SlideShare a Scribd company logo
1 of 26
Download to read offline
OTC-24721-MS
A Case Study Detailing the Design, Planning, Installation and Cost
and Environmental Benefit Analysis of a Reinforced Thermoplastic
Pipe Pulled Through the Inside of an Existing Offshore Steel Flow
Line in the East Malaysia Samarang Field
John R Wright Jr. Polyflow LLC, Khairul Anuar Karim, PETRONAS Carigali and Steve
Kennedy, SCG Oil and Gas
Agenda
1) Background
2) Steps and Analysis for Successful Rehabilitation
3) Details of the Installation
4) Benefits Analysis
5) Areas for Improvement
6) Q & A
Slide 2
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Background
• PL-112 Pipeline
• 52 Km off Labuan in Samarang Field
• 8-10 Meters of Water
• 6” API -5L X-42 Steel Pipe Installed in 1977
• Approximately 1Kilometer
• Anchor Hooked Pipe Causing a Kink in 2009
• Repairs Made with Misalignment Flanges
• Difficulty in Maintenance and Loss of Wall Thickness
Concluded Repairs as Temporary
• Current Infield Drilling
• Required New Pipeline for Next 25 Years
• New Steel Pipeline Replacement and Reinforced Thermoplastic
Pipe Rehabilitation were Evaluated
• Future Flowing Conditions
• 1,800bbl – 5,000bbl/day Depending upon Field Requirements
• Concern with SRB’s in Future
• Low Formation Pressure
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Analysis and Planning Steps for RTP Rehab
• Sizing of the New Flow Line
• Material Selection
• Pull Force Analysis
• Selection of Pulling Equipment
• Detailed Layout of Project
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Proper Sizing of Pipe
Slide 5
• Sized for Desired Production
 Fits Inside of Existing Steel
 Acceptable Pressure Drop
for Formation
 Ideally Fits Through Existing
Risers
• Design for Maintaining
Minimum Velocities
 0.61m/s will Carry Solids in
Liquids
 Reduces Ongoing
Maintenance (Pigging)
• Selected 3.5” RTP (2.95” ID)
 Acceptable Pressure Drops
 Minimal Velocities for Range
of Flow
 Risers Have to be Modified Modified Riser with 12D Bend
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Existing Riser with 5D Bend
Pressure Drops and Critical Velocities for 3.5” RTP
Velocity at
1,800bbl/day is
2 ft./sec (0.61 m/sec)
Typical Production
Volume Pressure
Drop of 15.3 psi @
1,800bbl/day
Maximum Production
Pressure drop 96.4 psi @
5,000bbl/day
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Material Selection
• RTP Components
 Inner Liner- Fluid Compatibility
 Reinforcement- Strength
 Jacket- Protects Reinforcement
• Liner- PPS/Fortron
 Hydrocarbon CO2, H2S, Brine
Resistance (Norsok 710 Testing)
 Low Permeation
• Reinforcement - Aramid/Twaron
 Static/Cyclic Strength
 Resistance to the Environment
• Outer Jacket- Nylon
 Abrasion Resistance
 Hydrocarbon Resistance
Aramid Reinforcement
PPS Liner
Volume (%) Composition
30 3% CO2, 2% H2S, 95% CH4
10 Distilled water (conductivity < 5 µS)
60 70% heptane, 20% cyclohexane, 10% toluene
Composition of NORSOK M710 Solution
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Nylon Jacket
RTP Components
Chemical Resistance and Permeation of PPS/Fortron
30
35
40
45
50
55
60
0 20 40 60 80 100 120
190
C
170
C
160
C
150
C
Tensile Strength of Fortron PPS (MPa) as a function of Ageing
(Days) from 140-190C
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Pre-Planning Project Layout
Spool off Location
Riser Termination
Project Pre-planning
• Gauging Pig for Existing Line
• Pull Force Analysis
• Wet vs. Dry
• 1,818 Kg Pull Force Wet
• Synthetic Rope (5X Safety Factor)
• Project Layout
• Platform Space vs. Boat
• Individual Steps
• Responsible Party
• Underwater Work
• Riser Bottom Bend Modifications
• Subsea Bend Modification
• Top Side Spools Modifications
• Project Scheduling
• Capabilities of Platform Equipment
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Platform A Platform B
Existing Pipeline
Plastic Insert Pipe
Messenger Pig
Cross-section
Messenger pig
Winch Spool Reel
Installation Method: Planning
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Installation Method: Planning
Winch
Existing Pipeline
Plastic Insert Pipe
Messenger Pig
Spool Reel
Cross-section
Plastic Insert Pipe
Platform A Platform B
Messenger wire
Winch
Platform A Platform B
Cross-section
Existing PL 112
Plastic Insert Pipe
Messenger Wire
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Installation Method: Actual
Winch
Platform A Platform B
Cross-section
Existing PL 112
Plastic Insert Pipe
Messenger Wire
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Installation Method: Actual
Spool
Reel
Vessel
Plastic Insert Pipe
Installing the RTP
• Cleaning the Line – Scrape Both
Directions
• Erect Scaffolding to Align Pipe from
Boat
• Foam Pig Synthetic Rope Through
Pipeline
• Set up Winch for Pulling
• Align Pulleys over Flange Opening
• Attach Pulling Cone to Pipe and
Cable
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Erecting Scaffolding
Cleaning Activity for Existing LineRTP Pull Thru Activity
Pulling the RTP and Splice Joints
• Pull Rate – 20m/min
• Cable Passed Through Load Cell
• Pull Force At Expected Value
• Indicator for Hang-ups
• Spliced Couplings
• 300 Meters Per Pipe Length
• Duplex 2205 Joint Splices
• End Connections
• Double Faced RTJ Flanged
• Seal off Annular Space
• Port on Annulus with Pressure Gage
Boat to Scaffold
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
RTP Pulling Activity
Jointing between two portions of RTP pipe
Splice Coupling
Inspection of the RTP After Pull Through
• Inspect Pulled RTP
• Inspect for Gouges & Jacket
Breaches
• Deformation in Pipe
• Cut to Length & Install
Termination
• Hydro- Test at 2X MAOP for 24
Hours (360PSI)
• Design Pressure – 1,440PSI
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Final Pull Out of RTP
Final Spool Make-up
Hydrotest Pressure Chart
Analysis of Benefits
• After One Year of Operation
 Flowing 1,800bb – 7,000bbl/day
• 7,000bbl/day Causing Excessive
Back Pressure
 No Chemical Treatment
 No Pigging/ Cleanout
• CAPEX 67% Lower than New Steel Line
 Eliminating Riser Modifications &
Pulling from Boat Creates 80+ %
Savings
• Benefit to Environment compared to
conventional steel replacement
 Minimum disturbance to seafloor &
marine life
 Reused of existing steel pipeline
• Existing Steel Line Remains Part of the
System and is not Abandoned
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Lessons Learned – Areas for Improvement
• Improvement in Planning
• Changed from Platform to Platform vs Boat to Platform
• Platform Deck Space Availability
• Crane on Platform Inoperable
• Making Sure Continuous Back Tension on Pipe During Pulling
• Sharp Changes in Tension can Kink Pipe
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Kink Portion Observed During Pulling Activity
Lessons Learned – Areas for Improvement cont.
• Better Pulling Rope Design to
Minimize Damage During Pulling
• Nylon Jacket on Rope too Thin
• Tore As Pulled Through Riser
• Rub on Sharp Flange
• Wrinkling Create Hang-up
• No Issue with Pipe
• Rope Broke 1 Meter from End of
Pull – Finish with Cable
• Jacket Tears Hung Up in Load
Cell
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Final Pull Out of RTP
Wrinkling of Pulling Rope When Bent Damage layer of Pulling Rope
Lessons Learned – Areas for Improvement cont.
• Alternative Rope Designs
• Heavier Nylon Jacket
• Braided Jacket
• Braided Jacket with Nylon Jacket
• Testing Ongoing
OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced
Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim,
Kennedy
Acknowledgements
Slide 22
Special thanks to:
a) P&E Management, PCSB
b) SBO Management, PCSB
- Maintenance & Operation, SBO
c) Samarang Operations
d) Technology Provider
- Polyflow Inc.
e) Contractors
Acknowledgements / Thank You / Questions
Slide 23
Appendix
OTC Asia 2014 Petronas
OTC Asia 2014 Petronas

More Related Content

What's hot

KPH- 4-2-15 resume-v2
KPH- 4-2-15 resume-v2KPH- 4-2-15 resume-v2
KPH- 4-2-15 resume-v2kim himel
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull
 
Mark c resume installation
Mark c resume installationMark c resume installation
Mark c resume installationMark Hensley
 
modeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by femmodeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by fem9845097705
 
Veerappa Panchal_Piping Stress Engineer
Veerappa Panchal_Piping Stress EngineerVeerappa Panchal_Piping Stress Engineer
Veerappa Panchal_Piping Stress Engineerveerappa panchal
 
CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000daniel cobar
 
Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland
 
peter.fitzpatrick.cv.2016-2017
peter.fitzpatrick.cv.2016-2017peter.fitzpatrick.cv.2016-2017
peter.fitzpatrick.cv.2016-2017Peter Fitzpatrick
 
Leisa Boos Resume 2016doc
Leisa Boos  Resume 2016docLeisa Boos  Resume 2016doc
Leisa Boos Resume 2016docLeisa B
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaMichaelUberti
 
ge_dp_scp_brochure
ge_dp_scp_brochurege_dp_scp_brochure
ge_dp_scp_brochureYanyan Wu
 
02 pipeline systems engineering and routing considerations
02   pipeline systems engineering and routing considerations02   pipeline systems engineering and routing considerations
02 pipeline systems engineering and routing considerationsalco345ua
 

What's hot (20)

KPH- 4-2-15 resume-v2
KPH- 4-2-15 resume-v2KPH- 4-2-15 resume-v2
KPH- 4-2-15 resume-v2
 
Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012Richard Turnbull CV Supplement 2012
Richard Turnbull CV Supplement 2012
 
Final Project Presentation
Final Project PresentationFinal Project Presentation
Final Project Presentation
 
Mark c resume installation
Mark c resume installationMark c resume installation
Mark c resume installation
 
modeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by femmodeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by fem
 
Latest CV of Gangadhar
Latest CV of GangadharLatest CV of Gangadhar
Latest CV of Gangadhar
 
Shafiq CV
Shafiq CVShafiq CV
Shafiq CV
 
Veerappa Panchal_Piping Stress Engineer
Veerappa Panchal_Piping Stress EngineerVeerappa Panchal_Piping Stress Engineer
Veerappa Panchal_Piping Stress Engineer
 
A SATTAR DC&WI CV-II
A SATTAR DC&WI CV-IIA SATTAR DC&WI CV-II
A SATTAR DC&WI CV-II
 
A SATTAR DC&WI CV-II
A SATTAR DC&WI CV-IIA SATTAR DC&WI CV-II
A SATTAR DC&WI CV-II
 
CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000CV MECHANICAL ENGR-2000
CV MECHANICAL ENGR-2000
 
Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015Thomas Cleveland Resume'- June 20th 2015
Thomas Cleveland Resume'- June 20th 2015
 
Acoustic emission
Acoustic emissionAcoustic emission
Acoustic emission
 
A SATTAR DC&WI CV-II
A SATTAR DC&WI CV-IIA SATTAR DC&WI CV-II
A SATTAR DC&WI CV-II
 
peter.fitzpatrick.cv.2016-2017
peter.fitzpatrick.cv.2016-2017peter.fitzpatrick.cv.2016-2017
peter.fitzpatrick.cv.2016-2017
 
Leisa Boos Resume 2016doc
Leisa Boos  Resume 2016docLeisa Boos  Resume 2016doc
Leisa Boos Resume 2016doc
 
RV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey Australia
 
Infrastructure preservation bridge inspection presentation 2018
Infrastructure preservation bridge inspection presentation 2018Infrastructure preservation bridge inspection presentation 2018
Infrastructure preservation bridge inspection presentation 2018
 
ge_dp_scp_brochure
ge_dp_scp_brochurege_dp_scp_brochure
ge_dp_scp_brochure
 
02 pipeline systems engineering and routing considerations
02   pipeline systems engineering and routing considerations02   pipeline systems engineering and routing considerations
02 pipeline systems engineering and routing considerations
 

Similar to OTC Asia 2014 Petronas

CV-AnirbanDatta-Stress Analysis-2016-03-25
CV-AnirbanDatta-Stress Analysis-2016-03-25CV-AnirbanDatta-Stress Analysis-2016-03-25
CV-AnirbanDatta-Stress Analysis-2016-03-25Anirban Datta, CEng
 
CV of MK Patham-Inner-groove Copper tube project
CV of MK Patham-Inner-groove Copper tube projectCV of MK Patham-Inner-groove Copper tube project
CV of MK Patham-Inner-groove Copper tube projectKunchitha Patham
 
2018 general frc_2018_12
2018 general frc_2018_122018 general frc_2018_12
2018 general frc_2018_12AsuSSEBENA
 
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanHDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanIndiaMART InterMESH Limited
 
Prem CV Oct 2015
Prem CV Oct 2015Prem CV Oct 2015
Prem CV Oct 2015Prem Kumar
 
Resume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerResume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerTarun Sharna
 
Resume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerResume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerTarun Sharna
 
AME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESAME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESCarlo Avanzini
 
number 1. pro cv
number 1. pro cvnumber 1. pro cv
number 1. pro cvDave Chase
 
Pilot Tube Guided Boring Solutions Meet Project Challenges
Pilot Tube Guided Boring Solutions Meet Project ChallengesPilot Tube Guided Boring Solutions Meet Project Challenges
Pilot Tube Guided Boring Solutions Meet Project ChallengesLaura Anderson
 

Similar to OTC Asia 2014 Petronas (20)

CV-AnirbanDatta-Stress Analysis-2016-03-25
CV-AnirbanDatta-Stress Analysis-2016-03-25CV-AnirbanDatta-Stress Analysis-2016-03-25
CV-AnirbanDatta-Stress Analysis-2016-03-25
 
Nazmy Markos
Nazmy MarkosNazmy Markos
Nazmy Markos
 
Srp 2018 00
Srp 2018 00Srp 2018 00
Srp 2018 00
 
Cv of mr.Jefferson Tomas Tulabot
Cv of mr.Jefferson Tomas TulabotCv of mr.Jefferson Tomas Tulabot
Cv of mr.Jefferson Tomas Tulabot
 
Nazmy Markos
Nazmy MarkosNazmy Markos
Nazmy Markos
 
Engineering and Design Webinar - September
Engineering and Design Webinar - SeptemberEngineering and Design Webinar - September
Engineering and Design Webinar - September
 
ASCE San Ramon Canyon Storm Drain 6 4-15
ASCE San Ramon Canyon Storm Drain 6 4-15 ASCE San Ramon Canyon Storm Drain 6 4-15
ASCE San Ramon Canyon Storm Drain 6 4-15
 
CV of MK Patham-Inner-groove Copper tube project
CV of MK Patham-Inner-groove Copper tube projectCV of MK Patham-Inner-groove Copper tube project
CV of MK Patham-Inner-groove Copper tube project
 
2018 general frc_2018_12
2018 general frc_2018_122018 general frc_2018_12
2018 general frc_2018_12
 
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanHDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
 
Prem CV Oct 2015
Prem CV Oct 2015Prem CV Oct 2015
Prem CV Oct 2015
 
Resume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerResume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineer
 
Resume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineerResume - Tarun Sharma - Pipe stress engineer
Resume - Tarun Sharma - Pipe stress engineer
 
Resume S B Mohapatra -SEP2015
Resume S B Mohapatra -SEP2015Resume S B Mohapatra -SEP2015
Resume S B Mohapatra -SEP2015
 
Paper
PaperPaper
Paper
 
Engineering & Design - April
Engineering & Design - April Engineering & Design - April
Engineering & Design - April
 
AME POWER PLANT REFERENCES
AME POWER PLANT REFERENCESAME POWER PLANT REFERENCES
AME POWER PLANT REFERENCES
 
Mithun Banjan CV
Mithun Banjan CVMithun Banjan CV
Mithun Banjan CV
 
number 1. pro cv
number 1. pro cvnumber 1. pro cv
number 1. pro cv
 
Pilot Tube Guided Boring Solutions Meet Project Challenges
Pilot Tube Guided Boring Solutions Meet Project ChallengesPilot Tube Guided Boring Solutions Meet Project Challenges
Pilot Tube Guided Boring Solutions Meet Project Challenges
 

OTC Asia 2014 Petronas

  • 1. OTC-24721-MS A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field John R Wright Jr. Polyflow LLC, Khairul Anuar Karim, PETRONAS Carigali and Steve Kennedy, SCG Oil and Gas
  • 2. Agenda 1) Background 2) Steps and Analysis for Successful Rehabilitation 3) Details of the Installation 4) Benefits Analysis 5) Areas for Improvement 6) Q & A Slide 2 OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy
  • 3. Background • PL-112 Pipeline • 52 Km off Labuan in Samarang Field • 8-10 Meters of Water • 6” API -5L X-42 Steel Pipe Installed in 1977 • Approximately 1Kilometer • Anchor Hooked Pipe Causing a Kink in 2009 • Repairs Made with Misalignment Flanges • Difficulty in Maintenance and Loss of Wall Thickness Concluded Repairs as Temporary • Current Infield Drilling • Required New Pipeline for Next 25 Years • New Steel Pipeline Replacement and Reinforced Thermoplastic Pipe Rehabilitation were Evaluated • Future Flowing Conditions • 1,800bbl – 5,000bbl/day Depending upon Field Requirements • Concern with SRB’s in Future • Low Formation Pressure OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy
  • 4. Analysis and Planning Steps for RTP Rehab • Sizing of the New Flow Line • Material Selection • Pull Force Analysis • Selection of Pulling Equipment • Detailed Layout of Project OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy
  • 5. Proper Sizing of Pipe Slide 5 • Sized for Desired Production  Fits Inside of Existing Steel  Acceptable Pressure Drop for Formation  Ideally Fits Through Existing Risers • Design for Maintaining Minimum Velocities  0.61m/s will Carry Solids in Liquids  Reduces Ongoing Maintenance (Pigging) • Selected 3.5” RTP (2.95” ID)  Acceptable Pressure Drops  Minimal Velocities for Range of Flow  Risers Have to be Modified Modified Riser with 12D Bend OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy Existing Riser with 5D Bend
  • 6. Pressure Drops and Critical Velocities for 3.5” RTP Velocity at 1,800bbl/day is 2 ft./sec (0.61 m/sec) Typical Production Volume Pressure Drop of 15.3 psi @ 1,800bbl/day Maximum Production Pressure drop 96.4 psi @ 5,000bbl/day OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy
  • 7. Material Selection • RTP Components  Inner Liner- Fluid Compatibility  Reinforcement- Strength  Jacket- Protects Reinforcement • Liner- PPS/Fortron  Hydrocarbon CO2, H2S, Brine Resistance (Norsok 710 Testing)  Low Permeation • Reinforcement - Aramid/Twaron  Static/Cyclic Strength  Resistance to the Environment • Outer Jacket- Nylon  Abrasion Resistance  Hydrocarbon Resistance Aramid Reinforcement PPS Liner Volume (%) Composition 30 3% CO2, 2% H2S, 95% CH4 10 Distilled water (conductivity < 5 µS) 60 70% heptane, 20% cyclohexane, 10% toluene Composition of NORSOK M710 Solution OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy Nylon Jacket RTP Components
  • 8. Chemical Resistance and Permeation of PPS/Fortron 30 35 40 45 50 55 60 0 20 40 60 80 100 120 190 C 170 C 160 C 150 C Tensile Strength of Fortron PPS (MPa) as a function of Ageing (Days) from 140-190C OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy
  • 9. OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy Pre-Planning Project Layout Spool off Location Riser Termination
  • 10. Project Pre-planning • Gauging Pig for Existing Line • Pull Force Analysis • Wet vs. Dry • 1,818 Kg Pull Force Wet • Synthetic Rope (5X Safety Factor) • Project Layout • Platform Space vs. Boat • Individual Steps • Responsible Party • Underwater Work • Riser Bottom Bend Modifications • Subsea Bend Modification • Top Side Spools Modifications • Project Scheduling • Capabilities of Platform Equipment OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy
  • 11. OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy Platform A Platform B Existing Pipeline Plastic Insert Pipe Messenger Pig Cross-section Messenger pig Winch Spool Reel Installation Method: Planning
  • 12. OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy Installation Method: Planning Winch Existing Pipeline Plastic Insert Pipe Messenger Pig Spool Reel Cross-section Plastic Insert Pipe Platform A Platform B
  • 13. Messenger wire Winch Platform A Platform B Cross-section Existing PL 112 Plastic Insert Pipe Messenger Wire OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy Installation Method: Actual
  • 14. Winch Platform A Platform B Cross-section Existing PL 112 Plastic Insert Pipe Messenger Wire OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy Installation Method: Actual Spool Reel Vessel Plastic Insert Pipe
  • 15. Installing the RTP • Cleaning the Line – Scrape Both Directions • Erect Scaffolding to Align Pipe from Boat • Foam Pig Synthetic Rope Through Pipeline • Set up Winch for Pulling • Align Pulleys over Flange Opening • Attach Pulling Cone to Pipe and Cable OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy Erecting Scaffolding Cleaning Activity for Existing LineRTP Pull Thru Activity
  • 16. Pulling the RTP and Splice Joints • Pull Rate – 20m/min • Cable Passed Through Load Cell • Pull Force At Expected Value • Indicator for Hang-ups • Spliced Couplings • 300 Meters Per Pipe Length • Duplex 2205 Joint Splices • End Connections • Double Faced RTJ Flanged • Seal off Annular Space • Port on Annulus with Pressure Gage Boat to Scaffold OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy RTP Pulling Activity Jointing between two portions of RTP pipe Splice Coupling
  • 17. Inspection of the RTP After Pull Through • Inspect Pulled RTP • Inspect for Gouges & Jacket Breaches • Deformation in Pipe • Cut to Length & Install Termination • Hydro- Test at 2X MAOP for 24 Hours (360PSI) • Design Pressure – 1,440PSI OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy Final Pull Out of RTP Final Spool Make-up Hydrotest Pressure Chart
  • 18. Analysis of Benefits • After One Year of Operation  Flowing 1,800bb – 7,000bbl/day • 7,000bbl/day Causing Excessive Back Pressure  No Chemical Treatment  No Pigging/ Cleanout • CAPEX 67% Lower than New Steel Line  Eliminating Riser Modifications & Pulling from Boat Creates 80+ % Savings • Benefit to Environment compared to conventional steel replacement  Minimum disturbance to seafloor & marine life  Reused of existing steel pipeline • Existing Steel Line Remains Part of the System and is not Abandoned OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy
  • 19. Lessons Learned – Areas for Improvement • Improvement in Planning • Changed from Platform to Platform vs Boat to Platform • Platform Deck Space Availability • Crane on Platform Inoperable • Making Sure Continuous Back Tension on Pipe During Pulling • Sharp Changes in Tension can Kink Pipe OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy Kink Portion Observed During Pulling Activity
  • 20. Lessons Learned – Areas for Improvement cont. • Better Pulling Rope Design to Minimize Damage During Pulling • Nylon Jacket on Rope too Thin • Tore As Pulled Through Riser • Rub on Sharp Flange • Wrinkling Create Hang-up • No Issue with Pipe • Rope Broke 1 Meter from End of Pull – Finish with Cable • Jacket Tears Hung Up in Load Cell OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy Final Pull Out of RTP Wrinkling of Pulling Rope When Bent Damage layer of Pulling Rope
  • 21. Lessons Learned – Areas for Improvement cont. • Alternative Rope Designs • Heavier Nylon Jacket • Braided Jacket • Braided Jacket with Nylon Jacket • Testing Ongoing OTC-24721-MS- A Case Study Detailing the Design, Planning, Installation and Cost and Environmental Benefit Analysis of a Reinforced Thermoplastic Pipe Pulled Through the Inside of an Existing Offshore Steel Flow Line in the East Malaysia Samarang Field- Wright, Karim, Kennedy
  • 22. Acknowledgements Slide 22 Special thanks to: a) P&E Management, PCSB b) SBO Management, PCSB - Maintenance & Operation, SBO c) Samarang Operations d) Technology Provider - Polyflow Inc. e) Contractors
  • 23. Acknowledgements / Thank You / Questions Slide 23