SlideShare a Scribd company logo
1 of 52
CONDITION SURVEY AND NON
DESTRUCTIVE EVALUTION
AVINASH KUMAR GUPTA
CCW TRAINING INSTITUTE
NEW DELHI
07/04/2017
CONDITION SURVEY
• Examination of concrete
• For identifying and defining areas of distress.
• Recording history from inception to
completion and subsequent life.
Objective
• Identify cause of distress and sources
• Assess: extent of distress due to corrosion,
fire, earthquake, any other reason
• Asses residual strength of structure and its
rehabilitability
• Prioritize the distressed elements as per
seriousness.
• To select and plan the effective remedy.
Stages of condition survey
• Prioritize distressed elements according to
seriousness for repairs.
• a) Preliminary inspection
• b) Planning
• c)Visual Inspection
• d) Field and laboratory testing.
Preliminary inspection
• History of structure from client, owner,
occupants, General public in building,
• Note records, previous repairs history and
expenses done for the same.
• All possible data and information.
• Practical restriction in survey and safety
requirements for survey team.
• Extent and quantum of survey work
• Time required ( survey and execution )
• Advise immediate safety measures
Information gathering
• . Period of construction
• Construction details (drg,arch,structural )
• Exposure conditions
• Designed and present use of structure.
• Previous changes in use
• Record of structural changes if done.
• Record of 1st
occurrence of defect.
• Details of repairs carried out previously.
• Previous reports etc.
• Details from owner, photographs
Planning survey
• Field documents
• Plans and actual observations each room-
wise.
• Previous report , advise if any and
implementation done as per report,
• Grouping of structural elements ( external,
interior etc )
• Exposure conditions
Classification of damage
• Class O : No distress but cosmetic repairs
• Class 1 : Minor repairs ( superficial repairs )
• Class 2 : Medium repairs ( patch repairs )
(minor structure cracks)
• Class 3 : Principal repairs (spalling of cover
concrete,structural cracks,cracks along bars)
• Class O : Major repairs(replacement of
structural Members)
Grade for Assessment of the building
• Based on the inspection and observation the distress level of the
selected buildings may be categorizedas mentioned below:
• G1 – No distress observed
• G1 – Minor distress observed in few structural members, which can
be repaired under the advice of a structural engineer.
• G2 – Medium distress observed in few structural members, which
can be repaired / rehabilitated including strengthening with the
advice of a structural engineer
• G3 – Severe distress observed in some of the structural members,
which can be rehabilitated including strengthening with the advice
of a structural engineer.
• G4 – Severe distress is observed which could prove dangerous,
hence evacuation at an early date is required.
Visual Inspection
• Workmanship, structural serviceability, material
deterioration mechanism
• General health( structural and non structural elements)
• Preparation of estimate / bill of quantities.
• Quantify extent of distress
• Photographic record.
• Obstructions for visual inspection to be noted.
• Understanding structural system / deviations
• Leakage , seepage due to inadequate drainage system
• Types of cracks and its pattern
• Color and texture of concrete surface (chemical attack or
disintegration by way of leaching
Record
• Areas of high distress
• Cracks and their locations
• Excessive deflections
• Exposure conditions of various distressed areas.
• Moisture / seepage / leakages / dampness
locations.
• Abnormal vibrations in structure.
• Algae, fungus growth, trees on structure.
• Photographic record.
• Areas of immediate concern
Considerations for repairs strategy
• Identification of cause of problem.
• Assessment and extent of damage.
• Availability space and accessibility w.r.t.
ongoing activities in building.
• propping structural members in case of major
repairs , severely damaged elements (columns
etc ).
• Safety measures to avoid mishaps
Non destructive Evaluation tests
• These tests do not impair performance of the
member, They are field or laboratory tests.
• Put under five categories based on purpose,
In-situ-Concrete strength
Chemical attack
Corrosion activity
Fire damage
Structural integrity and soundness
Non Destructive Testing
• Nondestructive testing in the broad sense
refers to methods whereby internal
characteristics of solid structures can be
examined without permanently affecting the
structure. Thus, parts that prove to be
satisfactory under specified test conditions
are not degraded by the test procedures
NDT , Introduction
• Nondestructive testing (NDT) is the process of
inspecting, testing, or evaluating materials,
components or assemblies for discontinuities,
or differences in characteristics without
destroying the serviceability of the part or
system. In other words, when the inspection
or test is completed the part can still be used
NDT- Purpose
•-Assessment of Existing Structures in the
Absence of Drawings.
•-Quick assessment of the structure
NDT -Advantages
• Access to hidden items – “see through
walls”
• Better investigations with NDT
• Rapid accumulation of data
• Generally less expensive than destructive
testing.
NDT - Disadvantages
1. More than one test method may be required
2. Environmental conditions may effect or
distort results
3. Construction details & building components
may effect results
4. Some conditions cannot be determined with
a reasonable degree of accuracy without
destructive testing
Non destructive Testing
• A : In- situ-concrete test
• - rebound hammer
• - Ultrasonic pulse velocity
• - Windsor probe
• - Pull out test :
• Core cutting / sampling, lab testing of cores
• - Load test
Non destructive Testing
• B : Chemical attack
• Carbonation test
• Chloride test
• Sulphate test
• C: Corrosion potential assessment
• Cover meter ( checking cover)
• Half cell potential
• Resistivity meter
• Permeability ( air and water )
Non destructive Testing.
• D: Fire damage assessment
• Thermo gravimetric analysis (TGA)
• Differential Thermal analysis (DTA)
• X-ray diffraction (XRD)
• E: Structural Integrity/ soundness
• Ultrasonic pulse velocity ( discontinuities, cracks
and depth of cracks)
• Radiography
• Impact echo test
• The rebound hammer can provide a fairly
accurate estimate of concrete compressive
strength.
• The concrete should be 14 to 56 days old.
• Surface Condition:
• The surface of the concrete at the point tested
must be smooth, dry, and free of honeycombing.
Otherwise, rebound readings will be low
Indicating a weaker concrete than is actually the
case. The rubbing stone provided can be used to
grind the surface smooth, if necessary
Location of Test PointsLocation of Test Points
• The concrete to be tested must be at least
four inches thick: It is also recommended that
readings be taken only where the concrete
has been in contact with the form. These
conditions are most easily satisfied if the
readings are taken along the edge of the tank
on the sides and ends where the adjoining
concrete face (i.e., wall, top, or bottom) can
support the point of contact.
PROCEDURE
• Remove hammer from case and press the
plunger end against a hard surface to release the
plunger from the locked position. (Do not press
lock button while doing this.)
• Position hammer horizontally with plunger end
against wall at a point.
• Slowly apply pressure until hammer fires. This
will occur when only approximately 1/2 inch of
the plunger is still visible. Do not press the lock
button during this step.
• A). Remove hammer from case and press the
plunger end against a hard surface to release
the plunger from the locked position. (Do not
press lock button while doing this.)
• B). Position hammer horizontally with plunger
end against wall at a point.
• C). Slowly apply pressure until hammer fires.
This will occur when only approximately 1/2
inch of the plunger is still visible. Do not press
the lock button during this step
Procedure Contd.
• With the hammer still pressed against the
wall, read the rebound number off the scale
provided on the hammer. If it is necessary to
move the hammer before reading, press the
lock button. The rebound number should be
read to two significant figures.
• Repeat the above procedure at different
points around the wall until a total of ten
readings has been taken
This is based on the principle that the velocity
of an ultrasonic pulse through any material
depends upon the density. Comparatively
higher velocity is obtained when concrete
quality is good in terms of density, uniformity
etc.
Pulse Velocity measurements can be used to
assess the presence of cracks, voids etc.,
quality of concrete relative to standards
requirements.
UPV Test contd.
There are three possible ways of measuring
pulse velocity.
 i) Direct transmission
ii) Semi direct transmission
iii) Indirect transmission (surface probing)
Out of the three methods, the direct
transmission method is considered to be the
best
condition of concrete based on
pulse velocity are given below
S.No. Pulse Velocity Condition of concrete
I in(Km/Sec.)
•1. Above 4.5 Excellent
•2. 3.5 to 4.5 Good
•3. 3.0 to 3.5 Medium
•4. Below 3.0 Poor
PULLOUT TESTPULLOUT TEST
• The fundamental principle behind pull out testing
with LOK-test and CAPO test is that the test
equipment designed to a specific geometry will
produce results (pull-out forces) that closely
correlate to the compressive strength of concrete.
The first method ,using the cast steel disc is called LOK
test. The second method shown in fig.2 using
expandable ring is called CAPO test (i.e. Cut and Pull
out Test). The diameter of both the disc and ring is
25mm. the distance to the concrete surface is also
25mm. the inner diameter of the counter-pressure is
55mm.
The relationship between the pullout force Fu
in kN and compressive strength Fc in MPa
The relationship between the pullout force Fu in kN and compressive strength Fc in MPa is given in fig
04/14/17 38
Pull out tests are used toPull out tests are used to
 Determine in-situ compressive strength of the
concrete
 Ascertain the strength of concrete for
carrying out post tensioning operations.
 Determine the time of removal of forms and
shores based on actual in-situ strength of the
structure.
 Terminate curing based on in-situ strength
of the structure
4.Core cutter4.Core cutter
The test should be taken at points where
minimum strength and maximum stress are
likely to coincide. But, at the same time, the
core cutting causes some damage to the
member and may impair the future
performance of the member. Therefore, in
slender members, the core should be taken
away from the critical section. For
compression testing, the diameter of the core
should be at least three times the nominal
maximum aggregate size
Core Cutter is used to cut the core from the
existing concrete structure for testing the
physical properties of the concrete like
compressive strength, density, water
absorption, crack depth and chemical test like
depth of carbonation and chloride content
etc. It can also be used to inspect the interior
region of the structural members.
Core Cutter Set UP
• Cover meters are electromagnetic in
operation. Electric currents in a coil winding in
the search head generate a magnetic field
which propagates through the concrete and
will interact with any buried metal present,
such as reinforcing steel.It is the generic term
for equipment used to locate steel reinforcing
bar in concrete and to estimate the thickness
of the concrete cover over the reinforcement
04/14/17 46
Tomography means imaging an object by
taking measurements from “slices” of its cross-
section.
Tomography means imaging an object by taking
measurements from “slices” of its cross-section.
04/14/17 47
4/14/17 4
04/14/17 49
This test is carried out to assess the quality / uniformity of concrete
at various depths. The instrument consists of a four probe device.
Electrical current is passed through the outer probes & the potential
drop is measured by the inner probes. From the current & voltage
drop measurements, the resistivity of concrete can be measured.
Electrical resistivity = 2(pi)aE/i (in kilo-ohm cm)
where a = distance between probes
= 5 cm in the 1st set of readings
= 10 cm in the 2nd set of readings
E = potential difference between inner two probes in mV
Most useful test in tunnel structure
CONDITION SURVEY AND NDE
CONDITION SURVEY AND NDE

More Related Content

What's hot

Advantages and types of prestressing
Advantages and types of prestressingAdvantages and types of prestressing
Advantages and types of prestressingSaurav Chaudhary
 
Deterioration of Concrete Structures
Deterioration of Concrete StructuresDeterioration of Concrete Structures
Deterioration of Concrete StructuresRAMPRASAD KUMAWAT
 
Chapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairsChapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairsAnkit Patel
 
Repair & Rehabilitation of Structures
Repair & Rehabilitation of StructuresRepair & Rehabilitation of Structures
Repair & Rehabilitation of StructuresRamanuj Jaldhari
 
Earthquake Resistant Building
Earthquake Resistant Building  Earthquake Resistant Building
Earthquake Resistant Building akhil reddy
 
Crack repair techniques
Crack repair techniquesCrack repair techniques
Crack repair techniquesNayana 54321
 
demolition techniques
demolition techniquesdemolition techniques
demolition techniquesbholu sharma
 
Construction of Special Structures.pptx
Construction of Special Structures.pptxConstruction of Special Structures.pptx
Construction of Special Structures.pptxAnanthakumar75
 
BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE VISHNU VIJAYAN
 
Causes & Damage Detection
Causes & Damage DetectionCauses & Damage Detection
Causes & Damage DetectionAbhay Abhale
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSASHOK KUMAR TIWARY
 
Different types of damages that have been observed in masonry buildings durin...
Different types of damages that have been observed in masonry buildings durin...Different types of damages that have been observed in masonry buildings durin...
Different types of damages that have been observed in masonry buildings durin...Nitin Kumar
 
Rebound Hammer Test-priciple,procedure,cons&pros.....
Rebound Hammer Test-priciple,procedure,cons&pros.....Rebound Hammer Test-priciple,procedure,cons&pros.....
Rebound Hammer Test-priciple,procedure,cons&pros.....SJMIT,now NMAMIT NITTE
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )mohit kumar panchal
 
Durability and Permeability of Concrete
Durability  and Permeability of ConcreteDurability  and Permeability of Concrete
Durability and Permeability of ConcreteGAURAV. H .TANDON
 

What's hot (20)

Advantages and types of prestressing
Advantages and types of prestressingAdvantages and types of prestressing
Advantages and types of prestressing
 
Deterioration of Concrete Structures
Deterioration of Concrete StructuresDeterioration of Concrete Structures
Deterioration of Concrete Structures
 
Chapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairsChapter 3 materials & techniques for repairs
Chapter 3 materials & techniques for repairs
 
Repair & Rehabilitation of Structures
Repair & Rehabilitation of StructuresRepair & Rehabilitation of Structures
Repair & Rehabilitation of Structures
 
Structural audit
Structural auditStructural audit
Structural audit
 
Earthquake Resistant Building
Earthquake Resistant Building  Earthquake Resistant Building
Earthquake Resistant Building
 
Crack repair techniques
Crack repair techniquesCrack repair techniques
Crack repair techniques
 
distress of concrete
distress of concretedistress of concrete
distress of concrete
 
Jacketing
JacketingJacketing
Jacketing
 
demolition techniques
demolition techniquesdemolition techniques
demolition techniques
 
Coffer dam and its type
Coffer dam and its typeCoffer dam and its type
Coffer dam and its type
 
Construction of Special Structures.pptx
Construction of Special Structures.pptxConstruction of Special Structures.pptx
Construction of Special Structures.pptx
 
BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE BUILDING FAILURE- FOUNDATION FAILURE
BUILDING FAILURE- FOUNDATION FAILURE
 
Causes & Damage Detection
Causes & Damage DetectionCauses & Damage Detection
Causes & Damage Detection
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
 
Different types of damages that have been observed in masonry buildings durin...
Different types of damages that have been observed in masonry buildings durin...Different types of damages that have been observed in masonry buildings durin...
Different types of damages that have been observed in masonry buildings durin...
 
Cracks in Buildings
Cracks in BuildingsCracks in Buildings
Cracks in Buildings
 
Rebound Hammer Test-priciple,procedure,cons&pros.....
Rebound Hammer Test-priciple,procedure,cons&pros.....Rebound Hammer Test-priciple,procedure,cons&pros.....
Rebound Hammer Test-priciple,procedure,cons&pros.....
 
Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )Highway notes (planning, alignment, & geometric design )
Highway notes (planning, alignment, & geometric design )
 
Durability and Permeability of Concrete
Durability  and Permeability of ConcreteDurability  and Permeability of Concrete
Durability and Permeability of Concrete
 

Similar to CONDITION SURVEY AND NDE

Non Destructive Test
Non Destructive TestNon Destructive Test
Non Destructive TestParth Desani
 
NDT (NON DESTRUCTIVE TESTING) OF CONCRETE STRUCTURE ANSHUL
NDT (NON DESTRUCTIVE TESTING) OF CONCRETE STRUCTURE ANSHULNDT (NON DESTRUCTIVE TESTING) OF CONCRETE STRUCTURE ANSHUL
NDT (NON DESTRUCTIVE TESTING) OF CONCRETE STRUCTURE ANSHULAnshul Shakya
 
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEMROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEMVineeshkumar K V
 
Strength evaluation of existing structures
Strength evaluation of existing structuresStrength evaluation of existing structures
Strength evaluation of existing structuresShahrukh Niaz
 
repairandrehabilitation-150105022737-conversion-gate02.pdf
repairandrehabilitation-150105022737-conversion-gate02.pdfrepairandrehabilitation-150105022737-conversion-gate02.pdf
repairandrehabilitation-150105022737-conversion-gate02.pdf027NaveenKumarV
 
Non destructive test in CIVIL ENGINEERING Construction
Non destructive test in CIVIL ENGINEERING Construction Non destructive test in CIVIL ENGINEERING Construction
Non destructive test in CIVIL ENGINEERING Construction SAURABH GUPTA
 
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / RestorationNon-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restorationpandian18
 
Repairs and rehabilitation 2012
Repairs and rehabilitation 2012Repairs and rehabilitation 2012
Repairs and rehabilitation 2012Dhaval Jadhav
 
Non destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxNon destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxReigerRoyal
 
Non Destructive and Partially Destructive Testing Of Concrete Structures
Non Destructive and Partially Destructive Testing Of Concrete StructuresNon Destructive and Partially Destructive Testing Of Concrete Structures
Non Destructive and Partially Destructive Testing Of Concrete StructuresGautam Chaurasia
 
summer training report .... non destructive testing equipments for railway br...
summer training report .... non destructive testing equipments for railway br...summer training report .... non destructive testing equipments for railway br...
summer training report .... non destructive testing equipments for railway br...Neha Singh
 
Non destructive testing of structures
Non destructive testing of structuresNon destructive testing of structures
Non destructive testing of structuressanjanam9
 
Material Testing, Machines And Equipment Requirements
Material Testing, Machines And Equipment RequirementsMaterial Testing, Machines And Equipment Requirements
Material Testing, Machines And Equipment Requirementsamrutaware2
 
MATERIAL TESTING,EQUIPMENTS.pptx
MATERIAL TESTING,EQUIPMENTS.pptxMATERIAL TESTING,EQUIPMENTS.pptx
MATERIAL TESTING,EQUIPMENTS.pptxPranotiHunungare
 
Non destructive testing (Civil Engineering )
Non destructive testing (Civil Engineering )Non destructive testing (Civil Engineering )
Non destructive testing (Civil Engineering )AkashBhardwaj103
 
Condition survey and nde
Condition survey and ndeCondition survey and nde
Condition survey and ndeJay Bhavsar
 
Maintenance and repair strategies
Maintenance and repair strategiesMaintenance and repair strategies
Maintenance and repair strategiesManikandan
 

Similar to CONDITION SURVEY AND NDE (20)

Non Destructive test
Non Destructive testNon Destructive test
Non Destructive test
 
UNIT 4.ppt
UNIT 4.pptUNIT 4.ppt
UNIT 4.ppt
 
Non Destructive Test
Non Destructive TestNon Destructive Test
Non Destructive Test
 
NDT (NON DESTRUCTIVE TESTING) OF CONCRETE STRUCTURE ANSHUL
NDT (NON DESTRUCTIVE TESTING) OF CONCRETE STRUCTURE ANSHULNDT (NON DESTRUCTIVE TESTING) OF CONCRETE STRUCTURE ANSHUL
NDT (NON DESTRUCTIVE TESTING) OF CONCRETE STRUCTURE ANSHUL
 
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEMROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEM
 
Strength evaluation of existing structures
Strength evaluation of existing structuresStrength evaluation of existing structures
Strength evaluation of existing structures
 
repairandrehabilitation-150105022737-conversion-gate02.pdf
repairandrehabilitation-150105022737-conversion-gate02.pdfrepairandrehabilitation-150105022737-conversion-gate02.pdf
repairandrehabilitation-150105022737-conversion-gate02.pdf
 
Non destructive test in CIVIL ENGINEERING Construction
Non destructive test in CIVIL ENGINEERING Construction Non destructive test in CIVIL ENGINEERING Construction
Non destructive test in CIVIL ENGINEERING Construction
 
Deterioration of Concrete
Deterioration of ConcreteDeterioration of Concrete
Deterioration of Concrete
 
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / RestorationNon-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
Non-Destructive-Testing-of-Concrete • Repair / Rehabilitation / Restoration
 
Repairs and rehabilitation 2012
Repairs and rehabilitation 2012Repairs and rehabilitation 2012
Repairs and rehabilitation 2012
 
Non destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptxNon destructive tests on Concrete.pptx
Non destructive tests on Concrete.pptx
 
Non Destructive and Partially Destructive Testing Of Concrete Structures
Non Destructive and Partially Destructive Testing Of Concrete StructuresNon Destructive and Partially Destructive Testing Of Concrete Structures
Non Destructive and Partially Destructive Testing Of Concrete Structures
 
summer training report .... non destructive testing equipments for railway br...
summer training report .... non destructive testing equipments for railway br...summer training report .... non destructive testing equipments for railway br...
summer training report .... non destructive testing equipments for railway br...
 
Non destructive testing of structures
Non destructive testing of structuresNon destructive testing of structures
Non destructive testing of structures
 
Material Testing, Machines And Equipment Requirements
Material Testing, Machines And Equipment RequirementsMaterial Testing, Machines And Equipment Requirements
Material Testing, Machines And Equipment Requirements
 
MATERIAL TESTING,EQUIPMENTS.pptx
MATERIAL TESTING,EQUIPMENTS.pptxMATERIAL TESTING,EQUIPMENTS.pptx
MATERIAL TESTING,EQUIPMENTS.pptx
 
Non destructive testing (Civil Engineering )
Non destructive testing (Civil Engineering )Non destructive testing (Civil Engineering )
Non destructive testing (Civil Engineering )
 
Condition survey and nde
Condition survey and ndeCondition survey and nde
Condition survey and nde
 
Maintenance and repair strategies
Maintenance and repair strategiesMaintenance and repair strategies
Maintenance and repair strategies
 

More from Avinash Kumar Gupta

Time schedule for preparation &and completion of APAR
Time schedule for preparation &and completion of APARTime schedule for preparation &and completion of APAR
Time schedule for preparation &and completion of APARAvinash Kumar Gupta
 
Engaging consultants, service providers in govrnment part i
Engaging consultants, service providers in govrnment part iEngaging consultants, service providers in govrnment part i
Engaging consultants, service providers in govrnment part iAvinash Kumar Gupta
 
Procurement of goods , GFR provisions
Procurement of goods , GFR provisionsProcurement of goods , GFR provisions
Procurement of goods , GFR provisionsAvinash Kumar Gupta
 
Construction and repair chemicals
Construction and repair  chemicalsConstruction and repair  chemicals
Construction and repair chemicalsAvinash Kumar Gupta
 
Illustrations. repairing of structures
Illustrations. repairing of structuresIllustrations. repairing of structures
Illustrations. repairing of structuresAvinash Kumar Gupta
 
Materials for rcc repairs and rehabilitation
Materials for rcc repairs and rehabilitationMaterials for rcc repairs and rehabilitation
Materials for rcc repairs and rehabilitationAvinash Kumar Gupta
 
Payments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTPayments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTAvinash Kumar Gupta
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractAvinash Kumar Gupta
 
AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016Avinash Kumar Gupta
 

More from Avinash Kumar Gupta (20)

Principles of natural justice
Principles of natural justicePrinciples of natural justice
Principles of natural justice
 
Time schedule for preparation &and completion of APAR
Time schedule for preparation &and completion of APARTime schedule for preparation &and completion of APAR
Time schedule for preparation &and completion of APAR
 
Orders regarding apar
Orders regarding apar Orders regarding apar
Orders regarding apar
 
APAR guidelines
APAR  guidelinesAPAR  guidelines
APAR guidelines
 
Total station
Total stationTotal station
Total station
 
GPS surveying/DIGITAL SURVEYING
GPS  surveying/DIGITAL SURVEYINGGPS  surveying/DIGITAL SURVEYING
GPS surveying/DIGITAL SURVEYING
 
Service contracts ii
Service contracts iiService contracts ii
Service contracts ii
 
Engaging consultants, service providers in govrnment part i
Engaging consultants, service providers in govrnment part iEngaging consultants, service providers in govrnment part i
Engaging consultants, service providers in govrnment part i
 
Procurement of goods , GFR provisions
Procurement of goods , GFR provisionsProcurement of goods , GFR provisions
Procurement of goods , GFR provisions
 
Procurement of services
Procurement of  servicesProcurement of  services
Procurement of services
 
GST on works contract
GST on  works contractGST on  works contract
GST on works contract
 
Soil penetration tests
Soil penetration testsSoil penetration tests
Soil penetration tests
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Construction and repair chemicals
Construction and repair  chemicalsConstruction and repair  chemicals
Construction and repair chemicals
 
Illustrations. repairing of structures
Illustrations. repairing of structuresIllustrations. repairing of structures
Illustrations. repairing of structures
 
Materials for rcc repairs and rehabilitation
Materials for rcc repairs and rehabilitationMaterials for rcc repairs and rehabilitation
Materials for rcc repairs and rehabilitation
 
Rehabilitation methods
Rehabilitation methodsRehabilitation methods
Rehabilitation methods
 
Payments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTPayments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACT
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction Contract
 
AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016
 

Recently uploaded

Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 

Recently uploaded (20)

Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 

CONDITION SURVEY AND NDE

  • 1. CONDITION SURVEY AND NON DESTRUCTIVE EVALUTION AVINASH KUMAR GUPTA CCW TRAINING INSTITUTE NEW DELHI 07/04/2017
  • 2. CONDITION SURVEY • Examination of concrete • For identifying and defining areas of distress. • Recording history from inception to completion and subsequent life.
  • 3. Objective • Identify cause of distress and sources • Assess: extent of distress due to corrosion, fire, earthquake, any other reason • Asses residual strength of structure and its rehabilitability • Prioritize the distressed elements as per seriousness. • To select and plan the effective remedy.
  • 4. Stages of condition survey • Prioritize distressed elements according to seriousness for repairs. • a) Preliminary inspection • b) Planning • c)Visual Inspection • d) Field and laboratory testing.
  • 5. Preliminary inspection • History of structure from client, owner, occupants, General public in building, • Note records, previous repairs history and expenses done for the same. • All possible data and information. • Practical restriction in survey and safety requirements for survey team. • Extent and quantum of survey work • Time required ( survey and execution ) • Advise immediate safety measures
  • 6. Information gathering • . Period of construction • Construction details (drg,arch,structural ) • Exposure conditions • Designed and present use of structure. • Previous changes in use • Record of structural changes if done. • Record of 1st occurrence of defect. • Details of repairs carried out previously. • Previous reports etc. • Details from owner, photographs
  • 7. Planning survey • Field documents • Plans and actual observations each room- wise. • Previous report , advise if any and implementation done as per report, • Grouping of structural elements ( external, interior etc ) • Exposure conditions
  • 8. Classification of damage • Class O : No distress but cosmetic repairs • Class 1 : Minor repairs ( superficial repairs ) • Class 2 : Medium repairs ( patch repairs ) (minor structure cracks) • Class 3 : Principal repairs (spalling of cover concrete,structural cracks,cracks along bars) • Class O : Major repairs(replacement of structural Members)
  • 9. Grade for Assessment of the building • Based on the inspection and observation the distress level of the selected buildings may be categorizedas mentioned below: • G1 – No distress observed • G1 – Minor distress observed in few structural members, which can be repaired under the advice of a structural engineer. • G2 – Medium distress observed in few structural members, which can be repaired / rehabilitated including strengthening with the advice of a structural engineer • G3 – Severe distress observed in some of the structural members, which can be rehabilitated including strengthening with the advice of a structural engineer. • G4 – Severe distress is observed which could prove dangerous, hence evacuation at an early date is required.
  • 10. Visual Inspection • Workmanship, structural serviceability, material deterioration mechanism • General health( structural and non structural elements) • Preparation of estimate / bill of quantities. • Quantify extent of distress • Photographic record. • Obstructions for visual inspection to be noted. • Understanding structural system / deviations • Leakage , seepage due to inadequate drainage system • Types of cracks and its pattern • Color and texture of concrete surface (chemical attack or disintegration by way of leaching
  • 11. Record • Areas of high distress • Cracks and their locations • Excessive deflections • Exposure conditions of various distressed areas. • Moisture / seepage / leakages / dampness locations. • Abnormal vibrations in structure. • Algae, fungus growth, trees on structure. • Photographic record. • Areas of immediate concern
  • 12. Considerations for repairs strategy • Identification of cause of problem. • Assessment and extent of damage. • Availability space and accessibility w.r.t. ongoing activities in building. • propping structural members in case of major repairs , severely damaged elements (columns etc ). • Safety measures to avoid mishaps
  • 13. Non destructive Evaluation tests • These tests do not impair performance of the member, They are field or laboratory tests. • Put under five categories based on purpose, In-situ-Concrete strength Chemical attack Corrosion activity Fire damage Structural integrity and soundness
  • 14. Non Destructive Testing • Nondestructive testing in the broad sense refers to methods whereby internal characteristics of solid structures can be examined without permanently affecting the structure. Thus, parts that prove to be satisfactory under specified test conditions are not degraded by the test procedures
  • 15. NDT , Introduction • Nondestructive testing (NDT) is the process of inspecting, testing, or evaluating materials, components or assemblies for discontinuities, or differences in characteristics without destroying the serviceability of the part or system. In other words, when the inspection or test is completed the part can still be used
  • 16. NDT- Purpose •-Assessment of Existing Structures in the Absence of Drawings. •-Quick assessment of the structure
  • 17. NDT -Advantages • Access to hidden items – “see through walls” • Better investigations with NDT • Rapid accumulation of data • Generally less expensive than destructive testing.
  • 18. NDT - Disadvantages 1. More than one test method may be required 2. Environmental conditions may effect or distort results 3. Construction details & building components may effect results 4. Some conditions cannot be determined with a reasonable degree of accuracy without destructive testing
  • 19. Non destructive Testing • A : In- situ-concrete test • - rebound hammer • - Ultrasonic pulse velocity • - Windsor probe • - Pull out test : • Core cutting / sampling, lab testing of cores • - Load test
  • 20. Non destructive Testing • B : Chemical attack • Carbonation test • Chloride test • Sulphate test • C: Corrosion potential assessment • Cover meter ( checking cover) • Half cell potential • Resistivity meter • Permeability ( air and water )
  • 21. Non destructive Testing. • D: Fire damage assessment • Thermo gravimetric analysis (TGA) • Differential Thermal analysis (DTA) • X-ray diffraction (XRD) • E: Structural Integrity/ soundness • Ultrasonic pulse velocity ( discontinuities, cracks and depth of cracks) • Radiography • Impact echo test
  • 22. • The rebound hammer can provide a fairly accurate estimate of concrete compressive strength. • The concrete should be 14 to 56 days old. • Surface Condition: • The surface of the concrete at the point tested must be smooth, dry, and free of honeycombing. Otherwise, rebound readings will be low Indicating a weaker concrete than is actually the case. The rubbing stone provided can be used to grind the surface smooth, if necessary
  • 23. Location of Test PointsLocation of Test Points • The concrete to be tested must be at least four inches thick: It is also recommended that readings be taken only where the concrete has been in contact with the form. These conditions are most easily satisfied if the readings are taken along the edge of the tank on the sides and ends where the adjoining concrete face (i.e., wall, top, or bottom) can support the point of contact.
  • 24.
  • 25. PROCEDURE • Remove hammer from case and press the plunger end against a hard surface to release the plunger from the locked position. (Do not press lock button while doing this.) • Position hammer horizontally with plunger end against wall at a point. • Slowly apply pressure until hammer fires. This will occur when only approximately 1/2 inch of the plunger is still visible. Do not press the lock button during this step.
  • 26. • A). Remove hammer from case and press the plunger end against a hard surface to release the plunger from the locked position. (Do not press lock button while doing this.) • B). Position hammer horizontally with plunger end against wall at a point. • C). Slowly apply pressure until hammer fires. This will occur when only approximately 1/2 inch of the plunger is still visible. Do not press the lock button during this step
  • 27. Procedure Contd. • With the hammer still pressed against the wall, read the rebound number off the scale provided on the hammer. If it is necessary to move the hammer before reading, press the lock button. The rebound number should be read to two significant figures. • Repeat the above procedure at different points around the wall until a total of ten readings has been taken
  • 28.
  • 29. This is based on the principle that the velocity of an ultrasonic pulse through any material depends upon the density. Comparatively higher velocity is obtained when concrete quality is good in terms of density, uniformity etc. Pulse Velocity measurements can be used to assess the presence of cracks, voids etc., quality of concrete relative to standards requirements.
  • 30. UPV Test contd. There are three possible ways of measuring pulse velocity.  i) Direct transmission ii) Semi direct transmission iii) Indirect transmission (surface probing) Out of the three methods, the direct transmission method is considered to be the best
  • 31.
  • 32.
  • 33.
  • 34. condition of concrete based on pulse velocity are given below S.No. Pulse Velocity Condition of concrete I in(Km/Sec.) •1. Above 4.5 Excellent •2. 3.5 to 4.5 Good •3. 3.0 to 3.5 Medium •4. Below 3.0 Poor
  • 35. PULLOUT TESTPULLOUT TEST • The fundamental principle behind pull out testing with LOK-test and CAPO test is that the test equipment designed to a specific geometry will produce results (pull-out forces) that closely correlate to the compressive strength of concrete. The first method ,using the cast steel disc is called LOK test. The second method shown in fig.2 using expandable ring is called CAPO test (i.e. Cut and Pull out Test). The diameter of both the disc and ring is 25mm. the distance to the concrete surface is also 25mm. the inner diameter of the counter-pressure is 55mm.
  • 36.
  • 37.
  • 38. The relationship between the pullout force Fu in kN and compressive strength Fc in MPa The relationship between the pullout force Fu in kN and compressive strength Fc in MPa is given in fig 04/14/17 38
  • 39. Pull out tests are used toPull out tests are used to  Determine in-situ compressive strength of the concrete  Ascertain the strength of concrete for carrying out post tensioning operations.  Determine the time of removal of forms and shores based on actual in-situ strength of the structure.  Terminate curing based on in-situ strength of the structure
  • 40. 4.Core cutter4.Core cutter The test should be taken at points where minimum strength and maximum stress are likely to coincide. But, at the same time, the core cutting causes some damage to the member and may impair the future performance of the member. Therefore, in slender members, the core should be taken away from the critical section. For compression testing, the diameter of the core should be at least three times the nominal maximum aggregate size
  • 41. Core Cutter is used to cut the core from the existing concrete structure for testing the physical properties of the concrete like compressive strength, density, water absorption, crack depth and chemical test like depth of carbonation and chloride content etc. It can also be used to inspect the interior region of the structural members.
  • 43.
  • 44.
  • 45. • Cover meters are electromagnetic in operation. Electric currents in a coil winding in the search head generate a magnetic field which propagates through the concrete and will interact with any buried metal present, such as reinforcing steel.It is the generic term for equipment used to locate steel reinforcing bar in concrete and to estimate the thickness of the concrete cover over the reinforcement
  • 47. Tomography means imaging an object by taking measurements from “slices” of its cross- section. Tomography means imaging an object by taking measurements from “slices” of its cross-section. 04/14/17 47
  • 50. This test is carried out to assess the quality / uniformity of concrete at various depths. The instrument consists of a four probe device. Electrical current is passed through the outer probes & the potential drop is measured by the inner probes. From the current & voltage drop measurements, the resistivity of concrete can be measured. Electrical resistivity = 2(pi)aE/i (in kilo-ohm cm) where a = distance between probes = 5 cm in the 1st set of readings = 10 cm in the 2nd set of readings E = potential difference between inner two probes in mV Most useful test in tunnel structure