SlideShare a Scribd company logo
1 of 21
HVDC MATIARI -LAHORE
TRANSMISSION PROJECT
MUHAMMAD FAZIL MEMON
PRESENTED TO:
ENGR.ZUHAIB MUKHTIAR
SEQUENCEOFPRESENTATION
OVERVIEW
THAR COAL BASED POWER GENERATION POTENTIAL
UPCOMING POWER GENERATION IN SOUTH – PRESENT
SCENARIO
SCOPE OF HVDC MATIARI – LAHORE PROJECT
CONVERTOR STATIONS LOCATIONS
HVDC MATIARI – LAHORE TRANSMISSION LINE
COMPLETOIONS TIME LINE
PROJECT MANAGEMENT UNIT
OPERATOR
EMPLOYMENT
ADDITIONAL PROJECT INFORMATION
OVERVIEW
• The 878 kilometres long HVDC transmission line from Matiari to Lahore is the first of its kind
in Pakistan.
• This HVDC transmission line project is being developed under the framework of China-Pakistan
Economic Corridor (CPEC) agreement with the main investor being China Electric Power
Equipment & Technology (CET).
• This transmission line will have 4,000 MW capacity at 660 kV voltage. The project is designed to
have bi-pole HVDC technology, three repeater stations, two grounding electrode stations and two
converter stations, one at the each end of the line - Matiari (Interior Sindh) and Lahore.
THAR COAL BASED POWER GENERATION
POTENTIAL
NATIONAL POWER SYSTEM EXPANSION PLAN FOR THE PERIOD
2011-2030 ENVISAGES DEVELOPMENT OF THAR COAL FIELD UPTO
40000 MW
YEAR 2011 COAL POWER GENERATION SCENARIO.
500 KV D/C THAR – MATIARI YEAR 2015-16 INSTALLED CAPACITY
1200 MW (THAR), 1200 MW (IMPORTED COAL AT KARACHI)
500 KV AC IN / OUT FROM EXISTING 500 KV HUB-JAMSHORO LINE
YEAR 2017-18 REACH TO 4000 MW
WHAT NEXT OPTIONS FOR EVACUATION OF POWER
UPCOMINGPOWERGENERATIONIN
SOUTH– PRESENTSCENARIO
THAR COALFIRED PROJECT 660 MW
BIN QASIM IMPORTED COALPOWER 1320 MW
PLANT
SSRLTHAR COALPOWER PLANT 1320 MW
HUBCO COALFIRED POWER PROJECT 1320 MW
SIDDIQUE SONS COALPOWER PLANT 330 MW
Contd.
• + 660 kV HVDC Bipole T/Line from Matiari to Lahore
(about 870 KM).
• HVDC Converter &Switching Control Stations at
Matiari &Lahore
• Transmission capability of Power - 4000 MW
16
• CONVERTOR STATION MATIARI SITE – NATIONAL
HIGHWAY, ABOUT 8 KM NORTH MATIARI VILLAGE
SIAKHART.
• CONVERTOR STATION LAHORE – PHOOL NAGAR
MORE KHUNDA ROAD 4 KM WEST HEAD BALLOKI
VILLAGEWAIZIR,ABOUT 60 KM TO LAHORE.
17
- ABOUT 870 KM
- IN SINDH PROVINCE, PASSES THROUGH
DISTRICTS OF MATIARI, SANGHAR, KHAIRPUR,
SUKKUR, GHOTKI (ABOUT 320 KM)
- IN PUNJAB PASSES
YAR
NAGAR,
THROUGH
KHAN,
PAK
DISTRICTS OF
BAHAWALPUR,
PROVINCE,
RAHIM
BAHAWAL
PATTAN, OKARA, KASUR,
(ABOUT 550 KM).
NANKANA
19
20
21
INTERCONNECTION SCHEME ATMATIARI
INTERCONNECTION SCHEME ATLAHORE
As per Cooperation Agreement Between State Grid China
and NTDC (20.04.2015):
• Feasibility study to be finalized by SGCC/CET upto end
of July, 2015
• Design completed upto December, 2015
• Construction period 24 months after design finalized
26
• Abdur Razzaq Cheema
Ex-GM GSC/Consultant
Team Leader
• Anjum Aziz
Manager (GSC)
Coordinator
• Tariq Shafi
Manager (EHV-I)
Progress Monitoring
• Muhammad Shabbir
Dy. GM Finance (WPPO)
Commercial Team Leader
27
OPERATOR
• China Electric Power Equipment and Technology Co. Ltd. (CET) is a wholly owned subsidiary
of State Grid Corporation of China (SGCC). CET is the operation platform and implementer of
SGCC in carrying out international Engineering-Procurement-Construction (EPC) business.
• CET will operate the Matiari-Lahore Transmission Line for 25 years and will transfer it afterwards
to the National Transmission and Dispatch Company (NTDC), the Pakistani government-owned
power transmission company.
• CET is under discussion to provide further transmission lines to Pakistan, such as one between Port
Qasim and Faisalabad.
EMPLOYMENT
• It is planned that during the 1-5th year the main employees in converter stations shall be skilled
Chinese. After a overhaul in the 15th year, there shall be only a few Chinese engineers (estimated 10-
12 persons) for each station to supervise and from the 21st year onwards local employees would
work independently in the converter stations.
ADDITIONAL PROJECT INFORMATION
• The Matiari-Lahore Transmission Line will transfer mainly electricity generated from coal power
projects such as Engro Thar Coal Power Projectand Port Qasim Power Project.
• The transmission line will have a 25-year operational life and afterwards will be transferred to
the National Transmission and Dispatch Company (NTDC), the Pakistani government-owned power
transmission company, which owns all existing transmission lines in Pakistan.
• For executing the Matiari-Lahore line, the government has already handed over two chunks of land
for building and installing two convertor stations (one in Matiari for converting alternate current
(AC) to direct current (DC) and another near Lahore for conversion of DC to AC) to the Chinese
company.
• Issues of system stability with proposed induction of HVDC
Transmission Scheme.
• Protection &Control
• Telecom / SCADA
• System losses (Permissible / Recommended)
• Standards / controlling specifications adopted internationally
dealing with:
• Availability of System
• Noise level / ROW
• Sending End / Receiving End System Topology
• Central Control Mechanism at NPCC for System Stability
• Lenders’ concern-Insurance of T/Line Section 29
HVDC MATIARI -LAHORE  TRANSMISSION PROJECT

More Related Content

What's hot

Hybrid AC/DC microgrid and Electric Vehicles
Hybrid AC/DC microgrid and Electric VehiclesHybrid AC/DC microgrid and Electric Vehicles
Hybrid AC/DC microgrid and Electric Vehicles
Md Shamiur Rahman
 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
sushrut p
 

What's hot (20)

Protection and control of Microgrid
Protection and control of MicrogridProtection and control of Microgrid
Protection and control of Microgrid
 
ppt on industrial training of final year studen from ptcul 132kv substation ...
ppt on industrial training of final year studen  from ptcul 132kv substation ...ppt on industrial training of final year studen  from ptcul 132kv substation ...
ppt on industrial training of final year studen from ptcul 132kv substation ...
 
Hvdc transmission & its applications
Hvdc transmission & its applicationsHvdc transmission & its applications
Hvdc transmission & its applications
 
Testing of circuit breakers
Testing of circuit breakersTesting of circuit breakers
Testing of circuit breakers
 
Smart grid presentation
Smart grid  presentationSmart grid  presentation
Smart grid presentation
 
VSC based HVDC system
VSC based HVDC systemVSC based HVDC system
VSC based HVDC system
 
Role of substation in smart grid
Role of substation in smart grid Role of substation in smart grid
Role of substation in smart grid
 
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
 
Hybrid AC/DC microgrid and Electric Vehicles
Hybrid AC/DC microgrid and Electric VehiclesHybrid AC/DC microgrid and Electric Vehicles
Hybrid AC/DC microgrid and Electric Vehicles
 
HVDC benefits and types
HVDC benefits and typesHVDC benefits and types
HVDC benefits and types
 
statcom
statcomstatcom
statcom
 
MTDC SYSTEMS
MTDC SYSTEMSMTDC SYSTEMS
MTDC SYSTEMS
 
A Hybrid Wind and Solar Energy System with Battery Energy Storage for an Isol...
A Hybrid Wind and Solar Energy System with Battery Energy Storage for an Isol...A Hybrid Wind and Solar Energy System with Battery Energy Storage for an Isol...
A Hybrid Wind and Solar Energy System with Battery Energy Storage for an Isol...
 
Solar Power Based Micro Grid Systems.pptx
Solar Power Based Micro Grid Systems.pptxSolar Power Based Micro Grid Systems.pptx
Solar Power Based Micro Grid Systems.pptx
 
Methods for Voltage Stability Enhancement
Methods for Voltage Stability EnhancementMethods for Voltage Stability Enhancement
Methods for Voltage Stability Enhancement
 
Load forecasting
Load forecastingLoad forecasting
Load forecasting
 
NEW STATCOM CONTROL SCHEME FOR POWER QUALITY IMPROVEMENT IN WIND FARM.
NEW STATCOM CONTROL SCHEME FOR POWER QUALITY IMPROVEMENT IN WIND FARM.NEW STATCOM CONTROL SCHEME FOR POWER QUALITY IMPROVEMENT IN WIND FARM.
NEW STATCOM CONTROL SCHEME FOR POWER QUALITY IMPROVEMENT IN WIND FARM.
 
An Overview Of Power Quality
An Overview Of Power QualityAn Overview Of Power Quality
An Overview Of Power Quality
 
Upfc & fact
Upfc & factUpfc & fact
Upfc & fact
 
220kv grid wapda town lahore
220kv grid wapda town lahore220kv grid wapda town lahore
220kv grid wapda town lahore
 

Similar to HVDC MATIARI -LAHORE TRANSMISSION PROJECT

800kv multiterminal system in india
800kv multiterminal system in india800kv multiterminal system in india
800kv multiterminal system in india
alpna1808
 
presentation-by-pgcil-development-of-transmission-system-in-india-foir-worksh...
presentation-by-pgcil-development-of-transmission-system-in-india-foir-worksh...presentation-by-pgcil-development-of-transmission-system-in-india-foir-worksh...
presentation-by-pgcil-development-of-transmission-system-in-india-foir-worksh...
WondererBack
 
Presentation on two major hydro electric power plants in india
Presentation on two major hydro electric power plants in indiaPresentation on two major hydro electric power plants in india
Presentation on two major hydro electric power plants in india
Saikat Ghosh
 
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
IPPAI
 
Gsm hvdc kolar_talcher line
Gsm hvdc kolar_talcher lineGsm hvdc kolar_talcher line
Gsm hvdc kolar_talcher line
Karthi Pasupathy
 
DFC Decongesting Indian Railways
DFC Decongesting Indian RailwaysDFC Decongesting Indian Railways
DFC Decongesting Indian Railways
Abeer Ray
 
2گزارش ریاست عملیاتی (2)
2گزارش ریاست عملیاتی (2)2گزارش ریاست عملیاتی (2)
2گزارش ریاست عملیاتی (2)
hekmatjoo
 

Similar to HVDC MATIARI -LAHORE TRANSMISSION PROJECT (20)

O&m of hvdc station power grid india
O&m of hvdc station power grid indiaO&m of hvdc station power grid india
O&m of hvdc station power grid india
 
800kv multiterminal system in india
800kv multiterminal system in india800kv multiterminal system in india
800kv multiterminal system in india
 
Power Grid and development in India
Power Grid and development in IndiaPower Grid and development in India
Power Grid and development in India
 
Sui Northern Gas Pipelines Limited
Sui Northern Gas Pipelines LimitedSui Northern Gas Pipelines Limited
Sui Northern Gas Pipelines Limited
 
Status of hvdc links
Status of hvdc linksStatus of hvdc links
Status of hvdc links
 
presentation-by-pgcil-development-of-transmission-system-in-india-foir-worksh...
presentation-by-pgcil-development-of-transmission-system-in-india-foir-worksh...presentation-by-pgcil-development-of-transmission-system-in-india-foir-worksh...
presentation-by-pgcil-development-of-transmission-system-in-india-foir-worksh...
 
Presentation on two major hydro electric power plants in india
Presentation on two major hydro electric power plants in indiaPresentation on two major hydro electric power plants in india
Presentation on two major hydro electric power plants in india
 
1_DFC.pdf
1_DFC.pdf1_DFC.pdf
1_DFC.pdf
 
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...The SAARC Grid:Policy, Regulatory, Infra-structure, Contractual Issues in C...
The SAARC Grid: Policy, Regulatory, Infra-structure, Contractual Issues in C...
 
Esia of 220 k v ug transmission line from lalazar to mauripur g.s & 132 ...
Esia of 220 k v ug transmission line from lalazar to  mauripur g.s & 132 ...Esia of 220 k v ug transmission line from lalazar to  mauripur g.s & 132 ...
Esia of 220 k v ug transmission line from lalazar to mauripur g.s & 132 ...
 
Gsm hvdc kolar_talcher line
Gsm hvdc kolar_talcher lineGsm hvdc kolar_talcher line
Gsm hvdc kolar_talcher line
 
DFC Decongesting Indian Railways
DFC Decongesting Indian RailwaysDFC Decongesting Indian Railways
DFC Decongesting Indian Railways
 
3D FLOW ANALYSIS OF HEAT TRANSFER IN A SCRAPED SURFACE HEAT EXCHANGER (SSHE)
3D FLOW ANALYSIS OF HEAT TRANSFER IN A SCRAPED SURFACE HEAT EXCHANGER (SSHE) 3D FLOW ANALYSIS OF HEAT TRANSFER IN A SCRAPED SURFACE HEAT EXCHANGER (SSHE)
3D FLOW ANALYSIS OF HEAT TRANSFER IN A SCRAPED SURFACE HEAT EXCHANGER (SSHE)
 
Energy Transit & Cross Border Electricity Trade-Pakistan
Energy Transit & Cross Border Electricity Trade-PakistanEnergy Transit & Cross Border Electricity Trade-Pakistan
Energy Transit & Cross Border Electricity Trade-Pakistan
 
Esia of 220 k v transmission lines at port qasim
Esia of  220 k v transmission lines at port qasimEsia of  220 k v transmission lines at port qasim
Esia of 220 k v transmission lines at port qasim
 
11 - China Pakistan Economic Corridor.pptx
11 - China Pakistan Economic Corridor.pptx11 - China Pakistan Economic Corridor.pptx
11 - China Pakistan Economic Corridor.pptx
 
2گزارش ریاست عملیاتی (2)
2گزارش ریاست عملیاتی (2)2گزارش ریاست عملیاتی (2)
2گزارش ریاست عملیاتی (2)
 
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPSOperational description of 400kv switchyard NTPC Ramagundam RSTPS
Operational description of 400kv switchyard NTPC Ramagundam RSTPS
 
Structure of Transmission System in India
Structure of Transmission System in IndiaStructure of Transmission System in India
Structure of Transmission System in India
 
power sector &ehv
power sector &ehvpower sector &ehv
power sector &ehv
 

More from MuhammadFazilMemon

More from MuhammadFazilMemon (7)

OverCurrent Relay & Protective Scheme
OverCurrent Relay & Protective SchemeOverCurrent Relay & Protective Scheme
OverCurrent Relay & Protective Scheme
 
Over/Under Voltage Protection Circuit
Over/Under Voltage Protection CircuitOver/Under Voltage Protection Circuit
Over/Under Voltage Protection Circuit
 
AUTOMATIC TEMPERATURE FAN CONTROLLER
AUTOMATIC TEMPERATURE FAN CONTROLLERAUTOMATIC TEMPERATURE FAN CONTROLLER
AUTOMATIC TEMPERATURE FAN CONTROLLER
 
Efficiency Of A DC Machine And Condition For Maximum Efficiency
Efficiency Of A DC Machine And Condition For Maximum EfficiencyEfficiency Of A DC Machine And Condition For Maximum Efficiency
Efficiency Of A DC Machine And Condition For Maximum Efficiency
 
DIgital Timer And Counter To Control Relays
DIgital Timer And Counter To Control RelaysDIgital Timer And Counter To Control Relays
DIgital Timer And Counter To Control Relays
 
Automatic plant watering using arduinos
Automatic plant watering using arduinosAutomatic plant watering using arduinos
Automatic plant watering using arduinos
 
Thermal Power Generation Of Pakistan
Thermal Power Generation Of PakistanThermal Power Generation Of Pakistan
Thermal Power Generation Of Pakistan
 

Recently uploaded

Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
dharasingh5698
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 

Recently uploaded (20)

Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Wakad Call Me 7737669865 Budget Friendly No Advance Booking
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 

HVDC MATIARI -LAHORE TRANSMISSION PROJECT

  • 1. HVDC MATIARI -LAHORE TRANSMISSION PROJECT MUHAMMAD FAZIL MEMON PRESENTED TO: ENGR.ZUHAIB MUKHTIAR
  • 2. SEQUENCEOFPRESENTATION OVERVIEW THAR COAL BASED POWER GENERATION POTENTIAL UPCOMING POWER GENERATION IN SOUTH – PRESENT SCENARIO SCOPE OF HVDC MATIARI – LAHORE PROJECT CONVERTOR STATIONS LOCATIONS HVDC MATIARI – LAHORE TRANSMISSION LINE COMPLETOIONS TIME LINE PROJECT MANAGEMENT UNIT OPERATOR EMPLOYMENT ADDITIONAL PROJECT INFORMATION
  • 3. OVERVIEW • The 878 kilometres long HVDC transmission line from Matiari to Lahore is the first of its kind in Pakistan. • This HVDC transmission line project is being developed under the framework of China-Pakistan Economic Corridor (CPEC) agreement with the main investor being China Electric Power Equipment & Technology (CET). • This transmission line will have 4,000 MW capacity at 660 kV voltage. The project is designed to have bi-pole HVDC technology, three repeater stations, two grounding electrode stations and two converter stations, one at the each end of the line - Matiari (Interior Sindh) and Lahore.
  • 4.
  • 5. THAR COAL BASED POWER GENERATION POTENTIAL NATIONAL POWER SYSTEM EXPANSION PLAN FOR THE PERIOD 2011-2030 ENVISAGES DEVELOPMENT OF THAR COAL FIELD UPTO 40000 MW YEAR 2011 COAL POWER GENERATION SCENARIO. 500 KV D/C THAR – MATIARI YEAR 2015-16 INSTALLED CAPACITY 1200 MW (THAR), 1200 MW (IMPORTED COAL AT KARACHI) 500 KV AC IN / OUT FROM EXISTING 500 KV HUB-JAMSHORO LINE YEAR 2017-18 REACH TO 4000 MW WHAT NEXT OPTIONS FOR EVACUATION OF POWER
  • 6. UPCOMINGPOWERGENERATIONIN SOUTH– PRESENTSCENARIO THAR COALFIRED PROJECT 660 MW BIN QASIM IMPORTED COALPOWER 1320 MW PLANT SSRLTHAR COALPOWER PLANT 1320 MW HUBCO COALFIRED POWER PROJECT 1320 MW SIDDIQUE SONS COALPOWER PLANT 330 MW Contd.
  • 7. • + 660 kV HVDC Bipole T/Line from Matiari to Lahore (about 870 KM). • HVDC Converter &Switching Control Stations at Matiari &Lahore • Transmission capability of Power - 4000 MW 16
  • 8. • CONVERTOR STATION MATIARI SITE – NATIONAL HIGHWAY, ABOUT 8 KM NORTH MATIARI VILLAGE SIAKHART. • CONVERTOR STATION LAHORE – PHOOL NAGAR MORE KHUNDA ROAD 4 KM WEST HEAD BALLOKI VILLAGEWAIZIR,ABOUT 60 KM TO LAHORE. 17
  • 9. - ABOUT 870 KM - IN SINDH PROVINCE, PASSES THROUGH DISTRICTS OF MATIARI, SANGHAR, KHAIRPUR, SUKKUR, GHOTKI (ABOUT 320 KM) - IN PUNJAB PASSES YAR NAGAR, THROUGH KHAN, PAK DISTRICTS OF BAHAWALPUR, PROVINCE, RAHIM BAHAWAL PATTAN, OKARA, KASUR, (ABOUT 550 KM). NANKANA
  • 10. 19
  • 11. 20
  • 12. 21
  • 15. As per Cooperation Agreement Between State Grid China and NTDC (20.04.2015): • Feasibility study to be finalized by SGCC/CET upto end of July, 2015 • Design completed upto December, 2015 • Construction period 24 months after design finalized 26
  • 16. • Abdur Razzaq Cheema Ex-GM GSC/Consultant Team Leader • Anjum Aziz Manager (GSC) Coordinator • Tariq Shafi Manager (EHV-I) Progress Monitoring • Muhammad Shabbir Dy. GM Finance (WPPO) Commercial Team Leader 27
  • 17. OPERATOR • China Electric Power Equipment and Technology Co. Ltd. (CET) is a wholly owned subsidiary of State Grid Corporation of China (SGCC). CET is the operation platform and implementer of SGCC in carrying out international Engineering-Procurement-Construction (EPC) business. • CET will operate the Matiari-Lahore Transmission Line for 25 years and will transfer it afterwards to the National Transmission and Dispatch Company (NTDC), the Pakistani government-owned power transmission company. • CET is under discussion to provide further transmission lines to Pakistan, such as one between Port Qasim and Faisalabad.
  • 18. EMPLOYMENT • It is planned that during the 1-5th year the main employees in converter stations shall be skilled Chinese. After a overhaul in the 15th year, there shall be only a few Chinese engineers (estimated 10- 12 persons) for each station to supervise and from the 21st year onwards local employees would work independently in the converter stations.
  • 19. ADDITIONAL PROJECT INFORMATION • The Matiari-Lahore Transmission Line will transfer mainly electricity generated from coal power projects such as Engro Thar Coal Power Projectand Port Qasim Power Project. • The transmission line will have a 25-year operational life and afterwards will be transferred to the National Transmission and Dispatch Company (NTDC), the Pakistani government-owned power transmission company, which owns all existing transmission lines in Pakistan. • For executing the Matiari-Lahore line, the government has already handed over two chunks of land for building and installing two convertor stations (one in Matiari for converting alternate current (AC) to direct current (DC) and another near Lahore for conversion of DC to AC) to the Chinese company.
  • 20. • Issues of system stability with proposed induction of HVDC Transmission Scheme. • Protection &Control • Telecom / SCADA • System losses (Permissible / Recommended) • Standards / controlling specifications adopted internationally dealing with: • Availability of System • Noise level / ROW • Sending End / Receiving End System Topology • Central Control Mechanism at NPCC for System Stability • Lenders’ concern-Insurance of T/Line Section 29