SlideShare a Scribd company logo
1 of 19
PREPARED BY: FARDHAH MANIRAH BINTI AZMAN
SUPERVISED BY: IR AZHAR AHMAD
SKAA 4034 FINAL YEAR PROJECT
Piles Eccentricity Analysis For Two
Columns Combined Pile Cap
INTRODUCTION
– One type of failure for piled foundation is eccentricity.
– Pile eccentricity happens when there is short comings of
driving pre-designated piles at exactly correct position
on the ground.
– The deviation of these piles may jeopardize the integrity
of pile cap.
PROBLEM STATEMENT
The short comings of driving pre-designated piles at
exactly correct position has introduced the ‘pile
eccentricity’. The issues addressed are:
– Does the pile eccentricity influences the overall pile
group centroid and reliability of load carrying
capacity?
– What is the allowable maximum eccentricity for the
pile cap to be safe and reliable?
– What happens when there is an excessive eccentricities
occur?
OBJECTIVES
The objectives of this study are:
1. To develop Microsoft Excel Spreadsheet for
analyzing two columns combined pile cap with zero
and non-zero pile eccentricity.
2. To establish Net Pile Group Eccentricity Limit
Chart that can be used on site for immediate checking.
3. To establish an Optimum Add-On Pile Location
Chart for cases where excessive eccentricities occur.
SCOPE OF STUDY
In order to ensure the results obtained can help achieve
the objectives of this study, the scope has been limited
to:
– Two columns combined pile cap.
– Spacing between column: 1.75 m.
– Type of pile: Pre-cast Square RC Pile.
– Working load is 300 kN for 300 × 300 mm pile.
– Range of pile group: 4-9 piles.
– Type of failure: Eccentricity.
METHODOLOGY
Piles Eccentricity Analysis for Two Columns Combined Pile Cap
Analysis
Zero Eccentricity Non-Zero Eccentricity
Load Balance Check
Establish Net Pile Group
Eccentricity Limit Chart
Establish Optimum Add-
On Pile Location
Load on column 1 & 2, k, conversion factor, eccentricity value
User input
verified
outside safe zone
Centroid Loading, Pile Arrangement & Load Distribution
Location Add-On Pile
to determine
to obtain
checking, < 300 kN
OBJECTIVE 1
OBJECTIVE 2
OBJECTIVE 3
RESULTS & ANALYSIS
1. Microsoft Excel Spreadsheet Program
User Key-In Value:
Results Obtained from Program:
1000 kN 1100 kN
1750 mm
Fixed Parameters
Spacing between pile cap = 1.75 m
Ø RC Pile = 300 × 300 mm
Pile Working Load = 300 kN
Number of Pile = 6
Size of Pile Cap = 1800 × 3000 × 1100 mm
Total Service Load + Self-weight Pile Cap = 1648.50 kN
Position of each piles
Value of Net Eccentricity
Centroid point for loading and pile group
k = 4
Conversion factor = 1.4
RESULTS & ANALYSIS
Pile group with zero eccentricity:
P1 P2 P3
P4 P5 P6
C1 C2
Centroid line for loading and pile group align on the same line at
(0.00, 0.00) indicates that there is no eccentricity occur.
Legend
Centroid line (PG)
Centroid line (Loading)
P1 P2 P3 P4 P5 P6 C1 C2
X-Coordinate -1200.00 0.00 1200.00 -1200.00 0.00 1200.00 -916.67 833.33
Y-Coordinate 600.00 600.00 600.00 -600.00 -600.00 -600.00 0.00 0.00
RESULTS & ANALYSIS
Pile group with eccentricity:
Centroid line for pile group has been deviated from its original position.
The new centroid point of pile group is (-39.67, 14.00) while the
centroid point for loading remains the same (0.00, 0.00).
Legend
Centroid line (PG)
Centroid line (Loading)
25.00
75.00
98.00
75.00
15.00
100.00
45.00
150.00
34.00
125.00
Net
Eccentricity
(-238.00, 84.00)
P1 P2 P3 P4 P5 P6 C1 C2
X-Coordinate -1125.00 -98.00 1215.00 -1155.00 -150.00 1075.00 -916.67 833.33
Y-Coordinate 625.00 525.00 600.00 -500.00 -566.00 -600.00 0.00 0.00
My
Mx
RESULTS & ANALYSIS
Loading distribution for zero and non-zero eccentricity:
Pile Service Load+Sw/n Mxy/Ix Myx/Iy Load per Pile (kN) Checking (< 300kN, OK!)
P1 274.75 7.21 13.51 254.03 OK!
P2 275.75 6.03 0.73 267.99 OK!
P3 274.75 6.92 15.61 283.45 OK!
P4 274.75 6.07 13.88 266.94 OK!
P5 274.75 6.85 1.37 280.22 OK!
P6 274.75 7.25 13.87 295.87 OK!
Total Load 1648.50 BALANCED
Pile Service Load+Sw/n Mxy/Ix Myx/Iy Load per Pile (kN) Checking (< 300kN, OK!)
P1 274.75 0.00 0.00 274.75 OK!
P2 275.75 0.00 0.00 275.75 OK!
P3 274.75 0.00 0.00 274.75 OK!
P4 274.75 0.00 0.00 274.75 OK!
P5 274.75 0.00 0.00 274.75 OK!
P6 274.75 0.00 0.00 274.75 OK!
Total Load 1648.50 BALANCED
Zero eccentricity:
Non-zero eccentricity:
Total Service Load + Self-weight of Pile Cap = Total Load per Pile subjected to Moment
RESULTS & ANALYSIS
2. Net Pile Group Eccentricity Limit Chart
RESULTS & ANALYSIS
The highlighted zone is called safe zone which means any points located inside the
safe zone, the structure is considered safe and reliable to use.
Safe zone
Nultimate = 2100 kN
Ratio = 5.5
Net Pile Group
Eccentricity
X = -238.00 mm
Y= 84.00 mm
RESULTS & ANALYSIS
3. Additional Pile Procedure
The ultimate load is changed from 2100 kN to 2205 kN while other parameters
remains. The area of safe zone became smaller due to increase in loading.
Safe zone
Nultimate = 2205 kN
Ratio = 5.75
Net Pile Group
Eccentricity
X = -238.00 mm
Y= 84.00 mm
RESULTS & ANALYSIS
– Since the net pile group eccentricity is located outside the safe zone, some pile
may subjected to failure. Table below shows the distribution of loading for
ultimate load 2205 kN with same value set of eccentricity.
Pile Service Load+Sw/n Mxy/Ix Myx/Iy Load per Pile (kN) Checking (< 300kN, OK!)
P1 287.25 7.54 14.12 265.59 OK!
P2 287.25 6.31 0.76 280.19 OK!
P3 287.25 7.23 16.33 296.34 OK!
P4 287.25 6.34 14.51 279.08 OK!
P5 287.75 7.16 1.44 292.97 OK!
P6 287.75 7.58 14.50 309.33 FAILED!
Total Load 1723.50 BALANCED
Total Service Load + Self-weight Pile Cap = 1723.50 kN
RESULTS & ANALYSIS
– Since Pile 6 exceeds pile working load, a new pile is added to the structure.
– The location of pile is determined from Optimum Position of Add-On Single
Pile chart below.
238.00
-84.00
14.00
-39.67
P1
P2
P3
P4
P5 P6
C1 C2
Add-On
Pile
(238.00, -84.00)
Failed Pile
RESULTS & ANALYSIS
– Pile capacity checking is performed as shown in the table below after
additional pile. Pile working load is reduced about 15% from 300 kN to 255
kN.
Pile Service Load+Sw/n Mxy/Ix Myx/Iy Load per Pile (kN) Checking (< 255 kN, OK!)
P1 246.21 0.00 0.00 246.21 OK!
P2 246.21 0.00 0.00 246.21 OK!
P3 246.21 0.00 0.00 246.21 OK!
P4 246.21 0.00 0.00 246.21 OK!
P5 246.21 0.00 0.00 246.21 OK!
P6 246.21 0.00 0.00 246.21 OK!
Add-On Pile 246.21 0.00 0.00 246.21 OK!
Total Load 1723.50 BALANCED
CONCLUSION
This program serves to reduce time and save cost to solve problem
regarding pile eccentricity for engineers. Findings conforming to the
objectives of this study can be summarized as below:
1. A program for analyzing two columns combined pile cap with zero
and non-zero eccentricity using Microsoft Excel Spreadsheet was
developed.
2. A Net Pile Group Eccentricity Limit Chart to determine the
maximum allowable net eccentricity was established. The chart can be
used on site for immediate checking.
3. An Optimum Add-On Pile Location Chart was established. Load
balance check was conducted for verification.
FUTURE STUDY
Include design stage for two column
combined pile cap.
Multiple number of additional pile for
excessive eccentricity.
1
2
Thank You!

More Related Content

What's hot

Pile cap two pile laod 50 t desigh and drawing
Pile cap  two pile laod 50 t  desigh and drawingPile cap  two pile laod 50 t  desigh and drawing
Pile cap two pile laod 50 t desigh and drawingRAJESH JAIN
 
Design of pile cap
Design of  pile capDesign of  pile cap
Design of pile capPuspendu Ray
 
Examples on total consolidation
Examples on total  consolidationExamples on total  consolidation
Examples on total consolidationMalika khalil
 
Problems on piles and deep footing
Problems on piles and deep footingProblems on piles and deep footing
Problems on piles and deep footingLatif Hyder Wadho
 
Permeability test.pdf
Permeability test.pdfPermeability test.pdf
Permeability test.pdfNatalie Ulza
 
Column Interaction Diagram construction
Column Interaction Diagram constructionColumn Interaction Diagram construction
Column Interaction Diagram constructionPritesh Parmar
 
Structural Analysis, Hibbeler, 8th ed Textbook
Structural Analysis, Hibbeler, 8th ed Textbook Structural Analysis, Hibbeler, 8th ed Textbook
Structural Analysis, Hibbeler, 8th ed Textbook Bahzad5
 
Tower design-Chapter 2-pile caps design
Tower design-Chapter 2-pile caps designTower design-Chapter 2-pile caps design
Tower design-Chapter 2-pile caps designNada Zarrak
 
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)Hossam Shafiq II
 
Settlement of shallow foundation
Settlement of shallow foundationSettlement of shallow foundation
Settlement of shallow foundationLatif Hyder Wadho
 
Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)Md. Shahadat Hossain
 
Geo Technical Engineering (computing lateral earth pressure)
Geo Technical Engineering (computing lateral earth pressure)Geo Technical Engineering (computing lateral earth pressure)
Geo Technical Engineering (computing lateral earth pressure)Latif Hyder Wadho
 
Isolated column footing
Isolated column footingIsolated column footing
Isolated column footingkamariya keyur
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma ABHISHEK SHARMA
 

What's hot (20)

Pile cap two pile laod 50 t desigh and drawing
Pile cap  two pile laod 50 t  desigh and drawingPile cap  two pile laod 50 t  desigh and drawing
Pile cap two pile laod 50 t desigh and drawing
 
Etabs (atkins)
Etabs (atkins)Etabs (atkins)
Etabs (atkins)
 
Design of pile cap
Design of  pile capDesign of  pile cap
Design of pile cap
 
Unit3 hbn
Unit3 hbnUnit3 hbn
Unit3 hbn
 
Examples on total consolidation
Examples on total  consolidationExamples on total  consolidation
Examples on total consolidation
 
Problems on piles and deep footing
Problems on piles and deep footingProblems on piles and deep footing
Problems on piles and deep footing
 
Steel warehouse design report
Steel warehouse design reportSteel warehouse design report
Steel warehouse design report
 
Permeability test.pdf
Permeability test.pdfPermeability test.pdf
Permeability test.pdf
 
Column Interaction Diagram construction
Column Interaction Diagram constructionColumn Interaction Diagram construction
Column Interaction Diagram construction
 
Structural Analysis, Hibbeler, 8th ed Textbook
Structural Analysis, Hibbeler, 8th ed Textbook Structural Analysis, Hibbeler, 8th ed Textbook
Structural Analysis, Hibbeler, 8th ed Textbook
 
Tower design-Chapter 2-pile caps design
Tower design-Chapter 2-pile caps designTower design-Chapter 2-pile caps design
Tower design-Chapter 2-pile caps design
 
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
 
Settlement of shallow foundation
Settlement of shallow foundationSettlement of shallow foundation
Settlement of shallow foundation
 
Design of footing as per IS 456-2000
Design of footing as per IS 456-2000Design of footing as per IS 456-2000
Design of footing as per IS 456-2000
 
Lecture 8 raft foundation
Lecture 8 raft foundationLecture 8 raft foundation
Lecture 8 raft foundation
 
Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)
 
Curved beam design
Curved beam designCurved beam design
Curved beam design
 
Geo Technical Engineering (computing lateral earth pressure)
Geo Technical Engineering (computing lateral earth pressure)Geo Technical Engineering (computing lateral earth pressure)
Geo Technical Engineering (computing lateral earth pressure)
 
Isolated column footing
Isolated column footingIsolated column footing
Isolated column footing
 
Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma Bearing capacity of shallow foundations by abhishek sharma
Bearing capacity of shallow foundations by abhishek sharma
 

Similar to Pile Eccentricity Analysis for 2 Columns Combined Pilecap

Analysis of Lifting Machine
Analysis of Lifting MachineAnalysis of Lifting Machine
Analysis of Lifting MachineAhsen Parwez
 
The static loading test bengt h. fellenius
The  static loading test   bengt h. felleniusThe  static loading test   bengt h. fellenius
The static loading test bengt h. felleniuscfpbolivia
 
IRJET-Fatigue Analysis of Crawler Chassis
IRJET-Fatigue Analysis of Crawler ChassisIRJET-Fatigue Analysis of Crawler Chassis
IRJET-Fatigue Analysis of Crawler ChassisIRJET Journal
 
CIVE702 Midterm Report Combined
CIVE702 Midterm Report CombinedCIVE702 Midterm Report Combined
CIVE702 Midterm Report CombinedCyle Teal
 
Kope winder or friction winder ppt
Kope winder or friction winder pptKope winder or friction winder ppt
Kope winder or friction winder pptAMIT SAHU
 
Analysis and design of high rise rc building under seismic load
Analysis and design of high rise rc building under seismic loadAnalysis and design of high rise rc building under seismic load
Analysis and design of high rise rc building under seismic loadHtinKyawHloon1
 
Team 32 Midterm Final Report
Team 32 Midterm  Final ReportTeam 32 Midterm  Final Report
Team 32 Midterm Final ReportSamuel Trejo
 
140204-5-PTI EDC-130-Continuous Members-41.pdf
140204-5-PTI EDC-130-Continuous Members-41.pdf140204-5-PTI EDC-130-Continuous Members-41.pdf
140204-5-PTI EDC-130-Continuous Members-41.pdfephrem53
 
structure analysis
structure analysisstructure analysis
structure analysisWeng Chuan
 
Design And Analysis of Test Rig for Rudder Pedal
Design And Analysis of Test Rig for Rudder PedalDesign And Analysis of Test Rig for Rudder Pedal
Design And Analysis of Test Rig for Rudder PedalIRJET Journal
 
F0366041045
F0366041045F0366041045
F0366041045theijes
 
DESIGN IMPROVISATION OF ELECTROMECHANICAL ACTUATORS FOR OPERATION AT SUB ZERO...
DESIGN IMPROVISATION OF ELECTROMECHANICAL ACTUATORS FOR OPERATION AT SUB ZERO...DESIGN IMPROVISATION OF ELECTROMECHANICAL ACTUATORS FOR OPERATION AT SUB ZERO...
DESIGN IMPROVISATION OF ELECTROMECHANICAL ACTUATORS FOR OPERATION AT SUB ZERO...ijmech
 

Similar to Pile Eccentricity Analysis for 2 Columns Combined Pilecap (20)

gantry crane report
gantry crane reportgantry crane report
gantry crane report
 
Analysis of Lifting Machine
Analysis of Lifting MachineAnalysis of Lifting Machine
Analysis of Lifting Machine
 
The static loading test bengt h. fellenius
The  static loading test   bengt h. felleniusThe  static loading test   bengt h. fellenius
The static loading test bengt h. fellenius
 
FEA_project1
FEA_project1FEA_project1
FEA_project1
 
IRJET-Fatigue Analysis of Crawler Chassis
IRJET-Fatigue Analysis of Crawler ChassisIRJET-Fatigue Analysis of Crawler Chassis
IRJET-Fatigue Analysis of Crawler Chassis
 
Design of bala school
Design of bala schoolDesign of bala school
Design of bala school
 
CIVE702 Midterm Report Combined
CIVE702 Midterm Report CombinedCIVE702 Midterm Report Combined
CIVE702 Midterm Report Combined
 
Kope winder or friction winder ppt
Kope winder or friction winder pptKope winder or friction winder ppt
Kope winder or friction winder ppt
 
CTA - LST - AZIMUTH SYSTEM 20160607
CTA - LST - AZIMUTH SYSTEM 20160607CTA - LST - AZIMUTH SYSTEM 20160607
CTA - LST - AZIMUTH SYSTEM 20160607
 
Analysis and design of high rise rc building under seismic load
Analysis and design of high rise rc building under seismic loadAnalysis and design of high rise rc building under seismic load
Analysis and design of high rise rc building under seismic load
 
Team 32 Midterm Final Report
Team 32 Midterm  Final ReportTeam 32 Midterm  Final Report
Team 32 Midterm Final Report
 
140204-5-PTI EDC-130-Continuous Members-41.pdf
140204-5-PTI EDC-130-Continuous Members-41.pdf140204-5-PTI EDC-130-Continuous Members-41.pdf
140204-5-PTI EDC-130-Continuous Members-41.pdf
 
Staircase Design Report
Staircase Design ReportStaircase Design Report
Staircase Design Report
 
Pile load test
Pile load testPile load test
Pile load test
 
structure analysis
structure analysisstructure analysis
structure analysis
 
Design And Analysis of Test Rig for Rudder Pedal
Design And Analysis of Test Rig for Rudder PedalDesign And Analysis of Test Rig for Rudder Pedal
Design And Analysis of Test Rig for Rudder Pedal
 
F0366041045
F0366041045F0366041045
F0366041045
 
G.p presentation
G.p presentationG.p presentation
G.p presentation
 
Precast driven pile 450 x450
Precast driven pile 450 x450Precast driven pile 450 x450
Precast driven pile 450 x450
 
DESIGN IMPROVISATION OF ELECTROMECHANICAL ACTUATORS FOR OPERATION AT SUB ZERO...
DESIGN IMPROVISATION OF ELECTROMECHANICAL ACTUATORS FOR OPERATION AT SUB ZERO...DESIGN IMPROVISATION OF ELECTROMECHANICAL ACTUATORS FOR OPERATION AT SUB ZERO...
DESIGN IMPROVISATION OF ELECTROMECHANICAL ACTUATORS FOR OPERATION AT SUB ZERO...
 

Recently uploaded

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 

Recently uploaded (20)

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 

Pile Eccentricity Analysis for 2 Columns Combined Pilecap

  • 1. PREPARED BY: FARDHAH MANIRAH BINTI AZMAN SUPERVISED BY: IR AZHAR AHMAD SKAA 4034 FINAL YEAR PROJECT Piles Eccentricity Analysis For Two Columns Combined Pile Cap
  • 2. INTRODUCTION – One type of failure for piled foundation is eccentricity. – Pile eccentricity happens when there is short comings of driving pre-designated piles at exactly correct position on the ground. – The deviation of these piles may jeopardize the integrity of pile cap.
  • 3. PROBLEM STATEMENT The short comings of driving pre-designated piles at exactly correct position has introduced the ‘pile eccentricity’. The issues addressed are: – Does the pile eccentricity influences the overall pile group centroid and reliability of load carrying capacity? – What is the allowable maximum eccentricity for the pile cap to be safe and reliable? – What happens when there is an excessive eccentricities occur?
  • 4. OBJECTIVES The objectives of this study are: 1. To develop Microsoft Excel Spreadsheet for analyzing two columns combined pile cap with zero and non-zero pile eccentricity. 2. To establish Net Pile Group Eccentricity Limit Chart that can be used on site for immediate checking. 3. To establish an Optimum Add-On Pile Location Chart for cases where excessive eccentricities occur.
  • 5. SCOPE OF STUDY In order to ensure the results obtained can help achieve the objectives of this study, the scope has been limited to: – Two columns combined pile cap. – Spacing between column: 1.75 m. – Type of pile: Pre-cast Square RC Pile. – Working load is 300 kN for 300 × 300 mm pile. – Range of pile group: 4-9 piles. – Type of failure: Eccentricity.
  • 6. METHODOLOGY Piles Eccentricity Analysis for Two Columns Combined Pile Cap Analysis Zero Eccentricity Non-Zero Eccentricity Load Balance Check Establish Net Pile Group Eccentricity Limit Chart Establish Optimum Add- On Pile Location Load on column 1 & 2, k, conversion factor, eccentricity value User input verified outside safe zone Centroid Loading, Pile Arrangement & Load Distribution Location Add-On Pile to determine to obtain checking, < 300 kN OBJECTIVE 1 OBJECTIVE 2 OBJECTIVE 3
  • 7. RESULTS & ANALYSIS 1. Microsoft Excel Spreadsheet Program User Key-In Value: Results Obtained from Program: 1000 kN 1100 kN 1750 mm Fixed Parameters Spacing between pile cap = 1.75 m Ø RC Pile = 300 × 300 mm Pile Working Load = 300 kN Number of Pile = 6 Size of Pile Cap = 1800 × 3000 × 1100 mm Total Service Load + Self-weight Pile Cap = 1648.50 kN Position of each piles Value of Net Eccentricity Centroid point for loading and pile group k = 4 Conversion factor = 1.4
  • 8. RESULTS & ANALYSIS Pile group with zero eccentricity: P1 P2 P3 P4 P5 P6 C1 C2 Centroid line for loading and pile group align on the same line at (0.00, 0.00) indicates that there is no eccentricity occur. Legend Centroid line (PG) Centroid line (Loading) P1 P2 P3 P4 P5 P6 C1 C2 X-Coordinate -1200.00 0.00 1200.00 -1200.00 0.00 1200.00 -916.67 833.33 Y-Coordinate 600.00 600.00 600.00 -600.00 -600.00 -600.00 0.00 0.00
  • 9. RESULTS & ANALYSIS Pile group with eccentricity: Centroid line for pile group has been deviated from its original position. The new centroid point of pile group is (-39.67, 14.00) while the centroid point for loading remains the same (0.00, 0.00). Legend Centroid line (PG) Centroid line (Loading) 25.00 75.00 98.00 75.00 15.00 100.00 45.00 150.00 34.00 125.00 Net Eccentricity (-238.00, 84.00) P1 P2 P3 P4 P5 P6 C1 C2 X-Coordinate -1125.00 -98.00 1215.00 -1155.00 -150.00 1075.00 -916.67 833.33 Y-Coordinate 625.00 525.00 600.00 -500.00 -566.00 -600.00 0.00 0.00 My Mx
  • 10. RESULTS & ANALYSIS Loading distribution for zero and non-zero eccentricity: Pile Service Load+Sw/n Mxy/Ix Myx/Iy Load per Pile (kN) Checking (< 300kN, OK!) P1 274.75 7.21 13.51 254.03 OK! P2 275.75 6.03 0.73 267.99 OK! P3 274.75 6.92 15.61 283.45 OK! P4 274.75 6.07 13.88 266.94 OK! P5 274.75 6.85 1.37 280.22 OK! P6 274.75 7.25 13.87 295.87 OK! Total Load 1648.50 BALANCED Pile Service Load+Sw/n Mxy/Ix Myx/Iy Load per Pile (kN) Checking (< 300kN, OK!) P1 274.75 0.00 0.00 274.75 OK! P2 275.75 0.00 0.00 275.75 OK! P3 274.75 0.00 0.00 274.75 OK! P4 274.75 0.00 0.00 274.75 OK! P5 274.75 0.00 0.00 274.75 OK! P6 274.75 0.00 0.00 274.75 OK! Total Load 1648.50 BALANCED Zero eccentricity: Non-zero eccentricity: Total Service Load + Self-weight of Pile Cap = Total Load per Pile subjected to Moment
  • 11. RESULTS & ANALYSIS 2. Net Pile Group Eccentricity Limit Chart
  • 12. RESULTS & ANALYSIS The highlighted zone is called safe zone which means any points located inside the safe zone, the structure is considered safe and reliable to use. Safe zone Nultimate = 2100 kN Ratio = 5.5 Net Pile Group Eccentricity X = -238.00 mm Y= 84.00 mm
  • 13. RESULTS & ANALYSIS 3. Additional Pile Procedure The ultimate load is changed from 2100 kN to 2205 kN while other parameters remains. The area of safe zone became smaller due to increase in loading. Safe zone Nultimate = 2205 kN Ratio = 5.75 Net Pile Group Eccentricity X = -238.00 mm Y= 84.00 mm
  • 14. RESULTS & ANALYSIS – Since the net pile group eccentricity is located outside the safe zone, some pile may subjected to failure. Table below shows the distribution of loading for ultimate load 2205 kN with same value set of eccentricity. Pile Service Load+Sw/n Mxy/Ix Myx/Iy Load per Pile (kN) Checking (< 300kN, OK!) P1 287.25 7.54 14.12 265.59 OK! P2 287.25 6.31 0.76 280.19 OK! P3 287.25 7.23 16.33 296.34 OK! P4 287.25 6.34 14.51 279.08 OK! P5 287.75 7.16 1.44 292.97 OK! P6 287.75 7.58 14.50 309.33 FAILED! Total Load 1723.50 BALANCED Total Service Load + Self-weight Pile Cap = 1723.50 kN
  • 15. RESULTS & ANALYSIS – Since Pile 6 exceeds pile working load, a new pile is added to the structure. – The location of pile is determined from Optimum Position of Add-On Single Pile chart below. 238.00 -84.00 14.00 -39.67 P1 P2 P3 P4 P5 P6 C1 C2 Add-On Pile (238.00, -84.00) Failed Pile
  • 16. RESULTS & ANALYSIS – Pile capacity checking is performed as shown in the table below after additional pile. Pile working load is reduced about 15% from 300 kN to 255 kN. Pile Service Load+Sw/n Mxy/Ix Myx/Iy Load per Pile (kN) Checking (< 255 kN, OK!) P1 246.21 0.00 0.00 246.21 OK! P2 246.21 0.00 0.00 246.21 OK! P3 246.21 0.00 0.00 246.21 OK! P4 246.21 0.00 0.00 246.21 OK! P5 246.21 0.00 0.00 246.21 OK! P6 246.21 0.00 0.00 246.21 OK! Add-On Pile 246.21 0.00 0.00 246.21 OK! Total Load 1723.50 BALANCED
  • 17. CONCLUSION This program serves to reduce time and save cost to solve problem regarding pile eccentricity for engineers. Findings conforming to the objectives of this study can be summarized as below: 1. A program for analyzing two columns combined pile cap with zero and non-zero eccentricity using Microsoft Excel Spreadsheet was developed. 2. A Net Pile Group Eccentricity Limit Chart to determine the maximum allowable net eccentricity was established. The chart can be used on site for immediate checking. 3. An Optimum Add-On Pile Location Chart was established. Load balance check was conducted for verification.
  • 18. FUTURE STUDY Include design stage for two column combined pile cap. Multiple number of additional pile for excessive eccentricity. 1 2