SlideShare a Scribd company logo
1 of 49
220kV
Grid
Wapda Town
A Complete overview of Power Grid
Abdul Samad
Presented By
Substation
An Electrical Substation is a subsidiary station of an
electricity Generation , Transmission And Distribution
System where voltage is transformed high to low or
reverse using transformer.
Examples of Substation:-
 220kV/132kV substation
 132kV/66kV substation
 66kV/11kV substation
220kV Substation
It is divided into to(3) parts:-
I. Panel Section
 Control Panel Section
 Relay and Protection Panel Section
II. Switch Yard
 220kV Section
 132kV section
 33kV section
III. Battery Room
Panel Section
It has two sections
I. Control Panel Section
 It contain panels related to controlling of instruments.
E.g.:- feeder panel, X-mer panel, etc.
II. Relay And Protection Panel Section
 It contains panels related to relay systems and
protection systems.
E.g.:- Relay panel, line protection panel, etc.
Switch Yard
 It is the field where components used in controlling
supply and measuring supply(incoming and outgoing)
are placed
Some of these many components are:-
 C.Bs
 Isolators
 C.Ts
 P.Ts
 L.As
 X-mers, etc.
Equipment's
used All Power-Grid Equipment's
MAIN EQUIPMENTS AT WAPDA TOWN SUBSTATION 220KV
Main equipment of Wapda town substation 220kV
* Ring Bus system :
I/C Supply
O/G feeder
Bus
CB
Tie CB
Main 1
Main 2
Feeder 1Feeder 2Feeder 2
Tie CB
Feeder 1
* One and Breaker Half :
Page 10
©
OMICR
Purpose of Circuit Breakers in Power
Systems
> Minimize losses in closed position
> Open and close on command
>Open or close a circuit to connect
the power to/from the transmission
line
(O - break, C - make)
>Open a circuit for planned
maintenance (O - break)
>Open a circuit at system fault to
protect the system behind the
circuit breaker (O break, O-C
reclose, O-CO, auto-reclose)
>Isolate between poles, open
contacts and earth
x
Busbar
Disconnector
Circuit Breaker
Power
Transformer
x Circuit Breaker
Network
Equipment's
used
Types of
Conductors
What we have learnt …??
Conductors
Why We use Aluminum in place of Copper …??
Types of conductors used in 220kV substations are
 AAC -> All Aluminum Conductors
 AAAC -> All Aluminum Alloy Conductors
 ACSR -> Aluminum Conductor Steel Reinforced
 ACAR -> Aluminum Conductor Alloy Reinforced
Equipment's
used
Types of
Conductors
What we have learnt …??
All Aluminum Conductors (AAC) &
All Aluminum-Alloy Conductor (AAAC)
For 36 kV transmission and above both aluminum conductor steel
reinforced (ACSR) and all aluminum alloy conductor (AAAC) may
be considered. Aluminum conductor alloy reinforced (ACAR) and
all aluminum alloy conductors steel reinforced (AACSR) are less
common than AAAC and all such conductors may be more
expensive than ACSR
Equipment's
used
Types of
Conductors
What we have learnt …??
Aluminum Conductor Steel Reinforced (ACSR)
Names of ASCRs
No. Of strands / No. Of steel Strands/diameter of strands
H.T Overhead Line
Sr. No. Names Size(mm)*
1. Rabbit 6/1/3.55
2. Panther 30/7/3.00
3. Zebra 54/7/3.00
4. Moose 54/7/3.53
Equipment's
used
Types of
Conductors
What we have learnt …??
Aluminum Conductor Aluminum Alloy Reinforced
(ACAR)
I. improved strength to weight ratio
II. better mechanical properties
III. improved electrical characteristics
IV. excellent resistance to corrosion
Equipment's
used
Types of
Conductors
Transformer
Transformer Colling Methods
ONAN
ONAF
OFAF
OFAN
Equipment's
used
Types of
Conductors
Transformer
Transformer Colling Methods
ONAN Cooling Method
Equipment's
used
Types of
Conductors
Transformer
Transformer Colling Methods
ONAF Cooling Method
Equipment's
used
Types of
Conductors
Transformer
Transformer Colling Methods
OFAN Cooling Method
Equipment's
used
Types of
Conductors
Transformer
Transformer Colling Methods
OFAF Cooling Method
Equipment's
used
Types of
Conductors
Transformer
Transformer Mechanical Protection
Buchholz Relay Working
Equipment's
used
Types of
Conductors
Transformer
Transformer Mechanical Protection
Buchholz Relay Position on Transformer
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Earthing Test of Transformer
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Earthing Test of Transformer Observations
 (2-1) at 100A voltage drop was 0.5V at test set
 (2-3) at 100A voltage drop was 0.39V because of test lead
 (2-10) at 100A voltage drop was 0.701V at test set
 (2-9) at 100A voltage drop was 0.6V at test set
 (2-8) at 100A voltage drop was 0.68V at test set
 (2-7) at 100A voltage drop was 0.59V at test set
 (2-6) at 100A voltage drop was 0.78V at test set
 (2-5) at 100A voltage drop was 0.43V at test set
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Transformer Turn Ratio Test
HV Side LV Side
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Step 1.
First, the tap changer of transformer is kept in lowest position and LV
terminals are kept open. In this test we check that the voltages at the LV
side according to the turn ratio of rated LV side and HV side are according
to the rated value. We use Megger for the supply of 400V during the testing
of TTR.
Step 2.
For testing purpose we open both the LV and HV sides. We supply 400V
using Megger Device. And at the side we received 34.28V.
Star-Delta Turns Ratio Delta-Star Turns Ratio
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Megger Insulation Resistance Test
1. HV to LV
Step 1.
Open HV & LV sides of the transformer.
Step 2.
Short the terminals of both sides of Star & Delta Winding
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Step 3.
We supplied voltages at the HV side of +5KV DC and -5KV DC at LV side.
Step 4.
By measuring the voltage drop we calculate the resistance of core and
windings.
Step 5.
And then we compare the calculated with the commissioned report.
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Step 1.
Open HV & LV sides of the transformer.
Step 2.
Short the terminals of both sides of Star
& Delta Winding.
Step 3.
We supplied voltages at the HV side of +12KV DC and GND at LV side.
Step 4.
By measuring the voltage drop we calculate the resistance between
windings turns of HV side
Step 5.
And then we compare the calculated with the commissioned report.
2. HV to GND
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
3. LV to GND
Step 1.
Open HV & LV sides of the transformer.
Step 2.
Short the terminals of both sides of
Star & Delta Winding.
Step 3.
We supplied voltages at the LV side of
+12KV DC and GND at HV side.
Step 4.
By measuring the voltage drop we calculate the resistance between
windings turns of LV side.
Step 5.
And then we compare the calculated with the commissioned report.
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Winding Resistance Test
Step 1.
We open the HV & LV windings of the
transformer.
Step 2.
Current is injected into winding using
current injection set.
Step 3.
Supply should be DC 100A because of measuring resistance and if we use
AC then it consists of capacitive reactance, inductive reactance and the
total combination of impedance of the above. So that’s why we don’t use
AC and hence we use DC to avoid the above problems to find the winding
resistance.
Step 4.
For LV side testing we test between red & Neutral, Yellow & Neutral, and
Blue & Neutral for LV side or star connected side.
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Step 5.
For HV side or Delta connected side we measure resistance between
phases (red,blue), (red,yellow) and (yellow,blue).
Purpose
 Calculate the I2 R losses in conductor.
 Calculation of winding temperature at the end of temperature test
cycle.
 It provides a base line which tells us about the possible damage in the
field.
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Temperature Rise Test
Step 1.
First the LV winding of the
transformer is short circuited.
Step 2.
Then one thermometer is placed
in a pocket in transformer top
cover. Other two thermometers
are placed at the inlet and outlet
of the cooler bank respectively.
Step 3.
The voltage of such value is applied to the HV winding that power
input is equal to no load losses plus load losses corrected to a
reference temperature of 75°C.
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Step 5.
During the test, hourly readings of top oil temperature are taken from
the thermometer already placed in the pocket of top cover.
Hourly readings of the thermometers placed at inlet and outlet of the
cooler bank are also noted to calculate the mean temperature of the
oil. And finally we read the temperature at steady state and stop the
testing method.
Step 6
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Current Transformer Test
The voltage shall be applied between:
1. Primary to secondary plus ground
(covered during switchgear test).
2. Secondary to primary plus ground.
3. Secondary core to core.
The above diagram shows that how a CT measure the current practically
or numerically.
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Capacitance and dissipation factor test
It is a low AC voltage maintenance test similar to power factor test to
measure capacitance and dissipation of transformer insulation system.
Acceptance testing stage to establish base line reading for future.
Step 1.
Isolate the equipment, apply working grounds to all incoming and outgoing
cables and disconnect all incoming and outgoing cables from the
transformer bushing terminals. Disconnected cables should have sufficient
clearance from the switchgear terminals greater that the phase spacing
distance.
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Step 2.
Isolate the neutral bushing connection if applicable from the transformer
grounding bar.
Step 3.
Short-circuit all high voltage bushing terminals together.
Step 4.
Short-circuit all low voltage bushing terminals and the neutral bushing
terminal together.
Step 5.
Connect the capacitance and dissipation factor test set. Refer to Figure , on
next slide.
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Step 6.
Record the capacitance and dissipation factor values once the null meter is
balance for both phasing position. Record values for the five test-variable
selector switch position.
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Transformer Testing
Purpose
 Condition of Bushing and overall insulation
of transformer can be investigated.
 Aging and decomposition of insulation increase the losses are
determined through this test.
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Monitoring
& Control
panel
Monitoring & Control Panels
Monitoring Panel Equipment
• Ampere meters
• Voltmeters
• Kilowatt meters
• KVAR meters
• Power factor meters
• Energy Meters
In the monitoring and control room, there are two kinds of panels;
Monitoring & Control
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Bus Bar,
Safety &
Battery
Room
Monitoring & Control Panels
Monitoring Panel Equipment
• Alarms
• Indications
Breaker
open
Buchhloz
Relay
SF6 low
pressure
Relay
active
Monitoring
& Control
panel
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Bus Bar,
Safety &
Battery
Room
Monitoring & Control Panels
• Push buttons and switches
• Power supply
• Relays
Control Panel Equipment
Rectifier
Battery charger
+
Batteries
To control panel
(dc)
AC
Backup supply for
control panel (dc)
Monitoring
& Control
panel
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Bus Bar,
Safety &
Battery
Room
Transformer
DY - 132/11kV, 20/26MVA
Rated current HV = 114 A
Rated current LV = 1366 A
If 10% of rated voltage (suppose), rated current flows in
secondary when short circuited.
13.2kV ==== 1366 A
13.2kV * 10 === 1366 A * 10
V1 V2Transformer
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Bus Bar &
Safety
Bus Bar Scheme
Different bus bar arrangements:
Some of the switching schemes are bus bar
arrangements employed in the substations are
listed below:
 Single Bus-bar arrangement
 Double Main Bus-bar scheme
 Main and Transfer bus-bar scheme
 One and half breaker scheme
 Ring Main arrangement scheme
Monitoring
& control
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Bus Bar &
Safety
Bus Bar Scheme
Double Main Bus-bar scheme
Advantages:
I. Any circuit can be taken out of circuit for
maintenance
II. Flexibility in connecting the feeder circuit
to either of the bus bars
Disadvantages:
I. Most expensive
II. Loose circuits connected to bus bar when
fault occurs on the bus bar
Monitoring
& control
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Bus Bar &
Safety
Fire Extinguishers Types
Monitoring
& control
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
BusBar,
Safety &
Battery
Room
Battery Room
What is the purpose of battery room ..??
 It is the Heart of Grid
 Provides backup
 Protection devices run on this
Monitoring
& control
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Bus Bar,
Safety &
Battery
Testing of Batteries
Monitoring
& control
Visual Inspection Test
Equipment's
used
Types of
Conductors
Transformer
X-mers
Testing
Bus Bar,
Safety &
Battery
Testing of Batteries
Monitoring
& control
Voltage Test
220kv grid wapda town lahore

More Related Content

What's hot

Measurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionMeasurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_version
Aman Ansari
 
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission lineMatlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
pamu17
 

What's hot (20)

Measurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_versionMeasurement of high_voltage_and_high_currentunit_iv_full_version
Measurement of high_voltage_and_high_currentunit_iv_full_version
 
Load flow analysis of radial distribution system
Load flow analysis of radial distribution system Load flow analysis of radial distribution system
Load flow analysis of radial distribution system
 
FACTS DEVICES AND POWER SYSTEM STABILITY ppt
FACTS DEVICES AND POWER SYSTEM STABILITY pptFACTS DEVICES AND POWER SYSTEM STABILITY ppt
FACTS DEVICES AND POWER SYSTEM STABILITY ppt
 
BUCK converter fed by PV array
BUCK converter fed by PV arrayBUCK converter fed by PV array
BUCK converter fed by PV array
 
3 reactive power and voltage control
3 reactive power and voltage control3 reactive power and voltage control
3 reactive power and voltage control
 
Reactive power management
Reactive power managementReactive power management
Reactive power management
 
INTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLERINTERLINE FLOW CONTROLLER
INTERLINE FLOW CONTROLLER
 
Voltage tolerance
Voltage toleranceVoltage tolerance
Voltage tolerance
 
Power system-analysis-psr murthy
Power system-analysis-psr murthyPower system-analysis-psr murthy
Power system-analysis-psr murthy
 
EHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniquesEHVAC transmission line maintenance techniques
EHVAC transmission line maintenance techniques
 
Power Factor
Power FactorPower Factor
Power Factor
 
Reactive power compensation
Reactive power compensationReactive power compensation
Reactive power compensation
 
Unified Power Flow Controller(upfc)1
Unified Power Flow Controller(upfc)1Unified Power Flow Controller(upfc)1
Unified Power Flow Controller(upfc)1
 
Selection Of Circuit Breaker
Selection Of Circuit BreakerSelection Of Circuit Breaker
Selection Of Circuit Breaker
 
Voltage sag and it’s mitigation
Voltage sag and it’s mitigationVoltage sag and it’s mitigation
Voltage sag and it’s mitigation
 
Different method of frequency and voltage control
Different method of frequency and voltage controlDifferent method of frequency and voltage control
Different method of frequency and voltage control
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGE
 
Load frequency control
Load frequency controlLoad frequency control
Load frequency control
 
Three level inverter
Three level inverterThree level inverter
Three level inverter
 
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission lineMatlab Simulink in Three-Phase Fault Analysis on Transmission line
Matlab Simulink in Three-Phase Fault Analysis on Transmission line
 

Viewers also liked (6)

Load Distribution
Load DistributionLoad Distribution
Load Distribution
 
SUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substationSUBSTATION OVERVIEW - A presentation on substation
SUBSTATION OVERVIEW - A presentation on substation
 
A 220kV Substation
A 220kV SubstationA 220kV Substation
A 220kV Substation
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
Substation overview
Substation overviewSubstation overview
Substation overview
 
Types Of Substations
Types Of SubstationsTypes Of Substations
Types Of Substations
 

Similar to 220kv grid wapda town lahore

REPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTREPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANT
RAJPRASAD RS
 
Best transformer-test-procedures-en
Best transformer-test-procedures-enBest transformer-test-procedures-en
Best transformer-test-procedures-en
Suresh Patil
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptx
RAJKIRANR3
 
Ppt on 132 kv gss by ashok khoja
Ppt on  132 kv gss  by ashok khojaPpt on  132 kv gss  by ashok khoja
Ppt on 132 kv gss by ashok khoja
ASHOK KHOJA
 

Similar to 220kv grid wapda town lahore (20)

TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
93518813-TESTING-MAINTENANCE-PROTECTION-OF-DISTRIBUTION-TRANSFORMERS.ppt
 
TESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.pptTESTING,MAINTENANCE&PROTECTION.ppt
TESTING,MAINTENANCE&PROTECTION.ppt
 
Distribution Transformer testing, West Bengal, India
Distribution Transformer testing,  West Bengal, IndiaDistribution Transformer testing,  West Bengal, India
Distribution Transformer testing, West Bengal, India
 
REPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTREPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANT
 
Testing,maintenance&protection
Testing,maintenance&protectionTesting,maintenance&protection
Testing,maintenance&protection
 
Transformer ppt.
Transformer ppt.Transformer ppt.
Transformer ppt.
 
Thesis grid station 1.pdf
Thesis grid station 1.pdfThesis grid station 1.pdf
Thesis grid station 1.pdf
 
Unit 1-2-b
Unit 1-2-bUnit 1-2-b
Unit 1-2-b
 
Best transformer-test-procedures-en
Best transformer-test-procedures-enBest transformer-test-procedures-en
Best transformer-test-procedures-en
 
TRANSFORMER DESIGN.pptx
TRANSFORMER DESIGN.pptxTRANSFORMER DESIGN.pptx
TRANSFORMER DESIGN.pptx
 
tcee-161003100321.pptx
tcee-161003100321.pptxtcee-161003100321.pptx
tcee-161003100321.pptx
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Best-transformer-test-procedures-en
  Best-transformer-test-procedures-en  Best-transformer-test-procedures-en
Best-transformer-test-procedures-en
 
Transformer
TransformerTransformer
Transformer
 
Untitled document.PDF
Untitled document.PDFUntitled document.PDF
Untitled document.PDF
 
Chapter 5 mukesh gurjar
Chapter 5 mukesh gurjarChapter 5 mukesh gurjar
Chapter 5 mukesh gurjar
 
Testing of Transformers.
Testing of Transformers.Testing of Transformers.
Testing of Transformers.
 
Presentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptxPresentation OutDoorSwithGear(AIS) .pptx
Presentation OutDoorSwithGear(AIS) .pptx
 
Ppt on 132 kv gss by ashok khoja
Ppt on  132 kv gss  by ashok khojaPpt on  132 kv gss  by ashok khoja
Ppt on 132 kv gss by ashok khoja
 

Recently uploaded

Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 

220kv grid wapda town lahore