5. INTRODUCTION
Environmental Impact Assessment (E.I.A.) is a tool for assisting
environmental management and for contributing to Sustainable
Development.
EIA is to identify potential environmental impacts from proposals, such
as projects and programs, and to propose means to avoid or reduce
the significant impacts.
According to The International Association of Impact Assessment(IAIA),
E.I.A. is the process of identifying, predicting, evaluating and mitigating
the biological, social, and other relevant effects of development
proposals prior to major decisions being taken and commitments.INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 503 JULY, 2017
6. INTRODUCTION
E.I.A. is both Art & Science
Science (Planning tools): Deal with methodology and technique for
identifying, predicting, and evaluating impacts associated with
particular project.
Art (Management tools): Complying with policy and legal provisions
and influencing the decision-making process.
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 603 JULY, 2017
8. E.I.A. – BENEFITS
Lower project cost in long-term.
Increase project acceptance.
Improve project design.
Informed decision makings.
Environmentally sensitive decision.
Increased accountability and transparency
Reduce environmental damage.
Improved integration of project into their environmental and social
settings.INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 803 JULY, 2017
9. WHICH TYPE OF PROJECTS UNDERGO E.I.A….?
Any development projects around protected nature areas
Clean development mechanism(CDM) Projects.
Agriculture
Construction(Road network, Township, Dam, etc.)
Industries
Electrical projects
Waste disposal
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 903 JULY, 2017
12. PROJECT SCREENING
It would be time consuming and a waste of resources for all proposed
projects and activities to undergo EIA
Not all development projects require an EIA, as some projects may not
pose an environmental threat
It is the process used to determine whether a proposed project or
activity requires an EIA and, if so, what level of environmental review is
necessary.
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 1203 JULY, 2017
14. SCOPING
A process of interaction between government agencies and project
proponents
Identifiers:
Spatial and temporal boundaries for the EIA.
Important issues and concern
Information necessary for decision making
Significant effects and factors to be considered
Establishes Terms of Reference for full-scale EIA
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 1403 JULY, 2017
15. PREPARATION OF TOR FOR AN EIA
BACKGROUND INFORMATION SECTION SHOULD INCLUDE:
Project Description (i.e., type, magnitude, location, alternatives and
constraints)
Environmental Setting (i.e., delineation of study area, listing of
environmental resources and sensitive or special value areas)
Background Reports (e.g., aspects of the environmental setting,
previous projects with relevant impacts or resources)
Significant effects and factors to be considered
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 1503 JULY, 2017
16. PREPARATION OF TOR FOR AN EIA
SPECIFIC EIA REQUIREMENTS TYPICALLY INCLUDE:
EIA objectives
Institutional context (i.e., legal and policy , requirements).
Significant issues of concern (SEIs).
Required information and data methodologies for impact
assessment.
Process for incorporating public input.
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 1603 JULY, 2017
17. BASELINE DATA COLLECTION
Baseline information is found in documents and data banks,
but field studies and interviews with indigenous and other local people
are often necessary.
knowledge of local cultural, social and ecological systems and the
changes in these systems over time, including recent trends, may be an
essential complement to scientific observations
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 1703 JULY, 2017
18. E.I.A. IN NEPAL
INITIATION OF EA IN NEPAL
Since 1980’s through policies
In 1990’s through laws
Use ramified along with development of guidelines and manuals
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 1803 JULY, 2017
19. E.I.A. LAWS IN NEPAL
LEGAL MEASURES
Forest Act,1993
Water Resources Act,1993
Electricity Act,1993
Environment Protection Act,1997
Environment Protection Rules,1997
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 1903 JULY, 2017
20. IDENTIFICATION OF ENVIRONMENT IMPACTS
Describes the proposed project or activity and examines alternatives
Identifies and addresses community concerns to extent possible
Identifies and assesses potential environmental effects
Directs future action
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 2003 JULY, 2017
21. CHARACTERISTICS AFFECTING IMPACT SIGNIFICANCE
Nature of impact (e.g., positive, negative, synergistic)
Extent and magnitude
Timing (i.e., construction, operation, closure)
Duration (i.e., short, chronic, intermittent)
Reversibility/irreversibility
Likelihood (i.e., probability, uncertainty)
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 2103 JULY, 2017
23. IMPACT MITIGATION & ENHANCEMENT MEASURES
ENHANCEMENT MEASURES WITH COST INDICATIONS:
Providing relevant training/skills to local people.
Priority to local people for employment in project
construction/operation works.
Construction/rehabilitation of some public facilities such as taps,
schools, health care centers, temples etc.
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 2303 JULY, 2017
24. IMPACT MITIGATION & ENHANCEMENT MEASURES
MITIGATION MEASURES:
Impact-wise mitigation measure's with indicative costs.
Avoidance, Corrective or Compensatory.
Cost incurring & Non-cost incurring.
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 2403 JULY, 2017
25. ENVIRONMENTAL MANAGEMENT PLAN (EMP)
“A plan to ensure systematic integration of all proposed mitigation
measures with the project construction/operation activities”
OBJECTIVES:
Formulate project management activities in particular implementation
of Environmental Protection Measures(EPM)
Formulate a monitoring programme for baseline, impact and
compliance monitoring
Formulate an environmental auditing programme to be implemented
after project construction
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 2503 JULY, 2017
26. ENVIRONMENTAL MANAGEMENT PLAN (EMP)
PLANS:
Project management for Environmental Protection Measures (EPM)
implementation
Monitoring Plan
Auditing Plan
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 2603 JULY, 2017
27. ENVIRONMENTAL MONITORING
“Environmental monitoring is used in the preparation of E.I.A., as
well as in many circumstances in which human activities carry a risk
of harmful effects on the natural environment.” –Wikipedia
TYPES:
Baseline Monitoring.
Compliance Monitoring.
Impact Monitoring.
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 2703 JULY, 2017
28. ENVIRONMENTAL MONITORING
BASELINE MONITORING:
Specific Objectives:
If anticipated time lapse between EIA approval and project execution is
significantly long.
To update the baseline information on the overall environmental
conditions of the project site prior to project implementation.
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 2803 JULY, 2017
29. ENVIRONMENTAL MONITORING
COMPLIANCE MONITORING:
Specific Objectives:
To ensure fulfillment of all conditions set forth and commitments made
in the approved EIA report
To ensure that other regulatory requirements/standards are well
integrated with subsequent project documents (e. g. detail engineering
design and tender documents etc.)
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 2903 JULY, 2017
30. ENVIRONMENTAL MONITORING
IMPACT MONITORING:
Specific Objectives:
To ensure that the actual impacts in the field are well within the
manageable limit of the designed mitigation measures and set
standards.
To detect any unexpected damages.
To provide early warning to the responsible agencies for undertaking
required corrective/additional measures to avert/minimize such
unanticipated impacts.INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 3003 JULY, 2017
31. ENVIRONMENTAL AUDIT
Environmental Audit is Post Project Assessment of :
Actual environmental impacts.
The accuracy of impact prediction.
Effectiveness of impact mitigation/benefit enhancement measures.
Functioning of monitoring mechanism.
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 3103 JULY, 2017
32. ENVIRONMENTAL AUDIT
When and How Many Times…?
Once for each project after two years of commencement of project
operation
Who is Responsible…?
Ministry of Science Technology and Environment(MoSTE). -as Per EPR,
1997
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 3203 JULY, 2017
33. OTHER LEGAL REQUIREMENTS
PUBLIC HERAING:
Once in the area of project implementation/operation. -as per EPA, 2053
Proceeding of public hearing
Signatures of all attendees
RECOMMENDATIONS FROM:
Concerned rural-municipality / municipalities
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 3303 JULY, 2017
34. POLICIES & PRACTICES OF E.I.A. / E.A. IN NEPAL
The Environmental Assessment system of Nepal has introduced
successfully after the enforcement of Environment Protection Rules (EPR)
1997, which made Initial Environmental Examination(IEE) / EIA mandatory
for the governmental as well as the private sector.
6th Five Year Plan (1980-’85) had first mentioned the need for EIA for
major infrastructure projects
7th Five Year Plan (1985-’90), first time a national level policy on
environment management was incorporated.
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 3403 JULY, 2017
35. POLICIES & PRACTICES OF E.I.A. / E.A. IN NEPAL
8th Five Year Plan(1991-’95) and the Nepal Environmental Policy and
Action Plan (1993) re-emphasized the need for an EIA system to
integrate environmental concerns into the development process.
10th Periodic Plan (2002-’07) the plan seeks to reduce poverty from
38% to 30% by 2007 through emphasis on four key areas, high,
sustainable, and broad based economic growth, social sector and rural
infrastructure development.
10th Five Year Plan, 2003 Conservation of biodiversity through
management of buffer zone involving local user groups, promote &
encourage Eco-tourism in the protected areasINSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 3503 JULY, 2017
36. CONCLUSION
EIA acts as a bridge between economic prosperity and environmental
sustainability.
Major aims: Environmental Friendly, Sustainable Development, Real
Prosperity.
The existing policy and legal instruments since beginning of the late
1980s has a big deal for the development of EIA system in Nepal,
though EIAs have been integrated in major development projects.
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 3603 JULY, 2017
37. RECOMMENDATIONS
All possible impacts of the project activities caused environmental
stress which could be properly managed or mitigated as per the
nature, magnitude and duration of the impacts.
For effective EIA implementation, international standards and
requirements of EIA is necessarily required.
A broader consultation is required among the professionals,
government agencies and concerned stakeholders towards the
effective implementation EIA approach and review of existing policy
and legal instruments.INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 3703 JULY, 2017
38. SLIDE OVER…
Thank You for Your Kind Attention…!
Any…
Queries…? | Comments…? | Suggestions…?
INSTITUTE OF ENGINEEGING, PASCHIMANCHAL CAMPUS, LAMACHOUR, POKHARA 3803 JULY, 2017