PLATFORM STABILITY
MANAGEMENT PROGRAM
Violeta Gabrovska
June 2015
ยฉ Copyright QinetiQ Pty Ltd 2013
2
Contents
1. Introduction
2. Stability program governance and management
๏ฏ Stability compliance
๏ฏ Weight management and various interfaces
๏ฏ Docking and slipping
3. Conclusion
ยฉ Copyright QinetiQ Pty Ltd 2013
1. Introduction
Stability - critical safety characteristic failure of which may
result in:
loss of life,
early cancellation of a mission and
total loss of a vessel
Maintain low risk of failure - compliance with designated
set of rules
Influencing factors -
lightship growth and
weight distribution
3
ยฉ Copyright QinetiQ Pty Ltd 2013
1. Introduction
Stability Program is
designed to manage the
compliance and validation
process and the interaction
between three major
components:
Stability
Weight management
Safety during docking
4
ยฉ Copyright QinetiQ Pty Ltd 2013
1. Introduction
Stability Management Program :
identifies requirements and their application
provides structure and management tools
assures vessels will have sufficient stability and
structural strength to operate in the defined service
category, environment and during maintenance periods
demonstrate compliance with the DEF (AUS) 5000
regulations or other designated rules as a minimum
assurance for safe operation
5
ยฉ Copyright QinetiQ Pty Ltd 2013
2. Stability program governance and management
Program management plan โ€“ governing document
Management structure โ€“ dynamic, allows flexibility in priorities
and can be amended as the needs change
Work instructions โ€“ describe the process
Custom tailored supporting tools:
compliance matrix;
activity schedule;
activity templates and check lists;
calculation spread sheets; and
vessel specific continuous compliance monitoring tools
6
ยฉ Copyright QinetiQ Pty Ltd 2013
2. Stability program governance and management
7
Governing structure
ยฉ Copyright QinetiQ Pty Ltd 2013
2.1 Stability
Stability compliance - KG (VCG) curve
Limiting KG curve is developed for each RAN class of ships -
trialling the highest KG for various intact and damage criteria
while still complying with all stability requirements
8
Once approved by the NA,
the Limiting KG Curve
becomes the stability
standard
Example โ€“ refer to the
chart
ยฉ Copyright QinetiQ Pty Ltd 2013
2.1 Stability
Compliance margins
With aging, platformโ€™s KG (VCG) and displacement margins
will be reduced due to capability upgrade, change in
operational requirements or various reasons and in some
cases those margins can be depleted, which may require
limitations on operation to maintain compliance, for example:
To reduce VCG โ€“ using ballast, increasing min BFR;
To reduce displacement - limiting fuel, fresh water, other
effects;
Limiting operational environment
Those limitations if not resolved, may limit the vessel ability to
complete the desired mission.
9
ยฉ Copyright QinetiQ Pty Ltd 2013
2.1 Stability
NA controls the compliance margins by assigning a stability
status for each class, which also influences the period at which
the stability compliance is verified and T&S Handbook updated
10
Stat D e f i n i t i o n
1 An increase in displacement and rise in KG are acceptable without compensation provided each
change is within the limits, and changes are notified to the Support Authority
2 Neither an increase in displacement nor a rise in KG can be accepted without prior approval of the
Naval Authority. Weight and moment compensation are required for all changes.
3 An increase in displacement is acceptable within the limits specified below, but a rise in KG must
be avoided. Moment compensation only is required. Ships with this status are permitted alterations
up to the limits specified below provided net weight increases occur below the lightship KG given
in the most recent T&S Handbook or net weight reductions occur above the same KG. Changes
shall be notified to Support Authority
4 A rise in KG is acceptable within the limits specified below, but an increase in displacement cannot
be accepted without prior approval of the Naval Authority. Weight compensation is required for all
changes
ยฉ Copyright QinetiQ Pty Ltd 2013
2.1 Stability
Management of compliance margins
Management of the stability configuration and changes to the
physical state of the vessels are responsibility of each SPO:
Stability schedule
Weight control
Monitoring of stability compliance
Interim checks
Stability in harbour environment
11
ยฉ Copyright QinetiQ Pty Ltd 2013
2.1 Stability
12
ยฉ Copyright QinetiQ Pty Ltd 2013
2.2 Weight management
Necessity
All RAN ships have to maintain:
limiting displacement (maximum weight a ship can
displace without adversely affecting ship stability,
structure or design speed) and
vertical centre of gravity
to ensure adequate reserves of stability and hull girder strength
Weight management is implemented to ensure the ship
remains below those limits throughout its life
13
ยฉ Copyright QinetiQ Pty Ltd 2013
2.2 Weight management
Contributing factors to weight change
14
Configuration change: Operational:
Modifications -
๏ฏ Design enhancement
๏ฏ Upgrade
๏ฏ New capability
Obsolescence
Maintenance
(accumulation of
spare parts)
Personal effects
Recreational sport
Change in loading
conditions
ยฉ Copyright QinetiQ Pty Ltd 2013
2.2 Weight management
Managing weight and moments: effort is required from both
sides - SPO and operator
15
ยฉ Copyright QinetiQ Pty Ltd 2013
2.2 Weight management
Weight Register โ€“
Available for assessment of configuration change proposal and
is updated after implementation
Provides continuous monitoring between compliance validations
Ship check โ€“
Lightship โ€“ Naval & Ship Stores
Provisions and stores โ€“ food, spare parts & tools etc.
Crew and effects โ€“ incl. recreational sport items
Miscellaneous - rigging, specialised equipment, gym etc.
Change in loading conditions โ€“ trainees, containers etc.
The program offers a link between regulator and operator by
providing up to date information about any changes in stability
configuration
16
ยฉ Copyright QinetiQ Pty Ltd 2013
2.2 Weight management
17
ยฉ Copyright QinetiQ Pty Ltd 2013
2.2 Weight management
Weight Register
Developed for each vessel โ€“ example โ€“
3 vessels in a class, stability status 2,3 or 4, stability check
every 2 years โ€“ each vessel stability is checked once in 6
years
1-st tab โ€“ Instructions and Definitions,
2-nd tab โ€“ Limitations, compliance with the KG curve
3-rd โ€“ Weight Register, entry of weight changes
Lightship measurements - updated after stability check
Loading conditions updated when necessary
18
ยฉ Copyright QinetiQ Pty Ltd 2013
2.2 Weight management
19
ยฉ Copyright QinetiQ Pty Ltd 2013
2.2 Weight management
Weight Register
Limitations โ€“
continuous monitoring of
the compliance with the
KG (VCG) curve
20
ยฉ Copyright QinetiQ Pty Ltd 2013
2.2 Weight management
Weight Register
Recording all weight changes to lightship
21
ยฉ Copyright QinetiQ Pty Ltd 2013
2.2 Weight management
Example
KG (VCG): 3mm margin on VCG
How easy is to exceed this
margin? (2000t displacement vessel)
-1.2t from ER
+0.3t on bridge
22
ยฉ Copyright QinetiQ Pty Ltd 2013
2.2 Weight management
Displacement:
Margin - 3.130t (0.16% of the limiting ๏„)
How easy is to monitor this margin?
Tonnes per Centimetre immersion (TPC) ~6.00t
Margin โ€“ less than 5mm draft to limiting draft
For practical reason margin on displacement should not be
less than the TPC
23
ยฉ Copyright QinetiQ Pty Ltd 2013
2.2 Weight management
Additional application of weight management:
Supporting Life of Type Extension (LOTE) programs
Supporting management of the interface between
launching/lifting equipment capacity and lifting loading
condition of small vessels
24
ยฉ Copyright QinetiQ Pty Ltd 2013
2.3 Docking and slipping
25
Important aspects for safe and successful docking:
Safety of the vessel during slipping/docking
Adequacy of the facility and qualification
Protection of the vessel during lay period
Adequacy of procedures
Personnel qualifications
ยฉ Copyright QinetiQ Pty Ltd 2013
2.3 Docking and slipping
The program can assist with:
Dockyard qualification assessment
Docking calculations and plan - Library of selected
dockyards spread-sheets
Weight management โ€“ WR used for configuration change
implementation during maintenance periods, refer to
Risk management during the docking period โ€“ utilaising
WR & docking spread-sheets for compliance monitoring
Contingency plan
26
ยฉ Copyright QinetiQ Pty Ltd 2013
2.3 Docking and slipping
27
ยฉ Copyright QinetiQ Pty Ltd 2013
3. Conclusion
Stability Management Program:
Flexible, customer oriented
Manage stability compliance
Supports maintenance process
Supports configuration change management
Supports Life of Type Extension programs
Manage interface between small boats and launching/
lifting appliances
28
www.QinetiQ.com.au
ยฉ Copyright QinetiQ Pty Ltd 2013
29

More Related Content

What's hot

Integrated hydrodynamic and structural analysis webinar presentation tcm4 601490
Integrated hydrodynamic and structural analysis webinar presentation tcm4 601490Integrated hydrodynamic and structural analysis webinar presentation tcm4 601490
Integrated hydrodynamic and structural analysis webinar presentation tcm4 601490Dai Hung
ย 
Southern Transport Service SOP
Southern Transport Service SOPSouthern Transport Service SOP
Southern Transport Service SOPRichard Gibbens
ย 
FLNG Offshore and Nearshore
FLNG Offshore and NearshoreFLNG Offshore and Nearshore
FLNG Offshore and NearshoreAdvisian
ย 
IRJET- A Study on the Optimization of Highly Stabled Ships by using Roll Stab...
IRJET- A Study on the Optimization of Highly Stabled Ships by using Roll Stab...IRJET- A Study on the Optimization of Highly Stabled Ships by using Roll Stab...
IRJET- A Study on the Optimization of Highly Stabled Ships by using Roll Stab...IRJET Journal
ย 
Set 1 certificates and survey
Set 1 certificates and surveySet 1 certificates and survey
Set 1 certificates and surveyMaanas Gopinath
ย 
Laid up vessel reactivation guide- West of England
Laid up vessel reactivation guide- West of EnglandLaid up vessel reactivation guide- West of England
Laid up vessel reactivation guide- West of EnglandDeva RG
ย 
RINA - AOG 2017 - Acceptance of performance based inspection - AMSA - Rob Geh...
RINA - AOG 2017 - Acceptance of performance based inspection - AMSA - Rob Geh...RINA - AOG 2017 - Acceptance of performance based inspection - AMSA - Rob Geh...
RINA - AOG 2017 - Acceptance of performance based inspection - AMSA - Rob Geh...Nick Bentley
ย 
Certificate list dry
Certificate list   dryCertificate list   dry
Certificate list dryMaanas Gopinath
ย 
Donato Current Resume[1]
Donato Current Resume[1]Donato Current Resume[1]
Donato Current Resume[1]D.j. Donato
ย 
Work n rest hours & olb
Work n rest hours  & olbWork n rest hours  & olb
Work n rest hours & olbMaanas Gopinath
ย 
Aircraft inspections
Aircraft inspectionsAircraft inspections
Aircraft inspectionsAgustin Limachi
ย 
Tarince Muhammad Updated Resume
Tarince Muhammad Updated ResumeTarince Muhammad Updated Resume
Tarince Muhammad Updated ResumeTarince Muhammad
ย 
Airworthiness Review Certificate
Airworthiness Review CertificateAirworthiness Review Certificate
Airworthiness Review CertificateS P Singh
ย 
Engineering of Subsea Production Systems
Engineering of Subsea Production SystemsEngineering of Subsea Production Systems
Engineering of Subsea Production SystemspetroEDGE
ย 
Wsc guidelines for implementing the solas container weight verification requi...
Wsc guidelines for implementing the solas container weight verification requi...Wsc guidelines for implementing the solas container weight verification requi...
Wsc guidelines for implementing the solas container weight verification requi...Uganda Coffee Federation
ย 

What's hot (20)

Integrated hydrodynamic and structural analysis webinar presentation tcm4 601490
Integrated hydrodynamic and structural analysis webinar presentation tcm4 601490Integrated hydrodynamic and structural analysis webinar presentation tcm4 601490
Integrated hydrodynamic and structural analysis webinar presentation tcm4 601490
ย 
Southern Transport Service SOP
Southern Transport Service SOPSouthern Transport Service SOP
Southern Transport Service SOP
ย 
FLNG Offshore and Nearshore
FLNG Offshore and NearshoreFLNG Offshore and Nearshore
FLNG Offshore and Nearshore
ย 
IRJET- A Study on the Optimization of Highly Stabled Ships by using Roll Stab...
IRJET- A Study on the Optimization of Highly Stabled Ships by using Roll Stab...IRJET- A Study on the Optimization of Highly Stabled Ships by using Roll Stab...
IRJET- A Study on the Optimization of Highly Stabled Ships by using Roll Stab...
ย 
Set 1 certificates and survey
Set 1 certificates and surveySet 1 certificates and survey
Set 1 certificates and survey
ย 
Surveys of Merchant Ships
Surveys of Merchant Ships Surveys of Merchant Ships
Surveys of Merchant Ships
ย 
Laid up vessel reactivation guide- West of England
Laid up vessel reactivation guide- West of EnglandLaid up vessel reactivation guide- West of England
Laid up vessel reactivation guide- West of England
ย 
JWDJr_resume
JWDJr_resumeJWDJr_resume
JWDJr_resume
ย 
RINA - AOG 2017 - Acceptance of performance based inspection - AMSA - Rob Geh...
RINA - AOG 2017 - Acceptance of performance based inspection - AMSA - Rob Geh...RINA - AOG 2017 - Acceptance of performance based inspection - AMSA - Rob Geh...
RINA - AOG 2017 - Acceptance of performance based inspection - AMSA - Rob Geh...
ย 
Certificate list dry
Certificate list   dryCertificate list   dry
Certificate list dry
ย 
Passage planning
Passage planningPassage planning
Passage planning
ย 
Donato Current Resume[1]
Donato Current Resume[1]Donato Current Resume[1]
Donato Current Resume[1]
ย 
Work n rest hours & olb
Work n rest hours  & olbWork n rest hours  & olb
Work n rest hours & olb
ย 
Aircraft inspections
Aircraft inspectionsAircraft inspections
Aircraft inspections
ย 
Tarince Muhammad Updated Resume
Tarince Muhammad Updated ResumeTarince Muhammad Updated Resume
Tarince Muhammad Updated Resume
ย 
Rule 05 look-out
Rule 05     look-outRule 05     look-out
Rule 05 look-out
ย 
Airworthiness Review Certificate
Airworthiness Review CertificateAirworthiness Review Certificate
Airworthiness Review Certificate
ย 
Engineering of Subsea Production Systems
Engineering of Subsea Production SystemsEngineering of Subsea Production Systems
Engineering of Subsea Production Systems
ย 
Anchor Handling Stability
Anchor Handling StabilityAnchor Handling Stability
Anchor Handling Stability
ย 
Wsc guidelines for implementing the solas container weight verification requi...
Wsc guidelines for implementing the solas container weight verification requi...Wsc guidelines for implementing the solas container weight verification requi...
Wsc guidelines for implementing the solas container weight verification requi...
ย 

Similar to Platform Stability Management Program

Towingrecomends.pdf
Towingrecomends.pdfTowingrecomends.pdf
Towingrecomends.pdfBoorajDuraisamy1
ย 
Towingrecomends
TowingrecomendsTowingrecomends
TowingrecomendsDuong Truong
ย 
Sneak preview - SMM presentation
Sneak preview - SMM presentationSneak preview - SMM presentation
Sneak preview - SMM presentationdkane27
ย 
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...Charlie Reith
ย 
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...Forum for the Future
ย 
Proboat - Practical Impact Exposure Testing
Proboat - Practical Impact Exposure TestingProboat - Practical Impact Exposure Testing
Proboat - Practical Impact Exposure TestingJussi Mannerberg
ย 
Widespread Fatigue Damage
Widespread Fatigue DamageWidespread Fatigue Damage
Widespread Fatigue Damagesyedrooh
ย 
DNV GL Asset Life Extension (ALE) Projects Showcase
DNV GL Asset Life Extension (ALE) Projects ShowcaseDNV GL Asset Life Extension (ALE) Projects Showcase
DNV GL Asset Life Extension (ALE) Projects ShowcaseIan Ng
ย 
Lifting Rules Example - DNV.pdf
Lifting Rules Example - DNV.pdfLifting Rules Example - DNV.pdf
Lifting Rules Example - DNV.pdflimkanghai
ย 
Ship conversion Overhaul and Repair.pptx
Ship conversion Overhaul and Repair.pptxShip conversion Overhaul and Repair.pptx
Ship conversion Overhaul and Repair.pptxMirTarequeAli1
ย 
Dissemination workshop-v2.1
Dissemination workshop-v2.1Dissemination workshop-v2.1
Dissemination workshop-v2.1Gรฉrald Morales
ย 
Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...
Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...
Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...minte3
ย 
Global Gravity - TubeLock brochure
Global Gravity - TubeLock brochureGlobal Gravity - TubeLock brochure
Global Gravity - TubeLock brochureGlobal Gravity
ย 
Amplus VPU Presentation
Amplus VPU PresentationAmplus VPU Presentation
Amplus VPU PresentationThomas Jeannin
ย 
Pr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning executionPr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning executionSergio Augusto Esteves
ย 
DNVGL_ReDAPT_Validation_Study
DNVGL_ReDAPT_Validation_StudyDNVGL_ReDAPT_Validation_Study
DNVGL_ReDAPT_Validation_StudySteven Parkinson
ย 
Energy Efficiency Definitions: EEDI, SEEMP and EEOI
Energy Efficiency Definitions: EEDI, SEEMP and EEOIEnergy Efficiency Definitions: EEDI, SEEMP and EEOI
Energy Efficiency Definitions: EEDI, SEEMP and EEOIMohammud Hanif Dewan M.Phil.
ย 
Mepc.213(63)
Mepc.213(63)Mepc.213(63)
Mepc.213(63)pawaner20
ย 

Similar to Platform Stability Management Program (20)

Towingrecomends.pdf
Towingrecomends.pdfTowingrecomends.pdf
Towingrecomends.pdf
ย 
Towingrecomends
TowingrecomendsTowingrecomends
Towingrecomends
ย 
Sneak preview - SMM presentation
Sneak preview - SMM presentationSneak preview - SMM presentation
Sneak preview - SMM presentation
ย 
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
Reliable Subsea Oil& Gas Transportation Paper - Presentation Slides 6 Novembe...
ย 
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
SSI workstream - Accelerating the uptake of technology: Demonstrating the bus...
ย 
Proboat - Practical Impact Exposure Testing
Proboat - Practical Impact Exposure TestingProboat - Practical Impact Exposure Testing
Proboat - Practical Impact Exposure Testing
ย 
Widespread Fatigue Damage
Widespread Fatigue DamageWidespread Fatigue Damage
Widespread Fatigue Damage
ย 
DNV GL Asset Life Extension (ALE) Projects Showcase
DNV GL Asset Life Extension (ALE) Projects ShowcaseDNV GL Asset Life Extension (ALE) Projects Showcase
DNV GL Asset Life Extension (ALE) Projects Showcase
ย 
Lifting Rules Example - DNV.pdf
Lifting Rules Example - DNV.pdfLifting Rules Example - DNV.pdf
Lifting Rules Example - DNV.pdf
ย 
Ship conversion Overhaul and Repair.pptx
Ship conversion Overhaul and Repair.pptxShip conversion Overhaul and Repair.pptx
Ship conversion Overhaul and Repair.pptx
ย 
Dissemination workshop-v2.1
Dissemination workshop-v2.1Dissemination workshop-v2.1
Dissemination workshop-v2.1
ย 
Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...
Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...
Dynamic positioning-accreditation-and-certification-scheme-standard-10th-janu...
ย 
Global Gravity - TubeLock brochure
Global Gravity - TubeLock brochureGlobal Gravity - TubeLock brochure
Global Gravity - TubeLock brochure
ย 
Amplus VPU Presentation
Amplus VPU PresentationAmplus VPU Presentation
Amplus VPU Presentation
ย 
Pr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning executionPr 1709 - lifting and hoisting procedure lift planning execution
Pr 1709 - lifting and hoisting procedure lift planning execution
ย 
DNVGL_ReDAPT_Validation_Study
DNVGL_ReDAPT_Validation_StudyDNVGL_ReDAPT_Validation_Study
DNVGL_ReDAPT_Validation_Study
ย 
Energy Efficiency Definitions: EEDI, SEEMP and EEOI
Energy Efficiency Definitions: EEDI, SEEMP and EEOIEnergy Efficiency Definitions: EEDI, SEEMP and EEOI
Energy Efficiency Definitions: EEDI, SEEMP and EEOI
ย 
satellite design requirements
satellite design requirementssatellite design requirements
satellite design requirements
ย 
Safety Meeting - Lifting 6Oct14
Safety Meeting - Lifting 6Oct14Safety Meeting - Lifting 6Oct14
Safety Meeting - Lifting 6Oct14
ย 
Mepc.213(63)
Mepc.213(63)Mepc.213(63)
Mepc.213(63)
ย 

More from QinetiQ Australia

Me, Helicopters and Women in Aviation
Me, Helicopters and Women in AviationMe, Helicopters and Women in Aviation
Me, Helicopters and Women in AviationQinetiQ Australia
ย 
2016 Aerospace Industry Night
2016 Aerospace Industry Night 2016 Aerospace Industry Night
2016 Aerospace Industry Night QinetiQ Australia
ย 
Defence In Business - Soldiers Five
Defence In Business - Soldiers FiveDefence In Business - Soldiers Five
Defence In Business - Soldiers FiveQinetiQ Australia
ย 
Defence Industry... Plus Some Thoughts
Defence Industry... Plus Some ThoughtsDefence Industry... Plus Some Thoughts
Defence Industry... Plus Some ThoughtsQinetiQ Australia
ย 
OptaSense and VicRoads Monash Freeway Project 2015
OptaSense and VicRoads Monash Freeway Project 2015OptaSense and VicRoads Monash Freeway Project 2015
OptaSense and VicRoads Monash Freeway Project 2015QinetiQ Australia
ย 
Global Marine Technology Trends 2030
Global Marine Technology Trends 2030Global Marine Technology Trends 2030
Global Marine Technology Trends 2030QinetiQ Australia
ย 
Submarine Escape at an Angle
Submarine Escape at an AngleSubmarine Escape at an Angle
Submarine Escape at an AngleQinetiQ Australia
ย 
Major Incident Capability Assurance
Major Incident Capability AssuranceMajor Incident Capability Assurance
Major Incident Capability AssuranceQinetiQ Australia
ย 

More from QinetiQ Australia (8)

Me, Helicopters and Women in Aviation
Me, Helicopters and Women in AviationMe, Helicopters and Women in Aviation
Me, Helicopters and Women in Aviation
ย 
2016 Aerospace Industry Night
2016 Aerospace Industry Night 2016 Aerospace Industry Night
2016 Aerospace Industry Night
ย 
Defence In Business - Soldiers Five
Defence In Business - Soldiers FiveDefence In Business - Soldiers Five
Defence In Business - Soldiers Five
ย 
Defence Industry... Plus Some Thoughts
Defence Industry... Plus Some ThoughtsDefence Industry... Plus Some Thoughts
Defence Industry... Plus Some Thoughts
ย 
OptaSense and VicRoads Monash Freeway Project 2015
OptaSense and VicRoads Monash Freeway Project 2015OptaSense and VicRoads Monash Freeway Project 2015
OptaSense and VicRoads Monash Freeway Project 2015
ย 
Global Marine Technology Trends 2030
Global Marine Technology Trends 2030Global Marine Technology Trends 2030
Global Marine Technology Trends 2030
ย 
Submarine Escape at an Angle
Submarine Escape at an AngleSubmarine Escape at an Angle
Submarine Escape at an Angle
ย 
Major Incident Capability Assurance
Major Incident Capability AssuranceMajor Incident Capability Assurance
Major Incident Capability Assurance
ย 

Recently uploaded

Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...9953056974 Low Rate Call Girls In Saket, Delhi NCR
ย 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
ย 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
ย 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
ย 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
ย 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
ย 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
ย 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
ย 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
ย 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
ย 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsArindam Chakraborty, Ph.D., P.E. (CA, TX)
ย 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
ย 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
ย 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
ย 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
ย 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
ย 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
ย 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
ย 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
ย 

Recently uploaded (20)

Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
ย 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
ย 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
ย 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
ย 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
ย 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
ย 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
ย 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
ย 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
ย 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
ย 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
ย 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
ย 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
ย 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
ย 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
ย 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
ย 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
ย 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
ย 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
ย 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
ย 

Platform Stability Management Program

  • 1. ยฉ Copyright QinetiQ Pty Ltd 2013 1 PLATFORM STABILITY MANAGEMENT PROGRAM Violeta Gabrovska June 2015
  • 2. ยฉ Copyright QinetiQ Pty Ltd 2013 2 Contents 1. Introduction 2. Stability program governance and management ๏ฏ Stability compliance ๏ฏ Weight management and various interfaces ๏ฏ Docking and slipping 3. Conclusion
  • 3. ยฉ Copyright QinetiQ Pty Ltd 2013 1. Introduction Stability - critical safety characteristic failure of which may result in: loss of life, early cancellation of a mission and total loss of a vessel Maintain low risk of failure - compliance with designated set of rules Influencing factors - lightship growth and weight distribution 3
  • 4. ยฉ Copyright QinetiQ Pty Ltd 2013 1. Introduction Stability Program is designed to manage the compliance and validation process and the interaction between three major components: Stability Weight management Safety during docking 4
  • 5. ยฉ Copyright QinetiQ Pty Ltd 2013 1. Introduction Stability Management Program : identifies requirements and their application provides structure and management tools assures vessels will have sufficient stability and structural strength to operate in the defined service category, environment and during maintenance periods demonstrate compliance with the DEF (AUS) 5000 regulations or other designated rules as a minimum assurance for safe operation 5
  • 6. ยฉ Copyright QinetiQ Pty Ltd 2013 2. Stability program governance and management Program management plan โ€“ governing document Management structure โ€“ dynamic, allows flexibility in priorities and can be amended as the needs change Work instructions โ€“ describe the process Custom tailored supporting tools: compliance matrix; activity schedule; activity templates and check lists; calculation spread sheets; and vessel specific continuous compliance monitoring tools 6
  • 7. ยฉ Copyright QinetiQ Pty Ltd 2013 2. Stability program governance and management 7 Governing structure
  • 8. ยฉ Copyright QinetiQ Pty Ltd 2013 2.1 Stability Stability compliance - KG (VCG) curve Limiting KG curve is developed for each RAN class of ships - trialling the highest KG for various intact and damage criteria while still complying with all stability requirements 8 Once approved by the NA, the Limiting KG Curve becomes the stability standard Example โ€“ refer to the chart
  • 9. ยฉ Copyright QinetiQ Pty Ltd 2013 2.1 Stability Compliance margins With aging, platformโ€™s KG (VCG) and displacement margins will be reduced due to capability upgrade, change in operational requirements or various reasons and in some cases those margins can be depleted, which may require limitations on operation to maintain compliance, for example: To reduce VCG โ€“ using ballast, increasing min BFR; To reduce displacement - limiting fuel, fresh water, other effects; Limiting operational environment Those limitations if not resolved, may limit the vessel ability to complete the desired mission. 9
  • 10. ยฉ Copyright QinetiQ Pty Ltd 2013 2.1 Stability NA controls the compliance margins by assigning a stability status for each class, which also influences the period at which the stability compliance is verified and T&S Handbook updated 10 Stat D e f i n i t i o n 1 An increase in displacement and rise in KG are acceptable without compensation provided each change is within the limits, and changes are notified to the Support Authority 2 Neither an increase in displacement nor a rise in KG can be accepted without prior approval of the Naval Authority. Weight and moment compensation are required for all changes. 3 An increase in displacement is acceptable within the limits specified below, but a rise in KG must be avoided. Moment compensation only is required. Ships with this status are permitted alterations up to the limits specified below provided net weight increases occur below the lightship KG given in the most recent T&S Handbook or net weight reductions occur above the same KG. Changes shall be notified to Support Authority 4 A rise in KG is acceptable within the limits specified below, but an increase in displacement cannot be accepted without prior approval of the Naval Authority. Weight compensation is required for all changes
  • 11. ยฉ Copyright QinetiQ Pty Ltd 2013 2.1 Stability Management of compliance margins Management of the stability configuration and changes to the physical state of the vessels are responsibility of each SPO: Stability schedule Weight control Monitoring of stability compliance Interim checks Stability in harbour environment 11
  • 12. ยฉ Copyright QinetiQ Pty Ltd 2013 2.1 Stability 12
  • 13. ยฉ Copyright QinetiQ Pty Ltd 2013 2.2 Weight management Necessity All RAN ships have to maintain: limiting displacement (maximum weight a ship can displace without adversely affecting ship stability, structure or design speed) and vertical centre of gravity to ensure adequate reserves of stability and hull girder strength Weight management is implemented to ensure the ship remains below those limits throughout its life 13
  • 14. ยฉ Copyright QinetiQ Pty Ltd 2013 2.2 Weight management Contributing factors to weight change 14 Configuration change: Operational: Modifications - ๏ฏ Design enhancement ๏ฏ Upgrade ๏ฏ New capability Obsolescence Maintenance (accumulation of spare parts) Personal effects Recreational sport Change in loading conditions
  • 15. ยฉ Copyright QinetiQ Pty Ltd 2013 2.2 Weight management Managing weight and moments: effort is required from both sides - SPO and operator 15
  • 16. ยฉ Copyright QinetiQ Pty Ltd 2013 2.2 Weight management Weight Register โ€“ Available for assessment of configuration change proposal and is updated after implementation Provides continuous monitoring between compliance validations Ship check โ€“ Lightship โ€“ Naval & Ship Stores Provisions and stores โ€“ food, spare parts & tools etc. Crew and effects โ€“ incl. recreational sport items Miscellaneous - rigging, specialised equipment, gym etc. Change in loading conditions โ€“ trainees, containers etc. The program offers a link between regulator and operator by providing up to date information about any changes in stability configuration 16
  • 17. ยฉ Copyright QinetiQ Pty Ltd 2013 2.2 Weight management 17
  • 18. ยฉ Copyright QinetiQ Pty Ltd 2013 2.2 Weight management Weight Register Developed for each vessel โ€“ example โ€“ 3 vessels in a class, stability status 2,3 or 4, stability check every 2 years โ€“ each vessel stability is checked once in 6 years 1-st tab โ€“ Instructions and Definitions, 2-nd tab โ€“ Limitations, compliance with the KG curve 3-rd โ€“ Weight Register, entry of weight changes Lightship measurements - updated after stability check Loading conditions updated when necessary 18
  • 19. ยฉ Copyright QinetiQ Pty Ltd 2013 2.2 Weight management 19
  • 20. ยฉ Copyright QinetiQ Pty Ltd 2013 2.2 Weight management Weight Register Limitations โ€“ continuous monitoring of the compliance with the KG (VCG) curve 20
  • 21. ยฉ Copyright QinetiQ Pty Ltd 2013 2.2 Weight management Weight Register Recording all weight changes to lightship 21
  • 22. ยฉ Copyright QinetiQ Pty Ltd 2013 2.2 Weight management Example KG (VCG): 3mm margin on VCG How easy is to exceed this margin? (2000t displacement vessel) -1.2t from ER +0.3t on bridge 22
  • 23. ยฉ Copyright QinetiQ Pty Ltd 2013 2.2 Weight management Displacement: Margin - 3.130t (0.16% of the limiting ๏„) How easy is to monitor this margin? Tonnes per Centimetre immersion (TPC) ~6.00t Margin โ€“ less than 5mm draft to limiting draft For practical reason margin on displacement should not be less than the TPC 23
  • 24. ยฉ Copyright QinetiQ Pty Ltd 2013 2.2 Weight management Additional application of weight management: Supporting Life of Type Extension (LOTE) programs Supporting management of the interface between launching/lifting equipment capacity and lifting loading condition of small vessels 24
  • 25. ยฉ Copyright QinetiQ Pty Ltd 2013 2.3 Docking and slipping 25 Important aspects for safe and successful docking: Safety of the vessel during slipping/docking Adequacy of the facility and qualification Protection of the vessel during lay period Adequacy of procedures Personnel qualifications
  • 26. ยฉ Copyright QinetiQ Pty Ltd 2013 2.3 Docking and slipping The program can assist with: Dockyard qualification assessment Docking calculations and plan - Library of selected dockyards spread-sheets Weight management โ€“ WR used for configuration change implementation during maintenance periods, refer to Risk management during the docking period โ€“ utilaising WR & docking spread-sheets for compliance monitoring Contingency plan 26
  • 27. ยฉ Copyright QinetiQ Pty Ltd 2013 2.3 Docking and slipping 27
  • 28. ยฉ Copyright QinetiQ Pty Ltd 2013 3. Conclusion Stability Management Program: Flexible, customer oriented Manage stability compliance Supports maintenance process Supports configuration change management Supports Life of Type Extension programs Manage interface between small boats and launching/ lifting appliances 28