SlideShare a Scribd company logo
1 of 40
Download to read offline
Maria Masten, MnDOT Concrete Engineer
ARM Convention
November 29, 2016
 NO AMOUNT OF TRAINING IS EVER ENOUGH
 Mix Design Approval Process
 Fabricating Cylinders
◦ Storing on a level surface
◦ Districts sawed or ground cylinders
 Curing and Handling Cylinders
◦ When Contractor’s didn’t supply equipment, some Agency
personnel ensured proper curing
 Transporting Cylinders
◦ Control Cylinders were being delivered prematurely
◦ Keeping 28 day cylinders in field > 7 days
 Reporting Strength Results
◦ 2014 vs. 2016 projects
◦ Passing, Low, Failing
 Spec was lacking enough guidance on
interpretation and acceptance of Strength Results
◦ Concrete Unit reviewed MnDOT tested cylinders and is
working with Engineer’s on determine monetary
adjustments
 Variables Affecting Strength
 Overall – things went well
 MnDOT Concrete Field I – Now ACI Concrete
Field Testing Technician 1
◦ Recert available through either MnDOT or ACI
 MnDOT Concrete Plant 1 and Plant 2
Recertification
◦ Combined into single class for 2016-2017 Training
Season
 MnDOT Concrete Plant 2
◦ Changing to more a of “Quality Control” Concept
◦ No longer a mix designer course
 Designated as Spec 3131
 Aggregate fraction with maximum size of ½
inch
 The Contractor may combine intermediate
aggregates with other aggregates to create a
Job Mix Formula (JMF).
 4 classifications
◦ Coarse Intermediate Aggregate (CIA)
◦ Fine Intermediate Aggregate (FIA)
◦ Coarse Sand (CS)
◦ Fine Sand (FS)
Page 1
 Grades G and P concrete
 Maximum 20% of total mix water by weight
 Obtain Approval:
◦ Meet ASTM C1602
◦ Plant Specific Clarified Water QC Plan
◦ QC Test Results
◦ 2 Independently tested samples per year
 Current Status: ARM Technical Committee
reviewing
 Producer/Concrete Unit Committee
◦ Meet Fall of 2017
◦ Discuss changes
◦ Implementation of new certificate of
compliance with publishing of 2020 Spec
Book
 Updates due February 1, 2017
 Published in June 2017
 English Units – NO Metric
 State Aid usually has one year grace
period
Please provide comments by
December 15, 2016
 Require Approval of Concrete Engineer
OR
 Allowed at the Contractor’s discretion when
a cold weather protection plan is approved
by the Engineer and the temperature
complies with 2461.3.G.2, “Placement
Temperatures.”
◦ 36 degrees or predicted to be 36 or less in the
next 24 hours Page 1
 In 2016 and beyond – Aggregate producers
expected to produce per ASTM, not MnDOT
Table 2461-3
Coarse Aggregate Gradation Designation for Concrete
Designation Coarse Aggregate Gradation
0 Job Mix Formula (JMF) combination of fine and coarse aggregate
Table 3137-4, “Coarse Aggregate Designation for Concrete”
1 ASTM #467
2 ASTM #67
3 ASTM #7
4 ASTM #89
7 CA-70
8 CA-80
Page 2
 Submit final mix design proportions on the
mix design submittal with other mixes
 Table 2461-5 shows proportions for the
following mixes:
◦ 1A Grout
◦ 3A Grout
◦ Lean Mix Backfill (Moved from 2520)
Page 3
Table 2461-6
Concrete Mix Design Requirements (Not applicable to High Performance Concrete or Mass Concrete)
Concrete Grade
Mix
Number
Intended Use *
Maximum
w/c ratio
†
Maximum
Cementitious
Content
(lbs/yd3)
Maximum
%SCM
(Fly Ash/
Slag/Ternary)
Slump
Range
Minimum
28-day
Compressive
Strength, f’c
3137
Spec
.
B
Bridge
Substructure
3B52 ‡
Abutment, stems, wingwalls, paving brackets, pier columns and
caps, pier struts
0.45 750 30/35/40 2 - 5” 4000 psi 2.D.1
F
Flatwork
3F32 ‡ Slipform curb and gutter 0.42 750 30/35/0 ½ - 3” # 4500 psi 2.D.1
3F52 ‡
3F52EX
3F53EX
3F52CO ║
Walks, curb and gutter, slope paving, median walks, driveway
entrances, ADA pedestrian walks
0.45 750 25/30/0 2 - 5” 4500 psi 2.D.1
G
General
Concrete
1G52 ‡ Footings and pilecap 0.55 750 30/35/40 2 - 5” 4500 psi 2.D.1
3G52 ‡
Footings, pilecap, walls, cast-in-place manholes and catch basins,
fence posts, signal bases, light pole foundations, erosion control
structures, cast-in-place box culverts, culvert headwalls, open
flumes, cast-in-place wall stems
0.45 750 30/35/40 2 - 5” 4500 psi 2.D.1
M
Median Barrier
3M12 Slipform barrier, median barrier, non-bridge 0.42 750 30/35/40 ½ - 1” # 4500 psi 2.D.1
3M52 Barrier, median barrier, non-bridge 0.45 750 30/35/40 2 - 5” 4500 psi 2.D.1
P
Piling
1P62 ‡ Piling, spread footing leveling pad 0.68 750 30/35/40 3 - 6” 3000 psi 2.D.1
R
Pavement
Rehabilitation
3R52 ‡ CPR - Full depth concrete repairs, concrete base 0.45 750 30/35/40 2 - 5” 4000 psi 2.D.3
S
Bridge
Superstructure
3S12 Slipform bridge barrier, parapets, end post 0.42 750 30/35/40 ½ - 1” # 4000 psi 2.D.2
3S52
Bridge median barrier, raised median, pilaster, curb, sidewalk,
approach panel, formed bridge barrier, parapet, end post, collar
0.45 750 30/35/40 2 - 5” 4000 psi 2.D.2
X
Miscellaneous
Bridge
1X62 Cofferdam seals, rock sockets, drilled shafts 0.45 750 30/35/40 3 - 6” 5000 psi 2.D.1
3X62 Drilled shafts above frost line 0.45 750 30/35/40 3 - 6” 5000 psi 2.D.1
Y
Bridge Deck
§
3Y42-M
3Y42-S
Bridge decks, integral abutment diaphragms, pier continuity
diaphragms, expansion joint replacement mix
0.45 750 30/35/40 2 - 4” 4000 psi 2.D.2
3Y47 ** Deck patching mix 0.45 750 30/35/40 2 - 4” 4000 psi 2.D.2
* If the intended use is not included elsewhere in the Specification or Special Provisions, use mix 3G52, unless otherwise directed by the Engineer.
║ Identify specific color used on the certificate of compliance. Colored concrete is only allowed when specified in the plans or the Contract.
† The minimum water/cement (w/c) ratio is 0.30.
‡ The Contractor may choose to use the Coarse Aggregate Designation “1” for the 4th digit in accordance with Table 2461-3.
# Adjust slump in accordance with 2461.3.G.7.a for slipform concrete placement.
§ The “-S” indicates a bridge deck with a structural slab and “-M” indicates a monolithic bridge deck.
** Mix 3Y47 requires the use of Coarse Aggregate Designation “7” or “3” for the 4th digit in accordance with Table 2461-3.
 Allow pre-approval of generic colored
concrete mix design – 3F52CO
 Must print actual color used somewhere on
the Certificate of Compliance
◦ Is this an issue?
 Cure colored concrete with material meeting
ASTM C 1315
 Incorporated into 2017 Special Provisions
◦ 2301 – Concrete Pavement
◦ 2521 - Walks Page 4
Table 2461-8
Project Specific Contractor Designed Mixes
Concrete
Grade
Intended Use Specification
3137
Spec.
A Concrete Pavement 2301 2.D.3
W and Y Precast Concrete 2462 Varies
HPC
High Performance
Concrete
Special Provision 2401 2.D.2
MC Mass Concrete Special Provision 2401 Varies
CLSM Cellular Concrete Grout 2519 None
Page 5
 For grades of concrete placed in accordance
with, 2461.3.G.7.a “Concrete Placed by the
Slip-Form Method”, the Engineer will allow
water adjustments as necessary to facilitate
slip-form placement. For all other grades of
concrete, do not make water adjustments
after discharging approximately 1 cubic yard.
Page 19
 Provide calibrated digital temperature
recording devices that record the daily
maximum and minimum temperatures of the
curing environment.
 The Engineer will monitor the daily
temperatures of the curing environments.
Agency monitoring does not relieve the
Contractor of the responsibility to maintain the
water temperature as specified herein.
Page 20
 The Engineer will transport standard (28-day)
strength cylinders for intermediate or final
curing as follows:
◦ A minimum of 16 hours after casting.
◦ High early strength (28-day) cylinders a minimum of 12 hours
after casting.
◦ With securely placed tight fitting plastic caps on plastic molds,
or by other methods to prevent moisture loss.
◦ Properly protected during transportation to prevent damage
from jarring, bouncing, and freezing.
◦ Transportation time not to exceed 4 hours, unless cylinders
are maintained in the moistened condition at ambient
temperature of 60 °F to 80 °F.
Page 20
 If 1 of the set of 3 cylinders shows variability >10%
outside of the initial calculated three cylinder
average strength, the Engineer will average the
remaining 2 cylinders and report as the 28-day
strength.
 If 2 or more of the set of 3 cylinders shows a
variability >10% outside of the initial calculated
average strength, the Engineer will use all 3
cylinder results to calculate the 28-day strength.
Page 21
 The Engineer will consider concrete acceptable in accordance with Table
2461-17 provided both the individual strength test and the moving average
of 3 consecutive strength tests are met for a required f’c.
Table 2461-17
Acceptance Criteria for Standard 28-day Cylinders
All strength tests
Moving average of 3 consecutive
strength tests *
f’c ≤ 5000 psi > (f’c – 500 psi) ≥ f’c
f’c > 5000 psi > 0.90 * f’c ≥ f’c
* If a project does not establish a moving average of 3 consecutive
strength tests, use the average of 2 strength tests to determine
acceptance. If there is only a single strength test, contact the Concrete
Engineer for recommendation.
Page 21
 If not deficient due to erroneous/invalid
strength tests
 No additional investigation will occur and the
Engineer will include the low strength test
result in the moving average.
Page 21
 If not deficient due to erroneous/invalid
strength tests
 The Engineer, in conjunction with the
Concrete Engineer, will investigate to
determine if the concrete has attained the
critical load-carrying capacity.
Page 21
The investigation may consist of, but is not
limited to reviewing the following:
(A) Sampling and testing plastic concrete
(B) Handling of cylinders
(C) Cylinder curing procedures
(D) Compressive strength testing procedures
(E) Certificate of Compliances
(F) Evaluation using Rebound Hammer (ASTM C803),
Penetration Resistance (ASTM C805), or other method
approved by the Concrete Engineer
(G) Review of the design calculations for the concrete in
question
Pages 21-22
 If it is determined that the concrete
represented by the single strength test has
attained the critical load carrying capacity,
the Engineer will include the strength test in
the moving average calculation.
Page 21
 If it is determined that the concrete has not attained the
critical load carrying capacity, the Engineer will direct
the Contractor to remove and replace concrete in
accordance with 1503, “Conformity with Contract
Documents,” and 1512, “Unacceptable and
Unauthorized Work.”
 The Contractor may dispute the remove and replace
order within 7 days of written notification by the
Engineer. If the Contractor disputes the order, follow
the dispute resolution coring procedure in accordance
with 2461.3.G.5.f(3), “Dispute Resolution Coring for
Single Strength Test Failure.”
Page 21
Table 2461-18
Evaluation of Core Test Results
Core (average of 3
cores) Test
Results:
Engineer
considers
concrete:
Cost of Coring
and Testing:
Resolution:
≥ 85% of f’c and
No individual core
is < 75% of f’c
Acceptable to
remain in place
Agency
No monetary adjustment for
single strength test failure. The
core test result will replace the
cylinder result in the moving
average calculation.
< 85% of f’c Unacceptable Contractor
Remove and replace concrete in
accordance with 1503,
“Conformity with Contract
Documents,” and 1512,
“Unacceptable and Unauthorized
Work,” as directed by the
Engineer.
Page 22
 If the moving average of three (3) consecutive
strength tests < f’c, the Concrete Engineer
will review the strength test results and
determine if a new mix design is required in
accordance with Table 2461-6 or Table
2461-7.
Page 22
 The Engineer will remove any strength test
results from the moving average if the
following occurs:
(A) After investigation the deficient concrete strength
is found to be an erroneous/invalid strength test
(B) The suspect concrete was removed and replaced
(C) Dispute resolution coring identified the concrete
acceptable to remain in place
Page 22
Reasons for finding erroneous test results as
determined by the Concrete Engineer:
(D) Cylinders kept in the field longer than 7 days,
(E) Improper handling/curing of the cylinders, and/or
(F) Improper testing of the cylinders
Page 22
Adjusted based upon concrete
cost of $200/cubic yard
Table 2461-19
All Concrete Grades
Moving average of 3
consecutive strength tests
Monetary Adjustment for Moving Average Failure *
> 93.0% of f’c
$20.00 per cubic yard or 10% of the Contractor-provided
invoice for quantity represented by test that brought moving
average into non-conformance
≥ 87.5% and ≤ 93.0% of f’c
$50.00 per cubic yard or 25% of the Contractor-provided
invoice for quantity represented by test that brought moving
average into non-conformance
< 87.5% of f’c
Remove and replace concrete in accordance with 1503,
“Conformity with Contract Documents,” and 1512,
“Unacceptable and Unauthorized Work,” as directed by the
Engineer.
If the Engineer, in conjunction with the Concrete Engineer,
determines the concrete can remain in place, the Engineer
will adjust the concrete at a reduction of $100.00 per cubic
yard or 50% of the Contractor-provided invoice for quantity
represented by test that brought moving average into non-
conformance.
Page 23
Table 2461-23
All Concrete Grades
> 1 in slump
Outside of Slump Range Monetary Adjustment
Below slump range *
No deduction for materials placed as approved
by the Engineer.
≤ 1½ in above slump
range
$20.00 per cubic yard or 10% of the Contractor-
provided invoice for quantity represented by the
materials placed
> 1½ in above slump
range
$50.00 per cubic yard or 25% of the Contractor-
provided invoice for quantity represented by the
materials placed
* The Department will not reduce contract unit price for low slump concrete
placed with the slip-form method as approved by the Engineer.
Page 26
Page 26
Page 26
Questions?

More Related Content

What's hot (17)

Quality assurance-for-ms-pipe itp-------------------------
Quality assurance-for-ms-pipe itp-------------------------Quality assurance-for-ms-pipe itp-------------------------
Quality assurance-for-ms-pipe itp-------------------------
 
Gabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentationGabriel India Limited_ProjectPresentation
Gabriel India Limited_ProjectPresentation
 
Introduction to superpave & Performance Grading(P.G)
Introduction to superpave & Performance Grading(P.G)Introduction to superpave & Performance Grading(P.G)
Introduction to superpave & Performance Grading(P.G)
 
wps qualification metho
wps qualification methowps qualification metho
wps qualification metho
 
Grca specification
Grca specificationGrca specification
Grca specification
 
43gradeopc
43gradeopc43gradeopc
43gradeopc
 
Selection of a_completion_material_for_a
Selection of a_completion_material_for_aSelection of a_completion_material_for_a
Selection of a_completion_material_for_a
 
Nwha tech weld_procedure_process_2014
Nwha tech weld_procedure_process_2014Nwha tech weld_procedure_process_2014
Nwha tech weld_procedure_process_2014
 
wps_variable
wps_variablewps_variable
wps_variable
 
Asme sec viii div 2
Asme sec viii div 2Asme sec viii div 2
Asme sec viii div 2
 
2015 asme-code-changes
2015 asme-code-changes2015 asme-code-changes
2015 asme-code-changes
 
Welding
WeldingWelding
Welding
 
Welding qualification a
Welding qualification aWelding qualification a
Welding qualification a
 
What is new with ASME BPVC Section IX - 2017
What is new with ASME BPVC Section IX - 2017What is new with ASME BPVC Section IX - 2017
What is new with ASME BPVC Section IX - 2017
 
My FS2 DEE
My FS2 DEEMy FS2 DEE
My FS2 DEE
 
Welding 4
Welding  4Welding  4
Welding 4
 
Polymer Modified Binders presentation for CalAPA Tech meeting
Polymer Modified Binders presentation for CalAPA Tech meetingPolymer Modified Binders presentation for CalAPA Tech meeting
Polymer Modified Binders presentation for CalAPA Tech meeting
 

Viewers also liked

Improving the Performance of Recycled Aggregate Pervious Concrete via Cement ...
Improving the Performance of Recycled Aggregate Pervious Concrete via Cement ...Improving the Performance of Recycled Aggregate Pervious Concrete via Cement ...
Improving the Performance of Recycled Aggregate Pervious Concrete via Cement ...Patrick Barnhouse, E.I.T
 
ITZ in Recycled Aggregate Concrete presentation
ITZ in Recycled Aggregate Concrete  presentationITZ in Recycled Aggregate Concrete  presentation
ITZ in Recycled Aggregate Concrete presentationbirbal singh
 
Recycled aggregate concrete
Recycled aggregate concreteRecycled aggregate concrete
Recycled aggregate concreteVignesh Nandha
 
Recycled Aggregate Concrete
Recycled Aggregate Concrete  Recycled Aggregate Concrete
Recycled Aggregate Concrete NEELANJAN SARKAR
 

Viewers also liked (7)

Improving the Performance of Recycled Aggregate Pervious Concrete via Cement ...
Improving the Performance of Recycled Aggregate Pervious Concrete via Cement ...Improving the Performance of Recycled Aggregate Pervious Concrete via Cement ...
Improving the Performance of Recycled Aggregate Pervious Concrete via Cement ...
 
Base Aggregate Testing
Base Aggregate TestingBase Aggregate Testing
Base Aggregate Testing
 
ITZ in Recycled Aggregate Concrete presentation
ITZ in Recycled Aggregate Concrete  presentationITZ in Recycled Aggregate Concrete  presentation
ITZ in Recycled Aggregate Concrete presentation
 
Final seminar rm
Final seminar rmFinal seminar rm
Final seminar rm
 
Recycled aggregate concrete
Recycled aggregate concreteRecycled aggregate concrete
Recycled aggregate concrete
 
Recycled Aggregate Concrete
Recycled Aggregate Concrete  Recycled Aggregate Concrete
Recycled Aggregate Concrete
 
Digital in 2016
Digital in 2016Digital in 2016
Digital in 2016
 

Similar to Performance Mixes MnDOT Specification Report - Aggregate and Ready Mix Association of Minnesota 2016 Convention

14325 connels house drafting (1)
14325 connels house drafting (1)14325 connels house drafting (1)
14325 connels house drafting (1)Yousef Riad
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structureMinh Bui Si
 
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdfStandard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdfParmeshworVetwal1
 
KEYSTONE-GRSW retaining_walls.pdf
KEYSTONE-GRSW retaining_walls.pdfKEYSTONE-GRSW retaining_walls.pdf
KEYSTONE-GRSW retaining_walls.pdfIstiHaryanto2
 
Engineering quality version 2014 for construction projects
Engineering quality version 2014 for construction projectsEngineering quality version 2014 for construction projects
Engineering quality version 2014 for construction projectsmeetgiannis
 
abermain.firestation
abermain.firestationabermain.firestation
abermain.firestationYousef Riad
 
6 pavement quality concrete
6 pavement quality concrete6 pavement quality concrete
6 pavement quality concretethamand7
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentationAKASHGARG131
 
4.IS-10262-2019-New-Mix-design.pdf
4.IS-10262-2019-New-Mix-design.pdf4.IS-10262-2019-New-Mix-design.pdf
4.IS-10262-2019-New-Mix-design.pdfPrasadnb55
 
Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement worksMohd Nizam Mohd Zan
 
Experimental Investigation To Prepared Mix Design of M25 And M20 Grade of Con...
Experimental Investigation To Prepared Mix Design of M25 And M20 Grade of Con...Experimental Investigation To Prepared Mix Design of M25 And M20 Grade of Con...
Experimental Investigation To Prepared Mix Design of M25 And M20 Grade of Con...IRJET Journal
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouringBharatha Rathnayke
 
3D_Distribution transformer_Specification.pdf
3D_Distribution transformer_Specification.pdf3D_Distribution transformer_Specification.pdf
3D_Distribution transformer_Specification.pdfShahrukhKhan424745
 

Similar to Performance Mixes MnDOT Specification Report - Aggregate and Ready Mix Association of Minnesota 2016 Convention (20)

14325 connels house drafting (1)
14325 connels house drafting (1)14325 connels house drafting (1)
14325 connels house drafting (1)
 
Concreting of super structure
Concreting of super structureConcreting of super structure
Concreting of super structure
 
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdfStandard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
Standard Operating Procedures SOP for Prestressed Concrete Members facility.pdf
 
KEYSTONE-GRSW retaining_walls.pdf
KEYSTONE-GRSW retaining_walls.pdfKEYSTONE-GRSW retaining_walls.pdf
KEYSTONE-GRSW retaining_walls.pdf
 
Engineering quality version 2014 for construction projects
Engineering quality version 2014 for construction projectsEngineering quality version 2014 for construction projects
Engineering quality version 2014 for construction projects
 
abermain.firestation
abermain.firestationabermain.firestation
abermain.firestation
 
6 pavement quality concrete
6 pavement quality concrete6 pavement quality concrete
6 pavement quality concrete
 
Yee s2&amp;s2
Yee s2&amp;s2Yee s2&amp;s2
Yee s2&amp;s2
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 
Column & beam
Column & beamColumn & beam
Column & beam
 
Is 10262 2019 latest
Is 10262  2019 latestIs 10262  2019 latest
Is 10262 2019 latest
 
4.IS-10262-2019-New-Mix-design.pdf
4.IS-10262-2019-New-Mix-design.pdf4.IS-10262-2019-New-Mix-design.pdf
4.IS-10262-2019-New-Mix-design.pdf
 
ME REVIEWER
ME REVIEWERME REVIEWER
ME REVIEWER
 
Post tensioning
Post tensioningPost tensioning
Post tensioning
 
Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement works
 
Experimental Investigation To Prepared Mix Design of M25 And M20 Grade of Con...
Experimental Investigation To Prepared Mix Design of M25 And M20 Grade of Con...Experimental Investigation To Prepared Mix Design of M25 And M20 Grade of Con...
Experimental Investigation To Prepared Mix Design of M25 And M20 Grade of Con...
 
uv_bpm.pdf
uv_bpm.pdfuv_bpm.pdf
uv_bpm.pdf
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
 
Concrete Mix Design.pdf
Concrete Mix Design.pdfConcrete Mix Design.pdf
Concrete Mix Design.pdf
 
3D_Distribution transformer_Specification.pdf
3D_Distribution transformer_Specification.pdf3D_Distribution transformer_Specification.pdf
3D_Distribution transformer_Specification.pdf
 

More from Tumer Akakin, P.E.

Jess Richards ARM 2016 Convention
Jess Richards ARM 2016 ConventionJess Richards ARM 2016 Convention
Jess Richards ARM 2016 ConventionTumer Akakin, P.E.
 
Terry Beaudry ARM Convetion 2016 presentation
Terry Beaudry ARM Convetion 2016 presentationTerry Beaudry ARM Convetion 2016 presentation
Terry Beaudry ARM Convetion 2016 presentationTumer Akakin, P.E.
 
Kevin MacDonald - ARM Convention 2016 presentation
Kevin MacDonald - ARM Convention 2016 presentationKevin MacDonald - ARM Convention 2016 presentation
Kevin MacDonald - ARM Convention 2016 presentationTumer Akakin, P.E.
 
Brett Trautman Unbounded Concrete Overlays
Brett Trautman Unbounded Concrete OverlaysBrett Trautman Unbounded Concrete Overlays
Brett Trautman Unbounded Concrete OverlaysTumer Akakin, P.E.
 
AGC Meeting Presentation - Coherent Supply Chain in Base Production
AGC Meeting Presentation - Coherent Supply Chain in Base ProductionAGC Meeting Presentation - Coherent Supply Chain in Base Production
AGC Meeting Presentation - Coherent Supply Chain in Base ProductionTumer Akakin, P.E.
 

More from Tumer Akakin, P.E. (6)

Jess Richards ARM 2016 Convention
Jess Richards ARM 2016 ConventionJess Richards ARM 2016 Convention
Jess Richards ARM 2016 Convention
 
Terry Beaudry ARM Convetion 2016 presentation
Terry Beaudry ARM Convetion 2016 presentationTerry Beaudry ARM Convetion 2016 presentation
Terry Beaudry ARM Convetion 2016 presentation
 
Kevin MacDonald - ARM Convention 2016 presentation
Kevin MacDonald - ARM Convention 2016 presentationKevin MacDonald - ARM Convention 2016 presentation
Kevin MacDonald - ARM Convention 2016 presentation
 
Brett Trautman Unbounded Concrete Overlays
Brett Trautman Unbounded Concrete OverlaysBrett Trautman Unbounded Concrete Overlays
Brett Trautman Unbounded Concrete Overlays
 
Frank kozeliski
Frank kozeliskiFrank kozeliski
Frank kozeliski
 
AGC Meeting Presentation - Coherent Supply Chain in Base Production
AGC Meeting Presentation - Coherent Supply Chain in Base ProductionAGC Meeting Presentation - Coherent Supply Chain in Base Production
AGC Meeting Presentation - Coherent Supply Chain in Base Production
 

Recently uploaded

Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...vershagrag
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxkalpana413121
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesRashidFaridChishti
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...ppkakm
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxNANDHAKUMARA10
 

Recently uploaded (20)

Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
💚Trustworthy Call Girls Pune Call Girls Service Just Call 🍑👄6378878445 🍑👄 Top...
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Electromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptxElectromagnetic relays used for power system .pptx
Electromagnetic relays used for power system .pptx
 

Performance Mixes MnDOT Specification Report - Aggregate and Ready Mix Association of Minnesota 2016 Convention

  • 1. Maria Masten, MnDOT Concrete Engineer ARM Convention November 29, 2016
  • 2.
  • 3.  NO AMOUNT OF TRAINING IS EVER ENOUGH  Mix Design Approval Process  Fabricating Cylinders ◦ Storing on a level surface ◦ Districts sawed or ground cylinders  Curing and Handling Cylinders ◦ When Contractor’s didn’t supply equipment, some Agency personnel ensured proper curing  Transporting Cylinders ◦ Control Cylinders were being delivered prematurely ◦ Keeping 28 day cylinders in field > 7 days
  • 4.  Reporting Strength Results ◦ 2014 vs. 2016 projects ◦ Passing, Low, Failing  Spec was lacking enough guidance on interpretation and acceptance of Strength Results ◦ Concrete Unit reviewed MnDOT tested cylinders and is working with Engineer’s on determine monetary adjustments  Variables Affecting Strength  Overall – things went well
  • 5.
  • 6.
  • 7.
  • 8.  MnDOT Concrete Field I – Now ACI Concrete Field Testing Technician 1 ◦ Recert available through either MnDOT or ACI  MnDOT Concrete Plant 1 and Plant 2 Recertification ◦ Combined into single class for 2016-2017 Training Season  MnDOT Concrete Plant 2 ◦ Changing to more a of “Quality Control” Concept ◦ No longer a mix designer course
  • 9.
  • 10.  Designated as Spec 3131  Aggregate fraction with maximum size of ½ inch  The Contractor may combine intermediate aggregates with other aggregates to create a Job Mix Formula (JMF).  4 classifications ◦ Coarse Intermediate Aggregate (CIA) ◦ Fine Intermediate Aggregate (FIA) ◦ Coarse Sand (CS) ◦ Fine Sand (FS) Page 1
  • 11.  Grades G and P concrete  Maximum 20% of total mix water by weight  Obtain Approval: ◦ Meet ASTM C1602 ◦ Plant Specific Clarified Water QC Plan ◦ QC Test Results ◦ 2 Independently tested samples per year  Current Status: ARM Technical Committee reviewing
  • 12.  Producer/Concrete Unit Committee ◦ Meet Fall of 2017 ◦ Discuss changes ◦ Implementation of new certificate of compliance with publishing of 2020 Spec Book
  • 13.  Updates due February 1, 2017  Published in June 2017  English Units – NO Metric  State Aid usually has one year grace period
  • 14. Please provide comments by December 15, 2016
  • 15.  Require Approval of Concrete Engineer OR  Allowed at the Contractor’s discretion when a cold weather protection plan is approved by the Engineer and the temperature complies with 2461.3.G.2, “Placement Temperatures.” ◦ 36 degrees or predicted to be 36 or less in the next 24 hours Page 1
  • 16.  In 2016 and beyond – Aggregate producers expected to produce per ASTM, not MnDOT Table 2461-3 Coarse Aggregate Gradation Designation for Concrete Designation Coarse Aggregate Gradation 0 Job Mix Formula (JMF) combination of fine and coarse aggregate Table 3137-4, “Coarse Aggregate Designation for Concrete” 1 ASTM #467 2 ASTM #67 3 ASTM #7 4 ASTM #89 7 CA-70 8 CA-80 Page 2
  • 17.  Submit final mix design proportions on the mix design submittal with other mixes  Table 2461-5 shows proportions for the following mixes: ◦ 1A Grout ◦ 3A Grout ◦ Lean Mix Backfill (Moved from 2520) Page 3
  • 18. Table 2461-6 Concrete Mix Design Requirements (Not applicable to High Performance Concrete or Mass Concrete) Concrete Grade Mix Number Intended Use * Maximum w/c ratio † Maximum Cementitious Content (lbs/yd3) Maximum %SCM (Fly Ash/ Slag/Ternary) Slump Range Minimum 28-day Compressive Strength, f’c 3137 Spec . B Bridge Substructure 3B52 ‡ Abutment, stems, wingwalls, paving brackets, pier columns and caps, pier struts 0.45 750 30/35/40 2 - 5” 4000 psi 2.D.1 F Flatwork 3F32 ‡ Slipform curb and gutter 0.42 750 30/35/0 ½ - 3” # 4500 psi 2.D.1 3F52 ‡ 3F52EX 3F53EX 3F52CO ║ Walks, curb and gutter, slope paving, median walks, driveway entrances, ADA pedestrian walks 0.45 750 25/30/0 2 - 5” 4500 psi 2.D.1 G General Concrete 1G52 ‡ Footings and pilecap 0.55 750 30/35/40 2 - 5” 4500 psi 2.D.1 3G52 ‡ Footings, pilecap, walls, cast-in-place manholes and catch basins, fence posts, signal bases, light pole foundations, erosion control structures, cast-in-place box culverts, culvert headwalls, open flumes, cast-in-place wall stems 0.45 750 30/35/40 2 - 5” 4500 psi 2.D.1 M Median Barrier 3M12 Slipform barrier, median barrier, non-bridge 0.42 750 30/35/40 ½ - 1” # 4500 psi 2.D.1 3M52 Barrier, median barrier, non-bridge 0.45 750 30/35/40 2 - 5” 4500 psi 2.D.1 P Piling 1P62 ‡ Piling, spread footing leveling pad 0.68 750 30/35/40 3 - 6” 3000 psi 2.D.1 R Pavement Rehabilitation 3R52 ‡ CPR - Full depth concrete repairs, concrete base 0.45 750 30/35/40 2 - 5” 4000 psi 2.D.3 S Bridge Superstructure 3S12 Slipform bridge barrier, parapets, end post 0.42 750 30/35/40 ½ - 1” # 4000 psi 2.D.2 3S52 Bridge median barrier, raised median, pilaster, curb, sidewalk, approach panel, formed bridge barrier, parapet, end post, collar 0.45 750 30/35/40 2 - 5” 4000 psi 2.D.2 X Miscellaneous Bridge 1X62 Cofferdam seals, rock sockets, drilled shafts 0.45 750 30/35/40 3 - 6” 5000 psi 2.D.1 3X62 Drilled shafts above frost line 0.45 750 30/35/40 3 - 6” 5000 psi 2.D.1 Y Bridge Deck § 3Y42-M 3Y42-S Bridge decks, integral abutment diaphragms, pier continuity diaphragms, expansion joint replacement mix 0.45 750 30/35/40 2 - 4” 4000 psi 2.D.2 3Y47 ** Deck patching mix 0.45 750 30/35/40 2 - 4” 4000 psi 2.D.2 * If the intended use is not included elsewhere in the Specification or Special Provisions, use mix 3G52, unless otherwise directed by the Engineer. ║ Identify specific color used on the certificate of compliance. Colored concrete is only allowed when specified in the plans or the Contract. † The minimum water/cement (w/c) ratio is 0.30. ‡ The Contractor may choose to use the Coarse Aggregate Designation “1” for the 4th digit in accordance with Table 2461-3. # Adjust slump in accordance with 2461.3.G.7.a for slipform concrete placement. § The “-S” indicates a bridge deck with a structural slab and “-M” indicates a monolithic bridge deck. ** Mix 3Y47 requires the use of Coarse Aggregate Designation “7” or “3” for the 4th digit in accordance with Table 2461-3.
  • 19.  Allow pre-approval of generic colored concrete mix design – 3F52CO  Must print actual color used somewhere on the Certificate of Compliance ◦ Is this an issue?  Cure colored concrete with material meeting ASTM C 1315  Incorporated into 2017 Special Provisions ◦ 2301 – Concrete Pavement ◦ 2521 - Walks Page 4
  • 20. Table 2461-8 Project Specific Contractor Designed Mixes Concrete Grade Intended Use Specification 3137 Spec. A Concrete Pavement 2301 2.D.3 W and Y Precast Concrete 2462 Varies HPC High Performance Concrete Special Provision 2401 2.D.2 MC Mass Concrete Special Provision 2401 Varies CLSM Cellular Concrete Grout 2519 None Page 5
  • 21.  For grades of concrete placed in accordance with, 2461.3.G.7.a “Concrete Placed by the Slip-Form Method”, the Engineer will allow water adjustments as necessary to facilitate slip-form placement. For all other grades of concrete, do not make water adjustments after discharging approximately 1 cubic yard. Page 19
  • 22.  Provide calibrated digital temperature recording devices that record the daily maximum and minimum temperatures of the curing environment.  The Engineer will monitor the daily temperatures of the curing environments. Agency monitoring does not relieve the Contractor of the responsibility to maintain the water temperature as specified herein. Page 20
  • 23.  The Engineer will transport standard (28-day) strength cylinders for intermediate or final curing as follows: ◦ A minimum of 16 hours after casting. ◦ High early strength (28-day) cylinders a minimum of 12 hours after casting. ◦ With securely placed tight fitting plastic caps on plastic molds, or by other methods to prevent moisture loss. ◦ Properly protected during transportation to prevent damage from jarring, bouncing, and freezing. ◦ Transportation time not to exceed 4 hours, unless cylinders are maintained in the moistened condition at ambient temperature of 60 °F to 80 °F. Page 20
  • 24.  If 1 of the set of 3 cylinders shows variability >10% outside of the initial calculated three cylinder average strength, the Engineer will average the remaining 2 cylinders and report as the 28-day strength.  If 2 or more of the set of 3 cylinders shows a variability >10% outside of the initial calculated average strength, the Engineer will use all 3 cylinder results to calculate the 28-day strength. Page 21
  • 25.  The Engineer will consider concrete acceptable in accordance with Table 2461-17 provided both the individual strength test and the moving average of 3 consecutive strength tests are met for a required f’c. Table 2461-17 Acceptance Criteria for Standard 28-day Cylinders All strength tests Moving average of 3 consecutive strength tests * f’c ≤ 5000 psi > (f’c – 500 psi) ≥ f’c f’c > 5000 psi > 0.90 * f’c ≥ f’c * If a project does not establish a moving average of 3 consecutive strength tests, use the average of 2 strength tests to determine acceptance. If there is only a single strength test, contact the Concrete Engineer for recommendation. Page 21
  • 26.  If not deficient due to erroneous/invalid strength tests  No additional investigation will occur and the Engineer will include the low strength test result in the moving average. Page 21
  • 27.  If not deficient due to erroneous/invalid strength tests  The Engineer, in conjunction with the Concrete Engineer, will investigate to determine if the concrete has attained the critical load-carrying capacity. Page 21
  • 28. The investigation may consist of, but is not limited to reviewing the following: (A) Sampling and testing plastic concrete (B) Handling of cylinders (C) Cylinder curing procedures (D) Compressive strength testing procedures (E) Certificate of Compliances (F) Evaluation using Rebound Hammer (ASTM C803), Penetration Resistance (ASTM C805), or other method approved by the Concrete Engineer (G) Review of the design calculations for the concrete in question Pages 21-22
  • 29.  If it is determined that the concrete represented by the single strength test has attained the critical load carrying capacity, the Engineer will include the strength test in the moving average calculation. Page 21
  • 30.  If it is determined that the concrete has not attained the critical load carrying capacity, the Engineer will direct the Contractor to remove and replace concrete in accordance with 1503, “Conformity with Contract Documents,” and 1512, “Unacceptable and Unauthorized Work.”  The Contractor may dispute the remove and replace order within 7 days of written notification by the Engineer. If the Contractor disputes the order, follow the dispute resolution coring procedure in accordance with 2461.3.G.5.f(3), “Dispute Resolution Coring for Single Strength Test Failure.” Page 21
  • 31. Table 2461-18 Evaluation of Core Test Results Core (average of 3 cores) Test Results: Engineer considers concrete: Cost of Coring and Testing: Resolution: ≥ 85% of f’c and No individual core is < 75% of f’c Acceptable to remain in place Agency No monetary adjustment for single strength test failure. The core test result will replace the cylinder result in the moving average calculation. < 85% of f’c Unacceptable Contractor Remove and replace concrete in accordance with 1503, “Conformity with Contract Documents,” and 1512, “Unacceptable and Unauthorized Work,” as directed by the Engineer. Page 22
  • 32.  If the moving average of three (3) consecutive strength tests < f’c, the Concrete Engineer will review the strength test results and determine if a new mix design is required in accordance with Table 2461-6 or Table 2461-7. Page 22
  • 33.  The Engineer will remove any strength test results from the moving average if the following occurs: (A) After investigation the deficient concrete strength is found to be an erroneous/invalid strength test (B) The suspect concrete was removed and replaced (C) Dispute resolution coring identified the concrete acceptable to remain in place Page 22
  • 34. Reasons for finding erroneous test results as determined by the Concrete Engineer: (D) Cylinders kept in the field longer than 7 days, (E) Improper handling/curing of the cylinders, and/or (F) Improper testing of the cylinders Page 22
  • 35. Adjusted based upon concrete cost of $200/cubic yard
  • 36. Table 2461-19 All Concrete Grades Moving average of 3 consecutive strength tests Monetary Adjustment for Moving Average Failure * > 93.0% of f’c $20.00 per cubic yard or 10% of the Contractor-provided invoice for quantity represented by test that brought moving average into non-conformance ≥ 87.5% and ≤ 93.0% of f’c $50.00 per cubic yard or 25% of the Contractor-provided invoice for quantity represented by test that brought moving average into non-conformance < 87.5% of f’c Remove and replace concrete in accordance with 1503, “Conformity with Contract Documents,” and 1512, “Unacceptable and Unauthorized Work,” as directed by the Engineer. If the Engineer, in conjunction with the Concrete Engineer, determines the concrete can remain in place, the Engineer will adjust the concrete at a reduction of $100.00 per cubic yard or 50% of the Contractor-provided invoice for quantity represented by test that brought moving average into non- conformance. Page 23
  • 37. Table 2461-23 All Concrete Grades > 1 in slump Outside of Slump Range Monetary Adjustment Below slump range * No deduction for materials placed as approved by the Engineer. ≤ 1½ in above slump range $20.00 per cubic yard or 10% of the Contractor- provided invoice for quantity represented by the materials placed > 1½ in above slump range $50.00 per cubic yard or 25% of the Contractor- provided invoice for quantity represented by the materials placed * The Department will not reduce contract unit price for low slump concrete placed with the slip-form method as approved by the Engineer. Page 26