In the NEC Engineering and Construction Contract
The role of the
Supervisor
House Keeping
Toilets Phones Fire alarms Drinks
29/10/2021 c. Mott MacDonald | ECC Supervisor 2
Disclaimer
This presentation is intended for internal use within the Mott MacDonald group of companies only. No person may rely on the content,
information or any views expressed in this presentation. We accept no duty of care, responsibility or liability to any recipient of this
presentation. This presentation is confidential and contains proprietary intellectual property.
Nothing in this presentation constitutes financial, insurance or legal advice or opinion and it should not serve as an alternative to obtaining
specialist legal advice from a professional legal services provider in relation to any specific circumstances. If you have any specific
questions about any legal matter you should consult a professional legal services provider.
No representation, warranty or undertaking, express or implied, is made and no responsibility or liability is accepted by us to any party as
to the content of this presentation including, without limitation, its accuracy, completeness or reliability.
We disclaim all and any liability whether arising in contract, tort or otherwise from the receipt, or use, of this presentation or any material
contained in it, or from any action or decision taken as a result of the receipt, or use, of this presentation or any such material.
Copyright
The copyright (and any and all other intellectual property rights) in all material in this presentation is vested in Mott MacDonald Limited.
You may not copy any part of this presentation or do any other act in relation to any part of this presentation which is protected by
copyright (or any other intellectual property right) other than printing the presentation or any other part of it or saving it to a local hard disk
for your personal use only.
Apart from this you may not reproduce or store any part of this presentation in any form, or for any purpose, without our prior written
consent.
The above consents do not authorize you to incorporate any part of this presentation in any commercial document or in any material sold
or otherwise made available to any third party, whether or not for profit, without our prior written consent.
The content of this disclaimer shall be governed and construed in accordance with the laws of England and Wales.
NEC Contracts
Advisory services
29/10/2021 c. Mott MacDonald | ECC Supervisor 3
29/10/2021 Mott MacDonald | NEC Programme 4
Where are you calling in from?
ⓘ Start presenting to display the poll results on this slide.
29/10/2021 (c) Mott MacDonald 2020 | NEC001 5
NEC Bitesize
2021
https://mottmac.sha
repoint.com/legal/in
dustryforms/nec/Pa
ges/necsessions.as
px
Date Session Code
22 January 2021 NEC Contracts - An Introduction - Why are they so different? NEC0001
09 February 2021 NEC - Introduction to the NEC Professional Services Contract (PSC) - pre-
award
NEC0020
01 March 2021 NEC - Introduction to the NEC Professional Services Contract (PSC) - contract
management
NEC0021
30 March 2021 NEC Engineering and Construction Contract (ECC) - Contract strategy (main &
secondary options)
NEC0003
29 April 2021 NEC Engineering and Construction Contract (ECC) - Preparing the tender
documents; tender evaluation
NEC0004
24 May 2021 NEC Engineering and Construction Short Contract (ECSC) NEC00??
22 June 2021 NEC ECC and temporary works NEC0028
14 July 2021 NEC Contracts - Programmes under ECC and PSC NEC0005
17 August 2021 NEC Contracts - The Risk Register/Early Warning Register and risk allocation
and management
NEC0006
13 September 2021 NEC Engineering and Construction Contract (ECC) - compensation events NEC0007
13 October 2021 NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and
responsibilities
NEC0008
08 November 2021 NEC Engineering and Construction Contract (ECC) - Defined Cost, the
Contractor's system and auditing
NEC0009
08 December 2021 NEC and BIM NEC0026
RP1
Slide 5
RP1 Richard Patterson, 11/02/2021
29/10/2021 c. Mott MacDonald | ECC Supervisor 6
Richard Patterson
Chartered Engineer
Mott MacDonald NEC
Advisory Services
32Years with
Mott MacDonald
25Years with
The NEC
1 Year with NEC as
NEC Consultant
29/10/2021 (c) Mott MacDonald 2020 | NEC001 7
What industry do you work in?
ⓘ Start presenting to display the poll results on this slide.
29/10/2021 (c) Mott MacDonald 2020 | NEC001 8
Do you work for:
ⓘ Start presenting to display the poll results on this slide.
29/10/2021 c. Mott MacDonald | ECC Supervisor 9
• Richard Patterson, WNE / Water Procurement and Project Finance Team,
Cambridge
• Petter Siljehag, BNI, SNI, Edinburgh
• Karen Radband,
• Hayman Choi, Environment, Cost & Project Management, Hong Kong
• Advice and training – internal and external
• Training to more than 15,000 people logged
• Reviews and ……help
NEC Contracts Advisory Services
29/10/2021 c. Mott MacDonald | ECC Supervisor 10
• Basic role
• Works Information / Scope in ECC4
• Managing the contract
• General
• Tests and Defects
• Title
• Summary
Contents
NEC - Putting the contracts together
29/10/2021 R Patterson - ECC in 30 flipcharts 11
Employer (ECC4 Client)
ECC
Contractor
PSC
or
PSSC
PSC
or
PSSC
PSC or PSSC
advisor/
designer
Project Manager Supervisor
mgt mgt
29/10/2021 ECC4 PMA - Feb 2020 12
Key roles
1 early warning
2 Subcontractor acceptance
3 programme acceptance
2 design acceptance
1 changing Works Information/ Scope
4 testing and Defects
5 payment
6 compensation events
technical both
7 title
8 insurance
Project Manager Supervisor
commercial
Key
stated period in
relevant clauses
period for reply
applies
ECC ‘Project Manager’ may also be client’s ‘project manager’
29/10/2021 c. Mott MacDonald | ECC Supervisor 13
• Supervisor is ‘like’ a ‘Clerk
of Works’ … but with real
actions and obligations
under the contract. Needs
to be ‘contractual’.
• Supervisor role is to
monitor that the Contractor
does ‘Provide the Works
in accordance with the
Works Information /
Scope’
The role
29/10/2021 c. Mott MacDonald | ECC Supervisor 14
Works Information / Scope is critical !
• 20.1 ‘The Contractor Provides the Works in
accordance with the Works Information / Scope.’
• 54.1 (ECC4 55.1) (options A&C) ‘Information in the
Activity Schedule is not Works Information / Scope
or Site Information.’
• 60.1 ‘The following are compensation events.
• (1) The Project Manager gives an instruction
changing the Works Information / Scope …..
If it’s not in the WI / Scope then the Contractor
does not have to do it. Simple !
Inside Out
The Supervisor must
know the Works
Information / Scope
29/10/2021 c. Mott MacDonald | ECC Supervisor 16
• specification and description of the
works (11.2(19) (ECC4 11.2(16))
• constraints on Providing the Works
(11.2(19) ECC4 11.2(16)))
• works by the Completion Date (11.2(2))
• H&S requirements (27.4)
• Contractor’s design
• parts of the works that
Contractor designs (21.1)
• particulars of design for
submission (21.2)
• purposes for which
Employer / Client may use
Contractor’s design (22.1)
Works Information / Scope
References from the conditions 1
Green: Supervisor take particular note
29/10/2021 c. Mott MacDonald | ECC Supervisor 17
• Working with the Employer / Client and
Others
• cooperation and sharing of the
Working Areas (25.1)
• provides services and other
things (25.2)
• limitations on subcontracting
(26.2)
• any further information on the
programme (31.2)
• use of part of the works before
take over (35.2)
Works Information
References from the conditions 2
29/10/2021 c. Mott MacDonald | ECC Supervisor 18
• tests and inspections (40.1 (ECC4
41.1) )
• materials, facilities and samples for
testing (40.2 (ECC4 41.2))
• tests on Plant and Materials before
delivery (41.1 (ECC4 42.1)
• Preparation for marking of
Equipment, Plant and Materials
outside Working Areas by
Supervisor (71.1)
• title to materials (73.2)
Works Information
References from the conditions 3
29/10/2021 c. Mott MacDonald | ECC Supervisor 19
• C, D, E, F
• acceptance / procurement procedures (11.2 (25) or 11.2
(26) (ECC4 11.2 (26) or 11.2(27))
• accounts and records (55.2)
• X4, X13, X14, guarantees and bonds
• form of parent company guarantee, performance bond,
advance payment bond
• X17 (low performance damages)
• tests and performance levels
Works Information – references from the
conditions - 4
And on to contract
management
Supervisor should have
been called ‘Inspector’
21
Mott MacDonald | ECC Introduction
Role is to monitor
(NOT ensure) ‘compliance’
29/10/2021 c. Mott MacDonald | ECC Supervisor 22
• Acceptance does not change the
Contractor’s responsibility to Provide the
Works or of his liability for his / its design
(14.1)
• Project Manager or Supervisor may
delegate any of their actions (14.2)
• Project Manager may instruct change
to the Works Information / Scope (14.3)
• …but NOT the Supervisor
Project Manager and the Supervisor (14)
29/10/2021 c. Mott MacDonald | ECC Supervisor 23
Supervisor and Project Manager could be …
• employees of the Employer
• independent organisations
• the same organisation or even
• on a simple contract, the same person
• two roles; two hats
• Either way, separate roles – but talk to each
other!
Appointment and delegation
Compensation events
under the contract
(CI.60.1 + certain main and
secondary Options incl.
Option Z)
cost consultants
(commercial
support)
Contract data part 1: either named individual or company (which must appoint individual)
29/10/2021 c. Mott MacDonald | ECC Supervisor
24
Project
Manager
Supervisor
Employer /
Client
Contractor
Contract
(eg PSC)
Communication
designer(s)
(technical support)
Support
Project Manager’s
delegates.
Actions delegated
under 14.2
Supervisor’s
delegates.
Actions delegated
under 14.2
Delegation
29/10/2021 c. Mott MacDonald | ECC Supervisor 25
• 1 General
• 2 Contractor’s main responsibilities
• 3 Time
• 4 testing and Defects
• 5 Payment
• 6 Compensation Events
• 7 Title, 8 Risks and insurance
• W Dispute resolution and 9 termination
Agenda 2: Managing the Contract
Key issues for
the Supervisor in
green
29/10/2021 c. Mott MacDonald | ECC Supervisor 26
• 1 General
• 2 Contractor’s main responsibilities
• 3 Time
• 4 testing and Defects
• 5 Payment
• 6 Compensation Events
• 7 Title, 8 Risks and insurance
• W Dispute resolution and 9 termination
Agenda 2: Managing the Contract
29/10/2021 c. Mott MacDonald | ECC Supervisor 27
RT_C
Read the _ contract
10.1 The Employer, the Contractor, the Project Manager and the Supervisor
shall
act as stated in this contract
and in a spirit of mutual trust
and co-operation.
DWISIT_C
Do what it says in the
_ contract
_TalTEO
_ talk and listen to
each other
ECC4 splits 10.1 into 10.1 and 10,2 - no real effect
29/10/2021 c. Mott MacDonald | ECC Supervisor 28
• Identified terms in Contract Data in italics
• Defined terms, capitalised and all in 11.2 READ
THEM! Eg and especially for the Supervisor
• (2) Completion (done all the work the Works
Info requires for Completion and no Defects that
would prevent Employer/Client using the works)
• (5 (ECC4 (6)) Defect (two types)
• (6 (ECC4 (7)) Defects Certificate (list of
Defects at defects date)
• (19) Works Information (ECC4 (16) Scope)
(what is to be provided and constraints)
Identified and Defined Terms
29/10/2021 c. Mott MacDonald | ECC Supervisor 29
• in a form that can be read, copied & recorded (13.1)
• replies within period for reply or period as in contract (13.3)
• Notifications communicated separately (13.7)
• NEED A SYSTEM!
• forms – basic versions on www.neccontract.com
• forms – developed versions on MM NEC intranet site
and required
• Developed forms in NEC ‘Manuals’
• bespoke IT systems available – CCM, CEMAR, Sypro,
others - we know them!
Communications (13)
29/10/2021 c. Mott MacDonald | ECC Supervisor 30
The best place for the contract is …
No, NEC is NOT a contract
for the ‘bottom drawer’!
29/10/2021 c. Mott MacDonald | ECC Supervisor 31
• 34.1 The Project Manager may
instruct the Contractor to stop or
not to start any work and may
later instruct him that he may re-
start or start it.
Before we really start … Stop the work!
• Supervisor needs to be PM
delegate for this action – at least
for health and safety issues
29/10/2021 c. Mott MacDonald | ECC Supervisor 32
• 1 General
• 2 Contractor’s main responsibilities
• 3 Time
• 4 testing and Defects
• 5 Payment
• 6 Compensation Events
• 7 Title, 8 Risks and insurance
• W Dispute resolution and 9 termination
Agenda 2: Managing the Contract
Part 4, Quality management,
has only one and a half
pages! 33
Mott MacDonald | ECC Introduction
29/10/2021 Mott MacDonald | ECC Introduction 34
Tests and inspections
all between
Contractor
and
Supervisor –
ideally the
Contractor’s
‘quality
manager’
only applies
if ‘tests and
inspections
’ required
by the
Works
Information
(ECC4
Scope) or
the law
materials,
facilities and
samples for
tests and
inspection
provided …
‘as stated in
the Works
Information’
(ECC4
Scope)
The C and the S informs the
other of each of their tests and
inspections before the test or
inspection starts
and afterwards informs the other
of the results.
If ‘test or
inspection’
shows Defect,
the Contractor
corrects the
Defect and the
test or
inspection is
repeated..
The C informs the S in time for a
test or inspection to be
arranged and done before doing
work which would obstruct the
test or inspection. The S may
watch any test ……
There is no ‘inspection and testing plan’
29/10/2021 Mott MacDonald | ECC Introduction 35
ECC4 new 40.1 Quality Management System
Contractor operates quality management system which complies with the Scope
Contractor provides the Project Manager with policy statement and quality plan for acceptance
… and changes to the quality plan
Project Manager may instruct Contractor to correct failure to comply with quality plan: not a
compensation event)
Note:
• Basically copied across from PSC3
• Project Manager, not Supervisor
• Bidders may have an issue with their (corporate) quality policy statement needing acceptance of the PM!
• Just adds one to ECC3 clause numbers!
(6) A Defect is
• a part of the works which is not in
accordance with the Scope or
• a part of the works designed by the
Contractor which is not in
accordance with the applicable law
or the Contractor’s design which the
Project Manager has accepted.
36
Mott MacDonald | ECC Introduction
29/10/2021 R Patterson - ECC in 30 flipcharts 37
testing and Defects
40.1 (41.1) tests and inspections in
Works Information / Scope
by
Supervisor
by Contractor
watched by
Supervisor
notify Defect (42.2 (43.2))
fail
In Works Information / Scope, details of
tests/inspections:
• Prior to delivery to Site
• Factory Acceptance Tests
• Routine tests on Site
• tests for Completion
• X17 - Performance tests re performance
levels (in Works Info / Scope for Contractor’s
design – link to performance damages
• Who to carry out tests
• Who to provide facilities for testing
• Pass criteria
search for
Defects
(42.1
(43.1))
Inspections (40.3 (41.3))
Logically (but
not in contract)
add to ‘list of
Defects’
At defects date or end
of last defects
correction period,
issue Defects
Certificate
(43.3 (44.3))
notify results
(40.3 (41.3))
Defects Certificate
(11.2(6) (11.2(7)) is a
list of Defects
29/10/2021 Mott MacDonald | ECC Introduction 38
So negative!
• 42.1 The Contractor does not bring to the Working
Areas those Plant and Materials which the Scope
states are to be tested or inspected before delivery
until the Supervisor has notified the Contractor that
they have passed the test or inspection.
• Just about the only positive action from the
Supervisor!
29/10/2021 c. Mott MacDonald | ECC Supervisor 39
• a part of the works which is not in
accordance with the Works Information /
Scope or
• a part of the works designed by the
Contractor which is not in accordance with
the applicable law or the Contractor’s
design which the Project Manager has
accepted.
• No ‘Snags’, no ‘NCRs’ in ECC
– just ‘Defects’!
A Defect is (11.2(5) (ECC411.2(5))
42.2 (ECC4 43.2) Until the defects
date the Supervisor and the
Contractor notifies the other as
soon as they
become aware of a Defect.
40
Mott MacDonald | ECC Introduction
notifications have to be separate (13.7)
29/10/2021 c. Mott MacDonald | ECC Supervisor 41
• Clause 40 (ECC4 41) (Tests and Inspections) only applies to
tests
• required by the Works Info / Scope
• or the law
• tests/inspections may be needed:
• before delivery
• ongoing
• to achieve Completion (Cl11.2(2)) - the KEY
• before take over - normally NONE
• to demonstrate performance level (Option X17)
• who, when, where, how, pass criteria?
Testing
Requirements in the Works Information / Scope
29/10/2021 c. Mott MacDonald | ECC Supervisor 42
Tests and inspections
• all between Contractor and Supervisor
• materials, facilities and samples for tests and
inspection provided … ‘as stated in the Works
Information / Scope’
• If ‘test or inspection’ shows Defect then:
• Notify the Defect
• correct and repeat (ECC3 40.4; ECC4 41.4)
• Project Manager assesses cost to Employer in
repeating test (ECC3 40.6, 40.7in C,D.E; ECC4
41.6 and 41.7 in C,D.E)
Need a clear testing plan and records system –
ideally part of the Contractor’s QA/QC system….
Simple form needed
• All done before
• Compass / Group support services /
contracts / NEC / contract administration
Also need a simple, joint
list of Defects
29/10/2021 c. Mott MacDonald | ECC Supervisor 43
29/10/2021 c. Mott MacDonald | ECC Supervisor 44
See Mott MacDonald starter for a list of Defects
https://mottmac.sharepoint.com/:x:/s/Practices/projectprogrammeandcommercialmgt/EXQVctbksENAoC_-
BLmOzrUBrSwv1LaT1Ue9UFKEuEBkMQ?email=Richard.Patterson%40mottmac.com&e=4%3AKcxPs0&at=9
29/10/2021 c. Mott MacDonald | ECC Supervisor 45
• Correcting Defects (43 (ECC4 44))
• Contractor corrects Defect whether
notified or not (43.1 (ECC4 44.1))
• Contractor corrects notified Defects before
the end of the (relevant) defects correction
period (43.2 (ECC4 44.2))
Correcting Defects No formal clause under which to
confirm correction of a Defect and
‘acceptance’ by Supervisor
• Project Manager arranges for the Employer /
Client to provide access required to correct a
Defect (43.4 (ECC4 44.4)) after take over
46
The Supervisor issues the Defects Certificate
There is no ‘Maintenance Period’ – just the ‘period with no name’ from the date of Completion to the defects date
defects correction period (43.2)
Defect
notified
defects
correction
period
defects
correction
period
Defect
notified
defects
correction
period
Defect
notified
43.4 – defects
correct period
starts when PM
has arranged
access to
correct
Completion is when the Contractor has
• done all the work which the Works
Information / Scope states he is to do by
the Completion Date and
• corrected notified Defects which would
have prevented the Employer / Client
from using the works and Others from
doing their work.
Contract Date
date of
Completion defects date
The defects date is
last date for
Supervisor to
• instruct search for
(42.1 (EEC4
43.1)) or
• notify (42.2
(EEC4 43.2)) ) a
Defect
There is no formal
process for the
Supervisor to ‘accept’
anything including that a
Defect has been
corrected
47
Mott MacDonald | ECC Introduction
29/10/2021 c. Mott MacDonald | ECC Supervisor 48
• accepting Defects
• Proposals to Project Manager (not
Supervisor) that Defect is not corrected
(44.1 (ECC4 45.1))
• quotation for reduced Prices and/or earlier
Completion Date (44.2 (ECC4 45.2) )
• a mechanism to ‘do a deal’
• uncorrected Defects (45 (ECC4 46))
• Contractor pays where Contractor has not
corrected Defect within defects correction
period
Accepting Defects; uncorrected Defects
29/10/2021 c. Mott MacDonald | ECC Supervisor 49
• 11.2 (2) Completion - definition
• done all the work the Works Info requires for Completion and
• no Defects that would prevent Employer using works
• Supervisor looks after tests (including for Completion) and
Defects
• but Project Manager certifies Completion (30.2)
• Employer/Client (unless they has said in Contract Data that it
won’t take over before Completion Date) takes over within two
weeks of Completion (35.1)
• Project Manager certifies take over of any part of the works
taken over by the Employer/Client (35.3)
Completion and take over
Supervisor and Project Manager
29/10/2021 c. Mott MacDonald | ECC Supervisor 50
• 11.2 (6) (ECC4 11.2(7)) The Defects
Certificate is either a list of Defects that
the Supervisor has notified before the
defects date which the Contractor has
not corrected or, if there are no such
Defects, a statement that there are
none.
• 43.3 (ECC4 44.3) The Employer’s
rights in respect of a Defect which
the Supervisor has not found or
notified are not affected by the
issue of the Defects Certificate.
• PM assesses cost of remaining
Defects (45 (ECC4 46)) and
makes last assessment of
amount due
The Supervisor issues the Defects Certificate
Defects Certificate is one action of the Supervisor
that is not normally delegated. Get the defects date
in your diary!
• Supervisor issues the Defects Certificate
• (ECC3 43.3) at the later of the defects date
and the end of the last defect correction period.
• (ECC4 44.3) at the defects date if there are no
notified Defects, or otherwise at the earlier of
• the end of the last defect correction period
and
• the date when all notified Defects have
been corrected.
29/10/2021 c. Mott MacDonald | ECC Supervisor 51
• 1 General
• 2 Contractor’s main responsibilities
• 3 Time
• 4 testing and Defects
• 5 Payment
• 6 Compensation Events
• 7 Title, 8 Risks and insurance
• W Dispute resolution and 9 termination
Agenda 2: Managing the Contract
29/10/2021 c. Mott MacDonald | ECC Supervisor 52
• Contractor’s title to Plant and
Materials passes to Employer
(70, 71)
• when within Working Areas
• outside Working Areas – only
when ‘marked by the Supervisor’
for this contact’
• 71.1 The Supervisor
marks Equipment, Plant
and Materials which are
outside the Working Areas
if
• this contract identifies them
for payment and
• the Contractor has prepared
them for marking as the
Works Information requires.
7 Title
WARNING – Contractor can only pass on title
that it has. May need procedures for ‘vesting’
– which are NOT in NEC.
The period with no name!! – ECC4
83.3 no
need for C
to insure
X16.2:
retention
halved
80.1 Loss of or
damage to the
parts of the
works taken over
by the Client
assessment
interval
PM continues routine
payment assessment and
certificates (50.1)
Contractor corrects
within one defects
correction period
Supervisor issues Defects
Certificate (44.3) at the
defects date if no Defects
or at earlier of
• End of last dcp or
• When all Defects
corrected
X16.2 –
retention
taken to
zero
target
options:
include final
assessment
of
Contractor’s
share
Defects?
PM assesses
cost of (46))
certified by
PM (30.2)
date of
Completion
defects date
The period with no name – set in Contract Data part one
assessment
at
Completion
(50.1)
dcp starts only when
PM has arranged
and Client has
provided access
(44.4)
target options:
include prelim
assessment of
Contractor’s share
take over
certified by
PM (35.3)
< 2wks 4 wks (50.1)
Last PM
assessment of
amount due
(50.1) and
payment
certificate (51.1)
Supervisor can
notify Defects
(43.2)
29/10/2021 c. Mott MacDonald | ECC Supervisor 54
Supervisor role summary
• Focused 100% on Contractor’s compliance with Works Information
• testing
• Defects – including issue of Defects Certificate
• Title
• ONLY
• But may /should also be supporting PM
29/10/2021 c. Mott MacDonald | ECC Supervisor 55
Supervisor and Project Manager interaction
More than explicit in the contract
Free at:
https://www.neccontract.com/
The-interaction-between-the-
Supervisor-PM
So how much of a Supervisor do we need?
29/10/2021 c. Mott MacDonald | ECC Supervisor 56
29/10/2021 c. Mott MacDonald | ECC Supervisor 57
But where else might the Supervisor support Project
Manager?
• records, records, records
• site diary
• photographs
• Contractor’s resources – Disallowed
Cost (C,D,E,F)
• progress records
• early warnings (16 (ECC4 15))
• ambiguities (17)
NEC Contracts – The Truth will Out
58
• NEC demands
good
communication
• NEC demands
active
management
Questions
Bedtime Reading
29/10/2021 Mott MacDonald | NEC articles 61
Some of our NEC articles, papers and books
Year Title Where published
2021Using NEC Outside the UK: an update NEC Newsletter , March 2021
2020Three years on it is time for clients to switch from NEC3 to NEC4 NEC Newsletter , Sept 2020
2020Helping NEC clients decide the best way to get a first programme in place NEC Newsletter , Sept 2020
2020NEC family of contracts pitches clearer, more flexible project management PMI UK Chapter 'Leader' magazine (article a copy of that previously published by
IACCM)
29/10/2021 Mott MacDonald | NEC articles 62
Some of our NEC articles, papers and books
Year Title Where published
2020NEC contracts: best practice tools for risk allocation and management NEC website May 2020
2020The all important F-words in the NEC NEC Newsletter , March 2020
2020ECC Risk allocation and compensation events NEC website, March 2020
2020How to ensure that bid-winning supply chains actually get used NEC Newsletter, January 2020
2019Project overruns? It’s time to use the F-word (and a proper contract) Mott MacDonald website
2019Links between key NEC processes NEC Newsletter, May 2019
2018Building time-related charges into NEC lump-sum and short contracts NEC Newsletter, November 2018
2018NEC Early warnings - the need for education NEC Newsletter, November 2018
2018NEC contracts – use them anywhere for any industry! - including how NEC covers
PMI's ideas on procurement and project management
IACCM's Contracting Excellence Journal, 18 June 2018
2018Design of Equipment in the ECC NEC Newsletter, 91, May 2018
2018NEC3 to NEC4 – evolution, not revolution; some fixes and some good ideas! In-procurement Magazine JanFeb 2018
2018NEC3 to NEC4 – evolution, not revolution; some fixes and some good ideas! ICE's Management Procurement and Law, December 2017 and on NEC website
from 26 Feb 2018
2018NEC Contracts - are they right for you? IACCM Contracting Excellence Journal, Feb 2018
2017NEC Engineering and Construction Contract (ECC): the necessary interaction
between the Supervisor and the Project Manager
Construction Law Quarterly / NEC website
2017When is task not a Task - in the NEC TSC contract NEC Newsletter Sep 2017, NEC website
2017NEC: how to require something is done by a certain date NEC Newsletter No 86, July 2017, NEC website
2017New NEC4 Design, Build and Operate Contract NEC website
2016How to procure a series of work packages using NEC NEC website
2016NEC contracts are ideal to support project management as set out in the PMI’s
‘Project Management Body of Knowledge’ (PMBOK®)
Linked-in
29/10/2021 Mott MacDonald | Prep of tender docs 63
Year Title Where published
2016How to procure a series of work packages using NEC NEC website
2016NEC contracts are ideal to support project management as set out in the PMI’s ‘Project
Management Body of Knowledge’ (PMBOK®)
Linked-in
2016Submission of deliverables under the PSC NEC Newsletter No 80, September 2016
2016Enforcement Clauses and Links in the ECC NEC Newsletter No 79, July 2016
2016Can we use the NEC as the basis for a standard international PPP contract? ACE's email newsletter, Infrastructure Intelligence
2016NEC contracts - good for hydropower? NEC Newsletter No 76, January 2016
2015NEC contracts - good for hydropower? Proceedings Hydro 2015, Bordeaux
2015Using NEC to incentivise
lowest whole-life cost
NEC Newsletter No 75, November 2015
2015NEC3 Compared and Contrasted, Second Edition - chapter on NEC vs IChemE
contracts
ICE publishing
2015NEC3 - the Role of the Supervisor ICE publishing
2015NEC for design build finance and operate (DBFO) contracts – taking best practice
procurement into PPPs
ICE’s Management, Procurement and Law, November 2015, and winner of the
Parkman medal for best MPL paper, 2015
2015NEC contracts and the CDM Regulations 2015 ICE’s Management, Procurement and Law, 168, June 2015
2015NEC contracts tick IACCM’s ‘top ten’ box NEC website
2015Making the most of your early warnings – sorting out your TQs and RFIs…. and what
about the opportunities?
NEC website
2015NEC contracts and the Construction (Design and Management) Regulations 2015 NEC website
2015NEC contracts and the CDM Regulations 2015 NEC Newsletter No 72, May 2015
2014Getting your project set
up for ECC
NEC Newsletter No 70, January 2015 (published December 2014)
2014Working with NEC Contracts (in landscape architecture) Landscape (Magazine of the Landscape Institute,. Winter 2014
Some of our NEC articles, papers and books
29/10/2021 Mott MacDonald | Prep of tender docs 64
Some of our NEC articles, papers and books
Year Title Where published
2014ECC Works Information provided by the Contractor - who takes the risk? NEC Newsletter No 69, October 2014
2014Understanding expenses
in a PSC
NEC Newsletter No 67, July 2014
2014The importance of quality works information and site information in ECC projects NEC Newsletter No 66, April 2014
2013NEC for DBO Proceedings of the ICE - Management, Procurement and Law, Volume 166,
Issue 5, May 2013
2013How to prepare the Scope for an NEC PSC Contract By NEC as part of NEC April 2013
2012Managing Reality - the ECC Manuals ICE publishing
2012NEC3: A User's Guide ICE publishing
2011NEC3: contracts for partnering NEC Newsletter No 56, October 2011
2010Ground Conditions and Risk Allocation: Combining the NEC Engineering and
Construction Contract (ECC) and the Geotechnical Baseline Report (GBR)
Tunnels and Tunnelling Magazine, Dec 2010
20106 key links in the ECC NEC Newsletter No 51, July 2010
2010NEC contracts as an enabler to Partnering May 2010 edition of 'The Partner', which is ‘the annual publication of PSL, which is a
CBI and BIS initiative to promote collaborative business relationships
www.pslcbi.com '
2009Using NEC contracts to manage risk and avoid disputes Proceedings of the ICE - Management, Procurement and Law, 2009, No 4.
2009Use of NEC in legal jurisdictions other than English law NEC Newsletter, No,47, July 2009
2009NEC – A real opportunity for the Clerk of Works Site Recorder, Magazine of the Institute of Clerks of Works
2007NEC and Risk Management NEC Newsletter No 40, Oct 2007
2005NEC Managing Reality: Introduction to the Engineering and Construction
Contract. 5 volumes
ICE publishing
2007Dealing with
contingencies - what happened to the 'Provisional Sum'
NEC Newsletter No 40, Oct 2007
2007NEC3 key dates – more risk on the contractor NEC Newsletter No 40, Oct 2007
2001Using NEC for multiple site, undefined contracts ICE’s ‘Civil Engineering’, May 2001
2000NEC and PFI first for Leeds Healthcare NEC Newsletter No 14, July 2000
29/10/2021 c. Mott MacDonald | ECC Supervisor 65
• NEC Managing Reality
• Five volumes covering all aspects of
NEC (ECC)
• 2nd Edition 2013
• Barry Trebes (Mott MacDonald) and
Bronwyn Mitchell
• Thomas Telford publishing
NEC manuals
29/10/2021 c. Mott MacDonald | ECC Supervisor 66
• NEC3 A User’s Guide
• Jon Broome
• ice publishing
• Published March 2012
• NEC4 version coming soon
NEC3 A User’s Guide
www.neccontract.com
Mott MacDonald NEC Contract Advisory
Services
www.mottmac.com
richard.patterson@mottmac.com
+44 (0) 1223 463 606
29/10/2021 c. Mott MacDonald | ECC Supervisor 67
Further Information
Thank you
29/10/2021 Mott MacDonald | NEC Programme 69
Tonight's session was good because:
ⓘ Start presenting to display the poll results on this slide.

More Related Content

What's hot

CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3 Rae Davies
 
M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3Project Controls Expo
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Sarah Fox
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4Moustafa Ismail Abu Dief
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview WorkshopRae Davies
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 

What's hot (20)

CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
NEC Term Service Contract (TSC)
NEC Term Service Contract (TSC)NEC Term Service Contract (TSC)
NEC Term Service Contract (TSC)
 
M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3M4 - Making Target Cost Contracts Work, under NEC3
M4 - Making Target Cost Contracts Work, under NEC3
 
NEC Engineering and Construction Short Contract (ECSC) webinar
NEC Engineering and Construction Short Contract (ECSC) webinarNEC Engineering and Construction Short Contract (ECSC) webinar
NEC Engineering and Construction Short Contract (ECSC) webinar
 
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP ContractsFIDIC 2017 Yellow and Silver in EPC and PPP Contracts
FIDIC 2017 Yellow and Silver in EPC and PPP Contracts
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
Nec3 introduction
Nec3 introductionNec3 introduction
Nec3 introduction
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
NEC Framework Contract webinar
NEC Framework Contract webinarNEC Framework Contract webinar
NEC Framework Contract webinar
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4Managing Risks and Changes under NEC4
Managing Risks and Changes under NEC4
 
NEC3 compensation events
NEC3 compensation eventsNEC3 compensation events
NEC3 compensation events
 
Epc contractor
Epc contractorEpc contractor
Epc contractor
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Design-Build Procurement Approaches
Design-Build Procurement ApproachesDesign-Build Procurement Approaches
Design-Build Procurement Approaches
 
Construction Futures Wales - NEC Contracts Overview Workshop
Construction Futures Wales  - NEC Contracts Overview WorkshopConstruction Futures Wales  - NEC Contracts Overview Workshop
Construction Futures Wales - NEC Contracts Overview Workshop
 
Fidic law1
Fidic law1Fidic law1
Fidic law1
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
 

Similar to NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and responsibilities webinar

NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017Browne Jacobson LLP
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...Rae Davies
 
On the Road to 6D Challenges and Responsibilities in all Stages of the Projec...
On the Road to 6D Challenges and Responsibilities in all Stages of the Projec...On the Road to 6D Challenges and Responsibilities in all Stages of the Projec...
On the Road to 6D Challenges and Responsibilities in all Stages of the Projec...Mauricio Munoz
 
NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017Browne Jacobson LLP
 
Lec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfLec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfGhulamQadirWaqar1
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxEdenBekele5
 
FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptDonaAlisyahSiregar
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017DarrenTofu
 
Nec fidic-jbcc-gcc- ct-marketing (1) (2)
Nec fidic-jbcc-gcc- ct-marketing (1) (2)Nec fidic-jbcc-gcc- ct-marketing (1) (2)
Nec fidic-jbcc-gcc- ct-marketing (1) (2)GPTraining
 
cdm-2015-designers-interactive.pdf
cdm-2015-designers-interactive.pdfcdm-2015-designers-interactive.pdf
cdm-2015-designers-interactive.pdfPeterBeta1
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksPankaj K Sinha
 

Similar to NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and responsibilities webinar (20)

NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017NEC4 overview: key changes and impacts - London, September 2017
NEC4 overview: key changes and impacts - London, September 2017
 
Chapter 1- Procurement management
Chapter 1- Procurement managementChapter 1- Procurement management
Chapter 1- Procurement management
 
Chapter 3- Contract Management
Chapter 3- Contract ManagementChapter 3- Contract Management
Chapter 3- Contract Management
 
Chapter 6- Contract Management
Chapter 6- Contract ManagementChapter 6- Contract Management
Chapter 6- Contract Management
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
Edinburgh Trams to Newhaven Project.pptx
Edinburgh Trams to Newhaven Project.pptxEdinburgh Trams to Newhaven Project.pptx
Edinburgh Trams to Newhaven Project.pptx
 
M Simpson coursework
M Simpson courseworkM Simpson coursework
M Simpson coursework
 
Kandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _bKandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _b
 
On the Road to 6D Challenges and Responsibilities in all Stages of the Projec...
On the Road to 6D Challenges and Responsibilities in all Stages of the Projec...On the Road to 6D Challenges and Responsibilities in all Stages of the Projec...
On the Road to 6D Challenges and Responsibilities in all Stages of the Projec...
 
NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017NEC4 overview: key changes and impacts - Nottingham, September 2017
NEC4 overview: key changes and impacts - Nottingham, September 2017
 
Lec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfLec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdf
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
C. Site managment chapter 5.pptx
C. Site managment chapter 5.pptxC. Site managment chapter 5.pptx
C. Site managment chapter 5.pptx
 
Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]Chapter 3 [compatibility mode]
Chapter 3 [compatibility mode]
 
FIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.pptFIDIC.RICS CPD Event Singapore 2012.ppt
FIDIC.RICS CPD Event Singapore 2012.ppt
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
PASBA 2010 presentation
PASBA 2010 presentationPASBA 2010 presentation
PASBA 2010 presentation
 
Nec fidic-jbcc-gcc- ct-marketing (1) (2)
Nec fidic-jbcc-gcc- ct-marketing (1) (2)Nec fidic-jbcc-gcc- ct-marketing (1) (2)
Nec fidic-jbcc-gcc- ct-marketing (1) (2)
 
cdm-2015-designers-interactive.pdf
cdm-2015-designers-interactive.pdfcdm-2015-designers-interactive.pdf
cdm-2015-designers-interactive.pdf
 
Strategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract RisksStrategic Planning : the best way to manage EPC Contract Risks
Strategic Planning : the best way to manage EPC Contract Risks
 

More from Association for Project Management

Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Association for Project Management
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...Association for Project Management
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024Association for Project Management
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Association for Project Management
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...Association for Project Management
 
Scaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakScaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakAssociation for Project Management
 
Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Association for Project Management
 
Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Association for Project Management
 
Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Association for Project Management
 
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...Association for Project Management
 

More from Association for Project Management (20)

Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024Leadership - the project professionals secret weapon, 24 April 2024
Leadership - the project professionals secret weapon, 24 April 2024
 
APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...APM Project Management Awards - Hints and tips for a winning award entry webi...
APM Project Management Awards - Hints and tips for a winning award entry webi...
 
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
The Vyrnwy Aqueduct Modernisation Programme webinar, 17 April 2024
 
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
Team Lead Succeed – Helping you and your team achieve high-performance teamwo...
 
Staurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptxStaurt Earl - ARCC Programme for APM Awards.pptx
Staurt Earl - ARCC Programme for APM Awards.pptx
 
If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?If AI changes everything – do feelings still matter?
If AI changes everything – do feelings still matter?
 
AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...AI in the project profession: examples of current use and roadmaps to adoptio...
AI in the project profession: examples of current use and roadmaps to adoptio...
 
Katharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainabilityKatharine Fox, WRAP - Valuing sustainability
Katharine Fox, WRAP - Valuing sustainability
 
The silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutionsThe silent project disruptor: Building AI solutions
The silent project disruptor: Building AI solutions
 
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdfPersonal Resilience in Project Management 2 - TV Edit 1a.pdf
Personal Resilience in Project Management 2 - TV Edit 1a.pdf
 
Scaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peakScaling New Heights: Project Management on the world’s 3rd highest peak
Scaling New Heights: Project Management on the world’s 3rd highest peak
 
Demystifying digital accessibility webinar
Demystifying digital accessibility webinarDemystifying digital accessibility webinar
Demystifying digital accessibility webinar
 
Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...Inspire inclusion within the project profession to attract and retain a diver...
Inspire inclusion within the project profession to attract and retain a diver...
 
Burnout_ Prevention Intervention Recovery.pdf
Burnout_ Prevention Intervention  Recovery.pdfBurnout_ Prevention Intervention  Recovery.pdf
Burnout_ Prevention Intervention Recovery.pdf
 
Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...Discussing the new Competence Framework for project managers in the built env...
Discussing the new Competence Framework for project managers in the built env...
 
Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...Successful projects and failed programmes – the cost of not designing the who...
Successful projects and failed programmes – the cost of not designing the who...
 
Risk in the changing world – Opportunity or threat
Risk in the changing world – Opportunity or threatRisk in the changing world – Opportunity or threat
Risk in the changing world – Opportunity or threat
 
Time-Honored Wisdom: African Teachings for VUCA Leaders
Time-Honored Wisdom: African Teachings for VUCA LeadersTime-Honored Wisdom: African Teachings for VUCA Leaders
Time-Honored Wisdom: African Teachings for VUCA Leaders
 
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
APM Volunteer opportunities - Insights in how you can get involved, 7 Februar...
 
Including mental health support in project delivery
Including mental health support in project deliveryIncluding mental health support in project delivery
Including mental health support in project delivery
 

Recently uploaded

Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Jisc
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...Postal Advocate Inc.
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxChelloAnnAsuncion2
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxCarlos105
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxMaryGraceBautista27
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parentsnavabharathschool99
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 

Recently uploaded (20)

Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...Procuring digital preservation CAN be quick and painless with our new dynamic...
Procuring digital preservation CAN be quick and painless with our new dynamic...
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
USPS® Forced Meter Migration - How to Know if Your Postage Meter Will Soon be...
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptxGrade 9 Q4-MELC1-Active and Passive Voice.pptx
Grade 9 Q4-MELC1-Active and Passive Voice.pptx
 
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptxBarangay Council for the Protection of Children (BCPC) Orientation.pptx
Barangay Council for the Protection of Children (BCPC) Orientation.pptx
 
Science 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptxScience 7 Quarter 4 Module 2: Natural Resources.pptx
Science 7 Quarter 4 Module 2: Natural Resources.pptx
 
Raw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptxRaw materials used in Herbal Cosmetics.pptx
Raw materials used in Herbal Cosmetics.pptx
 
Choosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for ParentsChoosing the Right CBSE School A Comprehensive Guide for Parents
Choosing the Right CBSE School A Comprehensive Guide for Parents
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 

NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and responsibilities webinar

  • 1. In the NEC Engineering and Construction Contract The role of the Supervisor
  • 2. House Keeping Toilets Phones Fire alarms Drinks 29/10/2021 c. Mott MacDonald | ECC Supervisor 2
  • 3. Disclaimer This presentation is intended for internal use within the Mott MacDonald group of companies only. No person may rely on the content, information or any views expressed in this presentation. We accept no duty of care, responsibility or liability to any recipient of this presentation. This presentation is confidential and contains proprietary intellectual property. Nothing in this presentation constitutes financial, insurance or legal advice or opinion and it should not serve as an alternative to obtaining specialist legal advice from a professional legal services provider in relation to any specific circumstances. If you have any specific questions about any legal matter you should consult a professional legal services provider. No representation, warranty or undertaking, express or implied, is made and no responsibility or liability is accepted by us to any party as to the content of this presentation including, without limitation, its accuracy, completeness or reliability. We disclaim all and any liability whether arising in contract, tort or otherwise from the receipt, or use, of this presentation or any material contained in it, or from any action or decision taken as a result of the receipt, or use, of this presentation or any such material. Copyright The copyright (and any and all other intellectual property rights) in all material in this presentation is vested in Mott MacDonald Limited. You may not copy any part of this presentation or do any other act in relation to any part of this presentation which is protected by copyright (or any other intellectual property right) other than printing the presentation or any other part of it or saving it to a local hard disk for your personal use only. Apart from this you may not reproduce or store any part of this presentation in any form, or for any purpose, without our prior written consent. The above consents do not authorize you to incorporate any part of this presentation in any commercial document or in any material sold or otherwise made available to any third party, whether or not for profit, without our prior written consent. The content of this disclaimer shall be governed and construed in accordance with the laws of England and Wales. NEC Contracts Advisory services 29/10/2021 c. Mott MacDonald | ECC Supervisor 3
  • 4. 29/10/2021 Mott MacDonald | NEC Programme 4 Where are you calling in from? ⓘ Start presenting to display the poll results on this slide.
  • 5. 29/10/2021 (c) Mott MacDonald 2020 | NEC001 5 NEC Bitesize 2021 https://mottmac.sha repoint.com/legal/in dustryforms/nec/Pa ges/necsessions.as px Date Session Code 22 January 2021 NEC Contracts - An Introduction - Why are they so different? NEC0001 09 February 2021 NEC - Introduction to the NEC Professional Services Contract (PSC) - pre- award NEC0020 01 March 2021 NEC - Introduction to the NEC Professional Services Contract (PSC) - contract management NEC0021 30 March 2021 NEC Engineering and Construction Contract (ECC) - Contract strategy (main & secondary options) NEC0003 29 April 2021 NEC Engineering and Construction Contract (ECC) - Preparing the tender documents; tender evaluation NEC0004 24 May 2021 NEC Engineering and Construction Short Contract (ECSC) NEC00?? 22 June 2021 NEC ECC and temporary works NEC0028 14 July 2021 NEC Contracts - Programmes under ECC and PSC NEC0005 17 August 2021 NEC Contracts - The Risk Register/Early Warning Register and risk allocation and management NEC0006 13 September 2021 NEC Engineering and Construction Contract (ECC) - compensation events NEC0007 13 October 2021 NEC Engineering and Construction Contract (ECC) -The Supervisor's roles and responsibilities NEC0008 08 November 2021 NEC Engineering and Construction Contract (ECC) - Defined Cost, the Contractor's system and auditing NEC0009 08 December 2021 NEC and BIM NEC0026 RP1
  • 6. Slide 5 RP1 Richard Patterson, 11/02/2021
  • 7. 29/10/2021 c. Mott MacDonald | ECC Supervisor 6 Richard Patterson Chartered Engineer Mott MacDonald NEC Advisory Services 32Years with Mott MacDonald 25Years with The NEC 1 Year with NEC as NEC Consultant
  • 8. 29/10/2021 (c) Mott MacDonald 2020 | NEC001 7 What industry do you work in? ⓘ Start presenting to display the poll results on this slide.
  • 9. 29/10/2021 (c) Mott MacDonald 2020 | NEC001 8 Do you work for: ⓘ Start presenting to display the poll results on this slide.
  • 10. 29/10/2021 c. Mott MacDonald | ECC Supervisor 9 • Richard Patterson, WNE / Water Procurement and Project Finance Team, Cambridge • Petter Siljehag, BNI, SNI, Edinburgh • Karen Radband, • Hayman Choi, Environment, Cost & Project Management, Hong Kong • Advice and training – internal and external • Training to more than 15,000 people logged • Reviews and ……help NEC Contracts Advisory Services
  • 11. 29/10/2021 c. Mott MacDonald | ECC Supervisor 10 • Basic role • Works Information / Scope in ECC4 • Managing the contract • General • Tests and Defects • Title • Summary Contents
  • 12. NEC - Putting the contracts together 29/10/2021 R Patterson - ECC in 30 flipcharts 11 Employer (ECC4 Client) ECC Contractor PSC or PSSC PSC or PSSC PSC or PSSC advisor/ designer Project Manager Supervisor mgt mgt
  • 13. 29/10/2021 ECC4 PMA - Feb 2020 12 Key roles 1 early warning 2 Subcontractor acceptance 3 programme acceptance 2 design acceptance 1 changing Works Information/ Scope 4 testing and Defects 5 payment 6 compensation events technical both 7 title 8 insurance Project Manager Supervisor commercial Key stated period in relevant clauses period for reply applies ECC ‘Project Manager’ may also be client’s ‘project manager’
  • 14. 29/10/2021 c. Mott MacDonald | ECC Supervisor 13 • Supervisor is ‘like’ a ‘Clerk of Works’ … but with real actions and obligations under the contract. Needs to be ‘contractual’. • Supervisor role is to monitor that the Contractor does ‘Provide the Works in accordance with the Works Information / Scope’ The role
  • 15. 29/10/2021 c. Mott MacDonald | ECC Supervisor 14 Works Information / Scope is critical ! • 20.1 ‘The Contractor Provides the Works in accordance with the Works Information / Scope.’ • 54.1 (ECC4 55.1) (options A&C) ‘Information in the Activity Schedule is not Works Information / Scope or Site Information.’ • 60.1 ‘The following are compensation events. • (1) The Project Manager gives an instruction changing the Works Information / Scope ….. If it’s not in the WI / Scope then the Contractor does not have to do it. Simple !
  • 16. Inside Out The Supervisor must know the Works Information / Scope
  • 17. 29/10/2021 c. Mott MacDonald | ECC Supervisor 16 • specification and description of the works (11.2(19) (ECC4 11.2(16)) • constraints on Providing the Works (11.2(19) ECC4 11.2(16))) • works by the Completion Date (11.2(2)) • H&S requirements (27.4) • Contractor’s design • parts of the works that Contractor designs (21.1) • particulars of design for submission (21.2) • purposes for which Employer / Client may use Contractor’s design (22.1) Works Information / Scope References from the conditions 1 Green: Supervisor take particular note
  • 18. 29/10/2021 c. Mott MacDonald | ECC Supervisor 17 • Working with the Employer / Client and Others • cooperation and sharing of the Working Areas (25.1) • provides services and other things (25.2) • limitations on subcontracting (26.2) • any further information on the programme (31.2) • use of part of the works before take over (35.2) Works Information References from the conditions 2
  • 19. 29/10/2021 c. Mott MacDonald | ECC Supervisor 18 • tests and inspections (40.1 (ECC4 41.1) ) • materials, facilities and samples for testing (40.2 (ECC4 41.2)) • tests on Plant and Materials before delivery (41.1 (ECC4 42.1) • Preparation for marking of Equipment, Plant and Materials outside Working Areas by Supervisor (71.1) • title to materials (73.2) Works Information References from the conditions 3
  • 20. 29/10/2021 c. Mott MacDonald | ECC Supervisor 19 • C, D, E, F • acceptance / procurement procedures (11.2 (25) or 11.2 (26) (ECC4 11.2 (26) or 11.2(27)) • accounts and records (55.2) • X4, X13, X14, guarantees and bonds • form of parent company guarantee, performance bond, advance payment bond • X17 (low performance damages) • tests and performance levels Works Information – references from the conditions - 4
  • 21. And on to contract management
  • 22. Supervisor should have been called ‘Inspector’ 21 Mott MacDonald | ECC Introduction Role is to monitor (NOT ensure) ‘compliance’
  • 23. 29/10/2021 c. Mott MacDonald | ECC Supervisor 22 • Acceptance does not change the Contractor’s responsibility to Provide the Works or of his liability for his / its design (14.1) • Project Manager or Supervisor may delegate any of their actions (14.2) • Project Manager may instruct change to the Works Information / Scope (14.3) • …but NOT the Supervisor Project Manager and the Supervisor (14)
  • 24. 29/10/2021 c. Mott MacDonald | ECC Supervisor 23 Supervisor and Project Manager could be … • employees of the Employer • independent organisations • the same organisation or even • on a simple contract, the same person • two roles; two hats • Either way, separate roles – but talk to each other!
  • 25. Appointment and delegation Compensation events under the contract (CI.60.1 + certain main and secondary Options incl. Option Z) cost consultants (commercial support) Contract data part 1: either named individual or company (which must appoint individual) 29/10/2021 c. Mott MacDonald | ECC Supervisor 24 Project Manager Supervisor Employer / Client Contractor Contract (eg PSC) Communication designer(s) (technical support) Support Project Manager’s delegates. Actions delegated under 14.2 Supervisor’s delegates. Actions delegated under 14.2 Delegation
  • 26. 29/10/2021 c. Mott MacDonald | ECC Supervisor 25 • 1 General • 2 Contractor’s main responsibilities • 3 Time • 4 testing and Defects • 5 Payment • 6 Compensation Events • 7 Title, 8 Risks and insurance • W Dispute resolution and 9 termination Agenda 2: Managing the Contract Key issues for the Supervisor in green
  • 27. 29/10/2021 c. Mott MacDonald | ECC Supervisor 26 • 1 General • 2 Contractor’s main responsibilities • 3 Time • 4 testing and Defects • 5 Payment • 6 Compensation Events • 7 Title, 8 Risks and insurance • W Dispute resolution and 9 termination Agenda 2: Managing the Contract
  • 28. 29/10/2021 c. Mott MacDonald | ECC Supervisor 27 RT_C Read the _ contract 10.1 The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of mutual trust and co-operation. DWISIT_C Do what it says in the _ contract _TalTEO _ talk and listen to each other ECC4 splits 10.1 into 10.1 and 10,2 - no real effect
  • 29. 29/10/2021 c. Mott MacDonald | ECC Supervisor 28 • Identified terms in Contract Data in italics • Defined terms, capitalised and all in 11.2 READ THEM! Eg and especially for the Supervisor • (2) Completion (done all the work the Works Info requires for Completion and no Defects that would prevent Employer/Client using the works) • (5 (ECC4 (6)) Defect (two types) • (6 (ECC4 (7)) Defects Certificate (list of Defects at defects date) • (19) Works Information (ECC4 (16) Scope) (what is to be provided and constraints) Identified and Defined Terms
  • 30. 29/10/2021 c. Mott MacDonald | ECC Supervisor 29 • in a form that can be read, copied & recorded (13.1) • replies within period for reply or period as in contract (13.3) • Notifications communicated separately (13.7) • NEED A SYSTEM! • forms – basic versions on www.neccontract.com • forms – developed versions on MM NEC intranet site and required • Developed forms in NEC ‘Manuals’ • bespoke IT systems available – CCM, CEMAR, Sypro, others - we know them! Communications (13)
  • 31. 29/10/2021 c. Mott MacDonald | ECC Supervisor 30 The best place for the contract is … No, NEC is NOT a contract for the ‘bottom drawer’!
  • 32. 29/10/2021 c. Mott MacDonald | ECC Supervisor 31 • 34.1 The Project Manager may instruct the Contractor to stop or not to start any work and may later instruct him that he may re- start or start it. Before we really start … Stop the work! • Supervisor needs to be PM delegate for this action – at least for health and safety issues
  • 33. 29/10/2021 c. Mott MacDonald | ECC Supervisor 32 • 1 General • 2 Contractor’s main responsibilities • 3 Time • 4 testing and Defects • 5 Payment • 6 Compensation Events • 7 Title, 8 Risks and insurance • W Dispute resolution and 9 termination Agenda 2: Managing the Contract
  • 34. Part 4, Quality management, has only one and a half pages! 33 Mott MacDonald | ECC Introduction
  • 35. 29/10/2021 Mott MacDonald | ECC Introduction 34 Tests and inspections all between Contractor and Supervisor – ideally the Contractor’s ‘quality manager’ only applies if ‘tests and inspections ’ required by the Works Information (ECC4 Scope) or the law materials, facilities and samples for tests and inspection provided … ‘as stated in the Works Information’ (ECC4 Scope) The C and the S informs the other of each of their tests and inspections before the test or inspection starts and afterwards informs the other of the results. If ‘test or inspection’ shows Defect, the Contractor corrects the Defect and the test or inspection is repeated.. The C informs the S in time for a test or inspection to be arranged and done before doing work which would obstruct the test or inspection. The S may watch any test …… There is no ‘inspection and testing plan’
  • 36. 29/10/2021 Mott MacDonald | ECC Introduction 35 ECC4 new 40.1 Quality Management System Contractor operates quality management system which complies with the Scope Contractor provides the Project Manager with policy statement and quality plan for acceptance … and changes to the quality plan Project Manager may instruct Contractor to correct failure to comply with quality plan: not a compensation event) Note: • Basically copied across from PSC3 • Project Manager, not Supervisor • Bidders may have an issue with their (corporate) quality policy statement needing acceptance of the PM! • Just adds one to ECC3 clause numbers!
  • 37. (6) A Defect is • a part of the works which is not in accordance with the Scope or • a part of the works designed by the Contractor which is not in accordance with the applicable law or the Contractor’s design which the Project Manager has accepted. 36 Mott MacDonald | ECC Introduction
  • 38. 29/10/2021 R Patterson - ECC in 30 flipcharts 37 testing and Defects 40.1 (41.1) tests and inspections in Works Information / Scope by Supervisor by Contractor watched by Supervisor notify Defect (42.2 (43.2)) fail In Works Information / Scope, details of tests/inspections: • Prior to delivery to Site • Factory Acceptance Tests • Routine tests on Site • tests for Completion • X17 - Performance tests re performance levels (in Works Info / Scope for Contractor’s design – link to performance damages • Who to carry out tests • Who to provide facilities for testing • Pass criteria search for Defects (42.1 (43.1)) Inspections (40.3 (41.3)) Logically (but not in contract) add to ‘list of Defects’ At defects date or end of last defects correction period, issue Defects Certificate (43.3 (44.3)) notify results (40.3 (41.3)) Defects Certificate (11.2(6) (11.2(7)) is a list of Defects
  • 39. 29/10/2021 Mott MacDonald | ECC Introduction 38 So negative! • 42.1 The Contractor does not bring to the Working Areas those Plant and Materials which the Scope states are to be tested or inspected before delivery until the Supervisor has notified the Contractor that they have passed the test or inspection. • Just about the only positive action from the Supervisor!
  • 40. 29/10/2021 c. Mott MacDonald | ECC Supervisor 39 • a part of the works which is not in accordance with the Works Information / Scope or • a part of the works designed by the Contractor which is not in accordance with the applicable law or the Contractor’s design which the Project Manager has accepted. • No ‘Snags’, no ‘NCRs’ in ECC – just ‘Defects’! A Defect is (11.2(5) (ECC411.2(5))
  • 41. 42.2 (ECC4 43.2) Until the defects date the Supervisor and the Contractor notifies the other as soon as they become aware of a Defect. 40 Mott MacDonald | ECC Introduction notifications have to be separate (13.7)
  • 42. 29/10/2021 c. Mott MacDonald | ECC Supervisor 41 • Clause 40 (ECC4 41) (Tests and Inspections) only applies to tests • required by the Works Info / Scope • or the law • tests/inspections may be needed: • before delivery • ongoing • to achieve Completion (Cl11.2(2)) - the KEY • before take over - normally NONE • to demonstrate performance level (Option X17) • who, when, where, how, pass criteria? Testing Requirements in the Works Information / Scope
  • 43. 29/10/2021 c. Mott MacDonald | ECC Supervisor 42 Tests and inspections • all between Contractor and Supervisor • materials, facilities and samples for tests and inspection provided … ‘as stated in the Works Information / Scope’ • If ‘test or inspection’ shows Defect then: • Notify the Defect • correct and repeat (ECC3 40.4; ECC4 41.4) • Project Manager assesses cost to Employer in repeating test (ECC3 40.6, 40.7in C,D.E; ECC4 41.6 and 41.7 in C,D.E) Need a clear testing plan and records system – ideally part of the Contractor’s QA/QC system….
  • 44. Simple form needed • All done before • Compass / Group support services / contracts / NEC / contract administration Also need a simple, joint list of Defects 29/10/2021 c. Mott MacDonald | ECC Supervisor 43
  • 45. 29/10/2021 c. Mott MacDonald | ECC Supervisor 44 See Mott MacDonald starter for a list of Defects https://mottmac.sharepoint.com/:x:/s/Practices/projectprogrammeandcommercialmgt/EXQVctbksENAoC_- BLmOzrUBrSwv1LaT1Ue9UFKEuEBkMQ?email=Richard.Patterson%40mottmac.com&e=4%3AKcxPs0&at=9
  • 46. 29/10/2021 c. Mott MacDonald | ECC Supervisor 45 • Correcting Defects (43 (ECC4 44)) • Contractor corrects Defect whether notified or not (43.1 (ECC4 44.1)) • Contractor corrects notified Defects before the end of the (relevant) defects correction period (43.2 (ECC4 44.2)) Correcting Defects No formal clause under which to confirm correction of a Defect and ‘acceptance’ by Supervisor • Project Manager arranges for the Employer / Client to provide access required to correct a Defect (43.4 (ECC4 44.4)) after take over
  • 47. 46 The Supervisor issues the Defects Certificate There is no ‘Maintenance Period’ – just the ‘period with no name’ from the date of Completion to the defects date defects correction period (43.2) Defect notified defects correction period defects correction period Defect notified defects correction period Defect notified 43.4 – defects correct period starts when PM has arranged access to correct Completion is when the Contractor has • done all the work which the Works Information / Scope states he is to do by the Completion Date and • corrected notified Defects which would have prevented the Employer / Client from using the works and Others from doing their work. Contract Date date of Completion defects date The defects date is last date for Supervisor to • instruct search for (42.1 (EEC4 43.1)) or • notify (42.2 (EEC4 43.2)) ) a Defect
  • 48. There is no formal process for the Supervisor to ‘accept’ anything including that a Defect has been corrected 47 Mott MacDonald | ECC Introduction
  • 49. 29/10/2021 c. Mott MacDonald | ECC Supervisor 48 • accepting Defects • Proposals to Project Manager (not Supervisor) that Defect is not corrected (44.1 (ECC4 45.1)) • quotation for reduced Prices and/or earlier Completion Date (44.2 (ECC4 45.2) ) • a mechanism to ‘do a deal’ • uncorrected Defects (45 (ECC4 46)) • Contractor pays where Contractor has not corrected Defect within defects correction period Accepting Defects; uncorrected Defects
  • 50. 29/10/2021 c. Mott MacDonald | ECC Supervisor 49 • 11.2 (2) Completion - definition • done all the work the Works Info requires for Completion and • no Defects that would prevent Employer using works • Supervisor looks after tests (including for Completion) and Defects • but Project Manager certifies Completion (30.2) • Employer/Client (unless they has said in Contract Data that it won’t take over before Completion Date) takes over within two weeks of Completion (35.1) • Project Manager certifies take over of any part of the works taken over by the Employer/Client (35.3) Completion and take over Supervisor and Project Manager
  • 51. 29/10/2021 c. Mott MacDonald | ECC Supervisor 50 • 11.2 (6) (ECC4 11.2(7)) The Defects Certificate is either a list of Defects that the Supervisor has notified before the defects date which the Contractor has not corrected or, if there are no such Defects, a statement that there are none. • 43.3 (ECC4 44.3) The Employer’s rights in respect of a Defect which the Supervisor has not found or notified are not affected by the issue of the Defects Certificate. • PM assesses cost of remaining Defects (45 (ECC4 46)) and makes last assessment of amount due The Supervisor issues the Defects Certificate Defects Certificate is one action of the Supervisor that is not normally delegated. Get the defects date in your diary! • Supervisor issues the Defects Certificate • (ECC3 43.3) at the later of the defects date and the end of the last defect correction period. • (ECC4 44.3) at the defects date if there are no notified Defects, or otherwise at the earlier of • the end of the last defect correction period and • the date when all notified Defects have been corrected.
  • 52. 29/10/2021 c. Mott MacDonald | ECC Supervisor 51 • 1 General • 2 Contractor’s main responsibilities • 3 Time • 4 testing and Defects • 5 Payment • 6 Compensation Events • 7 Title, 8 Risks and insurance • W Dispute resolution and 9 termination Agenda 2: Managing the Contract
  • 53. 29/10/2021 c. Mott MacDonald | ECC Supervisor 52 • Contractor’s title to Plant and Materials passes to Employer (70, 71) • when within Working Areas • outside Working Areas – only when ‘marked by the Supervisor’ for this contact’ • 71.1 The Supervisor marks Equipment, Plant and Materials which are outside the Working Areas if • this contract identifies them for payment and • the Contractor has prepared them for marking as the Works Information requires. 7 Title WARNING – Contractor can only pass on title that it has. May need procedures for ‘vesting’ – which are NOT in NEC.
  • 54. The period with no name!! – ECC4 83.3 no need for C to insure X16.2: retention halved 80.1 Loss of or damage to the parts of the works taken over by the Client assessment interval PM continues routine payment assessment and certificates (50.1) Contractor corrects within one defects correction period Supervisor issues Defects Certificate (44.3) at the defects date if no Defects or at earlier of • End of last dcp or • When all Defects corrected X16.2 – retention taken to zero target options: include final assessment of Contractor’s share Defects? PM assesses cost of (46)) certified by PM (30.2) date of Completion defects date The period with no name – set in Contract Data part one assessment at Completion (50.1) dcp starts only when PM has arranged and Client has provided access (44.4) target options: include prelim assessment of Contractor’s share take over certified by PM (35.3) < 2wks 4 wks (50.1) Last PM assessment of amount due (50.1) and payment certificate (51.1) Supervisor can notify Defects (43.2)
  • 55. 29/10/2021 c. Mott MacDonald | ECC Supervisor 54 Supervisor role summary • Focused 100% on Contractor’s compliance with Works Information • testing • Defects – including issue of Defects Certificate • Title • ONLY • But may /should also be supporting PM
  • 56. 29/10/2021 c. Mott MacDonald | ECC Supervisor 55 Supervisor and Project Manager interaction More than explicit in the contract Free at: https://www.neccontract.com/ The-interaction-between-the- Supervisor-PM
  • 57. So how much of a Supervisor do we need? 29/10/2021 c. Mott MacDonald | ECC Supervisor 56
  • 58. 29/10/2021 c. Mott MacDonald | ECC Supervisor 57 But where else might the Supervisor support Project Manager? • records, records, records • site diary • photographs • Contractor’s resources – Disallowed Cost (C,D,E,F) • progress records • early warnings (16 (ECC4 15)) • ambiguities (17)
  • 59. NEC Contracts – The Truth will Out 58 • NEC demands good communication • NEC demands active management
  • 62. 29/10/2021 Mott MacDonald | NEC articles 61 Some of our NEC articles, papers and books Year Title Where published 2021Using NEC Outside the UK: an update NEC Newsletter , March 2021 2020Three years on it is time for clients to switch from NEC3 to NEC4 NEC Newsletter , Sept 2020 2020Helping NEC clients decide the best way to get a first programme in place NEC Newsletter , Sept 2020 2020NEC family of contracts pitches clearer, more flexible project management PMI UK Chapter 'Leader' magazine (article a copy of that previously published by IACCM)
  • 63. 29/10/2021 Mott MacDonald | NEC articles 62 Some of our NEC articles, papers and books Year Title Where published 2020NEC contracts: best practice tools for risk allocation and management NEC website May 2020 2020The all important F-words in the NEC NEC Newsletter , March 2020 2020ECC Risk allocation and compensation events NEC website, March 2020 2020How to ensure that bid-winning supply chains actually get used NEC Newsletter, January 2020 2019Project overruns? It’s time to use the F-word (and a proper contract) Mott MacDonald website 2019Links between key NEC processes NEC Newsletter, May 2019 2018Building time-related charges into NEC lump-sum and short contracts NEC Newsletter, November 2018 2018NEC Early warnings - the need for education NEC Newsletter, November 2018 2018NEC contracts – use them anywhere for any industry! - including how NEC covers PMI's ideas on procurement and project management IACCM's Contracting Excellence Journal, 18 June 2018 2018Design of Equipment in the ECC NEC Newsletter, 91, May 2018 2018NEC3 to NEC4 – evolution, not revolution; some fixes and some good ideas! In-procurement Magazine JanFeb 2018 2018NEC3 to NEC4 – evolution, not revolution; some fixes and some good ideas! ICE's Management Procurement and Law, December 2017 and on NEC website from 26 Feb 2018 2018NEC Contracts - are they right for you? IACCM Contracting Excellence Journal, Feb 2018 2017NEC Engineering and Construction Contract (ECC): the necessary interaction between the Supervisor and the Project Manager Construction Law Quarterly / NEC website 2017When is task not a Task - in the NEC TSC contract NEC Newsletter Sep 2017, NEC website 2017NEC: how to require something is done by a certain date NEC Newsletter No 86, July 2017, NEC website 2017New NEC4 Design, Build and Operate Contract NEC website 2016How to procure a series of work packages using NEC NEC website 2016NEC contracts are ideal to support project management as set out in the PMI’s ‘Project Management Body of Knowledge’ (PMBOK®) Linked-in
  • 64. 29/10/2021 Mott MacDonald | Prep of tender docs 63 Year Title Where published 2016How to procure a series of work packages using NEC NEC website 2016NEC contracts are ideal to support project management as set out in the PMI’s ‘Project Management Body of Knowledge’ (PMBOK®) Linked-in 2016Submission of deliverables under the PSC NEC Newsletter No 80, September 2016 2016Enforcement Clauses and Links in the ECC NEC Newsletter No 79, July 2016 2016Can we use the NEC as the basis for a standard international PPP contract? ACE's email newsletter, Infrastructure Intelligence 2016NEC contracts - good for hydropower? NEC Newsletter No 76, January 2016 2015NEC contracts - good for hydropower? Proceedings Hydro 2015, Bordeaux 2015Using NEC to incentivise lowest whole-life cost NEC Newsletter No 75, November 2015 2015NEC3 Compared and Contrasted, Second Edition - chapter on NEC vs IChemE contracts ICE publishing 2015NEC3 - the Role of the Supervisor ICE publishing 2015NEC for design build finance and operate (DBFO) contracts – taking best practice procurement into PPPs ICE’s Management, Procurement and Law, November 2015, and winner of the Parkman medal for best MPL paper, 2015 2015NEC contracts and the CDM Regulations 2015 ICE’s Management, Procurement and Law, 168, June 2015 2015NEC contracts tick IACCM’s ‘top ten’ box NEC website 2015Making the most of your early warnings – sorting out your TQs and RFIs…. and what about the opportunities? NEC website 2015NEC contracts and the Construction (Design and Management) Regulations 2015 NEC website 2015NEC contracts and the CDM Regulations 2015 NEC Newsletter No 72, May 2015 2014Getting your project set up for ECC NEC Newsletter No 70, January 2015 (published December 2014) 2014Working with NEC Contracts (in landscape architecture) Landscape (Magazine of the Landscape Institute,. Winter 2014 Some of our NEC articles, papers and books
  • 65. 29/10/2021 Mott MacDonald | Prep of tender docs 64 Some of our NEC articles, papers and books Year Title Where published 2014ECC Works Information provided by the Contractor - who takes the risk? NEC Newsletter No 69, October 2014 2014Understanding expenses in a PSC NEC Newsletter No 67, July 2014 2014The importance of quality works information and site information in ECC projects NEC Newsletter No 66, April 2014 2013NEC for DBO Proceedings of the ICE - Management, Procurement and Law, Volume 166, Issue 5, May 2013 2013How to prepare the Scope for an NEC PSC Contract By NEC as part of NEC April 2013 2012Managing Reality - the ECC Manuals ICE publishing 2012NEC3: A User's Guide ICE publishing 2011NEC3: contracts for partnering NEC Newsletter No 56, October 2011 2010Ground Conditions and Risk Allocation: Combining the NEC Engineering and Construction Contract (ECC) and the Geotechnical Baseline Report (GBR) Tunnels and Tunnelling Magazine, Dec 2010 20106 key links in the ECC NEC Newsletter No 51, July 2010 2010NEC contracts as an enabler to Partnering May 2010 edition of 'The Partner', which is ‘the annual publication of PSL, which is a CBI and BIS initiative to promote collaborative business relationships www.pslcbi.com ' 2009Using NEC contracts to manage risk and avoid disputes Proceedings of the ICE - Management, Procurement and Law, 2009, No 4. 2009Use of NEC in legal jurisdictions other than English law NEC Newsletter, No,47, July 2009 2009NEC – A real opportunity for the Clerk of Works Site Recorder, Magazine of the Institute of Clerks of Works 2007NEC and Risk Management NEC Newsletter No 40, Oct 2007 2005NEC Managing Reality: Introduction to the Engineering and Construction Contract. 5 volumes ICE publishing 2007Dealing with contingencies - what happened to the 'Provisional Sum' NEC Newsletter No 40, Oct 2007 2007NEC3 key dates – more risk on the contractor NEC Newsletter No 40, Oct 2007 2001Using NEC for multiple site, undefined contracts ICE’s ‘Civil Engineering’, May 2001 2000NEC and PFI first for Leeds Healthcare NEC Newsletter No 14, July 2000
  • 66. 29/10/2021 c. Mott MacDonald | ECC Supervisor 65 • NEC Managing Reality • Five volumes covering all aspects of NEC (ECC) • 2nd Edition 2013 • Barry Trebes (Mott MacDonald) and Bronwyn Mitchell • Thomas Telford publishing NEC manuals
  • 67. 29/10/2021 c. Mott MacDonald | ECC Supervisor 66 • NEC3 A User’s Guide • Jon Broome • ice publishing • Published March 2012 • NEC4 version coming soon NEC3 A User’s Guide
  • 68. www.neccontract.com Mott MacDonald NEC Contract Advisory Services www.mottmac.com richard.patterson@mottmac.com +44 (0) 1223 463 606 29/10/2021 c. Mott MacDonald | ECC Supervisor 67 Further Information
  • 70. 29/10/2021 Mott MacDonald | NEC Programme 69 Tonight's session was good because: ⓘ Start presenting to display the poll results on this slide.