SlideShare a Scribd company logo
1 of 15
1
REINFORCEMENT
welding
Amardeep Singh
2
WELDING OF REINFORCEMENT
• IS : 1786 allows the chemical composition and carbon
equivalent to be limited so that the material can be
readily welded by conventional welding procedures.
• Material not conforming to these limits is generally
difficult to weld for which special care and
precautions will have to be exercised.
• IS : 9417 may be followed for welding in Cold Worked
Steel Bars
Is welding in reinforcement allowed ?
3
WELDING OF REINFORCEMENT
• For guaranteed weld ability, the Carbon Equivalent, CE using the
formula
CE = C+ Mn/6 + (Cr+Mo+V)/5 + (Ni+Cu)/15
shall not be more than 0.53 percent, when micro alloys/low alloys are
used.
CE = C+ Mn/6
• Carbon Equivalent, CE using the formula
shall not be more than 0.42 percent when micro alloys/low alloys are not
used.
Where,
CE = Carbon Equivalent, C = Carbon, MN = Manganese, Cr = Chromium, Mo = Molybdenum, V =
Vanadium, Ni = Nickel and Cu = Copper
Refer MTC of reinforcement Steel for values
4
WELDING OF REINFORCEMENT
• The parent metal shall be of guaranteed weld able quality of
steel conforming to IS : 1786 according to its CE.
• Electrodes used shall conform to IS : 814 – part 1.
Requirement :-
• Sometimes welding is required at limited working spaces.
• In piles where reinforcement cage bars get damaged while
cutting the pile heads.
• Where structure need to extended for any reason.
• In TG Deck slab where the reinforcement is much congested and
working space is less.
• Fixing of steel structural members in concrete.
5
WELDING OF REINFORCEMENT
• Cold-worked steel bars shall be either butt welded or lap welded. Butt
welding may be carried out either by flash butt, gas pressure or by
shielded metal arc welding process. Lap welding may be carried out by
shielded metal arc welding process.
• Bars of unequal diameter may be welded. However, in case of butt
welding, the difference in, diameter of bars shall not exceed 5 mm.
• The untwisted ends must be removed before welding and the surface of
the ends of the bars to be welded shall be clean and free from rust,
paint, grease and/or other contaminants which are likely to affect the
quality of weld.
6
WELDING OF REINFORCEMENT
• Butt-welds by metal arc welding process are normally adopted to join bars of thickness
more than 20 mm.
• The ends of the bars to be welded should be placed in proper alignment in clamps so that
bent or eccentric joints do not result.
• Flash Butt Welding of Cold-Worked Bars
The bar ends shall be uniformly pushed against each other from the moment of contact to the
up-setting. The transformer regulator should be so set that that current at contact area is
between 80 to 90 A/mm2.
If the capacity of butt welding machine or the available power is not sufficient to take the
load for welding from cold, welding may be done after preheating. Satisfactory joints with only
slight reduction in original strength of the bar can be achieved with a current density up to 25
A/mm2.
• Butt-Welding by Shielded Metal Arc Welding Process
Welding electrodes with flux covering of Type 3 or Type 6 of IS 815 : 1974
The size of electrodes depends upon the position of the bead and thickness of the bar to
be welded. The root runs should be made with electrodes of size not exceeding 2’5 mm. For
successive beads, the size of the electrodes should be progressively increased so that in the top
bead, the electrode size does not generally exceed 3.15 mm for 20 mm bars and 5 mm for 40
mm bars.
The temperature of the bars at a distance of about one bar diameter from the joints shall
not exceed 300°C immediately after the bead is made. Before commencing the next bead, the
temperature shall not exceed 250°C.
Butt Welding
7
WELDING OF REINFORCEMENT
• Butt Welding by Gas Pressure Welding Process
Gas pressure welding is basically a hot forging process of joining the two bars end to end.
The bar ends are heated by a multi-nozzle burner using oxy-acetylene flame and fused by
forcing the two bar ends against each other under pressure to effect a solid phase welded joint.
Butt Welding
8
WELDING OF REINFORCEMENT
Butt Welding
9
WELDING OF REINFORCEMENT
• Lap Welding of Cold-Worked Bars
Lap joints may be made in cold-worked bars of all sizes. They are preferred when access for
welding is from one side only, and while connecting prefabricated units. Use of electrodes with
flux covering of Type 3 or Type 6 of IS 815 : 1974
The surface of the bars to be welded shall be clean and free from rust, paint, grease and/or
other contaminants.
Lap Welding
Rebar Diameter vs. Electrode size
Sr. No Nominal Diameter of Bar (mm) Size of Electrode max
(mm)
1 Up to and including 10 mm 2.5
2 Over 10 up to and including 18 mm 3.15
3 Over 18 up to and including 28 mm 4.0
4 Over 28 mm 5.0
10
WELDING OF REINFORCEMENT
Lap Welding
11
WELDING OF REINFORCEMENT
Lap Welding
12
QUALITY CONTROL TESTS
• Tensile test : Specimens with a free length between grips about 20d should he used. The
selected pieces when subjected to a tensile test shall have tensile strength not less than 90
percent or the actual tensile strength of the bar but in no case less than 485 MPa for grade
Fe 415 and 545 MPa for grade Fe 500 of IS 1786. The fracture shall not take place in the
weld joint.
• Bend test : The welding flash or reinforcement shall be removed at the point where contact
is made with the mandrel. The welded joint shall be capable of being bent to an angle of 60
degree around a mandrel of diameter specified below, before any crack appears:
Sr. no Nominal Diameter of Bar
(mm)
Diameter of
mandrel ( mm)
1 Up to 5 d
2 Over 7 d
Butt Welding
13
QUALITY CONTROL TESTS
• Tensile test : The free specimen length between grips must be between 25 d and 30 d where
d is the nominal diameter of the bar. The breaking load shall not be less than the
guaranteed load in accordance with IS 1786 required to fracture the bar.
Lap Welding
14
PRECAUTIONS IN REINFORCEMENT BARS
The reinforcement bar should not cut with
flame because when it is heated and air
cooled the surface will be lost and strength
of bar will approach to center of bar. Loss
of strength is the reason to restrict the
cutting of bar with flame.
The bending of bar should be done in
correct radius of mandrel because tighter
the bend greater the strains around the
bar. The bend diameters should be
followed as per IS : 2502 to maintain
ductility and practical construction
operations.
15

More Related Content

What's hot

Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing MethodMd Tanvir Alam
 
Design of bolted connections
Design of bolted connectionsDesign of bolted connections
Design of bolted connectionsArjun raj.
 
Column Interaction Diagram construction
Column Interaction Diagram constructionColumn Interaction Diagram construction
Column Interaction Diagram constructionPritesh Parmar
 
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush SanthaliaPractical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush SanthaliaPiyush Kumar Santhalia
 
Special moment frames aci 318 - اطارات مقاومة للعزوم
Special moment frames aci   318 - اطارات مقاومة للعزوم Special moment frames aci   318 - اطارات مقاومة للعزوم
Special moment frames aci 318 - اطارات مقاومة للعزوم Dr.Youssef Hammida
 
P-Delta Effects on Tall RC Buildings with and Without Shear Wall
P-Delta Effects on Tall RC Buildings with and Without Shear WallP-Delta Effects on Tall RC Buildings with and Without Shear Wall
P-Delta Effects on Tall RC Buildings with and Without Shear WallIRJET Journal
 
Overview of Direct Analysis Method of Design for
Overview of Direct Analysis Method of Design forOverview of Direct Analysis Method of Design for
Overview of Direct Analysis Method of Design forRyan Brotherson
 
Design of column base plates anchor bolt
Design of column base plates anchor boltDesign of column base plates anchor bolt
Design of column base plates anchor boltKhaled Eid
 
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)Hossam Shafiq II
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structuresanand bhatnagar
 
Pile Eccentricity Analysis for 2 Columns Combined Pilecap
Pile Eccentricity Analysis for 2 Columns Combined PilecapPile Eccentricity Analysis for 2 Columns Combined Pilecap
Pile Eccentricity Analysis for 2 Columns Combined Pilecapazhar ahmad
 
Wind load calculation
Wind load calculationWind load calculation
Wind load calculationGodfrey James
 
Precast pretensioned concrete girders
Precast pretensioned concrete girdersPrecast pretensioned concrete girders
Precast pretensioned concrete girdersMD.Yeasin Mostafiz
 

What's hot (20)

Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing Method
 
Design of bolted connections
Design of bolted connectionsDesign of bolted connections
Design of bolted connections
 
Strut and Tie Model for Pile Cap
Strut and Tie Model for Pile CapStrut and Tie Model for Pile Cap
Strut and Tie Model for Pile Cap
 
Column Interaction Diagram construction
Column Interaction Diagram constructionColumn Interaction Diagram construction
Column Interaction Diagram construction
 
Is.sp.6.1.1964
Is.sp.6.1.1964Is.sp.6.1.1964
Is.sp.6.1.1964
 
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush SanthaliaPractical Design of Balanced Cantilever Bridges - Piyush Santhalia
Practical Design of Balanced Cantilever Bridges - Piyush Santhalia
 
Special moment frames aci 318 - اطارات مقاومة للعزوم
Special moment frames aci   318 - اطارات مقاومة للعزوم Special moment frames aci   318 - اطارات مقاومة للعزوم
Special moment frames aci 318 - اطارات مقاومة للعزوم
 
Box culvert
Box culvertBox culvert
Box culvert
 
3370 2
3370 23370 2
3370 2
 
P-Delta Effects on Tall RC Buildings with and Without Shear Wall
P-Delta Effects on Tall RC Buildings with and Without Shear WallP-Delta Effects on Tall RC Buildings with and Without Shear Wall
P-Delta Effects on Tall RC Buildings with and Without Shear Wall
 
Design of column according ACI codes
Design of column according ACI codesDesign of column according ACI codes
Design of column according ACI codes
 
Prestressed concrete continuous beam
Prestressed concrete continuous beamPrestressed concrete continuous beam
Prestressed concrete continuous beam
 
Overview of Direct Analysis Method of Design for
Overview of Direct Analysis Method of Design forOverview of Direct Analysis Method of Design for
Overview of Direct Analysis Method of Design for
 
Design of column base plates anchor bolt
Design of column base plates anchor boltDesign of column base plates anchor bolt
Design of column base plates anchor bolt
 
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
23-Design of Column Base Plates (Steel Structural Design & Prof. Shehab Mourad)
 
255788330 asi-steel-connections
255788330 asi-steel-connections255788330 asi-steel-connections
255788330 asi-steel-connections
 
Connections in steel structures
Connections in steel structuresConnections in steel structures
Connections in steel structures
 
Pile Eccentricity Analysis for 2 Columns Combined Pilecap
Pile Eccentricity Analysis for 2 Columns Combined PilecapPile Eccentricity Analysis for 2 Columns Combined Pilecap
Pile Eccentricity Analysis for 2 Columns Combined Pilecap
 
Wind load calculation
Wind load calculationWind load calculation
Wind load calculation
 
Precast pretensioned concrete girders
Precast pretensioned concrete girdersPrecast pretensioned concrete girders
Precast pretensioned concrete girders
 

Similar to Reinforcement welding in civil engineering

Weld Defects
Weld DefectsWeld Defects
Weld Defectsadminn2
 
Handboek Aristorod Lasdraden
Handboek Aristorod LasdradenHandboek Aristorod Lasdraden
Handboek Aristorod LasdradenJorg Eichhorn
 
UNIT 2 RESISTANCE WELDING PROCESSES
UNIT 2 RESISTANCE WELDING PROCESSESUNIT 2 RESISTANCE WELDING PROCESSES
UNIT 2 RESISTANCE WELDING PROCESSESLearnMech
 
Connection_Design.ppt
Connection_Design.pptConnection_Design.ppt
Connection_Design.pptkasarla sagar
 
Connection_Design.ppt
Connection_Design.pptConnection_Design.ppt
Connection_Design.pptDrAlfia
 
Connection_Design.ppt
Connection_Design.pptConnection_Design.ppt
Connection_Design.pptssuser474b33
 
Chapter 3.0.2 All Welding Part 2.pdf
Chapter 3.0.2 All Welding Part 2.pdfChapter 3.0.2 All Welding Part 2.pdf
Chapter 3.0.2 All Welding Part 2.pdfHemantchandraPatel
 
Manufacturing Technology I
Manufacturing Technology I Manufacturing Technology I
Manufacturing Technology I Karthikeyan I
 
Tube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptTube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptssuserea7ebc
 
DFM welding.pptx
DFM welding.pptxDFM welding.pptx
DFM welding.pptxPradeepNB2
 
Presentation on steel, fabrication & erection Munger Ganga Bridge
Presentation on steel, fabrication & erection  Munger Ganga BridgePresentation on steel, fabrication & erection  Munger Ganga Bridge
Presentation on steel, fabrication & erection Munger Ganga BridgeAshish Kumar Yadav
 
Catalogo cmw soldadura
Catalogo cmw soldaduraCatalogo cmw soldadura
Catalogo cmw soldaduraOscar Moro
 
How to weld fully austenitics
How to weld fully austeniticsHow to weld fully austenitics
How to weld fully austeniticsKamal Shah
 

Similar to Reinforcement welding in civil engineering (20)

9417
94179417
9417
 
Plasma Arc Welding
Plasma Arc WeldingPlasma Arc Welding
Plasma Arc Welding
 
Weld Defects
Weld DefectsWeld Defects
Weld Defects
 
Handboek Aristorod Lasdraden
Handboek Aristorod LasdradenHandboek Aristorod Lasdraden
Handboek Aristorod Lasdraden
 
UNIT 2 RESISTANCE WELDING PROCESSES
UNIT 2 RESISTANCE WELDING PROCESSESUNIT 2 RESISTANCE WELDING PROCESSES
UNIT 2 RESISTANCE WELDING PROCESSES
 
Welding
WeldingWelding
Welding
 
Connection_Design.ppt
Connection_Design.pptConnection_Design.ppt
Connection_Design.ppt
 
Connection_Design.ppt
Connection_Design.pptConnection_Design.ppt
Connection_Design.ppt
 
Connection_Design.ppt
Connection_Design.pptConnection_Design.ppt
Connection_Design.ppt
 
Welding techniques
Welding techniquesWelding techniques
Welding techniques
 
Chapter 3.0.2 All Welding Part 2.pdf
Chapter 3.0.2 All Welding Part 2.pdfChapter 3.0.2 All Welding Part 2.pdf
Chapter 3.0.2 All Welding Part 2.pdf
 
Manufacturing Technology I
Manufacturing Technology I Manufacturing Technology I
Manufacturing Technology I
 
Tube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptTube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.ppt
 
DFM welding.pptx
DFM welding.pptxDFM welding.pptx
DFM welding.pptx
 
Mig welding
Mig weldingMig welding
Mig welding
 
Presentation on steel, fabrication & erection Munger Ganga Bridge
Presentation on steel, fabrication & erection  Munger Ganga BridgePresentation on steel, fabrication & erection  Munger Ganga Bridge
Presentation on steel, fabrication & erection Munger Ganga Bridge
 
Catalogo cmw soldadura
Catalogo cmw soldaduraCatalogo cmw soldadura
Catalogo cmw soldadura
 
Catalogo cmw
Catalogo cmwCatalogo cmw
Catalogo cmw
 
Welding iv
Welding   ivWelding   iv
Welding iv
 
How to weld fully austenitics
How to weld fully austeniticsHow to weld fully austenitics
How to weld fully austenitics
 

More from Amardeep Singh

Concrete m ix design m 15 with bottom ash
Concrete m ix design m 15 with bottom ashConcrete m ix design m 15 with bottom ash
Concrete m ix design m 15 with bottom ashAmardeep Singh
 
Sand chimney and sand blanket in Earthen Dam construction
Sand chimney and sand blanket in Earthen Dam constructionSand chimney and sand blanket in Earthen Dam construction
Sand chimney and sand blanket in Earthen Dam constructionAmardeep Singh
 
Standard Penetration Test for soils
Standard Penetration Test for soilsStandard Penetration Test for soils
Standard Penetration Test for soilsAmardeep Singh
 
Sand chimney in embankment of dam
Sand chimney in embankment of damSand chimney in embankment of dam
Sand chimney in embankment of damAmardeep Singh
 
Roads design as per IRC 37
Roads design as per IRC 37Roads design as per IRC 37
Roads design as per IRC 37Amardeep Singh
 
Triaxial shear test of soils
Triaxial shear test of soilsTriaxial shear test of soils
Triaxial shear test of soilsAmardeep Singh
 
Bearing capacity of rocky strata
Bearing capacity of rocky strata Bearing capacity of rocky strata
Bearing capacity of rocky strata Amardeep Singh
 
Pre and post concreting checks
Pre and post concreting checksPre and post concreting checks
Pre and post concreting checksAmardeep Singh
 
Min max dosage of admixture
Min max dosage of admixtureMin max dosage of admixture
Min max dosage of admixtureAmardeep Singh
 
Design mix method of bitumenous materials by Marshall stability method
Design mix method of bitumenous materials by Marshall stability methodDesign mix method of bitumenous materials by Marshall stability method
Design mix method of bitumenous materials by Marshall stability methodAmardeep Singh
 

More from Amardeep Singh (11)

Concrete m ix design m 15 with bottom ash
Concrete m ix design m 15 with bottom ashConcrete m ix design m 15 with bottom ash
Concrete m ix design m 15 with bottom ash
 
Bearings in Bridges
Bearings in BridgesBearings in Bridges
Bearings in Bridges
 
Sand chimney and sand blanket in Earthen Dam construction
Sand chimney and sand blanket in Earthen Dam constructionSand chimney and sand blanket in Earthen Dam construction
Sand chimney and sand blanket in Earthen Dam construction
 
Standard Penetration Test for soils
Standard Penetration Test for soilsStandard Penetration Test for soils
Standard Penetration Test for soils
 
Sand chimney in embankment of dam
Sand chimney in embankment of damSand chimney in embankment of dam
Sand chimney in embankment of dam
 
Roads design as per IRC 37
Roads design as per IRC 37Roads design as per IRC 37
Roads design as per IRC 37
 
Triaxial shear test of soils
Triaxial shear test of soilsTriaxial shear test of soils
Triaxial shear test of soils
 
Bearing capacity of rocky strata
Bearing capacity of rocky strata Bearing capacity of rocky strata
Bearing capacity of rocky strata
 
Pre and post concreting checks
Pre and post concreting checksPre and post concreting checks
Pre and post concreting checks
 
Min max dosage of admixture
Min max dosage of admixtureMin max dosage of admixture
Min max dosage of admixture
 
Design mix method of bitumenous materials by Marshall stability method
Design mix method of bitumenous materials by Marshall stability methodDesign mix method of bitumenous materials by Marshall stability method
Design mix method of bitumenous materials by Marshall stability method
 

Recently uploaded

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 

Reinforcement welding in civil engineering

  • 2. 2 WELDING OF REINFORCEMENT • IS : 1786 allows the chemical composition and carbon equivalent to be limited so that the material can be readily welded by conventional welding procedures. • Material not conforming to these limits is generally difficult to weld for which special care and precautions will have to be exercised. • IS : 9417 may be followed for welding in Cold Worked Steel Bars Is welding in reinforcement allowed ?
  • 3. 3 WELDING OF REINFORCEMENT • For guaranteed weld ability, the Carbon Equivalent, CE using the formula CE = C+ Mn/6 + (Cr+Mo+V)/5 + (Ni+Cu)/15 shall not be more than 0.53 percent, when micro alloys/low alloys are used. CE = C+ Mn/6 • Carbon Equivalent, CE using the formula shall not be more than 0.42 percent when micro alloys/low alloys are not used. Where, CE = Carbon Equivalent, C = Carbon, MN = Manganese, Cr = Chromium, Mo = Molybdenum, V = Vanadium, Ni = Nickel and Cu = Copper Refer MTC of reinforcement Steel for values
  • 4. 4 WELDING OF REINFORCEMENT • The parent metal shall be of guaranteed weld able quality of steel conforming to IS : 1786 according to its CE. • Electrodes used shall conform to IS : 814 – part 1. Requirement :- • Sometimes welding is required at limited working spaces. • In piles where reinforcement cage bars get damaged while cutting the pile heads. • Where structure need to extended for any reason. • In TG Deck slab where the reinforcement is much congested and working space is less. • Fixing of steel structural members in concrete.
  • 5. 5 WELDING OF REINFORCEMENT • Cold-worked steel bars shall be either butt welded or lap welded. Butt welding may be carried out either by flash butt, gas pressure or by shielded metal arc welding process. Lap welding may be carried out by shielded metal arc welding process. • Bars of unequal diameter may be welded. However, in case of butt welding, the difference in, diameter of bars shall not exceed 5 mm. • The untwisted ends must be removed before welding and the surface of the ends of the bars to be welded shall be clean and free from rust, paint, grease and/or other contaminants which are likely to affect the quality of weld.
  • 6. 6 WELDING OF REINFORCEMENT • Butt-welds by metal arc welding process are normally adopted to join bars of thickness more than 20 mm. • The ends of the bars to be welded should be placed in proper alignment in clamps so that bent or eccentric joints do not result. • Flash Butt Welding of Cold-Worked Bars The bar ends shall be uniformly pushed against each other from the moment of contact to the up-setting. The transformer regulator should be so set that that current at contact area is between 80 to 90 A/mm2. If the capacity of butt welding machine or the available power is not sufficient to take the load for welding from cold, welding may be done after preheating. Satisfactory joints with only slight reduction in original strength of the bar can be achieved with a current density up to 25 A/mm2. • Butt-Welding by Shielded Metal Arc Welding Process Welding electrodes with flux covering of Type 3 or Type 6 of IS 815 : 1974 The size of electrodes depends upon the position of the bead and thickness of the bar to be welded. The root runs should be made with electrodes of size not exceeding 2’5 mm. For successive beads, the size of the electrodes should be progressively increased so that in the top bead, the electrode size does not generally exceed 3.15 mm for 20 mm bars and 5 mm for 40 mm bars. The temperature of the bars at a distance of about one bar diameter from the joints shall not exceed 300°C immediately after the bead is made. Before commencing the next bead, the temperature shall not exceed 250°C. Butt Welding
  • 7. 7 WELDING OF REINFORCEMENT • Butt Welding by Gas Pressure Welding Process Gas pressure welding is basically a hot forging process of joining the two bars end to end. The bar ends are heated by a multi-nozzle burner using oxy-acetylene flame and fused by forcing the two bar ends against each other under pressure to effect a solid phase welded joint. Butt Welding
  • 9. 9 WELDING OF REINFORCEMENT • Lap Welding of Cold-Worked Bars Lap joints may be made in cold-worked bars of all sizes. They are preferred when access for welding is from one side only, and while connecting prefabricated units. Use of electrodes with flux covering of Type 3 or Type 6 of IS 815 : 1974 The surface of the bars to be welded shall be clean and free from rust, paint, grease and/or other contaminants. Lap Welding Rebar Diameter vs. Electrode size Sr. No Nominal Diameter of Bar (mm) Size of Electrode max (mm) 1 Up to and including 10 mm 2.5 2 Over 10 up to and including 18 mm 3.15 3 Over 18 up to and including 28 mm 4.0 4 Over 28 mm 5.0
  • 12. 12 QUALITY CONTROL TESTS • Tensile test : Specimens with a free length between grips about 20d should he used. The selected pieces when subjected to a tensile test shall have tensile strength not less than 90 percent or the actual tensile strength of the bar but in no case less than 485 MPa for grade Fe 415 and 545 MPa for grade Fe 500 of IS 1786. The fracture shall not take place in the weld joint. • Bend test : The welding flash or reinforcement shall be removed at the point where contact is made with the mandrel. The welded joint shall be capable of being bent to an angle of 60 degree around a mandrel of diameter specified below, before any crack appears: Sr. no Nominal Diameter of Bar (mm) Diameter of mandrel ( mm) 1 Up to 5 d 2 Over 7 d Butt Welding
  • 13. 13 QUALITY CONTROL TESTS • Tensile test : The free specimen length between grips must be between 25 d and 30 d where d is the nominal diameter of the bar. The breaking load shall not be less than the guaranteed load in accordance with IS 1786 required to fracture the bar. Lap Welding
  • 14. 14 PRECAUTIONS IN REINFORCEMENT BARS The reinforcement bar should not cut with flame because when it is heated and air cooled the surface will be lost and strength of bar will approach to center of bar. Loss of strength is the reason to restrict the cutting of bar with flame. The bending of bar should be done in correct radius of mandrel because tighter the bend greater the strains around the bar. The bend diameters should be followed as per IS : 2502 to maintain ductility and practical construction operations.
  • 15. 15