1. SOURCE GROUNDED – EQUIPMENT UNGROUNDED
EARTHING IN LV & MV SYSTEMS
2. SOURCE GROUNDED – EQUIPMENT GROUNDED
3. SOURCES GROUNDED – EQUIPMENT GROUNDED
– WITH BONDING
4. LOW VOLTAGE (415V)
5. MV ( RESISTANCE GROUNDED SYSTEM )
6. MV ( UNGROUNDED SYSTEM )
7. ‘CLEAN’ EARTH
8. UPS SYSTEM EARTHING
3
REFERENCES
• IEEE Std – 80 : GUIDE FOR SAFETY IN AC
SUBSTATION GROUNDING
• IEEE Std – 1100 : GUIDE FOR POWERING AND GROUNDING
ELECTONIC EQUIPMENT
• IS – 3043 : CODE OF PRACTICE FOR EARTHING
• EARTHING PRINCIPLES AND PRACTICES : R W RYDER
• ELECTRICAL EARTHING AND ACCIDENT PREVENTION
: EDITED BY M G SAY
4
EARTHING IN LV & MV SYSTEMS
1. SOURCE GROUNDED – EQUIPMENT UNGROUNDED
• AB – SOURCE OF SUPPLY; C – EQUIPMENT
• B IS EARTHED TROUGH EARTH ELECTRODE 'E'
• FOR EASY CONCEPTUALIZATION, 1  NETWORK
SHOWN
A
V
B
E1
C
H
5
• UNDER NORMAL CONDITIONS, R  VERY HIGH.
EVEN IF A PERSON TOUCHES THE BODY, NO CURRENT
FLOWS THROUGH HIM
• INSULATION FAILURE OF EQUIPMENT  R = 0
• CURRENT THROUGH PERSON
V 240
H = ------------ = ------------  120 mA
RH + RE1 2000 + 1
• THIS CURRENT IS SMALL AND
NOT SUFFICIENT TO
BLOW THE FUSE
• BUT EVEN THIS SMALL
CURRENT CAN BE
DANGEROUS TO A PERSON ( IEEE STD - 116 mA FOR 1 Sec )
A
RC
R
X
RH
C
B
RE1
V
6
2. SOURCE GROUNDED – EQUIPMENT GROUNDED
• B & C ARE EARTHED
THROUGH EARTH
ELECTRODES 'E1' & 'E2'
• INSULATION FAILURE
OF EQUIPMENT  R = 0
• REQ = RE2 RH
= 1  2000 = 1
C
F
RC
R
X
RE1
RE2 RH
A
B
V
7
• FAULT CURRENT
• F IS SIGNIFICANT BUT NOT VERY HIGH.
FUSE MAY OR MAY NOT BLOW
• H - CURRENT THROUGH PERSON LOW BUT
NOT INSIGNIFICANT
V
F = ------------
REQ + RE1
240
= ------------  120 A
1 + 1 < 120 mA >
1
H = ----------- x 120  60 mA
1 + 2000 < 120 mA >
C
F
RC
R
X
RE1
RE2 RH
A
B
V
8
• BONDING CONDUCTOR – SHOWN IN RED
• PHYSICAL CONNECTION BETWEEN EQUIPMENT CASING
AND SOURCE
• ALSO CALLED EARTH CONTINUITY CONDUCTOR
• BONDING CONDUCTOR RESISTANCE : RB  VERY SMALL
3. SOURCE GROUNDED – EQUIPMENT GROUNDED –
WITH BONDING
• FIG_EA_20
9
240
F = --------- = 24 kA
0.01
• F IS VERY HIGH. FUSE WILL BLOW INSTANTANEOUSLY.
• HUMAN SAFETY INHERENTLY ACHIEVED
• CONCLUSION
DO NOT DEPEND ON 'MOTHER EARTH' FOR
RETURN OF FAULT CURRENT. DEPEND ON PHYSICAL
EARTH CONTINUITY CONDUCTOR (BONDING) THAT
RUNS FROM EQUIPMENT TO SOURCE.
• EVEN ASSUMING RB = 0.01 , FAULT CURRENT
• FIG_EA_20
IF FAULT CURRENT IS NOT DISCHARGED TO EARTH,
STEP & TOUCH POTENTIALS ARE IRRELEVANT.
10
1- F SUPPLY TO EQUIPMENT
A
A
RC
R
V
X
RE1 RB RE2 RH
E2
EQUIPMENT
GROUNDED
WITH BONDING
E1
B H B
C
C V
FIG_EA_20
SOURCE
GROUNDED
11
1- F SUPPLY TO EQUIPMENT
A
A
RC
R
V
X
RE1 RB RE2 RH
E2
EQUIPMENT
GROUNDED
WITH BONDING
E1
B H B
C
C V
FIG_EA_20
SOURCE
GROUNDED
12
4. LOW VOLTAGE (415V)
• GENERALLY SOLIDLY GROUNDED
• IE RULES
• IF FOR ANY REASON, IF LV SYSTEM IS NOT SOLIDLY
GROUNDED, SPECIAL PERMISSION FROM ELECTRICAL
INSPECTOR REQUIRED
• MYTH : EARTH IS GOOD EQUIPMENT GROUNDING
CONDUCTOR
• REALITY : EARTH IS THE MOST UNRELIABLE
EQUIPMENT GROUNDING CONDUCTOR
13
• BEST EARTH ELECTRODE RESISTANCE  1 
• ON 415 V SYSTEM, IF ONLY EARTH IS USED FOR RETURN OF
FAULT CURRENT,
MAX  (415/3) / 1
MAX  240 AMPS
• IF FAULT CURRENT IS LIMITED TO 240 A, NEITHER O/C RELAY
NOR FUSE WILL EVER OPERATE !
• FIG_EA_1
EARTH : UNRELIABLE EARTHING CONDUCTOR
14
FIG_EA_1
ACCIDENTAL CONTACT
SWITCHGEAR
N
R E =
1 
 E
VTOUCH
SOLIDLY GROUNDED NEUTRAL
15
• EARTH SHALL NOT BE TREATED AS SOLE EQUIPMENT
GROUNDING CONDUCTOR FOR FAULT CURRENT
RETURN PATH
• MAKE AS MANY SUPPLEMENTARY CONNECTION TO
EARTH FROM EQUIPMENT AS YOU WISH
• BUT MAKE SURE THAT ALL EQUIPMENT ARE
CONNECTED TO GROUNDING GRID (EARTH
CONTINUITY) CONDUCTOR WHICH SHALL BE
CONNECTED TO SOURCE NEUTRAL
• CONCLUSIONS
16
• MAJORITY OF FAULT CURRENTS SHALL BE CARRIED BY
GROUNDING GRID CONDUCTOR AND VERY LITTLE BY
'MOTHER' EARTH
• IF EARTH CURRENT IS LESS, TOUCH POTENTIAL IS ALSO
LESS
• FIG_EA_26
• IF NOT DONE  LEADS TO GROUND FAULT RELAYING
PROBLEMS
• EARTH CONDUCTOR MUST RUN ALL OVER THE PLANT
AND MUST CARRY RETURN CURRENT BACK TO SOURCE
NEUTRAL
LOW VOLTAGE (415V)
• CORRECT METHOD FIG_EA_99A
• WRONG METHOD FIG_EA_99B
17
FIG_EA_26
SOLIDLY GROUNDED SYSTEM
6.6 kV 415V
BKR
R
Y
B
N
E
18
EARTHING IN LV SYSTEM
CORRECT METHOD
M
E
MCC
E
PCC
R Y B N
6.6KV
E
40 x 6
FIG_EAR_99A
415V
19
EARTHING IN LV SYSTEM
WRONG METHOD
M
E
MCC
E
PCC
R Y B N
6.6KV
E
40 x 6
FIG_EAR_99B
E
415V
20
• UNSAFE EARTHING
• NO EARTH CONTINUITY
CONDUCTOR
• SAFE EARTHING
• WITH EARTH
CONTINUITY CONDUCTOR
21
• EVEN HERE THE EARTH CONDUCTOR MUST RUN ALL
OVER THE PLANT AND MUST CARRY RETURN CURRENT
BACK TO NGR
5. MV ( RESISTANCE GROUNDED SYSTEM )
• FIG_EA_27
ANIMATION
• DO NOT EARTH NGR BODY !
22
FIG_EA_27
RESISTANCE GROUNDED SYSTEM
16 kV 6.6 kV
BKR R
Y
B
NGR
E
23
CAUTION : DO NOT EARTH NGR CUBICLE !
FROM TRANSFORMER OR
GENERATOR NEUTRAL
RESISTOR
STACKS
TO
EARTH
GRID
EARTH PIT
NGR SUPPORT FRAME
EARTH PIT
INSULATOR
SHEET STEEL
ENCLOSURE
SOIL LEVEL
TO
EARTH
GRID
BUSHING
24
25
6. MV ( UNGROUNDED SYSTEM )
• FIG_EA_28
• EVEN FOR UNGROUNDED SYSTEM EARTH
CONTINUITY CONDUCTOR RECOMMENDED !
• FIG_EA_47
26
FIG_EA_28
UNGROUNDED SYSTEM
132kV 6.6 kV
BKR
27
FIG_EA_47
EARTHING CONDUCTOR IN UNGROUNDED SYSTEM
M
M
28
7. ‘CLEAN’ EARTH
❖ ELECTRONIC EQUIPMENT EARTHING
• FIG_EA_51 - CORRECT METHOD
• FIG_EA_52 - WRONG METHOD
• FIG_EA_53 - MONITORING
• NEUTRAL CURRENT HIGH
• CURRENT THROUGH ISOLATED GROUND
HIGH
29
‘CLEAN’ EARTH
• TWO CARDINAL PRINCIPLES
• NEUTRAL CONDUCTOR AND GROUND CONDUCTOR
CONNECTED ONLY AT THE SERVICE ENTRANCE. FROM
THIS POINT ON, NEUTRAL AND GROUND CONDUCTORS
SHOULD NOT BE BONDED TOGETHER. i.e. NEUTRAL AND
GROUND CONDUCTORS SHOULD NEVER TOUCH EACH
OTHER AFTER LEAVING SERVICE ENTRANCE PANEL
BOARD.
• UNBALANCED LOAD CURRENTS SHALL RETURN
ONLY THROUGH THE NEUTRAL BACK TO THE SERVICE
ENTRANCE. GROUND SHALL CARRY ONLY FAULT
CURRENT AND NOT UNBALANCED LOAD CURRENTS.
30
• MYTH
ELECTRONIC EQUIPMENT REQUIRE A ‘CLEAN,
DEDICATED AND ISOLATED GROUND’ AND SHOULD BE
ISOLATED FROM DIRTY ‘POWER EARTH’. THIS IS A
FAIRY TALE AND NOT AS PER CODES.
‘CLEAN’ EARTH
31
N N
ELECTRONIC EQUIPMENT EARTHING : CORRECT METHOD
SOURCE PANEL RECEPTACLE LOAD
N
N
N
IG
IG
G
G
G
FIG_EA_51
32
ELECTRONIC EQUIPMENT EARTHING : WRONG METHOD
CLEAN EARTH?
N N
SOURCE PANEL RECEPTACLE LOAD
N
N
N
IG
IG
G
G
G
FIG_EA_52
POWER EARTH
33
N N
ELECTRONIC EQUIPMENT EARTHING- MONITORING
SOURCE PANEL RECEPTACLE LOAD
N
N
N
IG
IG
G
G
G
FIG_EA_53
34
FIG_EA_26
SOLIDLY GROUNDED SYSTEM
6.6 kV 415V
BKR
R
Y
B
N
E
35
EARTHING IN LV SYSTEM
CORRECT METHOD
M
E
MCC
E
PCC
R Y B N
6.6KV
E
40 x 6
FIG_EAR_99A
415V
36
UPS SYSTEM EARTHING
NEUTRAL AND GROUND BOND AT SERVICE ENTRANCE
37
UPS SYSTEM EARTHING
UPS - SEPARATELY DERVIED SOURCE
38
UPS SYSTEM EARTHING
DISTRIBUTION BOARD - SEPARATELY DERIVED SOURCE
39

More Related Content

What's hot

What's hot (20)

Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Relay Generation and history
Relay Generation and historyRelay Generation and history
Relay Generation and history
 
Switch yard & Protection
Switch yard & ProtectionSwitch yard & Protection
Switch yard & Protection
 
BREAKDOWN IN LIQUIDS_NDS
BREAKDOWN IN LIQUIDS_NDSBREAKDOWN IN LIQUIDS_NDS
BREAKDOWN IN LIQUIDS_NDS
 
Vacuum circuit breaker selection of circuit breakers
Vacuum circuit breaker selection of circuit breakersVacuum circuit breaker selection of circuit breakers
Vacuum circuit breaker selection of circuit breakers
 
Testing of Transformer (AREVA)
Testing of Transformer (AREVA)Testing of Transformer (AREVA)
Testing of Transformer (AREVA)
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
4 PROTECTION OF ALTERNATOR.pptx
4 PROTECTION OF ALTERNATOR.pptx4 PROTECTION OF ALTERNATOR.pptx
4 PROTECTION OF ALTERNATOR.pptx
 
Chep 03 Electrical transient
Chep 03  Electrical transientChep 03  Electrical transient
Chep 03 Electrical transient
 
Faults on Power System
Faults on Power SystemFaults on Power System
Faults on Power System
 
Theory of AC and DC Meter Testing
Theory of AC and DC Meter TestingTheory of AC and DC Meter Testing
Theory of AC and DC Meter Testing
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
 
Vacuum circuit breaker
Vacuum circuit breakerVacuum circuit breaker
Vacuum circuit breaker
 
Protection of alternator
Protection of alternatorProtection of alternator
Protection of alternator
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1
 
The Excitation system by SAI
The Excitation system by SAIThe Excitation system by SAI
The Excitation system by SAI
 
Protection against overvoltage
Protection against overvoltageProtection against overvoltage
Protection against overvoltage
 
Basics of busbar protection
Basics of busbar protectionBasics of busbar protection
Basics of busbar protection
 
Buchholz relay
Buchholz relayBuchholz relay
Buchholz relay
 

Similar to Earthing System.pdf

C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
saurabhVEC
 
Electronic devices-and-circuit-theory-10th-ed-boylestad-chapter-15
Electronic devices-and-circuit-theory-10th-ed-boylestad-chapter-15Electronic devices-and-circuit-theory-10th-ed-boylestad-chapter-15
Electronic devices-and-circuit-theory-10th-ed-boylestad-chapter-15
Shiwam Isrie
 

Similar to Earthing System.pdf (20)

Manual 2
Manual 2Manual 2
Manual 2
 
Differentiator
DifferentiatorDifferentiator
Differentiator
 
Electrical Design calculations
Electrical Design calculationsElectrical Design calculations
Electrical Design calculations
 
Introduction to Electrical Engineering notes
Introduction to Electrical Engineering notesIntroduction to Electrical Engineering notes
Introduction to Electrical Engineering notes
 
Electric Utility Solutions: Voltage Regulation
Electric Utility Solutions: Voltage RegulationElectric Utility Solutions: Voltage Regulation
Electric Utility Solutions: Voltage Regulation
 
Ac distribution
Ac distributionAc distribution
Ac distribution
 
Chap 5 bte1013
Chap 5 bte1013Chap 5 bte1013
Chap 5 bte1013
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
 
Electrical services
Electrical servicesElectrical services
Electrical services
 
EMVT 12 september - Pavol Bauer - TU Delft
EMVT 12 september - Pavol Bauer - TU DelftEMVT 12 september - Pavol Bauer - TU Delft
EMVT 12 september - Pavol Bauer - TU Delft
 
Generator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkarGenerator protection by bhushan kumbhalkar
Generator protection by bhushan kumbhalkar
 
Basics of hvdc
Basics of hvdc Basics of hvdc
Basics of hvdc
 
DC Power Supply with a Full-Wave Bridge Rectifier
DC Power Supply with a Full-Wave Bridge RectifierDC Power Supply with a Full-Wave Bridge Rectifier
DC Power Supply with a Full-Wave Bridge Rectifier
 
Oscillator multivibrotor
Oscillator multivibrotorOscillator multivibrotor
Oscillator multivibrotor
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
 
Ies electrical-engineering-paper-2-2001
Ies electrical-engineering-paper-2-2001Ies electrical-engineering-paper-2-2001
Ies electrical-engineering-paper-2-2001
 
post_glover_resistance_grounding_2012.ppt
post_glover_resistance_grounding_2012.pptpost_glover_resistance_grounding_2012.ppt
post_glover_resistance_grounding_2012.ppt
 
post_glover_resistance_grounding_2012.ppt
post_glover_resistance_grounding_2012.pptpost_glover_resistance_grounding_2012.ppt
post_glover_resistance_grounding_2012.ppt
 
E&e lab manual
E&e lab manualE&e lab manual
E&e lab manual
 
Electronic devices-and-circuit-theory-10th-ed-boylestad-chapter-15
Electronic devices-and-circuit-theory-10th-ed-boylestad-chapter-15Electronic devices-and-circuit-theory-10th-ed-boylestad-chapter-15
Electronic devices-and-circuit-theory-10th-ed-boylestad-chapter-15
 

Recently uploaded

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Recently uploaded (20)

1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor
 
Introduction to Geographic Information Systems
Introduction to Geographic Information SystemsIntroduction to Geographic Information Systems
Introduction to Geographic Information Systems
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 

Earthing System.pdf

  • 1. 1
  • 2. 2 1. SOURCE GROUNDED – EQUIPMENT UNGROUNDED EARTHING IN LV & MV SYSTEMS 2. SOURCE GROUNDED – EQUIPMENT GROUNDED 3. SOURCES GROUNDED – EQUIPMENT GROUNDED – WITH BONDING 4. LOW VOLTAGE (415V) 5. MV ( RESISTANCE GROUNDED SYSTEM ) 6. MV ( UNGROUNDED SYSTEM ) 7. ‘CLEAN’ EARTH 8. UPS SYSTEM EARTHING
  • 3. 3 REFERENCES • IEEE Std – 80 : GUIDE FOR SAFETY IN AC SUBSTATION GROUNDING • IEEE Std – 1100 : GUIDE FOR POWERING AND GROUNDING ELECTONIC EQUIPMENT • IS – 3043 : CODE OF PRACTICE FOR EARTHING • EARTHING PRINCIPLES AND PRACTICES : R W RYDER • ELECTRICAL EARTHING AND ACCIDENT PREVENTION : EDITED BY M G SAY
  • 4. 4 EARTHING IN LV & MV SYSTEMS 1. SOURCE GROUNDED – EQUIPMENT UNGROUNDED • AB – SOURCE OF SUPPLY; C – EQUIPMENT • B IS EARTHED TROUGH EARTH ELECTRODE 'E' • FOR EASY CONCEPTUALIZATION, 1  NETWORK SHOWN A V B E1 C H
  • 5. 5 • UNDER NORMAL CONDITIONS, R  VERY HIGH. EVEN IF A PERSON TOUCHES THE BODY, NO CURRENT FLOWS THROUGH HIM • INSULATION FAILURE OF EQUIPMENT  R = 0 • CURRENT THROUGH PERSON V 240 H = ------------ = ------------  120 mA RH + RE1 2000 + 1 • THIS CURRENT IS SMALL AND NOT SUFFICIENT TO BLOW THE FUSE • BUT EVEN THIS SMALL CURRENT CAN BE DANGEROUS TO A PERSON ( IEEE STD - 116 mA FOR 1 Sec ) A RC R X RH C B RE1 V
  • 6. 6 2. SOURCE GROUNDED – EQUIPMENT GROUNDED • B & C ARE EARTHED THROUGH EARTH ELECTRODES 'E1' & 'E2' • INSULATION FAILURE OF EQUIPMENT  R = 0 • REQ = RE2 RH = 1  2000 = 1 C F RC R X RE1 RE2 RH A B V
  • 7. 7 • FAULT CURRENT • F IS SIGNIFICANT BUT NOT VERY HIGH. FUSE MAY OR MAY NOT BLOW • H - CURRENT THROUGH PERSON LOW BUT NOT INSIGNIFICANT V F = ------------ REQ + RE1 240 = ------------  120 A 1 + 1 < 120 mA > 1 H = ----------- x 120  60 mA 1 + 2000 < 120 mA > C F RC R X RE1 RE2 RH A B V
  • 8. 8 • BONDING CONDUCTOR – SHOWN IN RED • PHYSICAL CONNECTION BETWEEN EQUIPMENT CASING AND SOURCE • ALSO CALLED EARTH CONTINUITY CONDUCTOR • BONDING CONDUCTOR RESISTANCE : RB  VERY SMALL 3. SOURCE GROUNDED – EQUIPMENT GROUNDED – WITH BONDING • FIG_EA_20
  • 9. 9 240 F = --------- = 24 kA 0.01 • F IS VERY HIGH. FUSE WILL BLOW INSTANTANEOUSLY. • HUMAN SAFETY INHERENTLY ACHIEVED • CONCLUSION DO NOT DEPEND ON 'MOTHER EARTH' FOR RETURN OF FAULT CURRENT. DEPEND ON PHYSICAL EARTH CONTINUITY CONDUCTOR (BONDING) THAT RUNS FROM EQUIPMENT TO SOURCE. • EVEN ASSUMING RB = 0.01 , FAULT CURRENT • FIG_EA_20 IF FAULT CURRENT IS NOT DISCHARGED TO EARTH, STEP & TOUCH POTENTIALS ARE IRRELEVANT.
  • 10. 10 1- F SUPPLY TO EQUIPMENT A A RC R V X RE1 RB RE2 RH E2 EQUIPMENT GROUNDED WITH BONDING E1 B H B C C V FIG_EA_20 SOURCE GROUNDED
  • 11. 11 1- F SUPPLY TO EQUIPMENT A A RC R V X RE1 RB RE2 RH E2 EQUIPMENT GROUNDED WITH BONDING E1 B H B C C V FIG_EA_20 SOURCE GROUNDED
  • 12. 12 4. LOW VOLTAGE (415V) • GENERALLY SOLIDLY GROUNDED • IE RULES • IF FOR ANY REASON, IF LV SYSTEM IS NOT SOLIDLY GROUNDED, SPECIAL PERMISSION FROM ELECTRICAL INSPECTOR REQUIRED • MYTH : EARTH IS GOOD EQUIPMENT GROUNDING CONDUCTOR • REALITY : EARTH IS THE MOST UNRELIABLE EQUIPMENT GROUNDING CONDUCTOR
  • 13. 13 • BEST EARTH ELECTRODE RESISTANCE  1  • ON 415 V SYSTEM, IF ONLY EARTH IS USED FOR RETURN OF FAULT CURRENT, MAX  (415/3) / 1 MAX  240 AMPS • IF FAULT CURRENT IS LIMITED TO 240 A, NEITHER O/C RELAY NOR FUSE WILL EVER OPERATE ! • FIG_EA_1 EARTH : UNRELIABLE EARTHING CONDUCTOR
  • 14. 14 FIG_EA_1 ACCIDENTAL CONTACT SWITCHGEAR N R E = 1   E VTOUCH SOLIDLY GROUNDED NEUTRAL
  • 15. 15 • EARTH SHALL NOT BE TREATED AS SOLE EQUIPMENT GROUNDING CONDUCTOR FOR FAULT CURRENT RETURN PATH • MAKE AS MANY SUPPLEMENTARY CONNECTION TO EARTH FROM EQUIPMENT AS YOU WISH • BUT MAKE SURE THAT ALL EQUIPMENT ARE CONNECTED TO GROUNDING GRID (EARTH CONTINUITY) CONDUCTOR WHICH SHALL BE CONNECTED TO SOURCE NEUTRAL • CONCLUSIONS
  • 16. 16 • MAJORITY OF FAULT CURRENTS SHALL BE CARRIED BY GROUNDING GRID CONDUCTOR AND VERY LITTLE BY 'MOTHER' EARTH • IF EARTH CURRENT IS LESS, TOUCH POTENTIAL IS ALSO LESS • FIG_EA_26 • IF NOT DONE  LEADS TO GROUND FAULT RELAYING PROBLEMS • EARTH CONDUCTOR MUST RUN ALL OVER THE PLANT AND MUST CARRY RETURN CURRENT BACK TO SOURCE NEUTRAL LOW VOLTAGE (415V) • CORRECT METHOD FIG_EA_99A • WRONG METHOD FIG_EA_99B
  • 18. 18 EARTHING IN LV SYSTEM CORRECT METHOD M E MCC E PCC R Y B N 6.6KV E 40 x 6 FIG_EAR_99A 415V
  • 19. 19 EARTHING IN LV SYSTEM WRONG METHOD M E MCC E PCC R Y B N 6.6KV E 40 x 6 FIG_EAR_99B E 415V
  • 20. 20 • UNSAFE EARTHING • NO EARTH CONTINUITY CONDUCTOR • SAFE EARTHING • WITH EARTH CONTINUITY CONDUCTOR
  • 21. 21 • EVEN HERE THE EARTH CONDUCTOR MUST RUN ALL OVER THE PLANT AND MUST CARRY RETURN CURRENT BACK TO NGR 5. MV ( RESISTANCE GROUNDED SYSTEM ) • FIG_EA_27 ANIMATION • DO NOT EARTH NGR BODY !
  • 22. 22 FIG_EA_27 RESISTANCE GROUNDED SYSTEM 16 kV 6.6 kV BKR R Y B NGR E
  • 23. 23 CAUTION : DO NOT EARTH NGR CUBICLE ! FROM TRANSFORMER OR GENERATOR NEUTRAL RESISTOR STACKS TO EARTH GRID EARTH PIT NGR SUPPORT FRAME EARTH PIT INSULATOR SHEET STEEL ENCLOSURE SOIL LEVEL TO EARTH GRID BUSHING
  • 24. 24
  • 25. 25 6. MV ( UNGROUNDED SYSTEM ) • FIG_EA_28 • EVEN FOR UNGROUNDED SYSTEM EARTH CONTINUITY CONDUCTOR RECOMMENDED ! • FIG_EA_47
  • 27. 27 FIG_EA_47 EARTHING CONDUCTOR IN UNGROUNDED SYSTEM M M
  • 28. 28 7. ‘CLEAN’ EARTH ❖ ELECTRONIC EQUIPMENT EARTHING • FIG_EA_51 - CORRECT METHOD • FIG_EA_52 - WRONG METHOD • FIG_EA_53 - MONITORING • NEUTRAL CURRENT HIGH • CURRENT THROUGH ISOLATED GROUND HIGH
  • 29. 29 ‘CLEAN’ EARTH • TWO CARDINAL PRINCIPLES • NEUTRAL CONDUCTOR AND GROUND CONDUCTOR CONNECTED ONLY AT THE SERVICE ENTRANCE. FROM THIS POINT ON, NEUTRAL AND GROUND CONDUCTORS SHOULD NOT BE BONDED TOGETHER. i.e. NEUTRAL AND GROUND CONDUCTORS SHOULD NEVER TOUCH EACH OTHER AFTER LEAVING SERVICE ENTRANCE PANEL BOARD. • UNBALANCED LOAD CURRENTS SHALL RETURN ONLY THROUGH THE NEUTRAL BACK TO THE SERVICE ENTRANCE. GROUND SHALL CARRY ONLY FAULT CURRENT AND NOT UNBALANCED LOAD CURRENTS.
  • 30. 30 • MYTH ELECTRONIC EQUIPMENT REQUIRE A ‘CLEAN, DEDICATED AND ISOLATED GROUND’ AND SHOULD BE ISOLATED FROM DIRTY ‘POWER EARTH’. THIS IS A FAIRY TALE AND NOT AS PER CODES. ‘CLEAN’ EARTH
  • 31. 31 N N ELECTRONIC EQUIPMENT EARTHING : CORRECT METHOD SOURCE PANEL RECEPTACLE LOAD N N N IG IG G G G FIG_EA_51
  • 32. 32 ELECTRONIC EQUIPMENT EARTHING : WRONG METHOD CLEAN EARTH? N N SOURCE PANEL RECEPTACLE LOAD N N N IG IG G G G FIG_EA_52 POWER EARTH
  • 33. 33 N N ELECTRONIC EQUIPMENT EARTHING- MONITORING SOURCE PANEL RECEPTACLE LOAD N N N IG IG G G G FIG_EA_53
  • 35. 35 EARTHING IN LV SYSTEM CORRECT METHOD M E MCC E PCC R Y B N 6.6KV E 40 x 6 FIG_EAR_99A 415V
  • 36. 36 UPS SYSTEM EARTHING NEUTRAL AND GROUND BOND AT SERVICE ENTRANCE
  • 37. 37 UPS SYSTEM EARTHING UPS - SEPARATELY DERVIED SOURCE
  • 38. 38 UPS SYSTEM EARTHING DISTRIBUTION BOARD - SEPARATELY DERIVED SOURCE