Konstruksi Pracetak untuk Rumah Sederhana
0
Konstruksi Pracetak untuk Rumah Sederhana
1
DAFTAR ISI
DAFTAR ISI..................................................................................................................................0
DAFTAR GAMBAR....................................................................................................................................2
DAFTAR TABEL ........................................................................................................................................5
KATA PENGANTAR ..................................................................................................................................5
A. Pendahuluan.......................................................................................................................5
1. Latar Belakang.................................................................................................................6
2. Maksud dan Tujuan.........................................................................................................7
B. Gambaran Teknologi ..........................................................................................................7
C. Bahan..................................................................................................................................7
1. Beton...............................................................................................................................8
2. Komponen bangunan RISHA.........................................................................................10
D. Peralatan...........................................................................................................................13
E. Pelaksanaan......................................................................................................................14
1. Ketentuan ukuran Panel Struktural ..............................................................................14
2. Pelaksanaan pembuatan panel-panel RISHA................................................................16
3. Penentuan Denah Bangunan Rumah Tipe 36...............................................................22
4. Perakitan Rumah RISHA................................................................................................23
F. Perkiraan Biaya.................................................................................................................35
Konstruksi Pracetak untuk Rumah Sederhana
2
DAFTAR GAMBAR
Gambar 3. 1 Pencampuran Beton.............................................................................................8
Gambar 3. 2 Pengujian Sederhana Dengan Meletakkan Campuran Beton di tangan ..............8
Gambar 3. 3 Pengujian Sederhana Dengan Menggunakan Cetakan dan Mengukur Selisih
Ketinggian dengan Cetakan .......................................................................................................9
Gambar 3. 4 Diameter Kerikil Yang Baik Untuk Campuran Beton.............................................9
Gambar 3. 5 Contoh Semen Tipe 1..........................................................................................10
Gambar 3. 6 Pondasi pelat.......................................................................................................10
Gambar 3. 7 Panel penyambung .............................................................................................10
Gambar 3. 8 panel kolom bertulang.......................................................................................11
Gambar 3. 9 Panel kolom bertulang........................................................................................11
Gambar 3. 10 panel beton bertulang......................................................................................12
Gambar 3. 11 penel dinding.....................................................................................................12
Gambar 3. 12 panel pintu ........................................................................................................12
Gambar 3. 13 panel jendela.....................................................................................................13
Gambar 3. 14 panel ampig.......................................................................................................13
Gambar 3. 15 panel lantai........................................................................................................13
Gambar 5. 1 Penulangan Komponen RISHA P1 .......................................................................14
Gambar 5. 2 Penulangan Komponen RISHA P2 .......................................................................15
Gambar 5. 3 Penulangan Komponen RISHA Panel Penyambung............................................16
Gambar 5. 4 Bentuk Cetakan Kayu Panel P2 ...........................................................................16
Gambar 5. 5 Pelaksanaan Pembuatan Cetakan Panel P1........................................................17
Gambar 5. 6 Bentuk Bekisting Kayu Panel P2..........................................................................17
Gambar 5. 7 Bentuk Cetakan Kayu Panel Sambungan ............................................................18
Gambar 5. 8 Bentuk Cetakan Kayu Panel Sambungan ............................................................18
Gambar 5. 9 ukuran cetakan baja Panel P1.............................................................................19
Gambar 5. 10 Ukuran cetakan baja panel P2 ..........................................................................20
Gambar 5. 11 Bentuk cetakan baja panel sambungan............................................................20
Gambar 5. 12 Perakitan tulangan panel RISHA .......................................................................21
Gambar 5. 13............................................................................................................................23
Konstruksi Pracetak untuk Rumah Sederhana
3
Gambar 5. 14 Penempatan patok-patok rumah RISHA...........................................................24
Gambar 5. 15 Galian pondasi..................................................................................................25
Gambar 5. 16 Penempatan Pondasi ........................................................................................26
Gambar 5. 17 Pemasangan panel join kolom terhadap pondasi.............................................27
Gambar 5. 18 Pemasagan balok sloof......................................................................................28
Gambar 5. 19 Pemasangan kolom...........................................................................................29
Gambar 5. 20............................................................................................................................30
Gambar 5. 21............................................................................................................................31
Gambar 5. 22............................................................................................................................32
Gambar 5. 23............................................................................................................................32
Gambar 5. 24 Setelah Pekerjaan Pengurugan dan Pemasangan Lantai..................................33
Gambar 5. 25............................................................................................................................34
Konstruksi Pracetak untuk Rumah Sederhana
4
DAFTAR TABEL
Tabel 6. 1..................................................................................................................................35
Tabel 6. 2..................................................................................................................................37
Tabel 6. 3..................................................................................................................................40
Konstruksi Pracetak untuk Rumah Sederhana
5
KATA PENGANTAR
Guna menunjang program pemerintah dalam penyediaan infrastruktur
perdesaan, Puslitbang Perumahan dan Permukiman, Badan Penelitian dan
Pengembangan, Kementerian Pekerjaan Umum dan Perumahan Rakyat menerbitkan
buku panduan sederhana berjudul “Konstruksi Pracetak untuk Rumah Sederhana”
dengan tujuan untuk membantu para pelaksana pembangunan rumah sederhana
sistem pracetak bagi penduduk perdesaan dalam merencanakan, melaksanakan
pekerjaan konstruksi serta memperkirakan biaya secara sederhana.
Dalam buku Panduan ini dibahas pengenalan beton sistem pracetak,
komponen bangunan Rumah Instan Sederhana Sehat (RISHA), peralatan yang
digunakan untuk membuat rumah sederhana sistem pracetak, kemudian penjelasan
mengenai ketentuan dalam konstruksi rumah pracetak, mulai ukuran dan
pembuatan panel-panel, dan petunjuk perakitan rumah sederhana sistem pracetak
(RISHA).
Materi dalam Buku Panduan ini telah diuji penerapannya di Desa Sindang
Pakuon, Kecamatan Cimanggung, Kabupaten Sumedang, Propinsi Jawa Barat. Namun
demikian kami tetap mengharapkan masukan dari Kementerian Desa, Pembangunan
Daerah Tertinggal, dan Transmigrasi dan pihak lainnya untuk menyempurnakan buku
panduan ini.
Jakarta, Oktober 2016
Menteri Pekerjaan Umum dan Perumahan
Rakyat
Dr. Ir. M Basuki Hadimoeljono, MSc
Konstruksi Pracetak untuk Rumah Sederhana
6
A. Pendahuluan
1. Latar Belakang
Rumah Instan Sederhana Sehat disingkat Risha merupakan teknologi
pracetak yang ditujukan bagi pembangunan perumahan Rumah Sederhana Sehat /
RSH, Rumah Swadaya, Rumah Pengungsi serta Rumah Darurat, dengan acuan
persyaratan teknis mengacu pada Kepmen Kimpraswi No. 403/KPTS/M/2002 tentang
Pedoman Teknis Rumah Sederhana Sehat. Dalam Upaya percepatan pembangunan
serta menurunkan biaya produksi Rumah Sederhana Sehat, Risha merupakan
penemuan untuk menjawab kedua hal tersebut, yaitu melalui pabrikasi komponen-
komponennya dan dirakit dilapangan dengan sistem bongkar pasang atau Konck
down System maupun permanen. Sistem knockdown dapat dibangun dengan dinding
partisi yang terbuat dari panel-panel yang dipasang dengan baut sehingga dapat
dibongkar pasang. Sedangkan, untuk bangunan RISHA permanen, dindingnya dapat
dibuat dengan pasangan bata merah, bata ringan, conblock, dan lain-lain. Waktu
yang diperlukan untuk merakit satu unit hunian dengan tipe 28,8 m2 adalah 1 hari
saja, sehingga Risha ini dapat dipasarkan dengan jargon “Pagi Pesan Sore Huni“.
Risha adalah Teknologi Konstruksi Bangunan Rumah Tinggal dengan sistem
Pabrikasi pada komponen Struktur, Pengisi maupun Utilitasnya. Komponen struktur
menggunakan bahan Beton Bertulang dengan sistem Joint Kering. Komponen rangka
struktur atasnya terdiri dari dua komponen, yaitu Komponen Panel Struktur dan
Simpul, dari komponen-komponen tersebut sudah dapat membangun rangka
bangunan. Panel dinding pengisinya menggunakan tiga jenis Rancangan, yaitu Panel
Masif, Panel Kusen Pintu lengkap dengan daun pintunya dan Panel Kusen Jendela
lengkap dengan daun jendelanya. Sedangkan, untuk kamar mandi menggunakan
Kamar Mandi Sistem Kapsul yang terbuat dari bahan fiber glass dengan konstruksi
monolit. Sistem ini diperkenalkan sebagai suatu sistem konstruksi langsung jadi atau
Instan yang dapat dibongkar pasang yang dan dikenal sebagai Sistem Rihsa.
Konstruksi Pracetak untuk Rumah Sederhana
7
2. Maksud dan Tujuan
Maksud dari adanya modul ini adalah peserta diharapkan dapat mengerti dan
mampu mengerjakan pembangunan rumah sederhana dengan menggunakan
teknologi RISHA. Sedangkan, tujuan dari modul ini adalah untuk memberikan
panduan kepada masyarakat agar dapat mewujudkan bangunan rumah tinggal
tunggal dengan teknologi RISHA yang aman terhadap dampak kerusakan yang
diakibatkan oleh bencana gempa bumi.
a. Sumber-sumber Referensi
1. Pedoman Teknis Teknologi RISHA
2. Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No.
5/PRT/M/2016.
B. Gambaran Teknologi
Risha adalah kependekan dari Rumah Instan Sederhana Sehat, yaitu rumah
tinggal dengan menerapkan teknologi konstruksi sistem pracetak kecil, dengan sistem
sambungan kering. Tinjauan teknis dan kompetensi teknologi RISHA adalah sebagai
berikut:
a. Percepatan
b. Kesederhanaan
c. Fleksibilitas
d. Ramah lingkungan dan mengakomodasi material lokal
e. Kekuatan dan durabilitas
f. Berkualitas
C. Bahan
Rumah Instan Sederhana sehat terdiri dari komponen-komponen yang dibuat di
pabrik. Pada saat perakitannya, seluruh komponen dan peralatan bantu untuk perakitan
harus sudah tersedia di tempat dimana bangunan ini akan dibangun. Seluruh komponen
yang terbuat dari beton bertulang harus sudah mencapai umur 28 hari dengan
kekuatan tekan minimum 250 kg/cm2. Seluruh komponen yang mengunakan bahan
Konstruksi Pracetak untuk Rumah Sederhana
8
kayu harus kering dan telah diserut hingga permukaan kayu tersebut rata dan halus
dengan ukuran yang akurat sesuai dengan yang diperlukan atau sesuai dengan gambar
rencana.
1. Beton
Beberapa hal yang harus diperhatikan dalam membuat campuran beton adalah:
1. Campuran beton terdiri dari 1 semen : 2 pasir : 3 kerikil : 0,5 air.
Perlu diperhatikan penambahan air dilakukan sedikit demi sedikit dan
disesuaikan agar beton dalam keadaan pulen (tidak terlalu encer dan tidak
terlalu kental).
1 semen : 2 pasir : 3 kerikil air secukupnya dituang sedikit demi sedikit
Gambar 3.1 Pencampuran Beton
Gambar 3.2 Pengujian Sederhana Dengan Meletakkan Campuran Beton di tangan
Konstruksi Pracetak untuk Rumah Sederhana
9
Gambar 3.3 Pengujian Sederhana Dengan Menggunakan Cetakan dan Mengukur Selisih
Ketinggian dengan Cetakan
2. Ukuran kerikil yang baik maksimum 20 mm dengan gradasi yang baik.
Gambar 3.4 Diameter Kerikil Yang Baik Untuk Campuran Beton
Konstruksi Pracetak untuk Rumah Sederhana
10
3. Semen yang digunakan adalah semen tipe 1 yang berkualitas sesuai dengan
Standar Nasional Indonesia (SNI).
Gambar 3.5 Contoh Semen Tipe 1
2. Komponen bangunan RISHA
Rumah instan sederhana sehat tipe -1 (RIT-1) terdiri beberapa komponen yang
dibuat secara pabrikasi. Satu unit RIT – 1 terdiri dari komponen-komponen:
4. Pondasi pelat, berukuran 65 x 65 cm, dengan tinggi 12 cm, 6 unit.
Gambar 3.6 Pondasi pelat
5. Panel penyambung, bentuk “L” 30.30.30.10 cm, 16 panel.
Gambar 3.7 Panel penyambung
SNI 2049-2015
Konstruksi Pracetak untuk Rumah Sederhana
11
6. Panel kolom beton bertulang, berukuran 30 x 120 x 10 cm, 20 panel,
Gambar 3.8 panel kolom bertulang
7. Panel kolom beton bertulang, berukuran 20 x 120 x 10 cm, 12 panel,
Gambar 3.9 Panel kolom bertulang
Konstruksi Pracetak untuk Rumah Sederhana
12
8. Panel balok beton bertulang, berukuran 30 x 120 x 10 cm, 28 panel,
Gambar 3.10 panel beton bertulang
9. Panel dinding, berukuran 120 x 240 cm, 5 panel.
Gambar 3.11 penel dinding
10. Panel Pintu (lengkap dengan daun pintu), 2 panel,
Gambar 3.12 panel pintu
Konstruksi Pracetak untuk Rumah Sederhana
13
11. Panel jendela (lengkap dengan daun jendela), 1 panel.
Gambar 3.13 panel jendela
12. Panel ampig, 4 panel.
Gambar 3.14 panel ampig
13. Panel lantai berukuran 20 x 20 cm, 18 m2,
Gambar 3.15 panel lantai
D. Peralatan
Peralatan yang digunakan untuk pekerjaan pembangunan rumah RISHA adalah
peralatan pertukangan dan pendukung-pendukungnya dengan masing-masing
fungsinya disesuaikan untuk mewujudkan pendetailan konstruksi rumah RISHA yang
akan dibahas pada bab selanjutnya.
Konstruksi Pracetak untuk Rumah Sederhana
14
100
100
Besi 2x2  8 mm Besi 1x2  8 mm
Besi  6 mm
Besi  6 mm - 8 bh
Besi  8 mm - 4 bh
Besi  6 mm - 8 bh
1170
1200
60
300
300
45
300
75
84
187
243
84
45
80
69
100
60
80 100 100 210
260
36
26
275
275
Besi  8 mm - 2 bh
80100100210206
275
70
70
75
25
JUDUL GAMBAR : DIRENCANAKAN :
DIGAMBAR :
DISETUJUI :
TANGGAL :
GIN
No. Gambar
PUSAT LITBANG PERMUKIMAN - BALITBANG PU
KETERANGAN :
PENULANGAN PANEL RISHA TIPE-2
1200
1170
TAMPAK ATAS
RANGKAIAN TULANGAN PANEL
TAMPAK SAMPING
RANGKAIAN TULANGAN PANEL
DETAIL TULANGAN UTAMA
01
E. Pelaksanaan
1. Ketentuan ukuran Panel Struktural
Panel Struktural Risha mempunyai ukuran tebal 2 cm, lebar 30 cm, tinggi 120 cm
yang dikelilingi frame ukuran 6 cm x 10 cm, yang dilengkapi dengan lubang untuk
angker pada framenya dengan diameter lubang sebesar 16 mm, masing-masing sisi
sebanyak 2 buah dengan jarak antar as lubang 13,5 cm untuk kearah pendek yang
ditempatkan pada as panel dan untuk yang kearah tinggi 15 cm diukur dari ujung
frame sampai dengan as lubang.
Gambar 5.1 Penulangan Komponen RISHA P1
Konstruksi Pracetak untuk Rumah Sederhana
15
Gambar 5.2 Penulangan Komponen RISHA P2
100
100
Besi 2x2  8 mm Besi 1x2  8 mm
Besi  6 mm
Besi  6 mm
Besi  8 mm @ 2 bh
Besi  6 mm - 6 bh
1170
1200
60
1200
45
75
84
84
45
100
60
80 100 100 210
1170
36
275
Besi  8 mm - 2 bh
80100100210206
275
70
70
160
200
200
200
200
80
86
50
45
70
40
178
86
50
70
40
178
6 Bh 2 Bh
86
145
86
145
36
300
JUDUL GAMBAR : DIRENCANAKAN :
DIGAMBAR :
DISETUJUI
:
TANGGAL :
GIN
No. Gambar
PUSAT LITBANG PERMUKIMAN - BALITBANG PU
KETERANGAN :
TAMPAK ATAS
RANGKAIAN TULANGAN PANEL
TAMPAK SAMPING
RANGKAIAN TULANGAN PANEL
DETAIL TULANGAN UTAMA
PENULANGAN PANEL RISHA TIPE-2 02
Konstruksi Pracetak untuk Rumah Sederhana
16
Gambar 5.3 Penulangan Komponen RISHA Panel Penyambung
2. Pelaksanaan pembuatan panel-panel RISHA
1. Pembuatan Cetakan Kayu
a) Dimensi dan bentuk cetakan untuk panel P-1 adalah sebagai berikut:
Gambar 5.4 Bentuk Cetakan Kayu Panel P2
TAMPAK
PEMBESIAN PANEL
TAMPAK
PANEL PENGHUBUNG
PERSPEKTIF
PANEL PENGHUBUNG
300
100
300
100
50
50
200
300
135135
82.5
82.5
60
5050
82.5
300
200100
300
82.582.5
82.5
300
200100
135
135
300
CETAKAN
PANEL PENGHUBUNG
PENAMPANG
PANEL PENGHUBUNG
300
60
60
5050
60
13582.5
100
200100
300
Konstruksi Pracetak untuk Rumah Sederhana
17
Gambar 5.5 Pelaksanaan Pembuatan Cetakan Panel P1
b) Dimensi dan bentuk cetakan panel P2
Gambar 5.6 Bentuk Bekisting Kayu Panel P2
Konstruksi Pracetak untuk Rumah Sederhana
18
c) Dimensi dan bentuk cetakan panel join
Gambar 5.7 Bentuk Cetakan Kayu Panel Sambungan
Gambar 5.8 Bentuk Cetakan Kayu Panel Sambungan
Konstruksi Pracetak untuk Rumah Sederhana
19
2. Pembuatan Cetakan Besi Baja
Semua baja yang dipakai harus menggunakan minimal U 24 dengan
ketentuan berupa profil ( [ ) kanal dengan ukuran [ 100 x 50 x 5 mm, dan pelat
baja sebagai dasar cetakan tebal 5 mm yang memenuhi persyaratan yang
tercantum dalam buku Tabel Profil Konstruksi Baja. Baut dan Mur yang
digunakan sebagai pengunci antar panel yaitu ukuran diameter 8 mm. Pralon
yang digunakan adalah pralon listrik diameter 5/8 inchi. Pelat baja dengan tebal
2 mm dan ukurannya 4 x 6 cm dan diberi lubang di tengah – tengahnya dengan
diameter 5/8 inchi, yang digunakan sebagai pengaku lubang pralon.
Gambar 5.9 ukuran cetakan baja Panel P1
Konstruksi Pracetak untuk Rumah Sederhana
20
Gambar 5.10 Ukuran cetakan baja panel P2
Gambar 5.11 Bentuk cetakan baja panel sambungan
3. Perakitan Tulangan
Tulangan dirakit sedemikian sehingga sesuai dengan gambar teknis penulangan
panel RISHA. Lubang-lubang baut harus disediakan dengan cara memasang pipa-
pipa pada titik-titik baut.
Konstruksi Pracetak untuk Rumah Sederhana
21
Gambar 5.12 Perakitan tulangan panel RISHA
4. Pelaksanaan Pengecoran dan Pemadatan
Pengecoran dilakukan secara perlahan mulai dari bagian framenya dan dilakukan
penggetaran dengan vibrator dalam arah vertikal, sehingga beton mengalami
pemadatan yang maksimal, dengan memperhatikan batas waktu penggetaran
jangan sampai terjadi pemisahan campuran beton.
5. Pembukaan Cetakan
Cetakan dapat dibuka setelah 24 jam dari waktu pengecoran, dengan cara
perlahan dan hati-hati.
Konstruksi Pracetak untuk Rumah Sederhana
22
3. Penentuan Denah Bangunan Rumah Tipe 36
Gambar 5.13
3,003.00
3,00
1.50
6.00
Kamar Tidur
± 0.00
3,00
6.00
1.50
Kamar Tidur
± 0.00
Ruang Tengah
± 0.00
KM/WC
- 0.10
A
TERAS - 0.05
TERAS - 0.05
MejaDapur
B
Konstruksi Pracetak untuk Rumah Sederhana
23
Gambar 5.14
4. erakitan Rumah RISHA
1. Pengukuran dan penempatan patok-patok.
Penempatan patok-patok dilakukan untuk memberikan kepastian dan
kesikuan konstruksi bangunan RISHA. Jarak-jarak lahan yang dipatok
deisesuaikan dengan luas denah dan ketersediaan lPahan.
DENAH
A
B
3,003.00
3,00
1.50
6.00
3,00
6.00
1.80
Kamar Tidur
± 0.00
Teras Blkng
- 0.10
MejaDapur
Teras
- 0.10
0.60
C
Ruang Tamu
± 0.00
Ruang Keluarga
± 0.00
Dapur
± 0.00
Kamar Tidur
± 0.00
KM/WC
- 0.20
Konstruksi Pracetak untuk Rumah Sederhana
24
Gambar 5.15 Penempatan patok-patok rumah RISHA
Sisi atas dari papan duga di ratakan dengan menggunakan ketam sehingga
permukaan ini halus dan benar-benar horisontal.
Konstruksi Pracetak untuk Rumah Sederhana
25
2. Penggalian pondasi.
Gali tanah untuk pondasi dengan mengikuti pola galian pondasi hingga
kedalaman 20 cm dari permukaan tanah yang telah diratakan dan dibersikan
dari akar rumput. Titik fondasi disesuaikan dengan as bagian-bagian bangunan
yaitu as balok dan kolom serta ukuran panel-panel RISHA.
Gambar 5.16 Galian pondasi
Konstruksi Pracetak untuk Rumah Sederhana
26
3. Pemasangan Pondasi
a) Hamparkan pasir urug pada galin pondasi dan padatkan sehingga
diperoleh tebal padat pasir urug dibawah pondasi 8 cm.
b) Tempatkan pondasi pelat pada masing-masing galian dan atur sedemikian
sehingga baut yang tertanam pada pondasi ini sejajar dengan benang as
dinding bangunan baik pada arah lebar maupun pada arah panjang
bangunan.
Gambar 5.17 Penempatan Pondasi
Lubang
pondasi
Pondasi, digeser
kekakanan dan ke
kiri sedemikian
sehingga baut yang
tertanam pada
pondasi tepat
berada atau sejajar
dengan benang as
dinding bangunan
Benang as
dinding
bangunan
Konstruksi Pracetak untuk Rumah Sederhana
27
4. Pemasangan Panel Penyambung pada Pondasi
a) Pasang panel-panel penyambung pada setiap pondasi, dengan cara
masukan baut-baut yang ada di pondasi pada lubang yang tersedia pada
panel penyambung.
b) Pastikan baut yang digunakan adalah baut-baut yang segaris dengan
benang as dinding bangunan.
c) Kencangkan mur pada setiap baut penyambung hingga ½ kekuatan dari
yang seharusnya.
Gambar 5.18 Pemasangan panel join kolom terhadap pondasi
Konstruksi Pracetak untuk Rumah Sederhana
28
5. Pemasangan Balok Sloof
Gambar 5.19 Pemasagan balok sloof
6. Pemasangan Kolom
Konstruksi Pracetak untuk Rumah Sederhana
29
Gambar 5.20 Pemasangan kolom
7. Pemasangan Balok Atas
a) Sebelum sambungan pada kolom-kolom dikencangkan penuh, pasang
panel-panel penyambung untuk selanjutnya memasang panel-panel balok
atas (ring balok). Sambungan diberi kekuatan setengah penuh hingga
panel-panel penyambung dan panel ring balok terpasang seluruhnya.
b) Gunakan perancah dan tangga dalam pemasangan panel-panel ini untuk
memudahkan dalam pemasangannya secara lurus dan horisontal.
c) Kencangkan seluruh penyambung hingga mencapai kekuatan penuh sambil
terus menerus di cek dengan mengunakan alat water-pass pada setiap
panel yang sedang dikencangan.
Konstruksi Pracetak untuk Rumah Sederhana
30
Gambar 5.21
8. Pemasangan Ampig, Kuda-kuda dan Goring
a) pasang panel kolom pada kolom tengah dari bangunan, kencangkan
dengan menggunakan mur baut, kemudia pasang kaki kuda-kuda dari
kayu 5/10 cm dan gunakan baut untuk sambungan kaki kuda-kuda
dengan kolom dan balok (pada kaki kuda-kuda sudah tersedia lubang
baut yag sesuai dengan lubang pada kolom dan balok).
b) Pasang gording kayu 5/10 dengan menggunakan sambungan paku.
Konstruksi Pracetak untuk Rumah Sederhana
31
Gambar 5.22
9. Pemasangan Penutup Atap dan Lisplang
Pasang penutup atap sebelum pekerjaan pemasangan dinding dan pekerjaan
lantai, bila mengunakan penutup atap asbes gelombang, disarankan gunakan
alat penghubung yang mudah dilepas tanpa merusak asbesnya sendiri. Bila
mengunakan penutup atap genteng (baik keramik maupun beton) pasang
terlebih dahulu kaso 5/7 dan reng ¾.
Gordin
g 5/10
cm
Ka
ki
ku
da-
ku
da
Konstruksi Pracetak untuk Rumah Sederhana
32
Gambar 5.23
10. Pengurugan dan pemasangan lantai
a) Pekerjaan pengurugan dan pemadatan dilakukan mengikuti SNI 03 - ....-
.....dengan tebal padat 20 cm.
b) Sebarkan pasir urug dan padatkan hingga menapai tebal padat 5 cm.
c) Pasang lantai paving blok 20/20 cm dari bahan campuran .........tanpa
adukan spesi.
Gambar 5.24
Lantai paving blok
20/20 cmPasir urug padat
5 cmUrugan tanah tebal
padat 10 cm
Balok sloof
10x30x120 cm
Lantai di dalam
bangunan
Lantai teritisan disekeliling
bangunan
Konstruksi Pracetak untuk Rumah Sederhana
33
Gambar 5.25 Setelah Pekerjaan Pengurugan dan Pemasangan Lantai
Konstruksi Pracetak untuk Rumah Sederhana
34
11. Pemasangan panel dinding, panel jendela, panel pintu dan panel ampig
Gambar 5.26
12. Pemasangan Daun Pintu dan Jendela
Daun pintu dan jendela telah terpasang pada panel, yang perlu dilakukan
hanya pekerjaa pengaturan dan penyesuaian agar pintu dan jendela dapat
dibuka dan ditutup dengan mudah, dan pemasangan kaca pada jendela.
Konstruksi Pracetak untuk Rumah Sederhana
35
F. Perkiraan Biaya
Tabel 6. 1
No Uraian Pekerjan/Komponen Qty Sat
Harga Komp./
Harga Pekerjaan
(Rp)
Jumlah
(Rp)
I Pek Persiapan
3.987.207,60
1 Pembersihan Site ( 14 X 9.50 ) m2 133,00 m2
7.590,00 1.009.470,00
2
Gudang/Direksi Keet (1 unit per 10 unit
rumah)
9,00 m2
100.000,00 900.000,00
3 Pemasangan Bouwplank 22,00 m1
76.260,80 1.677.737,60
4 Papan nama Proyek 1,00 unit
400.000,00 400.000,00
II Pek Galian dan timbunan
4.569.316,95
1 Galian Tanah Biasa u/ pondasi setempat 11,52 m3
89.760,00 1.034.035,20
2 Timbunan tanah kembali 3,84 m3
121.550,00 466.752,00
3 Timbunan dgn pasir urug, di bwh lantai 25,25 m3
121.550,00 3.068.529,75
II Pek Pondasi
7.784.584,46
1
Pondasi setempat, pas. batu belah, camp
1 : 5
7,10 m3
698.121,16 4.956.660,24
2
Aanstamping t = 20 cm (di bwh pond
setempat)
1,76 m3
330.983,40 582.530,78
3
Pond. menerus, pas. batu belah, camp 1 :
5
2,60 m3
698.121,16 1.815.115,02
4
Aanstamping t = 20 cm (di bwh pond
menerus)
1,30 m3
330.983,40 430.278,42
III Pek Beton K-250
1.918.000,00
1 Kolom Praktis 10/10 (beton Bertulang) 0,29 m3
3.500.000,00 1.008.000,00
2 Balok Sloof dan ringbalk 10/12 (Beton 0,26 m3
Konstruksi Pracetak untuk Rumah Sederhana
36
No Uraian Pekerjan/Komponen Qty Sat
Harga Komp./
Harga Pekerjaan
(Rp)
Jumlah
(Rp)
bertulang) 3.500.000,00 910.000,00
IV LANTAI
13.492.544,78
1
Keramik 30 x 30, Termasuk teras, 2 *
(0,60 x 3)
75,60 m2
167.401,30 12.655.538,28
2 Keramik lantai KM 30 x 30 5,00 m2
167.401,30 837.006,50
3 Keramik dinding KM 25 x 30, tinggi 90 cm 10,00 m2
167.401,30 1.674.013,00
V Struktur Rangka Panel RISHA
39.156.000,00
A Balok Lantai 0.00 s.d - 0 30
1 Panel Tipe I, P1 (30 x 120) 44,00 bh
120.000,00 5.280.000,00
2 Komponen Simpul P3, (30 x 30) 32,00 bh
100.000,00 3.200.000,00
3 Angkur, Φ 12, panjang 40 cm 64,00 bh
14.000,00 896.000,00
B Kolom (+ 0,00 ) sampai (+ 2.40)
1 Panel Tipe I, P1 (30 x 120) 64,00 bh
120.000,00 7.680.000,00
2 Panel Tipe II, P2 (20 x 120) 64,00 bh
110.000,00 7.040.000,00
C Pembalokan (+ 2.40) - (+2.70) / Ringbalk
1 Panel Tipe I, P1 (30 x 120) 24,00 bh
120.000,00 2.880.000,00
2 Komponen Simpul P3, (30 x 30) 32,00 bh
100.000,00 3.200.000,00
D Pembalokan (+ 2.70) - (+5.00) / Ringbalk
1 Panel Tipe I, P1 (30 x 120) 28,00 bh
120.000,00 3.360.000,00
2 Komponen Simpul P3, (30 x 30) 16,00 bh
120.000,00 1.920.000,00
E Baut - Mur - Plat penyambung
1
Mur Baut Hitam HTB, 12+ plat
penyambung
1000 bh
3.700,00 3.700.000,00
Konstruksi Pracetak untuk Rumah Sederhana
37
No Uraian Pekerjan/Komponen Qty Sat
Harga Komp./
Harga Pekerjaan
(Rp)
Jumlah
(Rp)
VI Dinding
38.014.475,84
1 Pasangan bata merah 1/2 bt 87,00 m2
176.900,68 15.390.359,16
2 Plesteran tebal, t = 1.5 cm 151,00 m2
91.045,68 13.747.897,68
3 Acian PC (dinding yang diplester) 151,00 m2
29.386,50 4.437.361,50
4 Pas Bata merah ampig 28,00 m2
122.276,00 3.423.728,00
5 Plesteran ampig tebal, t = 1.5 cm 15,00 m2
38.288,80 574.332,00
6 Acian PC (dinding yang diplester) 15,00 m2
29.386,50 440.797,50
Tabel 6. 2
No Uraian Pekerjan/Komponen Qty Sat
Harga
Komponen/
Harga Pekerjaan
(Rp)
Jumlah
(Rp)
VII Pek Kusen Pintu dan jendela
10.995.778,00
1 Rangka Kusen Pintu, (PNT-1), 2,00 bh 450.000,00 900.000,00
2 Panel Daun Pintu dobel triplek, (PNT-1) 2,00 bh 317.889,00 635.778,00
3 Rangka Kusen Pintu, (PNT-2), 6,00 bh 450.000,00 2.700.000,00
4 Panel Daun Pintu dobel triplek, (PNT-2) 6,00 bh 400.000,00 2.400.000,00
5 Rangka Kusen Jendela, JD -1 2,00 bh 600.000,00 1.200.000,00
6 Rangka Kusen Jendela, JD -2 (tidak ada) - bh 500.000,00 -
7
Daun Jendela (JD-1)+(JD-2),+ kaca polos, 5
mm
4,00 bh 500.000,00 2.000.000,00
8 Pintu KM/WC, Fiber, lengkap 2,00 bh 260.000,00 520.000,00
9 Glass block (KM dan Dapur), (4 bhx 2), 2 bh 16,00 bh 40.000,00 640.000,00
Konstruksi Pracetak untuk Rumah Sederhana
38
No Uraian Pekerjan/Komponen Qty Sat
Harga
Komponen/
Harga Pekerjaan
(Rp)
Jumlah
(Rp)
VIII Rangka Atap
18.460.000,00
1 Konstruksi Kuda-Kuda Baja ringan, 142,00 m2 130.000,00 18.460.000,00
IX Penutup Atap 8.555.000,00
1 Lembaran asbes gelombang + Bubungan 142,00 m2 50.000,00 7.100.000,00
2 List plank, GRC, t : 4 mm, lebar 30 cm 58,20 m1 25.000,00 1.455.000,00
X Pek Gantungan Kunci dan lain-lain 1.660.000,00
1 Engsel Pintu 8,00 psng 30.000,00 240.000,00
2 Kunci Pintu, 2 track, setara Bremen 8,00 bh 90.000,00 720.000,00
3 Slot pintu, panjang 6 cm 8,00 bh 25.000,00 200.000,00
4
Pegangan Pintu, (Pintu depan dan
belakang)
4,00 bh 45.000,00 180.000,00
5 Engsel Jendela 4,00 psng 30.000,00 120.000,00
6 Slot Jendela 4,00 bh 25.000,00 100.000,00
7 Hak angin jendela 4,00 bh 25.000,00 100.000,00
XI Pekerjaan Langit-langit (Plafon) 20.231.164,80
1 Rangka langit-langit, kayu 5/7 .
ukuran Rangka langit-langit 60 x 60 cm 126,00 m2 122.276,00 15.406.776,00
2 Penutup langit-langit, GRC plat, t = 4 mm 126,00 m2 38.288,80 4.824.388,80
XII Pek Listrik 5.980.000,00
1 Meteran Listrik, Pulsa,kwh : 900 watt
Plus 3 titik lampu dari PLN 2,00 unit 1.400.000,00 2.800.000,00
2 Saklar, Stop kontak termasuk kabel 22,00 ttk 100.000,00 2.200.000,00
Konstruksi Pracetak untuk Rumah Sederhana
39
No Uraian Pekerjan/Komponen Qty Sat
Harga
Komponen/
Harga Pekerjaan
(Rp)
Jumlah
(Rp)
3 Lampu TL, 20 Watt 12,00 bh 40.000,00 480.000,00
4 Arde 2,00 bh 250.000,00 500.000,00
XIII Pekerjaan Pengecatan 6.572.415,19
1 Cat dinding/cat tembok 151,00 m2 15.365,90 2.320.250,90
2 Cat dinding GRC, ampig 28,00 m2 15.365,90 430.245,20
3 Cat Kayu 36,00 m2 39.963,00 1.438.668,00
4 Cat Listplank 29,10 m2 15.365,90 447.147,69
5 Cat Plafon/langit-langit 126,00 m2 15.365,90 1.936.103,40
XIV Pekerjaan KM dan perpipaan 8.881.458,80
1 Kloset jongkok 2,00 unit 295.629,40 591.258,80
2 Floor drain 2,00 bh 34.540,00 69.080,00
3 Kran Air D 3/4" 4,00 bh 18.000,00 72.000,00
4 Pipa PVC, D 3/4 18,00 m1 9.660,00 173.880,00
5 Pipa PVC, D 3" 18,00 m1 54.180,00 975.240,00
6 Biofil, ukuran untuk keluarga 1,00 unit 7.000.000,00 7.000.000,00
7 Bidang Resapan 1,00 unit - -
Konstruksi Pracetak untuk Rumah Sederhana
40
Tabel 6. 3
No Uraian Pekerjan/Komponen Qty Sat
Harga
Komponen/
Harga
Pekerjaan
(Rp)
Jumlah
(Rp)
XV
Pekerjaan Perakitan Komponen
Risha 3.040.000,00
1 Pemasangan Panel-Panel 304,00 Pcs
10.000,00 3.040.000,00
2
Biaya pengiriman panel dari
workshop ke lokasi
ls
-
-
3 Transport pekerja ke lokasi (PP) 4,00 org
400.000,00 1.600.000,00
XVI Pekerjaan penyelesaian
500.000,00
1 Pembersihan Lapangan 1,00 m2
500.000,00 500.000,00
Jumlah (1) 132.846.709,62
Keuntungan pemborong 12.5 % 16.605.838,70
Jumlah (2) 149.452.548,32
PPN, 10 % 14.945.254,83
Jumlah Total 164.397.803,15
Pembulatan 164.390.000,00
Konstruksi Pracetak untuk Rumah Sederhana
41

More Related Content

What's hot

AHS pekerjaan beton SNI 7394-2008
AHS pekerjaan beton SNI 7394-2008AHS pekerjaan beton SNI 7394-2008
AHS pekerjaan beton SNI 7394-2008Vanny Wayongkere
 
Perencanaan gaya gaya pondasi pada bangunan gedung dengan 1 basement
Perencanaan gaya gaya pondasi pada bangunan gedung dengan 1 basementPerencanaan gaya gaya pondasi pada bangunan gedung dengan 1 basement
Perencanaan gaya gaya pondasi pada bangunan gedung dengan 1 basementAfret Nobel
 
Rsni t 03-2005. jembatan
Rsni t 03-2005. jembatanRsni t 03-2005. jembatan
Rsni t 03-2005. jembataniky
 
Pd t 14-2003 - perencanaan perkerasan jalan beton semen
Pd t 14-2003 - perencanaan perkerasan jalan beton semenPd t 14-2003 - perencanaan perkerasan jalan beton semen
Pd t 14-2003 - perencanaan perkerasan jalan beton semenSyukri Ghazali
 
LAPORAN KERJA PRAKTEK PADA PROYEK PEMBANGUNAN HOTEL DAN APARTEMEN HADININGRAT...
LAPORAN KERJA PRAKTEK PADA PROYEK PEMBANGUNAN HOTEL DAN APARTEMEN HADININGRAT...LAPORAN KERJA PRAKTEK PADA PROYEK PEMBANGUNAN HOTEL DAN APARTEMEN HADININGRAT...
LAPORAN KERJA PRAKTEK PADA PROYEK PEMBANGUNAN HOTEL DAN APARTEMEN HADININGRAT...intan mustika
 
Buku laporan pptppo 2015 trafficking report indonesia
Buku laporan pptppo 2015 trafficking report indonesiaBuku laporan pptppo 2015 trafficking report indonesia
Buku laporan pptppo 2015 trafficking report indonesiaECPAT Indonesia
 
4.2 pelaksanaan pekerjaan abudment
4.2 pelaksanaan pekerjaan abudment4.2 pelaksanaan pekerjaan abudment
4.2 pelaksanaan pekerjaan abudmentMuhamadFarhan64
 
367417207 metode-pelaksanaan-pekerjaan-abutmen-dan-pilar-jembatan
367417207 metode-pelaksanaan-pekerjaan-abutmen-dan-pilar-jembatan367417207 metode-pelaksanaan-pekerjaan-abutmen-dan-pilar-jembatan
367417207 metode-pelaksanaan-pekerjaan-abutmen-dan-pilar-jembatanfianardi
 
Perencanaan jalan beton
Perencanaan jalan betonPerencanaan jalan beton
Perencanaan jalan betonAbd Hamid
 
Metode pelaksanaan pasang rangka atap baja ringan
Metode pelaksanaan pasang rangka atap baja ringanMetode pelaksanaan pasang rangka atap baja ringan
Metode pelaksanaan pasang rangka atap baja ringanHandry J
 
Desain Jembatan (By Anton H.P. ST., MT).pdf
Desain Jembatan (By Anton H.P. ST., MT).pdfDesain Jembatan (By Anton H.P. ST., MT).pdf
Desain Jembatan (By Anton H.P. ST., MT).pdfNhkHabit
 
TUGAS AKHIR TINJAUAN DESAIN BANGUNAN KOLAM RENANG PADA HOTEL WHIZ MAKASSAR
TUGAS AKHIR TINJAUAN DESAIN BANGUNAN KOLAM RENANG PADA HOTEL WHIZ MAKASSARTUGAS AKHIR TINJAUAN DESAIN BANGUNAN KOLAM RENANG PADA HOTEL WHIZ MAKASSAR
TUGAS AKHIR TINJAUAN DESAIN BANGUNAN KOLAM RENANG PADA HOTEL WHIZ MAKASSARSumarno Feriyal
 
penulangan kolom, balok dan plat bangunan gedung
penulangan kolom, balok dan plat bangunan gedungpenulangan kolom, balok dan plat bangunan gedung
penulangan kolom, balok dan plat bangunan gedungAgus Fitriyanto
 
TEKNIK PEMASANGAN TIANG PANCANG ULIN MENARA PENGAWAS MANGROVE DI MANGROVE CEN...
TEKNIK PEMASANGAN TIANG PANCANG ULIN MENARA PENGAWAS MANGROVE DI MANGROVE CEN...TEKNIK PEMASANGAN TIANG PANCANG ULIN MENARA PENGAWAS MANGROVE DI MANGROVE CEN...
TEKNIK PEMASANGAN TIANG PANCANG ULIN MENARA PENGAWAS MANGROVE DI MANGROVE CEN...Reski Aprilia
 

What's hot (20)

PPT Jalan Jalan.pdf
PPT Jalan Jalan.pdfPPT Jalan Jalan.pdf
PPT Jalan Jalan.pdf
 
AHS pekerjaan beton SNI 7394-2008
AHS pekerjaan beton SNI 7394-2008AHS pekerjaan beton SNI 7394-2008
AHS pekerjaan beton SNI 7394-2008
 
Perencanaan gaya gaya pondasi pada bangunan gedung dengan 1 basement
Perencanaan gaya gaya pondasi pada bangunan gedung dengan 1 basementPerencanaan gaya gaya pondasi pada bangunan gedung dengan 1 basement
Perencanaan gaya gaya pondasi pada bangunan gedung dengan 1 basement
 
Rsni t 03-2005. jembatan
Rsni t 03-2005. jembatanRsni t 03-2005. jembatan
Rsni t 03-2005. jembatan
 
Pd t 14-2003 - perencanaan perkerasan jalan beton semen
Pd t 14-2003 - perencanaan perkerasan jalan beton semenPd t 14-2003 - perencanaan perkerasan jalan beton semen
Pd t 14-2003 - perencanaan perkerasan jalan beton semen
 
LAPORAN KERJA PRAKTEK PADA PROYEK PEMBANGUNAN HOTEL DAN APARTEMEN HADININGRAT...
LAPORAN KERJA PRAKTEK PADA PROYEK PEMBANGUNAN HOTEL DAN APARTEMEN HADININGRAT...LAPORAN KERJA PRAKTEK PADA PROYEK PEMBANGUNAN HOTEL DAN APARTEMEN HADININGRAT...
LAPORAN KERJA PRAKTEK PADA PROYEK PEMBANGUNAN HOTEL DAN APARTEMEN HADININGRAT...
 
Buku laporan pptppo 2015 trafficking report indonesia
Buku laporan pptppo 2015 trafficking report indonesiaBuku laporan pptppo 2015 trafficking report indonesia
Buku laporan pptppo 2015 trafficking report indonesia
 
4.2 pelaksanaan pekerjaan abudment
4.2 pelaksanaan pekerjaan abudment4.2 pelaksanaan pekerjaan abudment
4.2 pelaksanaan pekerjaan abudment
 
208119724 rks-sumur-bor
208119724 rks-sumur-bor208119724 rks-sumur-bor
208119724 rks-sumur-bor
 
Spesifikasi teknis
Spesifikasi teknisSpesifikasi teknis
Spesifikasi teknis
 
367417207 metode-pelaksanaan-pekerjaan-abutmen-dan-pilar-jembatan
367417207 metode-pelaksanaan-pekerjaan-abutmen-dan-pilar-jembatan367417207 metode-pelaksanaan-pekerjaan-abutmen-dan-pilar-jembatan
367417207 metode-pelaksanaan-pekerjaan-abutmen-dan-pilar-jembatan
 
Perencanaan jalan beton
Perencanaan jalan betonPerencanaan jalan beton
Perencanaan jalan beton
 
Metode pelaksanaan pasang rangka atap baja ringan
Metode pelaksanaan pasang rangka atap baja ringanMetode pelaksanaan pasang rangka atap baja ringan
Metode pelaksanaan pasang rangka atap baja ringan
 
Desain Jembatan (By Anton H.P. ST., MT).pdf
Desain Jembatan (By Anton H.P. ST., MT).pdfDesain Jembatan (By Anton H.P. ST., MT).pdf
Desain Jembatan (By Anton H.P. ST., MT).pdf
 
TUGAS AKHIR TINJAUAN DESAIN BANGUNAN KOLAM RENANG PADA HOTEL WHIZ MAKASSAR
TUGAS AKHIR TINJAUAN DESAIN BANGUNAN KOLAM RENANG PADA HOTEL WHIZ MAKASSARTUGAS AKHIR TINJAUAN DESAIN BANGUNAN KOLAM RENANG PADA HOTEL WHIZ MAKASSAR
TUGAS AKHIR TINJAUAN DESAIN BANGUNAN KOLAM RENANG PADA HOTEL WHIZ MAKASSAR
 
Perkersan jalan
Perkersan jalanPerkersan jalan
Perkersan jalan
 
penulangan kolom, balok dan plat bangunan gedung
penulangan kolom, balok dan plat bangunan gedungpenulangan kolom, balok dan plat bangunan gedung
penulangan kolom, balok dan plat bangunan gedung
 
Pondasi sumuran
Pondasi sumuranPondasi sumuran
Pondasi sumuran
 
Pelaksanaan pondasi dalam
Pelaksanaan pondasi dalamPelaksanaan pondasi dalam
Pelaksanaan pondasi dalam
 
TEKNIK PEMASANGAN TIANG PANCANG ULIN MENARA PENGAWAS MANGROVE DI MANGROVE CEN...
TEKNIK PEMASANGAN TIANG PANCANG ULIN MENARA PENGAWAS MANGROVE DI MANGROVE CEN...TEKNIK PEMASANGAN TIANG PANCANG ULIN MENARA PENGAWAS MANGROVE DI MANGROVE CEN...
TEKNIK PEMASANGAN TIANG PANCANG ULIN MENARA PENGAWAS MANGROVE DI MANGROVE CEN...
 

Similar to 04 konstruksi pracetak_untuk_rumah_sederhana_2017

Laporan Pengawasan Pekerjaan Lapangan Pu
Laporan Pengawasan Pekerjaan Lapangan PuLaporan Pengawasan Pekerjaan Lapangan Pu
Laporan Pengawasan Pekerjaan Lapangan PuWiliam9
 
Perancangan struktur beton perpustakaan 4 lantai
Perancangan struktur beton perpustakaan 4 lantaiPerancangan struktur beton perpustakaan 4 lantai
Perancangan struktur beton perpustakaan 4 lantaiAfret Nobel
 
Lembar pengesahan dan daftar isi
Lembar pengesahan dan daftar  isiLembar pengesahan dan daftar  isi
Lembar pengesahan dan daftar isiAndriansyah Tsk
 
Laporan akhir perancangan elemen mesin kelompok 7 pengelasan
Laporan akhir perancangan elemen mesin kelompok 7 pengelasanLaporan akhir perancangan elemen mesin kelompok 7 pengelasan
Laporan akhir perancangan elemen mesin kelompok 7 pengelasandian haryanto
 
Rkjm sdn pondokkaso tonggoh
Rkjm sdn pondokkaso tonggohRkjm sdn pondokkaso tonggoh
Rkjm sdn pondokkaso tonggohagusrenggi
 
analisa str contoh.pdf
analisa str contoh.pdfanalisa str contoh.pdf
analisa str contoh.pdfrizki510207
 
Laporan Akhir EKPD 2010 - Sumbar - Unand
Laporan Akhir EKPD 2010 - Sumbar - UnandLaporan Akhir EKPD 2010 - Sumbar - Unand
Laporan Akhir EKPD 2010 - Sumbar - UnandEKPD
 
E book vba-excel dasar
E book vba-excel dasarE book vba-excel dasar
E book vba-excel dasarTommyAdrian
 
Tesis Kebutuhan Perlengkapan Jalan
Tesis Kebutuhan Perlengkapan JalanTesis Kebutuhan Perlengkapan Jalan
Tesis Kebutuhan Perlengkapan Jalanoktariansyah
 
222298712 rpi2 jm-5-ksn-ksn-pbts-aceh-sumut-sulut-gorontalo-sulteng-riau-kepr...
222298712 rpi2 jm-5-ksn-ksn-pbts-aceh-sumut-sulut-gorontalo-sulteng-riau-kepr...222298712 rpi2 jm-5-ksn-ksn-pbts-aceh-sumut-sulut-gorontalo-sulteng-riau-kepr...
222298712 rpi2 jm-5-ksn-ksn-pbts-aceh-sumut-sulut-gorontalo-sulteng-riau-kepr...radengembull
 
Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 3)
Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 3)Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 3)
Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 3)Donny Kurniawan
 
Rencana Detail Tata Ruang Wilayah Kota
Rencana Detail Tata Ruang Wilayah KotaRencana Detail Tata Ruang Wilayah Kota
Rencana Detail Tata Ruang Wilayah KotaPenataan Ruang
 
Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 4)
Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 4)Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 4)
Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 4)Donny Kurniawan
 
SMK MAK kelas10 smk kria tekstil budiyono
SMK MAK kelas10 smk kria tekstil budiyonoSMK MAK kelas10 smk kria tekstil budiyono
SMK MAK kelas10 smk kria tekstil budiyonosekolah maya
 
Kbli 2009
Kbli 2009Kbli 2009
Kbli 2009Yuni
 
Laporan Akhir EKPD 2010 - Sulbar - UNM
Laporan Akhir EKPD 2010 - Sulbar - UNMLaporan Akhir EKPD 2010 - Sulbar - UNM
Laporan Akhir EKPD 2010 - Sulbar - UNMEKPD
 

Similar to 04 konstruksi pracetak_untuk_rumah_sederhana_2017 (20)

Laporan Pengawasan Pekerjaan Lapangan Pu
Laporan Pengawasan Pekerjaan Lapangan PuLaporan Pengawasan Pekerjaan Lapangan Pu
Laporan Pengawasan Pekerjaan Lapangan Pu
 
Perancangan struktur beton perpustakaan 4 lantai
Perancangan struktur beton perpustakaan 4 lantaiPerancangan struktur beton perpustakaan 4 lantai
Perancangan struktur beton perpustakaan 4 lantai
 
Lembar pengesahan dan daftar isi
Lembar pengesahan dan daftar  isiLembar pengesahan dan daftar  isi
Lembar pengesahan dan daftar isi
 
Laporan akhir perancangan elemen mesin kelompok 7 pengelasan
Laporan akhir perancangan elemen mesin kelompok 7 pengelasanLaporan akhir perancangan elemen mesin kelompok 7 pengelasan
Laporan akhir perancangan elemen mesin kelompok 7 pengelasan
 
Rkjm sdn pondokkaso tonggoh
Rkjm sdn pondokkaso tonggohRkjm sdn pondokkaso tonggoh
Rkjm sdn pondokkaso tonggoh
 
analisa str contoh.pdf
analisa str contoh.pdfanalisa str contoh.pdf
analisa str contoh.pdf
 
Laporan Akhir EKPD 2010 - Sumbar - Unand
Laporan Akhir EKPD 2010 - Sumbar - UnandLaporan Akhir EKPD 2010 - Sumbar - Unand
Laporan Akhir EKPD 2010 - Sumbar - Unand
 
E book vba-excel dasar
E book vba-excel dasarE book vba-excel dasar
E book vba-excel dasar
 
Tesis Kebutuhan Perlengkapan Jalan
Tesis Kebutuhan Perlengkapan JalanTesis Kebutuhan Perlengkapan Jalan
Tesis Kebutuhan Perlengkapan Jalan
 
222298712 rpi2 jm-5-ksn-ksn-pbts-aceh-sumut-sulut-gorontalo-sulteng-riau-kepr...
222298712 rpi2 jm-5-ksn-ksn-pbts-aceh-sumut-sulut-gorontalo-sulteng-riau-kepr...222298712 rpi2 jm-5-ksn-ksn-pbts-aceh-sumut-sulut-gorontalo-sulteng-riau-kepr...
222298712 rpi2 jm-5-ksn-ksn-pbts-aceh-sumut-sulut-gorontalo-sulteng-riau-kepr...
 
Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 3)
Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 3)Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 3)
Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 3)
 
Rencana Detail Tata Ruang Wilayah Kota
Rencana Detail Tata Ruang Wilayah KotaRencana Detail Tata Ruang Wilayah Kota
Rencana Detail Tata Ruang Wilayah Kota
 
Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 4)
Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 4)Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 4)
Cara Membuat Program Chatting Sederhana Dengan Visual Basic (Program 4)
 
SMK MAK kelas10 smk kria tekstil budiyono
SMK MAK kelas10 smk kria tekstil budiyonoSMK MAK kelas10 smk kria tekstil budiyono
SMK MAK kelas10 smk kria tekstil budiyono
 
Kbli 2009
Kbli 2009Kbli 2009
Kbli 2009
 
Kbli 2009
Kbli 2009Kbli 2009
Kbli 2009
 
Kbli 2009
Kbli 2009Kbli 2009
Kbli 2009
 
14. kbli 2009
14. kbli   200914. kbli   2009
14. kbli 2009
 
Laporan Kkl Awal
Laporan Kkl AwalLaporan Kkl Awal
Laporan Kkl Awal
 
Laporan Akhir EKPD 2010 - Sulbar - UNM
Laporan Akhir EKPD 2010 - Sulbar - UNMLaporan Akhir EKPD 2010 - Sulbar - UNM
Laporan Akhir EKPD 2010 - Sulbar - UNM
 

Recently uploaded

TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdfTEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdfYogiCahyoPurnomo
 
MODUL AJAR PENGANTAR SURVEY PEMETAAN.pdf
MODUL AJAR PENGANTAR SURVEY PEMETAAN.pdfMODUL AJAR PENGANTAR SURVEY PEMETAAN.pdf
MODUL AJAR PENGANTAR SURVEY PEMETAAN.pdfihsan386426
 
Manual Desain Perkerasan jalan 2017 FINAL.pptx
Manual Desain Perkerasan jalan 2017 FINAL.pptxManual Desain Perkerasan jalan 2017 FINAL.pptx
Manual Desain Perkerasan jalan 2017 FINAL.pptxRemigius1984
 
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptxMateri Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptxarifyudianto3
 
Metode numerik Bidang Teknik Sipil perencanaan.pdf
Metode numerik Bidang Teknik Sipil perencanaan.pdfMetode numerik Bidang Teknik Sipil perencanaan.pdf
Metode numerik Bidang Teknik Sipil perencanaan.pdfArvinThamsir1
 
Strategi Pengembangan Agribisnis di Indonesia
Strategi Pengembangan Agribisnis di IndonesiaStrategi Pengembangan Agribisnis di Indonesia
Strategi Pengembangan Agribisnis di IndonesiaRenaYunita2
 
4. GWTJWRYJJJJJJJJJJJJJJJJJJWJSNJYSRR.pdf
4. GWTJWRYJJJJJJJJJJJJJJJJJJWJSNJYSRR.pdf4. GWTJWRYJJJJJJJJJJJJJJJJJJWJSNJYSRR.pdf
4. GWTJWRYJJJJJJJJJJJJJJJJJJWJSNJYSRR.pdfAnonymous6yIobha8QY
 
10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppt10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppttaniaalda710
 
MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++FujiAdam
 

Recently uploaded (9)

TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdfTEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
TEKNIS TES TULIS REKRUTMEN PAMSIMAS 2024.pdf
 
MODUL AJAR PENGANTAR SURVEY PEMETAAN.pdf
MODUL AJAR PENGANTAR SURVEY PEMETAAN.pdfMODUL AJAR PENGANTAR SURVEY PEMETAAN.pdf
MODUL AJAR PENGANTAR SURVEY PEMETAAN.pdf
 
Manual Desain Perkerasan jalan 2017 FINAL.pptx
Manual Desain Perkerasan jalan 2017 FINAL.pptxManual Desain Perkerasan jalan 2017 FINAL.pptx
Manual Desain Perkerasan jalan 2017 FINAL.pptx
 
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptxMateri Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
Materi Asesi SKK Manajer Pelaksana SPAM- jenjang 6.pptx
 
Metode numerik Bidang Teknik Sipil perencanaan.pdf
Metode numerik Bidang Teknik Sipil perencanaan.pdfMetode numerik Bidang Teknik Sipil perencanaan.pdf
Metode numerik Bidang Teknik Sipil perencanaan.pdf
 
Strategi Pengembangan Agribisnis di Indonesia
Strategi Pengembangan Agribisnis di IndonesiaStrategi Pengembangan Agribisnis di Indonesia
Strategi Pengembangan Agribisnis di Indonesia
 
4. GWTJWRYJJJJJJJJJJJJJJJJJJWJSNJYSRR.pdf
4. GWTJWRYJJJJJJJJJJJJJJJJJJWJSNJYSRR.pdf4. GWTJWRYJJJJJJJJJJJJJJJJJJWJSNJYSRR.pdf
4. GWTJWRYJJJJJJJJJJJJJJJJJJWJSNJYSRR.pdf
 
10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppt10.-Programable-Logic-Controller (1).ppt
10.-Programable-Logic-Controller (1).ppt
 
MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++MAteri:Penggunaan fungsi pada pemrograman c++
MAteri:Penggunaan fungsi pada pemrograman c++
 

04 konstruksi pracetak_untuk_rumah_sederhana_2017

  • 1. Konstruksi Pracetak untuk Rumah Sederhana 0
  • 2. Konstruksi Pracetak untuk Rumah Sederhana 1 DAFTAR ISI DAFTAR ISI..................................................................................................................................0 DAFTAR GAMBAR....................................................................................................................................2 DAFTAR TABEL ........................................................................................................................................5 KATA PENGANTAR ..................................................................................................................................5 A. Pendahuluan.......................................................................................................................5 1. Latar Belakang.................................................................................................................6 2. Maksud dan Tujuan.........................................................................................................7 B. Gambaran Teknologi ..........................................................................................................7 C. Bahan..................................................................................................................................7 1. Beton...............................................................................................................................8 2. Komponen bangunan RISHA.........................................................................................10 D. Peralatan...........................................................................................................................13 E. Pelaksanaan......................................................................................................................14 1. Ketentuan ukuran Panel Struktural ..............................................................................14 2. Pelaksanaan pembuatan panel-panel RISHA................................................................16 3. Penentuan Denah Bangunan Rumah Tipe 36...............................................................22 4. Perakitan Rumah RISHA................................................................................................23 F. Perkiraan Biaya.................................................................................................................35
  • 3. Konstruksi Pracetak untuk Rumah Sederhana 2 DAFTAR GAMBAR Gambar 3. 1 Pencampuran Beton.............................................................................................8 Gambar 3. 2 Pengujian Sederhana Dengan Meletakkan Campuran Beton di tangan ..............8 Gambar 3. 3 Pengujian Sederhana Dengan Menggunakan Cetakan dan Mengukur Selisih Ketinggian dengan Cetakan .......................................................................................................9 Gambar 3. 4 Diameter Kerikil Yang Baik Untuk Campuran Beton.............................................9 Gambar 3. 5 Contoh Semen Tipe 1..........................................................................................10 Gambar 3. 6 Pondasi pelat.......................................................................................................10 Gambar 3. 7 Panel penyambung .............................................................................................10 Gambar 3. 8 panel kolom bertulang.......................................................................................11 Gambar 3. 9 Panel kolom bertulang........................................................................................11 Gambar 3. 10 panel beton bertulang......................................................................................12 Gambar 3. 11 penel dinding.....................................................................................................12 Gambar 3. 12 panel pintu ........................................................................................................12 Gambar 3. 13 panel jendela.....................................................................................................13 Gambar 3. 14 panel ampig.......................................................................................................13 Gambar 3. 15 panel lantai........................................................................................................13 Gambar 5. 1 Penulangan Komponen RISHA P1 .......................................................................14 Gambar 5. 2 Penulangan Komponen RISHA P2 .......................................................................15 Gambar 5. 3 Penulangan Komponen RISHA Panel Penyambung............................................16 Gambar 5. 4 Bentuk Cetakan Kayu Panel P2 ...........................................................................16 Gambar 5. 5 Pelaksanaan Pembuatan Cetakan Panel P1........................................................17 Gambar 5. 6 Bentuk Bekisting Kayu Panel P2..........................................................................17 Gambar 5. 7 Bentuk Cetakan Kayu Panel Sambungan ............................................................18 Gambar 5. 8 Bentuk Cetakan Kayu Panel Sambungan ............................................................18 Gambar 5. 9 ukuran cetakan baja Panel P1.............................................................................19 Gambar 5. 10 Ukuran cetakan baja panel P2 ..........................................................................20 Gambar 5. 11 Bentuk cetakan baja panel sambungan............................................................20 Gambar 5. 12 Perakitan tulangan panel RISHA .......................................................................21 Gambar 5. 13............................................................................................................................23
  • 4. Konstruksi Pracetak untuk Rumah Sederhana 3 Gambar 5. 14 Penempatan patok-patok rumah RISHA...........................................................24 Gambar 5. 15 Galian pondasi..................................................................................................25 Gambar 5. 16 Penempatan Pondasi ........................................................................................26 Gambar 5. 17 Pemasangan panel join kolom terhadap pondasi.............................................27 Gambar 5. 18 Pemasagan balok sloof......................................................................................28 Gambar 5. 19 Pemasangan kolom...........................................................................................29 Gambar 5. 20............................................................................................................................30 Gambar 5. 21............................................................................................................................31 Gambar 5. 22............................................................................................................................32 Gambar 5. 23............................................................................................................................32 Gambar 5. 24 Setelah Pekerjaan Pengurugan dan Pemasangan Lantai..................................33 Gambar 5. 25............................................................................................................................34
  • 5. Konstruksi Pracetak untuk Rumah Sederhana 4 DAFTAR TABEL Tabel 6. 1..................................................................................................................................35 Tabel 6. 2..................................................................................................................................37 Tabel 6. 3..................................................................................................................................40
  • 6. Konstruksi Pracetak untuk Rumah Sederhana 5 KATA PENGANTAR Guna menunjang program pemerintah dalam penyediaan infrastruktur perdesaan, Puslitbang Perumahan dan Permukiman, Badan Penelitian dan Pengembangan, Kementerian Pekerjaan Umum dan Perumahan Rakyat menerbitkan buku panduan sederhana berjudul “Konstruksi Pracetak untuk Rumah Sederhana” dengan tujuan untuk membantu para pelaksana pembangunan rumah sederhana sistem pracetak bagi penduduk perdesaan dalam merencanakan, melaksanakan pekerjaan konstruksi serta memperkirakan biaya secara sederhana. Dalam buku Panduan ini dibahas pengenalan beton sistem pracetak, komponen bangunan Rumah Instan Sederhana Sehat (RISHA), peralatan yang digunakan untuk membuat rumah sederhana sistem pracetak, kemudian penjelasan mengenai ketentuan dalam konstruksi rumah pracetak, mulai ukuran dan pembuatan panel-panel, dan petunjuk perakitan rumah sederhana sistem pracetak (RISHA). Materi dalam Buku Panduan ini telah diuji penerapannya di Desa Sindang Pakuon, Kecamatan Cimanggung, Kabupaten Sumedang, Propinsi Jawa Barat. Namun demikian kami tetap mengharapkan masukan dari Kementerian Desa, Pembangunan Daerah Tertinggal, dan Transmigrasi dan pihak lainnya untuk menyempurnakan buku panduan ini. Jakarta, Oktober 2016 Menteri Pekerjaan Umum dan Perumahan Rakyat Dr. Ir. M Basuki Hadimoeljono, MSc
  • 7. Konstruksi Pracetak untuk Rumah Sederhana 6 A. Pendahuluan 1. Latar Belakang Rumah Instan Sederhana Sehat disingkat Risha merupakan teknologi pracetak yang ditujukan bagi pembangunan perumahan Rumah Sederhana Sehat / RSH, Rumah Swadaya, Rumah Pengungsi serta Rumah Darurat, dengan acuan persyaratan teknis mengacu pada Kepmen Kimpraswi No. 403/KPTS/M/2002 tentang Pedoman Teknis Rumah Sederhana Sehat. Dalam Upaya percepatan pembangunan serta menurunkan biaya produksi Rumah Sederhana Sehat, Risha merupakan penemuan untuk menjawab kedua hal tersebut, yaitu melalui pabrikasi komponen- komponennya dan dirakit dilapangan dengan sistem bongkar pasang atau Konck down System maupun permanen. Sistem knockdown dapat dibangun dengan dinding partisi yang terbuat dari panel-panel yang dipasang dengan baut sehingga dapat dibongkar pasang. Sedangkan, untuk bangunan RISHA permanen, dindingnya dapat dibuat dengan pasangan bata merah, bata ringan, conblock, dan lain-lain. Waktu yang diperlukan untuk merakit satu unit hunian dengan tipe 28,8 m2 adalah 1 hari saja, sehingga Risha ini dapat dipasarkan dengan jargon “Pagi Pesan Sore Huni“. Risha adalah Teknologi Konstruksi Bangunan Rumah Tinggal dengan sistem Pabrikasi pada komponen Struktur, Pengisi maupun Utilitasnya. Komponen struktur menggunakan bahan Beton Bertulang dengan sistem Joint Kering. Komponen rangka struktur atasnya terdiri dari dua komponen, yaitu Komponen Panel Struktur dan Simpul, dari komponen-komponen tersebut sudah dapat membangun rangka bangunan. Panel dinding pengisinya menggunakan tiga jenis Rancangan, yaitu Panel Masif, Panel Kusen Pintu lengkap dengan daun pintunya dan Panel Kusen Jendela lengkap dengan daun jendelanya. Sedangkan, untuk kamar mandi menggunakan Kamar Mandi Sistem Kapsul yang terbuat dari bahan fiber glass dengan konstruksi monolit. Sistem ini diperkenalkan sebagai suatu sistem konstruksi langsung jadi atau Instan yang dapat dibongkar pasang yang dan dikenal sebagai Sistem Rihsa.
  • 8. Konstruksi Pracetak untuk Rumah Sederhana 7 2. Maksud dan Tujuan Maksud dari adanya modul ini adalah peserta diharapkan dapat mengerti dan mampu mengerjakan pembangunan rumah sederhana dengan menggunakan teknologi RISHA. Sedangkan, tujuan dari modul ini adalah untuk memberikan panduan kepada masyarakat agar dapat mewujudkan bangunan rumah tinggal tunggal dengan teknologi RISHA yang aman terhadap dampak kerusakan yang diakibatkan oleh bencana gempa bumi. a. Sumber-sumber Referensi 1. Pedoman Teknis Teknologi RISHA 2. Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat No. 5/PRT/M/2016. B. Gambaran Teknologi Risha adalah kependekan dari Rumah Instan Sederhana Sehat, yaitu rumah tinggal dengan menerapkan teknologi konstruksi sistem pracetak kecil, dengan sistem sambungan kering. Tinjauan teknis dan kompetensi teknologi RISHA adalah sebagai berikut: a. Percepatan b. Kesederhanaan c. Fleksibilitas d. Ramah lingkungan dan mengakomodasi material lokal e. Kekuatan dan durabilitas f. Berkualitas C. Bahan Rumah Instan Sederhana sehat terdiri dari komponen-komponen yang dibuat di pabrik. Pada saat perakitannya, seluruh komponen dan peralatan bantu untuk perakitan harus sudah tersedia di tempat dimana bangunan ini akan dibangun. Seluruh komponen yang terbuat dari beton bertulang harus sudah mencapai umur 28 hari dengan kekuatan tekan minimum 250 kg/cm2. Seluruh komponen yang mengunakan bahan
  • 9. Konstruksi Pracetak untuk Rumah Sederhana 8 kayu harus kering dan telah diserut hingga permukaan kayu tersebut rata dan halus dengan ukuran yang akurat sesuai dengan yang diperlukan atau sesuai dengan gambar rencana. 1. Beton Beberapa hal yang harus diperhatikan dalam membuat campuran beton adalah: 1. Campuran beton terdiri dari 1 semen : 2 pasir : 3 kerikil : 0,5 air. Perlu diperhatikan penambahan air dilakukan sedikit demi sedikit dan disesuaikan agar beton dalam keadaan pulen (tidak terlalu encer dan tidak terlalu kental). 1 semen : 2 pasir : 3 kerikil air secukupnya dituang sedikit demi sedikit Gambar 3.1 Pencampuran Beton Gambar 3.2 Pengujian Sederhana Dengan Meletakkan Campuran Beton di tangan
  • 10. Konstruksi Pracetak untuk Rumah Sederhana 9 Gambar 3.3 Pengujian Sederhana Dengan Menggunakan Cetakan dan Mengukur Selisih Ketinggian dengan Cetakan 2. Ukuran kerikil yang baik maksimum 20 mm dengan gradasi yang baik. Gambar 3.4 Diameter Kerikil Yang Baik Untuk Campuran Beton
  • 11. Konstruksi Pracetak untuk Rumah Sederhana 10 3. Semen yang digunakan adalah semen tipe 1 yang berkualitas sesuai dengan Standar Nasional Indonesia (SNI). Gambar 3.5 Contoh Semen Tipe 1 2. Komponen bangunan RISHA Rumah instan sederhana sehat tipe -1 (RIT-1) terdiri beberapa komponen yang dibuat secara pabrikasi. Satu unit RIT – 1 terdiri dari komponen-komponen: 4. Pondasi pelat, berukuran 65 x 65 cm, dengan tinggi 12 cm, 6 unit. Gambar 3.6 Pondasi pelat 5. Panel penyambung, bentuk “L” 30.30.30.10 cm, 16 panel. Gambar 3.7 Panel penyambung SNI 2049-2015
  • 12. Konstruksi Pracetak untuk Rumah Sederhana 11 6. Panel kolom beton bertulang, berukuran 30 x 120 x 10 cm, 20 panel, Gambar 3.8 panel kolom bertulang 7. Panel kolom beton bertulang, berukuran 20 x 120 x 10 cm, 12 panel, Gambar 3.9 Panel kolom bertulang
  • 13. Konstruksi Pracetak untuk Rumah Sederhana 12 8. Panel balok beton bertulang, berukuran 30 x 120 x 10 cm, 28 panel, Gambar 3.10 panel beton bertulang 9. Panel dinding, berukuran 120 x 240 cm, 5 panel. Gambar 3.11 penel dinding 10. Panel Pintu (lengkap dengan daun pintu), 2 panel, Gambar 3.12 panel pintu
  • 14. Konstruksi Pracetak untuk Rumah Sederhana 13 11. Panel jendela (lengkap dengan daun jendela), 1 panel. Gambar 3.13 panel jendela 12. Panel ampig, 4 panel. Gambar 3.14 panel ampig 13. Panel lantai berukuran 20 x 20 cm, 18 m2, Gambar 3.15 panel lantai D. Peralatan Peralatan yang digunakan untuk pekerjaan pembangunan rumah RISHA adalah peralatan pertukangan dan pendukung-pendukungnya dengan masing-masing fungsinya disesuaikan untuk mewujudkan pendetailan konstruksi rumah RISHA yang akan dibahas pada bab selanjutnya.
  • 15. Konstruksi Pracetak untuk Rumah Sederhana 14 100 100 Besi 2x2  8 mm Besi 1x2  8 mm Besi  6 mm Besi  6 mm - 8 bh Besi  8 mm - 4 bh Besi  6 mm - 8 bh 1170 1200 60 300 300 45 300 75 84 187 243 84 45 80 69 100 60 80 100 100 210 260 36 26 275 275 Besi  8 mm - 2 bh 80100100210206 275 70 70 75 25 JUDUL GAMBAR : DIRENCANAKAN : DIGAMBAR : DISETUJUI : TANGGAL : GIN No. Gambar PUSAT LITBANG PERMUKIMAN - BALITBANG PU KETERANGAN : PENULANGAN PANEL RISHA TIPE-2 1200 1170 TAMPAK ATAS RANGKAIAN TULANGAN PANEL TAMPAK SAMPING RANGKAIAN TULANGAN PANEL DETAIL TULANGAN UTAMA 01 E. Pelaksanaan 1. Ketentuan ukuran Panel Struktural Panel Struktural Risha mempunyai ukuran tebal 2 cm, lebar 30 cm, tinggi 120 cm yang dikelilingi frame ukuran 6 cm x 10 cm, yang dilengkapi dengan lubang untuk angker pada framenya dengan diameter lubang sebesar 16 mm, masing-masing sisi sebanyak 2 buah dengan jarak antar as lubang 13,5 cm untuk kearah pendek yang ditempatkan pada as panel dan untuk yang kearah tinggi 15 cm diukur dari ujung frame sampai dengan as lubang. Gambar 5.1 Penulangan Komponen RISHA P1
  • 16. Konstruksi Pracetak untuk Rumah Sederhana 15 Gambar 5.2 Penulangan Komponen RISHA P2 100 100 Besi 2x2  8 mm Besi 1x2  8 mm Besi  6 mm Besi  6 mm Besi  8 mm @ 2 bh Besi  6 mm - 6 bh 1170 1200 60 1200 45 75 84 84 45 100 60 80 100 100 210 1170 36 275 Besi  8 mm - 2 bh 80100100210206 275 70 70 160 200 200 200 200 80 86 50 45 70 40 178 86 50 70 40 178 6 Bh 2 Bh 86 145 86 145 36 300 JUDUL GAMBAR : DIRENCANAKAN : DIGAMBAR : DISETUJUI : TANGGAL : GIN No. Gambar PUSAT LITBANG PERMUKIMAN - BALITBANG PU KETERANGAN : TAMPAK ATAS RANGKAIAN TULANGAN PANEL TAMPAK SAMPING RANGKAIAN TULANGAN PANEL DETAIL TULANGAN UTAMA PENULANGAN PANEL RISHA TIPE-2 02
  • 17. Konstruksi Pracetak untuk Rumah Sederhana 16 Gambar 5.3 Penulangan Komponen RISHA Panel Penyambung 2. Pelaksanaan pembuatan panel-panel RISHA 1. Pembuatan Cetakan Kayu a) Dimensi dan bentuk cetakan untuk panel P-1 adalah sebagai berikut: Gambar 5.4 Bentuk Cetakan Kayu Panel P2 TAMPAK PEMBESIAN PANEL TAMPAK PANEL PENGHUBUNG PERSPEKTIF PANEL PENGHUBUNG 300 100 300 100 50 50 200 300 135135 82.5 82.5 60 5050 82.5 300 200100 300 82.582.5 82.5 300 200100 135 135 300 CETAKAN PANEL PENGHUBUNG PENAMPANG PANEL PENGHUBUNG 300 60 60 5050 60 13582.5 100 200100 300
  • 18. Konstruksi Pracetak untuk Rumah Sederhana 17 Gambar 5.5 Pelaksanaan Pembuatan Cetakan Panel P1 b) Dimensi dan bentuk cetakan panel P2 Gambar 5.6 Bentuk Bekisting Kayu Panel P2
  • 19. Konstruksi Pracetak untuk Rumah Sederhana 18 c) Dimensi dan bentuk cetakan panel join Gambar 5.7 Bentuk Cetakan Kayu Panel Sambungan Gambar 5.8 Bentuk Cetakan Kayu Panel Sambungan
  • 20. Konstruksi Pracetak untuk Rumah Sederhana 19 2. Pembuatan Cetakan Besi Baja Semua baja yang dipakai harus menggunakan minimal U 24 dengan ketentuan berupa profil ( [ ) kanal dengan ukuran [ 100 x 50 x 5 mm, dan pelat baja sebagai dasar cetakan tebal 5 mm yang memenuhi persyaratan yang tercantum dalam buku Tabel Profil Konstruksi Baja. Baut dan Mur yang digunakan sebagai pengunci antar panel yaitu ukuran diameter 8 mm. Pralon yang digunakan adalah pralon listrik diameter 5/8 inchi. Pelat baja dengan tebal 2 mm dan ukurannya 4 x 6 cm dan diberi lubang di tengah – tengahnya dengan diameter 5/8 inchi, yang digunakan sebagai pengaku lubang pralon. Gambar 5.9 ukuran cetakan baja Panel P1
  • 21. Konstruksi Pracetak untuk Rumah Sederhana 20 Gambar 5.10 Ukuran cetakan baja panel P2 Gambar 5.11 Bentuk cetakan baja panel sambungan 3. Perakitan Tulangan Tulangan dirakit sedemikian sehingga sesuai dengan gambar teknis penulangan panel RISHA. Lubang-lubang baut harus disediakan dengan cara memasang pipa- pipa pada titik-titik baut.
  • 22. Konstruksi Pracetak untuk Rumah Sederhana 21 Gambar 5.12 Perakitan tulangan panel RISHA 4. Pelaksanaan Pengecoran dan Pemadatan Pengecoran dilakukan secara perlahan mulai dari bagian framenya dan dilakukan penggetaran dengan vibrator dalam arah vertikal, sehingga beton mengalami pemadatan yang maksimal, dengan memperhatikan batas waktu penggetaran jangan sampai terjadi pemisahan campuran beton. 5. Pembukaan Cetakan Cetakan dapat dibuka setelah 24 jam dari waktu pengecoran, dengan cara perlahan dan hati-hati.
  • 23. Konstruksi Pracetak untuk Rumah Sederhana 22 3. Penentuan Denah Bangunan Rumah Tipe 36 Gambar 5.13 3,003.00 3,00 1.50 6.00 Kamar Tidur ± 0.00 3,00 6.00 1.50 Kamar Tidur ± 0.00 Ruang Tengah ± 0.00 KM/WC - 0.10 A TERAS - 0.05 TERAS - 0.05 MejaDapur B
  • 24. Konstruksi Pracetak untuk Rumah Sederhana 23 Gambar 5.14 4. erakitan Rumah RISHA 1. Pengukuran dan penempatan patok-patok. Penempatan patok-patok dilakukan untuk memberikan kepastian dan kesikuan konstruksi bangunan RISHA. Jarak-jarak lahan yang dipatok deisesuaikan dengan luas denah dan ketersediaan lPahan. DENAH A B 3,003.00 3,00 1.50 6.00 3,00 6.00 1.80 Kamar Tidur ± 0.00 Teras Blkng - 0.10 MejaDapur Teras - 0.10 0.60 C Ruang Tamu ± 0.00 Ruang Keluarga ± 0.00 Dapur ± 0.00 Kamar Tidur ± 0.00 KM/WC - 0.20
  • 25. Konstruksi Pracetak untuk Rumah Sederhana 24 Gambar 5.15 Penempatan patok-patok rumah RISHA Sisi atas dari papan duga di ratakan dengan menggunakan ketam sehingga permukaan ini halus dan benar-benar horisontal.
  • 26. Konstruksi Pracetak untuk Rumah Sederhana 25 2. Penggalian pondasi. Gali tanah untuk pondasi dengan mengikuti pola galian pondasi hingga kedalaman 20 cm dari permukaan tanah yang telah diratakan dan dibersikan dari akar rumput. Titik fondasi disesuaikan dengan as bagian-bagian bangunan yaitu as balok dan kolom serta ukuran panel-panel RISHA. Gambar 5.16 Galian pondasi
  • 27. Konstruksi Pracetak untuk Rumah Sederhana 26 3. Pemasangan Pondasi a) Hamparkan pasir urug pada galin pondasi dan padatkan sehingga diperoleh tebal padat pasir urug dibawah pondasi 8 cm. b) Tempatkan pondasi pelat pada masing-masing galian dan atur sedemikian sehingga baut yang tertanam pada pondasi ini sejajar dengan benang as dinding bangunan baik pada arah lebar maupun pada arah panjang bangunan. Gambar 5.17 Penempatan Pondasi Lubang pondasi Pondasi, digeser kekakanan dan ke kiri sedemikian sehingga baut yang tertanam pada pondasi tepat berada atau sejajar dengan benang as dinding bangunan Benang as dinding bangunan
  • 28. Konstruksi Pracetak untuk Rumah Sederhana 27 4. Pemasangan Panel Penyambung pada Pondasi a) Pasang panel-panel penyambung pada setiap pondasi, dengan cara masukan baut-baut yang ada di pondasi pada lubang yang tersedia pada panel penyambung. b) Pastikan baut yang digunakan adalah baut-baut yang segaris dengan benang as dinding bangunan. c) Kencangkan mur pada setiap baut penyambung hingga ½ kekuatan dari yang seharusnya. Gambar 5.18 Pemasangan panel join kolom terhadap pondasi
  • 29. Konstruksi Pracetak untuk Rumah Sederhana 28 5. Pemasangan Balok Sloof Gambar 5.19 Pemasagan balok sloof 6. Pemasangan Kolom
  • 30. Konstruksi Pracetak untuk Rumah Sederhana 29 Gambar 5.20 Pemasangan kolom 7. Pemasangan Balok Atas a) Sebelum sambungan pada kolom-kolom dikencangkan penuh, pasang panel-panel penyambung untuk selanjutnya memasang panel-panel balok atas (ring balok). Sambungan diberi kekuatan setengah penuh hingga panel-panel penyambung dan panel ring balok terpasang seluruhnya. b) Gunakan perancah dan tangga dalam pemasangan panel-panel ini untuk memudahkan dalam pemasangannya secara lurus dan horisontal. c) Kencangkan seluruh penyambung hingga mencapai kekuatan penuh sambil terus menerus di cek dengan mengunakan alat water-pass pada setiap panel yang sedang dikencangan.
  • 31. Konstruksi Pracetak untuk Rumah Sederhana 30 Gambar 5.21 8. Pemasangan Ampig, Kuda-kuda dan Goring a) pasang panel kolom pada kolom tengah dari bangunan, kencangkan dengan menggunakan mur baut, kemudia pasang kaki kuda-kuda dari kayu 5/10 cm dan gunakan baut untuk sambungan kaki kuda-kuda dengan kolom dan balok (pada kaki kuda-kuda sudah tersedia lubang baut yag sesuai dengan lubang pada kolom dan balok). b) Pasang gording kayu 5/10 dengan menggunakan sambungan paku.
  • 32. Konstruksi Pracetak untuk Rumah Sederhana 31 Gambar 5.22 9. Pemasangan Penutup Atap dan Lisplang Pasang penutup atap sebelum pekerjaan pemasangan dinding dan pekerjaan lantai, bila mengunakan penutup atap asbes gelombang, disarankan gunakan alat penghubung yang mudah dilepas tanpa merusak asbesnya sendiri. Bila mengunakan penutup atap genteng (baik keramik maupun beton) pasang terlebih dahulu kaso 5/7 dan reng ¾. Gordin g 5/10 cm Ka ki ku da- ku da
  • 33. Konstruksi Pracetak untuk Rumah Sederhana 32 Gambar 5.23 10. Pengurugan dan pemasangan lantai a) Pekerjaan pengurugan dan pemadatan dilakukan mengikuti SNI 03 - ....- .....dengan tebal padat 20 cm. b) Sebarkan pasir urug dan padatkan hingga menapai tebal padat 5 cm. c) Pasang lantai paving blok 20/20 cm dari bahan campuran .........tanpa adukan spesi. Gambar 5.24 Lantai paving blok 20/20 cmPasir urug padat 5 cmUrugan tanah tebal padat 10 cm Balok sloof 10x30x120 cm Lantai di dalam bangunan Lantai teritisan disekeliling bangunan
  • 34. Konstruksi Pracetak untuk Rumah Sederhana 33 Gambar 5.25 Setelah Pekerjaan Pengurugan dan Pemasangan Lantai
  • 35. Konstruksi Pracetak untuk Rumah Sederhana 34 11. Pemasangan panel dinding, panel jendela, panel pintu dan panel ampig Gambar 5.26 12. Pemasangan Daun Pintu dan Jendela Daun pintu dan jendela telah terpasang pada panel, yang perlu dilakukan hanya pekerjaa pengaturan dan penyesuaian agar pintu dan jendela dapat dibuka dan ditutup dengan mudah, dan pemasangan kaca pada jendela.
  • 36. Konstruksi Pracetak untuk Rumah Sederhana 35 F. Perkiraan Biaya Tabel 6. 1 No Uraian Pekerjan/Komponen Qty Sat Harga Komp./ Harga Pekerjaan (Rp) Jumlah (Rp) I Pek Persiapan 3.987.207,60 1 Pembersihan Site ( 14 X 9.50 ) m2 133,00 m2 7.590,00 1.009.470,00 2 Gudang/Direksi Keet (1 unit per 10 unit rumah) 9,00 m2 100.000,00 900.000,00 3 Pemasangan Bouwplank 22,00 m1 76.260,80 1.677.737,60 4 Papan nama Proyek 1,00 unit 400.000,00 400.000,00 II Pek Galian dan timbunan 4.569.316,95 1 Galian Tanah Biasa u/ pondasi setempat 11,52 m3 89.760,00 1.034.035,20 2 Timbunan tanah kembali 3,84 m3 121.550,00 466.752,00 3 Timbunan dgn pasir urug, di bwh lantai 25,25 m3 121.550,00 3.068.529,75 II Pek Pondasi 7.784.584,46 1 Pondasi setempat, pas. batu belah, camp 1 : 5 7,10 m3 698.121,16 4.956.660,24 2 Aanstamping t = 20 cm (di bwh pond setempat) 1,76 m3 330.983,40 582.530,78 3 Pond. menerus, pas. batu belah, camp 1 : 5 2,60 m3 698.121,16 1.815.115,02 4 Aanstamping t = 20 cm (di bwh pond menerus) 1,30 m3 330.983,40 430.278,42 III Pek Beton K-250 1.918.000,00 1 Kolom Praktis 10/10 (beton Bertulang) 0,29 m3 3.500.000,00 1.008.000,00 2 Balok Sloof dan ringbalk 10/12 (Beton 0,26 m3
  • 37. Konstruksi Pracetak untuk Rumah Sederhana 36 No Uraian Pekerjan/Komponen Qty Sat Harga Komp./ Harga Pekerjaan (Rp) Jumlah (Rp) bertulang) 3.500.000,00 910.000,00 IV LANTAI 13.492.544,78 1 Keramik 30 x 30, Termasuk teras, 2 * (0,60 x 3) 75,60 m2 167.401,30 12.655.538,28 2 Keramik lantai KM 30 x 30 5,00 m2 167.401,30 837.006,50 3 Keramik dinding KM 25 x 30, tinggi 90 cm 10,00 m2 167.401,30 1.674.013,00 V Struktur Rangka Panel RISHA 39.156.000,00 A Balok Lantai 0.00 s.d - 0 30 1 Panel Tipe I, P1 (30 x 120) 44,00 bh 120.000,00 5.280.000,00 2 Komponen Simpul P3, (30 x 30) 32,00 bh 100.000,00 3.200.000,00 3 Angkur, Φ 12, panjang 40 cm 64,00 bh 14.000,00 896.000,00 B Kolom (+ 0,00 ) sampai (+ 2.40) 1 Panel Tipe I, P1 (30 x 120) 64,00 bh 120.000,00 7.680.000,00 2 Panel Tipe II, P2 (20 x 120) 64,00 bh 110.000,00 7.040.000,00 C Pembalokan (+ 2.40) - (+2.70) / Ringbalk 1 Panel Tipe I, P1 (30 x 120) 24,00 bh 120.000,00 2.880.000,00 2 Komponen Simpul P3, (30 x 30) 32,00 bh 100.000,00 3.200.000,00 D Pembalokan (+ 2.70) - (+5.00) / Ringbalk 1 Panel Tipe I, P1 (30 x 120) 28,00 bh 120.000,00 3.360.000,00 2 Komponen Simpul P3, (30 x 30) 16,00 bh 120.000,00 1.920.000,00 E Baut - Mur - Plat penyambung 1 Mur Baut Hitam HTB, 12+ plat penyambung 1000 bh 3.700,00 3.700.000,00
  • 38. Konstruksi Pracetak untuk Rumah Sederhana 37 No Uraian Pekerjan/Komponen Qty Sat Harga Komp./ Harga Pekerjaan (Rp) Jumlah (Rp) VI Dinding 38.014.475,84 1 Pasangan bata merah 1/2 bt 87,00 m2 176.900,68 15.390.359,16 2 Plesteran tebal, t = 1.5 cm 151,00 m2 91.045,68 13.747.897,68 3 Acian PC (dinding yang diplester) 151,00 m2 29.386,50 4.437.361,50 4 Pas Bata merah ampig 28,00 m2 122.276,00 3.423.728,00 5 Plesteran ampig tebal, t = 1.5 cm 15,00 m2 38.288,80 574.332,00 6 Acian PC (dinding yang diplester) 15,00 m2 29.386,50 440.797,50 Tabel 6. 2 No Uraian Pekerjan/Komponen Qty Sat Harga Komponen/ Harga Pekerjaan (Rp) Jumlah (Rp) VII Pek Kusen Pintu dan jendela 10.995.778,00 1 Rangka Kusen Pintu, (PNT-1), 2,00 bh 450.000,00 900.000,00 2 Panel Daun Pintu dobel triplek, (PNT-1) 2,00 bh 317.889,00 635.778,00 3 Rangka Kusen Pintu, (PNT-2), 6,00 bh 450.000,00 2.700.000,00 4 Panel Daun Pintu dobel triplek, (PNT-2) 6,00 bh 400.000,00 2.400.000,00 5 Rangka Kusen Jendela, JD -1 2,00 bh 600.000,00 1.200.000,00 6 Rangka Kusen Jendela, JD -2 (tidak ada) - bh 500.000,00 - 7 Daun Jendela (JD-1)+(JD-2),+ kaca polos, 5 mm 4,00 bh 500.000,00 2.000.000,00 8 Pintu KM/WC, Fiber, lengkap 2,00 bh 260.000,00 520.000,00 9 Glass block (KM dan Dapur), (4 bhx 2), 2 bh 16,00 bh 40.000,00 640.000,00
  • 39. Konstruksi Pracetak untuk Rumah Sederhana 38 No Uraian Pekerjan/Komponen Qty Sat Harga Komponen/ Harga Pekerjaan (Rp) Jumlah (Rp) VIII Rangka Atap 18.460.000,00 1 Konstruksi Kuda-Kuda Baja ringan, 142,00 m2 130.000,00 18.460.000,00 IX Penutup Atap 8.555.000,00 1 Lembaran asbes gelombang + Bubungan 142,00 m2 50.000,00 7.100.000,00 2 List plank, GRC, t : 4 mm, lebar 30 cm 58,20 m1 25.000,00 1.455.000,00 X Pek Gantungan Kunci dan lain-lain 1.660.000,00 1 Engsel Pintu 8,00 psng 30.000,00 240.000,00 2 Kunci Pintu, 2 track, setara Bremen 8,00 bh 90.000,00 720.000,00 3 Slot pintu, panjang 6 cm 8,00 bh 25.000,00 200.000,00 4 Pegangan Pintu, (Pintu depan dan belakang) 4,00 bh 45.000,00 180.000,00 5 Engsel Jendela 4,00 psng 30.000,00 120.000,00 6 Slot Jendela 4,00 bh 25.000,00 100.000,00 7 Hak angin jendela 4,00 bh 25.000,00 100.000,00 XI Pekerjaan Langit-langit (Plafon) 20.231.164,80 1 Rangka langit-langit, kayu 5/7 . ukuran Rangka langit-langit 60 x 60 cm 126,00 m2 122.276,00 15.406.776,00 2 Penutup langit-langit, GRC plat, t = 4 mm 126,00 m2 38.288,80 4.824.388,80 XII Pek Listrik 5.980.000,00 1 Meteran Listrik, Pulsa,kwh : 900 watt Plus 3 titik lampu dari PLN 2,00 unit 1.400.000,00 2.800.000,00 2 Saklar, Stop kontak termasuk kabel 22,00 ttk 100.000,00 2.200.000,00
  • 40. Konstruksi Pracetak untuk Rumah Sederhana 39 No Uraian Pekerjan/Komponen Qty Sat Harga Komponen/ Harga Pekerjaan (Rp) Jumlah (Rp) 3 Lampu TL, 20 Watt 12,00 bh 40.000,00 480.000,00 4 Arde 2,00 bh 250.000,00 500.000,00 XIII Pekerjaan Pengecatan 6.572.415,19 1 Cat dinding/cat tembok 151,00 m2 15.365,90 2.320.250,90 2 Cat dinding GRC, ampig 28,00 m2 15.365,90 430.245,20 3 Cat Kayu 36,00 m2 39.963,00 1.438.668,00 4 Cat Listplank 29,10 m2 15.365,90 447.147,69 5 Cat Plafon/langit-langit 126,00 m2 15.365,90 1.936.103,40 XIV Pekerjaan KM dan perpipaan 8.881.458,80 1 Kloset jongkok 2,00 unit 295.629,40 591.258,80 2 Floor drain 2,00 bh 34.540,00 69.080,00 3 Kran Air D 3/4" 4,00 bh 18.000,00 72.000,00 4 Pipa PVC, D 3/4 18,00 m1 9.660,00 173.880,00 5 Pipa PVC, D 3" 18,00 m1 54.180,00 975.240,00 6 Biofil, ukuran untuk keluarga 1,00 unit 7.000.000,00 7.000.000,00 7 Bidang Resapan 1,00 unit - -
  • 41. Konstruksi Pracetak untuk Rumah Sederhana 40 Tabel 6. 3 No Uraian Pekerjan/Komponen Qty Sat Harga Komponen/ Harga Pekerjaan (Rp) Jumlah (Rp) XV Pekerjaan Perakitan Komponen Risha 3.040.000,00 1 Pemasangan Panel-Panel 304,00 Pcs 10.000,00 3.040.000,00 2 Biaya pengiriman panel dari workshop ke lokasi ls - - 3 Transport pekerja ke lokasi (PP) 4,00 org 400.000,00 1.600.000,00 XVI Pekerjaan penyelesaian 500.000,00 1 Pembersihan Lapangan 1,00 m2 500.000,00 500.000,00 Jumlah (1) 132.846.709,62 Keuntungan pemborong 12.5 % 16.605.838,70 Jumlah (2) 149.452.548,32 PPN, 10 % 14.945.254,83 Jumlah Total 164.397.803,15 Pembulatan 164.390.000,00
  • 42. Konstruksi Pracetak untuk Rumah Sederhana 41