SlideShare a Scribd company logo
1 of 19
VISVESVARAYA TECHNOLOGICAL UNIVERSITY
BELAGAVI -590018
IMPLEMENTATION OF KAIZEN AS A PRODUCTIVITY
IMPROVEMENT TOOL IN SMALL MANUFACTURING COMPANY
Technical Seminar
on
Submitted By
MAHESH N
USN: 4AD15ME042
Submitted in the partial fulfillment of the requirements for the
award of degree
BACHELOR OF ENGINEERING
IN
MECHANICAL ENGINEERING
Under the guidance of
Dr. RATHNAKAR G
HOD & Professor
DEPARTMENT OF MECHANICAL ENGINEERING
ATME COLLEGE OF ENGINEERING
MYSURU -570028
• Introduction of Kaizen & 5S
• Objective
• Methodology
• Problem Statement
• Implementation of Kaizen & 5S
• Result & Discussion
• Conclusion
Contents
 Kaizen –Continuous Improvement.
‘KAI’ means ‘Change or the action to correct’.
‘ZEN’ means ‘Good’
 Purpose of Kaizen is to focus on each process in order to add value and
eliminating waste.
 A continuous improvement process which when apply with 5S solve many
of the problem related to Productivity improvement, stock-out,
increased lead time etc.
The present work is on finding out the improvement opportunity using
continuous improvement
INTRODUCTION
Pictorial Form of Kaizen Process
METHODOLOGY
COMPANY SELECTION
To implement Kaizen & 5S for a PVC pipe manufacturing company
currently facing with the problem of Increased lead time and Stock out
problem.
Company profile
Modigold Pipes Pvt. Ltd
B-10, MIDC, Buttibori, Nagpur.
PROBLEM STATEMENT
The company is dealing with the manufacturing of varieties of pipes
with the variation of 40mm to 200mm diameter pipe. Which is facing
with some of the problem
1. More lead time for sales order processing
2. More production cycle time.
3. Work hazardness
4. Stock out problem
Stepwise production process of
pipe
INDENTIFIED CAUSES OF PROBLEM
Fig1. Improper stock of Finish good Fig2. Improper arrangement of raw
material
Fig3. Poor working area Fig4. Improper arrangement of supporting tools
AREAS NEEDS TO IMPROVEMENT
• Raw material storage section
• Need of Inventory record keeping for data maintenance
• Finished good storage area
• Supporting tool storage area
• Working area
TIME CALCULATION BEFORE
IMPLEMENTATION
Sr
No
Time factor Calculated time
(In Hour)
1 Raw Material Preparation Time 0.54Hr
2 Machining Time 2.70Hr
3 Socket making time 1.25 Hr
4 Total Production Time( M/c warm up
time+RMPT+MT+SMT)
3.33+0.54+2.70+1.25 =
7.82Hr.
5 Lead Time ( Total production
time+transportation)
1 to 3.5 Days (depend on
source destination)
ESTIMATION OF STOCK OUT
Sr. No X (Demand per
month)
X-µ (X-µ)2
1 17.50 -7.975 63.60063
2 10.00 -15.475 239.4756
3 20.00 -5.475 29.97563
4 20.00 -5.475 29.97563
5 50.00 24.525 601.4756
6 53.20 27.725 768.6756
7 21.00 -4.475 20.02563
8 000 -25.475 648.9756
9 8.00 -17.475 305.3756
10 36.00 10.525 110.7756
11 30.00 4.525 20.47563
12 40.00 14.525 210.9756
Total 305.70 3049.783
Mean μ =
30570/12
= 25.475
Standard
deviation(σ)
σ =
√3049.783 12
=15.94204
Calculation of Safety stock
• If R is the consumption demand, L is the lead time, then consumption
rate during the lead time = RL
• If S is the safety stock, and Q is the re-order quantity, then Maximum
stock level is Q+S and Minimum stock level is s=S
• Production Point = Safety stock + consumption during lead time
= safety stock + mean lead time consumption
In this first we have to find the probability of stock out when the company is maintaining the minimum
stock of 18 units i.e 1800 pipes (one specific item).mean demand is 25.475 and std. deviation is 15.94,
the probability that the demand comes more than 18 unit is calculated as
• X=18 in terms of Z is
• Z= (18-25.475)/15.95= -0.46895 (approximately -0.47)
• P(x>18) = P (Z> -0.46895)
= Area right to Z= -0.47
= (area between Z=0 to Z=0.47) + 0.5000
= 0.1808+0.5000
= 0.6808
• 68.08% of probability of stock out when the company is maintaining a safety stock of 18 units. Then
what should be the safety stock?
 For the usual demand pattern drawn from the observation and production manager the mean
and standard deviation was found to be 25.475 and 15.94 respectively. The policy of the
management is to have 95% of the service level.
 For approximately 95% of the service level (approximately 0.9495 and 0.9405)The values
of area for Z= 1.64 and Z=1.65 which can be calculated as :
 Approximate values from table are
A = 0.9405 and A= 0.9505 which are taken from z= 1.64 and z= 1.65 By
interpolation actual value of z will be
 Z= 1.64 + [ (0.9500-0.9405)/(0.9505-0.9405)* (1.65-1.64) ]=1.68475
 µ = 25.475 and σ = 15.94
Therefore, Safety stock = Z*σ
= 1.64875 * 15.94
= 26.28 approximately (26.3 units)
Therefore the company should maintain a safety stock of 26.28 units for 95% of the service level.
Time difference calculation (Before and after implementation)
1. Raw material preparation time Before implementation = 0.54 hour After implementation = 0.495
hour Difference = (0.54- 0.495) = 0.045 Approximately time reduction of 3 min
2. Actual machining time or processing time before implementation (95% of efficiency of machine) =
2.70 hour after implementation (99 % of efficiency of machine) = 2.38 hour. Difference= (2.70-2.38) =
0.32 hour i.e before implementation 37 pipes will be manufactured in one hour and after
implementation the figure will be improved to 42 pipes in one hour.
Before implementation:
Machine is producing 37 pipes in 60 min Machine time for 1 piece will be = 1.62minutes
Actual machine time (before implementation) = available time per shift of 8 hour/ time per pipe.
= 8*60 / 1.62
= 296.29 pipes (actual output)
After Implementation: (the time for each pipe will be an ideal time or standard time per piece)
Ideally the machine now producing 42 pipes in 60 minutes
Standard time for one pipe will be = 1.428 min
Ideal machine time (after implementation) = available time per shift of 8 hour / time per pipe.
= 8 * 60 / 1.428
= 336.134 pipes
Machine productivity = (actual output / ideal output) * 100
= productivity per shift will be 88.12 %
RESULT
Sr Factor Before Kaizen implementation After Kaizen implementation Diffrence
no
1 Total Raw material preparation Raw material preparation Raw material
production time+Machining time+Socket time+Machining time+Socket preparation time
time making time+M/c warm up time making time+M/c warm up
time
Before:0.54Hr
=0.54Hr+2.70Hr+1.25Hr+3.33 =0.495Hr+2.38Hr+1.15Hr+3.33 After: 0.495
=7.82 Hour Hr Difference:
=7.315 Hr 0.54-0.495
=0.045Hr (2.7min)
2 Lead time 1 to 3.5 days 1 to 3.3 days Reduction of lead
time by 0.2 day
3 Safety stock 20 units (without any technical 26.3 units calculated value NA
assumption)
4 Probability of 50 % of the time stock out 40% probability of stock out Probability of
stock out situation stock out will be
reduce by 10 %
5 productivity 296.29 pipes ( actual output) 336.134 pipes Machine
CONCLUSION
• Kaizen has been successfully implemented in the PVC pipe manufacturing
company and the determination of stock out situation before kaizen
implementation is completed using simulation model & validation after
implementation is done with 10% reduction in stock out.
REFERENCES
1. AbhijitChakraborty, Madhuri Bhattacharya, “Importance of kaizen
concept in Medium manufacturing industries.” June-Jan 2013,
International journal of management & strategy, Volume No:4, issue 6.
2. D .Rajenthirakumar, P R. Thyla. Transformation to Lean Manufacturing
By an Automotive Component Manufacturing Company.
3. Mr. Bhupendra Kumar Daiya, “Applying Gemba Kaizen at SKS
Separator in cement plant” A case study IOSR Journal of Engineering
(IOSRJEN)e-ISSN: 2250-3021, p- ISSN: 2278-8719, www.iosrjen.org
Volume 2, Issue 9 (September 2012), PP 01-06
4. Gundeep Singh, Dr. R.M. Belokar “Lean Manufacturing Implementation
in the Assembly shop of Tractor Manufacturing”. International Journal of
Innovative Technology and Exploring Engineering (IJITEE) ISSN: 2278-
3075, Volume-1, Issue-2, July 2012.

More Related Content

Similar to 4AD15ME042.pptx

Machining time and costs
Machining time and costsMachining time and costs
Machining time and costsendika55
 
CIM report - final
CIM report - finalCIM report - final
CIM report - finalPraveen S R
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysisvideoaakash15
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysisvideoaakash15
 
Lean Manufacturing Applications Implementation
Lean Manufacturing Applications Implementation Lean Manufacturing Applications Implementation
Lean Manufacturing Applications Implementation Mostafa Alattar
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringIJECSJournal
 
Scooter india,sip presentation
Scooter india,sip presentationScooter india,sip presentation
Scooter india,sip presentationDeepak Gautam
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...Karina Islam
 
MMAE557 Consulting Project-Li He(A20358122),Xingye Dai(A20365915)
MMAE557 Consulting Project-Li He(A20358122),Xingye Dai(A20365915)MMAE557 Consulting Project-Li He(A20358122),Xingye Dai(A20365915)
MMAE557 Consulting Project-Li He(A20358122),Xingye Dai(A20365915)LI HE
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudybejayrocks
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study ChallengeNikhil Kejriwal
 
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdfRahbiMalek
 
Effect of work study & time study on production and quality
Effect of work study & time study on production and qualityEffect of work study & time study on production and quality
Effect of work study & time study on production and qualityMd. Mazadul Hasan Shishir
 
CASE STUDY ON IMPLEMENTATION OF KAIZEN AND 5S TECHNIQUES IN SMALL MANUFACTURI...
CASE STUDY ON IMPLEMENTATION OF KAIZEN AND 5S TECHNIQUES IN SMALL MANUFACTURI...CASE STUDY ON IMPLEMENTATION OF KAIZEN AND 5S TECHNIQUES IN SMALL MANUFACTURI...
CASE STUDY ON IMPLEMENTATION OF KAIZEN AND 5S TECHNIQUES IN SMALL MANUFACTURI...Shubhangi Gurway
 
standardised-work-overview-and-documents
standardised-work-overview-and-documentsstandardised-work-overview-and-documents
standardised-work-overview-and-documentsAngelo Del Grosso
 

Similar to 4AD15ME042.pptx (20)

Machining time and costs
Machining time and costsMachining time and costs
Machining time and costs
 
Work measurement
Work measurementWork measurement
Work measurement
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM Report
CIM ReportCIM Report
CIM Report
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysis
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysis
 
Lean Manufacturing Applications Implementation
Lean Manufacturing Applications Implementation Lean Manufacturing Applications Implementation
Lean Manufacturing Applications Implementation
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ring
 
Scooter india,sip presentation
Scooter india,sip presentationScooter india,sip presentation
Scooter india,sip presentation
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
MMAE557 Consulting Project-Li He(A20358122),Xingye Dai(A20365915)
MMAE557 Consulting Project-Li He(A20358122),Xingye Dai(A20365915)MMAE557 Consulting Project-Li He(A20358122),Xingye Dai(A20365915)
MMAE557 Consulting Project-Li He(A20358122),Xingye Dai(A20365915)
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudy
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study Challenge
 
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
05-Chapter_5_Automated_Work_Cells_and_CIM_Systems_Final.pdf
 
Effect of work study & time study on production and quality
Effect of work study & time study on production and qualityEffect of work study & time study on production and quality
Effect of work study & time study on production and quality
 
CASE STUDY ON IMPLEMENTATION OF KAIZEN AND 5S TECHNIQUES IN SMALL MANUFACTURI...
CASE STUDY ON IMPLEMENTATION OF KAIZEN AND 5S TECHNIQUES IN SMALL MANUFACTURI...CASE STUDY ON IMPLEMENTATION OF KAIZEN AND 5S TECHNIQUES IN SMALL MANUFACTURI...
CASE STUDY ON IMPLEMENTATION OF KAIZEN AND 5S TECHNIQUES IN SMALL MANUFACTURI...
 
standardised-work-overview-and-documents
standardised-work-overview-and-documentsstandardised-work-overview-and-documents
standardised-work-overview-and-documents
 
All in 1 IE
All in 1 IEAll in 1 IE
All in 1 IE
 
Operation management problems
Operation management problemsOperation management problems
Operation management problems
 

Recently uploaded

Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...Call Girls in Nagpur High Profile
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 

Recently uploaded (20)

Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
High Profile Call Girls Nashik Megha 7001305949 Independent Escort Service Na...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 

4AD15ME042.pptx

  • 1. VISVESVARAYA TECHNOLOGICAL UNIVERSITY BELAGAVI -590018 IMPLEMENTATION OF KAIZEN AS A PRODUCTIVITY IMPROVEMENT TOOL IN SMALL MANUFACTURING COMPANY Technical Seminar on Submitted By MAHESH N USN: 4AD15ME042 Submitted in the partial fulfillment of the requirements for the award of degree BACHELOR OF ENGINEERING IN MECHANICAL ENGINEERING Under the guidance of Dr. RATHNAKAR G HOD & Professor DEPARTMENT OF MECHANICAL ENGINEERING ATME COLLEGE OF ENGINEERING MYSURU -570028
  • 2. • Introduction of Kaizen & 5S • Objective • Methodology • Problem Statement • Implementation of Kaizen & 5S • Result & Discussion • Conclusion Contents
  • 3.  Kaizen –Continuous Improvement. ‘KAI’ means ‘Change or the action to correct’. ‘ZEN’ means ‘Good’  Purpose of Kaizen is to focus on each process in order to add value and eliminating waste.  A continuous improvement process which when apply with 5S solve many of the problem related to Productivity improvement, stock-out, increased lead time etc. The present work is on finding out the improvement opportunity using continuous improvement INTRODUCTION
  • 4. Pictorial Form of Kaizen Process
  • 6. COMPANY SELECTION To implement Kaizen & 5S for a PVC pipe manufacturing company currently facing with the problem of Increased lead time and Stock out problem. Company profile Modigold Pipes Pvt. Ltd B-10, MIDC, Buttibori, Nagpur.
  • 7. PROBLEM STATEMENT The company is dealing with the manufacturing of varieties of pipes with the variation of 40mm to 200mm diameter pipe. Which is facing with some of the problem 1. More lead time for sales order processing 2. More production cycle time. 3. Work hazardness 4. Stock out problem
  • 9. INDENTIFIED CAUSES OF PROBLEM Fig1. Improper stock of Finish good Fig2. Improper arrangement of raw material Fig3. Poor working area Fig4. Improper arrangement of supporting tools
  • 10. AREAS NEEDS TO IMPROVEMENT • Raw material storage section • Need of Inventory record keeping for data maintenance • Finished good storage area • Supporting tool storage area • Working area
  • 11. TIME CALCULATION BEFORE IMPLEMENTATION Sr No Time factor Calculated time (In Hour) 1 Raw Material Preparation Time 0.54Hr 2 Machining Time 2.70Hr 3 Socket making time 1.25 Hr 4 Total Production Time( M/c warm up time+RMPT+MT+SMT) 3.33+0.54+2.70+1.25 = 7.82Hr. 5 Lead Time ( Total production time+transportation) 1 to 3.5 Days (depend on source destination)
  • 12. ESTIMATION OF STOCK OUT Sr. No X (Demand per month) X-µ (X-µ)2 1 17.50 -7.975 63.60063 2 10.00 -15.475 239.4756 3 20.00 -5.475 29.97563 4 20.00 -5.475 29.97563 5 50.00 24.525 601.4756 6 53.20 27.725 768.6756 7 21.00 -4.475 20.02563 8 000 -25.475 648.9756 9 8.00 -17.475 305.3756 10 36.00 10.525 110.7756 11 30.00 4.525 20.47563 12 40.00 14.525 210.9756 Total 305.70 3049.783 Mean μ = 30570/12 = 25.475 Standard deviation(σ) σ = √3049.783 12 =15.94204
  • 13. Calculation of Safety stock • If R is the consumption demand, L is the lead time, then consumption rate during the lead time = RL • If S is the safety stock, and Q is the re-order quantity, then Maximum stock level is Q+S and Minimum stock level is s=S • Production Point = Safety stock + consumption during lead time = safety stock + mean lead time consumption
  • 14. In this first we have to find the probability of stock out when the company is maintaining the minimum stock of 18 units i.e 1800 pipes (one specific item).mean demand is 25.475 and std. deviation is 15.94, the probability that the demand comes more than 18 unit is calculated as • X=18 in terms of Z is • Z= (18-25.475)/15.95= -0.46895 (approximately -0.47) • P(x>18) = P (Z> -0.46895) = Area right to Z= -0.47 = (area between Z=0 to Z=0.47) + 0.5000 = 0.1808+0.5000 = 0.6808 • 68.08% of probability of stock out when the company is maintaining a safety stock of 18 units. Then what should be the safety stock?
  • 15.  For the usual demand pattern drawn from the observation and production manager the mean and standard deviation was found to be 25.475 and 15.94 respectively. The policy of the management is to have 95% of the service level.  For approximately 95% of the service level (approximately 0.9495 and 0.9405)The values of area for Z= 1.64 and Z=1.65 which can be calculated as :  Approximate values from table are A = 0.9405 and A= 0.9505 which are taken from z= 1.64 and z= 1.65 By interpolation actual value of z will be  Z= 1.64 + [ (0.9500-0.9405)/(0.9505-0.9405)* (1.65-1.64) ]=1.68475  µ = 25.475 and σ = 15.94 Therefore, Safety stock = Z*σ = 1.64875 * 15.94 = 26.28 approximately (26.3 units) Therefore the company should maintain a safety stock of 26.28 units for 95% of the service level.
  • 16. Time difference calculation (Before and after implementation) 1. Raw material preparation time Before implementation = 0.54 hour After implementation = 0.495 hour Difference = (0.54- 0.495) = 0.045 Approximately time reduction of 3 min 2. Actual machining time or processing time before implementation (95% of efficiency of machine) = 2.70 hour after implementation (99 % of efficiency of machine) = 2.38 hour. Difference= (2.70-2.38) = 0.32 hour i.e before implementation 37 pipes will be manufactured in one hour and after implementation the figure will be improved to 42 pipes in one hour. Before implementation: Machine is producing 37 pipes in 60 min Machine time for 1 piece will be = 1.62minutes Actual machine time (before implementation) = available time per shift of 8 hour/ time per pipe. = 8*60 / 1.62 = 296.29 pipes (actual output) After Implementation: (the time for each pipe will be an ideal time or standard time per piece) Ideally the machine now producing 42 pipes in 60 minutes Standard time for one pipe will be = 1.428 min Ideal machine time (after implementation) = available time per shift of 8 hour / time per pipe. = 8 * 60 / 1.428 = 336.134 pipes Machine productivity = (actual output / ideal output) * 100 = productivity per shift will be 88.12 %
  • 17. RESULT Sr Factor Before Kaizen implementation After Kaizen implementation Diffrence no 1 Total Raw material preparation Raw material preparation Raw material production time+Machining time+Socket time+Machining time+Socket preparation time time making time+M/c warm up time making time+M/c warm up time Before:0.54Hr =0.54Hr+2.70Hr+1.25Hr+3.33 =0.495Hr+2.38Hr+1.15Hr+3.33 After: 0.495 =7.82 Hour Hr Difference: =7.315 Hr 0.54-0.495 =0.045Hr (2.7min) 2 Lead time 1 to 3.5 days 1 to 3.3 days Reduction of lead time by 0.2 day 3 Safety stock 20 units (without any technical 26.3 units calculated value NA assumption) 4 Probability of 50 % of the time stock out 40% probability of stock out Probability of stock out situation stock out will be reduce by 10 % 5 productivity 296.29 pipes ( actual output) 336.134 pipes Machine
  • 18. CONCLUSION • Kaizen has been successfully implemented in the PVC pipe manufacturing company and the determination of stock out situation before kaizen implementation is completed using simulation model & validation after implementation is done with 10% reduction in stock out.
  • 19. REFERENCES 1. AbhijitChakraborty, Madhuri Bhattacharya, “Importance of kaizen concept in Medium manufacturing industries.” June-Jan 2013, International journal of management & strategy, Volume No:4, issue 6. 2. D .Rajenthirakumar, P R. Thyla. Transformation to Lean Manufacturing By an Automotive Component Manufacturing Company. 3. Mr. Bhupendra Kumar Daiya, “Applying Gemba Kaizen at SKS Separator in cement plant” A case study IOSR Journal of Engineering (IOSRJEN)e-ISSN: 2250-3021, p- ISSN: 2278-8719, www.iosrjen.org Volume 2, Issue 9 (September 2012), PP 01-06 4. Gundeep Singh, Dr. R.M. Belokar “Lean Manufacturing Implementation in the Assembly shop of Tractor Manufacturing”. International Journal of Innovative Technology and Exploring Engineering (IJITEE) ISSN: 2278- 3075, Volume-1, Issue-2, July 2012.