SlideShare a Scribd company logo
1 of 54
UTRACON STRUCTURAL SYSTEMS PVT LTD
ISO 9001 : 2008
POST TENSIONING SLABS CONSTRUCTION SEQUENCE
VIT UNIVERSITY - AMARAVATHI
11 October 2017 2
PT Flat slab : Shuttering Plan drawing
11 October 2017 3
Bottom shuttering in progress.
11 October 2017 4
Completion of Bottom shuttering.
11 October 2017 5
PT Flat slab : Reinforcement drawing
11 October 2017 6
Tying of Bottom Nominal reinforcements
11 October 2017 7
Completion of Bottom Nominal reinforcements
11 October 2017 8
Drawings For Tendon Layout indicating Pour strips and stressing
ends
11 October 2017 9
GI Ducts Laying in Progress
11 October 2017 10
Fixing of ducts at end stressing anchorages.
11 October 2017 11
Stressing end Anchorages fixed at Edge RCC Beams .
11 October 2017 12
De coiling of HT strands
HT strands are cut to
required length
11 October 2017 13
Inserting of HT strands into GI Ducts .
11 October 2017 14
Shop drawings showing Tendon Layout Profile
11 October 2017 15
Fixing of bar chairs to form tendon profile.
11 October 2017 16
Stressing end anchorage, grout vents on completion of laying
11 October 2017 17
Bursting links at Stressing anchorages
11 October 2017 18
Fixing of Dead ends and Fixing of grout vent.
11 October 2017 19
Laying of Tendons on completion
11 October 2017 20
Pour strip provided for construction feasibility
11 October 2017 21
Side Shuttering
Strands
Block Out
Castings
G.I.Duct
Grout Hose
Grout Vent
Working Platform
PT Materials
11 October 2017 22
Aerial view of Tendons Laying before concreting
11 October 2017 23
PT Flat slab after completion of Tendon laying ,before concreting
11 October 2017 24
Concreting In Progress
11 October 2017 25
Block outs/Recess Formers
at Stressing anchorages
Fixing of anchor Blocks and
wedges .
11 October 2017 26
25 % of initial stressing to remove slag.
11 October 2017 27
Stressing Of Slab Tendons.
Paint Mark shows
Elongation
11 October 2017 28
Paint Mark
shows
Elongation
11 October 2017 29
Anchorages seen after stressing in edge beams
11 October 2017 30
Excess strand has been cut after stressing
11 October 2017 31
Patching of stressing Pockets
11 October 2017 32
Adding cement in to the mixing tank
11 October 2017 33
Mixing of Cementicious Grout
11 October 2017 34
Tying the hose at other end
after witnessing good grout
mix and exists of air bubbles
if.
Closing of Grout hose end .
Primary Objective Secondary Objective
QA / QC Recommendations
Registering of Drawing
PT Laying
Profiles
Stressing
Grouting
Check the
shuttering
Check the bottom
rebar orientation
Registration of Drawing
Latest incoming drawing register should be maintained at site
office with the details of
1. Drawing number
2. Revision
3. Date of receipt
4. Date of approval by consultant.
Based on this register Project Manager has to arrange the drawing
for site execution.
PT - Laying
 Drawings to be thoroughly studied by Utracon team at site.
Clarifications are to be brought to the Utracon design team through project manager at site
Approved drawing / corresponding Engineering instructions are to be made available before
commencing the work at site.
 Tendon spacing should be followed as per tendon layout drawing.
 Duct joints are to be sealed well to avoid any ingress of concrete.
 Based on tendon layout drg, the live and dead ends are to be fixed. If any
difficulties/deviations /obstructions ,it is to be brought to the notice of concerned Design
Engineer.
Ensure that the protruding strand length is sufficient for stressing ( min 350 – 400 mm)
Based on Tendon layout no. of strands to be
threaded into ducts.
Fix the grout vents.
 Profiles need to be checked by PT team and finally verified /approved by PMC team.
 PT Engineer should make sure that while checking the profiles, all the tendon support bars &
chairs are placed at specified intervals as per the drawings.
The tolerances of vertical profiles is ± 5mm for high and low points.
 The tolerances for horizontal profiles are ± 150 mm.
Any openings / fixing of rebars ,etc. are to be provided ,the importance should be given to the
Profiles
Stressing
 Before stressing PT Engineer has to check with the cube result with the main contractor
 whether the slab has achieved the minimum cube strength as specified in design/drg.
 Once concreting is completed ,the platform are to be arranged for
carrying out the stressing with the help of Main contractor.
Remove the block outs and clean the castings to fix the anchor blocks
for stressing activity
 The theoretical elongation calculations must be approved by the consultant before stressing.
 Fix the wedge plate and wedges.
 25% of the stressing force shall be applied to the tendon to remove the slack in the strands.
 spray mark should be made to strands.
Once the cube test result is made available by main contractor,
stressing can be started to initial stressing of 25% ,to remove slacks
 Marking is to be done in strands before carrying out the 75% stressing
and elongation is to be measured This will reflect the strand’s
elongation form 25 % to 100% force.
 Elongation shall be checked with measured reading in random after 24 hrs of final
stressing to confirm that there is no slippage of strands
The recess pockets left for the stressing shall be patched with cement mortar.
Stressing
Grouting
1. After consultant /PMC has approved the stressing result ,grouting can be started.
2. Before grouting the ducts shall be thoroughly cleaned by compressed air.
3. Grout mix shall be prepared in W/C ratio of 0.45 with workability additive of 0.2% of weight
of cement.
4. Inject grout from the tendons inlet hose and lock the
outlet hose
Lock the outlet hose when the pressure of 3 bars is achieved.
6
Do Before Concreting
1. After the Bottom mat completed. We start our work
2. We lay the tendon both horizontal and vertical then fix our castings.
3. After laying of tendons both directions and making the profiles then start the
tieing of top reinforcement
4. Side shuttering can made after fixing of our casting & backing.
5. Proper VIBRATIONS required at the time of concrete (At least at the place of
live ends & Dead ends).
Do after concreting
1. Curing properly then only we can achieve the concrete strength.
2. Side shuttering should be removed next day of the concrete.
3. If any honeycomb found immediately batch up with fosroc or rich mix depends
upon honeycomb at site condition.
Don’t Do
1. Don’t walk onto tendon Profile.
2. Don’t dump materials like Rebar’s, Shuttering materials onto tendon
3. Don’t disturb tendon profile.
4. After concrete anybody should not cut the grout hose at any reason.
5. At the time of stressing anybody should not stand behind the stressing jack.
6. Don’t remove shuttering before getting approval from engineer.
DO’s and DONT’s
Don'ts
1. Don’t place the strand on the ground. It has to be placed above the ground with wooden
packers to avoid contamination.
2. Don’t start tendon laying without checking the slab bottom reinforcement orientation and
cover.
3. If you found any defect on the bulb of the strands, should be replaced with the new bulb.
4. Don’t allow the peoples to stepping on ducts.
6. Don’t commence the stressing without confirmation from main contractor on the required
cube result.
7. Don’t stand in front of the jack and look behind the jack while stressing in progress.
8. Don’t allow grouting without cleaning the ducts by using compressed air.
9. Don’t allow to do grounding if water cement ratio is more than 0.45
10. Ducts to be grouted using max pressure of 0.5 N/mm2 and not lower than 0.2N/mm2
11. Pressure should be duly controlled so as not to cause segregation of grout. Required
pressure to be maintained shall be 3 to 5 bars
LAYING CHECKLIST
STRESSING – CHECKLIST
GROUTING – CHECKLIST
Sample Elongation Calculation
1 st basement flr
D = (PL /AE)
Where P = (Po + PI) / 2
Po = Force @ Stressing end
75% UTS
0.75 X 183.7 = 138 KN
PI = Force @ Far end
E = Modulus of Elasticity = 1 9 5 KN/MM2
A = Area of Stand
PI = Po x e-(µα + kL)
Where µ = Co efficient of friction = 0 .2
K = Wobble Factor = 0 .0 0 1 7
L= Length of Tendon
α = Angular Deviation
α =
D = (PL /AE)
where P = (Po+ PI) /2
Theroritical Elongation = D
Sample Elongation Calculation:
+ +
Horizontal Distance Between HP2-LP2
4 (HP1-LP1) 4 (HP2-LP2)
Horizontal Distance Between HP1-LP1
10/11/2017
Sample Elongation Calculation
Example : Calculation of 1st basement flr
( Refer Attached Drawing)
Tendon No : T1 2 1
Length of Tendon = 1 3 .6 8 m
α = 4 (190-115) 4 (190-35) 4 (115-35)
3200 5500 4975
α = 0.27 Radian
Po= 138 KN
PI = Po x e
-(µα+ kL)
= 138 x e
-(0.2x0.271 + 0.0017x13.68)
PI = 1 2 7 .7 1 KN
D = (PL )
AE
P0+ PI X L
d1 = 2
138+ 127.71 x 13.68
= 2
100x195
Theritical Elongation = 9 3 .2 mm
+ +
AE
Jacking force
UTS= 183.7 KN
Stress=Load/Area
Apply=75%
NO OF STRAND 75% 76% 80% 75% 76% 80% Jack loss =2%
Anchorage Loss = 3%
= (183.7*0.75*1.05*1000)/3325
= 43.51 Mpa
JACK LOSS
ANCHORAGE LOSS
STRESSING PRESSURE OF ALL HIS JACK MODELS
All Pressure indicated above is in Mpa
For conversion to Bar = Mpa X 10
UTS=Ultimate tensile strength
3% 3%
46.41
PISTON AREA 3709MM2 3325MM2
2% 2%
1
39 39.52 41.6 43.51 44.09
STRAND TYPE: 0.5"(12.7MM)
TYPES OF JACK
IHS IHS
CH 258 DA CH 258 DA
UTS UTS
Jacking force
UTS= 260.7 KN
Stress=Load/Area
Apply=75%
NO OF STRAND 75% 76% 80% 75% 76% 80% Jack loss =2%
Anchorage Loss = 3%
= (260.7*0.75*1.05*1000)/3325
= 61.74 Mpa
JACK LOSS
ANCHORAGE LOSS
STRESSING PRESSURE OF ALL HIS JACK MODELS
All Pressure indicated above is in Mpa
For conversion to Bar = Mpa X 10
UTS=Ultimate tensile strength
STRAND TYPE: 0.6"(15.2MM)
3% 3%
2% 2%
UTS
TYPES OF JACK
1
PISTON AREA 3709MM2 3325MM2
55.35 56.09 59.04 61.74 62.57 65.86
CH 258 DA
IHS
UTS
IHS
CH 258 DA

More Related Content

What's hot

Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C BeamAr. Aakansha
 
Construction of post tension slab
Construction of post tension slabConstruction of post tension slab
Construction of post tension slabArvind Vishwakarma
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshulAnshul Shakya
 
crack control and crack width estimation
crack control and crack width estimationcrack control and crack width estimation
crack control and crack width estimationKumar Anjneya
 
Introduction of Reinforced Concrete Design
Introduction of Reinforced Concrete DesignIntroduction of Reinforced Concrete Design
Introduction of Reinforced Concrete Designmaylene san luis
 
Study of Bridge Bearings
Study of Bridge BearingsStudy of Bridge Bearings
Study of Bridge BearingsAyushHajare
 
Reinforcement welding in civil engineering
Reinforcement welding in civil engineeringReinforcement welding in civil engineering
Reinforcement welding in civil engineeringAmardeep Singh
 
Beam and slab design
Beam and slab designBeam and slab design
Beam and slab designIvan Ferrer
 
Design and Detailing of RC structures
Design and Detailing of RC structuresDesign and Detailing of RC structures
Design and Detailing of RC structuresgssnie
 
52436966 lecture-13-plate-girders
52436966 lecture-13-plate-girders52436966 lecture-13-plate-girders
52436966 lecture-13-plate-girdersSaleem Malik
 

What's hot (20)

Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C Beam
 
Construction of post tension slab
Construction of post tension slabConstruction of post tension slab
Construction of post tension slab
 
Beam design
Beam designBeam design
Beam design
 
Lecture 7 strap footing
Lecture 7  strap  footingLecture 7  strap  footing
Lecture 7 strap footing
 
Multi story building construction training report anshul
Multi story building construction training report anshulMulti story building construction training report anshul
Multi story building construction training report anshul
 
3370 2
3370 23370 2
3370 2
 
crack control and crack width estimation
crack control and crack width estimationcrack control and crack width estimation
crack control and crack width estimation
 
Introduction of Reinforced Concrete Design
Introduction of Reinforced Concrete DesignIntroduction of Reinforced Concrete Design
Introduction of Reinforced Concrete Design
 
EC3 design
EC3 designEC3 design
EC3 design
 
Study of Bridge Bearings
Study of Bridge BearingsStudy of Bridge Bearings
Study of Bridge Bearings
 
Bc prestressing
Bc prestressingBc prestressing
Bc prestressing
 
Reinforcement welding in civil engineering
Reinforcement welding in civil engineeringReinforcement welding in civil engineering
Reinforcement welding in civil engineering
 
Chapter27(1)
Chapter27(1)Chapter27(1)
Chapter27(1)
 
Rivet connection
Rivet connectionRivet connection
Rivet connection
 
Stepped footing
Stepped footingStepped footing
Stepped footing
 
Beam and slab design
Beam and slab designBeam and slab design
Beam and slab design
 
Design and Detailing of RC structures
Design and Detailing of RC structuresDesign and Detailing of RC structures
Design and Detailing of RC structures
 
Steel Structure Design
Steel Structure DesignSteel Structure Design
Steel Structure Design
 
52436966 lecture-13-plate-girders
52436966 lecture-13-plate-girders52436966 lecture-13-plate-girders
52436966 lecture-13-plate-girders
 
Pt slabs
Pt slabsPt slabs
Pt slabs
 

Similar to Post tensioning

Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insituLingWei11
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.Rais Uddin
 
As-Welded Tube Securing DOM-Like Dimensional Accuracy
As-Welded Tube Securing DOM-Like Dimensional AccuracyAs-Welded Tube Securing DOM-Like Dimensional Accuracy
As-Welded Tube Securing DOM-Like Dimensional AccuracyHyojeong Suh
 
Performance Mixes MnDOT Specification Report - Aggregate and Ready Mix Associ...
Performance Mixes MnDOT Specification Report - Aggregate and Ready Mix Associ...Performance Mixes MnDOT Specification Report - Aggregate and Ready Mix Associ...
Performance Mixes MnDOT Specification Report - Aggregate and Ready Mix Associ...Tumer Akakin, P.E.
 
pilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdfpilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdfAbdurRazzak187410
 
pilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdfpilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdfAbdurRazzak187410
 
14325 connels house drafting (1)
14325 connels house drafting (1)14325 connels house drafting (1)
14325 connels house drafting (1)Yousef Riad
 
Isokern Celsius stove system installation instructions
Isokern Celsius stove system installation instructionsIsokern Celsius stove system installation instructions
Isokern Celsius stove system installation instructionsSchiedel UK
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion jointakash yadav
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptxssuser480182
 
Consistency test,Initial & Final setting time of Hydraulic Cement specimen
Consistency test,Initial & Final setting time of Hydraulic Cement specimenConsistency test,Initial & Final setting time of Hydraulic Cement specimen
Consistency test,Initial & Final setting time of Hydraulic Cement specimenMUST,Mirpur AJK,Pakistan
 
abermain.firestation
abermain.firestationabermain.firestation
abermain.firestationYousef Riad
 
Good practices in PSC work.ppt
Good practices in PSC work.pptGood practices in PSC work.ppt
Good practices in PSC work.pptssusercaf1a41
 
02725 sewer manholes
02725 sewer manholes02725 sewer manholes
02725 sewer manholesAni Alikaj
 
Coupler (08102015)
Coupler (08102015)Coupler (08102015)
Coupler (08102015)Khairul Amri
 

Similar to Post tensioning (20)

Bored cast insitu
Bored cast insituBored cast insitu
Bored cast insitu
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
Presentation on Retrofittion of broken pile Reinforcement at Pile Cut off Level.
 
As-Welded Tube Securing DOM-Like Dimensional Accuracy
As-Welded Tube Securing DOM-Like Dimensional AccuracyAs-Welded Tube Securing DOM-Like Dimensional Accuracy
As-Welded Tube Securing DOM-Like Dimensional Accuracy
 
Yee s2&s2
Yee s2&s2Yee s2&s2
Yee s2&s2
 
Performance Mixes MnDOT Specification Report - Aggregate and Ready Mix Associ...
Performance Mixes MnDOT Specification Report - Aggregate and Ready Mix Associ...Performance Mixes MnDOT Specification Report - Aggregate and Ready Mix Associ...
Performance Mixes MnDOT Specification Report - Aggregate and Ready Mix Associ...
 
pilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdfpilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdf
 
pilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdfpilefoundation-141216072447-conversion-gate01.pdf
pilefoundation-141216072447-conversion-gate01.pdf
 
14325 connels house drafting (1)
14325 connels house drafting (1)14325 connels house drafting (1)
14325 connels house drafting (1)
 
Isokern Celsius stove system installation instructions
Isokern Celsius stove system installation instructionsIsokern Celsius stove system installation instructions
Isokern Celsius stove system installation instructions
 
Casing_Design(1).ppt
Casing_Design(1).pptCasing_Design(1).ppt
Casing_Design(1).ppt
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion joint
 
Construction Sequence.pptx
Construction Sequence.pptxConstruction Sequence.pptx
Construction Sequence.pptx
 
Consistency test,Initial & Final setting time of Hydraulic Cement specimen
Consistency test,Initial & Final setting time of Hydraulic Cement specimenConsistency test,Initial & Final setting time of Hydraulic Cement specimen
Consistency test,Initial & Final setting time of Hydraulic Cement specimen
 
Column & beam
Column & beamColumn & beam
Column & beam
 
Metroppt
MetropptMetroppt
Metroppt
 
abermain.firestation
abermain.firestationabermain.firestation
abermain.firestation
 
Good practices in PSC work.ppt
Good practices in PSC work.pptGood practices in PSC work.ppt
Good practices in PSC work.ppt
 
02725 sewer manholes
02725 sewer manholes02725 sewer manholes
02725 sewer manholes
 
Coupler (08102015)
Coupler (08102015)Coupler (08102015)
Coupler (08102015)
 

Recently uploaded

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

Post tensioning

  • 1. UTRACON STRUCTURAL SYSTEMS PVT LTD ISO 9001 : 2008 POST TENSIONING SLABS CONSTRUCTION SEQUENCE VIT UNIVERSITY - AMARAVATHI
  • 2. 11 October 2017 2 PT Flat slab : Shuttering Plan drawing
  • 3. 11 October 2017 3 Bottom shuttering in progress.
  • 4. 11 October 2017 4 Completion of Bottom shuttering.
  • 5. 11 October 2017 5 PT Flat slab : Reinforcement drawing
  • 6. 11 October 2017 6 Tying of Bottom Nominal reinforcements
  • 7. 11 October 2017 7 Completion of Bottom Nominal reinforcements
  • 8. 11 October 2017 8 Drawings For Tendon Layout indicating Pour strips and stressing ends
  • 9. 11 October 2017 9 GI Ducts Laying in Progress
  • 10. 11 October 2017 10 Fixing of ducts at end stressing anchorages.
  • 11. 11 October 2017 11 Stressing end Anchorages fixed at Edge RCC Beams .
  • 12. 11 October 2017 12 De coiling of HT strands HT strands are cut to required length
  • 13. 11 October 2017 13 Inserting of HT strands into GI Ducts .
  • 14. 11 October 2017 14 Shop drawings showing Tendon Layout Profile
  • 15. 11 October 2017 15 Fixing of bar chairs to form tendon profile.
  • 16. 11 October 2017 16 Stressing end anchorage, grout vents on completion of laying
  • 17. 11 October 2017 17 Bursting links at Stressing anchorages
  • 18. 11 October 2017 18 Fixing of Dead ends and Fixing of grout vent.
  • 19. 11 October 2017 19 Laying of Tendons on completion
  • 20. 11 October 2017 20 Pour strip provided for construction feasibility
  • 21. 11 October 2017 21 Side Shuttering Strands Block Out Castings G.I.Duct Grout Hose Grout Vent Working Platform PT Materials
  • 22. 11 October 2017 22 Aerial view of Tendons Laying before concreting
  • 23. 11 October 2017 23 PT Flat slab after completion of Tendon laying ,before concreting
  • 24. 11 October 2017 24 Concreting In Progress
  • 25. 11 October 2017 25 Block outs/Recess Formers at Stressing anchorages Fixing of anchor Blocks and wedges .
  • 26. 11 October 2017 26 25 % of initial stressing to remove slag.
  • 27. 11 October 2017 27 Stressing Of Slab Tendons. Paint Mark shows Elongation
  • 28. 11 October 2017 28 Paint Mark shows Elongation
  • 29. 11 October 2017 29 Anchorages seen after stressing in edge beams
  • 30. 11 October 2017 30 Excess strand has been cut after stressing
  • 31. 11 October 2017 31 Patching of stressing Pockets
  • 32. 11 October 2017 32 Adding cement in to the mixing tank
  • 33. 11 October 2017 33 Mixing of Cementicious Grout
  • 34. 11 October 2017 34 Tying the hose at other end after witnessing good grout mix and exists of air bubbles if. Closing of Grout hose end .
  • 35. Primary Objective Secondary Objective QA / QC Recommendations Registering of Drawing PT Laying Profiles Stressing Grouting Check the shuttering Check the bottom rebar orientation
  • 36. Registration of Drawing Latest incoming drawing register should be maintained at site office with the details of 1. Drawing number 2. Revision 3. Date of receipt 4. Date of approval by consultant. Based on this register Project Manager has to arrange the drawing for site execution.
  • 37. PT - Laying  Drawings to be thoroughly studied by Utracon team at site. Clarifications are to be brought to the Utracon design team through project manager at site Approved drawing / corresponding Engineering instructions are to be made available before commencing the work at site.  Tendon spacing should be followed as per tendon layout drawing.  Duct joints are to be sealed well to avoid any ingress of concrete.
  • 38.  Based on tendon layout drg, the live and dead ends are to be fixed. If any difficulties/deviations /obstructions ,it is to be brought to the notice of concerned Design Engineer. Ensure that the protruding strand length is sufficient for stressing ( min 350 – 400 mm) Based on Tendon layout no. of strands to be threaded into ducts. Fix the grout vents.
  • 39.  Profiles need to be checked by PT team and finally verified /approved by PMC team.  PT Engineer should make sure that while checking the profiles, all the tendon support bars & chairs are placed at specified intervals as per the drawings. The tolerances of vertical profiles is ± 5mm for high and low points.  The tolerances for horizontal profiles are ± 150 mm. Any openings / fixing of rebars ,etc. are to be provided ,the importance should be given to the Profiles
  • 40. Stressing  Before stressing PT Engineer has to check with the cube result with the main contractor  whether the slab has achieved the minimum cube strength as specified in design/drg.  Once concreting is completed ,the platform are to be arranged for carrying out the stressing with the help of Main contractor. Remove the block outs and clean the castings to fix the anchor blocks for stressing activity  The theoretical elongation calculations must be approved by the consultant before stressing.  Fix the wedge plate and wedges.  25% of the stressing force shall be applied to the tendon to remove the slack in the strands.  spray mark should be made to strands.
  • 41. Once the cube test result is made available by main contractor, stressing can be started to initial stressing of 25% ,to remove slacks  Marking is to be done in strands before carrying out the 75% stressing and elongation is to be measured This will reflect the strand’s elongation form 25 % to 100% force.  Elongation shall be checked with measured reading in random after 24 hrs of final stressing to confirm that there is no slippage of strands The recess pockets left for the stressing shall be patched with cement mortar. Stressing
  • 42. Grouting 1. After consultant /PMC has approved the stressing result ,grouting can be started. 2. Before grouting the ducts shall be thoroughly cleaned by compressed air. 3. Grout mix shall be prepared in W/C ratio of 0.45 with workability additive of 0.2% of weight of cement. 4. Inject grout from the tendons inlet hose and lock the outlet hose Lock the outlet hose when the pressure of 3 bars is achieved. 6
  • 43. Do Before Concreting 1. After the Bottom mat completed. We start our work 2. We lay the tendon both horizontal and vertical then fix our castings. 3. After laying of tendons both directions and making the profiles then start the tieing of top reinforcement 4. Side shuttering can made after fixing of our casting & backing. 5. Proper VIBRATIONS required at the time of concrete (At least at the place of live ends & Dead ends). Do after concreting 1. Curing properly then only we can achieve the concrete strength. 2. Side shuttering should be removed next day of the concrete. 3. If any honeycomb found immediately batch up with fosroc or rich mix depends upon honeycomb at site condition. Don’t Do 1. Don’t walk onto tendon Profile. 2. Don’t dump materials like Rebar’s, Shuttering materials onto tendon 3. Don’t disturb tendon profile. 4. After concrete anybody should not cut the grout hose at any reason. 5. At the time of stressing anybody should not stand behind the stressing jack. 6. Don’t remove shuttering before getting approval from engineer. DO’s and DONT’s
  • 44. Don'ts 1. Don’t place the strand on the ground. It has to be placed above the ground with wooden packers to avoid contamination. 2. Don’t start tendon laying without checking the slab bottom reinforcement orientation and cover.
  • 45. 3. If you found any defect on the bulb of the strands, should be replaced with the new bulb. 4. Don’t allow the peoples to stepping on ducts. 6. Don’t commence the stressing without confirmation from main contractor on the required cube result. 7. Don’t stand in front of the jack and look behind the jack while stressing in progress. 8. Don’t allow grouting without cleaning the ducts by using compressed air. 9. Don’t allow to do grounding if water cement ratio is more than 0.45 10. Ducts to be grouted using max pressure of 0.5 N/mm2 and not lower than 0.2N/mm2 11. Pressure should be duly controlled so as not to cause segregation of grout. Required pressure to be maintained shall be 3 to 5 bars
  • 46.
  • 50.
  • 51. Sample Elongation Calculation 1 st basement flr D = (PL /AE) Where P = (Po + PI) / 2 Po = Force @ Stressing end 75% UTS 0.75 X 183.7 = 138 KN PI = Force @ Far end E = Modulus of Elasticity = 1 9 5 KN/MM2 A = Area of Stand PI = Po x e-(µα + kL) Where µ = Co efficient of friction = 0 .2 K = Wobble Factor = 0 .0 0 1 7 L= Length of Tendon α = Angular Deviation α = D = (PL /AE) where P = (Po+ PI) /2 Theroritical Elongation = D Sample Elongation Calculation: + + Horizontal Distance Between HP2-LP2 4 (HP1-LP1) 4 (HP2-LP2) Horizontal Distance Between HP1-LP1
  • 52. 10/11/2017 Sample Elongation Calculation Example : Calculation of 1st basement flr ( Refer Attached Drawing) Tendon No : T1 2 1 Length of Tendon = 1 3 .6 8 m α = 4 (190-115) 4 (190-35) 4 (115-35) 3200 5500 4975 α = 0.27 Radian Po= 138 KN PI = Po x e -(µα+ kL) = 138 x e -(0.2x0.271 + 0.0017x13.68) PI = 1 2 7 .7 1 KN D = (PL ) AE P0+ PI X L d1 = 2 138+ 127.71 x 13.68 = 2 100x195 Theritical Elongation = 9 3 .2 mm + + AE
  • 53. Jacking force UTS= 183.7 KN Stress=Load/Area Apply=75% NO OF STRAND 75% 76% 80% 75% 76% 80% Jack loss =2% Anchorage Loss = 3% = (183.7*0.75*1.05*1000)/3325 = 43.51 Mpa JACK LOSS ANCHORAGE LOSS STRESSING PRESSURE OF ALL HIS JACK MODELS All Pressure indicated above is in Mpa For conversion to Bar = Mpa X 10 UTS=Ultimate tensile strength 3% 3% 46.41 PISTON AREA 3709MM2 3325MM2 2% 2% 1 39 39.52 41.6 43.51 44.09 STRAND TYPE: 0.5"(12.7MM) TYPES OF JACK IHS IHS CH 258 DA CH 258 DA UTS UTS
  • 54. Jacking force UTS= 260.7 KN Stress=Load/Area Apply=75% NO OF STRAND 75% 76% 80% 75% 76% 80% Jack loss =2% Anchorage Loss = 3% = (260.7*0.75*1.05*1000)/3325 = 61.74 Mpa JACK LOSS ANCHORAGE LOSS STRESSING PRESSURE OF ALL HIS JACK MODELS All Pressure indicated above is in Mpa For conversion to Bar = Mpa X 10 UTS=Ultimate tensile strength STRAND TYPE: 0.6"(15.2MM) 3% 3% 2% 2% UTS TYPES OF JACK 1 PISTON AREA 3709MM2 3325MM2 55.35 56.09 59.04 61.74 62.57 65.86 CH 258 DA IHS UTS IHS CH 258 DA