385 4390 Fax. +52 81 8385 4391 SPIROL Brazil Rua Mafalda Barnabé Soliane, 134 Comercial Vitória Martini, Distrito Industrial CEP 13347-610, Indaiatuba, SP, Brazil Tel. +55 19 3936 2701 Fax. +55 19 3936 7121 SPIROL France Cité de l’Automobile ZAC Croix Blandin 18 Rue Léna Bernstein 51100 Reims, France Tel. +33 3 26 36 31 42 Fax. +33 3 26 09 19 76 SPIROL United Kingdom 17 Princewood Road Corby, Northants NN17 4ET United Kingdom Tel. +44 1536 444800 Fax. +44 1536 203415 SPIROL Germany Ottostr. 4 80333 Munich, Germany Tel. +49 89 4 111 905 71 Fax. +49 89 4 111 905 72 SPIROL Spain 08940 Cornellà de Llobregat Barcelona, Spain Tel. +34 93 193 05 32 Fax. +34 93 193 25 43 SPIROL Czech Republic Sokola Tůmy 743/16 Ostrava-Mariánské Hory 70900 Czech Republic Tel/Fax. +420 417 537 979 SPIROL Poland ul. Solec 38 lok. 10 00-394, Warszawa, Poland Tel. +48 71 399 44 55 SPIROL Asia Headquarters 1st Floor, Building 22, Plot D9, District D No. 122 HeDan Road Wai Gao Qiao Free Trade Zone Shanghai, China 200131 Tel. +86 21 5046 1451 Fax. +86 21 5046 1540 SPIROL Korea 160-5 Seokchon-Dong Songpa-gu, Seoul, 138-844, Korea Tel. +86 (0) 21 5046-1451 Fax. +86 (0) 21 5046-1540 Europe Americas Asia Pacific Technical Centers info@spirol.com Please refer to www.SPIROL.com for current specifications and standard product offerings. e-mail: SPIROL.com Installation Technology Coiled Spring Pins Rolled Tubular Components Spacers Parts Feeding Technology Dowel Bushings / Spring Dowels Inserts for Plastics Precision Shims & Thin Metal Stampings Disc Springs Solid Pins Ground Hollow Dowels Slotted Spring Pins Precision Washers Compression Limiters Innovative fastening solutions. Lower assembly costs.