SlideShare a Scribd company logo
1 of 20
GROUP MEMBERS: NA YONG YI 0324458
CHAI JIA ERN 0324653
GOH XINGXIN 0325587
TAN KAI XUAN 0325066
TEE WAN NEE 0325074
CHEAH MAN YEE 0324743
LECTURER: MS. TAY SHIR MEN
SCHOOL OF ARCHITECTURE,
BUILDING AND DESIGN
BACHELOR OF QUANTITY SURVEYING (HONS)
CONSTRUCTION OF SUPPLY
CHAIN MANAGEMENT (MGT
60803)
(GROUP ASSIGNMENT)
BIM
Building Information Modelling
CONTENTS
INTRODUCTION
1.1 BIM (BUILDING INFORMATION MODELLING)
1.2 BIM CYCLE
DIMENSION IN BIM
2.1 ADVANTAGES OF 3D
3.1 ADVANTAGES OF 4D
4.1 ADVANTAGES OF 5D
5.1 ADVANTAGES OF 6D
6.1 ADVANTAGES OF 7D
DISADVANTAGES
CONCLUSION AND RECOMMENDATIONS
7.0 CONCLUSION
7.1 RECOMMENDATIONS
REFERENCES
5.1 REFERENCES
ADVANTAGES2.0 INTRODUCTION IN 3D
3.0 INTRODUCTION IN 4D
4.0 INTRODUCTION IN 5D
5.0 INTRODUCTION IN 6D
6.0 INTRODUCTION IN 7D
2.2 DISADVANTAGES OF 3D
3.2 DISADVANTAGES OF 4D
4.2 DISADVANTAGES OF 5D
5.2 DISADVANTAGES OF 6D
6.2 DISADVANTAGES OF 7D
BIMBuilding Information Modelling
Building Information Modeling (BIM) is a digital
representation of physical and functional
characteristics of a facility. It is an intelligent,
model-based process for planning,
designing, constructing, and managing
various buildings and infrastructures. A
BIM is a shared knowledge resource
for information about a facility
forming a reliable basis for
decisions during its life-cycle;
defined as existing from earliest
conception to demolition. In
another word, BIM is a process
for creating and managing all
of the information on a project
– before, during and after
construction.
DESIGN PHASE CONSTRUCTION PHASE MANAGEMENT PHASE MAINTENANCE PHASE
DATA COLLECTED FROM
DIGITAL MODELS
BIM model consists of the virtual equivalents of the actual building parts used to build a building. These elements
have all the characteristics - both physical and logical - of their real counterparts. These intelligent elements are
the digital prototype of the physical building architecture and structural elements that allow us to simulate the
building and understand its behavior in a computer environment way before the actual construction starts.
USED BY
ALL CONSTRUCTION PARTNERS
CONCEPTUAL DESIGN
PROGRAMMING
DETAILED DESIGN
ANALYSIS
DOCUMENTATION
FABRICATION
CONSTRUCTION
CONSTRUCTION
LOGISTICS
OPERATION &
MAINTENANCE
DEMOLITION
RENOVATION
BIM
Building Information Modelling
C Y C L E
The program can
only be properly
considered once
awareness is gained
of the design team’s
BIM capabilities. If
you have appointed a
design team strong in
BIM across the board,
you can reduce the
program time down
significantly. In
addition, through the
use of phasing in
software, contractors
can program out
the order of works
much more efficiently.
This is where the design
process really starts,
and it can be a very
unstable or fluid
process. All designers
will work in the same
model (database). This
way, any coordination
issues can be worked
out in the design phase
rather than interrupting
the construction phase.
This is where the
magic really
happens. The
concept should be
predominantly
fixed and
therefore it is time
to start modelling.
The majority of
3D modelling
should have
been completed.
It is at this stage
you will start
extracting the
information you
require from it This is where we
finish the design
documents to a
construction level.
The type of contract
put in place will
determine who
produces the
documentation and
to what level.
This is what we
refer to as shop
drawings. All shop
drawings are a
product of the
information given
from BIM. At this
stage there are
often questions
from contractors if
they require more
information to
understand the
design intent. BIM
allows additional
information to be
extracted to easily
answer design
queries.
The software will
simulates the
operation and
maintenance. The
structure will be
tested through the
simulation to see if it
serves its intended
purpose. The
detailed look and
feel of the intended
architecture as well
as Its functionality
will be tested using
the simulation. The
building operations
will be simulated over
time and wear and
tear of the construct
will be noted.
Buildings do have life
cycles, and over time
they will need
renovation. This type
of work is not as
common in the BIM at
present as a many of
the buildings are so
new. BIM is an
excellent process to
use for the design/
management of
demolition works.
Renovation can be
simulated using the
computer added
design to allow the
involved parties to
understand the
implication faced in
case of any decision
to renovate the
construct based on
the present design.
Once the design
has been
finalized, the
construction of
the building can
commence.
The whole
construction of
the building is
simulated using
the software.
The logistics of all
the materials from
the warehouse to
the construction
site to be placed
to the proper
location area in
order for the
construction to
take place will also
be calculated and
decided upon
through
simulation.
3D BIM - The shared information model
3D models represent a physical body using a collection of
points in 3D space, connected by various geometric entities
such as triangles, lines, curved surfaces, etc. It is the most
commonly known dimension, as it refers to the “visible” part
of a BIM model. Being a collection of data (points and other
information) BIM revolves around an integrated data model
from which various stakeholders such as Architects, Civil
Engineers, Structural Engineers, MEP System Engineers,
Builders, Manufacturers and Project Owners can extract
and generate views and information's according to their
needs. 3D BIM's visualizations capabilities enables
participants to not only see the building in three dimensions
before ground is ever broken, but also to automatically
update these views along the project life cycle, from earliest
conception to demolition.
SOFTWARE USED
Sketch Up Blender Auto CAD RhinoBIM
Autodesk Revit 3ds Max Maya ZBRUSH
Infrawork 360 Softtech Spirit ARC+ x9
VisualARQMidas Design
3D BIM - The shared information model
ADVANTAGES:
 Improved visualization of the project &communication of design intent .
It allows one to see a project in plan, elevation, section, and perspective
simultaneously. This is important because it significantly improves coordination
between drawings and reduces the potential for errors.
 Reduce rework
Visualisation of projects to enable greater understanding of all members of the
team. For example, it is far easier to schedule scaffolding requirements looking at a
3D model than in 2D. . The impact of a change made to a floor plan is instantly
available to review in section, elevation, and perspective views.
 Disputes avoided
It enhances the communication among the different team members of a project
like design team, subcontractors, owners and others that leads to a significant
development in the planning process of a project as they are more easy to
understand on the features and ideas that are proposed.
MAIN ADVANTAGE ABLE TO COMMUNICATE THE DESIGN INTENT
 Improved multidisciplinary collaboration.
Synchronization between different disciplines, such as architecture and structural
engineering, is improved because the impact of one discipline’s work on another is
immediately apparent. Complicated structures can be studied in section, instead of
drawing sections manually. This increased coordination can greatly speed up the
design process.
DISADVANTAGES:
 More work upfront in 3D BIM
The implementation of 3D BIM require more effort at the outset of a project. When
BIM is used, it is insufficient for a contractor to simply submit plans or drawing and
begin to construct. The contractor team must first sit down with the design team to
create a collaborative model.
 High software cost
The upfront cost for hardware, software, training, and implementation can be
pretty hefty. This causes small and medium companies do not interested in
implementing BIM and thus it may be a barrier to communicate with other
parties.
 Copyright
Practical issues about BIM concerns the copyright and ownership of contributed
designs. Where various different design elements produced by separate
consultants are fed into a composite model, and then adapted, authorship will
become blurred.
 Corruption in transmission
Electronically transmitted information becoming corrupted or altered is also a
main concern in BIM. Such concern are not exclusive to BIM projects but
because of their nature any such corruption or alternation will be compounded
and could therefore have an enormous impact on the success of the project.
3D BIM - The shared information model
4D BIM - Scheduling
4D BIM refers to the intelligent linking of individual 3D CAD
components or assemblies with time-related information.
Time-related information for a particular element might
include information on lead time, how long it takes to install
or construct, the time needed to become operational, the
sequence in which components should be installed, and
dependencies on other areas of the project. The fourth
dimension of BIM is used for construction site planning related
activities. It is possible to visualize and to control the progress
of the activities through the lifetime of the project. It allows
construction planners to run simulations to assess how
proposed design features will impact the construction
schedule and workflow. With 4D BIM, planners can
determine appropriate resource scheduling, identify potential
bottlenecks, develop phasing plans, communicate and track
milestones, and find opportunities to improve the schedule
overall. 4D BIM provides methods for managing and
visualizing site status information, change impacts as well as
supporting communication in various situations such as
informing site staff or warning about risks.
SOFTWARE USED
Vico Software Synchro Bentley Navigator ITwo
Naviswork Manage Gest Mideplan Primavera P6
Gestproject MS Project TCQ
4D BIM - Scheduling
ADVANTAGES
 More effective& efficient explanation and communication of schedule
It provides Identification of problems not visible via traditional schedules.
Builders and manufacturers can optimize their construction activities and team
coordination.
 Production of more rigorous schedules
4D BIM allow to analyse the schedule to asses feasibility of execution.
 Improved control over conflict detection
The complexity of changes occurring during the course of a construction project.
4D BIM provides methods for managing and visualizing site status information,
change impacts as well as supporting communication in various situations such
as informing site staff or warning about risks.
MAIN ADVANTAGE FOLLOW UP TOO THE SCHEDULE IN CASE OF
PROJECT CHANGES.
DISADVANTAGES:
 Does not support procurement & offsite activities
4D models do not support offsite activities such as the submittal – approval and the
procurement cycles, offsite work such as fabrication or activities like coordination
etc. These important and often critical activities must be carried in the conventional
schedule but cannot be displayed visually.
 Time consuming for transmission
Development of 4D model from 2D documents is timely and challenging. It also
requires highly skilled and trained staff to execute the process which is short supply
and expensive to bear.
 Disruptive in construction
Although one of the advantages of using a BIM model is that changes can
be made quickly, BIM can disrupt the general procurement and
construction process when ordering items that require a long lead time.
5D BIM - Cost
Drawing on the components of the information model being able to
extract accurate cost information is what's at the heart of 5D BIM.
QUANTITY TAKEOFFS
To determine a project's construction cost and requirements,
contractors traditionally perform material ‘take-offs’ manually, a
process fraught with the potential for error. With BIM, the model
includes information that allows a contractor to accurately and rapidly
generate an array of essential estimating information, such as materials
quantities and costs, size and area estimates, and productivity
projections. As changes are made, estimating information
automatically adjusts, allowing greater contractor productivity.
‘REAL TIME’ COST ESTIMATING
In a BIM model cost data can be added to each object enabling the
model to automatically calculate a rough estimate of material costs.
This provides a valuable tool for designers, enabling them to conduct
value engineering thereby reaching an overall cost for the
development.
SOFTWARE USED
Vico Software Nevaris Bentley ConstructSim Presto Cost‐it
GLODON BIM 5D PriMus BIM constructSIM
DESTINI Estimator TCQ 2000 BIM
5D BIM - Cost
ADVANTAGES
 A greater accuracy and predictability of project's estimates.
It allows participants to visualize the progress of their activities and related costs over
time. The costs here include the purchasing, installing, running, maintenance and
renewal costs. Formulas drive costs on each building system based on the specific
design, materials, site conditions, phasing and other parameters according to the
owner’s timeline.
 Save time in calculating cost
It save times and patience for calculations pertaining to the entire project cost. Thus,
whenever a single component is replaced or changed, the direct impact on the cost
gets calculated automatically.
 Reliable, accurate updates in real time drive efficiency
Data is provided in real time as the model is developed or changed. Alternative
concepts can be easily explored; while owner and project team can see the cost and
other data unfold instantaneously. This drastically shortens design and estimation
cycle time. All major project stakeholders can visualize the end product and
understand exactly what is included in the budget.
MAIN ADVANTAGE COST CHANGES AUTOMATICALLY IN CASE OF
PROJECT CHANGES.
DISADVANTAGES:
 Lack of electronic standard for coding
Lack of an electronic standard for coding BIM software to Standard Methods of
Measurement limits the potential of 5D BIM. Although BIM assisted estimating tools
can generate large quantities of construction items in order to efficiently produce
cost estimates, the extracted quantities have a lack of understanding of
construction methods, which reduces the accuracy of estimates.
 No software for full function of BIM
There are currently no single software available that can perform all functions that
BIM is capable of enabling. Therefore incorporating 5D BIM the team also had to
assist in several projects that were using for 3D clash detection and 4D simulation
purposes.
 Complicated to control
The 5D software was described as robust but complicated to use. The software
program that enable 5D-BIM require a high level of technological expertise as well
as expertise with construction processes.
6D BIM - Sustainability
SOFTWARE USED
Vasari Autodesk Green Building Studio Bentley Hevacomp Trimble Sefaira
The sixth dimension of BIM is used for energy
assessment during the design phase and operational
phase. 6D BIM facilitates the implementation of
energy analysis for buildings. 6D BIM involves the
inclusion of information to support facilities
management and operation to drive better business
outcomes. This data might include information on the
manufacturer of a component, its installation date,
required maintenance and details of how the item
should be configured and operated for optimal
performance, energy performance, along with lifespan
and decommissioning data. An efficient data
collection from installed sensors enables to better
understand the building’s performance and define a
strategy aiming to optimize the building’s energy
consumption. In effect, designers can explore a whole
range of permutations across the lifecycle of a built
assets and quickly get an understanding of impacts
including costs.
Design Builder Software Open Studio Ecotect Analysis
6D BIM - Sustainability
 Result in more complete and accurate energy
It also allows for measurement and verification during building occupation, and
improved processes for gathering lessons learned in high performance
facilities.
ADVANTAGES
 Overall reduction in energy consumption
Helps facility managers to bring down utility bills and operate a
building in the most efficient manner, ensuring highest level of
occupant comfort.
MAIN ADVANTAGE HELPS TO PERFORM ENERGY CONSUMPTION
ANALYSIS
 Support decision making
At delivery phase, it enables design teams to consider their impact of their
proposals over a built asset’s lifecycle, simulating outcomes and anticipated
costs. But the ultimate value, lies in the use of that data to support the
operational phase.
 Support the operation of the built asset
At handover, project teams can pass their complete data set (known as
an Asset Information Model or AIM) over to the end-user. The digital
model offers them a more controlled, accessible and easily navigable way
of managing their information.
6D BIM - Sustainability
 Restriction of sharing information
Do not allow for knowledge sharing among energy managers across all public
departments. The restriction of sharing information unable to add value to
the used system which will affect the sustainability of the buildings, such as
preservation of historical building.
DISADVANTAGES
 Fragmented
It is fragmented which is created by different teams with different
objectives and stored in different system. Therefore, this identifies that
lack of integration of information is the barrier for energy managers in
using BIM 6D.
 Cost intensive & not easy to use
This specialized training is necessary to use them. Other than that, a
contractor may need to upgrade its computer system to effectively use the
BIM software.
 Not yet universally used
6D Bim is not yet universally used among construction professionals.
There is always the possibility that one of the subcontractors may not
use 6D Bim and may not be able to use your models. It is also critical for
operators and facility management to read and study the models using
the BIM software, since they do not undergo significant training.
Problems may occur if the drawing design and the related information
are precise and accurate.
7D BIM - Facility Management
SOFTWARE USED
Autodesk Building ops Asset Wise ArchiFM Tekla BIM Sight
The seventh dimension is used to extract and collect
relevant information related to the operation and
maintenance status of the facility throughout its life
cycle. 7D is the main field where BIM model’s data
can definitely make the difference. Starting a Facility
Management program based on reliable extracted
information from an as-built BIM provide the most
effective solutions for the management of a
building. Besides, tracking and maintaining lifecycle
information about the building structure as well as
the equipment serving the to plan and schedule a
program of maintenance activities that will improve
building performance, reduce repairs, and reduce
overall maintenance costs.
GestProject YouBim Archibus Ecodomus
7D BIM - Facility Management
ADVANTAGES
MAIN ADVANTAGE MANAGE ASSETS LIFE CYCLE.
 Allows participants to extract and track relevant asset data
(Such as component status, specifications, maintenance/operation manuals,
warranty data etc. for easier and quicker parts replacements). It is an approach
to the facility management process not only improves the whole process, but
also improves the quality of services.
 Easier and quicker parts replacements
Optimized compliance and a streamlined asset life cycle management over
time. 7D BIM provides processes for managing subcontractor/supplier data
and facility component through the entire facility life cycle.
 Integrating BIM with 7D CAD simulation models optimizes asset
management from design to demolition
DISADVANTAGES:
 Requiring updated hardware and software
Modelling is more concern on post-construction and project life cycle where
frequent updates are inserted into the modelling which will result in the
difficulty in managing additional volume and complexity of digital information.
This will require an upgrade in hardware and software to manage the
information which will lead to increase in cost.
 Training needed
Training will also need to be provided to facilities managers to understand
and operate 7D BIM which will incur cost. Interoperability between software
applications by different party and different point of time will cause large
number of data exchange and updating takes place. This is due to individual
and firms will have their own preferred system, software application and
processes.
Conclusion
In conclusion, BIM can help quantity surveyors to speed up the estimating process compared to the
traditional method that many of the surveyors are still using and as technology evolves, the QS are
forced to evolve as well so that they would not be left out by the society. On the other hand, the
foundation, which is also the traditional method is also important this is so that all the surveyors have
a strong foundation of estimating.
Furthermore, from this report, we know that the BIM requires a lot of upfront calibration between the
QS and also designer, such as, inputting the correct coding, zoning and ensuring that the building is
drawn as it should be built. Even after all the upfront work QS have to interrogate, interpret and also
extract the quantities and align with standard methods of measurement.
With the development of technology like BIM, the responsibilities of the professionals are starting to
shift. Not only that, BIM includes a series of cost management functions that could change the
processes of cost management of construction projects. This allows the Quantity Surveyor to delve
deeper into different parts of the cost management process.
In addition, there are also some of the challenges that are faced by the surveyors while using the BIM
which are the advancement of technology which can be also seen from the few decades behind which
transforms from using the ‘paper’ system to initial simple Excel spreadsheet to BIM. Next, it is the
reluctance of designers to allow 3D models to be used where the designers are reluctant to issue 3D
models that are not substantially complete to QS. The third one would be new terminology, as we the
technologies have evolved, it also means that there are new terminologies that would be used and QS
needs to understand and familiarize the implications of each terms and how this new terminology can
assist them in delivering their traditional services.
FLEXIBILITY CHANGES
Recommendation
Ability to read and import different file format. The file format that is able
currently is only the BIM file and a computer or laptop without the software,
it can’t be opened and view it. Therefore, if the file can be saved as PDF to
be sent to clients it would ease the QS more.
Able to allow project team members to collaborate, access or retrieve the
information easily and securely. This would ease the project team to finish
up the task fast and efficiently. Not only that, if the BIM software can
track changes, track errors, record variations and perform checks, it would
also add a point into helping to finish up the work as fast as possible.
Allowing users the flexibility to add
build-up rates or refer rates from cost
libraries or previous projects. This can
make the Bills Of Quantities to be
more accurate with the updated cost
of the materials in the industry.
ABILITY TO READ AND IMPORT DIFFERENT FILE FORMAT
ABLE TO ALLOW PROJECT TEAM MENBERS TO COLLABORATE
References
Anon, (2017). [online]
https://www.linkedin.com/pulse/20140822053129-66002134-benefits-of-4d-bim-in-project-phasing/
BIMPanzee. (2017). BIM 3D,4D, 5D, 6D & 7D. [online]
http://www.bimpanzee.com/bim-3d-4d--5d--6d---7d.html
GenieBelt (2017). 5D BIM: How It Will Help the Construction Industry - GenieBelt Blog. [online] GenieBelt Blog.
https://geniebelt.com/blog/5d-bim-in-construction
BIMestiMate. (2017). The theory of evolution. BIM 3D … 7D … - BIMestiMate. [online]
http://bimestimate.eu/en/the-theory-of-evolution-bim-3d-7d/
SlideOnline.com. (2017). Advantages offered by 3D, 4D, 5D and 6D BIM modeling. [online]
http://slideonline.com/presentation/29916-advantages-offered-by-3d-4d-5d-and-6d-bim-modeling
Trivedi, G. and Trivedi, G. (2017). Benefits of 4D/5D BIM to General Contractors across Construction Projects |
TrueCADD. [online] Truecadd.com.
http://www.truecadd.com/news/benefits-of-4d-5d-bim-to-general-contractors-across-construction-projects
Anon, (2017). [online]
https://www.linkedin.com/pulse/bim-3d-7d-implementation-hani-elsafadi/
Theb1m.com. (2017). What is 6D BIM?. [online]
http://www.theb1m.com/video/what-is-6d-bim
Bimsg.org. (2017). BIM for Quantity Surveying | BIM@SG. [online]
http://bimsg.org/resources/other-software-resources/bim-for-qs/
Sourceable - Construction . Design . Engineering . Property. (2017). BIM and the Quantity Surveyor. [online]
https://sourceable.net/bim-and-the-quantity-surveyor/
Anon, (2017). [online]
https://www.linkedin.com/pulse/bim-its-impact-future-role-quantity-surveyor-himani-shah
FM Systems. (2017). The Benefits of Lifecycle BIM for Facility Management. [online]
https://fmsystems.com/blog/the-benefits-of-lifecycle-bim-for-facility-management/
www.vackerglobal.com. (2017). Building Information Modelling (BIM) UAE, Qatar, KSA | VackerGlobal. [online]
https://www.vackerglobal.com/divisions/automation/building-information-modelling-bim/
BSBG | Brewer Smith Brewer Group. (2017). The BIM Cycle | BSBG | Brewer Smith Brewer Group. [online]
http://bsbgltd.com/blog/the-bim-cycle/
Anon, (2017). [online]
https://www.linkedin.com/pulse/bim-3d-7d-implementation-hani-elsafad
AXD. (2017). All the BIM dimensions. [online]
http://www.axdstudio.com/portfolio/all-the-bim-dimensions/
BIMestiMate. (2017). The theory of evolution. BIM 3D … 7D … - BIMestiMate. [online]
http://bimestimate.eu/en/the-theory-of-evolution-bim-3d-7d/
McPartland, R., McPartland, R., McPartland, R., McPartland, R. and McPartland, R. (2017). BIM dimensions -
3D, 4D, 5D, 6D BIM explained. [online] NBS.
https://www.thenbs.com/knowledge/bim-dimensions-3d-4d-5d-6d-bim-explained
Sage Advice US. (2017). Defining the dimensions of BIM | Sage Advice US. [online]
https://www.sage.com/en-us/blog/defining-dimensions-bim/#
References
Out-law.com. (2017). Building Information Modelling. [online]
https://www.out-law.com/en/topics/projects--construction/projects-and-procurement/building-information-
modelling/
Anon, (2017). [online]
http://www.bimpanzee.com/bim-3d-4d--5d--6d---7d.html
5D-BIM: A CASE STUDY OF AN IMPLEMENTATION STRATEGY IN THE CONSTRUCTION INDUSTY.
(2014). [online]
http://www.iaarc.org/publications/fulltext/isarc2014_submission_112.pdf
Smith, P. (2016). Project Cost Management with 5D BIM. Project Cost Management with 5D BIM. [online]
http://www.sciencedirect.com/science/article/pii/S1877042816308655
Kehily, D., & Underwood, J. (2017). Embedding life cycle costing in 5D BIM. [online]
http://www.itcon.org/paper/2017/8
Carlin, E. (2010). The Legal Risks of Building Information Modeling (BIM). [online]
https://www.constructionlawnowblog.com/design-and-technology/the-legal-risks-of-building-
information-modeling-bim/
Phuong Dang, D., & Tarar, M. (2012). IMPACT OF 4D MODELING ON CONSTRUCTION PLANNING
PROCESS. [online]
http://publications.lib.chalmers.se/records/fulltext/161015.pdf

More Related Content

What's hot

CSCM group project aug 2016
CSCM group project aug 2016CSCM group project aug 2016
CSCM group project aug 2016Est
 
Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryCCT International
 
Bim challenges and potential
Bim challenges and potentialBim challenges and potential
Bim challenges and potentialThomas Goubau
 
Building Information Modelling (BIM): Benefits for Small Scale Construction I...
Building Information Modelling (BIM): Benefits for Small Scale Construction I...Building Information Modelling (BIM): Benefits for Small Scale Construction I...
Building Information Modelling (BIM): Benefits for Small Scale Construction I...Dr. Amarjeet Singh
 

What's hot (6)

CSCM group project aug 2016
CSCM group project aug 2016CSCM group project aug 2016
CSCM group project aug 2016
 
Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction Industry
 
Bim challenges and potential
Bim challenges and potentialBim challenges and potential
Bim challenges and potential
 
Ijebea14 244
Ijebea14 244Ijebea14 244
Ijebea14 244
 
Nw b im_hub_-_march2013
Nw b im_hub_-_march2013Nw b im_hub_-_march2013
Nw b im_hub_-_march2013
 
Building Information Modelling (BIM): Benefits for Small Scale Construction I...
Building Information Modelling (BIM): Benefits for Small Scale Construction I...Building Information Modelling (BIM): Benefits for Small Scale Construction I...
Building Information Modelling (BIM): Benefits for Small Scale Construction I...
 

Similar to Supply Chain

Sc bim
Sc bimSc bim
Sc bimLam Yu
 
Cscm group report
Cscm  group reportCscm  group report
Cscm group reportlohwenjun
 
CSCM Bim group assignment.docx
CSCM Bim group assignment.docxCSCM Bim group assignment.docx
CSCM Bim group assignment.docxEst
 
Construction Supply Chain Management (Group Assignment) - BIM 7D
Construction Supply Chain Management (Group Assignment) - BIM 7DConstruction Supply Chain Management (Group Assignment) - BIM 7D
Construction Supply Chain Management (Group Assignment) - BIM 7DYee Len Wan
 
Cscm group assignment
Cscm group assignmentCscm group assignment
Cscm group assignmentjk tan
 
Bim in Construction Management
Bim in Construction ManagementBim in Construction Management
Bim in Construction ManagementMd Manzoor Akhtar
 
How BIM can Impact Structural Engineerings?
How BIM can Impact Structural Engineerings?How BIM can Impact Structural Engineerings?
How BIM can Impact Structural Engineerings?MarsBIM1
 
The top 3 benefits of bim in the construction industry
The top 3 benefits of bim in the construction industry The top 3 benefits of bim in the construction industry
The top 3 benefits of bim in the construction industry Agon Coordination
 
5 Powers of BIM that can change the face of a Renovation Project (2).pdf
5 Powers of BIM that can change the face of a Renovation Project (2).pdf5 Powers of BIM that can change the face of a Renovation Project (2).pdf
5 Powers of BIM that can change the face of a Renovation Project (2).pdfPratap Dhopte
 
IRJET- Application of 4D CAD BIM Technology in Construction Scheduling
IRJET- Application of 4D CAD BIM Technology in Construction SchedulingIRJET- Application of 4D CAD BIM Technology in Construction Scheduling
IRJET- Application of 4D CAD BIM Technology in Construction SchedulingIRJET Journal
 
Bim beyond construction project management
Bim beyond construction project managementBim beyond construction project management
Bim beyond construction project managementnibtedu
 
Construction industry content sample
Construction industry content sampleConstruction industry content sample
Construction industry content sampleTina Ingalls
 
BIM workflow for construction
BIM workflow for constructionBIM workflow for construction
BIM workflow for constructionCesare Caoduro
 
Exploring BIM Dimensions: 3D, 4D, 5D, 6D, 7D and 8D BIM
Exploring BIM Dimensions: 3D, 4D, 5D, 6D, 7D and 8D BIMExploring BIM Dimensions: 3D, 4D, 5D, 6D, 7D and 8D BIM
Exploring BIM Dimensions: 3D, 4D, 5D, 6D, 7D and 8D BIMChandresh Chudasama
 
Scan to BIM Overview: Your Complete Guide
Scan to BIM Overview: Your Complete GuideScan to BIM Overview: Your Complete Guide
Scan to BIM Overview: Your Complete GuideChandresh Chudasama
 
The Role of BIM in Modern Construction Projects
The Role of BIM in Modern Construction ProjectsThe Role of BIM in Modern Construction Projects
The Role of BIM in Modern Construction ProjectsTawwabKhan4
 

Similar to Supply Chain (20)

Sc bim
Sc bimSc bim
Sc bim
 
Cscm group report
Cscm  group reportCscm  group report
Cscm group report
 
CSCM Bim group assignment.docx
CSCM Bim group assignment.docxCSCM Bim group assignment.docx
CSCM Bim group assignment.docx
 
Construction Supply Chain Management (Group Assignment) - BIM 7D
Construction Supply Chain Management (Group Assignment) - BIM 7DConstruction Supply Chain Management (Group Assignment) - BIM 7D
Construction Supply Chain Management (Group Assignment) - BIM 7D
 
Cscm group assignment
Cscm group assignmentCscm group assignment
Cscm group assignment
 
Bim in Construction Management
Bim in Construction ManagementBim in Construction Management
Bim in Construction Management
 
Cscm group assignment
Cscm group assignmentCscm group assignment
Cscm group assignment
 
How BIM can Impact Structural Engineerings?
How BIM can Impact Structural Engineerings?How BIM can Impact Structural Engineerings?
How BIM can Impact Structural Engineerings?
 
The top 3 benefits of bim in the construction industry
The top 3 benefits of bim in the construction industry The top 3 benefits of bim in the construction industry
The top 3 benefits of bim in the construction industry
 
5 Powers of BIM that can change the face of a Renovation Project (2).pdf
5 Powers of BIM that can change the face of a Renovation Project (2).pdf5 Powers of BIM that can change the face of a Renovation Project (2).pdf
5 Powers of BIM that can change the face of a Renovation Project (2).pdf
 
IRJET- Application of 4D CAD BIM Technology in Construction Scheduling
IRJET- Application of 4D CAD BIM Technology in Construction SchedulingIRJET- Application of 4D CAD BIM Technology in Construction Scheduling
IRJET- Application of 4D CAD BIM Technology in Construction Scheduling
 
Bim beyond construction project management
Bim beyond construction project managementBim beyond construction project management
Bim beyond construction project management
 
Group 14 presentation.pptx
Group 14 presentation.pptxGroup 14 presentation.pptx
Group 14 presentation.pptx
 
3 d modeling using bim ppt
3 d modeling using bim ppt3 d modeling using bim ppt
3 d modeling using bim ppt
 
Construction industry content sample
Construction industry content sampleConstruction industry content sample
Construction industry content sample
 
What are the advantages of using point clouds in construction?
What are the advantages of using point clouds in construction?What are the advantages of using point clouds in construction?
What are the advantages of using point clouds in construction?
 
BIM workflow for construction
BIM workflow for constructionBIM workflow for construction
BIM workflow for construction
 
Exploring BIM Dimensions: 3D, 4D, 5D, 6D, 7D and 8D BIM
Exploring BIM Dimensions: 3D, 4D, 5D, 6D, 7D and 8D BIMExploring BIM Dimensions: 3D, 4D, 5D, 6D, 7D and 8D BIM
Exploring BIM Dimensions: 3D, 4D, 5D, 6D, 7D and 8D BIM
 
Scan to BIM Overview: Your Complete Guide
Scan to BIM Overview: Your Complete GuideScan to BIM Overview: Your Complete Guide
Scan to BIM Overview: Your Complete Guide
 
The Role of BIM in Modern Construction Projects
The Role of BIM in Modern Construction ProjectsThe Role of BIM in Modern Construction Projects
The Role of BIM in Modern Construction Projects
 

More from Wan Nee

Presentation 7-pp-final
Presentation 7-pp-finalPresentation 7-pp-final
Presentation 7-pp-finalWan Nee
 
Professional practice-1-1-1-autosaved (1)
Professional practice-1-1-1-autosaved (1)Professional practice-1-1-1-autosaved (1)
Professional practice-1-1-1-autosaved (1)Wan Nee
 
Structures final 20th june
Structures final 20th juneStructures final 20th june
Structures final 20th juneWan Nee
 
Eca presentation slide (group a)
Eca presentation slide (group a)Eca presentation slide (group a)
Eca presentation slide (group a)Wan Nee
 
Estimating final
Estimating  final Estimating  final
Estimating final Wan Nee
 
Seminar question
Seminar questionSeminar question
Seminar questionWan Nee
 
Estimating presentation
Estimating presentation Estimating presentation
Estimating presentation Wan Nee
 
Evaluation brief qsb2134 tender (1)
Evaluation brief qsb2134 tender (1)Evaluation brief qsb2134 tender (1)
Evaluation brief qsb2134 tender (1)Wan Nee
 
Estimating Assignment Brief
Estimating Assignment BriefEstimating Assignment Brief
Estimating Assignment BriefWan Nee
 
Estimating Assignment
Estimating AssignmentEstimating Assignment
Estimating AssignmentWan Nee
 
Supply chain
Supply chain  Supply chain
Supply chain Wan Nee
 
Supply chain
Supply chainSupply chain
Supply chainWan Nee
 
Management Science
Management Science Management Science
Management Science Wan Nee
 
Qsb 2413 group project august 2017
Qsb 2413 group project august 2017 Qsb 2413 group project august 2017
Qsb 2413 group project august 2017 Wan Nee
 
BS 2 PRESENTATION
BS 2 PRESENTATION BS 2 PRESENTATION
BS 2 PRESENTATION Wan Nee
 
CT 3 Group Assignment Presentation Slide
CT 3 Group Assignment Presentation SlideCT 3 Group Assignment Presentation Slide
CT 3 Group Assignment Presentation SlideWan Nee
 
CT3 Group Assignment Report
CT3 Group Assignment ReportCT3 Group Assignment Report
CT3 Group Assignment ReportWan Nee
 
Ct2 latest1-1 (3)
Ct2 latest1-1 (3)Ct2 latest1-1 (3)
Ct2 latest1-1 (3)Wan Nee
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORTWan Nee
 
INTEGRATED ASSIGNMENT - CT BM M
INTEGRATED ASSIGNMENT - CT BM MINTEGRATED ASSIGNMENT - CT BM M
INTEGRATED ASSIGNMENT - CT BM MWan Nee
 

More from Wan Nee (20)

Presentation 7-pp-final
Presentation 7-pp-finalPresentation 7-pp-final
Presentation 7-pp-final
 
Professional practice-1-1-1-autosaved (1)
Professional practice-1-1-1-autosaved (1)Professional practice-1-1-1-autosaved (1)
Professional practice-1-1-1-autosaved (1)
 
Structures final 20th june
Structures final 20th juneStructures final 20th june
Structures final 20th june
 
Eca presentation slide (group a)
Eca presentation slide (group a)Eca presentation slide (group a)
Eca presentation slide (group a)
 
Estimating final
Estimating  final Estimating  final
Estimating final
 
Seminar question
Seminar questionSeminar question
Seminar question
 
Estimating presentation
Estimating presentation Estimating presentation
Estimating presentation
 
Evaluation brief qsb2134 tender (1)
Evaluation brief qsb2134 tender (1)Evaluation brief qsb2134 tender (1)
Evaluation brief qsb2134 tender (1)
 
Estimating Assignment Brief
Estimating Assignment BriefEstimating Assignment Brief
Estimating Assignment Brief
 
Estimating Assignment
Estimating AssignmentEstimating Assignment
Estimating Assignment
 
Supply chain
Supply chain  Supply chain
Supply chain
 
Supply chain
Supply chainSupply chain
Supply chain
 
Management Science
Management Science Management Science
Management Science
 
Qsb 2413 group project august 2017
Qsb 2413 group project august 2017 Qsb 2413 group project august 2017
Qsb 2413 group project august 2017
 
BS 2 PRESENTATION
BS 2 PRESENTATION BS 2 PRESENTATION
BS 2 PRESENTATION
 
CT 3 Group Assignment Presentation Slide
CT 3 Group Assignment Presentation SlideCT 3 Group Assignment Presentation Slide
CT 3 Group Assignment Presentation Slide
 
CT3 Group Assignment Report
CT3 Group Assignment ReportCT3 Group Assignment Report
CT3 Group Assignment Report
 
Ct2 latest1-1 (3)
Ct2 latest1-1 (3)Ct2 latest1-1 (3)
Ct2 latest1-1 (3)
 
SITE VISIT REPORT
SITE VISIT REPORTSITE VISIT REPORT
SITE VISIT REPORT
 
INTEGRATED ASSIGNMENT - CT BM M
INTEGRATED ASSIGNMENT - CT BM MINTEGRATED ASSIGNMENT - CT BM M
INTEGRATED ASSIGNMENT - CT BM M
 

Recently uploaded

KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...jaredbarbolino94
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 

Recently uploaded (20)

KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...Historical philosophical, theoretical, and legal foundations of special and i...
Historical philosophical, theoretical, and legal foundations of special and i...
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 

Supply Chain

  • 1. GROUP MEMBERS: NA YONG YI 0324458 CHAI JIA ERN 0324653 GOH XINGXIN 0325587 TAN KAI XUAN 0325066 TEE WAN NEE 0325074 CHEAH MAN YEE 0324743 LECTURER: MS. TAY SHIR MEN SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOR OF QUANTITY SURVEYING (HONS) CONSTRUCTION OF SUPPLY CHAIN MANAGEMENT (MGT 60803) (GROUP ASSIGNMENT) BIM Building Information Modelling
  • 2. CONTENTS INTRODUCTION 1.1 BIM (BUILDING INFORMATION MODELLING) 1.2 BIM CYCLE DIMENSION IN BIM 2.1 ADVANTAGES OF 3D 3.1 ADVANTAGES OF 4D 4.1 ADVANTAGES OF 5D 5.1 ADVANTAGES OF 6D 6.1 ADVANTAGES OF 7D DISADVANTAGES CONCLUSION AND RECOMMENDATIONS 7.0 CONCLUSION 7.1 RECOMMENDATIONS REFERENCES 5.1 REFERENCES ADVANTAGES2.0 INTRODUCTION IN 3D 3.0 INTRODUCTION IN 4D 4.0 INTRODUCTION IN 5D 5.0 INTRODUCTION IN 6D 6.0 INTRODUCTION IN 7D 2.2 DISADVANTAGES OF 3D 3.2 DISADVANTAGES OF 4D 4.2 DISADVANTAGES OF 5D 5.2 DISADVANTAGES OF 6D 6.2 DISADVANTAGES OF 7D
  • 3. BIMBuilding Information Modelling Building Information Modeling (BIM) is a digital representation of physical and functional characteristics of a facility. It is an intelligent, model-based process for planning, designing, constructing, and managing various buildings and infrastructures. A BIM is a shared knowledge resource for information about a facility forming a reliable basis for decisions during its life-cycle; defined as existing from earliest conception to demolition. In another word, BIM is a process for creating and managing all of the information on a project – before, during and after construction. DESIGN PHASE CONSTRUCTION PHASE MANAGEMENT PHASE MAINTENANCE PHASE DATA COLLECTED FROM DIGITAL MODELS BIM model consists of the virtual equivalents of the actual building parts used to build a building. These elements have all the characteristics - both physical and logical - of their real counterparts. These intelligent elements are the digital prototype of the physical building architecture and structural elements that allow us to simulate the building and understand its behavior in a computer environment way before the actual construction starts. USED BY ALL CONSTRUCTION PARTNERS
  • 4. CONCEPTUAL DESIGN PROGRAMMING DETAILED DESIGN ANALYSIS DOCUMENTATION FABRICATION CONSTRUCTION CONSTRUCTION LOGISTICS OPERATION & MAINTENANCE DEMOLITION RENOVATION BIM Building Information Modelling C Y C L E The program can only be properly considered once awareness is gained of the design team’s BIM capabilities. If you have appointed a design team strong in BIM across the board, you can reduce the program time down significantly. In addition, through the use of phasing in software, contractors can program out the order of works much more efficiently. This is where the design process really starts, and it can be a very unstable or fluid process. All designers will work in the same model (database). This way, any coordination issues can be worked out in the design phase rather than interrupting the construction phase. This is where the magic really happens. The concept should be predominantly fixed and therefore it is time to start modelling. The majority of 3D modelling should have been completed. It is at this stage you will start extracting the information you require from it This is where we finish the design documents to a construction level. The type of contract put in place will determine who produces the documentation and to what level. This is what we refer to as shop drawings. All shop drawings are a product of the information given from BIM. At this stage there are often questions from contractors if they require more information to understand the design intent. BIM allows additional information to be extracted to easily answer design queries. The software will simulates the operation and maintenance. The structure will be tested through the simulation to see if it serves its intended purpose. The detailed look and feel of the intended architecture as well as Its functionality will be tested using the simulation. The building operations will be simulated over time and wear and tear of the construct will be noted. Buildings do have life cycles, and over time they will need renovation. This type of work is not as common in the BIM at present as a many of the buildings are so new. BIM is an excellent process to use for the design/ management of demolition works. Renovation can be simulated using the computer added design to allow the involved parties to understand the implication faced in case of any decision to renovate the construct based on the present design. Once the design has been finalized, the construction of the building can commence. The whole construction of the building is simulated using the software. The logistics of all the materials from the warehouse to the construction site to be placed to the proper location area in order for the construction to take place will also be calculated and decided upon through simulation.
  • 5. 3D BIM - The shared information model 3D models represent a physical body using a collection of points in 3D space, connected by various geometric entities such as triangles, lines, curved surfaces, etc. It is the most commonly known dimension, as it refers to the “visible” part of a BIM model. Being a collection of data (points and other information) BIM revolves around an integrated data model from which various stakeholders such as Architects, Civil Engineers, Structural Engineers, MEP System Engineers, Builders, Manufacturers and Project Owners can extract and generate views and information's according to their needs. 3D BIM's visualizations capabilities enables participants to not only see the building in three dimensions before ground is ever broken, but also to automatically update these views along the project life cycle, from earliest conception to demolition. SOFTWARE USED Sketch Up Blender Auto CAD RhinoBIM Autodesk Revit 3ds Max Maya ZBRUSH Infrawork 360 Softtech Spirit ARC+ x9 VisualARQMidas Design
  • 6. 3D BIM - The shared information model ADVANTAGES:  Improved visualization of the project &communication of design intent . It allows one to see a project in plan, elevation, section, and perspective simultaneously. This is important because it significantly improves coordination between drawings and reduces the potential for errors.  Reduce rework Visualisation of projects to enable greater understanding of all members of the team. For example, it is far easier to schedule scaffolding requirements looking at a 3D model than in 2D. . The impact of a change made to a floor plan is instantly available to review in section, elevation, and perspective views.  Disputes avoided It enhances the communication among the different team members of a project like design team, subcontractors, owners and others that leads to a significant development in the planning process of a project as they are more easy to understand on the features and ideas that are proposed. MAIN ADVANTAGE ABLE TO COMMUNICATE THE DESIGN INTENT  Improved multidisciplinary collaboration. Synchronization between different disciplines, such as architecture and structural engineering, is improved because the impact of one discipline’s work on another is immediately apparent. Complicated structures can be studied in section, instead of drawing sections manually. This increased coordination can greatly speed up the design process.
  • 7. DISADVANTAGES:  More work upfront in 3D BIM The implementation of 3D BIM require more effort at the outset of a project. When BIM is used, it is insufficient for a contractor to simply submit plans or drawing and begin to construct. The contractor team must first sit down with the design team to create a collaborative model.  High software cost The upfront cost for hardware, software, training, and implementation can be pretty hefty. This causes small and medium companies do not interested in implementing BIM and thus it may be a barrier to communicate with other parties.  Copyright Practical issues about BIM concerns the copyright and ownership of contributed designs. Where various different design elements produced by separate consultants are fed into a composite model, and then adapted, authorship will become blurred.  Corruption in transmission Electronically transmitted information becoming corrupted or altered is also a main concern in BIM. Such concern are not exclusive to BIM projects but because of their nature any such corruption or alternation will be compounded and could therefore have an enormous impact on the success of the project. 3D BIM - The shared information model
  • 8. 4D BIM - Scheduling 4D BIM refers to the intelligent linking of individual 3D CAD components or assemblies with time-related information. Time-related information for a particular element might include information on lead time, how long it takes to install or construct, the time needed to become operational, the sequence in which components should be installed, and dependencies on other areas of the project. The fourth dimension of BIM is used for construction site planning related activities. It is possible to visualize and to control the progress of the activities through the lifetime of the project. It allows construction planners to run simulations to assess how proposed design features will impact the construction schedule and workflow. With 4D BIM, planners can determine appropriate resource scheduling, identify potential bottlenecks, develop phasing plans, communicate and track milestones, and find opportunities to improve the schedule overall. 4D BIM provides methods for managing and visualizing site status information, change impacts as well as supporting communication in various situations such as informing site staff or warning about risks. SOFTWARE USED Vico Software Synchro Bentley Navigator ITwo Naviswork Manage Gest Mideplan Primavera P6 Gestproject MS Project TCQ
  • 9. 4D BIM - Scheduling ADVANTAGES  More effective& efficient explanation and communication of schedule It provides Identification of problems not visible via traditional schedules. Builders and manufacturers can optimize their construction activities and team coordination.  Production of more rigorous schedules 4D BIM allow to analyse the schedule to asses feasibility of execution.  Improved control over conflict detection The complexity of changes occurring during the course of a construction project. 4D BIM provides methods for managing and visualizing site status information, change impacts as well as supporting communication in various situations such as informing site staff or warning about risks. MAIN ADVANTAGE FOLLOW UP TOO THE SCHEDULE IN CASE OF PROJECT CHANGES. DISADVANTAGES:  Does not support procurement & offsite activities 4D models do not support offsite activities such as the submittal – approval and the procurement cycles, offsite work such as fabrication or activities like coordination etc. These important and often critical activities must be carried in the conventional schedule but cannot be displayed visually.  Time consuming for transmission Development of 4D model from 2D documents is timely and challenging. It also requires highly skilled and trained staff to execute the process which is short supply and expensive to bear.  Disruptive in construction Although one of the advantages of using a BIM model is that changes can be made quickly, BIM can disrupt the general procurement and construction process when ordering items that require a long lead time.
  • 10. 5D BIM - Cost Drawing on the components of the information model being able to extract accurate cost information is what's at the heart of 5D BIM. QUANTITY TAKEOFFS To determine a project's construction cost and requirements, contractors traditionally perform material ‘take-offs’ manually, a process fraught with the potential for error. With BIM, the model includes information that allows a contractor to accurately and rapidly generate an array of essential estimating information, such as materials quantities and costs, size and area estimates, and productivity projections. As changes are made, estimating information automatically adjusts, allowing greater contractor productivity. ‘REAL TIME’ COST ESTIMATING In a BIM model cost data can be added to each object enabling the model to automatically calculate a rough estimate of material costs. This provides a valuable tool for designers, enabling them to conduct value engineering thereby reaching an overall cost for the development. SOFTWARE USED Vico Software Nevaris Bentley ConstructSim Presto Cost‐it GLODON BIM 5D PriMus BIM constructSIM DESTINI Estimator TCQ 2000 BIM
  • 11. 5D BIM - Cost ADVANTAGES  A greater accuracy and predictability of project's estimates. It allows participants to visualize the progress of their activities and related costs over time. The costs here include the purchasing, installing, running, maintenance and renewal costs. Formulas drive costs on each building system based on the specific design, materials, site conditions, phasing and other parameters according to the owner’s timeline.  Save time in calculating cost It save times and patience for calculations pertaining to the entire project cost. Thus, whenever a single component is replaced or changed, the direct impact on the cost gets calculated automatically.  Reliable, accurate updates in real time drive efficiency Data is provided in real time as the model is developed or changed. Alternative concepts can be easily explored; while owner and project team can see the cost and other data unfold instantaneously. This drastically shortens design and estimation cycle time. All major project stakeholders can visualize the end product and understand exactly what is included in the budget. MAIN ADVANTAGE COST CHANGES AUTOMATICALLY IN CASE OF PROJECT CHANGES. DISADVANTAGES:  Lack of electronic standard for coding Lack of an electronic standard for coding BIM software to Standard Methods of Measurement limits the potential of 5D BIM. Although BIM assisted estimating tools can generate large quantities of construction items in order to efficiently produce cost estimates, the extracted quantities have a lack of understanding of construction methods, which reduces the accuracy of estimates.  No software for full function of BIM There are currently no single software available that can perform all functions that BIM is capable of enabling. Therefore incorporating 5D BIM the team also had to assist in several projects that were using for 3D clash detection and 4D simulation purposes.  Complicated to control The 5D software was described as robust but complicated to use. The software program that enable 5D-BIM require a high level of technological expertise as well as expertise with construction processes.
  • 12. 6D BIM - Sustainability SOFTWARE USED Vasari Autodesk Green Building Studio Bentley Hevacomp Trimble Sefaira The sixth dimension of BIM is used for energy assessment during the design phase and operational phase. 6D BIM facilitates the implementation of energy analysis for buildings. 6D BIM involves the inclusion of information to support facilities management and operation to drive better business outcomes. This data might include information on the manufacturer of a component, its installation date, required maintenance and details of how the item should be configured and operated for optimal performance, energy performance, along with lifespan and decommissioning data. An efficient data collection from installed sensors enables to better understand the building’s performance and define a strategy aiming to optimize the building’s energy consumption. In effect, designers can explore a whole range of permutations across the lifecycle of a built assets and quickly get an understanding of impacts including costs. Design Builder Software Open Studio Ecotect Analysis
  • 13. 6D BIM - Sustainability  Result in more complete and accurate energy It also allows for measurement and verification during building occupation, and improved processes for gathering lessons learned in high performance facilities. ADVANTAGES  Overall reduction in energy consumption Helps facility managers to bring down utility bills and operate a building in the most efficient manner, ensuring highest level of occupant comfort. MAIN ADVANTAGE HELPS TO PERFORM ENERGY CONSUMPTION ANALYSIS  Support decision making At delivery phase, it enables design teams to consider their impact of their proposals over a built asset’s lifecycle, simulating outcomes and anticipated costs. But the ultimate value, lies in the use of that data to support the operational phase.  Support the operation of the built asset At handover, project teams can pass their complete data set (known as an Asset Information Model or AIM) over to the end-user. The digital model offers them a more controlled, accessible and easily navigable way of managing their information.
  • 14. 6D BIM - Sustainability  Restriction of sharing information Do not allow for knowledge sharing among energy managers across all public departments. The restriction of sharing information unable to add value to the used system which will affect the sustainability of the buildings, such as preservation of historical building. DISADVANTAGES  Fragmented It is fragmented which is created by different teams with different objectives and stored in different system. Therefore, this identifies that lack of integration of information is the barrier for energy managers in using BIM 6D.  Cost intensive & not easy to use This specialized training is necessary to use them. Other than that, a contractor may need to upgrade its computer system to effectively use the BIM software.  Not yet universally used 6D Bim is not yet universally used among construction professionals. There is always the possibility that one of the subcontractors may not use 6D Bim and may not be able to use your models. It is also critical for operators and facility management to read and study the models using the BIM software, since they do not undergo significant training. Problems may occur if the drawing design and the related information are precise and accurate.
  • 15. 7D BIM - Facility Management SOFTWARE USED Autodesk Building ops Asset Wise ArchiFM Tekla BIM Sight The seventh dimension is used to extract and collect relevant information related to the operation and maintenance status of the facility throughout its life cycle. 7D is the main field where BIM model’s data can definitely make the difference. Starting a Facility Management program based on reliable extracted information from an as-built BIM provide the most effective solutions for the management of a building. Besides, tracking and maintaining lifecycle information about the building structure as well as the equipment serving the to plan and schedule a program of maintenance activities that will improve building performance, reduce repairs, and reduce overall maintenance costs. GestProject YouBim Archibus Ecodomus
  • 16. 7D BIM - Facility Management ADVANTAGES MAIN ADVANTAGE MANAGE ASSETS LIFE CYCLE.  Allows participants to extract and track relevant asset data (Such as component status, specifications, maintenance/operation manuals, warranty data etc. for easier and quicker parts replacements). It is an approach to the facility management process not only improves the whole process, but also improves the quality of services.  Easier and quicker parts replacements Optimized compliance and a streamlined asset life cycle management over time. 7D BIM provides processes for managing subcontractor/supplier data and facility component through the entire facility life cycle.  Integrating BIM with 7D CAD simulation models optimizes asset management from design to demolition DISADVANTAGES:  Requiring updated hardware and software Modelling is more concern on post-construction and project life cycle where frequent updates are inserted into the modelling which will result in the difficulty in managing additional volume and complexity of digital information. This will require an upgrade in hardware and software to manage the information which will lead to increase in cost.  Training needed Training will also need to be provided to facilities managers to understand and operate 7D BIM which will incur cost. Interoperability between software applications by different party and different point of time will cause large number of data exchange and updating takes place. This is due to individual and firms will have their own preferred system, software application and processes.
  • 17. Conclusion In conclusion, BIM can help quantity surveyors to speed up the estimating process compared to the traditional method that many of the surveyors are still using and as technology evolves, the QS are forced to evolve as well so that they would not be left out by the society. On the other hand, the foundation, which is also the traditional method is also important this is so that all the surveyors have a strong foundation of estimating. Furthermore, from this report, we know that the BIM requires a lot of upfront calibration between the QS and also designer, such as, inputting the correct coding, zoning and ensuring that the building is drawn as it should be built. Even after all the upfront work QS have to interrogate, interpret and also extract the quantities and align with standard methods of measurement. With the development of technology like BIM, the responsibilities of the professionals are starting to shift. Not only that, BIM includes a series of cost management functions that could change the processes of cost management of construction projects. This allows the Quantity Surveyor to delve deeper into different parts of the cost management process. In addition, there are also some of the challenges that are faced by the surveyors while using the BIM which are the advancement of technology which can be also seen from the few decades behind which transforms from using the ‘paper’ system to initial simple Excel spreadsheet to BIM. Next, it is the reluctance of designers to allow 3D models to be used where the designers are reluctant to issue 3D models that are not substantially complete to QS. The third one would be new terminology, as we the technologies have evolved, it also means that there are new terminologies that would be used and QS needs to understand and familiarize the implications of each terms and how this new terminology can assist them in delivering their traditional services.
  • 18. FLEXIBILITY CHANGES Recommendation Ability to read and import different file format. The file format that is able currently is only the BIM file and a computer or laptop without the software, it can’t be opened and view it. Therefore, if the file can be saved as PDF to be sent to clients it would ease the QS more. Able to allow project team members to collaborate, access or retrieve the information easily and securely. This would ease the project team to finish up the task fast and efficiently. Not only that, if the BIM software can track changes, track errors, record variations and perform checks, it would also add a point into helping to finish up the work as fast as possible. Allowing users the flexibility to add build-up rates or refer rates from cost libraries or previous projects. This can make the Bills Of Quantities to be more accurate with the updated cost of the materials in the industry. ABILITY TO READ AND IMPORT DIFFERENT FILE FORMAT ABLE TO ALLOW PROJECT TEAM MENBERS TO COLLABORATE
  • 19. References Anon, (2017). [online] https://www.linkedin.com/pulse/20140822053129-66002134-benefits-of-4d-bim-in-project-phasing/ BIMPanzee. (2017). BIM 3D,4D, 5D, 6D & 7D. [online] http://www.bimpanzee.com/bim-3d-4d--5d--6d---7d.html GenieBelt (2017). 5D BIM: How It Will Help the Construction Industry - GenieBelt Blog. [online] GenieBelt Blog. https://geniebelt.com/blog/5d-bim-in-construction BIMestiMate. (2017). The theory of evolution. BIM 3D … 7D … - BIMestiMate. [online] http://bimestimate.eu/en/the-theory-of-evolution-bim-3d-7d/ SlideOnline.com. (2017). Advantages offered by 3D, 4D, 5D and 6D BIM modeling. [online] http://slideonline.com/presentation/29916-advantages-offered-by-3d-4d-5d-and-6d-bim-modeling Trivedi, G. and Trivedi, G. (2017). Benefits of 4D/5D BIM to General Contractors across Construction Projects | TrueCADD. [online] Truecadd.com. http://www.truecadd.com/news/benefits-of-4d-5d-bim-to-general-contractors-across-construction-projects Anon, (2017). [online] https://www.linkedin.com/pulse/bim-3d-7d-implementation-hani-elsafadi/ Theb1m.com. (2017). What is 6D BIM?. [online] http://www.theb1m.com/video/what-is-6d-bim Bimsg.org. (2017). BIM for Quantity Surveying | BIM@SG. [online] http://bimsg.org/resources/other-software-resources/bim-for-qs/ Sourceable - Construction . Design . Engineering . Property. (2017). BIM and the Quantity Surveyor. [online] https://sourceable.net/bim-and-the-quantity-surveyor/ Anon, (2017). [online] https://www.linkedin.com/pulse/bim-its-impact-future-role-quantity-surveyor-himani-shah FM Systems. (2017). The Benefits of Lifecycle BIM for Facility Management. [online] https://fmsystems.com/blog/the-benefits-of-lifecycle-bim-for-facility-management/ www.vackerglobal.com. (2017). Building Information Modelling (BIM) UAE, Qatar, KSA | VackerGlobal. [online] https://www.vackerglobal.com/divisions/automation/building-information-modelling-bim/ BSBG | Brewer Smith Brewer Group. (2017). The BIM Cycle | BSBG | Brewer Smith Brewer Group. [online] http://bsbgltd.com/blog/the-bim-cycle/ Anon, (2017). [online] https://www.linkedin.com/pulse/bim-3d-7d-implementation-hani-elsafad AXD. (2017). All the BIM dimensions. [online] http://www.axdstudio.com/portfolio/all-the-bim-dimensions/ BIMestiMate. (2017). The theory of evolution. BIM 3D … 7D … - BIMestiMate. [online] http://bimestimate.eu/en/the-theory-of-evolution-bim-3d-7d/ McPartland, R., McPartland, R., McPartland, R., McPartland, R. and McPartland, R. (2017). BIM dimensions - 3D, 4D, 5D, 6D BIM explained. [online] NBS. https://www.thenbs.com/knowledge/bim-dimensions-3d-4d-5d-6d-bim-explained Sage Advice US. (2017). Defining the dimensions of BIM | Sage Advice US. [online] https://www.sage.com/en-us/blog/defining-dimensions-bim/#
  • 20. References Out-law.com. (2017). Building Information Modelling. [online] https://www.out-law.com/en/topics/projects--construction/projects-and-procurement/building-information- modelling/ Anon, (2017). [online] http://www.bimpanzee.com/bim-3d-4d--5d--6d---7d.html 5D-BIM: A CASE STUDY OF AN IMPLEMENTATION STRATEGY IN THE CONSTRUCTION INDUSTY. (2014). [online] http://www.iaarc.org/publications/fulltext/isarc2014_submission_112.pdf Smith, P. (2016). Project Cost Management with 5D BIM. Project Cost Management with 5D BIM. [online] http://www.sciencedirect.com/science/article/pii/S1877042816308655 Kehily, D., & Underwood, J. (2017). Embedding life cycle costing in 5D BIM. [online] http://www.itcon.org/paper/2017/8 Carlin, E. (2010). The Legal Risks of Building Information Modeling (BIM). [online] https://www.constructionlawnowblog.com/design-and-technology/the-legal-risks-of-building- information-modeling-bim/ Phuong Dang, D., & Tarar, M. (2012). IMPACT OF 4D MODELING ON CONSTRUCTION PLANNING PROCESS. [online] http://publications.lib.chalmers.se/records/fulltext/161015.pdf