SlideShare a Scribd company logo
1 of 15
INTERNSHIP ON
ERECTION, COMMISSIONING AND PRE-
COMISSIONING OF 500MVA TRANSFORMER
PRESENTED BY
AKINAPELLI RAHUL
161230007
Internship at
400/220KV POWER GRID
WARANGAL-SS
Submitted at
NATIONAL INSTIUTE OF TECHNOLOY DELHI
PGCIL
PGCIL –POWERGRID CORPORATION OF INDIA LIMITED
Incorporated on 23 October 1989 under the Companies Act, 1956 with an authorized share capital of Rs. 5,000
Crore.
POWERGRID transmits about 50% of the total power generated in India on its transmission network.
Its transmission network consists of roughly 148,838 circuit kilometres and 236 EHVAC and HVDC substations,
which provide total transformation capacity of 332,163 MVA. POWERGRID's interregional capacity is 75,050 MW.
POWER TRANSMISSION
THROUGH GRID SYSTEM
SINGLE LINE DIAGRAM
OF POWER GRID
DUTIES OF 400/220KV PGCIL WARANGAL-SS
Connects three power
plants with 400KV lines
Khammam
Bhupalpally
Ramagundam
Supplies power to two
cities with 220KV lines
Nagaram
Durshed
Uses ICT’s to step down
voltage from 400KV to
220KV.
One 500MVA
ICT
Two 315MVA
ICT
500MVA INTER CONNECTING TRANSFORMER
AND ITS PARTS
Provided with 3 windings
•Primary winding of 400KV and star type
•Secondary winding of 220KV and star type
•Tertiary winding of 33KV and delta type
Parts of 500MVA ICT
•Main Tank
•Laminated Core
•Windings
•Transformer Oil
•Conservator Tank
•Breather
•Radiator
•Buchholz Relay
•Pressure relief valve
•Tap Changer
ERECTION AND UNLOADING TRANSFORMER
Unloading of transformer
Erection process
• External and internal inspection
• Final tightness test with vacuum and pressure.
• Oil filling
• Hot oil circulation using oil filter machine
PRE-COMMISSIONING CHECKS
• 1st step is to prepare testing program schedule.
• Next step is pre-commissioning checks
Examples :-
a. Should be from visible defects,
b. All the valves are tightened properly,
c. Oil is filled up to desired level in bushings, main tank, conservator tank and also in
OLTC etc,.
d. All the cables are tightened and etc,.
PRE-COMMISSIONING TESTS
SFRA test:
Sweep Frequency Response Analysis is
to evaluate the mechanical integrity of core,
windings and clamping structures by
measuring their electrical transfer functions
over a wide frequency range.
Performed at 10V AC from 20Hz-20MHz
supply
Eg :-
Voltage and Turns ratio measurement:
1. Voltage ratio test uses digital multi
meter performed at 415V.
2. Transformer turns ratio test uses
automatic transformer turns ratio(TTR)
meter performed at 110V.
• Performed to locate defect
in magnetic core structure,
shifting of windings, failure
in turn to turn insulation or
problem in tap changer.
• Performed at 440V AC on
HV side and LV side is open
• Carried on min, normal and
max tap positions.
Magnetizing
current test:
• Performed to check balance in the
magnetic circuit.
• 1-phase 230V supplied between phase
and neutral and measure the voltage
induced in other two phases of the
same winding.
• Equipment used is digital multimeter.
• When voltage is applied at R-phase, Y-
phase should be 50-90% and B- phase
should be in 20-40%
• When voltage is applied at Y-phase,
other two phases induced voltage
should be in 30-70%.
Magnetic
balance
test:
• Performed to detect winding
movement which occurs due to
heavy fault current or mechanical
damage during transportation.
• A 3 phase 440V supply is given to
HV winding and LV is shorted .
• Measure primary voltage and
current in primary and secondary
• Performed on min, normal and
maximum tap positions.
• Acceptance values should be
within 3 % of impedance specified.
Short
circuit
impedance
test
• BDV test
acceptance value > 70KV
• PPM test
Moisture content < 5ppm
Tan delta at 90 degree
<0.01 Moisture content <
5ppm
Oil
characteristics
test
OTHER REMAINING TESTS
Capacitance and tan delta measurement
Verification of vector group and polarity test
Measurement of winding resistance
Winding insulation resistance measurement
Core insulation test
Testing on bushing CT’s
Measurement of earthing resistance
FINAL COMMISSIONING CHECKS
All the test results are verified and compared with factory results before commissioning.
No leakage oil in any part of unit. Ensure oil level in the Bushings
Ensure that tertiary winding terminals are insulated, when they are not used.
Ensure earthing of Neutral, main tank body, radiator frame structure, fans and motor.
And all the final verifications, continuity between switchyard and transformer meters, connections, sensors, fans attached and etc,.
ENERGISATION OF UNIT
1st charge the transformer under no load for 24 – 48 hours.
Gradually load the transformer observing the noise, vibration, temperature rise, oil leakage etc.
Check OLTC operation.
Carry out Thermo vision scanning of HV/LV terminals and tank body.
Carry out DGA test of oil as per schedule given in flow chart of this manual.
THANK YOU!!!

More Related Content

What's hot

Slip power recovery schemes EDC
Slip power recovery schemes EDC Slip power recovery schemes EDC
Slip power recovery schemes EDC STALLONRAJ
 
Method of voltage control
Method of voltage controlMethod of voltage control
Method of voltage controlVaibhav Singh
 
Distribution and Load Sharing of Transformer Automatically by using Microcont...
Distribution and Load Sharing of Transformer Automatically by using Microcont...Distribution and Load Sharing of Transformer Automatically by using Microcont...
Distribution and Load Sharing of Transformer Automatically by using Microcont...IRJET Journal
 
Methode of voltage control TD
Methode of voltage control TDMethode of voltage control TD
Methode of voltage control TDMdYeakubulHasan
 
Choice of converter configuration
Choice of converter configurationChoice of converter configuration
Choice of converter configurationjawaharramaya
 
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...Rishabhlko
 
Uttar Pradesh Power Corparation Ltd. Training Report
Uttar Pradesh Power Corparation Ltd. Training ReportUttar Pradesh Power Corparation Ltd. Training Report
Uttar Pradesh Power Corparation Ltd. Training ReportAmitKumar6931
 
Multilevel inverter fed induction motor drives
Multilevel inverter fed induction motor drivesMultilevel inverter fed induction motor drives
Multilevel inverter fed induction motor driveseSAT Journals
 
HVDC & FACTS
HVDC & FACTSHVDC & FACTS
HVDC & FACTSBrunda R
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level CalculationDinesh Sarda
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptAshutosh Srivastava
 
Unit 2.Converter and Chopper fed Dc drives
Unit 2.Converter and Chopper fed Dc drivesUnit 2.Converter and Chopper fed Dc drives
Unit 2.Converter and Chopper fed Dc drivesraviarmugam
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performancemichaeljmack
 
Automatic load sharing of transformer using microcontroller
Automatic load sharing of transformer using microcontrollerAutomatic load sharing of transformer using microcontroller
Automatic load sharing of transformer using microcontrollerPrakhar Anand
 
Speed control of dc motor using matlab
Speed control of dc motor using matlabSpeed control of dc motor using matlab
Speed control of dc motor using matlabShridhar kulkarni
 
Flexible AC Transmission (FACTS)
Flexible AC Transmission (FACTS)Flexible AC Transmission (FACTS)
Flexible AC Transmission (FACTS)SHIMI S L
 
A CASE STUDY : CHANDRAPUR-PADGHE HVDC BIPOLE
 A CASE STUDY : CHANDRAPUR-PADGHE HVDC BIPOLE A CASE STUDY : CHANDRAPUR-PADGHE HVDC BIPOLE
A CASE STUDY : CHANDRAPUR-PADGHE HVDC BIPOLEMANISH CHAVAN
 

What's hot (20)

J D J
J D JJ D J
J D J
 
Slip power recovery schemes EDC
Slip power recovery schemes EDC Slip power recovery schemes EDC
Slip power recovery schemes EDC
 
Method of voltage control
Method of voltage controlMethod of voltage control
Method of voltage control
 
Distribution and Load Sharing of Transformer Automatically by using Microcont...
Distribution and Load Sharing of Transformer Automatically by using Microcont...Distribution and Load Sharing of Transformer Automatically by using Microcont...
Distribution and Load Sharing of Transformer Automatically by using Microcont...
 
Methode of voltage control TD
Methode of voltage control TDMethode of voltage control TD
Methode of voltage control TD
 
Static kramer system
Static kramer systemStatic kramer system
Static kramer system
 
Choice of converter configuration
Choice of converter configurationChoice of converter configuration
Choice of converter configuration
 
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
PRESENTATION ON UPPTCL 220 KV TRANSMISSION SUMMER TRAINING BANDA, BANDA FROM ...
 
Uttar Pradesh Power Corparation Ltd. Training Report
Uttar Pradesh Power Corparation Ltd. Training ReportUttar Pradesh Power Corparation Ltd. Training Report
Uttar Pradesh Power Corparation Ltd. Training Report
 
Multilevel inverter fed induction motor drives
Multilevel inverter fed induction motor drivesMultilevel inverter fed induction motor drives
Multilevel inverter fed induction motor drives
 
HVDC & FACTS
HVDC & FACTSHVDC & FACTS
HVDC & FACTS
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
Hvdc
HvdcHvdc
Hvdc
 
Industrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation pptIndustrial summer training on 220 kv substation ppt
Industrial summer training on 220 kv substation ppt
 
Unit 2.Converter and Chopper fed Dc drives
Unit 2.Converter and Chopper fed Dc drivesUnit 2.Converter and Chopper fed Dc drives
Unit 2.Converter and Chopper fed Dc drives
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
 
Automatic load sharing of transformer using microcontroller
Automatic load sharing of transformer using microcontrollerAutomatic load sharing of transformer using microcontroller
Automatic load sharing of transformer using microcontroller
 
Speed control of dc motor using matlab
Speed control of dc motor using matlabSpeed control of dc motor using matlab
Speed control of dc motor using matlab
 
Flexible AC Transmission (FACTS)
Flexible AC Transmission (FACTS)Flexible AC Transmission (FACTS)
Flexible AC Transmission (FACTS)
 
A CASE STUDY : CHANDRAPUR-PADGHE HVDC BIPOLE
 A CASE STUDY : CHANDRAPUR-PADGHE HVDC BIPOLE A CASE STUDY : CHANDRAPUR-PADGHE HVDC BIPOLE
A CASE STUDY : CHANDRAPUR-PADGHE HVDC BIPOLE
 

Similar to INSTALLATION OF 500MVA TRANSFORMER AT PGCIL

REPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTREPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTRAJPRASAD RS
 
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622MOHAMMAD KHALID MUSTAFA
 
Appraisal ppt ankur
Appraisal ppt ankurAppraisal ppt ankur
Appraisal ppt ankurAnkur Mishra
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptChristinaBoyd12
 
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.pptsantubanga333
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptssuser1f60f6
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protectionRakesh Joshi
 
Introduction of transfromer
Introduction of transfromerIntroduction of transfromer
Introduction of transfromerpretty gurna
 
MPEB, MPPKVVCL Indore 15 days Training Seminar
MPEB, MPPKVVCL Indore 15 days Training SeminarMPEB, MPPKVVCL Indore 15 days Training Seminar
MPEB, MPPKVVCL Indore 15 days Training SeminarSuraj Talreja
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHShankar Singh
 
C18808 elc tech
C18808 elc techC18808 elc tech
C18808 elc techEDWIN S
 
Switch yard pp 2 kanti thermal power station
Switch yard pp 2 kanti thermal power stationSwitch yard pp 2 kanti thermal power station
Switch yard pp 2 kanti thermal power stationneeraj prasad
 
Vipin Resume
Vipin ResumeVipin Resume
Vipin ResumeVipin Das
 

Similar to INSTALLATION OF 500MVA TRANSFORMER AT PGCIL (20)

REPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTREPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANT
 
cv of pjnehru
cv of pjnehrucv of pjnehru
cv of pjnehru
 
16950
1695016950
16950
 
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622ELECHTRICAL   COMMISSIONING  TECHNICIAN   2201622
ELECHTRICAL COMMISSIONING TECHNICIAN 2201622
 
Appraisal ppt ankur
Appraisal ppt ankurAppraisal ppt ankur
Appraisal ppt ankur
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protection
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Introduction of transfromer
Introduction of transfromerIntroduction of transfromer
Introduction of transfromer
 
MPEB, MPPKVVCL Indore 15 days Training Seminar
MPEB, MPPKVVCL Indore 15 days Training SeminarMPEB, MPPKVVCL Indore 15 days Training Seminar
MPEB, MPPKVVCL Indore 15 days Training Seminar
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
 
Transformer
TransformerTransformer
Transformer
 
Gss ppt by kanhaiya
Gss ppt  by kanhaiyaGss ppt  by kanhaiya
Gss ppt by kanhaiya
 
C18808 elc tech
C18808 elc techC18808 elc tech
C18808 elc tech
 
Switch yard pp 2 kanti thermal power station
Switch yard pp 2 kanti thermal power stationSwitch yard pp 2 kanti thermal power station
Switch yard pp 2 kanti thermal power station
 
Vipin Resume
Vipin ResumeVipin Resume
Vipin Resume
 

Recently uploaded

ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxDr.Ibrahim Hassaan
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxabhijeetpadhi001
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 

Recently uploaded (20)

ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Gas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptxGas measurement O2,Co2,& ph) 04/2024.pptx
Gas measurement O2,Co2,& ph) 04/2024.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptx
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 

INSTALLATION OF 500MVA TRANSFORMER AT PGCIL

  • 1. INTERNSHIP ON ERECTION, COMMISSIONING AND PRE- COMISSIONING OF 500MVA TRANSFORMER PRESENTED BY AKINAPELLI RAHUL 161230007 Internship at 400/220KV POWER GRID WARANGAL-SS Submitted at NATIONAL INSTIUTE OF TECHNOLOY DELHI
  • 2. PGCIL PGCIL –POWERGRID CORPORATION OF INDIA LIMITED Incorporated on 23 October 1989 under the Companies Act, 1956 with an authorized share capital of Rs. 5,000 Crore. POWERGRID transmits about 50% of the total power generated in India on its transmission network. Its transmission network consists of roughly 148,838 circuit kilometres and 236 EHVAC and HVDC substations, which provide total transformation capacity of 332,163 MVA. POWERGRID's interregional capacity is 75,050 MW.
  • 5. DUTIES OF 400/220KV PGCIL WARANGAL-SS Connects three power plants with 400KV lines Khammam Bhupalpally Ramagundam Supplies power to two cities with 220KV lines Nagaram Durshed Uses ICT’s to step down voltage from 400KV to 220KV. One 500MVA ICT Two 315MVA ICT
  • 6. 500MVA INTER CONNECTING TRANSFORMER AND ITS PARTS Provided with 3 windings •Primary winding of 400KV and star type •Secondary winding of 220KV and star type •Tertiary winding of 33KV and delta type Parts of 500MVA ICT •Main Tank •Laminated Core •Windings •Transformer Oil •Conservator Tank •Breather •Radiator •Buchholz Relay •Pressure relief valve •Tap Changer
  • 7. ERECTION AND UNLOADING TRANSFORMER Unloading of transformer Erection process • External and internal inspection • Final tightness test with vacuum and pressure. • Oil filling • Hot oil circulation using oil filter machine
  • 8. PRE-COMMISSIONING CHECKS • 1st step is to prepare testing program schedule. • Next step is pre-commissioning checks Examples :- a. Should be from visible defects, b. All the valves are tightened properly, c. Oil is filled up to desired level in bushings, main tank, conservator tank and also in OLTC etc,. d. All the cables are tightened and etc,.
  • 9. PRE-COMMISSIONING TESTS SFRA test: Sweep Frequency Response Analysis is to evaluate the mechanical integrity of core, windings and clamping structures by measuring their electrical transfer functions over a wide frequency range. Performed at 10V AC from 20Hz-20MHz supply Eg :- Voltage and Turns ratio measurement: 1. Voltage ratio test uses digital multi meter performed at 415V. 2. Transformer turns ratio test uses automatic transformer turns ratio(TTR) meter performed at 110V.
  • 10. • Performed to locate defect in magnetic core structure, shifting of windings, failure in turn to turn insulation or problem in tap changer. • Performed at 440V AC on HV side and LV side is open • Carried on min, normal and max tap positions. Magnetizing current test: • Performed to check balance in the magnetic circuit. • 1-phase 230V supplied between phase and neutral and measure the voltage induced in other two phases of the same winding. • Equipment used is digital multimeter. • When voltage is applied at R-phase, Y- phase should be 50-90% and B- phase should be in 20-40% • When voltage is applied at Y-phase, other two phases induced voltage should be in 30-70%. Magnetic balance test:
  • 11. • Performed to detect winding movement which occurs due to heavy fault current or mechanical damage during transportation. • A 3 phase 440V supply is given to HV winding and LV is shorted . • Measure primary voltage and current in primary and secondary • Performed on min, normal and maximum tap positions. • Acceptance values should be within 3 % of impedance specified. Short circuit impedance test • BDV test acceptance value > 70KV • PPM test Moisture content < 5ppm Tan delta at 90 degree <0.01 Moisture content < 5ppm Oil characteristics test
  • 12. OTHER REMAINING TESTS Capacitance and tan delta measurement Verification of vector group and polarity test Measurement of winding resistance Winding insulation resistance measurement Core insulation test Testing on bushing CT’s Measurement of earthing resistance
  • 13. FINAL COMMISSIONING CHECKS All the test results are verified and compared with factory results before commissioning. No leakage oil in any part of unit. Ensure oil level in the Bushings Ensure that tertiary winding terminals are insulated, when they are not used. Ensure earthing of Neutral, main tank body, radiator frame structure, fans and motor. And all the final verifications, continuity between switchyard and transformer meters, connections, sensors, fans attached and etc,.
  • 14. ENERGISATION OF UNIT 1st charge the transformer under no load for 24 – 48 hours. Gradually load the transformer observing the noise, vibration, temperature rise, oil leakage etc. Check OLTC operation. Carry out Thermo vision scanning of HV/LV terminals and tank body. Carry out DGA test of oil as per schedule given in flow chart of this manual.