Analysis of Risk Management for Construction Projects
ER. Hassan Mohamed Abdulnabi 1
Prof. (Dr.) V. C. Agarwal 2
PhD student, Department of Civil Engineering Faculty of Engineering and Technology
SHIATS University, Allahabad, India 1
Professor Dr, Head of Department of Civil Engineering Faculty of Engineering and
Technology SHIATS University, Allahabad, India 2
INTRODUCTION
The sector of construction is one of the key
economic sectors and is the main force the
Libyan economy, in the last has
witnessed in noticeable expansion
activities. This has resulted in the recovery of the
construction profession and subsidiary industries,
therefore, the construction sector has taken the
foremost position among the other, mainly in the
attraction of investments and creation of new
jobs. The management of risks is very important
in the planning and management of the projects,
construction industry is subject to more risks and
uncertainty than several other industries. The take
off process of project from initial investment
assessment to completion and into use is a
difficult process. The construction industry in
Libya Strip is suffering from the
misunderstanding of risk management including
risk identification, analysis and assessment.
I. PROJECT RISK CONCEPT
Risks can be defined in any of the projects an
event is uncertain which results from the
occurrence or negative impact positively on the
goal of the project (PMBOK, 2002, P127). Every
risk of reason leads to a result, for example, the
reason may be the qualified labour force limited
for the project and that the result clear will appear
in the additional cost or imbalance in scheduling
work and the length of the implementation period
or the quality of implementation. There are some
known risks that have been identified, analysed
and can now be planned. On the contrary the
unknown Risks cannot be managed, although the
managers of the project can deal with it by
applying General Contingency Plans based on
past experience gained during the implementation
of previous projects. A risk is anything that
threatens the success of the project but accepted
RESEARCH ARTICLE OPEN ACCESS
Abstract:
The length of the implementation period in the construction of projects may lead to a change in
circumstances which expose them to many risks because of the length of the implementation period and multiple
stages, beginning with the start-up phase and even phase of the project, and this leads to increased circumstances of
uncertainty and increasing the probability of the occurrence of risks, and this is reflected negatively on the
construction contracting and construction economy.In this research questionnaire was developed to identify the
risks encountered in construction. Projects have been distributed to some local and foreign construction companies
in Libya, having been identified the risks that may face the projects. Through questionnaires and interviews with
engineers and project managers of companies, and making risk analysis qualitatively, there was a need to prepare a
checklist of the risks facing projects in Libya, and know the benefit of the contractor and the owner based on the
results. This paper examines the most important risks faced by construction projects in Libya, which is difficult and
how they are able to implement these projects and housing companies, the research explains a formulated model to
evaluate companies before being contracted to know the financial and technical capabilities.
Keywords — Risk management, construction of projects, evaluating the risks, risk analysis
International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016
ISSN: 2395-1303 http://www.ijetjournal.org Page 154
when undergoing budget in return which will
result.
II. THE RISK MANAGEMENT
PROCESS
Overall risk management is the process of
identifying and evaluating the risks and
developing strategies to manage it. These
strategies include the transfer of risks to other
parties and to avoid and minimize the negative
effects and to accept some or all of its
consequences. Traditional risk management
focuses on the risks arising from physical or legal
reasons (example: natural disasters, fires,
accidents, death and lawsuits) on the other hand,
financial risk management focus on those risks
that can be managed using financial barter.
Regardless of the type of risk management, all
the big companies and small businesses have a
dedicated team of risk management.
The risk management process should include the
definition of risk identification, risk analysis, risk
mitigation, monitoring and control of risk as
show in Figure (1)
Figure (1). The Risk Management Process
1. RISK IDENTIFICATION
The aim of this phase is to identify all the
potential risks that may face the project and
threaten its goals, and this requires methods to
identify risks such as questionnaire, interviews
with project managers or officials in companies,
checklists, brainstorming, or Delphi Technique.
Risk identification can depend on goals, any risk
impedes the achievement of project goals
considered risk.
2. QUALITATIVE RISK ANALYSIS
Qualitative analysis of risks is most common in
the risk analysis process. On part, uses qualitative
risk analysis to prioritize risks that affect the
goals of the project, and must be done on
qualitative analysis of the risks at the beginning
of the project and reviewed during the
implementation to keep pace with changes in the
level of risk.
The ranking of risks:
Each project has different risks associated with
its processes, risk implementation, all of which
affect the activities of the project. A technique
used in risk arrangement is Probability Impact
Risk Rating Matrix( ward،1999) as shown in
Table (1), which expresses the value of all the
risk in numbers 1,5,10 to signal risk arrangement
(low, Medium, High). Risk = Possibility x
impact.
Table (1), Probability Impact Risk Rating Matrix(ward،1999).
3. RISK MITIGATION
The goal of this strategy is to mitigate the
consequences of the risk to an acceptable level.
Taking some of the actions that mitigate the risks
for the best to take action to address the
consequences of that risk. Examples of actions
taken before the start of implementation of the
projects during implementation, or the
engineering or seismic tests or the selection of
suitable suppliers, These procedures may include
International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016
ISSN: 2395-1303 http://www.ijetjournal.org Page 155
changing the conditions to mitigate the potential
for danger, such as adding resources or time to
the activities of the project.
4. RISK MONITORING AND FOLLOW UP
It is monitor and follow up of the effectiveness of
the actions taken or any other deviations can
occur in the project.
III. CHECK LIST
Questionnaire was developed to identify the risks
faced by projects in Libya. Financial and
economic impact of projects on the distribution
of the questionnaire section for 32 the company
implemented housing projects in Libya to get to
know some of the risks faced by projects in Libya
with an estimate of the probability of occurrence
and the resulting impact.
Table 2 shows the checklist risks that could have
faced the owner or contractor in the construction
projects. The list of these risks that have been
identified from the companies in the study
sample had a negative impact on the project in
terms of (time, cost and quality).
N The risk
1 Lack of companies ability to implement
2 Delays in the payment of payment certificates
3 Political factors.
4 Lack of security and stability.
5 Design errors.
6 Errors in the calculation of quantities.
7 Obtaining permits and approvals.
8 The lack of experience of supervising engineers.
9 The inexperience of the offices of the National
Advisory.
10 Centralised decision-making.
11 Technical specifications change during the
execution of the project.
12 Lack of experience and financial and technical
capacity of the contractor
13 Lack of labor experience.
14 Lack of materials.
Table ( )2 the checklist risks
Most of the participating companies in the study
questionnaire reported that the risks from 1 to 7
have very high probability of occurrence .All of
these risks are described in Figure 2 and impact
are as follows: -
-1 Lack of companies ability to implement
-2 Delays in the payment of payment certificates
-3 Political factors.
-4 Lack of security and stability.
-5 Design errors.
-6 Errors in the calculation of quantities.
7- Obtaining permits and approvals.
Figure (2). The risks very high probability of occurrence.
Lack of companies ability to implement:-
Lack of companies able to implement projects
due to three reasons must be considered when
contracting and these reasons are: -
1- Organizational ability
2- Financial ability
3- Financial and technical ability and experience
in the implementation of projects.
Delays in the payment of payment certificates:
Delays in the payment of payment certificates for
the executed works, and can reduce these risks
through the following actions: -
1- Must submit payment certificates timely.
2- Must prepare preparation payment certificates
before submission it to owner.
Political factors:
The worry of foreign financiers and domestic
companies from the collapse of the political
regime in the country where the result in the
collapse of the security and economic level and
the lack of the rule of law. In this case, one of the
main parties in the contract is unable to fulfil its
contractual obligations.
Lack of security and stability:
The risks security have a negative impact on the
projects. The companies face a big problem in
terms of the inability to bring in workers from
International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016
ISSN: 2395-1303 http://www.ijetjournal.org Page 156
abroad to work to the project. Also many of the
projects turned to a military barracks of the
armed militias, and some subjected to breaking in
from the citizens.
Design errors and Errors in the calculation of
quantities:-
There are technical risks amendments to the
designs and construction methods of execution
during the implementation, in addition to the
wrong estimate for quantities necessary to
implement the projects in contracts.
Obtaining permits and approvals:-
The difficulty in obtaining permits and approvals
before and during the implementation of projects
is one of the most important risks that affect the
project duration as these procedures may take
months before the completion of its cycle of
administrative between the owner and the
contractor.
Rehabilitation of construction companies
before contracting with them
One of the most important risks facing
construction projects in Libya is the ability of
companies implementing projects on time and at
cost and specifications agreed upon. So it was a
study for the rehabilitation of these companies
before contracting with them and suggests forms
for the rehabilitation of these companies so as to
know the financial, technical and managerial its
potential before being contracted. And
classification of companies should be in
accordance with the several criteria such as the
share capital and years of experience as well as
volume of technical manpower and the cadres of
administrative and equipment and machinery.
1. Suggested form for evaluating construction
companies.
After seeing the economic laws in Libya, which
identifies and assesses companies activities and
most recently the Council of Ministers
Resolution No. (171) of 2006, Issuing the
executive regulations of Law No. (21) Of 2001
concerning the practice of economic activities in
Libya. It has been proposed as a form for
evaluating construction companies, through a
questionnaire which was distributed to 32 of the
companies that implement projects in Libya. The
aim is to identify the main criteria that should be
used in the assessment of the construction
companies.
2. The criteria that must be provided in the
proposed form
A- Financial situation: This includes aspects
related to the financial status of the company and
the documents to be submitted and knowledge of
monetary flowability and financial ability.
B- Material resources file: A file that includes
all the machinery and equipment available to the
company to implement the project.
C- Years of experience of the company: The
company's experience in the implementation of
projects as well as the professional reputation of
the company.
D- Technical File: A file that includes all the
technical possibilities available to the company.
E- Human Resource file: A file that includes all
administrative and technical cadres available to
the company to implement the project.
F- Planning and Follow-up: Is the company's
ability to management, planning and control
work on the project.
G- Safety and Insurance: Includes the industrial
safety of the project and the safety of labourers
and insurance on the project.
3. The questionnaire results in the proposed
form
It created a form for evaluating companies and
write all the basic criteria format questions with
the use of economic laws in Libya and that define
and assess the activities of construction
companies. With included questionnaire on 7
basic criteria, each of which contains several
secondary standards were the result of many
questions to illustrate different aspects and to
evaluate construction companies before
contracting with them, were distributed to the
project managers and contractors and consultants,
and the table 3 major shows the results of the
questionnaire ratios basic standards.
the basic criteria Secondary criteria
Financial situation
28.1%
Having current accounts in banks
Cash flow of the company
Material resources file
Owning machines and equipment
required for the work
International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016
ISSN: 2395-1303 http://www.ijetjournal.org Page 157
15.6% Owning construction materials
required for the work
Years of experience of
the company 15.6%
The lack of previously unsuccessful
projects
The absence of a lawsuits against the
company
A number of similar projects for the
current project
Quality certificates in the
implementation of previous projects.
Technical File 12.5% Providing cadre trained in project
implementation
Human Resource file
12.5%
Having integrated engineering
specialities for the project wanted
implement
Having the entire organisational
structure of the company
Planning and Follow-up
9.4%
Having research and development
department
Having of control system and follow-
up work carried out in the project
Safety and Insurance
6.3%
Having certificates of insurance
project
The existence of previous incidents of
death for workers
Provide a cadre of industrial security
company
Provide training programs for the
prevention of accidents
Provide protection from natural
disasters system
Table (3) the basic criteria and Secondary files in the proposed form
Results from the survey shows that the financial
situation of the companies is the most important
factor in the proposed model for the evaluation of
construction companies. Where the percentage
rate of 28.1% of the companies participating in
the survey, and then followed by materials
resources file and years of experience of the
company by percentage rate of 15.6% , and then
comes to the files in the order as follows:-
Technical File 12.5%
Human Resource file 12.5%
Planning and Follow-up 9.4%
Safety and Insurance 6.3%
Figure 4 shows the proportions of these files in
suggested form.
Figur (4). Files used in suggested form.
Depending on the obtained results of the
questionnaire, the companies were ranked
according to their potential and capabilities, and
so the candidate is notified for the tender, while
the companies that did not get the required grades
are excluded. That the reality of companies in
Libya indicates the presence of a large deviation
in the success of these projects and the reason for
the deviation is due to many factors, including
those related to Implementing the company or the
royal institution. The evaluation of companies is
a key factor in the success of the project by
making sure their potential financial and
technical capabilities and administrative and its
previous experience in the projects implemented.
VI. CONCLUSION
Construction projects are always associated with
risk and uncertainty because of the length of the
implementation period that change the conditions
making it contain multiple risks. The most
important risk facing the projects in Libya are the
presence of companies not able to implement
projects on time and in the required quality and
the approved budget and specifications agreed
upon. Valuation of companies is a key factor in
the success of the project by making sure the
financial, technical and administrative
capabilities and expertise in the implementation
of previous projects. Therefore this field study
was to determine suggested form for the
International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016
ISSN: 2395-1303 http://www.ijetjournal.org Page 158
rehabilitation of the construction companies
before contracting with them, and the purpose of
this model is to ensure the ability of companies
financial, technical and administrative
capabilities and expertise in the implementation
of projects The definition of criteria that must be
available in these companies in the suggested
form to be invited to the auction. These
companies in the project and these standards are
(financial situation, material resources file, years
of experience of the company, technical file,
human resource file, planning and Follow-up,
safety and Insurance). using this suggested form
to evaluate companies before contracting with
them is recommended. The preparation checklist
contains the risk of the projects to be a reference
point for any owner or implementer of projects to
be taken into account when hiring or
implementation of projects. These risks have the
greatest impact on the time, cost and quality.
REFERENCES
1. Carter, B., Hancock, T., Morin, J.M., and Robins, N.,
Introducing RI methodology, the Stationery Office,
London. (1996).
2. Dave H and David H , Universal Risk Project, Risk
Management Institute , UK , (2002).
3. Fouzi, hossen, Analyse and manage the risks faced by
construction projects, Faculty of Engineering,
University of Omar Mukhtar, Libya, (2012).
4. Gillett, J. E., Hazard Study and Risk Assessment in
the Pharmaceutical Industry, Interpharm Press,Inc,
USA, (1997).
5. Hossen Fouzi A. Planning Risk Assessment in the
Manufacture of Complex Capital Goods, PhD Thesis,
Newcastle University, UK, (2006).
6. Hulettvice ,D T , Project Risk Management, Risk
Management Institute, U.K, (2001).
7. Raftery, J.,Risk Analysis in Project Management,
Suffolk: St Ed Bury Press Limited, Bury St Edmunds,
(1994).
8. Kevin, J. Implementing A Design / Build.
Prequalification System, Journal of Management
in Engineering, vol11 (3), 31-37, USA, (1995).
9. McNamara, C., Authenticity Consulting, LLC
Copyright 2008, (2008).
10. Rodger, C, and Jason P , Uncertainty and Risk
Analysis, price water house ,U.K, (1999).
11. Samuel G S, Estimation of the Financial Risk Public
Enterprises Construction in Egypt, Cairo-University,
Egypt, (1996).
12. Sonmez, M. H., Graham, G., Applying Evidential
Reasoning to Prequalifying Construction
Contractors, Journal of Management in Engineering,
18(3), 116-118, USA, (2002).
13. WARD, S. C., Assessing and Managing Important
Risks, International Journal of Project Management,
17(6), 331-336, (1999).

More Related Content

What's hot

IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET Journal
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSvivatechijri
 
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITYRISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITYA Makwana
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)inventionjournals
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...IRJET Journal
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...Dr. Amarjeet Singh
 
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...IJCMESJOURNAL
 
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...IRJET Journal
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingAlexander Decker
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential SectorIRJET Journal
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentationvivatechijri
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET Journal
 
Construction project risk management
Construction project risk managementConstruction project risk management
Construction project risk managementIQPC
 
Critical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction ProjectsCritical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction Projectstheijes
 
risk management: a better approach
risk management: a better approachrisk management: a better approach
risk management: a better approachMadhumanti Samaddar
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...IRJET Journal
 

What's hot (20)

J1303045360
J1303045360J1303045360
J1303045360
 
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
 
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTSEFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
EFFECTIVE RISK MANAGEMENT IN CONSTRUCTION PROJECTS
 
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITYRISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
RISK MANAGEMENT IN HIGH RISE CONSTRUCTION PROJECTS IN SURAT CITY
 
International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)International Journal of Engineering and Science Invention (IJESI)
International Journal of Engineering and Science Invention (IJESI)
 
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
Assessment of Risk in Construction Projects by Modified Fuzzy Analytic Hierar...
 
The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...The Identification of Risks and its Criticality in the Nigeria Construction I...
The Identification of Risks and its Criticality in the Nigeria Construction I...
 
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
Evaluation of Risk Factors Affecting Cost Performance of Construction Project...
 
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...IRJET-  	  A Review Paper on Risk Management using Primavera for Residential ...
IRJET- A Review Paper on Risk Management using Primavera for Residential ...
 
A fuzzy ahp model in risk ranking
A fuzzy ahp model in risk rankingA fuzzy ahp model in risk ranking
A fuzzy ahp model in risk ranking
 
IRJET- Risk Management using Primavera Software for Residential Sector
IRJET-  	  Risk Management using Primavera Software for Residential SectorIRJET-  	  Risk Management using Primavera Software for Residential Sector
IRJET- Risk Management using Primavera Software for Residential Sector
 
Claims Management And Assessment Through Documentation
Claims Management And Assessment Through DocumentationClaims Management And Assessment Through Documentation
Claims Management And Assessment Through Documentation
 
IRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature ReviewIRJET- Risk Management in Construction: A Literature Review
IRJET- Risk Management in Construction: A Literature Review
 
C1303032126
C1303032126C1303032126
C1303032126
 
Construction project risk management
Construction project risk managementConstruction project risk management
Construction project risk management
 
Critical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction ProjectsCritical Factors Influencing to Management Risk in Construction Projects
Critical Factors Influencing to Management Risk in Construction Projects
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Project risk management
Project risk managementProject risk management
Project risk management
 
risk management: a better approach
risk management: a better approachrisk management: a better approach
risk management: a better approach
 
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...IRJET-  	  Study and Analysis of Risk Management Strategies in Construction P...
IRJET- Study and Analysis of Risk Management Strategies in Construction P...
 

Similar to Analysis of Risk Management for Construction Projects in Libya

IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET Journal
 
Construction project management & risk mitigation
Construction project management & risk mitigationConstruction project management & risk mitigation
Construction project management & risk mitigationrajlaxmipardeshi
 
IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET Journal
 
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIOIAEME Publication
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET Journal
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsIRJET Journal
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk ManagementSAJJAD KHUDHUR ABBAS
 
Software Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanSoftware Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanEECJOURNAL
 
Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projectsPALLA NARASIMHUDU
 
Risk management plan
Risk management planRisk management plan
Risk management planKashif Mastan
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSIRJET Journal
 
Risk Management in Retrofitting Projects
Risk Management in Retrofitting ProjectsRisk Management in Retrofitting Projects
Risk Management in Retrofitting ProjectsIRJET Journal
 
Ijirt100070 paper
Ijirt100070 paperIjirt100070 paper
Ijirt100070 paperMolay Reja
 
Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Sibo Kanyambari Aimable
 
Risk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesRisk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesIRJET Journal
 
Risk Management in Construction Project
Risk Management in Construction ProjectRisk Management in Construction Project
Risk Management in Construction ProjectDr. Amarjeet Singh
 
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...Sibo Kanyambari Aimable
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsIRJET Journal
 

Similar to Analysis of Risk Management for Construction Projects in Libya (20)

IRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction ProjectsIRJET-Qualitative Risk Analysis for Construction Projects
IRJET-Qualitative Risk Analysis for Construction Projects
 
Construction project management & risk mitigation
Construction project management & risk mitigationConstruction project management & risk mitigation
Construction project management & risk mitigation
 
IRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera SoftwareIRJET- Risk Management in Residential Project by Primavera Software
IRJET- Risk Management in Residential Project by Primavera Software
 
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIORISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
RISK MANAGEMENT IN CONSTRUCTION PROJECTS AS PER INDIAN SCENARIO
 
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
IRJET- Review on Developing a Model of Risk Allocation and Risk Handling for ...
 
Risk Management In High Rise Construction Projects
Risk Management In High Rise Construction ProjectsRisk Management In High Rise Construction Projects
Risk Management In High Rise Construction Projects
 
112 risk management
112 risk management112 risk management
112 risk management
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Software Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanSoftware Project Risk Management Practice in Oman
Software Project Risk Management Practice in Oman
 
Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projects
 
Risk management plan
Risk management planRisk management plan
Risk management plan
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTSRISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
RISK ASSESSMENT OF CONSTRUCTION BUILDING PROJECTS
 
Risk Management in Retrofitting Projects
Risk Management in Retrofitting ProjectsRisk Management in Retrofitting Projects
Risk Management in Retrofitting Projects
 
Ijirt100070 paper
Ijirt100070 paperIjirt100070 paper
Ijirt100070 paper
 
Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...Effect or Risk Management Methods on project performance in Rwandan Construct...
Effect or Risk Management Methods on project performance in Rwandan Construct...
 
Risk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction IndustriesRisk Management Methodologies in Construction Industries
Risk Management Methodologies in Construction Industries
 
Risk Management in Construction Project
Risk Management in Construction ProjectRisk Management in Construction Project
Risk Management in Construction Project
 
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
EFFECTS OF RISK MANAGEMENT METHODS ON PROJECT PERFORMANCE IN RWANDAN CONSTRUC...
 
Study and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction ProjectsStudy and Need of Risk Management for Construction Projects
Study and Need of Risk Management for Construction Projects
 

More from IJET - International Journal of Engineering and Techniques

More from IJET - International Journal of Engineering and Techniques (20)

healthcare supervising system to monitor heart rate to diagonize and alert he...
healthcare supervising system to monitor heart rate to diagonize and alert he...healthcare supervising system to monitor heart rate to diagonize and alert he...
healthcare supervising system to monitor heart rate to diagonize and alert he...
 
verifiable and multi-keyword searchable attribute-based encryption scheme for...
verifiable and multi-keyword searchable attribute-based encryption scheme for...verifiable and multi-keyword searchable attribute-based encryption scheme for...
verifiable and multi-keyword searchable attribute-based encryption scheme for...
 
Ijet v5 i6p18
Ijet v5 i6p18Ijet v5 i6p18
Ijet v5 i6p18
 
Ijet v5 i6p17
Ijet v5 i6p17Ijet v5 i6p17
Ijet v5 i6p17
 
Ijet v5 i6p16
Ijet v5 i6p16Ijet v5 i6p16
Ijet v5 i6p16
 
Ijet v5 i6p15
Ijet v5 i6p15Ijet v5 i6p15
Ijet v5 i6p15
 
Ijet v5 i6p14
Ijet v5 i6p14Ijet v5 i6p14
Ijet v5 i6p14
 
Ijet v5 i6p13
Ijet v5 i6p13Ijet v5 i6p13
Ijet v5 i6p13
 
Ijet v5 i6p12
Ijet v5 i6p12Ijet v5 i6p12
Ijet v5 i6p12
 
Ijet v5 i6p11
Ijet v5 i6p11Ijet v5 i6p11
Ijet v5 i6p11
 
Ijet v5 i6p10
Ijet v5 i6p10Ijet v5 i6p10
Ijet v5 i6p10
 
Ijet v5 i6p2
Ijet v5 i6p2Ijet v5 i6p2
Ijet v5 i6p2
 
IJET-V3I2P24
IJET-V3I2P24IJET-V3I2P24
IJET-V3I2P24
 
IJET-V3I2P23
IJET-V3I2P23IJET-V3I2P23
IJET-V3I2P23
 
IJET-V3I2P22
IJET-V3I2P22IJET-V3I2P22
IJET-V3I2P22
 
IJET-V3I2P21
IJET-V3I2P21IJET-V3I2P21
IJET-V3I2P21
 
IJET-V3I2P20
IJET-V3I2P20IJET-V3I2P20
IJET-V3I2P20
 
IJET-V3I2P19
IJET-V3I2P19IJET-V3I2P19
IJET-V3I2P19
 
IJET-V3I2P18
IJET-V3I2P18IJET-V3I2P18
IJET-V3I2P18
 
IJET-V3I2P17
IJET-V3I2P17IJET-V3I2P17
IJET-V3I2P17
 

Recently uploaded

Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 

Analysis of Risk Management for Construction Projects in Libya

  • 1. International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016 ISSN: 2395-1303 http://www.ijetjournal.org Page 153 Analysis of Risk Management for Construction Projects ER. Hassan Mohamed Abdulnabi 1 Prof. (Dr.) V. C. Agarwal 2 PhD student, Department of Civil Engineering Faculty of Engineering and Technology SHIATS University, Allahabad, India 1 Professor Dr, Head of Department of Civil Engineering Faculty of Engineering and Technology SHIATS University, Allahabad, India 2 INTRODUCTION The sector of construction is one of the key economic sectors and is the main force the Libyan economy, in the last has witnessed in noticeable expansion activities. This has resulted in the recovery of the construction profession and subsidiary industries, therefore, the construction sector has taken the foremost position among the other, mainly in the attraction of investments and creation of new jobs. The management of risks is very important in the planning and management of the projects, construction industry is subject to more risks and uncertainty than several other industries. The take off process of project from initial investment assessment to completion and into use is a difficult process. The construction industry in Libya Strip is suffering from the misunderstanding of risk management including risk identification, analysis and assessment. I. PROJECT RISK CONCEPT Risks can be defined in any of the projects an event is uncertain which results from the occurrence or negative impact positively on the goal of the project (PMBOK, 2002, P127). Every risk of reason leads to a result, for example, the reason may be the qualified labour force limited for the project and that the result clear will appear in the additional cost or imbalance in scheduling work and the length of the implementation period or the quality of implementation. There are some known risks that have been identified, analysed and can now be planned. On the contrary the unknown Risks cannot be managed, although the managers of the project can deal with it by applying General Contingency Plans based on past experience gained during the implementation of previous projects. A risk is anything that threatens the success of the project but accepted RESEARCH ARTICLE OPEN ACCESS Abstract: The length of the implementation period in the construction of projects may lead to a change in circumstances which expose them to many risks because of the length of the implementation period and multiple stages, beginning with the start-up phase and even phase of the project, and this leads to increased circumstances of uncertainty and increasing the probability of the occurrence of risks, and this is reflected negatively on the construction contracting and construction economy.In this research questionnaire was developed to identify the risks encountered in construction. Projects have been distributed to some local and foreign construction companies in Libya, having been identified the risks that may face the projects. Through questionnaires and interviews with engineers and project managers of companies, and making risk analysis qualitatively, there was a need to prepare a checklist of the risks facing projects in Libya, and know the benefit of the contractor and the owner based on the results. This paper examines the most important risks faced by construction projects in Libya, which is difficult and how they are able to implement these projects and housing companies, the research explains a formulated model to evaluate companies before being contracted to know the financial and technical capabilities. Keywords — Risk management, construction of projects, evaluating the risks, risk analysis
  • 2. International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016 ISSN: 2395-1303 http://www.ijetjournal.org Page 154 when undergoing budget in return which will result. II. THE RISK MANAGEMENT PROCESS Overall risk management is the process of identifying and evaluating the risks and developing strategies to manage it. These strategies include the transfer of risks to other parties and to avoid and minimize the negative effects and to accept some or all of its consequences. Traditional risk management focuses on the risks arising from physical or legal reasons (example: natural disasters, fires, accidents, death and lawsuits) on the other hand, financial risk management focus on those risks that can be managed using financial barter. Regardless of the type of risk management, all the big companies and small businesses have a dedicated team of risk management. The risk management process should include the definition of risk identification, risk analysis, risk mitigation, monitoring and control of risk as show in Figure (1) Figure (1). The Risk Management Process 1. RISK IDENTIFICATION The aim of this phase is to identify all the potential risks that may face the project and threaten its goals, and this requires methods to identify risks such as questionnaire, interviews with project managers or officials in companies, checklists, brainstorming, or Delphi Technique. Risk identification can depend on goals, any risk impedes the achievement of project goals considered risk. 2. QUALITATIVE RISK ANALYSIS Qualitative analysis of risks is most common in the risk analysis process. On part, uses qualitative risk analysis to prioritize risks that affect the goals of the project, and must be done on qualitative analysis of the risks at the beginning of the project and reviewed during the implementation to keep pace with changes in the level of risk. The ranking of risks: Each project has different risks associated with its processes, risk implementation, all of which affect the activities of the project. A technique used in risk arrangement is Probability Impact Risk Rating Matrix( ward،1999) as shown in Table (1), which expresses the value of all the risk in numbers 1,5,10 to signal risk arrangement (low, Medium, High). Risk = Possibility x impact. Table (1), Probability Impact Risk Rating Matrix(ward،1999). 3. RISK MITIGATION The goal of this strategy is to mitigate the consequences of the risk to an acceptable level. Taking some of the actions that mitigate the risks for the best to take action to address the consequences of that risk. Examples of actions taken before the start of implementation of the projects during implementation, or the engineering or seismic tests or the selection of suitable suppliers, These procedures may include
  • 3. International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016 ISSN: 2395-1303 http://www.ijetjournal.org Page 155 changing the conditions to mitigate the potential for danger, such as adding resources or time to the activities of the project. 4. RISK MONITORING AND FOLLOW UP It is monitor and follow up of the effectiveness of the actions taken or any other deviations can occur in the project. III. CHECK LIST Questionnaire was developed to identify the risks faced by projects in Libya. Financial and economic impact of projects on the distribution of the questionnaire section for 32 the company implemented housing projects in Libya to get to know some of the risks faced by projects in Libya with an estimate of the probability of occurrence and the resulting impact. Table 2 shows the checklist risks that could have faced the owner or contractor in the construction projects. The list of these risks that have been identified from the companies in the study sample had a negative impact on the project in terms of (time, cost and quality). N The risk 1 Lack of companies ability to implement 2 Delays in the payment of payment certificates 3 Political factors. 4 Lack of security and stability. 5 Design errors. 6 Errors in the calculation of quantities. 7 Obtaining permits and approvals. 8 The lack of experience of supervising engineers. 9 The inexperience of the offices of the National Advisory. 10 Centralised decision-making. 11 Technical specifications change during the execution of the project. 12 Lack of experience and financial and technical capacity of the contractor 13 Lack of labor experience. 14 Lack of materials. Table ( )2 the checklist risks Most of the participating companies in the study questionnaire reported that the risks from 1 to 7 have very high probability of occurrence .All of these risks are described in Figure 2 and impact are as follows: - -1 Lack of companies ability to implement -2 Delays in the payment of payment certificates -3 Political factors. -4 Lack of security and stability. -5 Design errors. -6 Errors in the calculation of quantities. 7- Obtaining permits and approvals. Figure (2). The risks very high probability of occurrence. Lack of companies ability to implement:- Lack of companies able to implement projects due to three reasons must be considered when contracting and these reasons are: - 1- Organizational ability 2- Financial ability 3- Financial and technical ability and experience in the implementation of projects. Delays in the payment of payment certificates: Delays in the payment of payment certificates for the executed works, and can reduce these risks through the following actions: - 1- Must submit payment certificates timely. 2- Must prepare preparation payment certificates before submission it to owner. Political factors: The worry of foreign financiers and domestic companies from the collapse of the political regime in the country where the result in the collapse of the security and economic level and the lack of the rule of law. In this case, one of the main parties in the contract is unable to fulfil its contractual obligations. Lack of security and stability: The risks security have a negative impact on the projects. The companies face a big problem in terms of the inability to bring in workers from
  • 4. International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016 ISSN: 2395-1303 http://www.ijetjournal.org Page 156 abroad to work to the project. Also many of the projects turned to a military barracks of the armed militias, and some subjected to breaking in from the citizens. Design errors and Errors in the calculation of quantities:- There are technical risks amendments to the designs and construction methods of execution during the implementation, in addition to the wrong estimate for quantities necessary to implement the projects in contracts. Obtaining permits and approvals:- The difficulty in obtaining permits and approvals before and during the implementation of projects is one of the most important risks that affect the project duration as these procedures may take months before the completion of its cycle of administrative between the owner and the contractor. Rehabilitation of construction companies before contracting with them One of the most important risks facing construction projects in Libya is the ability of companies implementing projects on time and at cost and specifications agreed upon. So it was a study for the rehabilitation of these companies before contracting with them and suggests forms for the rehabilitation of these companies so as to know the financial, technical and managerial its potential before being contracted. And classification of companies should be in accordance with the several criteria such as the share capital and years of experience as well as volume of technical manpower and the cadres of administrative and equipment and machinery. 1. Suggested form for evaluating construction companies. After seeing the economic laws in Libya, which identifies and assesses companies activities and most recently the Council of Ministers Resolution No. (171) of 2006, Issuing the executive regulations of Law No. (21) Of 2001 concerning the practice of economic activities in Libya. It has been proposed as a form for evaluating construction companies, through a questionnaire which was distributed to 32 of the companies that implement projects in Libya. The aim is to identify the main criteria that should be used in the assessment of the construction companies. 2. The criteria that must be provided in the proposed form A- Financial situation: This includes aspects related to the financial status of the company and the documents to be submitted and knowledge of monetary flowability and financial ability. B- Material resources file: A file that includes all the machinery and equipment available to the company to implement the project. C- Years of experience of the company: The company's experience in the implementation of projects as well as the professional reputation of the company. D- Technical File: A file that includes all the technical possibilities available to the company. E- Human Resource file: A file that includes all administrative and technical cadres available to the company to implement the project. F- Planning and Follow-up: Is the company's ability to management, planning and control work on the project. G- Safety and Insurance: Includes the industrial safety of the project and the safety of labourers and insurance on the project. 3. The questionnaire results in the proposed form It created a form for evaluating companies and write all the basic criteria format questions with the use of economic laws in Libya and that define and assess the activities of construction companies. With included questionnaire on 7 basic criteria, each of which contains several secondary standards were the result of many questions to illustrate different aspects and to evaluate construction companies before contracting with them, were distributed to the project managers and contractors and consultants, and the table 3 major shows the results of the questionnaire ratios basic standards. the basic criteria Secondary criteria Financial situation 28.1% Having current accounts in banks Cash flow of the company Material resources file Owning machines and equipment required for the work
  • 5. International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016 ISSN: 2395-1303 http://www.ijetjournal.org Page 157 15.6% Owning construction materials required for the work Years of experience of the company 15.6% The lack of previously unsuccessful projects The absence of a lawsuits against the company A number of similar projects for the current project Quality certificates in the implementation of previous projects. Technical File 12.5% Providing cadre trained in project implementation Human Resource file 12.5% Having integrated engineering specialities for the project wanted implement Having the entire organisational structure of the company Planning and Follow-up 9.4% Having research and development department Having of control system and follow- up work carried out in the project Safety and Insurance 6.3% Having certificates of insurance project The existence of previous incidents of death for workers Provide a cadre of industrial security company Provide training programs for the prevention of accidents Provide protection from natural disasters system Table (3) the basic criteria and Secondary files in the proposed form Results from the survey shows that the financial situation of the companies is the most important factor in the proposed model for the evaluation of construction companies. Where the percentage rate of 28.1% of the companies participating in the survey, and then followed by materials resources file and years of experience of the company by percentage rate of 15.6% , and then comes to the files in the order as follows:- Technical File 12.5% Human Resource file 12.5% Planning and Follow-up 9.4% Safety and Insurance 6.3% Figure 4 shows the proportions of these files in suggested form. Figur (4). Files used in suggested form. Depending on the obtained results of the questionnaire, the companies were ranked according to their potential and capabilities, and so the candidate is notified for the tender, while the companies that did not get the required grades are excluded. That the reality of companies in Libya indicates the presence of a large deviation in the success of these projects and the reason for the deviation is due to many factors, including those related to Implementing the company or the royal institution. The evaluation of companies is a key factor in the success of the project by making sure their potential financial and technical capabilities and administrative and its previous experience in the projects implemented. VI. CONCLUSION Construction projects are always associated with risk and uncertainty because of the length of the implementation period that change the conditions making it contain multiple risks. The most important risk facing the projects in Libya are the presence of companies not able to implement projects on time and in the required quality and the approved budget and specifications agreed upon. Valuation of companies is a key factor in the success of the project by making sure the financial, technical and administrative capabilities and expertise in the implementation of previous projects. Therefore this field study was to determine suggested form for the
  • 6. International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016 ISSN: 2395-1303 http://www.ijetjournal.org Page 158 rehabilitation of the construction companies before contracting with them, and the purpose of this model is to ensure the ability of companies financial, technical and administrative capabilities and expertise in the implementation of projects The definition of criteria that must be available in these companies in the suggested form to be invited to the auction. These companies in the project and these standards are (financial situation, material resources file, years of experience of the company, technical file, human resource file, planning and Follow-up, safety and Insurance). using this suggested form to evaluate companies before contracting with them is recommended. The preparation checklist contains the risk of the projects to be a reference point for any owner or implementer of projects to be taken into account when hiring or implementation of projects. These risks have the greatest impact on the time, cost and quality. REFERENCES 1. Carter, B., Hancock, T., Morin, J.M., and Robins, N., Introducing RI methodology, the Stationery Office, London. (1996). 2. Dave H and David H , Universal Risk Project, Risk Management Institute , UK , (2002). 3. Fouzi, hossen, Analyse and manage the risks faced by construction projects, Faculty of Engineering, University of Omar Mukhtar, Libya, (2012). 4. Gillett, J. E., Hazard Study and Risk Assessment in the Pharmaceutical Industry, Interpharm Press,Inc, USA, (1997). 5. Hossen Fouzi A. Planning Risk Assessment in the Manufacture of Complex Capital Goods, PhD Thesis, Newcastle University, UK, (2006). 6. Hulettvice ,D T , Project Risk Management, Risk Management Institute, U.K, (2001). 7. Raftery, J.,Risk Analysis in Project Management, Suffolk: St Ed Bury Press Limited, Bury St Edmunds, (1994). 8. Kevin, J. Implementing A Design / Build. Prequalification System, Journal of Management in Engineering, vol11 (3), 31-37, USA, (1995). 9. McNamara, C., Authenticity Consulting, LLC Copyright 2008, (2008). 10. Rodger, C, and Jason P , Uncertainty and Risk Analysis, price water house ,U.K, (1999). 11. Samuel G S, Estimation of the Financial Risk Public Enterprises Construction in Egypt, Cairo-University, Egypt, (1996). 12. Sonmez, M. H., Graham, G., Applying Evidential Reasoning to Prequalifying Construction Contractors, Journal of Management in Engineering, 18(3), 116-118, USA, (2002). 13. WARD, S. C., Assessing and Managing Important Risks, International Journal of Project Management, 17(6), 331-336, (1999).