SlideShare a Scribd company logo
1 of 36
ASHRAE Pittsburgh Chapter March 6, 2014
Are We There Yet?
What is "Substantial Completion" ?
(…and how do we know when we get there?)
E. Mitchell Swann P.E., LEED AP
F. CIBSE, C.Eng
Principal
MDCSystems®
www.MDCSystems.com
Copyright E. Mitchell Swann & MDC Systems
2
Program Overview
What is “Substantial Completion”
Implication of the selected definition on
actual project completion
New considerations in the industry
Example circumstances
Summary
Questions & Answers
3
Program Overview
Are We There Yet? What is "Substantial Completion"
and how do we know when we get there?
"Substantial completion": These two words can change
the course of history. Well, the course of your payment
history, anyway. Many contracts contain that phrase as
a key indicator of major project milestones for the
release of retainage, the start of warranty periods and
more frequently everyday, the start up of energy
measurement and verification programs. But the
definition of "substantial" and "complete" are wide and
varied. This program will explore the permutations and
implications of the various interpretations of "substantial
completion" and how it can affect the happy family that is
your project team.
4
So…
what
is
Substantial Completion?
5
Some synonyms….(?)
Mechanical Completion
Unit is essentially complete for
start-up operation and test run.
All major work is completed.
Minor work not interfering with
operation may not be completed,
such as punch list and minor
touch-up work.
(from dictionaryofconstruction.com)
6
U
Mechanical other stuff to do…
Completion
7
Beneficial Occupancy
When an owner of a property
can use it before all the
construction is completed.
(from Black’s Law Dictionary)
Use of a building, structure,
or facility by the owner for its
intended purpose (functionally
complete), although other
contract work, nonessential to the
function of the occupied section,
remains to be completed.
(emphasis added)
(from theconstructiondictionary.com)
Certificate of
Occupancy
A document issued by a local
government agency or building
department certifying a building's
compliance with applicable building
codes and other laws, and
indicating it to be in a condition
suitable for occupancy.
The purpose is to prove
that,
according to the law, the building is
in livable condition.A certificate of occupancy is evidence that the
building complies substantially with the plans
and specifications that have been submitted to,
and approved by, the local authority.
(emphasis added)
So what is substantial completion?
The answer varies,
but…
I know it when I see it!
- Judge Potter Stuart
10
So how about this?
Section A.9.8.1 (from the AIA 201 - General Conditions of the Contract for Construction) :
“the stage in the progress of the Work when the Work
or designated portion thereof is sufficiently complete in
accordance with the Contract Documents so that the
Owner can occupy or utilize the Work for its intended
use.”
Sounds like….
Is “mechanical completion” required?
Is a C of O required?
11
Why does this matter?
The date of substantial completion can establish…
…the date that the owner becomes responsible
for the property, (the “clock” starts - builders’ warranty);
…the date that a contractor is no longer fully
liable for delayed completion;
…the date the “Statute of Limitations” clock starts
(what’s this?) ;
…the date the “Statute of Repose” clock starts
(what’s that?);
12
The
date of substantial
completion
(…could become a day that might live in infamy.)
Builders Warranty:
…the hands of time….
Written statement by a builder
assuring that a project was
completed according to a stipulated
set of standards. It protects the buyer
from latent defects.
Patent Defects
Latent Defects
13
The date of substantial completion
(…could become a day that might live in infamy.)
…a contractor is no longer fully liable for delayed completion
Liquidated Damages:
Monetary compensation for a loss, detriment, or
injury to a person or a person's rights or
property, awarded by a court judgment or by a
contract stipulation regarding breach of
contract. (Legal Law Dictionary)
(Think of it as "contract performance
insurance.”)
LIMITATIONS!Allowed when exact quantification of damages is difficult (but ARE “real”!)
MUST be “reasonable” with respect to the “value” of the damages that
could be incurred.
NOT to be considered/”constructed as a “penalty”.
14
The date of substantial completion
(…could become a day that might live in infamy.)
Statute of Limitations:
A law that restricts the time within which legal
proceedings may be brought.
…a fundamental part of European and U.S. law.
…apply to both civil and criminal actions,
…designed to prevent fraudulent and stale claims
…after all evidence has been lost…
…after the facts have become obscured over time…
…defective memory, death, or disappearance of witnesses.
…a defense that is ordinarily asserted by the defendant
…the parties may either shorten or extend the prescribed time
period by agreement, such as a provision in a contract.
15
The date of substantial completion
(…could become a day that might live in infamy.)
Statute of Repose:
Provides a date upon which the action no longer can be
taken - it entirely cuts off an injured person's right of
action even before it accrues.
…stricter deadline than statute of limitations
…it may not be tolled by fraud, discovery of injury, etc.
…neither an avoidance nor a defense
…because the cause of action does not exist after “repose”
…bars an action after a specified period of time has run
from the occurrence of some event.
…but NOT injury or “discovery”
16
New considerations…
Commissioning
between “complete enough” and “acceptable”
Energy (& resource) Performance M&V
“Green Certification”
Outside the project “bubble”
Validation
Regulatory Hurdles
Accreditation
Specialty Operations
17
New considerations…
Commissioning
integrated application of a set of engineering techniques
and procedures to check, inspect and test every operational
component of the project, from individual functions, such
as instruments and equipment, up to complex
amalgamations such as modules, subsystems and systems.
18
New
considerations
Energy
(& resource)
Performance M&V
19
New considerations…
“Green Certification”
A third party vetting of the
completed project?
20
New considerations…
Validation
Pharmaceuticals
biotechnology
medical devices
21
New considerations…
Accreditation
Hospitals
Animal Facilities
Data Centers
22
So the on-going question is….
ARE
WE
THERE
YET?
23
So there can be
variations upon a theme.
Let’s consider…
24
Multi-story Laboratory Building
Program features
Biotech research
GMP compliant
BL-3 Suites
Sterilization
operations
Laboratory
Information
Management
System
Building features
VAV HVAC
systems
DDC BAS
integrated to
existing campus
Sterilization line
by equipment
provider
Commissioning
(total building)
25
New Critical Care Hospital
Program features
400 std beds
60 CCUICU beds
Incl. 20 bed burn unit
Operating Suites
Standard
Transplants
BurnTrauma
MRI Suites (2)
ASHE
Accreditation
Building features
Provisions for TB
isolation
“Controlled
Environment”
Operating Theatres
DDC BAS
MRI by equipment
provider
Commissioning
26
Convention Center Hotel
Program features
500 Rooms
Meeting Rooms
Ballrooms
Restaurants
Fitness Center
Pool
Spa
Building features
DOAS
LEED Platinum
Connected to
Convention
Center Plant
Anchor for
downtown
redevelopment
Location of next
G8 + conference
27
What gets done after it’s “done”…
The sources of dispute
Impact of Liquidated Damages on Risk of Dispute
Things to think about
Contract language…
…to address specifics (when, what, by whom)
…for “phased” completion
…to define “acceptance”
…to address “what about”s
…and “I thought you meant…”
…to consider…
time.
We are all faced with a series of
great opportunities brilliantly
disguised as insoluble problems.
John W. Gardner
E. Mitchell Swann P.E.,
LEED AP, F.CIBSE, C.Eng
Principal - MDCSystems®
swann@mdcsystems.com
www.MDCSystems.com
Questions?
E. Mitchell Swann, P.E., LEED AP
swann@mdcsystems.com
Principal and Partner
MDC Systems, LLC
Licensed Professional Engineer:
Pennsylvania, New Jersey, New York, Connecticut, California, Michigan, Illinois, Georgia, Kentucky
US Green Building Council LEED Accredited Professional
Mr. Swann has over 20 years of extensive experience on both domestic and international projects in the areas of
management consulting and problem solving, engineering design, project and construction management, forensic
engineering and construction claims analysis. Mr. Swann’s career includes the analysis, evaluation and design of complex
systems across a wide range of industries and buildings types including commercial, institutional and industrial facilities,
hospitals laboratories, pharmaceutical manufacturing, microelectronic operations and data centers. Mr. Swann has chaired
technical committee within national and international organizations and been a contributing author and editor for a number
of technical publications and journals. He is a frequent speaker both nationally and internationally and is a listed member of
the speakers’ bureau in the Distinguished Lecturer program of ASHRAE. He has recently presented on Green Building
issues in Abu Dhabi, Dubai, Delhi, Detroit, Chicago, Seattle, New York City, Indianapolis, Kansas City, Virginia and
Delaware. He is a contributing author to the ASHRAE “Green Guide - The Design, Construction and Operation of
Sustainable Buildings” and co-author of the ASHRAE Survival Guide to Design|Build Project Execution.
Professional Affiliations:
American Bar Association, American Society of Heating, Refrigeration, and Air Conditioning Engineers, International
Society of Pharmaceutical Engineering, US Green Building Council, Defense Research Institute
Other Activities:
Pennsylvania Environmental Council - Board
The Engineer’s Club of Philadelphia - Board of Directors
Enterprise Heights CDC - Board Chair
Drexel University - Alumni Board of Governors
National Association of Asian American Professionals (Philadelphia Chapter) - Board of Directors
National Society of Black Engineers Greater Philadelphia Chapter - President Emeritus
MDCSystems® Summary of Services
Program & Project Development
including…
Performance Assessment &
Benchmarking
Project Modeling including…
“What if…” Scenario Analyses
Variability/Sensitivity Analyses
‘Out of Bounds’/”Go - No Go”
Limits
Project Planning including…
Feasibility Studies
Master Scheduling including…
Resource & Constraint Analysis
Project Monitoring including…
Schedule Compliance
Cash Flow & “Burn rate” projections
Resource Utilization
Consulting Services including…
Sustainability/Green Buildings
Peer Review
Practice Management
Forensic Analyses including:
Building Systems:
Architectural incl. Building Envelope
HVAC/Mechanical, Electrical & Piping
Structural
Instrumentation & Controls
Design Errors & Omissions (Standard of
Care)
Differing Site
Conditions
Forensic Project Management®Schedule Analysis
Delay, Disruption, Suspension
&
AccelerationLabor Productivity & Inefficiency
Scope Definition and Change
Termination - Default or Convenience
Procurement - Bid/Award Transparency
Forensic Accounting including…
Valuation of Damages
Overhead & General
Conditions
Business Interruption & Lost Profit
MDCSystems®
Providing Expert Project Delivery Solutions Worldwide
MDC Systems is a project and construction management consultancy
with
over 40 years of experience serving a wide array of clients and industries both
nationally and around the globe.MDC has worked on projects as diverse as residential property
developments
to pharmaceutical plants to highway excavation and construction.MDC concentrates its services in primarily four areas:
program management, project management consulting, forensic
engineering
and construction claims consulting.One of the key facets of MDC’s professional staff is our expertise in the
technology driven issues that are so frequently at the heart of today’s complex
projects.
MDC’s construction claims consulting practice combines all of the skills
inherent to our other service offerings and deploys it for our clients when and
where projects don’t go quite as smoothly as everyone had hoped. MDC is an
industry leader in the area of construction schedule development and analysis
including delay, acceleration, interruption and extended duration. MDC pioneered
the court tested and approved Time Impact Analysis methodology for scientifically
analyzing construction schedules and the impact of events upon their execution
and completion.
www.MDCSystems.com
Selected Recent Assignments
Engineering Consulting and Project Management, Execution &
Technical Analyses: Construction Claims :
Analysis of Moisture Migration and RH
Control in a Microelectronics Product
R&D Facility (Colorado).
Analysis and Improvement of Energy
Consumption at a “Green” School
(Pennsylvania)
Peer Review & Design Supervision for a
Radiant Heating/Cooling Floor System
(New Jersey)
Peer Review of Schematic Engineering
Design Effort for Hospital Complex
(Qatar)
Analysis of Formaldehyde Outgassing
from Construction Materials
(Pennsylvania)
HVAC System Failures in
Pharmaceutical Packaging Facility
(New Jersey)
Analysis of Process Technology Failure
at Waste Treatment Plant (New Jersey)
Analysis of Piping System Joint
Failures at a Hospital central Plant
(New Jersey)
Analysis of Destructive Vibration
Harmonics on Large Industrial
Compressors at a Chemical Plant
(Louisiana)
Excess Rock Excavation Claim on a Highway
Project - Unforeseen Conditions (New
Jersey)
Electrical Contractor Inefficiency Claim on
Multi-Prime Project (New Jersey)
Electrical Usage Charge Dispute Between
Landlord & Tenant (New York)
Schedule Delays and Change Orders on
multiple Airport Projects for Major
Equipment Supplier (various)
Schedule Delays and Associated Cost
Overruns for Underwater Pipeline Project
(Ireland)
“Standard of Care” Defense - Design of a
Food Processing Facility (Pennsylvania)
“Custom & Practice” - Specifications
Development and Bid Transparency Issues
(California)
“Standard of Care” Defense - Design and
Documentation of a Pharmaceutical Plant
using 3D Modeling (Texas)
“Standard of Care” Plaintiff - Delay and
Cost Overruns for a Pharmaceutical Plant
using 3D Modeling (Singapore)

More Related Content

Similar to Are We There Yet - Substantial-Completion

Best practices for commercial construction contracting 1-6
Best practices for commercial construction contracting 1-6Best practices for commercial construction contracting 1-6
Best practices for commercial construction contracting 1-6
Kevin Connolly
 
Clients in construction_best_practice_guidance (1)
Clients in construction_best_practice_guidance (1)Clients in construction_best_practice_guidance (1)
Clients in construction_best_practice_guidance (1)
Mirela M
 
03 CONSTRUCTION OWNERS REP INFORMATION
03 CONSTRUCTION OWNERS REP INFORMATION03 CONSTRUCTION OWNERS REP INFORMATION
03 CONSTRUCTION OWNERS REP INFORMATION
Joe Trujillo
 
Aba div 4_swann_design_build_standard_of_care_2014_05_27
Aba div 4_swann_design_build_standard_of_care_2014_05_27Aba div 4_swann_design_build_standard_of_care_2014_05_27
Aba div 4_swann_design_build_standard_of_care_2014_05_27
Roland_Nikles
 
Control and Risk Mitigation Whitepaper
Control and Risk Mitigation WhitepaperControl and Risk Mitigation Whitepaper
Control and Risk Mitigation Whitepaper
Greg Fry
 

Similar to Are We There Yet - Substantial-Completion (20)

Best practices for commercial construction contracting 1-6
Best practices for commercial construction contracting 1-6Best practices for commercial construction contracting 1-6
Best practices for commercial construction contracting 1-6
 
disruption-claims-forum-presentation.pptx
disruption-claims-forum-presentation.pptxdisruption-claims-forum-presentation.pptx
disruption-claims-forum-presentation.pptx
 
Managing Contractors Effectively 2011
Managing Contractors Effectively 2011Managing Contractors Effectively 2011
Managing Contractors Effectively 2011
 
CDM 2015 - A quick summary
CDM 2015 - A quick summaryCDM 2015 - A quick summary
CDM 2015 - A quick summary
 
Clients in construction_best_practice_guidance (1)
Clients in construction_best_practice_guidance (1)Clients in construction_best_practice_guidance (1)
Clients in construction_best_practice_guidance (1)
 
Professional Practice for Architecture II
Professional Practice for Architecture IIProfessional Practice for Architecture II
Professional Practice for Architecture II
 
SLI Corporate Overview - April 2023.pdf
SLI Corporate Overview - April 2023.pdfSLI Corporate Overview - April 2023.pdf
SLI Corporate Overview - April 2023.pdf
 
Do You Need A Construction Phase Plan
Do You Need A Construction Phase PlanDo You Need A Construction Phase Plan
Do You Need A Construction Phase Plan
 
Paradigm change
Paradigm change  Paradigm change
Paradigm change
 
03 CONSTRUCTION OWNERS REP INFORMATION
03 CONSTRUCTION OWNERS REP INFORMATION03 CONSTRUCTION OWNERS REP INFORMATION
03 CONSTRUCTION OWNERS REP INFORMATION
 
SRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONSRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTION
 
Aba div 4_swann_design_build_standard_of_care_2014_05_27
Aba div 4_swann_design_build_standard_of_care_2014_05_27Aba div 4_swann_design_build_standard_of_care_2014_05_27
Aba div 4_swann_design_build_standard_of_care_2014_05_27
 
SRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONSRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTION
 
SRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTIONSRI AARUTHRAA CONSTRUCTION
SRI AARUTHRAA CONSTRUCTION
 
LEEDigation: LEEDs Impact on the Practice of Law
LEEDigation:  LEEDs Impact on the Practice of LawLEEDigation:  LEEDs Impact on the Practice of Law
LEEDigation: LEEDs Impact on the Practice of Law
 
Against all odds
Against all odds Against all odds
Against all odds
 
Project Controls Expo 18th Nov 2014 - "Project Controls – The Legal Perspecti...
Project Controls Expo 18th Nov 2014 - "Project Controls – The Legal Perspecti...Project Controls Expo 18th Nov 2014 - "Project Controls – The Legal Perspecti...
Project Controls Expo 18th Nov 2014 - "Project Controls – The Legal Perspecti...
 
Agile in a highly regulated organization 2014
Agile in a highly regulated organization 2014Agile in a highly regulated organization 2014
Agile in a highly regulated organization 2014
 
Control and Risk Mitigation Whitepaper
Control and Risk Mitigation WhitepaperControl and Risk Mitigation Whitepaper
Control and Risk Mitigation Whitepaper
 
Al Bawardi Critchlow
Al Bawardi CritchlowAl Bawardi Critchlow
Al Bawardi Critchlow
 

Recently uploaded

result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 

Recently uploaded (20)

Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 

Are We There Yet - Substantial-Completion

  • 1. ASHRAE Pittsburgh Chapter March 6, 2014 Are We There Yet? What is "Substantial Completion" ? (…and how do we know when we get there?) E. Mitchell Swann P.E., LEED AP F. CIBSE, C.Eng Principal MDCSystems® www.MDCSystems.com Copyright E. Mitchell Swann & MDC Systems 2
  • 2. Program Overview What is “Substantial Completion” Implication of the selected definition on actual project completion New considerations in the industry Example circumstances Summary Questions & Answers 3
  • 3. Program Overview Are We There Yet? What is "Substantial Completion" and how do we know when we get there? "Substantial completion": These two words can change the course of history. Well, the course of your payment history, anyway. Many contracts contain that phrase as a key indicator of major project milestones for the release of retainage, the start of warranty periods and more frequently everyday, the start up of energy measurement and verification programs. But the definition of "substantial" and "complete" are wide and varied. This program will explore the permutations and implications of the various interpretations of "substantial completion" and how it can affect the happy family that is your project team. 4
  • 5. Some synonyms….(?) Mechanical Completion Unit is essentially complete for start-up operation and test run. All major work is completed. Minor work not interfering with operation may not be completed, such as punch list and minor touch-up work. (from dictionaryofconstruction.com) 6
  • 6. U Mechanical other stuff to do… Completion 7
  • 7. Beneficial Occupancy When an owner of a property can use it before all the construction is completed. (from Black’s Law Dictionary) Use of a building, structure, or facility by the owner for its intended purpose (functionally complete), although other contract work, nonessential to the function of the occupied section, remains to be completed. (emphasis added) (from theconstructiondictionary.com)
  • 8. Certificate of Occupancy A document issued by a local government agency or building department certifying a building's compliance with applicable building codes and other laws, and indicating it to be in a condition suitable for occupancy. The purpose is to prove that, according to the law, the building is in livable condition.A certificate of occupancy is evidence that the building complies substantially with the plans and specifications that have been submitted to, and approved by, the local authority. (emphasis added)
  • 9. So what is substantial completion? The answer varies, but… I know it when I see it! - Judge Potter Stuart 10
  • 10. So how about this? Section A.9.8.1 (from the AIA 201 - General Conditions of the Contract for Construction) : “the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use.” Sounds like…. Is “mechanical completion” required? Is a C of O required? 11
  • 11. Why does this matter? The date of substantial completion can establish… …the date that the owner becomes responsible for the property, (the “clock” starts - builders’ warranty); …the date that a contractor is no longer fully liable for delayed completion; …the date the “Statute of Limitations” clock starts (what’s this?) ; …the date the “Statute of Repose” clock starts (what’s that?); 12
  • 12. The date of substantial completion (…could become a day that might live in infamy.) Builders Warranty: …the hands of time…. Written statement by a builder assuring that a project was completed according to a stipulated set of standards. It protects the buyer from latent defects. Patent Defects Latent Defects 13
  • 13. The date of substantial completion (…could become a day that might live in infamy.) …a contractor is no longer fully liable for delayed completion Liquidated Damages: Monetary compensation for a loss, detriment, or injury to a person or a person's rights or property, awarded by a court judgment or by a contract stipulation regarding breach of contract. (Legal Law Dictionary) (Think of it as "contract performance insurance.”) LIMITATIONS!Allowed when exact quantification of damages is difficult (but ARE “real”!) MUST be “reasonable” with respect to the “value” of the damages that could be incurred. NOT to be considered/”constructed as a “penalty”. 14
  • 14. The date of substantial completion (…could become a day that might live in infamy.) Statute of Limitations: A law that restricts the time within which legal proceedings may be brought. …a fundamental part of European and U.S. law. …apply to both civil and criminal actions, …designed to prevent fraudulent and stale claims …after all evidence has been lost… …after the facts have become obscured over time… …defective memory, death, or disappearance of witnesses. …a defense that is ordinarily asserted by the defendant …the parties may either shorten or extend the prescribed time period by agreement, such as a provision in a contract. 15
  • 15. The date of substantial completion (…could become a day that might live in infamy.) Statute of Repose: Provides a date upon which the action no longer can be taken - it entirely cuts off an injured person's right of action even before it accrues. …stricter deadline than statute of limitations …it may not be tolled by fraud, discovery of injury, etc. …neither an avoidance nor a defense …because the cause of action does not exist after “repose” …bars an action after a specified period of time has run from the occurrence of some event. …but NOT injury or “discovery” 16
  • 16. New considerations… Commissioning between “complete enough” and “acceptable” Energy (& resource) Performance M&V “Green Certification” Outside the project “bubble” Validation Regulatory Hurdles Accreditation Specialty Operations 17
  • 17. New considerations… Commissioning integrated application of a set of engineering techniques and procedures to check, inspect and test every operational component of the project, from individual functions, such as instruments and equipment, up to complex amalgamations such as modules, subsystems and systems. 18
  • 19. New considerations… “Green Certification” A third party vetting of the completed project? 20
  • 22. So the on-going question is…. ARE WE THERE YET? 23
  • 23. So there can be variations upon a theme. Let’s consider… 24
  • 24. Multi-story Laboratory Building Program features Biotech research GMP compliant BL-3 Suites Sterilization operations Laboratory Information Management System Building features VAV HVAC systems DDC BAS integrated to existing campus Sterilization line by equipment provider Commissioning (total building) 25
  • 25. New Critical Care Hospital Program features 400 std beds 60 CCUICU beds Incl. 20 bed burn unit Operating Suites Standard Transplants BurnTrauma MRI Suites (2) ASHE Accreditation Building features Provisions for TB isolation “Controlled Environment” Operating Theatres DDC BAS MRI by equipment provider Commissioning 26
  • 26. Convention Center Hotel Program features 500 Rooms Meeting Rooms Ballrooms Restaurants Fitness Center Pool Spa Building features DOAS LEED Platinum Connected to Convention Center Plant Anchor for downtown redevelopment Location of next G8 + conference 27
  • 27. What gets done after it’s “done”…
  • 28. The sources of dispute
  • 29. Impact of Liquidated Damages on Risk of Dispute
  • 30. Things to think about Contract language… …to address specifics (when, what, by whom) …for “phased” completion …to define “acceptance” …to address “what about”s …and “I thought you meant…” …to consider… time.
  • 31. We are all faced with a series of great opportunities brilliantly disguised as insoluble problems. John W. Gardner
  • 32. E. Mitchell Swann P.E., LEED AP, F.CIBSE, C.Eng Principal - MDCSystems® swann@mdcsystems.com www.MDCSystems.com Questions?
  • 33. E. Mitchell Swann, P.E., LEED AP swann@mdcsystems.com Principal and Partner MDC Systems, LLC Licensed Professional Engineer: Pennsylvania, New Jersey, New York, Connecticut, California, Michigan, Illinois, Georgia, Kentucky US Green Building Council LEED Accredited Professional Mr. Swann has over 20 years of extensive experience on both domestic and international projects in the areas of management consulting and problem solving, engineering design, project and construction management, forensic engineering and construction claims analysis. Mr. Swann’s career includes the analysis, evaluation and design of complex systems across a wide range of industries and buildings types including commercial, institutional and industrial facilities, hospitals laboratories, pharmaceutical manufacturing, microelectronic operations and data centers. Mr. Swann has chaired technical committee within national and international organizations and been a contributing author and editor for a number of technical publications and journals. He is a frequent speaker both nationally and internationally and is a listed member of the speakers’ bureau in the Distinguished Lecturer program of ASHRAE. He has recently presented on Green Building issues in Abu Dhabi, Dubai, Delhi, Detroit, Chicago, Seattle, New York City, Indianapolis, Kansas City, Virginia and Delaware. He is a contributing author to the ASHRAE “Green Guide - The Design, Construction and Operation of Sustainable Buildings” and co-author of the ASHRAE Survival Guide to Design|Build Project Execution. Professional Affiliations: American Bar Association, American Society of Heating, Refrigeration, and Air Conditioning Engineers, International Society of Pharmaceutical Engineering, US Green Building Council, Defense Research Institute Other Activities: Pennsylvania Environmental Council - Board The Engineer’s Club of Philadelphia - Board of Directors Enterprise Heights CDC - Board Chair Drexel University - Alumni Board of Governors National Association of Asian American Professionals (Philadelphia Chapter) - Board of Directors National Society of Black Engineers Greater Philadelphia Chapter - President Emeritus
  • 34. MDCSystems® Summary of Services Program & Project Development including… Performance Assessment & Benchmarking Project Modeling including… “What if…” Scenario Analyses Variability/Sensitivity Analyses ‘Out of Bounds’/”Go - No Go” Limits Project Planning including… Feasibility Studies Master Scheduling including… Resource & Constraint Analysis Project Monitoring including… Schedule Compliance Cash Flow & “Burn rate” projections Resource Utilization Consulting Services including… Sustainability/Green Buildings Peer Review Practice Management Forensic Analyses including: Building Systems: Architectural incl. Building Envelope HVAC/Mechanical, Electrical & Piping Structural Instrumentation & Controls Design Errors & Omissions (Standard of Care) Differing Site Conditions Forensic Project Management®Schedule Analysis Delay, Disruption, Suspension & AccelerationLabor Productivity & Inefficiency Scope Definition and Change Termination - Default or Convenience Procurement - Bid/Award Transparency Forensic Accounting including… Valuation of Damages Overhead & General Conditions Business Interruption & Lost Profit
  • 35. MDCSystems® Providing Expert Project Delivery Solutions Worldwide MDC Systems is a project and construction management consultancy with over 40 years of experience serving a wide array of clients and industries both nationally and around the globe.MDC has worked on projects as diverse as residential property developments to pharmaceutical plants to highway excavation and construction.MDC concentrates its services in primarily four areas: program management, project management consulting, forensic engineering and construction claims consulting.One of the key facets of MDC’s professional staff is our expertise in the technology driven issues that are so frequently at the heart of today’s complex projects. MDC’s construction claims consulting practice combines all of the skills inherent to our other service offerings and deploys it for our clients when and where projects don’t go quite as smoothly as everyone had hoped. MDC is an industry leader in the area of construction schedule development and analysis including delay, acceleration, interruption and extended duration. MDC pioneered the court tested and approved Time Impact Analysis methodology for scientifically analyzing construction schedules and the impact of events upon their execution and completion. www.MDCSystems.com
  • 36. Selected Recent Assignments Engineering Consulting and Project Management, Execution & Technical Analyses: Construction Claims : Analysis of Moisture Migration and RH Control in a Microelectronics Product R&D Facility (Colorado). Analysis and Improvement of Energy Consumption at a “Green” School (Pennsylvania) Peer Review & Design Supervision for a Radiant Heating/Cooling Floor System (New Jersey) Peer Review of Schematic Engineering Design Effort for Hospital Complex (Qatar) Analysis of Formaldehyde Outgassing from Construction Materials (Pennsylvania) HVAC System Failures in Pharmaceutical Packaging Facility (New Jersey) Analysis of Process Technology Failure at Waste Treatment Plant (New Jersey) Analysis of Piping System Joint Failures at a Hospital central Plant (New Jersey) Analysis of Destructive Vibration Harmonics on Large Industrial Compressors at a Chemical Plant (Louisiana) Excess Rock Excavation Claim on a Highway Project - Unforeseen Conditions (New Jersey) Electrical Contractor Inefficiency Claim on Multi-Prime Project (New Jersey) Electrical Usage Charge Dispute Between Landlord & Tenant (New York) Schedule Delays and Change Orders on multiple Airport Projects for Major Equipment Supplier (various) Schedule Delays and Associated Cost Overruns for Underwater Pipeline Project (Ireland) “Standard of Care” Defense - Design of a Food Processing Facility (Pennsylvania) “Custom & Practice” - Specifications Development and Bid Transparency Issues (California) “Standard of Care” Defense - Design and Documentation of a Pharmaceutical Plant using 3D Modeling (Texas) “Standard of Care” Plaintiff - Delay and Cost Overruns for a Pharmaceutical Plant using 3D Modeling (Singapore)