PLASTERING PROCEDURE:
 PLASTER WON’T STICK TO JUST ANY SURFACE AND
YOU DON’T WANT IT TO START FALLING AWAY, SO
ENSURE YOUR SURFACE IS READY TO BE PLASTERED.
 MAKE SURE IT IS CLEAN – REMOVE BITS OF EXISTING
PLASTER, DUST OR WALLPAPER.
 CHECK THE SUCTION OF YOUR WALL.
 HIGH SUCTION POROUS BACKGROUNDS CAN SUCK THE
MOISTURE FROM THE PLASTER MEANING IT DRIES TOO
QUICK – SO YOU MAY NEED TO WET THE WALL BEFORE
YOU START.
 WHEN WETTING YOUR WALLS USE A FINE MIST SPRAY
GUN TO AVOID HAVING TO KEEP REACHING DOWN TO
RE-WET YOUR BRUSH.
 ONCE THE WATER STARTS RUNNING DOWN THE WALL,
YOU KNOW YOU’VE CONTROLLED THE SUCTION.
 LOW SUCTION BACKGROUNDS, SUCH AS PAINTED
SURFACES WILL ALSO NEED TO BE PROPERLY PREPARED.
 WHILE PLASTERBOARD OR BACKING COAT CAN BE
SKIMMED OVER WITHOUT PREPARATION – EXISTING
PLASTER OR PREVIOUSLY PAINTED SURFACES WILL NEED
TREATING WITH A BONDING AGENT, SUCH AS A MIX OF
PVA GLUE AND WATER TO ENSURE THE PLASTER STICKS
TO THE WALL.
 YOU COULD ALSO TRY ADDING A HANDFUL OF SAND TO
THE PVA MIXTURE TO GIVE IT A ROUGHER TEXTURE AND
BETTER ADHESION.
 CLEAN AS YOU GO ALONG – IT MAY SOUND OVER THE TOP
BUT IT’S VITAL TO HAVE CLEAN BUCKETS, TOOLS AND
EQUIPMENT TO ENSURE YOUR PLASTER DOESN’T GO OFF
AND YOU GET A BETTER FINISH THAT LASTS.
• ALSO, DRY PLASTER IS A NIGHTMARE TO REMOVE FROM YOUR TOOLS AND CAN CAUSE
DRAGS IN THE PLASTER FINISH ON YOUR NEXT JOB!
• ALWAYS USE CLEAN WATER, AGAIN TO AVOID CONTAMINATING YOUR PLASTER AND
MAKE IT GO OFF OR SET TOO QUICK.
• ALWAYS MIX PLASTER BY ADDING PLASTER TO THE WATER AND NOT THE OTHER WAY
AROUND.
• ADD JUST ENOUGH PLASTER FIRST TO MAKE A HEAP ON THE TOP OF THE WATER AND
MIX IT SO THAT IT’S LUMP FREE, THEN SLOWLY ADD THE PLASTER TO GET THE CORRECT
CONSISTENCY EITHER WITH A WOODEN STICK OR MIXER DRILL.
• PLASTER AND WATER MIX TOGETHER ROUGHLY HALF AND HALF – SO HALF A (CLEAN)
BUCKET OF WATER SHOULD MAKE A FULL BUCKET OF PLASTER.
• THE PLASTER SHOULD BE THE CONSISTENCY OF MELTED ICE CREAM – TRY STANDING A
STICK IN IT – IF IT CAN STAND UP, THE PLASTER IS MIXED RIGHT.
• PLASTER MUST BE APPLIED WHEN A SURFACE FEELS TACKY, BUT NOT TOO WET, TO HELP
IT BOND TO THE SURFACE WELL.
. WHEN PLASTERING A ROOM, TRY NOT TO DO TWO WALLS THAT ARE TOUCHING EACH OTHER AS
YOU RISK DAMAGING ONE WALL WHILE PLASTERING THE OTHER.
• KEEP IT COOL IN THE ROOM YOU ARE PLASTERING – RADIATORS SHOULD BE TURNED OFF OR THE
PLASTER WILL DRY OUT TOO QUICKLY, MAKING IT DIFFICULT TO APPLY AND CRACK.
• BEGINNERS SHOULD START ON A SMALL AREA FIRST TO ENSURE THEY’RE GETTING THE
TECHNIQUE RIGHT.
• START WITH AN AREA WHICH ONLY TAKES 30 MINS OR LESS FOR THE FIRST COAT.
• ENSURE YOU FOLLOW THE SIX STAGES OF PLASTERING CORRECTLY AND CONFIDENTLY – FROM THE
FIRST COAT TO THE FINAL FINISH.
• A GOOD PLASTER FINISH CAN BE ACHIEVED WITH A COMBINATION OF CONFIDENT FIRM PRESSURE
AND THE CORRECT ANGLE OF YOUR TROWEL.
• DON’T TRY AND GET YOUR SURFACE PERFECT IN THE FIRST COAT – IT TAKES TOO MUCH TIME AND
THE PLASTER MAY DRY TOO SOON – IMPERFECTIONS CAN BE IRONED OUT IN LATER STAGES.
• WHEN YOU FIRST APPLY YOUR TROWEL TO THE CEILING OR WALL, START WITH ONE EDGE OF THE
TROWEL ANGLED AWAY FROM IT.
• AS THE PLASTER ON YOUR TROWEL GETS LESS AND LESS WITH YOUR MOVEMENT, THE ANGLE
BETWEEN YOUR TROWEL AND THE SURFACE GETS SMALLER.
• WATCH FOR SPILLAGE WHEN REDUCING THE ANGLE OF YOUR TROWEL!
IF YOU’RE DOING A CEILING, DON’T STAND DIRECTLY UNDER YOUR TROWEL, JUST IN CASE
YOU GET PLASTER IN YOUR EYE!
• ARTEX CEILINGS CAN BE PLASTERED BY JUST USING A THICKER COAT OF PLASTER.
• DON’T GO INTO THE EDGES BETWEEN THE CEILING AND WALL STRAIGHT AWAY WITH
YOUR PLASTER – IT CAN BE WORKED INTO THE EDGES AT A LATER DATE AND AVOID LUMPS
OF PLASTER CLUMPING IN THE CORNERS.
• BUT, WHEN YOU DO DO YOUR CORNERS, MAKE SURE THEY’RE FLAT – IT MAKES THE
WHOLE WALL LOOK GOOD!
• ENSURE THE THICKNESS OF THE PLASTER IS EVEN ON THE FIRST AND SECOND COAT. USE
FIRM PRESSURE TO ENSURE IT IS FLAT WITH NO BULGES.
• YOU DON’T NEED TO WORRY TOO MUCH ABOUT SMOOTHNESS OR TROWEL MARKS AT
THIS STAGE, JUST THAT IT’S FLAT AND EVEN.
• MAKE SURE THE FIRST THIN COAT IS WET AND PLIABLE WHEN YOU APPLY THE SECOND
COAT.
• DON’T WORRY ABOUT FILLING EVERY LITTLE HOLE AT THIS STAGE – IT’S BETTER TO
AVOID YOUR PLASTER FIRMING UP TOO QUICK.
• AFTER THE FIRST TWO COATS, THE ‘TROWELLING UP’ PROCESS BEGINS. THIS IS TIME TO
FILL ALL THOSE HOLES, REMOVE YOUR TROWEL MARKS AND GET IT SMOOTH.
• Make sure before you start the plaster is
tacky – pliable enough to push the plaster
into the holes, but not so wet you make
new holes.
• As the plaster sets it will darken in
colour, which means it’s time for the final
trowel.
• Don’t over polish the plaster on the final
dry trowel stage – it should be even and
slightly polished, but feel like eggshell –
any smoother, it makes paint and
wallpaper a nightmare to stick to.
SPECIFICATION
• R.C.C. Frame structure.
• External & Internal walls in AAC blocks
• Internal wall finish with Gypsum, Gypsum to ceiling and OBD
paint.
• Rolling shutters to each shops & doors to Offices.
• Flooring-2’X2’ vitrified tiles.
• Finished toilets with branded fixtures for offices & common
area.
• Vitrified Flooring in passages and pavers in walkway area.
• Common area lighting and Lifts with backup.
• High visibility of all shops from all level with large frontal display.
• Spacious layout that respects liberty for shops and privacy for offices.
• Multiple entrances.
• Excellent finishes and aesthetic to provide a soothing effect.
• Plenty of parking area.
• Options of different sizes for shops and offices.
• Energy efficient design incorporating natural lights.
• Plenty of landscape area located at different locations.
DETAILS OF SITE .
SITE NAME : NIRMAN BHARTI CITY CENTER
ADDRESS : CTS NO. 17849 /17850 VEER SAVARKAR MARG ,
NIRALA BAZAAR AURANGABAD.
PROJECT
DEVELOPER : CITY BHARTI TECHNO HERITAGE LLP.
ARCHITECT : MANOJ KALA
(SPACE OLYMPIA , SUTGIRNI CHOWK , GARKHEDA ,
AURANGABAD. )
CONTD. . .
CONTRACTOR : ESSEN CONSTRUCTION
PROJECT
COMMENCEMENT DATE : 27TH APRIL 2014
ESTIMATED DATE OF
COMPLETION : 31ST AUGUST 2018
ESTIMATE PROJECT : RS. 15,00,00,000 /-
COST
WHETHER PERMISSION TAKEN FROM AMC:- YES
WATER SUPPLY SOURCE: - BORING.
ELECTRICITY AVAILABLE :- YES
METHOD OF CONCRETE MIXING:- CONCRETE MIXER
NUBMER OF LABOUR WORK :- 25
LABOUR CHARGES :- 400-500/SQ.FT.
TYPE OF BUILDING
COMMERCIAL BUILDING
G+ 3 PLAN
PLOT SIZE
14024.39 SQ.M
LAYOUT
PLANS OF VISITED SITE
LAYOUT PLAN OF
BASEMENT
FIRST FLOOR PLAN
SECOND FLOOR PLAN
THIRD FLOOR PLAN
MATERIAL USED FOR
CONSTRUCTION
OPC CEMENT COROMANDEL GRADE “53”
TRADITIONAL BRICK
19 X 9 X 9 CM
ACC(AUTOCLAVED CELLULAR CONCRETE ) BLOCK
(SIPOREX)
MANUFACTURING OF ACC BLOCK
 ACC IS PRODUCED USING NO AGGREGATE LARGER THAN SAND.
 QUARTZ SAND, CALCITE GYPSUM, LIME (MINERAL) AND/OR CEMENT AND WATER
ARE USED AS A BINDING AGENT.
 ALUMINUM POWDER IS USED AT A RATE OF 0.05%–0.08% BY VOLUME
(DEPENDING ON THE PRE-SPECIFIED DENSITY).
 IN SOME COUNTRIES, LIKE INDIA AND CHINA, FLY ASH GENERATED FROM
THERMAL POWER PLANTS AND HAVING 50-65% SILICA CONTENT IS USED AS AN
AGGREGATE.
 WHEN AAC IS MIXED AND CAST IN FORMS, SEVERAL CHEMICAL REACTIONS TAKE
PLACE THAT GIVE AAC ITS LIGHT WEIGHT (VIZ. 20% OF THE WEIGHT OF
CONCRETE)
 ALUMINUM POWDER REACTS WITH CALCIUM HYDROXIDE AND WATER TO
FORM HYDROGEN
 DURING MANUFACTURING OF BLOCK CHEMICAL REACTION TAKES PLACE
WHICH EVOLVE HYDOGEN FROM MIX AND IT GIVE SOLID SURFACE BUT
STILL SOFT.
 IT IS THEN CUT INTO EITHER BLOCKS OR PANELS, AND PLACED IN
AN AUTOCLAVE CHAMBER FOR 12 HOURS
 DURING THIS STEAM PRESSURE HARDENING PROCESS ARE CARRIED,
WHICH GIVES AAC ITS HIGH STRENGTH AND OTHER UNIQUE
PROPERTIES.
 AFTER THE AUTOCLAVING PROCESS, THE MATERIAL IS READY FOR
IMMEDIATE USE ON THE CONSTRUCTION SITE.
 IT CAN CARRY LOADS OF UP TO 8 MPA (1,160 PSI), APPROXIMATELY 50%
OF THE COMPRESSIVE STRENGTH OF REGULAR CONCRETE.
 SINCE 1980, THERE HAS BEEN A WORLDWIDE INCREASE IN THE USE AND
PRODUCTION OF AAC MATERIALS. .
 AAC IS INCREASINGLY USED BY DEVELOPERS, ARCHITECTS, AND HOME
BUILDERS WORLDWIDE.
ACC BLOCKS DIMENSIONS
ACC WALL
AGGREGATES AND OTHER MIXING MATERIALS
PROBLEMS FACED :
1) HARD STRATA AVAILABLE.
2) PROBLEM OF DEWATERING .
SOLUTION OF PROBLEM FACED
• BLASTING IS ADOPTED
• DEWATERING BY MEANS OF MOTOR.
A
TEP-1 (PREPARATION OF SURFACE FOR PLASTERING)
KEEP ALL THE MORTAR JOINTS OF WALL ROUGH, SO AS TO GIVE A GOOD BONDING TO
HOLD PLASTER.
CLEAN ALL THE JOINTS AND SURFACES OF THE WALL WITH A WIRE BRUSH, THERE
SHOULD BE NO OIL OR GREASE ETC. LEFT ON WALL SURFACE.
IF THE SURFACE IS SMOOTH OR THE WALL TO BE PLASTERED IS OLD ONE, THEN RAKE
OUT THE MORTAR JOINT TO A DEPTH OF AT LEAST 12 MM TO GIVE A BETTER BONDING
TO THE PLASTER.
IF THE PROJECTION ON THE WALL SURFACE IS MORE THAN 12 MM, THEN KNOCK IT OFF,
SO AS TO OBTAIN A UNIFORM SURFACE OF WALL. THIS WILL REDUCE THE
CONSUMPTION OF PLASTER.
IF THERE EXIST ANY CAVITIES OR HOLES ON THE SURFACE, THEN FILL IT IN ADVANCE
WITH APPROPRIATE MATERIAL.
ROUGHEN THE ENTIRE WALL TO BE PLASTERED.
WASH THE MORTAR JOINTS AND ENTIRE WALL TO BE PLASTERED, AND KEEP IT WET
FOR AT LEAST 6 HOURS BEFORE APPLYING CEMENT PLASTER.
A
STEP-2 (GROUND WORK FOR PLASTER)
IN ORDER TO GET UNIFORM THICKNESS OF
PLASTERING THROUGHOUT THE WALL SURFACE,
FIRST FIX DOTS ON THE WALL. A DOT MEANS
PATCH OF PLASTER OF SIZE 15 MM * 15 MM AND
HAVING THICKNESS OF ABOUT 10 MM.
DOTS ARE FIXED ON THE WALL FIRST
HORIZONTALLY AND THEN VERTICALLY AT A
DISTANCE OF ABOUT 2 METERS COVERING THE
ENTIRE WALL SURFACE.
CHECK THE VERTICALITY OF DOTS, ONE OVER
THE OTHER, BY MEANS OF PLUMB-BOB.
AFTER FIXING DOTS, THE VERTICAL STRIPS OF
PLASTER, KNOWN AS SCREEDS, ARE FORMED IN
BETWEEN THE DOTS. THESE SCREEDS SERVE AS
THE GAUGES FOR MAINTAINING EVEN
THICKNESS OF PLASTERING BEING APPLIED.
A
STEP-3 (APPLYING FIRST COAT OR UNDER COAT OR RENDERING COAT)
IN CASE OF BRICK MASONRY THE THICKNESS OF FIRST COAT PLASTER IS IN GENERAL12
MM AND IN CASE OF CONCRETE MASONRY THIS THICKNESS VARIES FROM 9 TO 15 MM.
THE RATIO OF CEMENT AND SAND FOR FIRST COAT PLASTER VARIES FROM 1:3 TO 1:6.
APPLY THE FIRST COAT OF PLASTER BETWEEN THE SPACES FORMED BY THE SCREEDS
ON THE WALL SURFACE. THIS IS DONE BY MEANS OF TROWEL.
LEVEL THE SURFACE BY MEANS OF FLAT WOODEN FLOATS AND WOODEN STRAIGHT
EDGES.
AFTER LEVELING, LEFT THE FIRST COAT TO SET BUT NOT TO DRY AND THEN ROUGHEN
IT WITH A SCRATCHING TOOL TO FORM A KEY TO THE SECOND COAT OF PLASTER.
A
STEP-4 (APPLYING SECOND COAT OR FINISHING COAT OR FINE COAT)
THE THICKNESS OF SECOND COAT OR FINISHING COAT MAY VARY BETWEEN 2 TO 3 MM.
THE RATIO OF CEMENT AND SAND FOR SECOND COAT PLASTER VARIES FROM 1:4 TO 1:6.
BEFORE APPLYING THE SECOND COAT, DAMP THE FIRST COAT EVENLY.
APPLY THE FINISHING COAT WITH WOODEN FLOATS TO A TRUE EVEN SURFACE AND
USING A STEEL TROWEL, GIVE IT A FINISHING TOUCH.
AS FAR AS POSSIBLE, THE FINISHING COAT SHOULD BE APPLIED STARTING FROM TOP
TOWARDS BOTTOM AND COMPLETED IN ONE OPERATION TO ELIMINATE JOINING
MARKS.
INTERNAL
PLASTERING
WALL
SCRATCHING
INSERTING
PIPES
INSERING
WIRES
WALL
LEVELLING
MORTAR
FILLING
12MM UNDER
COAT
6MM
FINISHING
COAT
APPLYING
POP
PAINT
THANK YOU

More Related Content

What's hot

Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training pptSumit Singh
 
RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING Vikas Sukhwal
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSASHOK KUMAR TIWARY
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentationemdad bhuiyan
 
Analysis and design of commercial building
Analysis and design of commercial buildingAnalysis and design of commercial building
Analysis and design of commercial buildingSatrudhan11240
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineeringalok0025
 
Industrial training report of construction of the residential building
Industrial training report of construction of the residential buildingIndustrial training report of construction of the residential building
Industrial training report of construction of the residential buildingsuraj jha
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selectionanojan kanagarathnam
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction pptBeing Deepak
 
Construction defects
Construction defectsConstruction defects
Construction defectsshivam tomar
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specificationsSimran Vats
 
Safety in construction
Safety in constructionSafety in construction
Safety in constructionJitesh Dhule
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction CostingManish Kandpal
 
minor project report on design of residential building
minor project report on design of residential buildingminor project report on design of residential building
minor project report on design of residential buildingtushar garg
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...A Makwana
 

What's hot (20)

Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Construction process
Construction processConstruction process
Construction process
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
Cracks in Buildings
Cracks in BuildingsCracks in Buildings
Cracks in Buildings
 
RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
 
Building project presentation
Building project presentationBuilding project presentation
Building project presentation
 
Analysis and design of commercial building
Analysis and design of commercial buildingAnalysis and design of commercial building
Analysis and design of commercial building
 
Summer training report in civil engineering
Summer training report in civil engineeringSummer training report in civil engineering
Summer training report in civil engineering
 
Industrial training report of construction of the residential building
Industrial training report of construction of the residential buildingIndustrial training report of construction of the residential building
Industrial training report of construction of the residential building
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selection
 
Formwork
FormworkFormwork
Formwork
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
Construction defects
Construction defectsConstruction defects
Construction defects
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
 
Safety in construction
Safety in constructionSafety in construction
Safety in construction
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
 
minor project report on design of residential building
minor project report on design of residential buildingminor project report on design of residential building
minor project report on design of residential building
 
Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...Introduction-construction management_Construction Management (2180611) (Semes...
Introduction-construction management_Construction Management (2180611) (Semes...
 

Similar to construction management site visit ppt

Cement tiles as cladding material
Cement tiles as cladding materialCement tiles as cladding material
Cement tiles as cladding materialAamir Farhan Sheikh
 
Fabrication of a new full lower denture revised
Fabrication of a new full lower denture revisedFabrication of a new full lower denture revised
Fabrication of a new full lower denture revisedEugene Royzengurt
 
Plastering Process (Cement/Masonry/Finishing Layer)
Plastering Process (Cement/Masonry/Finishing Layer)Plastering Process (Cement/Masonry/Finishing Layer)
Plastering Process (Cement/Masonry/Finishing Layer)Zelkhan
 
Carpet Install and re-install 101
Carpet Install and re-install 101Carpet Install and re-install 101
Carpet Install and re-install 101Rob Decker
 
clay tiles brick paving stone paving.pptx
clay tiles brick paving stone paving.pptxclay tiles brick paving stone paving.pptx
clay tiles brick paving stone paving.pptxMEGHANA S
 
Laminate and wood
Laminate  and woodLaminate  and wood
Laminate and woodRahul Verma
 
Copy of Plastering.pptx
Copy of Plastering.pptxCopy of Plastering.pptx
Copy of Plastering.pptxSantoshreddy B
 
Low cost construction
Low cost constructionLow cost construction
Low cost constructionAnuj Singhal
 
ROLE OF STEMMING IN OPEN CAST MINE
ROLE OF STEMMING IN OPEN CAST MINEROLE OF STEMMING IN OPEN CAST MINE
ROLE OF STEMMING IN OPEN CAST MINEPANKAJ PATIDAR
 
A Guide To Internal Lime Plastering
A Guide To Internal Lime PlasteringA Guide To Internal Lime Plastering
A Guide To Internal Lime PlasteringThe WDS Group
 
How to test absorbency of a fabric.
How to test absorbency of a fabric.How to test absorbency of a fabric.
How to test absorbency of a fabric.Sayeed Ahmed
 
educational sheet clay plaster
educational sheet clay plastereducational sheet clay plaster
educational sheet clay plasterlibnam
 
basics of plaster and slabs
basics of plaster and slabsbasics of plaster and slabs
basics of plaster and slabsNandan Marathe
 
Final impression boxing and pouring
Final impression  boxing and pouringFinal impression  boxing and pouring
Final impression boxing and pouringBkPradeep1
 

Similar to construction management site visit ppt (20)

Cement tiles as cladding material
Cement tiles as cladding materialCement tiles as cladding material
Cement tiles as cladding material
 
Fabrication of a new full lower denture revised
Fabrication of a new full lower denture revisedFabrication of a new full lower denture revised
Fabrication of a new full lower denture revised
 
Plastering Process (Cement/Masonry/Finishing Layer)
Plastering Process (Cement/Masonry/Finishing Layer)Plastering Process (Cement/Masonry/Finishing Layer)
Plastering Process (Cement/Masonry/Finishing Layer)
 
Carpet Install and re-install 101
Carpet Install and re-install 101Carpet Install and re-install 101
Carpet Install and re-install 101
 
clay tiles brick paving stone paving.pptx
clay tiles brick paving stone paving.pptxclay tiles brick paving stone paving.pptx
clay tiles brick paving stone paving.pptx
 
Laminate and wood
Laminate  and woodLaminate  and wood
Laminate and wood
 
porcelain tiles
porcelain tilesporcelain tiles
porcelain tiles
 
Aquarium
AquariumAquarium
Aquarium
 
Copy of Plastering.pptx
Copy of Plastering.pptxCopy of Plastering.pptx
Copy of Plastering.pptx
 
Low cost construction
Low cost constructionLow cost construction
Low cost construction
 
ROLE OF STEMMING IN OPEN CAST MINE
ROLE OF STEMMING IN OPEN CAST MINEROLE OF STEMMING IN OPEN CAST MINE
ROLE OF STEMMING IN OPEN CAST MINE
 
A Guide To Internal Lime Plastering
A Guide To Internal Lime PlasteringA Guide To Internal Lime Plastering
A Guide To Internal Lime Plastering
 
How to test absorbency of a fabric.
How to test absorbency of a fabric.How to test absorbency of a fabric.
How to test absorbency of a fabric.
 
educational sheet clay plaster
educational sheet clay plastereducational sheet clay plaster
educational sheet clay plaster
 
Birdon
BirdonBirdon
Birdon
 
SAP
SAPSAP
SAP
 
Welesgard. water tank refurbishment
Welesgard. water tank refurbishmentWelesgard. water tank refurbishment
Welesgard. water tank refurbishment
 
basics of plaster and slabs
basics of plaster and slabsbasics of plaster and slabs
basics of plaster and slabs
 
Udu drum project
Udu drum projectUdu drum project
Udu drum project
 
Final impression boxing and pouring
Final impression  boxing and pouringFinal impression  boxing and pouring
Final impression boxing and pouring
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 

construction management site visit ppt

  • 1. CONSTRUCTION MANAGEMENT PRACTICAL STUDY OF CIVIL ENGINEERING STRUCTURE
  • 2.
  • 3. PLASTERING PROCEDURE:  PLASTER WON’T STICK TO JUST ANY SURFACE AND YOU DON’T WANT IT TO START FALLING AWAY, SO ENSURE YOUR SURFACE IS READY TO BE PLASTERED.  MAKE SURE IT IS CLEAN – REMOVE BITS OF EXISTING PLASTER, DUST OR WALLPAPER.  CHECK THE SUCTION OF YOUR WALL.  HIGH SUCTION POROUS BACKGROUNDS CAN SUCK THE MOISTURE FROM THE PLASTER MEANING IT DRIES TOO QUICK – SO YOU MAY NEED TO WET THE WALL BEFORE YOU START.  WHEN WETTING YOUR WALLS USE A FINE MIST SPRAY GUN TO AVOID HAVING TO KEEP REACHING DOWN TO RE-WET YOUR BRUSH.
  • 4.  ONCE THE WATER STARTS RUNNING DOWN THE WALL, YOU KNOW YOU’VE CONTROLLED THE SUCTION.  LOW SUCTION BACKGROUNDS, SUCH AS PAINTED SURFACES WILL ALSO NEED TO BE PROPERLY PREPARED.  WHILE PLASTERBOARD OR BACKING COAT CAN BE SKIMMED OVER WITHOUT PREPARATION – EXISTING PLASTER OR PREVIOUSLY PAINTED SURFACES WILL NEED TREATING WITH A BONDING AGENT, SUCH AS A MIX OF PVA GLUE AND WATER TO ENSURE THE PLASTER STICKS TO THE WALL.  YOU COULD ALSO TRY ADDING A HANDFUL OF SAND TO THE PVA MIXTURE TO GIVE IT A ROUGHER TEXTURE AND BETTER ADHESION.  CLEAN AS YOU GO ALONG – IT MAY SOUND OVER THE TOP BUT IT’S VITAL TO HAVE CLEAN BUCKETS, TOOLS AND EQUIPMENT TO ENSURE YOUR PLASTER DOESN’T GO OFF AND YOU GET A BETTER FINISH THAT LASTS.
  • 5. • ALSO, DRY PLASTER IS A NIGHTMARE TO REMOVE FROM YOUR TOOLS AND CAN CAUSE DRAGS IN THE PLASTER FINISH ON YOUR NEXT JOB! • ALWAYS USE CLEAN WATER, AGAIN TO AVOID CONTAMINATING YOUR PLASTER AND MAKE IT GO OFF OR SET TOO QUICK. • ALWAYS MIX PLASTER BY ADDING PLASTER TO THE WATER AND NOT THE OTHER WAY AROUND. • ADD JUST ENOUGH PLASTER FIRST TO MAKE A HEAP ON THE TOP OF THE WATER AND MIX IT SO THAT IT’S LUMP FREE, THEN SLOWLY ADD THE PLASTER TO GET THE CORRECT CONSISTENCY EITHER WITH A WOODEN STICK OR MIXER DRILL. • PLASTER AND WATER MIX TOGETHER ROUGHLY HALF AND HALF – SO HALF A (CLEAN) BUCKET OF WATER SHOULD MAKE A FULL BUCKET OF PLASTER. • THE PLASTER SHOULD BE THE CONSISTENCY OF MELTED ICE CREAM – TRY STANDING A STICK IN IT – IF IT CAN STAND UP, THE PLASTER IS MIXED RIGHT. • PLASTER MUST BE APPLIED WHEN A SURFACE FEELS TACKY, BUT NOT TOO WET, TO HELP IT BOND TO THE SURFACE WELL.
  • 6. . WHEN PLASTERING A ROOM, TRY NOT TO DO TWO WALLS THAT ARE TOUCHING EACH OTHER AS YOU RISK DAMAGING ONE WALL WHILE PLASTERING THE OTHER. • KEEP IT COOL IN THE ROOM YOU ARE PLASTERING – RADIATORS SHOULD BE TURNED OFF OR THE PLASTER WILL DRY OUT TOO QUICKLY, MAKING IT DIFFICULT TO APPLY AND CRACK. • BEGINNERS SHOULD START ON A SMALL AREA FIRST TO ENSURE THEY’RE GETTING THE TECHNIQUE RIGHT. • START WITH AN AREA WHICH ONLY TAKES 30 MINS OR LESS FOR THE FIRST COAT. • ENSURE YOU FOLLOW THE SIX STAGES OF PLASTERING CORRECTLY AND CONFIDENTLY – FROM THE FIRST COAT TO THE FINAL FINISH. • A GOOD PLASTER FINISH CAN BE ACHIEVED WITH A COMBINATION OF CONFIDENT FIRM PRESSURE AND THE CORRECT ANGLE OF YOUR TROWEL. • DON’T TRY AND GET YOUR SURFACE PERFECT IN THE FIRST COAT – IT TAKES TOO MUCH TIME AND THE PLASTER MAY DRY TOO SOON – IMPERFECTIONS CAN BE IRONED OUT IN LATER STAGES. • WHEN YOU FIRST APPLY YOUR TROWEL TO THE CEILING OR WALL, START WITH ONE EDGE OF THE TROWEL ANGLED AWAY FROM IT. • AS THE PLASTER ON YOUR TROWEL GETS LESS AND LESS WITH YOUR MOVEMENT, THE ANGLE BETWEEN YOUR TROWEL AND THE SURFACE GETS SMALLER. • WATCH FOR SPILLAGE WHEN REDUCING THE ANGLE OF YOUR TROWEL!
  • 7. IF YOU’RE DOING A CEILING, DON’T STAND DIRECTLY UNDER YOUR TROWEL, JUST IN CASE YOU GET PLASTER IN YOUR EYE! • ARTEX CEILINGS CAN BE PLASTERED BY JUST USING A THICKER COAT OF PLASTER. • DON’T GO INTO THE EDGES BETWEEN THE CEILING AND WALL STRAIGHT AWAY WITH YOUR PLASTER – IT CAN BE WORKED INTO THE EDGES AT A LATER DATE AND AVOID LUMPS OF PLASTER CLUMPING IN THE CORNERS. • BUT, WHEN YOU DO DO YOUR CORNERS, MAKE SURE THEY’RE FLAT – IT MAKES THE WHOLE WALL LOOK GOOD! • ENSURE THE THICKNESS OF THE PLASTER IS EVEN ON THE FIRST AND SECOND COAT. USE FIRM PRESSURE TO ENSURE IT IS FLAT WITH NO BULGES. • YOU DON’T NEED TO WORRY TOO MUCH ABOUT SMOOTHNESS OR TROWEL MARKS AT THIS STAGE, JUST THAT IT’S FLAT AND EVEN. • MAKE SURE THE FIRST THIN COAT IS WET AND PLIABLE WHEN YOU APPLY THE SECOND COAT. • DON’T WORRY ABOUT FILLING EVERY LITTLE HOLE AT THIS STAGE – IT’S BETTER TO AVOID YOUR PLASTER FIRMING UP TOO QUICK. • AFTER THE FIRST TWO COATS, THE ‘TROWELLING UP’ PROCESS BEGINS. THIS IS TIME TO FILL ALL THOSE HOLES, REMOVE YOUR TROWEL MARKS AND GET IT SMOOTH.
  • 8. • Make sure before you start the plaster is tacky – pliable enough to push the plaster into the holes, but not so wet you make new holes. • As the plaster sets it will darken in colour, which means it’s time for the final trowel. • Don’t over polish the plaster on the final dry trowel stage – it should be even and slightly polished, but feel like eggshell – any smoother, it makes paint and wallpaper a nightmare to stick to.
  • 9.
  • 10. SPECIFICATION • R.C.C. Frame structure. • External & Internal walls in AAC blocks • Internal wall finish with Gypsum, Gypsum to ceiling and OBD paint. • Rolling shutters to each shops & doors to Offices. • Flooring-2’X2’ vitrified tiles. • Finished toilets with branded fixtures for offices & common area. • Vitrified Flooring in passages and pavers in walkway area.
  • 11. • Common area lighting and Lifts with backup. • High visibility of all shops from all level with large frontal display. • Spacious layout that respects liberty for shops and privacy for offices. • Multiple entrances. • Excellent finishes and aesthetic to provide a soothing effect. • Plenty of parking area. • Options of different sizes for shops and offices. • Energy efficient design incorporating natural lights. • Plenty of landscape area located at different locations.
  • 12. DETAILS OF SITE . SITE NAME : NIRMAN BHARTI CITY CENTER ADDRESS : CTS NO. 17849 /17850 VEER SAVARKAR MARG , NIRALA BAZAAR AURANGABAD. PROJECT DEVELOPER : CITY BHARTI TECHNO HERITAGE LLP. ARCHITECT : MANOJ KALA (SPACE OLYMPIA , SUTGIRNI CHOWK , GARKHEDA , AURANGABAD. )
  • 13. CONTD. . . CONTRACTOR : ESSEN CONSTRUCTION PROJECT COMMENCEMENT DATE : 27TH APRIL 2014 ESTIMATED DATE OF COMPLETION : 31ST AUGUST 2018 ESTIMATE PROJECT : RS. 15,00,00,000 /- COST
  • 14. WHETHER PERMISSION TAKEN FROM AMC:- YES WATER SUPPLY SOURCE: - BORING. ELECTRICITY AVAILABLE :- YES METHOD OF CONCRETE MIXING:- CONCRETE MIXER NUBMER OF LABOUR WORK :- 25 LABOUR CHARGES :- 400-500/SQ.FT.
  • 15. TYPE OF BUILDING COMMERCIAL BUILDING G+ 3 PLAN
  • 23. OPC CEMENT COROMANDEL GRADE “53”
  • 25. ACC(AUTOCLAVED CELLULAR CONCRETE ) BLOCK (SIPOREX)
  • 26. MANUFACTURING OF ACC BLOCK  ACC IS PRODUCED USING NO AGGREGATE LARGER THAN SAND.  QUARTZ SAND, CALCITE GYPSUM, LIME (MINERAL) AND/OR CEMENT AND WATER ARE USED AS A BINDING AGENT.  ALUMINUM POWDER IS USED AT A RATE OF 0.05%–0.08% BY VOLUME (DEPENDING ON THE PRE-SPECIFIED DENSITY).  IN SOME COUNTRIES, LIKE INDIA AND CHINA, FLY ASH GENERATED FROM THERMAL POWER PLANTS AND HAVING 50-65% SILICA CONTENT IS USED AS AN AGGREGATE.
  • 27.  WHEN AAC IS MIXED AND CAST IN FORMS, SEVERAL CHEMICAL REACTIONS TAKE PLACE THAT GIVE AAC ITS LIGHT WEIGHT (VIZ. 20% OF THE WEIGHT OF CONCRETE)  ALUMINUM POWDER REACTS WITH CALCIUM HYDROXIDE AND WATER TO FORM HYDROGEN  DURING MANUFACTURING OF BLOCK CHEMICAL REACTION TAKES PLACE WHICH EVOLVE HYDOGEN FROM MIX AND IT GIVE SOLID SURFACE BUT STILL SOFT.  IT IS THEN CUT INTO EITHER BLOCKS OR PANELS, AND PLACED IN AN AUTOCLAVE CHAMBER FOR 12 HOURS
  • 28.  DURING THIS STEAM PRESSURE HARDENING PROCESS ARE CARRIED, WHICH GIVES AAC ITS HIGH STRENGTH AND OTHER UNIQUE PROPERTIES.  AFTER THE AUTOCLAVING PROCESS, THE MATERIAL IS READY FOR IMMEDIATE USE ON THE CONSTRUCTION SITE.  IT CAN CARRY LOADS OF UP TO 8 MPA (1,160 PSI), APPROXIMATELY 50% OF THE COMPRESSIVE STRENGTH OF REGULAR CONCRETE.  SINCE 1980, THERE HAS BEEN A WORLDWIDE INCREASE IN THE USE AND PRODUCTION OF AAC MATERIALS. .  AAC IS INCREASINGLY USED BY DEVELOPERS, ARCHITECTS, AND HOME BUILDERS WORLDWIDE.
  • 31. AGGREGATES AND OTHER MIXING MATERIALS
  • 32. PROBLEMS FACED : 1) HARD STRATA AVAILABLE. 2) PROBLEM OF DEWATERING .
  • 33. SOLUTION OF PROBLEM FACED • BLASTING IS ADOPTED • DEWATERING BY MEANS OF MOTOR.
  • 34. A TEP-1 (PREPARATION OF SURFACE FOR PLASTERING) KEEP ALL THE MORTAR JOINTS OF WALL ROUGH, SO AS TO GIVE A GOOD BONDING TO HOLD PLASTER. CLEAN ALL THE JOINTS AND SURFACES OF THE WALL WITH A WIRE BRUSH, THERE SHOULD BE NO OIL OR GREASE ETC. LEFT ON WALL SURFACE. IF THE SURFACE IS SMOOTH OR THE WALL TO BE PLASTERED IS OLD ONE, THEN RAKE OUT THE MORTAR JOINT TO A DEPTH OF AT LEAST 12 MM TO GIVE A BETTER BONDING TO THE PLASTER. IF THE PROJECTION ON THE WALL SURFACE IS MORE THAN 12 MM, THEN KNOCK IT OFF, SO AS TO OBTAIN A UNIFORM SURFACE OF WALL. THIS WILL REDUCE THE CONSUMPTION OF PLASTER. IF THERE EXIST ANY CAVITIES OR HOLES ON THE SURFACE, THEN FILL IT IN ADVANCE WITH APPROPRIATE MATERIAL. ROUGHEN THE ENTIRE WALL TO BE PLASTERED. WASH THE MORTAR JOINTS AND ENTIRE WALL TO BE PLASTERED, AND KEEP IT WET FOR AT LEAST 6 HOURS BEFORE APPLYING CEMENT PLASTER.
  • 35. A STEP-2 (GROUND WORK FOR PLASTER) IN ORDER TO GET UNIFORM THICKNESS OF PLASTERING THROUGHOUT THE WALL SURFACE, FIRST FIX DOTS ON THE WALL. A DOT MEANS PATCH OF PLASTER OF SIZE 15 MM * 15 MM AND HAVING THICKNESS OF ABOUT 10 MM. DOTS ARE FIXED ON THE WALL FIRST HORIZONTALLY AND THEN VERTICALLY AT A DISTANCE OF ABOUT 2 METERS COVERING THE ENTIRE WALL SURFACE. CHECK THE VERTICALITY OF DOTS, ONE OVER THE OTHER, BY MEANS OF PLUMB-BOB. AFTER FIXING DOTS, THE VERTICAL STRIPS OF PLASTER, KNOWN AS SCREEDS, ARE FORMED IN BETWEEN THE DOTS. THESE SCREEDS SERVE AS THE GAUGES FOR MAINTAINING EVEN THICKNESS OF PLASTERING BEING APPLIED.
  • 36. A STEP-3 (APPLYING FIRST COAT OR UNDER COAT OR RENDERING COAT) IN CASE OF BRICK MASONRY THE THICKNESS OF FIRST COAT PLASTER IS IN GENERAL12 MM AND IN CASE OF CONCRETE MASONRY THIS THICKNESS VARIES FROM 9 TO 15 MM. THE RATIO OF CEMENT AND SAND FOR FIRST COAT PLASTER VARIES FROM 1:3 TO 1:6. APPLY THE FIRST COAT OF PLASTER BETWEEN THE SPACES FORMED BY THE SCREEDS ON THE WALL SURFACE. THIS IS DONE BY MEANS OF TROWEL. LEVEL THE SURFACE BY MEANS OF FLAT WOODEN FLOATS AND WOODEN STRAIGHT EDGES. AFTER LEVELING, LEFT THE FIRST COAT TO SET BUT NOT TO DRY AND THEN ROUGHEN IT WITH A SCRATCHING TOOL TO FORM A KEY TO THE SECOND COAT OF PLASTER.
  • 37. A STEP-4 (APPLYING SECOND COAT OR FINISHING COAT OR FINE COAT) THE THICKNESS OF SECOND COAT OR FINISHING COAT MAY VARY BETWEEN 2 TO 3 MM. THE RATIO OF CEMENT AND SAND FOR SECOND COAT PLASTER VARIES FROM 1:4 TO 1:6. BEFORE APPLYING THE SECOND COAT, DAMP THE FIRST COAT EVENLY. APPLY THE FINISHING COAT WITH WOODEN FLOATS TO A TRUE EVEN SURFACE AND USING A STEEL TROWEL, GIVE IT A FINISHING TOUCH. AS FAR AS POSSIBLE, THE FINISHING COAT SHOULD BE APPLIED STARTING FROM TOP TOWARDS BOTTOM AND COMPLETED IN ONE OPERATION TO ELIMINATE JOINING MARKS.