SITE INDUCTION
WELCOME 
Site Induction For Your Safety 
Introduction 
This induction is given to all operatives before they work on site. 
It provides you with specific information about the project, the team 
undertaking the work and how you can actively participate in the safe 
completion of the works. 
The company expects employees to put Safety First before anything else
The Project 
 Installation of a 16.2 MW Photovoltaic Plant. 
 Erecting security fencing; 
 Driving the framework into the ground; 
 Affixing the panels to the mounting frames; 
 Trenching for the cable runs to depth of approximately 1m, and laying cables; 
 Installation of the inverter, transformer cabinets, control room and substation;
Key Personnel 
 Client Sun Edison 
 CDMC HSEF 
 Principal Contractor Sun Edison 
 Project Manager Carlos Rodriguez 
 Site Manager Jorge Arce 
Contractors 
 Eiffage Energia 
 Axial Solar
Responsibilities and Duty of Care 
 You have a legal duty to take care of your own Health & 
Safety as well as people around you. 
 You must inspect your own workplace before starting work 
and during work regularly. 
 You have a legal responsibility regarding the Health & 
Safety of members the public.(NB unauthorised entry) 
 It is the responsibility of all personnel to improve Health & 
Safety standards.
PPE (Personal Protective Equipment) 
Minimum PPE requirements (to be worn at all times): 
 Hard hat 
 Safety boots 
 High visibility vest 
 Gloves 
 Light eye protection (task specific) 
Other items will be worn as operations dictate i.e. goggles/dust masks/ear 
defenders/harnesses etc. 
Your supervisor will be responsible for instructing you on when and where 
these should be worn.
Site Rules 
 Wear correct fitting PPE appropriate to the operation and which is in good 
condition, at all times; 
 Anyone considered to have taken alcohol or be under the influence of drugs 
will be permanently removed from site; 
 Permits are required for the following operations: excavations, lifting 
operation, hot works, confined space entry; 
 Obey all safety notices and signs; 
 Do not indulge in horseplay; 
 Do not intentionally misuse anything which is provided in the interest of 
H&S or welfare facilities.
Site Rules 
 Maintain the workplace in a tidy condition free from avoidable hazards; 
 Report any concerns, near misses or incidents to site management immediately; 
 All vehicles/plant must be kept securely locked when left unattended; 
 A banksman shall be utilised for all plant movements; 
 No keys to be left in unattended vehicles; 
 Temporary fencing must be maintained at all times; 
 Mobile phones can only be used from a position of safety when person is not 
directly involved in an ongoing operation.
Welfare Arrangements 
 Toilets are located in the site compound area; 
 A canteen is provided in the site compound area; 
 A drying room is provided in the site compound area. 
Please ensure that welfare facilities are kept clean & tidy
Emergency Procedures 
 In the event of an emergency or fire, the alarm shall be 
raised by shouting or using the horn located in the project 
office. 
 Operatives shall follow the designated trakway route from 
their working area to the site assembly point behind the 
security cabin (near the entrance to site)
Accident & Near Miss Reporting Procedures 
 If you suffer an injury, how ever small please inform one of our first 
aiders immediately and report it to the site manager as soon as 
possible. The health & safety advisor will then enter your details into 
the Accident Book located in the project office. 
 If you are involved in a near miss or are witness to one please help 
us to prevent reoccurrence by reporting it using one of the following 
ways: 
• Telling a member of staff. 
• Completing a near miss form located in the project office 
• Telephoning the site offices
Hazards on Site 
Overhead Power Lines 
 High voltage lines 8 meters above the ground level 
 Goalpost system must be adhered to when passing or 
working under
Vehicles and Heavy Machinery
Environmental Protection 
In the event of a spill 
STOP WORK – PREVENT anymore material spilling. 
Eliminate all sources of ignition if it’s flammable. 
Contain the spill using bunds, absorbent pads or sand, check spills 
have not reached any ditches or water courses. 
Notify your supervisor of the material spilt, quantity, location of 
spill, and any action taken. 
Ensure that you dispose of your waste in the correct skip. 
All waste must be segregated to satisfy our Duty of care to eliminate, 
reduce, reuse and recycle waste bound for landfill.

More Related Content

What's hot

HSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptHSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptssuser0ebdc3
 
Working at-height
Working at-height Working at-height
Working at-height Reliance
 
Emergency Response Planning Training
Emergency Response Planning Training Emergency Response Planning Training
Emergency Response Planning Training Laura Lee
 
Visitors SHE Induction Presentation 2016
Visitors SHE Induction Presentation 2016Visitors SHE Induction Presentation 2016
Visitors SHE Induction Presentation 2016Chris Morris
 
Arabtec safety man and machine presentation june 2019 rev-1
Arabtec safety man and machine presentation june 2019 rev-1Arabtec safety man and machine presentation june 2019 rev-1
Arabtec safety man and machine presentation june 2019 rev-1Dwarika Bhushan Sharma
 
Emergency Evacuation Procedures
Emergency Evacuation ProceduresEmergency Evacuation Procedures
Emergency Evacuation Procedurestrevor_heller
 
EHS induction Presentation slides
EHS induction Presentation slidesEHS induction Presentation slides
EHS induction Presentation slidesMaffino
 
Induction process for new employee
Induction process for new employeeInduction process for new employee
Induction process for new employeeseamjami
 
New Employee Safety Orientation
New Employee Safety OrientationNew Employee Safety Orientation
New Employee Safety OrientationBeamer
 
EMERGENCY RESPONSE TEAM (ERT).pptx
EMERGENCY RESPONSE TEAM (ERT).pptxEMERGENCY RESPONSE TEAM (ERT).pptx
EMERGENCY RESPONSE TEAM (ERT).pptxssuserd19c3e
 
Gsk training general 2017
Gsk training general   2017Gsk training general   2017
Gsk training general 2017brijesh singh
 
Weekly safety report abhishek vij
Weekly safety report abhishek vijWeekly safety report abhishek vij
Weekly safety report abhishek vijAbhishek Vij
 
New Employee Orientation 05
New Employee Orientation 05New Employee Orientation 05
New Employee Orientation 05txsafety1
 

What's hot (20)

HSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.pptHSE-INDUCTION-TRAINING.ppt
HSE-INDUCTION-TRAINING.ppt
 
Working at-height
Working at-height Working at-height
Working at-height
 
Emergency Response Planning Training
Emergency Response Planning Training Emergency Response Planning Training
Emergency Response Planning Training
 
Visitors SHE Induction Presentation 2016
Visitors SHE Induction Presentation 2016Visitors SHE Induction Presentation 2016
Visitors SHE Induction Presentation 2016
 
Arabtec safety man and machine presentation june 2019 rev-1
Arabtec safety man and machine presentation june 2019 rev-1Arabtec safety man and machine presentation june 2019 rev-1
Arabtec safety man and machine presentation june 2019 rev-1
 
Forklift training
Forklift training Forklift training
Forklift training
 
Emergency Evacuation Procedures
Emergency Evacuation ProceduresEmergency Evacuation Procedures
Emergency Evacuation Procedures
 
EHS induction Presentation slides
EHS induction Presentation slidesEHS induction Presentation slides
EHS induction Presentation slides
 
Induction process for new employee
Induction process for new employeeInduction process for new employee
Induction process for new employee
 
Toolbox Talk-Working at height
Toolbox Talk-Working at height Toolbox Talk-Working at height
Toolbox Talk-Working at height
 
Workplace hazards
Workplace hazardsWorkplace hazards
Workplace hazards
 
Emergency Response Teams
Emergency Response TeamsEmergency Response Teams
Emergency Response Teams
 
Work at height. The basic needs.
Work at height. The basic needs.Work at height. The basic needs.
Work at height. The basic needs.
 
Construction Safety Training
Construction Safety TrainingConstruction Safety Training
Construction Safety Training
 
New Employee Safety Orientation
New Employee Safety OrientationNew Employee Safety Orientation
New Employee Safety Orientation
 
EMERGENCY RESPONSE TEAM (ERT).pptx
EMERGENCY RESPONSE TEAM (ERT).pptxEMERGENCY RESPONSE TEAM (ERT).pptx
EMERGENCY RESPONSE TEAM (ERT).pptx
 
Lifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptxLifting Operation Safety ppt.pptx
Lifting Operation Safety ppt.pptx
 
Gsk training general 2017
Gsk training general   2017Gsk training general   2017
Gsk training general 2017
 
Weekly safety report abhishek vij
Weekly safety report abhishek vijWeekly safety report abhishek vij
Weekly safety report abhishek vij
 
New Employee Orientation 05
New Employee Orientation 05New Employee Orientation 05
New Employee Orientation 05
 

Similar to SITE INDUCTION Version 2

DPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxDPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxAamirAbbas75
 
Iipp haz com-ppe-fp-evac-p65-bp
Iipp haz com-ppe-fp-evac-p65-bpIipp haz com-ppe-fp-evac-p65-bp
Iipp haz com-ppe-fp-evac-p65-bpKJP Consulting
 
Sydney Gateway Rail Duplication Induction v1.4
Sydney Gateway Rail Duplication Induction v1.4Sydney Gateway Rail Duplication Induction v1.4
Sydney Gateway Rail Duplication Induction v1.4Garry Pepper
 
Sydney gateway rail duplication induction v1.4
Sydney gateway rail duplication induction v1.4Sydney gateway rail duplication induction v1.4
Sydney gateway rail duplication induction v1.4Garry Pepper
 
AMA 2A SHE Induction 2022....pdf
AMA 2A SHE Induction 2022....pdfAMA 2A SHE Induction 2022....pdf
AMA 2A SHE Induction 2022....pdfIbukunOwolabi4
 
General Safety Presentation
General Safety PresentationGeneral Safety Presentation
General Safety Presentationgtwaddell
 
General Safety Presentationupdated 04842993 1
General Safety Presentationupdated 04842993 1General Safety Presentationupdated 04842993 1
General Safety Presentationupdated 04842993 1debandleigh
 
general-safety-presentationupdated-gt-1233624442182954-1.pptx
general-safety-presentationupdated-gt-1233624442182954-1.pptxgeneral-safety-presentationupdated-gt-1233624442182954-1.pptx
general-safety-presentationupdated-gt-1233624442182954-1.pptxsyedatifullahhadi
 
Turn Key Group Services - OHS Toolkit
Turn Key Group Services - OHS ToolkitTurn Key Group Services - OHS Toolkit
Turn Key Group Services - OHS Toolkitturnkeygroupservices
 
Operator Training
Operator TrainingOperator Training
Operator TrainingDariusDelon
 
Health and safety plan generic
Health and safety plan genericHealth and safety plan generic
Health and safety plan genericfirstpick
 
ACT Environment Induction
ACT Environment InductionACT Environment Induction
ACT Environment InductionDotjo Dev
 
SITE SAFETY INDUCTION ENGINEERING TRAINING
SITE SAFETY INDUCTION ENGINEERING TRAININGSITE SAFETY INDUCTION ENGINEERING TRAINING
SITE SAFETY INDUCTION ENGINEERING TRAININGsatheesh843134
 
Home Builders Training Program | Chris Collins Dacula ga
Home Builders Training Program | Chris Collins Dacula gaHome Builders Training Program | Chris Collins Dacula ga
Home Builders Training Program | Chris Collins Dacula gaChris Collins Dacula ga
 
117921179 saudi-aramco-safety-handbook
117921179 saudi-aramco-safety-handbook117921179 saudi-aramco-safety-handbook
117921179 saudi-aramco-safety-handbookkhalil maroun
 
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14
Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14fahadansari131
 
Infraworks plumbing induction feb 19 v1.0
Infraworks plumbing induction feb 19 v1.0Infraworks plumbing induction feb 19 v1.0
Infraworks plumbing induction feb 19 v1.0Garry Pepper
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdfFESTUS RICHARD SIAME
 

Similar to SITE INDUCTION Version 2 (20)

DPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptxDPL-SP - Safety Induction Presentation 00.pptx
DPL-SP - Safety Induction Presentation 00.pptx
 
Iipp haz com-ppe-fp-evac-p65-bp
Iipp haz com-ppe-fp-evac-p65-bpIipp haz com-ppe-fp-evac-p65-bp
Iipp haz com-ppe-fp-evac-p65-bp
 
Sydney Gateway Rail Duplication Induction v1.4
Sydney Gateway Rail Duplication Induction v1.4Sydney Gateway Rail Duplication Induction v1.4
Sydney Gateway Rail Duplication Induction v1.4
 
Sydney gateway rail duplication induction v1.4
Sydney gateway rail duplication induction v1.4Sydney gateway rail duplication induction v1.4
Sydney gateway rail duplication induction v1.4
 
AMA 2A SHE Induction 2022....pdf
AMA 2A SHE Induction 2022....pdfAMA 2A SHE Induction 2022....pdf
AMA 2A SHE Induction 2022....pdf
 
General Safety Presentation
General Safety PresentationGeneral Safety Presentation
General Safety Presentation
 
General Safety Presentationupdated 04842993 1
General Safety Presentationupdated 04842993 1General Safety Presentationupdated 04842993 1
General Safety Presentationupdated 04842993 1
 
general-safety-presentationupdated-gt-1233624442182954-1.pptx
general-safety-presentationupdated-gt-1233624442182954-1.pptxgeneral-safety-presentationupdated-gt-1233624442182954-1.pptx
general-safety-presentationupdated-gt-1233624442182954-1.pptx
 
Turn Key Group Services - OHS Toolkit
Turn Key Group Services - OHS ToolkitTurn Key Group Services - OHS Toolkit
Turn Key Group Services - OHS Toolkit
 
Safety.pdf
Safety.pdfSafety.pdf
Safety.pdf
 
Operator Training
Operator TrainingOperator Training
Operator Training
 
Health and safety plan generic
Health and safety plan genericHealth and safety plan generic
Health and safety plan generic
 
ACT Environment Induction
ACT Environment InductionACT Environment Induction
ACT Environment Induction
 
SITE SAFETY INDUCTION ENGINEERING TRAINING
SITE SAFETY INDUCTION ENGINEERING TRAININGSITE SAFETY INDUCTION ENGINEERING TRAINING
SITE SAFETY INDUCTION ENGINEERING TRAINING
 
Home Builders Training Program | Chris Collins Dacula ga
Home Builders Training Program | Chris Collins Dacula gaHome Builders Training Program | Chris Collins Dacula ga
Home Builders Training Program | Chris Collins Dacula ga
 
117921179 saudi-aramco-safety-handbook
117921179 saudi-aramco-safety-handbook117921179 saudi-aramco-safety-handbook
117921179 saudi-aramco-safety-handbook
 
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14
Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14Safety handbook Saudi Aramco  BY Muhammad Fahad Ansari  12IEEM14
Safety handbook Saudi Aramco BY Muhammad Fahad Ansari 12IEEM14
 
Infraworks plumbing induction feb 19 v1.0
Infraworks plumbing induction feb 19 v1.0Infraworks plumbing induction feb 19 v1.0
Infraworks plumbing induction feb 19 v1.0
 
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
008-SWMS-GENERAL-ONSITE-ACTIVITIES-AND-REPAIRS.pdf
 
Safety_First
Safety_FirstSafety_First
Safety_First
 

SITE INDUCTION Version 2

  • 2. WELCOME Site Induction For Your Safety Introduction This induction is given to all operatives before they work on site. It provides you with specific information about the project, the team undertaking the work and how you can actively participate in the safe completion of the works. The company expects employees to put Safety First before anything else
  • 3. The Project  Installation of a 16.2 MW Photovoltaic Plant.  Erecting security fencing;  Driving the framework into the ground;  Affixing the panels to the mounting frames;  Trenching for the cable runs to depth of approximately 1m, and laying cables;  Installation of the inverter, transformer cabinets, control room and substation;
  • 4. Key Personnel  Client Sun Edison  CDMC HSEF  Principal Contractor Sun Edison  Project Manager Carlos Rodriguez  Site Manager Jorge Arce Contractors  Eiffage Energia  Axial Solar
  • 5. Responsibilities and Duty of Care  You have a legal duty to take care of your own Health & Safety as well as people around you.  You must inspect your own workplace before starting work and during work regularly.  You have a legal responsibility regarding the Health & Safety of members the public.(NB unauthorised entry)  It is the responsibility of all personnel to improve Health & Safety standards.
  • 6. PPE (Personal Protective Equipment) Minimum PPE requirements (to be worn at all times):  Hard hat  Safety boots  High visibility vest  Gloves  Light eye protection (task specific) Other items will be worn as operations dictate i.e. goggles/dust masks/ear defenders/harnesses etc. Your supervisor will be responsible for instructing you on when and where these should be worn.
  • 7. Site Rules  Wear correct fitting PPE appropriate to the operation and which is in good condition, at all times;  Anyone considered to have taken alcohol or be under the influence of drugs will be permanently removed from site;  Permits are required for the following operations: excavations, lifting operation, hot works, confined space entry;  Obey all safety notices and signs;  Do not indulge in horseplay;  Do not intentionally misuse anything which is provided in the interest of H&S or welfare facilities.
  • 8. Site Rules  Maintain the workplace in a tidy condition free from avoidable hazards;  Report any concerns, near misses or incidents to site management immediately;  All vehicles/plant must be kept securely locked when left unattended;  A banksman shall be utilised for all plant movements;  No keys to be left in unattended vehicles;  Temporary fencing must be maintained at all times;  Mobile phones can only be used from a position of safety when person is not directly involved in an ongoing operation.
  • 9. Welfare Arrangements  Toilets are located in the site compound area;  A canteen is provided in the site compound area;  A drying room is provided in the site compound area. Please ensure that welfare facilities are kept clean & tidy
  • 10. Emergency Procedures  In the event of an emergency or fire, the alarm shall be raised by shouting or using the horn located in the project office.  Operatives shall follow the designated trakway route from their working area to the site assembly point behind the security cabin (near the entrance to site)
  • 11. Accident & Near Miss Reporting Procedures  If you suffer an injury, how ever small please inform one of our first aiders immediately and report it to the site manager as soon as possible. The health & safety advisor will then enter your details into the Accident Book located in the project office.  If you are involved in a near miss or are witness to one please help us to prevent reoccurrence by reporting it using one of the following ways: • Telling a member of staff. • Completing a near miss form located in the project office • Telephoning the site offices
  • 12. Hazards on Site Overhead Power Lines  High voltage lines 8 meters above the ground level  Goalpost system must be adhered to when passing or working under
  • 13. Vehicles and Heavy Machinery
  • 14. Environmental Protection In the event of a spill STOP WORK – PREVENT anymore material spilling. Eliminate all sources of ignition if it’s flammable. Contain the spill using bunds, absorbent pads or sand, check spills have not reached any ditches or water courses. Notify your supervisor of the material spilt, quantity, location of spill, and any action taken. Ensure that you dispose of your waste in the correct skip. All waste must be segregated to satisfy our Duty of care to eliminate, reduce, reuse and recycle waste bound for landfill.