HAMILTON INTERNATIONAL
PROJECT LIFE CYCLE – BUILD ONLY (MAJOR PROJECTS)
Pre-Construction Phase (HI.BO.PC.01)
Contract Setting Up Planning Phase Engineering and Procurement
COMMERCIAL
BUSINESS
DEVELOPMENT
FINANCEOPERATIONSCLIENT
Price agreed.
Award of contract /
LOI / LOA
“Advice of New
Contract”
(HI.QF.05.01)
Conduct and minute
Tender Handover
Meeting (HI.QF.05.02).
Handover the “Contract
Conditions Summary”
(HI.QF.04.19) to Q.S and
Contract Manager.
Prepare the “Construction Preliminary Budget”
(HI.QF.04.10)
Obtain Client
document and
NOC for authority
approvals.
Commercial
Engineering
Submittals:
1. RFI (HI.QF.05.07)
2. Shop drawings
3. Material Submittal
4. Method Statement
5. HSE
6. Quality Plan
Procurement
Operations
Place order, as per the
“Purchasing Procedure”
(HI.QAP.06).
Link to
BO.EP.01
Prepare:
1. Tender Event Schedule (HI.QF.04.05)
2. Subcontractor /Material Procurement Log”
(HI.QF.04.06) (Identify long lead items and bulk
items.).
3. “Material Submission Tracking Log”
(HI.QF.04.08)
PROJECT EXECUTION PLANPrepare the “Project
Invoicing / Valuation
Protocol” (HI.QF.04.21)
and attach it to the
minutes of the Client KO
meeting.
Conduct and minute Client
Kick Off Meeting, based on
standard agenda,
HI.QF.05.05.
Conduct and minute the
Internal Kick Off Meeting,
based on the standard
agenda, (HI.QF.05.03).
Prepare the “Cash Flow
and Valuation Schedule”
(HI.QF.04.11) and input
the “Valuation Tracking
Log” (HI.QF.04.13) with
the forecast valuations.
Populate Project Specific
Cost Report template.
Prepare Preliminary Cash
Flow based on the tender
program, for bank bond
application.
Application for municipality
approval.
Receipt of municipality approval.
Raise “Invoice
Request Form”
(HI.QF.04.12) for
advance payment as
per “Invoicing /
Collections Procedure”
(HI.QAP.04.01)
Raise Invoice for
advance payment as
per “Invoicing /
Collections Procedure”
(HI.QAP.04.01)
Obtain the APG,
Performance Bond and
Insurance.
Apply for APG,
Performance bond and
Insurance (where
applicable). Agree
bond wording with
client and bank.
Arrange for the “Notice of
Assignment” (If required)
Release of advance
payment. Client approval
Review cost report
and agree on monthly
reporting.
Prepare “Project Execution Plan”:
1. Project Directory
2. Tender Program
3. Contract Program
4. Target Program
5. Critical Milestone Schedule
6. Authority Approval / Fit out Permit
7. Site Survey Report
8. Shop drawing Submittal Schedule
(HI.QF.05.18)
9. RFI Log (HI.QF.05.08)
10. Contract Manager Daily Diary Tracker
11. Construction Managers Daily Diary Tracker.
12. Labour Histogram
13. Quality Plan
14. H&S Plan
15. Contract Documentation
16. Site Office Set-up Document / Pack.
Possiblythe2meetingscanmerge.
Approved
Tender all project specific
material / sub-contractors.
HAMILTON INTERNATIONAL
PROJECT LIFE CYCLE – BUILD ONLY (MAJOR PROJECTS)
Execution Phase and Defects Liability Period Phase (HI.BO.EP.01)
Project Execution Phase Defects Liability Period
CLIENTFINANCEOPERATIONSCOMMERCIAL
Maintain the “Contract Managers
Daily Diary Tracker” and update
“Critical Milestone Schedule”.
Submit to the Operations Director on
a weekly basis.
Conduct weekly the “Internal
Project Review Meeting”
(HI.QF.05.04).
Submit “Weekly
Progress
Reports”
(HI.QF.05.38) to
client, signed off
by the Operations
Director.
Mobilisation
Raise Material Request from site.
Link
BO.EP.01
Identify all project specific items and place order, as per the “Purchasing Procedure” (HI.QAP.06).
Raise Valuations as per
“Project Invoicing/
Valuation Protocol”
(HI.QF.04.)
Client
certification
Release
payments against
invoice.
Approved
Update “Project
Critical Tasks
Log”
Issue “Taking
Over Certificate”
to client.
1 month prior to the
completion of DLP,
notify the client of
the completion of
DLP.
Issue Final Taking
Over Certificate.
Prepare:
1. O&M Manual
2. As build drawings
3. Close out authority
approvals.
Raise “Invoice Request
Form” (HI.QF.04.12).
Issue an invoice.
Prepare “Monthly Cost
Reports” (HI.QF.04.15).
Update the “Cash Flow
and Valuation
Schedule”
(HI.QF.04.11).
HI final snagging.
Final inspection done
before handover, using
the “Pre handover
Prompt Sheet”
(HI.QF.05.41) as a
checklist.
INTERNAL PROGRESS REPORTING
Identify, prepare and file the project
close out documentation.
Review “Monthly Cost
Reports”
(HI.QF.04.15).
Update the “Project
Critical Tasks Log” and
inform Document Control
to move the Project folder
from the Completed folder
to Archived folder.
Agree Final
Account with
client.
INVOICING / COLLECTIONS PROCEDURE (HI.QAP.04.01) *
“Invoicing /
Collections
Procedure”
(HI.QAP.04.01)
“Invoicing /
Collections
Procedure”
(HI.QAP.04.01)
Snagging process
* Update the “Valuation Tracking Log” (HI.QF.04.13) at each stage of the “Invoicing / Collections Procedure” (HI.QAP.04.01)
12 months period
NOTE: Variations shall be controlled as per the “Contracts Management / Process Control Procedure” (HI.QAP.05).

More Related Content

What's hot

Pengantar pelaksanaan anggaran
Pengantar pelaksanaan anggaranPengantar pelaksanaan anggaran
Pengantar pelaksanaan anggaranTatang Suwandi
 
Ebook presentasi pengantar manajemen proyek
Ebook   presentasi pengantar manajemen proyekEbook   presentasi pengantar manajemen proyek
Ebook presentasi pengantar manajemen proyekhandasah
 
Mitigasi Risiko dan Pengendalian Kontrak PBJ
Mitigasi Risiko dan Pengendalian Kontrak PBJMitigasi Risiko dan Pengendalian Kontrak PBJ
Mitigasi Risiko dan Pengendalian Kontrak PBJKhalid Mustafa
 
04. Konsep Perancangan Sistem Produksi, Teknik Tata Cara Kerja, dan Peta Kerja
04. Konsep Perancangan Sistem Produksi, Teknik Tata Cara Kerja, dan Peta Kerja04. Konsep Perancangan Sistem Produksi, Teknik Tata Cara Kerja, dan Peta Kerja
04. Konsep Perancangan Sistem Produksi, Teknik Tata Cara Kerja, dan Peta KerjaMercu Buana University
 
Form HIRADC (2).docx
Form HIRADC (2).docxForm HIRADC (2).docx
Form HIRADC (2).docxDangkosAja
 
Peralatan dan perlengkapan_kerja
Peralatan dan perlengkapan_kerjaPeralatan dan perlengkapan_kerja
Peralatan dan perlengkapan_kerjaEko Supriyadi
 
Manajemen proyek konstruksi
Manajemen proyek konstruksiManajemen proyek konstruksi
Manajemen proyek konstruksiNurul Angreliany
 
Materi 01 Pengantar Pengadaan Barang/Jasa
Materi 01 Pengantar Pengadaan Barang/JasaMateri 01 Pengantar Pengadaan Barang/Jasa
Materi 01 Pengantar Pengadaan Barang/JasaMassaputro Delly TP
 
مقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةمقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةM Maged Hegazy, LLM, MBA, CCP, P3O
 
Contracts bidding and negotiation
Contracts bidding and negotiationContracts bidding and negotiation
Contracts bidding and negotiationSamir ALI
 
Multimoda & inter. freight forwarding presentation
Multimoda & inter. freight forwarding presentationMultimoda & inter. freight forwarding presentation
Multimoda & inter. freight forwarding presentationsyalindrihs
 
Pembekalan magang blu blud
Pembekalan magang blu bludPembekalan magang blu blud
Pembekalan magang blu bludsridermawani
 
ADMINISTRASI PROYEK.pptx
ADMINISTRASI PROYEK.pptxADMINISTRASI PROYEK.pptx
ADMINISTRASI PROYEK.pptxsahramaulidar1
 
Contoh metode pelaksanaan rehab jalan
Contoh metode pelaksanaan rehab jalanContoh metode pelaksanaan rehab jalan
Contoh metode pelaksanaan rehab jalanpt baranugraha
 
Spesifikasi teknis jembatan
Spesifikasi teknis jembatanSpesifikasi teknis jembatan
Spesifikasi teknis jembatanDwie Cahyono
 

What's hot (20)

Pengantar pelaksanaan anggaran
Pengantar pelaksanaan anggaranPengantar pelaksanaan anggaran
Pengantar pelaksanaan anggaran
 
Ebook presentasi pengantar manajemen proyek
Ebook   presentasi pengantar manajemen proyekEbook   presentasi pengantar manajemen proyek
Ebook presentasi pengantar manajemen proyek
 
Виконавче провадження в Україні
Виконавче провадження в УкраїніВиконавче провадження в Україні
Виконавче провадження в Україні
 
Mitigasi Risiko dan Pengendalian Kontrak PBJ
Mitigasi Risiko dan Pengendalian Kontrak PBJMitigasi Risiko dan Pengendalian Kontrak PBJ
Mitigasi Risiko dan Pengendalian Kontrak PBJ
 
18.K3 Mekanik.ppt
18.K3 Mekanik.ppt18.K3 Mekanik.ppt
18.K3 Mekanik.ppt
 
04. Konsep Perancangan Sistem Produksi, Teknik Tata Cara Kerja, dan Peta Kerja
04. Konsep Perancangan Sistem Produksi, Teknik Tata Cara Kerja, dan Peta Kerja04. Konsep Perancangan Sistem Produksi, Teknik Tata Cara Kerja, dan Peta Kerja
04. Konsep Perancangan Sistem Produksi, Teknik Tata Cara Kerja, dan Peta Kerja
 
Form HIRADC (2).docx
Form HIRADC (2).docxForm HIRADC (2).docx
Form HIRADC (2).docx
 
Peralatan dan perlengkapan_kerja
Peralatan dan perlengkapan_kerjaPeralatan dan perlengkapan_kerja
Peralatan dan perlengkapan_kerja
 
Manajemen proyek konstruksi
Manajemen proyek konstruksiManajemen proyek konstruksi
Manajemen proyek konstruksi
 
Perencanaan k3 dalam proyek
Perencanaan k3 dalam proyekPerencanaan k3 dalam proyek
Perencanaan k3 dalam proyek
 
Materi 01 Pengantar Pengadaan Barang/Jasa
Materi 01 Pengantar Pengadaan Barang/JasaMateri 01 Pengantar Pengadaan Barang/Jasa
Materi 01 Pengantar Pengadaan Barang/Jasa
 
مقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةمقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافية
 
Contracts bidding and negotiation
Contracts bidding and negotiationContracts bidding and negotiation
Contracts bidding and negotiation
 
Multimoda & inter. freight forwarding presentation
Multimoda & inter. freight forwarding presentationMultimoda & inter. freight forwarding presentation
Multimoda & inter. freight forwarding presentation
 
Pembekalan magang blu blud
Pembekalan magang blu bludPembekalan magang blu blud
Pembekalan magang blu blud
 
ADMINISTRASI PROYEK.pptx
ADMINISTRASI PROYEK.pptxADMINISTRASI PROYEK.pptx
ADMINISTRASI PROYEK.pptx
 
Contoh metode pelaksanaan rehab jalan
Contoh metode pelaksanaan rehab jalanContoh metode pelaksanaan rehab jalan
Contoh metode pelaksanaan rehab jalan
 
Contractor safety management system
Contractor safety  management systemContractor safety  management system
Contractor safety management system
 
Mevsimlik sezonluk is sozlesmesi ornegi mavi yaka
Mevsimlik sezonluk is sozlesmesi ornegi   mavi yakaMevsimlik sezonluk is sozlesmesi ornegi   mavi yaka
Mevsimlik sezonluk is sozlesmesi ornegi mavi yaka
 
Spesifikasi teknis jembatan
Spesifikasi teknis jembatanSpesifikasi teknis jembatan
Spesifikasi teknis jembatan
 

Similar to Project Flow Chart-BO Major Projects FINAL (with Hyperlinks)

Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
Job Profile as a Planning Engineer
Job Profile as a Planning EngineerJob Profile as a Planning Engineer
Job Profile as a Planning EngineerMD TAUSIF ASLAM
 
IFAD Procurement Guidelines revised 2008
IFAD Procurement Guidelines revised 2008IFAD Procurement Guidelines revised 2008
IFAD Procurement Guidelines revised 2008IFAD Vietnam
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
LECTURE - Planning.ppt
LECTURE - Planning.pptLECTURE - Planning.ppt
LECTURE - Planning.pptshinawaro27
 
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...yusuf699644
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTSHossamNegidaPMPRMPPS
 
projectclosure-rutik.pptx project management
projectclosure-rutik.pptx project managementprojectclosure-rutik.pptx project management
projectclosure-rutik.pptx project managementakashdhewale87
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.pptTecnicoItca
 
PROJECT 2Construction of a Medical ClinicMany people were severe.pdf
PROJECT 2Construction of a Medical ClinicMany people were severe.pdfPROJECT 2Construction of a Medical ClinicMany people were severe.pdf
PROJECT 2Construction of a Medical ClinicMany people were severe.pdfabdulrahamanbags
 
MBA 572Project Management WorksheetsReprinted from The Project.docx
MBA 572Project Management WorksheetsReprinted from The Project.docxMBA 572Project Management WorksheetsReprinted from The Project.docx
MBA 572Project Management WorksheetsReprinted from The Project.docxandreecapon
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017DarrenTofu
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo
 
Procurement Expediting _ Materi Training SCM
Procurement Expediting _ Materi Training SCMProcurement Expediting _ Materi Training SCM
Procurement Expediting _ Materi Training SCMKanaidi ken
 

Similar to Project Flow Chart-BO Major Projects FINAL (with Hyperlinks) (20)

Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Job Profile as a Planning Engineer
Job Profile as a Planning EngineerJob Profile as a Planning Engineer
Job Profile as a Planning Engineer
 
Maaden Exp.
Maaden Exp.Maaden Exp.
Maaden Exp.
 
Pc iv-new
Pc iv-newPc iv-new
Pc iv-new
 
IFAD Procurement Guidelines revised 2008
IFAD Procurement Guidelines revised 2008IFAD Procurement Guidelines revised 2008
IFAD Procurement Guidelines revised 2008
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
LECTURE - Planning.ppt
LECTURE - Planning.pptLECTURE - Planning.ppt
LECTURE - Planning.ppt
 
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
dokumen.tips_installation-of-api-610-centrifugal-pumps-to-achieve-a-8-api-686...
 
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
 
projectclosure-rutik.pptx project management
projectclosure-rutik.pptx project managementprojectclosure-rutik.pptx project management
projectclosure-rutik.pptx project management
 
Construction process
Construction processConstruction process
Construction process
 
08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt08-Project-Control-ppt.ppt
08-Project-Control-ppt.ppt
 
PROJECT 2Construction of a Medical ClinicMany people were severe.pdf
PROJECT 2Construction of a Medical ClinicMany people were severe.pdfPROJECT 2Construction of a Medical ClinicMany people were severe.pdf
PROJECT 2Construction of a Medical ClinicMany people were severe.pdf
 
MBA 572Project Management WorksheetsReprinted from The Project.docx
MBA 572Project Management WorksheetsReprinted from The Project.docxMBA 572Project Management WorksheetsReprinted from The Project.docx
MBA 572Project Management WorksheetsReprinted from The Project.docx
 
CV_Saifullah Khalid-
CV_Saifullah Khalid-CV_Saifullah Khalid-
CV_Saifullah Khalid-
 
API 610 pumps .pdf
API 610 pumps .pdfAPI 610 pumps .pdf
API 610 pumps .pdf
 
Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017Construction lawprint-final-update-21112017
Construction lawprint-final-update-21112017
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
RIBA Revit.pdf
RIBA Revit.pdfRIBA Revit.pdf
RIBA Revit.pdf
 
Procurement Expediting _ Materi Training SCM
Procurement Expediting _ Materi Training SCMProcurement Expediting _ Materi Training SCM
Procurement Expediting _ Materi Training SCM
 

Project Flow Chart-BO Major Projects FINAL (with Hyperlinks)

  • 1. HAMILTON INTERNATIONAL PROJECT LIFE CYCLE – BUILD ONLY (MAJOR PROJECTS) Pre-Construction Phase (HI.BO.PC.01) Contract Setting Up Planning Phase Engineering and Procurement COMMERCIAL BUSINESS DEVELOPMENT FINANCEOPERATIONSCLIENT Price agreed. Award of contract / LOI / LOA “Advice of New Contract” (HI.QF.05.01) Conduct and minute Tender Handover Meeting (HI.QF.05.02). Handover the “Contract Conditions Summary” (HI.QF.04.19) to Q.S and Contract Manager. Prepare the “Construction Preliminary Budget” (HI.QF.04.10) Obtain Client document and NOC for authority approvals. Commercial Engineering Submittals: 1. RFI (HI.QF.05.07) 2. Shop drawings 3. Material Submittal 4. Method Statement 5. HSE 6. Quality Plan Procurement Operations Place order, as per the “Purchasing Procedure” (HI.QAP.06). Link to BO.EP.01 Prepare: 1. Tender Event Schedule (HI.QF.04.05) 2. Subcontractor /Material Procurement Log” (HI.QF.04.06) (Identify long lead items and bulk items.). 3. “Material Submission Tracking Log” (HI.QF.04.08) PROJECT EXECUTION PLANPrepare the “Project Invoicing / Valuation Protocol” (HI.QF.04.21) and attach it to the minutes of the Client KO meeting. Conduct and minute Client Kick Off Meeting, based on standard agenda, HI.QF.05.05. Conduct and minute the Internal Kick Off Meeting, based on the standard agenda, (HI.QF.05.03). Prepare the “Cash Flow and Valuation Schedule” (HI.QF.04.11) and input the “Valuation Tracking Log” (HI.QF.04.13) with the forecast valuations. Populate Project Specific Cost Report template. Prepare Preliminary Cash Flow based on the tender program, for bank bond application. Application for municipality approval. Receipt of municipality approval. Raise “Invoice Request Form” (HI.QF.04.12) for advance payment as per “Invoicing / Collections Procedure” (HI.QAP.04.01) Raise Invoice for advance payment as per “Invoicing / Collections Procedure” (HI.QAP.04.01) Obtain the APG, Performance Bond and Insurance. Apply for APG, Performance bond and Insurance (where applicable). Agree bond wording with client and bank. Arrange for the “Notice of Assignment” (If required) Release of advance payment. Client approval Review cost report and agree on monthly reporting. Prepare “Project Execution Plan”: 1. Project Directory 2. Tender Program 3. Contract Program 4. Target Program 5. Critical Milestone Schedule 6. Authority Approval / Fit out Permit 7. Site Survey Report 8. Shop drawing Submittal Schedule (HI.QF.05.18) 9. RFI Log (HI.QF.05.08) 10. Contract Manager Daily Diary Tracker 11. Construction Managers Daily Diary Tracker. 12. Labour Histogram 13. Quality Plan 14. H&S Plan 15. Contract Documentation 16. Site Office Set-up Document / Pack. Possiblythe2meetingscanmerge. Approved Tender all project specific material / sub-contractors.
  • 2. HAMILTON INTERNATIONAL PROJECT LIFE CYCLE – BUILD ONLY (MAJOR PROJECTS) Execution Phase and Defects Liability Period Phase (HI.BO.EP.01) Project Execution Phase Defects Liability Period CLIENTFINANCEOPERATIONSCOMMERCIAL Maintain the “Contract Managers Daily Diary Tracker” and update “Critical Milestone Schedule”. Submit to the Operations Director on a weekly basis. Conduct weekly the “Internal Project Review Meeting” (HI.QF.05.04). Submit “Weekly Progress Reports” (HI.QF.05.38) to client, signed off by the Operations Director. Mobilisation Raise Material Request from site. Link BO.EP.01 Identify all project specific items and place order, as per the “Purchasing Procedure” (HI.QAP.06). Raise Valuations as per “Project Invoicing/ Valuation Protocol” (HI.QF.04.) Client certification Release payments against invoice. Approved Update “Project Critical Tasks Log” Issue “Taking Over Certificate” to client. 1 month prior to the completion of DLP, notify the client of the completion of DLP. Issue Final Taking Over Certificate. Prepare: 1. O&M Manual 2. As build drawings 3. Close out authority approvals. Raise “Invoice Request Form” (HI.QF.04.12). Issue an invoice. Prepare “Monthly Cost Reports” (HI.QF.04.15). Update the “Cash Flow and Valuation Schedule” (HI.QF.04.11). HI final snagging. Final inspection done before handover, using the “Pre handover Prompt Sheet” (HI.QF.05.41) as a checklist. INTERNAL PROGRESS REPORTING Identify, prepare and file the project close out documentation. Review “Monthly Cost Reports” (HI.QF.04.15). Update the “Project Critical Tasks Log” and inform Document Control to move the Project folder from the Completed folder to Archived folder. Agree Final Account with client. INVOICING / COLLECTIONS PROCEDURE (HI.QAP.04.01) * “Invoicing / Collections Procedure” (HI.QAP.04.01) “Invoicing / Collections Procedure” (HI.QAP.04.01) Snagging process * Update the “Valuation Tracking Log” (HI.QF.04.13) at each stage of the “Invoicing / Collections Procedure” (HI.QAP.04.01) 12 months period NOTE: Variations shall be controlled as per the “Contracts Management / Process Control Procedure” (HI.QAP.05).