HSE AUDIT REPORT
Notes: NCR shall be finalized and feedback to HSE Group after 03 days
Pr-HSE-07-32
I. INTRODUCTION
Pjt name Work scope Contract amount No. of workers
Safety budget
(plan/actual)
Progress
(plan/actual)
 SITE INFORMATION
Overview Current work Current work
Pr-HSE-07-32
1. ENVIRONMENT PERFORMANCE
NO Items Subcontractor
Resul
Remark
Before last
month
Last month This month
1 Material yard (arrangement)
2
Housekeeping (working area
and non-working area)
Note: 03 monthly continuously un-improvement, action plan shall be conducted by site
I = Improved; U = Unimproved
II. SITE HSE SITUATION
Pr-HSE-07-32
NO
Subcon’
(SM)
Work scope
(location)
Site Manager
CE/SE
in charged
Before After
NC/Unsafe
Description
/Suggestion
Improved
measure
# ENVIRONMENT PERFORMANCE BAD PRACTICE
Pr-HSE-07-32
2. BEAUTIFUL SITE PERFORMANCE
Items Detail Requirement Checked items
Result
Comments
OK NC
Toilet
Equipment Equipment installation (door knob, paper box and paper, water, soup, tissue )
Hygiene Housekeeping inside, surrounding and floor hygiene
Rest place
Equipment Table, chair, bed, water providing
Hygiene Maintaining situation
Way of
change
Installed Install following standard (signboard, led, handle bar)
Maintaining Using and maintaining situation
Compliance Workers use the handle bar when access
Internal
access way
(if provided)
Installation Access way installed at the jobsite for worker and vehicle
Worker management Workers follow the designated access way
Guide center
Situation Installed follow standard, cleaning situation
Security staff Security’s uniform (helmet, shoes), hygiene and attitude
Material
yard
Layout
Designating material storage yard, separate each kind of materials and access
way for yard situation
Storage management Storage with safe height, fixed and well displaced
Housekeep-
ping
Before work
(preparation)
Checking and using suitable quantity for work
During & after work Rearrange material, cleanup
Canteen (if
provided)
Hygiene (food safety) Canteen floor, food displace table …
Cooking staff Attitude, hygiene uniform
Health check
/ medical
(if provided)
Health check
Health check when recruit, yearly check and monitoring health of worker for
dangerous work
Medical box Provision medicine sufficiently
Medical device Blood pressure meter, alcoholic meter, monitoring temperature and humid
Pr-HSE-07-32
NO 1
Subcon’
(SM)
Work scope
(location)
Site Manager
CE/SE
in charged
Before After
NC/Unsafe
Description
/Suggestion
Improved
measure
# BEAUTYFUL SITE BAD PRACTICE
Pr-HSE-07-32
3. BASIC SAFETY PERFORMANCE
NO Items Subcontractor
Result
Remark
Before last
month
Last month This month
1
Providing PPE (helmet, shoes,
uniform, belt)
2
Scaffolding (working platform,
cross bracing, base, support)
3 Safety handrail
4 Opening area and cover
5 Electric safety control
Note: 03 monthly continuously un-improvement, action plan shall be conducted by site
I = Improved; U = Unimproved
Pr-HSE-07-32
NO 1
Subcon’
(SM)
Work scope
(location)
Site Manager
CE/SE
in charged
Before After
NC/Unsafe
Description
/Suggestion
Improved
measure
# SAFETY PERFORMANCE BAD PRACTICE
Pr-HSE-07-32
No Items
Result
Comments
Feedback by site
(evidence attached)
OK NC N/A
1
One-out & Three out commitment of
Subcontract’s director
2
One-out & Three out commitment of
workers
3
One-out & Three out: Training for
violated workers (list & picture)
4
One-out & Three out: Discipline
conducted (record)
5
One-out & Three out: Status checking
board (Installing the board in office &
monitoring)
6 Participation of CM, CE, SE
4. CONDUCTING THE ONE OUT – THREE OUT REQULATION
Pr-HSE-07-32
5. DOCUMENTATION PERFORMANCE
Type Items to be checked
Check
Comments
Feedback by site
(evidence attached)
OK NC N/A
1.
Documentation
requirements
1 Risk assessment record & JSA
2 Joint management patrol report / record
3 PTW record
4
HSE committee minute meeting (Safety Day 3rd)
record
5
HSE committee minute meeting (weekly & monthly)
record
6
Safety Inspection Day report / record (including tools
and electric devices)
7 The Environment Day (every Saturday) report / record
8
Training newcomer (induction) and annual, special,
one out – three out, hazard,… record
9 HSE Organization chart record
10 Daily & weekly report
11 HSE plan
12 Safety facilities installation plan
13 TBM registered list and manpower update record
14 HSE feedback patrol report
15
Accident status & report (near miss, incident,
accident) & manpower accumulation record
16 Entrance card for employees / tag
17 HSE campaign record
Pr-HSE-07-32
5. DOCUMENTATION PERFORMANCE
Tasks Items to be checked
Check
Comments
Feedback by site
(evidence attached)
OK NC N/A
2.
Legal
requirement
1 Subcon's safety plan / method statement
2 Subcon's worker info: ID, contract, health check, certificate
3 Subcon's WCI
4
Subcon's equipment safety document: operator license,
signalman, banksman, rigger safety training certificates,
verification certificate, insurance
5
Dangerous equipment (vehicle, bottle) report: daily, monthly checking
– maintenance – repair record
6 Earth / ground and lighting resistant testing
7 Medical contract
8 First aid kit and facilities
9 Hazardous waste registration
10
Hazardous waste transportation & disposal contract and waste source
registration
11 Underground water using and discharge license
12 MSDS for chemical
13 Fire drill plan / other emergency drill record
14 Drinking water test certificate
15 Vector control record
16 Toilet, tissue, washing water, soap provided
17 Health check record (yearly – engineer)
18
Environment Impact Evaluation document (Including environment
protection commitment)
19 Environmental monitoring report (4 times/ year)
20 Labor & hygiene monitoring report (2 times/year)
21 Authority inspection periodically record (DOLISA, DOC )
22 Other issues

More Related Content

Similar to HSE Evaluation FORM-V4-by ssg of Pebsteel building co.,Ltd

Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...Canberra Institute of technology
 
54231708 hse-audit-hse-procedure
54231708 hse-audit-hse-procedure54231708 hse-audit-hse-procedure
54231708 hse-audit-hse-procedureMohammed Alam
 
Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...Canberra Institute of technology
 
Presentation SLOB Material Reduction
Presentation SLOB Material ReductionPresentation SLOB Material Reduction
Presentation SLOB Material ReductionCATHERINE NGUYEN
 
Engineering plant facilities 12 mechanics building preventive maintenance and...
Engineering plant facilities 12 mechanics building preventive maintenance and...Engineering plant facilities 12 mechanics building preventive maintenance and...
Engineering plant facilities 12 mechanics building preventive maintenance and...Luis Cabrera
 
Hse presentation general rev.00 may 2014
Hse presentation general rev.00 may 2014Hse presentation general rev.00 may 2014
Hse presentation general rev.00 may 2014Fitri Ifony
 
Investigation report 05.12.2017 lifting operation failure during tower erect...
Investigation report 05.12.2017  lifting operation failure during tower erect...Investigation report 05.12.2017  lifting operation failure during tower erect...
Investigation report 05.12.2017 lifting operation failure during tower erect...Arber Dogani
 
Prevention of occupational diseases
Prevention of occupational diseasesPrevention of occupational diseases
Prevention of occupational diseasesArun Raj
 
Prevention of occupational diseases
Prevention of occupational diseasesPrevention of occupational diseases
Prevention of occupational diseasesArun Raj
 
Misión, Función y Estructura Organizacional de los Servicios del Departamento...
Misión, Función y Estructura Organizacional de los Servicios del Departamento...Misión, Función y Estructura Organizacional de los Servicios del Departamento...
Misión, Función y Estructura Organizacional de los Servicios del Departamento...Rigoberto José Meléndez Cuauro
 
EHS Tracker 27.01.2023.pptx
EHS Tracker 27.01.2023.pptxEHS Tracker 27.01.2023.pptx
EHS Tracker 27.01.2023.pptxzoredatta1
 

Similar to HSE Evaluation FORM-V4-by ssg of Pebsteel building co.,Ltd (20)

4. Assessment Practical.docx
4. Assessment Practical.docx4. Assessment Practical.docx
4. Assessment Practical.docx
 
Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...Practical assessment 4 - Identify construction work hazards and select risk c...
Practical assessment 4 - Identify construction work hazards and select risk c...
 
PPT ON PERMIT TO WORK, by Ekemezie E
PPT ON PERMIT TO WORK, by Ekemezie EPPT ON PERMIT TO WORK, by Ekemezie E
PPT ON PERMIT TO WORK, by Ekemezie E
 
54231708 hse-audit-hse-procedure
54231708 hse-audit-hse-procedure54231708 hse-audit-hse-procedure
54231708 hse-audit-hse-procedure
 
3. Assessment Practical.docx
3. Assessment Practical.docx3. Assessment Practical.docx
3. Assessment Practical.docx
 
Naren_Saudi
Naren_SaudiNaren_Saudi
Naren_Saudi
 
Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...Practical assessment 3 - Identify construction work hazards and select risk c...
Practical assessment 3 - Identify construction work hazards and select risk c...
 
AMT CV (3)
AMT CV (3)AMT CV (3)
AMT CV (3)
 
Presentation SLOB Material Reduction
Presentation SLOB Material ReductionPresentation SLOB Material Reduction
Presentation SLOB Material Reduction
 
Subhani_CV1
Subhani_CV1Subhani_CV1
Subhani_CV1
 
Engineering plant facilities 12 mechanics building preventive maintenance and...
Engineering plant facilities 12 mechanics building preventive maintenance and...Engineering plant facilities 12 mechanics building preventive maintenance and...
Engineering plant facilities 12 mechanics building preventive maintenance and...
 
Gobi resume
Gobi resumeGobi resume
Gobi resume
 
Hse presentation general rev.00 may 2014
Hse presentation general rev.00 may 2014Hse presentation general rev.00 may 2014
Hse presentation general rev.00 may 2014
 
WHS practical.docx
WHS practical.docxWHS practical.docx
WHS practical.docx
 
Investigation report 05.12.2017 lifting operation failure during tower erect...
Investigation report 05.12.2017  lifting operation failure during tower erect...Investigation report 05.12.2017  lifting operation failure during tower erect...
Investigation report 05.12.2017 lifting operation failure during tower erect...
 
WHS_Practical Assessment.docx
WHS_Practical Assessment.docxWHS_Practical Assessment.docx
WHS_Practical Assessment.docx
 
Prevention of occupational diseases
Prevention of occupational diseasesPrevention of occupational diseases
Prevention of occupational diseases
 
Prevention of occupational diseases
Prevention of occupational diseasesPrevention of occupational diseases
Prevention of occupational diseases
 
Misión, Función y Estructura Organizacional de los Servicios del Departamento...
Misión, Función y Estructura Organizacional de los Servicios del Departamento...Misión, Función y Estructura Organizacional de los Servicios del Departamento...
Misión, Función y Estructura Organizacional de los Servicios del Departamento...
 
EHS Tracker 27.01.2023.pptx
EHS Tracker 27.01.2023.pptxEHS Tracker 27.01.2023.pptx
EHS Tracker 27.01.2023.pptx
 

Recently uploaded

Principle of erosion control- Introduction to contouring,strip cropping,conto...
Principle of erosion control- Introduction to contouring,strip cropping,conto...Principle of erosion control- Introduction to contouring,strip cropping,conto...
Principle of erosion control- Introduction to contouring,strip cropping,conto...ZAPPAC1
 
Book Call Girls in Kathua { 9332606886 } VVIP NISHA Call Girls Near 5 Star Hotel
Book Call Girls in Kathua { 9332606886 } VVIP NISHA Call Girls Near 5 Star HotelBook Call Girls in Kathua { 9332606886 } VVIP NISHA Call Girls Near 5 Star Hotel
Book Call Girls in Kathua { 9332606886 } VVIP NISHA Call Girls Near 5 Star Hotelkumargunjan9515
 
Call girl in Ajman 0503464457 Ajman Call girl services
Call girl in Ajman 0503464457 Ajman Call girl servicesCall girl in Ajman 0503464457 Ajman Call girl services
Call girl in Ajman 0503464457 Ajman Call girl servicesMonica Sydney
 
RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995garthraymundo123
 
Cyclone Case Study Odisha 1999 Super Cyclone in India.
Cyclone Case Study Odisha 1999 Super Cyclone in India.Cyclone Case Study Odisha 1999 Super Cyclone in India.
Cyclone Case Study Odisha 1999 Super Cyclone in India.cojitesh
 
Call Girls in Gachibowli / 8250092165 Genuine Call girls with real Photos and...
Call Girls in Gachibowli / 8250092165 Genuine Call girls with real Photos and...Call Girls in Gachibowli / 8250092165 Genuine Call girls with real Photos and...
Call Girls in Gachibowli / 8250092165 Genuine Call girls with real Photos and...kumargunjan9515
 
Call Girls in Dattatreya Nagar / 8250092165 Genuine Call girls with real Phot...
Call Girls in Dattatreya Nagar / 8250092165 Genuine Call girls with real Phot...Call Girls in Dattatreya Nagar / 8250092165 Genuine Call girls with real Phot...
Call Girls in Dattatreya Nagar / 8250092165 Genuine Call girls with real Phot...kumargunjan9515
 
Joka \ Call Girls Service Kolkata - 450+ Call Girl Cash Payment 8005736733 Ne...
Joka \ Call Girls Service Kolkata - 450+ Call Girl Cash Payment 8005736733 Ne...Joka \ Call Girls Service Kolkata - 450+ Call Girl Cash Payment 8005736733 Ne...
Joka \ Call Girls Service Kolkata - 450+ Call Girl Cash Payment 8005736733 Ne...HyderabadDolls
 
Introduction to heat waves and Heatwaves in Bangladesh.pptx
Introduction to heat waves and Heatwaves in Bangladesh.pptxIntroduction to heat waves and Heatwaves in Bangladesh.pptx
Introduction to heat waves and Heatwaves in Bangladesh.pptxNazmusSakibNS
 
Trusted call girls in Fatehabad 9332606886 High Profile Call Girls You Can...
Trusted call girls in Fatehabad   9332606886  High Profile Call Girls You Can...Trusted call girls in Fatehabad   9332606886  High Profile Call Girls You Can...
Trusted call girls in Fatehabad 9332606886 High Profile Call Girls You Can...kumargunjan9515
 
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...AICCRA
 
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi EscortsHigh Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi EscortsMonica Sydney
 
Russian Call girls in Dubai 0508644382 Dubai Call girls
Russian Call girls in Dubai 0508644382 Dubai Call girlsRussian Call girls in Dubai 0508644382 Dubai Call girls
Russian Call girls in Dubai 0508644382 Dubai Call girlsMonica Sydney
 
Faridabad Call Girl ₹7.5k Pick Up & Drop With Cash Payment 8168257667 Badarpu...
Faridabad Call Girl ₹7.5k Pick Up & Drop With Cash Payment 8168257667 Badarpu...Faridabad Call Girl ₹7.5k Pick Up & Drop With Cash Payment 8168257667 Badarpu...
Faridabad Call Girl ₹7.5k Pick Up & Drop With Cash Payment 8168257667 Badarpu...Hyderabad Escorts Agency
 
Fuel Cells and Hydrogen in Transportation - An Introduction
Fuel Cells and Hydrogen in Transportation - An IntroductionFuel Cells and Hydrogen in Transportation - An Introduction
Fuel Cells and Hydrogen in Transportation - An IntroductionGlenn Rambach
 
Hook Up Call Girls Rajgir 9332606886 High Profile Call Girls You Can Get T...
Hook Up Call Girls Rajgir   9332606886  High Profile Call Girls You Can Get T...Hook Up Call Girls Rajgir   9332606886  High Profile Call Girls You Can Get T...
Hook Up Call Girls Rajgir 9332606886 High Profile Call Girls You Can Get T...Sareena Khatun
 
2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx
2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx
2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptxEllen Book
 

Recently uploaded (20)

Principle of erosion control- Introduction to contouring,strip cropping,conto...
Principle of erosion control- Introduction to contouring,strip cropping,conto...Principle of erosion control- Introduction to contouring,strip cropping,conto...
Principle of erosion control- Introduction to contouring,strip cropping,conto...
 
Book Call Girls in Kathua { 9332606886 } VVIP NISHA Call Girls Near 5 Star Hotel
Book Call Girls in Kathua { 9332606886 } VVIP NISHA Call Girls Near 5 Star HotelBook Call Girls in Kathua { 9332606886 } VVIP NISHA Call Girls Near 5 Star Hotel
Book Call Girls in Kathua { 9332606886 } VVIP NISHA Call Girls Near 5 Star Hotel
 
Call girl in Ajman 0503464457 Ajman Call girl services
Call girl in Ajman 0503464457 Ajman Call girl servicesCall girl in Ajman 0503464457 Ajman Call girl services
Call girl in Ajman 0503464457 Ajman Call girl services
 
RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995RA 7942:vThe Philippine Mining Act of 1995
RA 7942:vThe Philippine Mining Act of 1995
 
Cyclone Case Study Odisha 1999 Super Cyclone in India.
Cyclone Case Study Odisha 1999 Super Cyclone in India.Cyclone Case Study Odisha 1999 Super Cyclone in India.
Cyclone Case Study Odisha 1999 Super Cyclone in India.
 
Call Girls in Gachibowli / 8250092165 Genuine Call girls with real Photos and...
Call Girls in Gachibowli / 8250092165 Genuine Call girls with real Photos and...Call Girls in Gachibowli / 8250092165 Genuine Call girls with real Photos and...
Call Girls in Gachibowli / 8250092165 Genuine Call girls with real Photos and...
 
Call Girls in Dattatreya Nagar / 8250092165 Genuine Call girls with real Phot...
Call Girls in Dattatreya Nagar / 8250092165 Genuine Call girls with real Phot...Call Girls in Dattatreya Nagar / 8250092165 Genuine Call girls with real Phot...
Call Girls in Dattatreya Nagar / 8250092165 Genuine Call girls with real Phot...
 
Climate Change
Climate ChangeClimate Change
Climate Change
 
Joka \ Call Girls Service Kolkata - 450+ Call Girl Cash Payment 8005736733 Ne...
Joka \ Call Girls Service Kolkata - 450+ Call Girl Cash Payment 8005736733 Ne...Joka \ Call Girls Service Kolkata - 450+ Call Girl Cash Payment 8005736733 Ne...
Joka \ Call Girls Service Kolkata - 450+ Call Girl Cash Payment 8005736733 Ne...
 
Introduction to heat waves and Heatwaves in Bangladesh.pptx
Introduction to heat waves and Heatwaves in Bangladesh.pptxIntroduction to heat waves and Heatwaves in Bangladesh.pptx
Introduction to heat waves and Heatwaves in Bangladesh.pptx
 
Trusted call girls in Fatehabad 9332606886 High Profile Call Girls You Can...
Trusted call girls in Fatehabad   9332606886  High Profile Call Girls You Can...Trusted call girls in Fatehabad   9332606886  High Profile Call Girls You Can...
Trusted call girls in Fatehabad 9332606886 High Profile Call Girls You Can...
 
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...Presentation: Farmer-led climate adaptation - Project launch and overview by ...
Presentation: Farmer-led climate adaptation - Project launch and overview by ...
 
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi EscortsHigh Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
High Profile Escort in Abu Dhabi 0524076003 Abu Dhabi Escorts
 
Russian Call girls in Dubai 0508644382 Dubai Call girls
Russian Call girls in Dubai 0508644382 Dubai Call girlsRussian Call girls in Dubai 0508644382 Dubai Call girls
Russian Call girls in Dubai 0508644382 Dubai Call girls
 
Faridabad Call Girl ₹7.5k Pick Up & Drop With Cash Payment 8168257667 Badarpu...
Faridabad Call Girl ₹7.5k Pick Up & Drop With Cash Payment 8168257667 Badarpu...Faridabad Call Girl ₹7.5k Pick Up & Drop With Cash Payment 8168257667 Badarpu...
Faridabad Call Girl ₹7.5k Pick Up & Drop With Cash Payment 8168257667 Badarpu...
 
Fuel Cells and Hydrogen in Transportation - An Introduction
Fuel Cells and Hydrogen in Transportation - An IntroductionFuel Cells and Hydrogen in Transportation - An Introduction
Fuel Cells and Hydrogen in Transportation - An Introduction
 
Hook Up Call Girls Rajgir 9332606886 High Profile Call Girls You Can Get T...
Hook Up Call Girls Rajgir   9332606886  High Profile Call Girls You Can Get T...Hook Up Call Girls Rajgir   9332606886  High Profile Call Girls You Can Get T...
Hook Up Call Girls Rajgir 9332606886 High Profile Call Girls You Can Get T...
 
Water Pollution
Water Pollution Water Pollution
Water Pollution
 
Jumping Scales and Producing peripheries.pptx
Jumping Scales and Producing peripheries.pptxJumping Scales and Producing peripheries.pptx
Jumping Scales and Producing peripheries.pptx
 
2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx
2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx
2024-05-08 Composting at Home 101 for the Rotary Club of Pinecrest.pptx
 

HSE Evaluation FORM-V4-by ssg of Pebsteel building co.,Ltd

  • 1. Think Safety Project Date Audit & Support Team Site PM HSE manager HSE AUDIT REPORT Notes: NCR shall be finalized and feedback to HSE Group after 03 days
  • 2. Pr-HSE-07-32 I. INTRODUCTION Pjt name Work scope Contract amount No. of workers Safety budget (plan/actual) Progress (plan/actual)  SITE INFORMATION Overview Current work Current work
  • 3. Pr-HSE-07-32 1. ENVIRONMENT PERFORMANCE NO Items Subcontractor Resul Remark Before last month Last month This month 1 Material yard (arrangement) 2 Housekeeping (working area and non-working area) Note: 03 monthly continuously un-improvement, action plan shall be conducted by site I = Improved; U = Unimproved II. SITE HSE SITUATION
  • 4. Pr-HSE-07-32 NO Subcon’ (SM) Work scope (location) Site Manager CE/SE in charged Before After NC/Unsafe Description /Suggestion Improved measure # ENVIRONMENT PERFORMANCE BAD PRACTICE
  • 5. Pr-HSE-07-32 2. BEAUTIFUL SITE PERFORMANCE Items Detail Requirement Checked items Result Comments OK NC Toilet Equipment Equipment installation (door knob, paper box and paper, water, soup, tissue ) Hygiene Housekeeping inside, surrounding and floor hygiene Rest place Equipment Table, chair, bed, water providing Hygiene Maintaining situation Way of change Installed Install following standard (signboard, led, handle bar) Maintaining Using and maintaining situation Compliance Workers use the handle bar when access Internal access way (if provided) Installation Access way installed at the jobsite for worker and vehicle Worker management Workers follow the designated access way Guide center Situation Installed follow standard, cleaning situation Security staff Security’s uniform (helmet, shoes), hygiene and attitude Material yard Layout Designating material storage yard, separate each kind of materials and access way for yard situation Storage management Storage with safe height, fixed and well displaced Housekeep- ping Before work (preparation) Checking and using suitable quantity for work During & after work Rearrange material, cleanup Canteen (if provided) Hygiene (food safety) Canteen floor, food displace table … Cooking staff Attitude, hygiene uniform Health check / medical (if provided) Health check Health check when recruit, yearly check and monitoring health of worker for dangerous work Medical box Provision medicine sufficiently Medical device Blood pressure meter, alcoholic meter, monitoring temperature and humid
  • 6. Pr-HSE-07-32 NO 1 Subcon’ (SM) Work scope (location) Site Manager CE/SE in charged Before After NC/Unsafe Description /Suggestion Improved measure # BEAUTYFUL SITE BAD PRACTICE
  • 7. Pr-HSE-07-32 3. BASIC SAFETY PERFORMANCE NO Items Subcontractor Result Remark Before last month Last month This month 1 Providing PPE (helmet, shoes, uniform, belt) 2 Scaffolding (working platform, cross bracing, base, support) 3 Safety handrail 4 Opening area and cover 5 Electric safety control Note: 03 monthly continuously un-improvement, action plan shall be conducted by site I = Improved; U = Unimproved
  • 8. Pr-HSE-07-32 NO 1 Subcon’ (SM) Work scope (location) Site Manager CE/SE in charged Before After NC/Unsafe Description /Suggestion Improved measure # SAFETY PERFORMANCE BAD PRACTICE
  • 9. Pr-HSE-07-32 No Items Result Comments Feedback by site (evidence attached) OK NC N/A 1 One-out & Three out commitment of Subcontract’s director 2 One-out & Three out commitment of workers 3 One-out & Three out: Training for violated workers (list & picture) 4 One-out & Three out: Discipline conducted (record) 5 One-out & Three out: Status checking board (Installing the board in office & monitoring) 6 Participation of CM, CE, SE 4. CONDUCTING THE ONE OUT – THREE OUT REQULATION
  • 10. Pr-HSE-07-32 5. DOCUMENTATION PERFORMANCE Type Items to be checked Check Comments Feedback by site (evidence attached) OK NC N/A 1. Documentation requirements 1 Risk assessment record & JSA 2 Joint management patrol report / record 3 PTW record 4 HSE committee minute meeting (Safety Day 3rd) record 5 HSE committee minute meeting (weekly & monthly) record 6 Safety Inspection Day report / record (including tools and electric devices) 7 The Environment Day (every Saturday) report / record 8 Training newcomer (induction) and annual, special, one out – three out, hazard,… record 9 HSE Organization chart record 10 Daily & weekly report 11 HSE plan 12 Safety facilities installation plan 13 TBM registered list and manpower update record 14 HSE feedback patrol report 15 Accident status & report (near miss, incident, accident) & manpower accumulation record 16 Entrance card for employees / tag 17 HSE campaign record
  • 11. Pr-HSE-07-32 5. DOCUMENTATION PERFORMANCE Tasks Items to be checked Check Comments Feedback by site (evidence attached) OK NC N/A 2. Legal requirement 1 Subcon's safety plan / method statement 2 Subcon's worker info: ID, contract, health check, certificate 3 Subcon's WCI 4 Subcon's equipment safety document: operator license, signalman, banksman, rigger safety training certificates, verification certificate, insurance 5 Dangerous equipment (vehicle, bottle) report: daily, monthly checking – maintenance – repair record 6 Earth / ground and lighting resistant testing 7 Medical contract 8 First aid kit and facilities 9 Hazardous waste registration 10 Hazardous waste transportation & disposal contract and waste source registration 11 Underground water using and discharge license 12 MSDS for chemical 13 Fire drill plan / other emergency drill record 14 Drinking water test certificate 15 Vector control record 16 Toilet, tissue, washing water, soap provided 17 Health check record (yearly – engineer) 18 Environment Impact Evaluation document (Including environment protection commitment) 19 Environmental monitoring report (4 times/ year) 20 Labor & hygiene monitoring report (2 times/year) 21 Authority inspection periodically record (DOLISA, DOC ) 22 Other issues