SlideShare a Scribd company logo
1 of 26
1
Early Warning of NEC3 ECC, A Solution for Dutch Design&
Build Construction Problem Solving?
Graduation committee:
Prof. mr. dr. M.A.B. (Monika) Chao-Duivis (TU Delft)
Dr. Ir. L.H.M.J. (Louis) Lousberg (TU Delft)
Ir. L.P.I.M. (Leon) Hombergen (TU Delft)
Ir. R.A.J. (Rob) Rijnen (Witteveen+Bos)
Ir. J. (Jelmer) Kooij (Witteveen+Bos)
Yu Gao
Construction Management and Engineering
Faculty of Civil Engineering and Geosciences
Delft University of Technology
2
Construction fraud (2002) in the Netherlands
3
Driven by ‘Value for Money’
4
‘Old ways of problem solving’
• There is in general a lack of interaction and
communication between parties;
• Warning is often too late;
• Consequences of problem are large;
• People begin to blame each other;
• “Ball in the court”
• Duty to warn obligation of UAV-GC 2005 is
insufficient in facilitating problem solving
5
‘Early warning as a foreign way of problem solving’
• Early warning obligation of NEC3 ECC for
reducing unnecessary costs;
• Parties working together based on the ‘spirit of
mutual trust and cooperation’;
• It is used for “Best for projects”
• “Jewel in the crown”.
• Nevertheless, only one project in the
Netherlands was executed under NEC3 ECC
6
International Criminal Court in The Hague (NEC3 ECC)
7
Problem is ‘twofold’
Duty to warn
of UAV-GC
2005 is
insufficient in
facilitating
problem
solving
between
parties.
Early warning
of NEC3 ECC
is alien to
Dutch
construction
industry.
8
“Can Early warning of NEC3 ECC be expected to function properly
under UAV-GC 2005, with the aim of improving Dutch Design and
Build construction problem solving?
Literature
Review
• Early warning in Project Management (Q1)
• Construction Problem Solving (Q2)
• Comparative Analysis (Q3)
Expert
Interview
• Experts’ opinion concerning duty to warn and early warning in
practice (Q4)
• Conditions for proper functioning of Early warning (Q5)
9
Early warning in project management
“Early warning is an observation, a signal, a message or some other
item that is or can be seen as an expression, an indication, a proof,
or a sign of the existence of some future or incipient positive or
negative issue. It is a signal, omen, or indication of future
developments.” (Nikander, 2002, p. 48)
10
The concept of ‘time available’ (Nikander, 2002,
p. 86)
The earlier you pick up the problem, the more ‘time available’ you
have so as to reduce the potential impact of problem.
11
Construction Problem Solving
Culture
Transition
Working
Together
Win-win
situation
Climate
of
Mutual
Trust
Early
Problem
Intervention
Problem
Solving at
the
lowest
level
Problem
Solving as
soon as
possible
Avoidance of
Problem
Recurrence
Learning
from
Problem
Solving
3. Joint problem
solving process
1. Reasonable behavior
2. Equal and balanced
warning responsibility
4. Win-win
attitude
5. The presence
of early warning
6. Learning from
problem solving
12
A comparison of UAV-GC 2005, NEC3 ECC, and
FIDIC yellow book
13
Result of the comparative analysis
Dimensions of
Problem solving
Aspects
(requirements)
Criteria UAV-GC
2005
NEC3 ECC FIDIC YB
Culture
Transition
Climate of mutual
trust
Reasonable
behavior
+/- √ ꓫ
Equal and
balanced warning
responsibility
ꓫ √
(EW)
ꓫ
Working together
(Integration)
Joint problem
solving process
ꓫ √
(EW)
ꓫ
Win-win attitude Win-win attitude +/- √
(EW)
ꓫ
Early Problem
Intervention
Problem solving at
the lowest possible
authority level
The presence of
early warning
+/-
(DTW)
√
(EW)
+/-
(EWP)
Problem solving as
quickly as possible
Avoidance of
Problem
Recurrence
Learning from
problem solving
Learning from
problem solving
ꓫ ꓫ ꓫ
14
Expert interview
Operation side Abbreviation Contract mgt.
experience
Other relevant
experience
2 Employer (E) JD UAV-GC 2005 -
RM UAV-GC 2005 -
6 Employer’s Agent (E)
PS UAV-GC 2005 -
MM2 UAV-GC 2005
-
MKB UAV-GC 2005
-
AV UAV-GC 2005 UAV-GC trainer
JTB UAV-GC 2005 Dutch arbitration
MM1 NEC3 ECC& UAV-
GC 2005 -
4 Contractor (C)
CK UAV-GC 2005
-
JU UAV-GC 2005 -
RS UAV-GC 2005 -
JVR NEC3 ECC& UAV-
GC 2005
-
15
Dutch construction culture
Traditional blame
culture
Dutch construction
culture
No blame
culture
Determining
features
Suspicion of each other Suspicion of each other Climate of mutual
trust
‘Working alone’
(fragmentation)
‘Working Alone’
(Fragmentation)
‘Working together’
(Integration)
‘Win-lose’ (dispute
often end up in court)
‘Give and take’
(dispute resolved
through negotiation)
‘Win-win’ (effective
problem solving)
16
Redelijkheid en Billijkheid (the principle of good
faith)
Article 3:12 The principle of ‘reasonableness and fairness’ (Dutch
Civil Code 3:12, 1992)
At determining what the principle of ‘reasonableness and fairness’
demands in a specific situation, one has to take into account the
general accepted legal principles, the fundamental conceptions of law
in the Netherlands and the relevant social and personal interests
which are involved in the given situation.
17
Influence on people’s attitude and behavior
• It is inferred that the principle is exploited by the contractor
as a bargaining chip for the negotiation about
compensation with the employer
• UNFORTUNATELY, it does not promote trust.
“What can you
expect from the
other
party”(interview)
Take each other’s
reasonable
interests into
account (DCC)
18
Deficiencies of Duty to warn of UAV-GC 2005
Clause 4-7 The Contractor shall warn the Employer in writing
without delay if:
(a)the Employer’s Requirements; or (b)information; or (c)the land
and/or the water; or (d)goods; or (e)any measure; or (f)any
Variation
ordered, provided, or taken by the Employer, evidently contain or
show such faults or defects that the Contractor would be in
breach of the requirements of good faith if he were to continue
work without issuing any warning about such faults or defects.
Clause 4-8 If the Contractor fails to perform his obligation
referred to in section 7, he shall be liable for any damaging
consequences caused by his failure.
Clause 20-4 The Employer shall be under no obligation
whatsoever to use his authority to test pursuant to this clause. It
shall be at the Employer’s discretion to decide whether and how
he uses such authority in the course of Design Work.
Nevertheless, the Employer shall inform the Contractor in writing
in due time if he actually discovers a failure by the Contractor or if
he must have been aware of such a failure.
Duty to warn is not highlighted
Warning is not incentivized
Collaboration is not described
(no ‘follow ups’)
Less equal and balanced
warning responsibility
‘Obvious error’
19
Added Value of Early warning of NEC3 ECC
Clause 16.1 The Contractor and the Project
Manager give an early warning by
notifying the other as soon as either
becomes aware of any matter which could
• Increase the total of the Prices.
• Delay Completion,
• Delay meeting a Key Date or
• Impair the Performance of the works in
use.
The Contractor may give an early warning
by notifying the Project Manager of any
other matter which could increase his total
cost. The Project Manager enters early
warning matters in the Risk Register. Early
warning of a matter for which a
compensation event has previously been
notified is not required.
Early warning as an independent and essential
article
‘Any matter’
More equal and balanced responsibility
Project management instrument (clause 16.2-
16.4)
Early warning is incentivized through ‘Early warning
mechanism’ (trust and compensation event)
20
Project management instrument (clause 16.2- 16.4)
Clause 16.2 Either the Project Manager or the Contractor may
instruct the other to attend the risk reduction meeting. Each
may instruct other people to attend if the other agrees.
Clause 16.3 At a risk reduction meeting, those who attend co-
operate in 1)making and considering proposals for how the
effect of the registered risks can be avoided or reduced,2)
seeking solutions that will bring advantage to all those who will
be affected, 3) deciding on the actions which will be taken and
who, in accordance with this contract, will take them and 4)
deciding which risks have now been avoided or have passed
and can be removed from the risk register. (Meeting agenda)
Clause 16.4 The Project Manager revises the risk register to
record the decisions made at each risk reduction meeting and
issues the revised risk register to the Contractor. If a decision
needs a change to the works information, the Project Manager
instructs the change at the same time as he issues the revised
risk register.
21
Early warning mechanisms (two conditions)
1. Condition 1 Trust as Passive control over opportunistic behavior
- Clause 10.1 The Employer, the Contractor, the Project Manager and the Supervisor
shall act as stated in this contract and in a spirit of mutual trust and co-operation.
- Option C Target contract with activity schedule (sharing ‘pain/gain’)
2. Condition 2 Compensation event as Active control over opportunistic behavior
Clause 63.5 If the Project Manager has notified the Contractor of his decision that
the Contractor did not give an early warning of a compensation event which an
experienced contractor could have given, the event is assessed as if the Contractor
had given early warning.
Compensation
event
22
Is Early warning of NEC3 ECC a solution to Dutch
Design and Build Construction Problem Solving?
No, but Yes!!
23
Why not?
• Lack of ‘active control’
• Lack of ‘support’ for trust
Contract
mechanisms
(UAV-GC
2005)
• A lack of trust between parties is a major
challenge
• Warning often too late
• The contractor is more focusing on being
compensated than warning earlier
• Technicians are strict and bad at communication
Dutch
construction
culture
24
But, ‘every coin has two sides’
The
Spirit of
mutual
trust
Early
Warning
• A lack of trust is not only a threat
but also an opportunity to early
warning;
• Early warning can promote mutual
trust, which in turn encouraging
early warning.
• The more information they share at
an early stage, the better they know
each other
• If people are willing to build trust
and work ‘best for projects’, it can
start with the Early warning.
25
Limitation of the research
• This research has made a start with researching early
warning of NEC3 ECC within the context of Dutch
design and build construction projects.
• Due to scarcity of case projects (NEC3 ECC), project
specific characteristics are not taken into account;
• The result of this research is not typical to one specific
scenario project (e.g. large infra design and build project).
26
Thanks for your attention!
Any questions?

More Related Content

What's hot

Construction Contract Dispute Resolution
Construction Contract Dispute ResolutionConstruction Contract Dispute Resolution
Construction Contract Dispute Resolutionrcnewcomer
 
Measures to Reduce Dispute in Projects
Measures to Reduce Dispute in Projects   Measures to Reduce Dispute in Projects
Measures to Reduce Dispute in Projects Nilendra Kumar
 
Risk Management of PPP
Risk Management of PPPRisk Management of PPP
Risk Management of PPPRupertBooth
 
Terms and Conditions NACM Northwest March 2017
Terms and Conditions NACM Northwest March 2017Terms and Conditions NACM Northwest March 2017
Terms and Conditions NACM Northwest March 2017Sam Smith
 
Civil engineering practice (lec 5)
Civil engineering practice (lec 5)Civil engineering practice (lec 5)
Civil engineering practice (lec 5)Muhammad Khan
 
Crisis Management and Protecting Your Reputation
Crisis Management and Protecting Your ReputationCrisis Management and Protecting Your Reputation
Crisis Management and Protecting Your ReputationTiffanyMiller57
 
Probability Assessment:
 How Do We Get "Good" Numbers For Litigation Decision...
Probability Assessment:
 How Do We Get "Good" Numbers For Litigation Decision...Probability Assessment:
 How Do We Get "Good" Numbers For Litigation Decision...
Probability Assessment:
 How Do We Get "Good" Numbers For Litigation Decision...brucelb
 
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITYHOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITYBurns White LLC
 

What's hot (10)

Construction Contract Dispute Resolution
Construction Contract Dispute ResolutionConstruction Contract Dispute Resolution
Construction Contract Dispute Resolution
 
Measures to Reduce Dispute in Projects
Measures to Reduce Dispute in Projects   Measures to Reduce Dispute in Projects
Measures to Reduce Dispute in Projects
 
Risk Management of PPP
Risk Management of PPPRisk Management of PPP
Risk Management of PPP
 
Terms and Conditions NACM Northwest March 2017
Terms and Conditions NACM Northwest March 2017Terms and Conditions NACM Northwest March 2017
Terms and Conditions NACM Northwest March 2017
 
Civil engineering practice (lec 5)
Civil engineering practice (lec 5)Civil engineering practice (lec 5)
Civil engineering practice (lec 5)
 
Crisis Management and Protecting Your Reputation
Crisis Management and Protecting Your ReputationCrisis Management and Protecting Your Reputation
Crisis Management and Protecting Your Reputation
 
Probability Assessment:
 How Do We Get "Good" Numbers For Litigation Decision...
Probability Assessment:
 How Do We Get "Good" Numbers For Litigation Decision...Probability Assessment:
 How Do We Get "Good" Numbers For Litigation Decision...
Probability Assessment:
 How Do We Get "Good" Numbers For Litigation Decision...
 
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITYHOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
 
Construction disputes
Construction disputesConstruction disputes
Construction disputes
 
Slide 2_Arpita
Slide 2_ArpitaSlide 2_Arpita
Slide 2_Arpita
 

Similar to Master thesis defence presentation

20090714 Contracts Workshop
20090714 Contracts Workshop20090714 Contracts Workshop
20090714 Contracts WorkshopSteven Jackson
 
Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith mark woodward-smith
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Roland_Nikles
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidicAhmetArslan47
 
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...Association for Project Management
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation Lin Hui
 
Lecture4construction contract.ppt
Lecture4construction contract.pptLecture4construction contract.ppt
Lecture4construction contract.pptIrynaRudnieva
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsFrancis Ho
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m magedM Maged Hegazy, LLM, MBA, CCP, P3O
 
Rework: Anticipating What May Go Wrong
Rework: Anticipating What May Go WrongRework: Anticipating What May Go Wrong
Rework: Anticipating What May Go Wrongpedlove
 
7.ias 37 provision
7.ias 37 provision7.ias 37 provision
7.ias 37 provisionTenkir Seifu
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3 Rae Davies
 
Are We There Yet - Substantial-Completion
Are We There Yet - Substantial-CompletionAre We There Yet - Substantial-Completion
Are We There Yet - Substantial-CompletionMDCSystems
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...Rae Davies
 
M32089 Construction Contracts And Dispute Resolution.docx
M32089 Construction Contracts And Dispute Resolution.docxM32089 Construction Contracts And Dispute Resolution.docx
M32089 Construction Contracts And Dispute Resolution.docxstirlingvwriters
 
Dispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxDispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxPujanNeupane6
 

Similar to Master thesis defence presentation (20)

20090714 Contracts Workshop
20090714 Contracts Workshop20090714 Contracts Workshop
20090714 Contracts Workshop
 
Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith Systech insights edition-Mark Woodward Smith
Systech insights edition-Mark Woodward Smith
 
Concurrent Delay in Construction
Concurrent Delay in ConstructionConcurrent Delay in Construction
Concurrent Delay in Construction
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)
 
2 claims under new fidic
2 claims under new fidic2 claims under new fidic
2 claims under new fidic
 
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
NEC Contracts - The Risk Register/Early Warning Register and risk allocation ...
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
Lecture4construction contract.ppt
Lecture4construction contract.pptLecture4construction contract.ppt
Lecture4construction contract.ppt
 
Managing the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction ProjectsManaging the Risks of Delay in Construction Projects
Managing the Risks of Delay in Construction Projects
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m magedDelay, dispute  (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
Delay, dispute (1st annual conf. of planning in cairo 23-8-2014) engr. m maged
 
Rework: Anticipating What May Go Wrong
Rework: Anticipating What May Go WrongRework: Anticipating What May Go Wrong
Rework: Anticipating What May Go Wrong
 
7.ias 37 provision
7.ias 37 provision7.ias 37 provision
7.ias 37 provision
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
Are We There Yet - Substantial-Completion
Are We There Yet - Substantial-CompletionAre We There Yet - Substantial-Completion
Are We There Yet - Substantial-Completion
 
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...Construction Futures Wales  - NEC3 Workshop - Understanding Works Information...
Construction Futures Wales - NEC3 Workshop - Understanding Works Information...
 
M32089 Construction Contracts And Dispute Resolution.docx
M32089 Construction Contracts And Dispute Resolution.docxM32089 Construction Contracts And Dispute Resolution.docx
M32089 Construction Contracts And Dispute Resolution.docx
 
Chapter 3- Construction Law
Chapter 3- Construction Law Chapter 3- Construction Law
Chapter 3- Construction Law
 
Dispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxDispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptx
 

Recently uploaded

Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 

Recently uploaded (20)

Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 

Master thesis defence presentation

  • 1. 1 Early Warning of NEC3 ECC, A Solution for Dutch Design& Build Construction Problem Solving? Graduation committee: Prof. mr. dr. M.A.B. (Monika) Chao-Duivis (TU Delft) Dr. Ir. L.H.M.J. (Louis) Lousberg (TU Delft) Ir. L.P.I.M. (Leon) Hombergen (TU Delft) Ir. R.A.J. (Rob) Rijnen (Witteveen+Bos) Ir. J. (Jelmer) Kooij (Witteveen+Bos) Yu Gao Construction Management and Engineering Faculty of Civil Engineering and Geosciences Delft University of Technology
  • 2. 2 Construction fraud (2002) in the Netherlands
  • 3. 3 Driven by ‘Value for Money’
  • 4. 4 ‘Old ways of problem solving’ • There is in general a lack of interaction and communication between parties; • Warning is often too late; • Consequences of problem are large; • People begin to blame each other; • “Ball in the court” • Duty to warn obligation of UAV-GC 2005 is insufficient in facilitating problem solving
  • 5. 5 ‘Early warning as a foreign way of problem solving’ • Early warning obligation of NEC3 ECC for reducing unnecessary costs; • Parties working together based on the ‘spirit of mutual trust and cooperation’; • It is used for “Best for projects” • “Jewel in the crown”. • Nevertheless, only one project in the Netherlands was executed under NEC3 ECC
  • 6. 6 International Criminal Court in The Hague (NEC3 ECC)
  • 7. 7 Problem is ‘twofold’ Duty to warn of UAV-GC 2005 is insufficient in facilitating problem solving between parties. Early warning of NEC3 ECC is alien to Dutch construction industry.
  • 8. 8 “Can Early warning of NEC3 ECC be expected to function properly under UAV-GC 2005, with the aim of improving Dutch Design and Build construction problem solving? Literature Review • Early warning in Project Management (Q1) • Construction Problem Solving (Q2) • Comparative Analysis (Q3) Expert Interview • Experts’ opinion concerning duty to warn and early warning in practice (Q4) • Conditions for proper functioning of Early warning (Q5)
  • 9. 9 Early warning in project management “Early warning is an observation, a signal, a message or some other item that is or can be seen as an expression, an indication, a proof, or a sign of the existence of some future or incipient positive or negative issue. It is a signal, omen, or indication of future developments.” (Nikander, 2002, p. 48)
  • 10. 10 The concept of ‘time available’ (Nikander, 2002, p. 86) The earlier you pick up the problem, the more ‘time available’ you have so as to reduce the potential impact of problem.
  • 11. 11 Construction Problem Solving Culture Transition Working Together Win-win situation Climate of Mutual Trust Early Problem Intervention Problem Solving at the lowest level Problem Solving as soon as possible Avoidance of Problem Recurrence Learning from Problem Solving 3. Joint problem solving process 1. Reasonable behavior 2. Equal and balanced warning responsibility 4. Win-win attitude 5. The presence of early warning 6. Learning from problem solving
  • 12. 12 A comparison of UAV-GC 2005, NEC3 ECC, and FIDIC yellow book
  • 13. 13 Result of the comparative analysis Dimensions of Problem solving Aspects (requirements) Criteria UAV-GC 2005 NEC3 ECC FIDIC YB Culture Transition Climate of mutual trust Reasonable behavior +/- √ ꓫ Equal and balanced warning responsibility ꓫ √ (EW) ꓫ Working together (Integration) Joint problem solving process ꓫ √ (EW) ꓫ Win-win attitude Win-win attitude +/- √ (EW) ꓫ Early Problem Intervention Problem solving at the lowest possible authority level The presence of early warning +/- (DTW) √ (EW) +/- (EWP) Problem solving as quickly as possible Avoidance of Problem Recurrence Learning from problem solving Learning from problem solving ꓫ ꓫ ꓫ
  • 14. 14 Expert interview Operation side Abbreviation Contract mgt. experience Other relevant experience 2 Employer (E) JD UAV-GC 2005 - RM UAV-GC 2005 - 6 Employer’s Agent (E) PS UAV-GC 2005 - MM2 UAV-GC 2005 - MKB UAV-GC 2005 - AV UAV-GC 2005 UAV-GC trainer JTB UAV-GC 2005 Dutch arbitration MM1 NEC3 ECC& UAV- GC 2005 - 4 Contractor (C) CK UAV-GC 2005 - JU UAV-GC 2005 - RS UAV-GC 2005 - JVR NEC3 ECC& UAV- GC 2005 -
  • 15. 15 Dutch construction culture Traditional blame culture Dutch construction culture No blame culture Determining features Suspicion of each other Suspicion of each other Climate of mutual trust ‘Working alone’ (fragmentation) ‘Working Alone’ (Fragmentation) ‘Working together’ (Integration) ‘Win-lose’ (dispute often end up in court) ‘Give and take’ (dispute resolved through negotiation) ‘Win-win’ (effective problem solving)
  • 16. 16 Redelijkheid en Billijkheid (the principle of good faith) Article 3:12 The principle of ‘reasonableness and fairness’ (Dutch Civil Code 3:12, 1992) At determining what the principle of ‘reasonableness and fairness’ demands in a specific situation, one has to take into account the general accepted legal principles, the fundamental conceptions of law in the Netherlands and the relevant social and personal interests which are involved in the given situation.
  • 17. 17 Influence on people’s attitude and behavior • It is inferred that the principle is exploited by the contractor as a bargaining chip for the negotiation about compensation with the employer • UNFORTUNATELY, it does not promote trust. “What can you expect from the other party”(interview) Take each other’s reasonable interests into account (DCC)
  • 18. 18 Deficiencies of Duty to warn of UAV-GC 2005 Clause 4-7 The Contractor shall warn the Employer in writing without delay if: (a)the Employer’s Requirements; or (b)information; or (c)the land and/or the water; or (d)goods; or (e)any measure; or (f)any Variation ordered, provided, or taken by the Employer, evidently contain or show such faults or defects that the Contractor would be in breach of the requirements of good faith if he were to continue work without issuing any warning about such faults or defects. Clause 4-8 If the Contractor fails to perform his obligation referred to in section 7, he shall be liable for any damaging consequences caused by his failure. Clause 20-4 The Employer shall be under no obligation whatsoever to use his authority to test pursuant to this clause. It shall be at the Employer’s discretion to decide whether and how he uses such authority in the course of Design Work. Nevertheless, the Employer shall inform the Contractor in writing in due time if he actually discovers a failure by the Contractor or if he must have been aware of such a failure. Duty to warn is not highlighted Warning is not incentivized Collaboration is not described (no ‘follow ups’) Less equal and balanced warning responsibility ‘Obvious error’
  • 19. 19 Added Value of Early warning of NEC3 ECC Clause 16.1 The Contractor and the Project Manager give an early warning by notifying the other as soon as either becomes aware of any matter which could • Increase the total of the Prices. • Delay Completion, • Delay meeting a Key Date or • Impair the Performance of the works in use. The Contractor may give an early warning by notifying the Project Manager of any other matter which could increase his total cost. The Project Manager enters early warning matters in the Risk Register. Early warning of a matter for which a compensation event has previously been notified is not required. Early warning as an independent and essential article ‘Any matter’ More equal and balanced responsibility Project management instrument (clause 16.2- 16.4) Early warning is incentivized through ‘Early warning mechanism’ (trust and compensation event)
  • 20. 20 Project management instrument (clause 16.2- 16.4) Clause 16.2 Either the Project Manager or the Contractor may instruct the other to attend the risk reduction meeting. Each may instruct other people to attend if the other agrees. Clause 16.3 At a risk reduction meeting, those who attend co- operate in 1)making and considering proposals for how the effect of the registered risks can be avoided or reduced,2) seeking solutions that will bring advantage to all those who will be affected, 3) deciding on the actions which will be taken and who, in accordance with this contract, will take them and 4) deciding which risks have now been avoided or have passed and can be removed from the risk register. (Meeting agenda) Clause 16.4 The Project Manager revises the risk register to record the decisions made at each risk reduction meeting and issues the revised risk register to the Contractor. If a decision needs a change to the works information, the Project Manager instructs the change at the same time as he issues the revised risk register.
  • 21. 21 Early warning mechanisms (two conditions) 1. Condition 1 Trust as Passive control over opportunistic behavior - Clause 10.1 The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of mutual trust and co-operation. - Option C Target contract with activity schedule (sharing ‘pain/gain’) 2. Condition 2 Compensation event as Active control over opportunistic behavior Clause 63.5 If the Project Manager has notified the Contractor of his decision that the Contractor did not give an early warning of a compensation event which an experienced contractor could have given, the event is assessed as if the Contractor had given early warning. Compensation event
  • 22. 22 Is Early warning of NEC3 ECC a solution to Dutch Design and Build Construction Problem Solving? No, but Yes!!
  • 23. 23 Why not? • Lack of ‘active control’ • Lack of ‘support’ for trust Contract mechanisms (UAV-GC 2005) • A lack of trust between parties is a major challenge • Warning often too late • The contractor is more focusing on being compensated than warning earlier • Technicians are strict and bad at communication Dutch construction culture
  • 24. 24 But, ‘every coin has two sides’ The Spirit of mutual trust Early Warning • A lack of trust is not only a threat but also an opportunity to early warning; • Early warning can promote mutual trust, which in turn encouraging early warning. • The more information they share at an early stage, the better they know each other • If people are willing to build trust and work ‘best for projects’, it can start with the Early warning.
  • 25. 25 Limitation of the research • This research has made a start with researching early warning of NEC3 ECC within the context of Dutch design and build construction projects. • Due to scarcity of case projects (NEC3 ECC), project specific characteristics are not taken into account; • The result of this research is not typical to one specific scenario project (e.g. large infra design and build project).
  • 26. 26 Thanks for your attention! Any questions?